You are on page 1of 10

Rock Mechanics and Rock Engineering

https://doi.org/10.1007/s00603-020-02114-2

TECHNICAL NOTE

An Analytical Investigation on the Estimation of Water Inflow


into a Circular Tunnel Based On‑site Data
Qian Liu1 · Zhiye Zhao1 · Wen Nie2 · Jianping Sun1 · Fei Xiao1

Received: 13 May 2019 / Accepted: 7 April 2020


© Springer-Verlag GmbH Austria, part of Springer Nature 2020

Keywords  Pre-excavation grouting · Water inflow · Analytical solution · Probe hole · Tunnel

1 Introduction the geological and hydrogeological conditions, the grout


mix and the grouting pressure, etc. (Stille 2012; Stille 2015;
Pre-excavation grouting (PEG) was developed in early Shi et al. 2016; Shang 2020; Fan et al. 2020). The limit of
1980s to reduce water inflow in hard rock tunnelling. Over residual inflow, Qlim, specifies the project requirements of
the years, positive experiences have been made with this groundwater control during tunneling as shown in Table 1.
method, particularly during the construction of subsea tun- Qlim is one of the measures to assess the likely groundwater
nels and tunnelling in urban environments which are sensi- inflow that may occur during tunnelling. For tunneling in an
tive to groundwater drawdown. The technical procedure of environment which are sensitive to the groundwater draw-
PEG has also been improved in order to satisfy the increas- down, systematic grouting is usually adopted. If the tunnel
ingly strict technical and environmental requirements. is in a rural area without specific requirements on the inflow
A common criterion for PEG application is based on the rate, a PEG trigger value might be adopted for the determi-
observational approach. The water inflow from probe holes nation of the execution of grouting. The PEG trigger value,
might be used to predict the potential water inflow into the QA, is usually defined using the observation of water inflow
tunnel for the execution of grouting based on the predefined from the probe hole. Generally, a lower PEG trigger value
measures in terms of grouting pressure and grout take. A indicates a lower residual water inflow into tunnel, and the
prerequisite for PEG application is the availability of a cal- PEG trigger values vary with rock conditions and the limit of
culation method to obtain a quick estimation of potential residual inflow. By empirical estimation, the range of upper
water inflow into tunnels based on-site data. To meet this limits of targeted residual inflow for different projects and
prerequisite, several relevant problems have been involved, situations can be in the range from 5 to 50 L/min per 100 m,
such as the determinations of the limit of residual inflow, as shown in Table 2. The ratio of Qlim/QA is about 12.5–15,
except the case in Qingdao subsea tunnel.
The empirical relationships shown in Tables 1 and 2 are
* Wen Nie
wnie001@e.ntu.edu.sg case-specific and may not be applicable to tunnels under
other geological and hydrogeological conditions. This study
Qian Liu
liuq0025@e.ntu.edu.sg aims to establish the general relationships among the water
inflow rates observed or estimated from the probe holes,
Zhiye Zhao
czzhao@ntu.edu.sg the tunnel and the grouted tunnel, based on the analytical
solutions derived by Park et al. (2008) and Li et al. (2018).
Jianping Sun
SUNJ0030@e.ntu.edu.sg
Fei Xiao
fxiao005@e.ntu.edu.sg 2 Problem Description
1
School of Civil and Environmental Engineering, 2.1 A Simplified Procedure of Grouting
Nanyang Technological University, 50 Nanyang Ave,
Singapore 639798, Singapore
Garshol et al. (2012) simplified the grouting procedure into
2
School of Civil and Transportation Engineering, Hebei several steps, as shown in Fig. 1. The probe holes are firstly
University of Technology, Tianjin 300401, China

13
Vol.:(0123456789)
Q. Liu et al.

Table 1  Examples of the residual inflow limits for individual sections of the tunnel (modified after Grøv and Woldmo 2012)
Project related Country Limit of residual inflow, Qlim PEG requirements

