You are on page 1of 6

KEMENTERIAN KESEHATAN REPUBLIK INDONESIA

DIREKTORAT JENDERAL PELAYANAN KESEHATAN


RUMAH SAKIT UMUM PUSAT DR. SARDITJO
Jl. Kesehatan, Sekip-Yogyakarta 552484 Telp : (0274) 587333 Ext 451, 339 Fax : (0274) 565639, 520410
Pos-El : ppk_sardjito@yahoo.co.id ppk.sardjito@gmail.com
Laman: www.sardjitohospital.co.id

SPESIFIKASI TEKNIS
Pemindahan Lokasi Server, Lokasi Operator, Penambahan Ekstensi, PABX Alcatel-Lucent OmniPCX Enterprice

No. U R A I A N VOLUME
1 2 3
A Remote PABX Lokasi ICC
1 Wallmount Rack 19" 12U Depth 550 1
2 Shelf ACT-14 Slot 1
3 Cos-mo connector direct FO SM 2
4 INTOF2 Board Interface Fiber Optic 2
5 Analog Extension (eZ32 Board) 2
32 Ports analog extension equipment (Cap: 128 Analog Ext.)
6 Kabel TYI-64-32 pair connection cable termasuk : 2
1. 1 pcs Back Mount frame 11 ways
2. 10 pcs Terminal LSA 10 pairs
3. 1 roll jumper cable @500 meter

7 Digital Rectifier System + Battery Back Up 1


1. 1 Unit Digital Rectifier 48VDC/40A
2. 4x12VDC 40AH Seal Lead Acid Battery

B Remote PABX Lokasi PJT


1 Wallmount Rack 19" 12U Depth 550 1
2 Shelf ACT-14 Slot 1
3 Cos-mo connector direct FO SM 2
4 INTOF2 Board Interface Fiber Optic 2
5 Analog Extension (eZ32 Board) 2
32 Ports analog extension equipment (Cap: 128 Analog Ext.)
6 Kabel TYI-64-32 pair connection cable termasuk : 2
1. 1 pcs Back Mount frame 11 ways
2. 10 pcs Terminal LSA 10 pairs
3. 1 roll jumper cable @500 meter
7 Digital Rectifier System + Battery Back Up 1
1. 1 Unit Digital Rectifier 48VDC/40A
2. 4x12VDC 40AH Seal Lead Acid Battery

C Main Unit PABX Lokasi IRJ


1 Kabel TYI-64-32 pair connection cable termasuk : 9
1. 2 pcs Back Mount frame 11 ways
2. 20 pcs Terminal LSA 10 pairs
3. 1 roll jumper cable @500 meter
2 Telephone Grounding max. 1 Ohm, termasuk : 1
1. Baar terminal grounding
2. Grounding Test max. 1 ohm
3 Instalasi Kabel Data Cat-5e Operator Console+Billing Telephone 3
1. 50 meter UTP Cable Cat-5e
4 Note Book (Technical Operation) 1
1. LED Screen 14"
2. Intel Corei5/RAM4Gb/HDD1TB, Win 10 Pro

D Additional Digital Board Remote MG


1 UAI-8 Board (Digital Equipment 8 port) 2
termasuk instalasi up to terminal Box

E Relokasi Instalasi Kabel Telepon


1 Instalasi Gd. IRNA 2 - Gd. Tumbang
Kabel telepon Indoor 2x0.6 (60 pair) termasuk : 90
6 pcs Terminal LSA 10 pairs
2 Instalasi Gd. Cendrawasih- Gd. Ayodya
Kabel telepon Indoor 2x0.6 (60 pair) termasuk : 80
6 pcs Terminal LSA 10 pairs
3 Instalasi Panel MDF Gd. IRJ - Blok 1
a. Panel MDF 2 x 200 pair, termasuk : 1
1. 4 pcs Back Mount Frame 11 ways
2. 40 pcs Terminal LSA 10 pairs
3. 2 roll Jumper cable @500 meter
b. Panel TB 2x100 pair, termasuk : 1
1. 2 pcs Back Mount Frame 11 ways
2. 20 pcs Terminal LSA 10 pairs
3. 1 roll Jumper cable @500 meter
c. Kabel telepon Indoor 60 pair termasuk : 70
6 pcs Terminal LSA 10 pairs
4 Instalasi Panel MDF Gd. IRJ - Blok 2
a. Panel TB 2x100 pair, termasuk : 1
1. 2 pcs Back Mount Frame 11 ways
2. 20 pcs Terminal LSA 10 pairs
3. 1 roll Jumper cable @500 meter
b. Kabel telepon Indoor 60 pair termasuk : 152
6 pcs Terminal LSA 10 pairs
5 Instalasi Panel MDF Gd. IRJ - Blok 3
a. Panel TB 2x100 pair, termasuk : 1
1. 2 pcs Back Mount Frame 11 ways
2. 20 pcs Terminal LSA 10 pairs
3. 1 roll Jumper cable @500 meter
b. Kabel telepon Indoor 60 pair termasuk : 95
6 pcs Terminal LSA 10 pairs
F Relokasi Instalasi Kabel Fibre Optic
Kabel Duct Fiber optic SM 12 Core FO (Koneksi exist. Gd. Admin ke Gd. IRJ/R. Sentral Telephone
1 Baru), termasuk : Pipa standar 234
Kabel Duct Fiber optic SM 48 Core FO (Koneksi exist. Gd. IRNA 2 ke Gd. IBS lama ke Gd. IRJ/R.
2 Sentral Telephone Baru), termasuk : Pipa standar 190
3 Kabel Duct Fiber optic SM 12 Core FO (Gd. GBST ke Gd. PJT ke Gd. IRJ), termasuk : Pipa standar 159
4 Kabel Duct Fiber optic SM 12 Core FO (Gd. PJT ke Gd. ICC), termasuk : Pipa standar 159
5 Kabel Duct Fiber optic SM 12 Core FO (Gd. ICC ke Gd. Cendrawasih), termasuk : Pipa standar 349
6 OTB 24 Core Adapter (SC Conector), Pigtail & Protection Sleeve termasuk : Terminasi dan OTDR - Lok 1
7 OTB 24 Core Adapter (SC Conector), Pigtail & Protection Sleeve termasuk : Terminasi dan OTDR - Lok 1
8 Kabel Duct Fiber Optic SM 12 Core FO (Call Center) 200

9 OTB 24 Core Adapter (SC Connector), Pigtail & Protection Sleeve termasuk : Terminasi dan OTDR - Lokasi1 Contact Center

Keterangan :
* Harga sudah termasuk pemasangan, uji coba dan uji fungsi.

* Pada saat pemindahan, penyedia harus menyiapkan backup PABX dengan kapasitas dan kemampuan setara dengan
PABX eksisting.
VOLUME

set
set
unit
unit
unit

set

set

set
set
unit
unit
unit

set

set

set
set

set

unit

unit

set

set

set

set

m
m

m
m
m
m
set
set
mtr

set