Project Details Information available as on 31-May-2021 18:58
PM

Project General Information


Four laning of fagne to Gujarat-Maharashtra Border section of NH 6 from Km 510 to Km 650.79 in Maharashtra under
Project Name
NHDP Phase IV
Project Brief The project involves four / six-laning of Fagne-Maharashtra / Gujarat Border section of NH-6 (Package-III) from 510.00
km to 650.79 km in Maharashtra under NHDP -IV.
Operation and
Sector Transport Project Status
Maintenance Stage
Nodal Authority Centre
Sub-Sector Roads and bridges

Project Capacity 140.79 KM (Kilometer) Concession Duration 228

Location Maharashtra Bid Parameter Concession Duration


Type of PPP Design-Build-Finance-Operate-Transfer
(DBFOT)
Government/Non Government Government

Any Other Information This is a PPPAC Recommended Project.

Project Authority
National Highways Authority of India
Name Of Authority Email Not Available
(NHAI)

Name Of Contact Person Not Available Phone Not Available


G-5 & G-6, Sector-10, Dwarka, Delhi-
Address Fax Not Applicable
110075, Delhi
Project Contractor

Name Of Authority Fagne Songadh Expressway Limited Email Not Available

Name Of Contact Person Not Available Phone (022)-26533333/26593591


C/o IL&FS Transportation Networks,
The IL&FS Financial Centre,Plot
Address C22G Block, Bandra-Kurla Complex, Fax 26533295
Bandra East, Mumbai-400051,
Maharashtra

Page 1 of 2
Last Updated on : 09-Nov-2019 21:15 PM
Project Timeline

Date to Start of Commercial Operation (as per


Concession Agreement Signing Date 08-Sep-2015 31-May-2019
Concession Agreement)

Financial Closure Date Not Available Date to Start of Commercial Operation (Actual) Not Applicable

Concession End Date (as per Concession


Apointed Date 09-Nov-2016 07-Sep-2034
Agreement)
Construction Completion Date (as per Concession Revised end date of the concession, if any
Agreement) 31-May-2019 Not Applicable

Construction Completion Date (Actual) Not Applicable Concession End Date (Actual) Not Applicable

Project Costs

Project Cost (as per Concession Agreement) in 1885.74


Project Funding Private
Rs Crore
Not Applicable
Type Of Grant Not Available Project Cost (Revised) in Rs Crore
Not Available Not Applicable
Grant Amount in Rs. Crore Project Cost (Actual) in Rs Crore