Tunnelling in urban environments which are Norwegian 2–4 L/min per 100 m Systematic grouting
sensitive to groundwater drawdown Swedish 2–5 L/min per 100 m
Finland < 2 L/min per 100 m
Subsea tunnels and rural tunnels Norwegian 10–30 L/min per 100 m PEG initiates if the water inflow
Tunnels without specific requirements Norwegian > 30 L/min per 100 m is beyond the PEG trigger
value

Table 2  Some relationships Limit of residual inflow, Qlim Trigger value for single Trigger value
between the target residual hole, QA for all holes,
inflow limit and PEG trigger QA’
values (modified after Mao
et al. 2016) 15 L/min per 100 m tunnel 1 L/min 3 L/min
30 L/min per 100 m tunnel 2 L/min 6 L/min
50 L/min per 100 m tunnel 4 L/min 10 L/min
15 L/min per 100 m, Harbor area treatment scheme 1.0 L/min 3.0 L/min
27.8 L/min per 100 m, Qingdao Subsea tunnel 5 L/min 10 L/min

The probe holes are assumed to be over 20 m long; If the targeted residual inflow limits are not met, the
trigger values of measured inflow can be checked and modified subject to the ground response during tun-
nelling

Yes
Probe hole(s) qp > qA Add grout holes

No No
Check hole(s)
qck < qB or reach the
termination criteria

Yes

No grouting Stop grouting


Probe hole
Grout hole
Check hole
Fill holes Advance
NOTE:
Qp is the water inflow in probe hole, unit in L/min;
Qck is the water inflow in check hole, unit in L/min;
QA is the PEG trigger value to determine the needs of grouting, unit in L/min;
QB is the trigger value at check hole to determine the continuation of grouting, unit in L/min.

Fig. 1  Flowchart of simplified grouting procedure (modified after Garshol et al. 2012)

drilled to obtain the water inflow Qp which will be used to the grouting process. The check hole, Qck, is drilled later to
determine the execution of grouting based on its comparison measure the water inflow into it. In general, the check hole
with QA. If Qp ≥ QA, the grout holes may drill, and then all trigger values QB should be continuously reviewed and may
probe and grout holes are grouted with the monitoring of be modified according to the ground response and grouting

13
An Analytical Investigation on the Estimation of Water Inflow into a Circular Tunnel Based On‑site…

performance (Høien and Nilsen 2014; Holmøy and Nilsen surface. The above assumptions make it possible to sim-
2014) and in some practical cases, we may set QA = QB. If plify the 3D flow problem into a 2D flow problem. Tani
Qck ≥ QB, an additional round of grouting might be required. (1999a, b) has studied the influences of the tunnel shapes
on the water inflow into tunnels, and it was suggested that
2.2 Definition of the Problem the equivalent circular shape with an equal area could be
used to consider the different tunnel shapes. It also should
Researchers have presented closed-form solutions to cal- be noticed that the water flow into the grouted zone has
culate steady-state inflow into a circular tunnel in homo- been simplified from a three-dimensional domain to a
geneous rock mass with isotropic permeability (Rat 1973; two-dimensional model, and it is assumed that a full-face
Lei 1999; El Tani 2003, 2010; Kolymbas and Wagner injection of grouting create a grouted zone which is con-
2007; Park et al. 2008; Coli and Pinzani 2014; Nikvar centric with the circular tunnel as those used in previously
Hassani et al. 2018). Rat (1973) has presented the exact analytical analyses (Li et al. 2018; Pan et al. 2018; Yang
relation for the water inflow considering a constant poten- et al. 2016).
tial and pointed out the importance of the pressure prob- Based on the above assumptions, the solutions for the
lem. Considering the problem as a simplification of a two- water inflow rate per unit length of probe hole (qp), circu-
dimensional problem where the ground surface serves as lar tunnel (qto), check hole (qck) and grouted tunnel (qtg)
the elevation reference datum, the steady seepage field can could be calculated based on the following 4 cases which
have 3 boundary conditions (see Fig. 2): (1) total hydraulic are further listed in Table 3.
head at the ground surface is H  , (2) constant water pres- Case A: water inflow into a probe hole under constant
sure pp might occur at the probe hole, and (3) constant water pressure pp (Rat 1973; Park et al. 2008).
water pressure pg is assumed at the outer boundary of ( )
p
grouted zone. Several other assumptions have been made 2𝜋k H + hp − 𝛾 p
to derive the analytical solutions, including (El Tani 2003; √
w
qp = ( ) (1)
h2p
Park et al. 2008; Li et al. 2018): (1) the circular tunnel is in hp
ln r + r2 − 1
a fully saturated, homogeneous, isotropic and semi-infinite p p

