Professional Documents
Culture Documents
1 Management Accounting
Question-1
STATE the Cost Control and Cost Reduction objectives of Cost and Management Accounting
system.
Answer:
Among other objectives of cost and management accounting system, cost control and cost
reduction are principal objectives. Cost control objective ensures the compliance with the set
standard of procedures, Cost Reduction objective explores the possibilities of improvements in
terms of both quantitative and qualitative aspects. Both objectives are briefly explained as
below:
Cost Control: Maintaining discipline in expenditure is one of the main objectives of a good
cost and management accounting system. It ensures that expenditures are in consonance with
predetermined set standard and any variation from these set standards is noted and reported
on continuous basis. To exercise control over cost, following steps are followed:
(a) Determination of pre-determined standard or results: Standard cost or performance
targets for a cost object or a cost centre is set before initiation of production or service
activity. These are desired cost or result that need to be achieved.
(b) Measurement of actual performance: Actual cost or result of the cost object or cost
centre is measured. Performance should be measured in the same manner in which the
targets are set i.e. if the targets are set up operation-wise, and then the actual costs
should also be collected and measured operation-wise to have a common basis for
comparison.
(c) Comparison of actual performance with set standard or target: The actual performance
so measured is compared against the set standard and desired target. Any deviation
(variance) between the two is noted and reported to the appropriate person or authority.
(d) Analysis of variance and action: The variance in results so noted are further analysed to
know the reasons for variance and appropriate action is taken to ensure compliance in
future. If necessary, the standards are further amended to take developments into
account.
Cost Reduction: It may be defined "as the achievement of real and permanent reduction in
the unit cost of goods manufactured or services rendered without impairing their suitability for
the use intended or diminution in the quality of the product."
Cost reduction is an approach of management where cost of an object is believed to be further
reduced. No cost is termed as lowest and every possibility of cost reduction is explored. To do
cost reduction, the following action is taken:
(a) Each activity within an entity is segmented to analyse and identify value added and non-
value added activities. All non-value added activities are eliminated without affecting the
essential characteristics of the product or process. Value chain Analysis, a strategic tool,
developed by Michael Porter, is one of the methods to do value analysis.
(b) Conducting continuous research and study to know better way to do anything.
The three-fold assumptions involved in the definition of cost reduction may be summarised as
under:
(i) There is a saving in unit cost.
(ii) Such saving is of permanent nature.
(iii) The utility and quality of the goods and services remain unaffected, if not improved.
Question-2
STATE in brief how Cost Accounting and Management Accounting is related or different from
each other.
Answer:
The term Cost Accounting and Management Accounting is interchangeably by various
laureates as both the disciplines are interrelated. Management accounting to enable its
users to take timely and judicious decisions takes inputs from cost accounting, financial
accounting, statistics and operation management tools etc. Among other sources of
information Cost Accounting system provides cost related information. There are few
differences between these two disciplines which are tabulated as below:
Difference between Cost Accounting and Management Accounting
Basis Cost Accounting Management Accounting
(i) Nature It records the quantitative aspect It records both qualitative and
only. quantitative aspect.
(ii) Objective It records the cost of producing a It Provides information to
product and providing a service. management for planning and
co-ordination.
(iii) Area It only deals with cost It is wider in scope as it includes
Ascertainment. financial accounting, budgeting,
taxation, planning etc.
(iv) Recording of It uses both past and present It is focused with the projection
data figures. of figures for future.
(v) Development Its development is related to It develops in accordance to the
industrial revolution. need of modern business world.
(vi) Rules and It follows certain principles and It does not follow any specific
Regulation procedures for recording costs rules and regulations.
of different products.
