You are on page 1of 42

CSU Brewery Design and Automation

Mid-project Report
Fall Semester 2016

- Full Report -

By:
Keaton Sloan
Briana Chamberlain
Andy Ross
Julia Tucker
Dustin Tauxe
Nick Wells

Department of Electrical and Computer Engineering


Colorado State University
Fort Collins, Colorado 80523

Project advisor: ​Dr. Tony Maciejewski

Approved by: ____​Dan Malyszko​______


Mid-Project Report
Page 1/42

ABSTRACT

The CSU Brewery Design and Automation senior design team has been tasked to design
and implement the Fermentation Science and Technology Department’s state of the art, training
brewery. Located within the Gifford building, the team has the distinct challenge of designing a
real world system within a predefined and pre-existing workspace. The system must meet not
only the immediate needs of the FST program, but also serve as a platform for future
modifications. This brewing system and laboratory will serve as the cornerstone of the
department’s experiential learning opportunities and departmental growth.
In the initial planning stages, it was assumed the team would be be actively automating a
brewing system. Soon after the senior design team began work on the project, the customer
realized that the LSC did not align well with the academic timeline, and that the team would gain
more experience through the design of a full brewing system, as well as see through the final
fabrication, implementation, and commissioning of the Gifford system.
Starting with the piping and instrumentation diagram as the foundation, the team has
gone through arduous revisions to meet customer specifications as well as industry standards.
Concurrently, with the help of industry experts, the senior design team has revised the design of
several of the brewing vessels including but not limited to: Mash Tun, Lauter Tun, Fermentation
Vessels, etc. Initial electrical and power compliance groundwork has been completed to ensure
that installation and construction can begin as soon as possible. Aside from the physical design,
an equal amount of resources has been allocated to creating an IT system topology design, which
includes virtual machines and process simulation environments. Some of the specific design
challenges include ensuring proper compliance with existing National Electric Code statutes and
working with existing HVAC, conduit, and brine heating and cooling lines. Besides constraint
specifications, considerable engineering problem solving is being applied towards making the
system efficient and safe.
Future work on the project includes installing, commissioning, and automating the
Gifford brewery. During this phase, the team will implement the automation platform and
extensively troubleshoot the system. Additionally, components researched for the physical power
side of the system will be seamlessly integrated into the Rockwell Automation software.
Programming architecture of the Batch program provided by Malisko Engineering will allow the
team and future users to fully simulate the brewing process from inception to consumption. The
team will soon begin work involving the Lory Student Center Brewery automation system, as
well as various systems adjustments, to ensure functionality and longevity of the systems.
Mid-Project Report
Page 2/42

TABLE OF CONTENTS
ABSTRACT 1

TABLE OF CONTENTS 2

Chapter 1 – Introduction 3

Chapter 2 – Summary of Previous Work 5


2.1 LSC Brewery 5
2.2 Gifford Brewery 5

Chapter 3 – Purpose, Objectives and Constraints 5


3.1 Purpose 6
3.2 Objectives 6
3.3 Constraints 6

Chapter 4 – System Design and Development 7


4.1 Process Development 7
4.2 Infrastructure 9
4.2.1 System Design 9
4.2.2 Piping and Instrumentation 9
4.2.3 Vessels 10
4.2.4 Power and Electrical 13
4.3 Automation 14
4.3.1 Integration 14

Chapter 5 – Future Work 15


5.1 Infrastructure 15
5.1.1 Piping and Instrumentation and Vessels 15
5.1.2 Power and Electrical 16
5.2 Automation 16
5.2.1 Integration 17