porous aquifer with a constantly horizontal water head; where qp is water inflow rate per unit length of probe hole; k
(2) the surrounding ground has the isotropic permeability is isotropic permeability of the surrounding rock; γw is unit
and a steady-state groundwater flow, and (3) the grout- weight of water; H is depth of ground surface from water
ing material is homogeneous and isotropic and a full face table; hp is probe hole depth from the probe hole center to
injection of grouting is extended beyond the excavation the ground surface, and rp is radius of probe hole.

Fig. 2  Schematic diagram of the steady water inflow into probe hole (a), circular tunnel (b), check hole (c) and grouted tunnel (d)

13
Q. Liu et al.

Table 3  Parameters and notations used in the four cases


Cases Targets Water pressure at hole/tunnel Total water head Radii
perimeter

A Probe hole pp H + hp −
pp
rp , radius of the probe hole
𝛾w
B Circular tunnel before grouting Atmospheric pressure H+A r, radius of the circular tunnel
C Check hole pck H + hck −
pck
rck , the radius of the control
hole, rg , external radius of
𝛾w

the grouted zone


D Grouted circular tunnel Atmospheric pressure H+h−
pg
r, radius of the circular tun-
𝛾w
nel,rg , external radius of the
grouted zone

H is the depth of ground surface from water table; h is the tunnel depth from the tunnel centre to the ground surface; hp is depth of the probe
hole (from the centre of probe hole to the ground surface); hck is depth of the check hole (from the centre of check hole to the ground surface);
pp is water pressure in the probe hole; pck is water pressure
√ in the control hole; pg is water pressure effective at the inner boundary of the grouted
tunnel, and A=h(1 − 𝛼 2 )∕(1 + 𝛼 2 ) in which 𝛼 = 1r (h − h2 − r2 )

As rp ≪ hp , Eq. (1) could be further simplified as shown Case D: water inflow rate per unit length of grouted cir-
by Tani (1999a, b). Thus, the permeability of surrounding cular tunnel qtg by assuming a constant pore pressure pg is
rock masses could be back-calculated as: effective at the tunnel perimeter (Li et al. 2018).
( 2h ) ( p
)
qp ln r p 2𝜋k h + H − 𝛾 g
( )
w
(2)
p
k= ( ) qtg = √( )
p (r ) 2 (5)
2𝜋 H + hp − 𝛾 p kr g h h
w
k
ln r
− ln r
− r
− 1
g t g g

According to Eq.  (2), the influence of the radius of


probe hole on the water inflow could be ignored as the In practice, after grouting works, the atmospheric pres-
variation of water inflow is only about 1% when the radius sure is effective at the premier of the tunnel, Eq. (5) can be
of probe hole rp increases from 48 to 60 mm. simplified as follows:
Case B: water inflow into a tunnel where atmospheric
2𝜋k(h + H)
pressure is effective inside the tunnel and at the tunnel qtg = ( √( ) )
(r )
perimeter (El Tani 2003; Park et al. 2008). kr g h h
2
(6)
k
ln r − ln r − r
−1
g t g g
2𝜋k(A + H)
qto = ( √ )
2 (3)
ln hr + hr2 − 1

