PROJECT :- LANDCARE REALTY LLP

SUBJECT :- DAILY PROGRESS REPORT OF EXCAVATION WORK

CONTRACTING FIRM :- PATRU EARTH MOVERS


NAME OF CONTRACTOR :- PATRU PATEL
ACTUAL WORK START DATE:- 31.03.2021

Date :- 25.04.2021

Total Exavation Qty 36115


Equpiment Mobilised (PC200) 3
Diesel Issued in ltrs 2500.00
Royalty issued in Brass 800 Royalty Remaining
Nos. of Trips in present day 46
Cumulative Nos. of Trip 834

PROGRESS
Sr.no Activity Unit Estimated Qty Present day EX. Qty
1 Excavation in soil (Retained) Cum. 7287 -
2 Excavation in soil (outside) Cum. 11908 460
3 Excavation in Hard Rock (Retained) Cum. 608 -
4 Excavation in Hard Rock (outside) Cum. 16312
36115 460

Client Representative Sign.


EALTY LLP

200

Cumulative Qty % Work Done


1180 16.19%
6870 57.69%
0 0.00%
290 1.78%
8340 23.09%

Contractor Representative Sign.


Daily Trip Record
Sr.no. Date Soft Soil (Retained) Soft Soil (Outside) Hard Rock (Retained)
1 06.02.2021 17
2 07.02.2021 14
3 08.02.2021 14
4 11.02.2021 13
5 12.02.2021 16
6 14.02.2021 5
7 16.02.2021 12
8 17.02.2021 14
9 18.02.2021 9
10 20.02.2021 4
11 31.03.2021 4
12 01.04.2021 27
13 02.04.2021 20
14 03.04.2021 20
15 04.04.2021 31
16 05.04.2021 15
17 06.04.2021 31
18 07.04.2021 30
19 08.04.2021 54
20 09.04.2021 33
21 10.04.2021 17
22 11.04.2021 20
23 12.04.2021 31
24 18.04.2021 30
25 19.04.2021 49
26 20.04.2021 46
27 21.04.2021 50
28 22.04.2021 52
29 23.04.2021 66
30 24.04.2021 15 29
31 25.04.2021 46
TOTAL 118 687 29

834
Hard Rock (Outside)

0
Project :- Land Care Realty LLP

Subject :- Daily Daily Records


Sr.no. Date Qty in liters
1 01.04.2021 100
2 03.04.2021 100

3 04.04.2021 100

4 05.04.2021 100

5 06.04.2021 100

6 07.04.2021 100

7 08.04.2021 300

8 10.04.2021 200

9 12.04.2021 100

10 18.04.2021 100

11 19.04.2021 200

12 20.04.2021 100

13 21.04.2021 100

14 22.04.2021 100

15 23.04.2021 200

16 24.04.2021 200

17 25.04.2021 300

Total 2500.00