Professional Documents
Culture Documents
Davison Construction Company is building a luxury lakefront home in the Finger Lakes region
of New York. Coordination of the architect and subcontractors will require a major effort to
meet the 44-week (approximately 10-month) completion date requested by the owner. The
Davison project manager prepared the following project network.
m
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are
er as
as follows:
co
eH w
m
a Most b
o.
Activit Optimistic Probable Pessimistic
D 3 5 7
aC s
E 6 9 18
vi y re
F 5 8 17
G 10 15 20
H 5 6 13
ed d
ar stu
This study source was downloaded by 100000777811222 from CourseHero.com on 06-13-2021 01:46:41 GMT -05:00
https://www.coursehero.com/file/28529281/MGMT-651-Chapter-9-Question-14docx/
Tabular Data
(a+ 4 m+b)
First, calculate the Average Time for each activity, tA = 4
Second, do a forward pass through the activities to determine ES and EF. ES is the
maximum EF of an activities predecessors. EF = ES + tA.
Third, do a backward pass through the activities to determine LF and LS. LF is the
minimum LS of an activities successors. LS = LF - tA.
Forth, determine Slack by calculating the difference between LS and ES.
Finally, the critical path follows those activities with zero slack.
m
Early Late σ2
er as
tA Early Finish Start Late Critical
Average Start EF LS Finish Slack
co
Critical path
(ES + tA) (LF- tA)
eH w
Activity Time Predecessors ES LF (LS-ES) Path? variance
A 8 0 8 0 8 0 Yes 1.7778
o.
B 7 A 8 15 14 21 6
C 12 rs e
A 8 20 8 20 0 Yes 4
ou urc
D 5 A 8 13 15 20 7
E 10 C,D 20 30 20 30 0 Yes 4
o
F 9 C,B 20 29 21 30 1
aC s
c) Based on the critical path, what is the estimated probability the project can be completed in
the 44 weeks as requested by the owner?
Th
First, calculate the variance for each activity on the critical path using the equation:
2
b−a
( )
sh
2
σ = 6
Calculated values are shown in the tabular data above. Summing these up gives a total critical
path variance of, σ2 for Tcrit = 14.333.
This study source was downloaded by 100000777811222 from CourseHero.com on 06-13-2021 01:46:41 GMT -05:00
https://www.coursehero.com/file/28529281/MGMT-651-Chapter-9-Question-14docx/
It follows that the standard deviation is, σ = √ 14.333=3.786 weeks.
x−μ
The z-value is then calculated using the equation z= , where x = 44 weeks, and µ is the
σ
mean and equals 52 weeks.
44−52
z= =−2.113
3.786
m
run more than 3 months late? Use 57 weeks for this calculation.
er as
co
Following the same calculations for z, above, we get
eH w
o.
57−52
z=
3.786
=1.3207
rs e
ou urc
The corresponding probability from Appendix B in the textbook is 0.9066 or 90.66%. This is the
estimated probability that the project will take 57 weeks or less. The estimated probability the
o
project could run more than 57 weeks is found by 1-.9067 = .0934, or 9.34%.
aC s
vi y re
e) The construction company should tell the owner that the estimated project completion time is
52 weeks. It is unlikely the project will be completed in the 44 weeks requested. Running 3
months over schedule is very likely.
ed d
ar stu
is
Th
sh
This study source was downloaded by 100000777811222 from CourseHero.com on 06-13-2021 01:46:41 GMT -05:00
https://www.coursehero.com/file/28529281/MGMT-651-Chapter-9-Question-14docx/
Powered by TCPDF (www.tcpdf.org)