3 Relationship Among Water Inflows


where q to is water inflow rate per unit length of cir- into Probe Holes, into Tunnels
cular tunnel; r is radius of the circular √ tunnel, and and into Grouted Tunnels
A = h(1 − 𝛼 2 )∕(1 + 𝛼 2 ) in which 𝛼 = 1r (h − h2 − r2 ).
Case C: water inflow into the check hole under constant 3.1 Relationship Between qp and qto
water pressure pck (Li et al. 2018).
( ) By submitting Eqs. (2) into (3), the water inflow into the
p
2𝜋k hck + H − 𝛾ck
tunnel qto could be estimated based on the water inflow into

w
qck = ( ) ( ) ( ) (4)
k r g h h2ck the probe hole qp as:
k
ln r
− ln r
ck
− r2
− 1 ( 2h )
g ck g g
(A + H)ln r p
qto
where kg is permeability of the grouted zone; rg is external
p
=( ) ( √ ) (7)
qp
radius of the grouted zone; rck is the radius of the check p 2
H + hp − 𝛾 p ln hr + hr2 − 1
hole; hck is depth of the check hole (depth from the hole w

centre to the ground surface), and pck is water pressure in


the check hole.

13
An Analytical Investigation on the Estimation of Water Inflow into a Circular Tunnel Based On‑site…

As shown in Eq. (7), the relationship between the water limited effects on the variations of qto ∕qp . In the following
inflow into the probe hole ( qp ) and the water inflow into tun- discussions, the depth of the probe hole is assumed the
nel ( qto ) is related to the depth of ground surface from water same as the depth of the tunnel, i.e. hp = h.
table H  , the geometry of tunnel (depth h and radius r ), the If it is assumed r∕rp = 200 and r << h , a simplified
geometry of the probe hole (depth hp and radius rp ), and the solution for the ratio of qto ∕qp can be obtained, based on
water pressure in the probe hole ( pp). Eq. (7), as follows:
The change in qto ∕qp due to the depth of the probe hole ( )
( hp ) is firstly examined in different depths of tunnels by qto (H + h)ln 400h
r
assuming the other parameters are constant (i.e., H = 50m =( ) ( ) (8)
qp pp
H + hp − 𝛾 ln 2hr
and pp ∕𝛾w = 20m ). As shown in Fig. 3a, the ratio of qto ∕qp w
is sensitive to h p when the tunnel located at a shallow
depth ( h = 50m ) with a large cross-section (i.e. r ≥ 10m ). Figure 4a plots the lowest boundary of qto/qp by vary-
For example, the ratio of qto ∕qp may increase from 4.47 to ing the ratio of h/r. It shows qto/qp may decrease with the
5.25 when the probe hole depth is changed from mid-wall increase of h/r. Specifically, when h/r changes from 7 to
(hp = h) to the crown ( hp = h − r ) for the tunnel with radius 30, the ratio of q to/q p will be reduced from 3.0 to 2.3.
r = 12m . However, the influence of the depth of the probe When h/r is larger than 30, the decrease gradient of qto/qp
hole on the ratio of qto ∕qp becomes less significant when with the increase of h/r becomes much lower. For a tunnel
the tunnel is deeper (see Fig. 3b for the case of h = 100m ). with h∕r = 10 and r = 10m , the ratio of q to/qp increases
The difference in the ratio of qto ∕qp is within 6% when the with the increase of pp ∕𝛾w under a constant depth from
probe hole depth is changed from the crown ( hp = h − r  ) the water table to ground surface ( H  ) as shown in Fig. 4b.
to the floor ( hp = h + r  ) for tunnel with radius r = 12m . A smaller H will result in a larger increase of qto ∕qp ratio
Considering the influence of both rp and hp on the water with the increase of pp ∕𝛾w . It also shows the ratio of qto/qp
inflow into the probe hole in Eq. (2) and into tunnel in may not less than 2.77 under such conditions. Therefore,
Eq. (7) and the fact that probe holes are usually drilled it is important to measure the water pressure in the probe
in the central area of the excavated surface, it could be hole ( pp ) to obtain a reasonable estimation of water inflow
concluded that the changes of the geometry of probe hole using the ratio of qto ∕qp to assist the preliminary grouting
(probe hole depth hp and probe hole radius rp ) might have design.

