HSE Daily Report

PROJECT: DAMMAM INDEPENDENT SEWAGE TREATMEENT PLANT (DMMISTP)

Report No.: DISTP-SPV-EPC-HSEDR-001 Date: 20-DEC-2020


Safety Officer: Muhammad Asif

Weather Condition Temperature


Cloudy ☐ Stormy ☐ Clear ☒ Cold ☐ Hot ☐ Rainy ☐ 22o C Dammam

Sr.# Activities in Progress Locations Remarks


a) Inlet Headwork
1 Excavation Satisfactory
b) Biological Tank A&B
a) Warehouse
2 Rigging Satisfactory
b) Balancing Tack
Hot Work a) Warehouse
3 Satisfactory
(Welding, Grinding & Cutting) b) Workshop
4 Working at Height a) Warehouse Satisfactory
5 Steel Fixing a) Balancing Tank Good
6 Road Work a) All Site Area In process
7 Scaffold Erecting a) Primary Clarifier D Not satisfactory (1)

Incident: Location Description


No
Near Miss
No
HSE Violation:
No
Other:
1- Imbalance Scaffold without tag: Scaffolders fixed it as given instructions.

HSE Officer: Muhammad Asif


Sign:
Technical Director: Hayder AL-Rawashdeh Sign: