A. 26 days
B. 18 days
C. 44 days
D. 8 days
Answer: D
2: What is float?
A. The latest time an activity can be started without affecting the next activity’s earliest
start
B. The length of time an activity can be deferred without affecting the project duration
C. The length of time an activity can be deferred without affecting the next activity’s
earliest start
D. The latest time an activity can be started without affecting the project duration
Answer: B
3: Select the correct equation for calculating total float for an activity.
A. Total Float = LFT - EST
B. Total Float = EFT - EST
C. Total Float = LFT - EFT
D. Total Float = LST – EFT
Answer: C
4: The length of time an activity can be deferred without affecting the earliest start time of
any immediate successor activity is called ______________.
A. non-float
B. free float
C. zero float
D. intermediate float
Answer: B
5: What is the term for an activity that cannot be deferred without affecting the project
completion date or another activity’s start date?
A. Standard float
B. Intermediate float
C. Free float
D. Zero float
Answer: D
6: PERT stands for :
Answer: A
A. Critical Activities
B. Dummy activities
C. Non-critical activities
D. None of these
Answer: A
8: Select the two time estimates that are used to determine project duration by using PERT.
Answer: B
9: Consider an EST of five days and duration of four days. Now, calculate the EFT of the
activity.
A. 1 day
B. 9 days
C. 10 days
D. 20 days
Answer: B