6 6
r=5 r=5
qto / qp
qto / qp

r=10 r=10
5 5
r=12 r=12

4 4

3 3

2
2

Depth of probe hole, hp Depth of probe hole, hp

(a) (b)

Fig. 3  Effects of the depth of probe hole with tunnel depths h = 50 m (a) and h = 100 m (b)

13
Q. Liu et al.

6 6

Lowest boundary of qto/qp


H = 50 m

qto / qp
H = 100 m
5
4 H = 200 m
2.77
2.77 -- 4

2
3 2.77

0 2
0 10 20 30 40 0 10 20 30 40 50
h/r pp/γw, m

(a) (b)

Fig. 4  Variations of the ratio of qto/qp its lowest boundary (a) and the changes with H at h/r = 10 (b)

As it can be observed from the above analytical solutions, Figure 5 plots the variation of ratio of qtg ∕qto with differ-
the relationship between water inflows into the probe hole ( qp ) ent sealing efficiencies, based on Eq. (10), which shows that
and that into the tunnel ( qto ) are affected by the groundwater the qtg ∕qto ratio are initially small and will increase with the
table, the depth and size of the tunnel, and the water pressure increase of sealing efficiency. When the sealing efficiency is
in the probe hole. To estimate the water inflow into the tun- increased from 90 to 100%, the ratio of qtg ∕qto is decreased
nel based on the probe hole data, we need to know the water by almost 36% for h∕r = 10 and rg ∕r = 1.8 . In the case of
inflow and the water pressure in the probe hole, as well as the a lower rg ∕r, for example rg ∕r = 1.2 , the ratio of qtg ∕qto is
requirement that the geological conditions are similar between decreased by 64.7%. This might be the reason that PEG
the tunnel and the probe hole. might not be practical if the sealing efficiency needs to be
higher than 90% (Stille 2015). The approximated solution
3.2 Relationship Between qto and qtg of qtg ∕qto could be used to estimate the grouting efficiency
during the preliminary design stage.
To investigate the grouting effect, Stille (2012) introduced
the sealing efficiency (1 − kg ∕kr ) to measure the relative
number of fractures that need to be sealed, followed by the 4 A Case Study
evaluation of the grouting difficulties. The sealing efficiency
is related to the water inflow into the tunnel after grouting A storage rock cavern project in Singapore is used for the
which could be related to the ratio between qto and qtg . By case study, which consists of 5 underground rock caverns
combining Eqs. (3) and (5), the relationship between qto and and associated tunnels, with the total excavated volume of
qtg can be written as: more than 2 million m3 (Shao et al. 2015; Zhou et al. 2017;
Fan et al. 2018). The operation tunnel A (OT-A) is located
⎧ � � � ⎫ at Level 1 about 100 m below the sea, which we considered
⎪ h
ln r + r2 − 1 h2 ⎪
⎪h+H ⎪ as a circular tunnel with an equivalent area in this case (see
qtg = ⎨ × � � � ⎬qto Fig. 6a). During deep investigation work, seepage water
⎪ A + H � k � � rg � h
� �2
h ⎪ encountered from investigation holes. Probe hole with a
⎪ ln − ln − −1 ⎪
⎩ kg r rg rg
⎭ radius rp = 54 mm and a length of 15 m was drilled to inves-
(9) tigate the water-bearing layers. Both the water inflow and
If r << h , Eq. (9) can be rewritten as: the pressure ( pp ) from the probe hole were recorded after
( ) drilling. The pre-grouting works were going to be performed
qtg ln 2h if the water ingress from the probe hole was larger than 6 L/
r
= ( √( ) ) min. A typical fan grouting pattern and its profile are shown
q ( ) ( ) (10)
to k rg h h
2 in Fig. 6b. In practice, the probe hole locations and grout-
ln − ln − −1
kg r rg rg ing patterns at each stage would be adjusted to suit local
geological and hydrogeological observations.