Chapter 6 – Ethics and Marketability 17

Chapter 7 – Conclusion 18

APPENDIX A - Abbreviations 19

APPENDIX B - Budget 20

APPENDIX C - Project Plan Evolution 22

APPENDIX D - Design Revisions 28


Vessels 28
Piping and Instrumentation Diagrams 37

ACKNOWLEDGEMENTS 42
Mid-Project Report
Page 3/42

Chapter 1 – Introduction

Colorado State University is a college located in Northern Colorado that provides a broad
variety of majors to over thirty thousand enrolled students. The university offers various majors,
but prides itself in academic excellence of the sciences. CSU has a strong culture of experiential
learning and providing the hands on experience that will aid in graduates’ success. One such
department is the Food Science and Human Nutrition Department which houses a program called
Fermentation Science and Technology. The program, hereafter referred to as “FST”, specializes
in the science and art form of fermenting beverages and food. Common examples of fermented
food and beverages are beer, cheese, meat, and wine. Fermentation of food is truly a
combination of both art and biochemical sciences. The program is only one of 22 in the country
that teach such a unique set of highly sought after skills in an industry that is an integral part of
an operating society. FST is relatively new in the context of the university timeline, however, is
already a leader among collegiate programs across the nation who offer such a unique major.
The FST program stands out nation-wide because of the hands on learning space that it
provides to its students. This comes in the form of multiple sensory and food science labs, with a
curriculum structured to best teach students how to practice food science safely and successfully.
An area of focus in this program is the fermentation of beer and the brewing process. The
curriculum currently focuses on the biochemistry involved, the brewing processes in small and
large scale breweries, and the engineering required in large scale food processing plants. All of
the aforementioned facets are crucial to educating a well rounded graduate of the program. To
compliment all three of these areas of education, as well as those not mentioned, the program
focuses on providing as much hands on and practical experience as possible to students.
Currently, the program teaches students the process of brewing through a lab based class
that brews on a small scale, modular brewing system. This system functions well, however, it is
not representative of what actually exists in the brewing industry. Due to its size and overall
design, the program is not able to sufficiently represent these aspects such as general automation,
automatic process monitoring, fluid movement, and complex flow system cleaning.
To overcome these insufficiencies, the program has decided to build two functional
breweries on campus. The purpose of these two breweries is to aid student learning and
development, and to support continual growth and research in the local brewing community. For
this reason, the two breweries will have different end users. One is a research and development
based system located in the Gifford Building, while the other is more of a practice and outside
industry focused pub style brewery, located in the Lory Student Center. The research and
development brewery will be more robust and capable compared to the pub style brewery,
including an addition of a second cooking vessel and the ability to control the process to a
greater degree. Both brewing systems have received the stamp of approval from the university,
and their design has been in progress for approximately the last year.
In order to get the breweries approved, one requirement the FST Program has to fulfill is
including other colleges and majors in this innovative and incredible opportunity. With this in
mind, the College of Engineering was offered an involvement opportunity to help develop these
two breweries. The decision was made to open up the design and automation of the breweries to
the College of Engineering as a means of providing engineering students with the chance to gain
experience on a real world project. More specifically, the project was offered to the graduating
class of 2017, and for years to come, as a senior design project for a team of interdisciplinary
Mid-Project Report
Page 4/42

students. Typical senior design projects consist of engineering need based projects, from
industry or the university, that a team of single major engineers complete over the course of two
semesters. Within these projects, the team of engineering students operate as a consulting firm,
with an industry professional as the customer. With the Brewery Design and Automation
project, Jeff Callaway, the Director of Fermentation Science, is the associated customer.
This project is meant for a multi-disciplinary team of engineers because of the wide scope
defined by the customer. In order to complete the project and have two working breweries, there
is quite an extensive list of engineering to be completed. A few of these tasks are the system
design, vessel specification, flow control equipment specification, IT infrastructure, automation,
and automation integration. All of the listed aspects are being considered and executed by the
senior design team that is comprised of a total of six students, studying electrical, computer,
chemical/biological, and mechanical engineering.
With such a broad project scope, the Gifford brewery has been assigned as top priority by
the customer, and the design process of this brewery was approached as the first step. After
design, the team aims to oversee the installation of the brewing vessels, flow equipment,
instrumentation, electrical/power, and automation equipment. Upon process installation, the
team will integrate the automation simulation platform that was developed with the help of
industry associates. This will make the Gifford Brewery an automated, scaled down version of
an innovative and industry standard brewing system.
The purpose of this report is to highlight the student engineering team’s current status in
regards to the project, and also to describe the future plans and next steps of the project that will
be completed in the Spring 2017 semester. The document is broken down into numbered
chapters that provide the skeleton of the report; Chapter 1 is the overall project introduction;
Chapter 2 contains information pertaining to previous project work and historical work of
brewing; Chapter 3 explains the purpose, objectives, and constraints of the project; Chapter 4
contains the in-depth system design progress with details of each area of the design; Chapter 5
covers the future work needing to be done and conclusions from the Fall 2016 semester; Chapter
6 focuses on the ethics and marketability of the project as a whole, and chapter 7 is the
document’s conclusion. Following the numbered chapters, there will be multiple Appendix
sections that include important details of the project such as the project evolution, budget,
abbreviation glossary, and design revisions.
Mid-Project Report
Page 5/42

