Engineering & Project Management - AE555EPM Final exam

Duration: 1.25 Hours 1 Pages 11:00 a.m. Sunday 15th July 2018

1. You are required to issue an RFP to purchase a Flight Simulator


Describe the main sections of the RFP content and what they should
include as follows:
a. Summarise the main components: Scope, deliverables etc..)
b. Sketch a preliminary Gantt chart
c. What do you expect to be critical path of the project
d. What approach would you suggest for such project?
e. What are the risks involved
f. If you are a contractor, what would your offer constitute
g. Discuss the evaluation system and its impact
Bearing in mind the following conditions:
The contractor must submit a design for the necessary building and civil
works requirements including utilities (electricity, water, firefighting etc..)
List your requirements for training, maintenance and support

2. With reference to figures below, find IRR for case where the Major
Machine is rented vs. bought. Given rent is 10,000.00 per month
Bought

Setup costs Major Machine 1,000,000.00


Equipment & Furniture 100,000.00
Others 20,000.00
Total 1,120,000.00-
Cash
Flow Year Revenue Expenses Nett
1 1,000,000.00 750,000.00 250,000.00
2 1,100,000.00 700,000.00 400,000.00
3 1,050,000.00 800,000.00 250,000.00
4 900,000.00 670,000.00 230,000.00
IRR
What would you decide? How long is capital payback period?