13
An Analytical Investigation on the Estimation of Water Inflow into a Circular Tunnel Based On‑site…

100%
h/r = 10, rg/r = 1.2
h/r = 30, rg/r = 1.4
qtg / qto
80% h/r = 20, rg/r = 1.4
h/r = 10, rg/r = 1.4
qtg / qto = 64.7%
h/r = 5, rg/r = 1.4
60%
h/r = 10, rg/r = 1.8

Sealing efficiency = 90%


40% qtg / qto = 36.2%

20%

0%
0% 20% 40% 60% 80% 100%
Sealing efficiency (1-kg/kr)

Fig. 5  Variations of qtg/qto with different sealing efficiency

Fig. 6  Schematic diagrams of the tunnel location (a) and typical grouting pattern (b)

The water inflow measured from the probe holes was and hp = 86m , the potential water inflow rate into the cav-
used to estimate the water inflow of the tunnel. The water ern qto could be estimated using Eq. (7) by inputting the
inflow into the tunnel was calculated as the sum of water relative pressure pp and water inflow rate qp of the probe
inflow from grout holes at the same excavated face, which hole. The comparison of the real site observation inflow
is used to calculate water inflow rate per unit length qp . data and the estimation of the water inflow is shown in
The observations of the water inflow into the tunnel dur- Fig. 7b, which indicates a reasonable level of accuracy.
ing the construction are presented in Fig. 7a, which shows However, the accuracy might be higher if we consider the
that the water inflow into the tunnel varies significantly regions with the observed water inflow less than 120 L/
along the tunnel. By assuming H = 20m, h = 80m, r = m min ( qp = 8L∕min∕m  ) (see Fig.  7c). As the analytical

13
Q. Liu et al.

500
Estimation
400 Observation
Water inflow, L/min

300

200

100

0
0 50 100 150 200 250
Along the operation tunnel (OT), m

(a)

400 125

100
300
Estimation, L/min
Estimation, L/min

75
200
50
y = 0.6959x y = 0.8266x
100 R² = 0.9312
R² = 0.6924 25

0 0
0 100 200 300 400 0 25 50 75 100 125
Observation, L/min Observation, L/min

(b) (c)

Fig. 7  Estimated water inflow along the operation tunnel (a) and the comparisons with all measured data (b) and the observed water ingress (c)
of the tunnel is less than 120 L/min

solutions for the water inflow into the tunnel in 15  m large geological discontinuity is encountered in the section
length are based on the assumption that the hydrogeologi- which may induce large water inflow into the tunnel, the
cal condition at the probe hole should be similar to the hydrogeological condition at the probe hole cannot repre-
hydrogeological condition at the tunnel, it implies that the sent the complex hydrogeological condition at the tunnel,
tunnel section under consideration should have fewer geo- then the prediction may have a poor accuracy. For the rela-
logical discontinuity features (faults/water-bearing zone, tionship between the water inflow in the tunnel before and
etc.), which may explain the better estimation accuracy after the grouting, there was lack of onsite data available.
for the section with small water inflow. However, when a More exploration study will be carried out in the future.