Chapter 2 – Summary of Previous Work

The concept inception for this project was approximately three years prior to the current
project's timeline. In that 3 year period, the dream grew and developed and reached a point
where the project design could begin. Considering the two-fold nature of this senior design
project, it is best to describe previous work in a fashion which conforms to this duplicitousness;
specifically, elucidating prior work for the Lory Student Center (LSC) Brewery and Gifford
Building Brewery separately.

2.1 LSC Brewery

Prior to the senior design team’s involvement in this project, a significant amount of
infrastructural work had already been accomplished with regards to the LSC Brewery: vessels
had been finalized and manufactured, piping and instrumentation diagrams (P&ID’s) had been
approved, and contractors were lined up to perform construction on the utilities systems of the
LSC. On the automation front, preliminary work had begun: human-machine interface (HMI)
template screens were in development and programmable logic controller (PLC) structures were
laid out for the augmentation of process-specific code.
This work, largely performed by Malisko Engineering, was primarily destined for use in
the LSC Brewery and as such, it was designed specifically with the Ramskeller-adjacent location
in mind. Unfortunately, this means that such extensive work could not simply be carbon-copied
for use in the Gifford location, as each required distinctly unique modifications and
specifications be made to their idiosyncrasies. It is because of this fact that the previous work on
the LSC Brewery cannot also be considered prior work for the Gifford Brewery.

2.2 Gifford Brewery

The Gifford Brewery was far less complete in design at project inauguration than its LSC
counterpart. Only rough vessel designs existed, there were no P&ID’s, and vessels had not begun
to be manufactured. The only notable progress which existed at the time was that the
construction site had been roughly prepared for the implementation of a system: overhead piping
support was welded into place; floor berms were erected around the prospective hot liquor, cold
liquor, and clean-in-place (CIP) tank locations; and both the brine chiller and glycol compressor
were installed.
This work adequately prepared the design location for construction, come the time when
the senior design team deems it appropriate to proceed. No prior design work had occurred,
however, on neither the physical brewery plant nor the virtual automation environment.

Chapter 3 – Purpose, Objectives and Constraints

Before beginning design on any system, it is important to clearly define the purpose,
objectives and constraints. The purpose describes the goals of a project, and leads into more
specific outcomes through objectives and constraints. Objectives are an integral part of solving
engineering problems, as they turn the scope of work into measureable outcomes. The
Mid-Project Report
Page 6/42

tangibility of objectives helps to translate ideas into plans, which can be carefully analyzed and
used for progress. Another important step before attempting to solve an engineering problem is
to identify the project’s constraints. These constraints delve deeper into specific objectives and
define the bounds within which a design or project needs to operate. All three parts of the design
process will be discussed below.

3.1 Purpose

At Colorado State University, a multidisciplinary senior design team from the College of
Engineering will work hand in hand with the Fermentation Science and Technology department
to build two functional breweries on campus. The focus of the senior design team assigned to
this task is to design, construct, and automate the Gifford Brewery, as well as assist with the
automation of the LSC Ramskeller Brewery as needed. The purpose of these breweries is to
incorporate experiential learning into the FST program, and to lead universities across the nation
in growth and research in the brewing industry.
The customer (FST) has assigned the Gifford brewery as the primary focus of the senior
design team. The senior design team’s work on the Gifford Brewery will include, but is not
limited to, the system design, vessel specification, flow control equipment specification, IT
infrastructure, automation, and system integration. After the design, the team aims to oversee the
installation of the brewing vessels, flow equipment, instrumentation, and electrical/power
equipment. Upon installation, the team will integrate the automation simulation platform that
they developed with the help of industry associates to make the process an automated, scaled
down version of an industry brewing system.

