Earned Value (EV) 104,193,000 Actual Cost (AC) 130,000,000 Schedule Variance (SV)=EV-PV (18,387,000) Cost Variance (CV)=EV-AC (25,807,000)
Schedule Performance Index (SPI)=EV/PV 0.85
Cost Performance Index (CPI)=EV/AC 0.801
Forecasting Budget At Completion (BAC) 204,300,000
Estimate To Complete (ETC)=(BAC – EV) / CPI 124,901,960.78
EAC Estimate At Completion (EAC)=AC+ETC 254,901,960.78
Estimate At Completion (EAC)=AC+(BAC – EV) 230,107,000.00
Estimate At Completion (EAC)=BAC/CPI 254,901,960.78
Estimate At Completion (EAC)=AC + [(BAC – 276,943,483.28 EV)/(CPI x SPI)] VAC Variance at completion (VAC)=BAC-EAC (50,601,960.78) TCPI To-Complete Performance Index (TCPI)=Work remaining (BAC–EV)/Funds remaining (BAC– 1.35 AC)
To-Complete Performance Index (TCPI)=Work
remaining (BAC–EV)/Funds remaining (EAC– 0.80 AC) Phase Amount (PKR) Duration Budgeted Cost of Work Scheduled (BCWS) 1 61,290,000 3 months Budgeted Cost of Work Performed (BCWP) 2 61,290,000 3 months Actual Cost of Work Performed (ACWP) 3 81,720,000 4 months