Answer:
Workings:
Annual production of Product X = Annual demand – Opening stock
= 5,00,000 – 12,000 = 4,88,000 units
Annual requirement for raw materials = Annual production × Material per unit – Opening
stock of material
Material A = 4,88,000 × 4 units – 24,000 units = 19,28,000 units
Material B = 4,88,000 × 16 units – 52,000 units = 77,56,000 units
(i) Computation of EOQ when purchase order for the both materials is placed
separately
(ii) Computation of EOQ when purchase order for the both materials is not placed
separately
2 (19,28,000 77,56,000)units `15,000
Material A & B =
13%of `190
1,93,68,000 `15,000
= = 1,08,452 units
`24.7
1,08,452 19,28,000
Material A = = 21,592 units
96,84,000
1,08,452 77,56,000
Material A = = 86,860 units
96,84,000
(`150 19,28,000) (`200 77,56,00)
* = `190
(19,28,000 77,56,000)
C 136 48 6,528
(ii) Computation of wages of each worker under piece work earnings basis
Worker A Worker B Worker C
Product Rate per Units Wages Units Wages Units Wages
unit (`) (`) (`)
(a) (b) (c) (d= b*c) (e) (f = b*e) (g) (h=b*g)
P 12 84 1,008 - - 240 2,880
Q 18 144 2,592 - - 540 9,720
R 30 184 5,520 100 3,000 - -
9,120 3,000 12,600
Since each worker has been guaranteed at 75% of basic pay, if their earnings are less
than 50% of basic pay (guaranteed hourly rate), earning of the workers will be as follows:
Workers A and C will be paid the wages as computed viz., `9,120 and `12,600
respectively. The computed earnings under piece rate basis for worker B is `3,000 which
is less than 50% of basic pay i.e., ` 4,400 (`8,800 × 50%) therefore B would be paid
`6,600 i.e. 75% × `8,800 .
Working Notes:
1. Piece rate / per unit
Product Standard time per Piece rate each Piece rate per unit
unit in minutes minute (`) (`)
(a) (b) (c) (d) = (b) × (c)
P 12 1.00 12.00
Q 18 1.00 18.00
R 30 1.00 30.00
2. Time allowed to each worker
Worker A = (84 units × 12 minutes) + (144 units × 18 minutes) + (184 units × 30
minutes)
= 9,120 minutes or 152 hours
Worker B = 100 units × 30 minutes
= 3,000 minutes or 50 hours
Worker C = (240 units × 12 minutes) + (540 units × 18 minutes)
= 12,600 minutes or 210 hours
(iii) Computation of wages of each worker under Premium bonus basis (where each
worker receives bonus based on Rowan Scheme)
Workers Time Time Time Wage Earnings Bonus Total of
allowed taken saved rate/hour earning &
hours hours hours bonus
(`) (`) (`) (`)
A 152 152 - 50 7,600 - 7,600
B 50 160 - 55 8,800 - 8,800
C 210 136 74 48 6,528 2,300* 8,828
Time saved
* Bonus under Rowan scheme = × Time taken × Rate per hour
Time allowed
74 hours
= × 136 hours × `48 = `2,300
210hours
Question 2 :
The existing incentive system of Alpha Limited is as under:
Normal working week 5 days of 8 hours each plus 3 late shifts of 3
hours each
Rate of Payment Day work: `160 per hour
Late shift: `225 per hour
Average output per operator for 49-hours 240 articles
week i.e. including 3 late shifts
In order to increase output and eliminate overtime, it is decided to switch on to a system of
payment by results. The following information is obtained:
Time-rate (as usual) : `160 per hour
Basic time allowed for 15 : 2.5 hours
articles
Piece-work rate : Add 20% to basic piece-
rate
Premium Bonus : Add 50% to time.
If during the last week 270 articles are produced in a 40-hour week.
Required:
(i) CALCULATE weekly earnings, number of articles produced and labour cost per article for
one operator under the following systems:
(a) Existing time-rate
(b) Straight piece-work
(c) Rowan system
(d) Halsey premium system
(ii) PREPARE a Statement showing hours worked, weekly earnings, number of articles
produced and labour cost per article for one operator under the above systems.
Answer:
(i) (a) Existing time rate
Weekly wages:
Normal shift (40 hours × `160): `6,400
Late shift (9 hours × `225) `2,025
`8,425
(b) Piece Rate System
15 articles are produced in 2.5 hours
2.5hours
Therefore, to produce 270 articles, hours required is ×270articles = 45 hours.