3.2 Objectives

Of the 22 FST programs in the nation, CSU will be the only one to have a brewery of this
caliber and complexity designed by students. As this experiential learning opportunity for FST
students will greatly enhance the department, a key objective of the CSU Brewery Design and
Automation project is to incorporate both education and industry standards into the final
brewery. Many learning tools are therefore incorporated into this design, including but not
limited to sight glasses, hand valves, and manual system control. New Belgium Brewery and
many other industry collaborators are helping to provide knowledge on industry standards.
Using this guidance, the senior design team is creating a system that reflects a large brewery,
simply on a smaller scale.
Due to the nature of the CSU Brewery Design and Automation project, the scope is
incredibly complex and expansive. The senior design project must be continued for future years
in order to build out and optimize this year’s team design and automation processes of the
Gifford Brewery. All execution processes must therefore be fully documented to allow for a
transition phase between senior design teams.

3.3 Constraints

Like many real world projects, the CSU Brewery and Automation project has many
constraints to work within. One large constraint is the Gifford building itself. The lab space has
Mid-Project Report
Page 7/42

already been designed and constructed, therefore, the mechanical and electrical designs must be
organized within the existing space. Another constraint defined by the building is designing and
using the existing electrical, water, and steam systems.
An unusual constraint for a senior design project is departmental logistics. This project
operates under the jurisdiction of the Electrical Engineering department, however, the customer
and sponsor is the Fermentation Science and Technology department. Academics must be
considered during this project, however, the senior design team must deliver the desired design
only to the customer. Another sponsor, Malisko Engineering, as well as many industry
collaborators including New Belgium Brewing, Northand Process and Piping, and CSU facilities
also contribute and hold influence on this project.
Another integral consideration to this system design is safety. The entire system is
designed for safety with flow control components, such as valves, places specifically for process
design and safety measures. Vessel instrumentation is also designed for safety. The system
design includes level switches protect against boil over and proximity sensors prevent the system
from running while a hatchway is open. Steam and glycol systems are also used, therefore must
follow industry protocol. Clean-in-Place, or CIP will be a system used to clean after each brew,
and will use high molarity, FDA standard, chemicals. All of these items will be part of the
system’s operational protocol. Additional industry-wide safety protocol will be implemented for
Lock Out Tag Out as well as Confined Space Entry.
The final constraint is budget. Primarily donations, the budget has to operate within the
bounds of both engineering work/time and monetary donations. Please refer to Appendix B for
more information.

Chapter 4 – System Design and Development

4.1 Process Development

In any project, documentation is one of the most important elements. With this project in
particular, standardized documentation is crucial as the project will be continued on by other
senior design teams in the following years. The first documentation created was the process
descriptions, hereafter referred to as “PDs”. PDs are a step-by-step explanation of the flow of
the process which includes every vessel with its subsystem, and how a particular vessel and
subsystem are involved with each other. In industry, the Process Descriptions would normally
be created after the P&IDs are complete. However, the team worked on the Process Descriptions
simultaneously with P&ID development to allow every student to be involved at all stages.
The team followed Figure 1 from the ISA88 standards, which represents the procedural
control model for a batch system, to develop the PDs. For this project, the “Procedure” at the top
of this model represents the whole brewhouse as a system. The Procedure is comprised of “Unit
Procedures” which are the vessels individually. For example, one unit procedure is the Mash
Tun. The “Operation” goes into even more detail of what makes up the units, thus multiple
operations and systems make up one unit procedure or vessel. Lastly, the “Phase” is the basic
building block that makes up the individual operations. The phase details are what will be
specifically programmed into the PLC. In summary, multiple phases make up one operation,
multiple operations make up one Unit Procedure, and ultimately, multiple unit procedures make
up the desired Procedure, which again, is the brewhouse system as a whole.
Mid-Project Report
Page 8/42

Figure 1:​ Procedural control model from ISA-88 standards.