13
An Analytical Investigation on the Estimation of Water Inflow into a Circular Tunnel Based On‑site…

5 Conclusions El Tani M (1999) Water inflow into tunnels. In: Proceedings of the
World Tunnel Congress ITA-AITES
El Tani M (2003) Circular tunnel in a semi-infinite aquifer. Tunn
In this study, the relationships among the water inflows into Undergr Space Technol 18:49–55. https​://doi.org/10.1016/S0886​
probe holes, into the tunnel and into the grouted tunnel are -7798(02)00102​-5
investigated using the analytical solutions derived by Park El Tani M (2010) Helmholtz evolution of a semi-infinite aquifer drained
by a circular tunnel. Tunn Undergr Space Technol 25:54–62. https​
et al. (2008) and Li et al. (2018). It can be observed that the ://doi.org/10.1016/j.tust.2009.08.005
water inflow into the probe hole ( qp ) and into the tunnel ( qto ) Fan LF, Gao JW, Wu ZJ, Yang SQ, Ma GW (2018) An investigation of
are affected by the groundwater table, the depth and size of thermal effects on micro-properties of granite by X-ray CT tech-
the tunnel, and the water pressure in the probe hole. The nique. Appl Thermal Eng 140:505–519. https:​ //doi.org/10.1016/j.
applt​herma​leng.2018.05.074
lowest boundary of the ratio of qto ∕qp might decrease with Fan LF, Gao JW, Du XL (2020) Thermal cycling effects on micro-
the increase of h∕r . Specifically, when h∕r changes from 7 property variation of granite by a spatial micro-observation. Rock
to 30, the ratio of qto ∕qp will be reduced from 3.0 to 2.3. The Mech Rock Eng. https​://doi.org/10.1007/s0060​3-020-02065​-8
relationship between the water inflows into the tunnel before Garshol KF, Tam KWJ, Mui WBS, Chau KMH, Lau KCK (2012)
Grouting techniques for deep subsea tunnels in Hong Kong, In:
and after grouting ( qto ∕qtg ) illustrates the level of difficulty Proceedings of World Tunnel Congress
to perform grouting for the case of sealing efficiency > 90%. Grøv E and Woldmo O (2012) Modern pre-grouting technology in
A case study of an operation tunnel in a rock cavern pro- Norway. Proceedings of the Fourth International Conference
ject shows that the possible application of the analytical on Grouting and Deep Mixing, Grouting and Deep Mixing, pp.
805–815. https​://doi.org/10.1061/97807​84412​350
solutions to predict the water inflow into a tunnel based on Høien AH, Nilsen B (2014) Rock mass grouting in the Løren Tunnel:
the water inflow into probe holes. The case study shows a case study with the main focus on the groutability and feasibility
reasonable agreement between the observation at the site of drill parameter interpretation. Rock Mech Rock Eng 47:967–
and the estimation using Eq. (7) for water inflow less than 983. https​://doi.org/10.1007/s0060​3-013-0386-7
Holmøy KH, Nilsen B (2014) Significance of geological parameters for
120 L/min. As all the relationships presented in the paper predicting water inflow in hard rock tunnels. Rock Mech Rock Eng
are derived based on a simplified geological condition, the 47:853–868. https​://doi.org/10.1007/s0060​3-013-0384-9
analytical solutions should be used under the condition that Kolymbas D, Wagner P (2007) Groundwater ingress to tunnels: The
the geological and the hydrogeological conditions at the exact analytical solution. Tunn Undergr Space Technol 22:23–27.
https​://doi.org/10.1016/j.tust.2006.02.001
probe hole and for the tunnel should be similar without large Lei S (1999) An analytical solution for steady flow into a tunnel.
discontinuity features. In this work, the scenario that the Groundwater 37:23–26. https:​ //doi.org/10.1111/j.1745-6584.1999.
geological and hydrogeological conditions at the probe hole tb009​53.x
