TAPAZ WTP - PHASE1 1 of 3 TAPAZ WTP - Work Status (LGU)

Subject: Tapaz WTP Work Status Phase 1


As of: June 14, 2021

Percentage of Completion
ITEM ACTIVITIES
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%

Raw Water Intake (River Well)


1 MOBILIZATION, CLEARING AND LAY-OUT
PROCUREMENT AND DELIVERY OF RAW WATER PUMP AND
2
CONTROL PANEL
3 INSTALLATION OF SUBMERSIBLE PUMP
4 PROCUREMENT AND DELIVERY OF RAW WATER PIPES
5 RAW WATER PIPE INSTALLATION
6 WIRING OF RAW SUBMERSIBLE PUMP
7 TESTING AND COMMISSIONING

Main Operation Building


1 EXCAVATION, BACK FILLING AND COMPACTION
2 FLOOR REBARS WORK
3 CONCRETE FLOORING/ MASONRY WORKS
4 FLOOR FINISHES AND TILE WORKS
5 ROOFING AND PARAPET WORKS
6 CARPENTRY, FINISHING AND CEILING WORKS
7 WALL FINISHES
8 PAINTING WORKS
9 POWER/LIGHTING PANELS AND CABLING WORKS
10 LIGHTING AND POWER FIXTURES
11 HAND RAILS, DOORS, SHUTTER ROLLERS AND WINDOWS
12 PLUMBING AND SANITARY WORKS

Process Tank Foundations


1 SITE LAY OUT AND SETTING OUT
2 GROUND LEVELING CUT AND FILL,COMPACTION
3 GRAVEL BEDDING AND COMPACTION
4 SUPPLY AND FIX REINFORCED STEEL BAR G40
5 FORMWORKs
SUPPLY, PLACE AND FINISH REINFORCED CONCRETE
6
(3000PSI@28DAYS)
TAPAZ WTP - PHASE1 2 of 3 TAPAZ WTP - Work Status (LGU)
Subject: Tapaz WTP Work Status Phase 1
As of: June 14, 2021

Percentage of Completion
ITEM ACTIVITIES
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%

Chlorine Contac Tank Foundation


1 SITE LAY OUT AND SETTING OUT
2 GROUND LEVELING, CUT AND FILL, COMPACTION
3 GRAVEL BEDDING AND COMPACTION
4 FORMWORKS
5 SUPPLY AND FIX REINFORCED STEEL BAR G40
SUPPLY, PLACE AND FINISH REINFORCED CONCRETE
6
(3000PSI@28DAYS)

Sludge Management Tank


1 SITE LAY OUT AND SETTING OUT
2 GROUND LEVELING CUT AND FILL,COMPACTION
3 GRAVEL BEDDING AND COMPACTION
4 SUPPLY AND FIX REINFORCED STEEL BAR G40
5 FORMWORKs
SUPPLY, PLACE AND FINISH REINFORCED CONCRETE
6
(3000PSI@28DAYS)
7 FABRICATION AND INSTALLATION OF DRAIN PIPES
8 GRAVEL AND SAND BEDDING

PROCESS TANKS, EQUIPMENTS AND DISTRIBUTION


SYSTEM
1 FLOCCULATION TANK FABRICATION
PROCUREMENT, DELIVERY AND INATALLATION OF FLOCC
2
MIXER
3 CLARIFIER TANK FABRICATION
FABRICATION OF LAUNDERS, LAMELLA TUBES AND
4
SUPPORT
5 FILTER TANK FABRICATION WITH FILTER UNDERDRAIN
6 PROCUREMENT AND DELIVERY OF GLASS FILTER MEDIA
7 FLOCC TANK INSTALLATION WITH MIXER
8 CLARIFIER INSTALLATION WITH LAMELLA TUBES
TAPAZ WTP - PHASE1 3 of 3 TAPAZ WTP - Work Status (LGU)
Subject: Tapaz WTP Work Status Phase 1
As of: June 14, 2021

Percentage of Completion
ITEM ACTIVITIES
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%
FILTER TANK INSTALLATION AND ASSEMBLY WITH FILTER
9
MEDIA
10 CHLORINE CONTACT TANK FABRICATION
FABRICATION OF OVERHEAD PLATFORM/WALKWAYS AND
11
ACCESS LADDERS
PROCUREMENT, DELIVERY AND FABRICATION OF SHORT
12
PIPES AND FITTINGS
PROCUREMENT AND DELIVERY GASKET,BOLTS, NUTS AND
13
WASHERS
14 ASSEMBLY OF INTERCONNECTING PIPING WORKS
ELECTRO-MECHANICAL PROCUREMENT OF VARIOUS
15
PUMPS
16 ELECTRO-MECHANICAL PROCUREMENT OF VALVES
ELECTRO-MECHANICAL PROCUREMENT OF DISTRIBUTION
17
PIPES
18 ELECTRO-MECHANICAL PROCUREMENT OF WATER METERS
19 ELECTRO-MECHANICAL INSTALLATION OF PUMPS
20 ELECTRO-MECHANICAL INSTALLATION OF VALVES
ELECTRO-MECHANICAL INSTALLATION OF DISTRIBUTION
21
PIPES
PROCUREMENT OF ELECTRICAL PANELS, CONDUIT AND
22
CABLING WORKS
INSTALLATION OF ELECTRICAL PANELS CONDUIT AND
23
CABLING WORKS
24 PROCUREMENT AND DELIVERY OF CHEMICALS
25 PROCUREMENT AND DELIVERY OF CHEMICAL TANKS
26 TEST & COMMISSION WTP
27 FLUSH PIPELINES
28 ELECTRO-MECHANICAL INSTALLATION OF WATER METERS
29 WATER QUALITY PROVING PERIOD