15articles
Cost of producing 270 articles:
At basic time rate (45 hours × `160) = `7,200
Add: Bonus @ 20% on basic Piece rate `1,440
Earning for the week `8,640
(c) Rowan Premium System
2.5hours
(i) Time allowed for producing 270 articles ×270articles×150% = 67.5 hours
15articles
(ii) Time taken to produce 270 articles = 40.0 hours
(iii) Time Saved = 67.5 – 40 = 27.5 hours
Earnings under Rowan Premium system:
Time saved
= (Time taken×Rateper hour)+ ×Time taken×Rate per hour
Time allowed
27.5hours
= (40hours× ` 160)+ ×40hours× ` 160 = `9,007.41
67.5hours
(d) Halsey Premium System
1
= (Time taken×Rate per hour)+ ( ×Time saved×Rate per hour)
2
1
= (40hours× ` 160)+ ×27.5hours× ` 160 = `6,400 + `2,200 = `8,600
2
(ii) Statement showing hours worked, weekly earnings, number of articles produced and
cost per article
Method of Payment Hours Weekly Number of Labour cost
worked earnings articles per article
(`) produced (`)
Existing time rate 49 8,425.00 240 35.10
Straight piece rate system 40 8,640.00 270 32.00
Rowan Premium System 40 9,007.41 270 33.36
Halsey Premium System 40 8,600.00 270 31.85
(`)
Depreciation on Machinery 7,92,000
Insurance of Machinery 1,44,000
Insurance of Building 64,800 (Total building insurance cost for M1 is
one third of annual premium)
Power 1,29,600
Light 1,08,000
Rent 2,53,500 (The general service deptt. is located in a
Indirect Allocation given 25,02,800 9,30,400 8,26,800 3,24,400 1,64,000 1,06,800 1,50,400
wages
Consumable Allocation given 9,04,000 2,52,000 3,64,000 84,000 56,000 84,000 64,000
stores
Depreciation Capital value of 7,92,000 3,16,800 2,37,600 79,200 31,680 95,040 31,680
machine
(20:15:5:2:6:2)
Insurance of Capital value of 1,44,000 57,600 43,200 14,400 5,760 17,280 5,760
Machine machine
(20:15:5:2:6:2)
Insurance on 1/3rd to M1 64,800 21,600 12,960 17,280 4,320 5,400 3,240
Building Balance area
basis
(-:12:16:4:5:3)
Power HP Hr% 1,29,600 64,800 45,360 6,480 12,960
(10:7:1:-:2:-)
Light Area 1,08,000 21,600 25,920 34,560 8,640 10,800 6,480
(10:12:16:4:5:3)
Rent* Area 2,53,500 53,940 64,720 86,300 21,580 26,960 --
(10:12:16:4:5:-)
Total 48,98,700 17,18,740 16,20,560 6,46,620 2,91,980 3,59,240 2,61,560
*Rent to be apportioned among the departments which actually use the rented building. The notional
rent is imputed cost and is not included in the calculation.
Depreciation 20,00,000
Other 1,80,00,000
overheads
Additional information:
Area (Sq. ft.) 500 250 500 250 500
Capital value of assets (` 400 800 400 200 200
lakhs)
Machine hours 1,000 2,000 4,000 1,000 1,000
Horse power of machines 50 40 20 15 25
Required:
(i) IDENTIFY Cost pool, Cost drivers.
(ii) CALCULATE cost driver rate.
(iii) CALCULATE overheads rate per unit using activity- based costing method.
Answer:
(i) Identification of Cost pools and cost drivers:
Cost Pools Cost Drivers
Machine operating cost No. of machine hours
Machine set-up cost No. of machine set-ups
Order processing cost No. of orders
Question-2
CDE Ltd. is following Activity based costing. Budgeted overheads, cost drivers and volume are
as follows:
Cost pool Budgeted Cost driver Budgeted volume
overheads (`)
Question-3
MST Limited has collected the following data for its two activities. It calculates activity cost rates
based on cost driver capacity.
Activity Cost Driver Capacity Cost (`)
Power Kilowatt hours 50,000 kilowatt hours 40,00,000
Quality Inspections Number of 10,000 Inspections 60,00,000
Inspections
The company makes three products M, S and T. For the year ended March 31, 20X7, the following
consumption of cost drivers was reported:
Product Kilowatt hours Quality Inspections
M 10,000 3,500
S 20,000 2,500
T 15,000 3,000
Required:
(i) PREPARE a statement showing cost allocation to each product from each activity.
(ii) CALCULATE the cost of unused capacity for each activity.
(iii) STATE the factors the management considers in choosing a capacity level to compute the
budgeted fixed overhead cost rate.