and at the tunnel face are significantly different is not consid- Li P, Wang F, Long Y, Zhao X (2018) Investigation of steady water
inflow into a subsea grouted tunnel. Tunn Undergr Space Technol
ered. It should be noted that conclusions from this study are 80:92–102. https​://doi.org/10.1016/j.tust.2018.06.003
based on simplified models, so they should be used for the Mao D, Lu M, Zhao Z, Ng M (2016) Effects of water related factors
preliminary design stage only. The relationship between the on pre-grouting in hard rock tunnelling. Proc Eng 165:300–307.
water inflows from the tunnel before and after grouting was https​://doi.org/10.1016/j.proen​g.2016.11.704
Nikvar Hassani A, Farhadian H, Katibeh H (2018) A comparative study
not verified in this study due to the lack of check hole data. on evaluation of steady-state groundwater inflow into a circular
In the future, data from check holes should be collected so shallow tunnel. Tunn Undergr Space Technol 73:15–25. https​://
as to check the efficiency of grouting. doi.org/10.1016/j.tust.2017.11.019
Pan Y, Luo Q, Zhou B, Chen J (2018) Analytical study on seepage
Acknowledgements  The authors thank NTU-JTC Industrial Infra- field of deep tunnel with grouting circle in half plane. J ZheJiang
structure Innovation Centre (I3C) and Nanyang Centre for Under- Uni (Eng Sci) 52:1114–1122. https:​ //doi.org/10.3785/j.issn.1008-
ground Space for financial support. The third author also wants to 973X.2018.06.010 (in Chinese)
thank National Natural Science Foundation of China (Grant number Park KH, Owatsiriwong A, Lee JG (2008) Analytical solution for
51908186). steady-state groundwater inflow into a drained circular tunnel in
a semi-infinite aquifer: a revisit. Tunn Undergr Space Technol
23:206–209. https​://doi.org/10.1016/j.tust.2007.02.004
Compliance with Ethical Standards  Rat M (1973) Ecoulement et répartition des pressions interstitielles
autour des tunnels. Bull Liaison Lab Ponts Chaussées 68:109–124
Conflict of interest  The authors declare that they have no conflict of Shang J (2020) Rupture of veined granite in polyaxial compression:
interest. Insights from three-dimensional Discrete Element Method mod-
elling. J Geophys Res Solid Earth. https​://doi.org/10.1029/2019J​
B0190​52
Shao Z, Varun M, Lee KT, Tiong YT (2015) Dat modifications
References and its application in large-scale cavern construction. Tunn
Undergr Space Technol 50:209–217. https​://doi.org/10.1016/j.
Coli M, Pinzani A (2014) Tunnelling and hydrogeological issues: a tust.2015.07.007
short review of the current state of the art. Rock Mech Rock Eng Shi P, Zhang D, Pan J, Liu W (2016) Geological investigation and tun-
47:839–851. https​://doi.org/10.1007/s0060​3-012-0319-x nel excavation aspects of the weakness zones of Xiang’an subsea

13
Q. Liu et al.

tunnels in China. Rock Mech Rock Eng 49:4853–4867. https​:// Zhou Y, Teo TY, Cai JG (2017) Rock engineering practice for develop-
doi.org/10.1007/s0060​3-016-1076-z ment of underground caverns in Singapore. GeoSS 10th Anniver-
Stille H (2012) Rock grouting in tunnel construction-models and sary Conference, Sinagpore
design, Proc. EUROCK 2012 keynote lecture. Stockholm, Sweden
Stille H (2015) Rock grouting: theories and applications. BeFo Rock Publisher’s Note Springer Nature remains neutral with regard to
Engineering Research Foundation, Stockholm jurisdictional claims in published maps and institutional affiliations.
Tani ME (1999) Water inflow into tunnels. In: Proceedings of the
World Tunnel Congress ITA-AITES. pp 61–70
Yang G, Wang X, Wang X, Cao Y (2016) Analyses of seepage prob-
lems in a subsea tunnel considering effects of grouting and lin-
ing structure. Mar Georesour Geotechnol 34:65–70. https​://doi.
org/10.1080/10641​19X.2014.95888​2

13

You might also like