Answer:
(i) Statement of cost allocation to each product from each activity
Product
M (`) S (`) T (`) Total (`)
Working Note:
Rate per unit of cost driver:
Power :(`40,00,000 ÷ 50,000 kWh) = `80/kWh
Quality Inspection :(`60,00,000 ÷ 10,000 inspections) = `600 per inspection
(ii) Calculation of cost of unused capacity for each activity:
(`)
Power 4,00,000
(`40,00,000 – `36,00,000)
Quality Inspections 6,00,000
(`60,00,000 – `54,00,000)
Total cost of unused capacity 10,00,000
(iii) Factors management consider in choosing a capacity level to compute the budgeted fixed
overhead cost rate:
- Effect on product costing & capacity management
- Effect on pricing decisions.
- Effect on performance evaluation
- Effect on financial statements
- Regulatory requirements.
- Difficulties in forecasting for any capacity level.
Amount realized by selling of scrap and waste generated during manufacturing process –
`86,000/-
From the above data you are requested to PREPARE Statement of cost for Arnav Ispat Udyog
Ltd. for the year ended 31st March, 20X8, showing (i) Prime cost, (ii) Factory cost, (iii) Cost of
Production, (iv) Cost of goods sold and (v) Cost of sales.
Answer:
Statement of Cost of Arnav Ispat Udyog Ltd. for the year ended 31st March, 20X8:
Sl. Particulars Amount (`) Amount (`)
No.
(i) Material Consumed:
- Raw materials purchased 10,00,00,000
- Freight inward 11,20,600
Add: Opening stock of raw materials 18,00,000
Less: Closing stock of raw materials (9,60,000) 10,19,60,600
(ii) Direct employee (labour) cost:
- Wages paid to factory workers 29,20,000
- Contribution made towards employees’ PF 3,60,000
& ESIS
- Production bonus paid to factory workers 2,90,000 35,70,000
(iii) Direct expenses:
- Royalty paid for production 1,72,600
- Amount paid for power & fuel 4,62,000
- Amortised cost of moulds and patterns 4,48,000
- Job charges paid to job workers 8,12,000 18,94,600
Prime Cost 10,74,25,200
(iv) Works/ Factory overheads:
- Stores and spares consumed 1,12,000
- Depreciation on factory building 84,000
- Depreciation on plant & machinery 1,26,000
- Repairs & Maintenance paid for plant & 48,000
machinery
- Insurance premium paid for plant & 31,200
machinery
- Insurance premium paid for factory building 18,100
- Insurance premium paid for stock of raw 36,000
materials & WIP
Notes:
(i) GST paid of purchase of raw materials would not be part of cost of materials as it is eligible for
input credit.
TotalCost `17,88,000
Minimum fee to be charged = = = `11,920/-
No. of students 150 students
`26,82,000
= `21,456/-
125 students
Required:
(i) CACULATE the total project cost per day of concession period.
(ii) COMPUTE toll fee to be charged for per vehicle of each type, if the company wants earn a profit
of 15% on total cost.
[Note: Concession period is a period for which an infrastructure is allowed to operate and recovers its
investment]
Answer:
(i) Calculation of total project cost per day of concession period:
Activities Amount (` in lakh)
`14,57,050
Cost per equivalent vehicle = = `19.06 per equivalent vehicle
76,444units(Re fer workingnote)
Vehicle type-wise toll fee:
Sl. Type of vehicle Equivalent cost Weight Toll fee per vehicle
No. [A] [B] [A×B]
1. Two wheelers `19.06 1 19.06
2. Car and SUVs `19.06 4 76.24
3. Bus and LCV `19.06 6 114.36
4. Heavy commercial vehicles `19.06 9 171.54
Working Note:
The cost per day has to be recovered from the daily traffic. The each type of vehicle is to be
converted into equivalent unit. Let’s convert all vehicle types equivalent to Two-wheelers..
Sl. Type of vehicle Daily traffic Weight Ratio [B] Equivalent Two-
No. volume [A] wheeler [A×B]
1. Two wheelers 44,500 0.05 1 44,500
2. Car and SUVs 3,450 0.20 4 13,800
3. Bus and LCV 1,800 0.30 6 10,800
4. Heavy commercial 816 0.45 9 7,344
vehicles
Total 76,444