Using the model above as a guideline to develop the Process Descriptions, the team
utilized a variety of resources to gather more knowledge on the brewing process and brewing
equipment. Online research was conducted and multiple meetings were held with folks in the
brewing industry here in the Northern Colorado area. The industry meetings were especially
helpful. In those meetings, the team was able to gain insight into more of the details in regards
to the system itself, rather than just the broad concepts of brewing. Specifically, the team met
with New Belgium and Funkwerks breweries and learned more about particular process
parameters, in addition to how to conduct flow path analyses.
Once Process Descriptions and P&IDs are completed, Functional Design Specifications
are the next step. FDSs are essentially the most detailed version possible of the Process
Descriptions. These will be the most vital documents in regards to the system integration from
the raw process side, to the technological automation side. As this is a batch process, the FDSs
include every phase that will make up the operations for the unit procedures such as the Mash
Tun, Lauter Tun, etc. In each step, every valve, motor, and piece of instrumentation that will be
Mid-Project Report
Page 9/42

utilized is included on the FDS so the programmer for the PLC will know exactly which devices
to include in that step.
Once the PLC is programmed, which will be elaborated on in Chapter 4.3, and the
vessels/piping/instrumentation is installed, the next step towards the true integration of the
system is to conduct extensive testing known as an Input Output checkout. For IO check, every
single device on the vessels is tested with the PLC and HMI screen to ensure full and correct
functionality before beer is actually brewed.

4.2 Infrastructure

4.2.1 System Design

The full Gifford Brewery system design was added as a part of this senior design after the
class started. This addition redirected the timeline of the project considerably. The team focused
heavily on the flow system design this semester and has done so under the guidance of our
customer, and industry associates such as Malisko Engineering and New Belgium Brewing
Engineers. The design includes creating of piping and instrumentation diagrams as well as
specification of all the brewing and system vessels. Designing the brewing process has been of
the top most priority to the team because of how crucial it is to the rest of the project. Any
system can be automated including a poorly designed and barely functioning system. That
being said, the system design and development has been a very intentional and thought out
process in order to make a brewery that the customer satisfied with.
Development of the process design began by considering a broad variety of elements.
First the team considered how to make beer and how it is traditionally done at most breweries.
Then, the uniqueness and robustness of the system was also considered, for example the use of
extensive automation and and adjunct material cooking vessel. The next consideration was the
vessel design that was handed to the team at the beginning of the project. The vessels had gone
through a preliminary design phase but needed extensive reviews and corrections. However, the
preliminary vessel drawings were utilized as a mere starting block for process flow system
design. Next, a list of instrumentation needed to correctly control and monitor the system was
compiled by the customer. Including these instruments and flow control elements is crucial to a
functional and well automated system.

4.2.2 Piping and Instrumentation

With all the considerations above, the drafting process began. This was done in 2D
AutoCAD software by AutoDesk. Starting with creating vessels with the correct number of
ports and approximate locations denoted, they were then connected with basic process piping.
The basic piping transfers actual brewing materials between the vessels. An example being
transferring cooked mash to the lauter tun to be filtered into pure brewing wort. Auxiliary and
secondary processes were then added in. These systems included steam/condensate, glycol, and
clean in place. The next step in the process involved flow control, now that all the vessels were
connected by some means of piping.
Flow movement and control refers to pumps and valves and these were added to the
piping and instrumentation diagram next. This system needs to be able to precisely control flow
Mid-Project Report
Page 10/42

movement and paths. Manipulation is physically done by opening and closing valves along
piping and vessels and by increasing and decreasing pump speed until the desired flow velocity
is reached. Movement in this system has the ability to go in the logical forward direction from
cooking vessels, to separation and boil vessels as well as the other direction. This reverse feature
is useful for some specific recipes as well as cleaning. The brewing process is only one of the
processes that has had these flow control and movement equipment added to them, other systems
such as steam, glycol, and CIP have pumps and valves as well.

Figure 2​: Segmented version of the piping and instrumentation diagram.

With all of the previous work being completed, and having a working piping and
instrumentation diagram, one of the last steps towards completion is flow path analysis. The
purpose of this current analysis state is to complete a major component fail safe check against
our design. It approaches the system batch by batch and walks through the process descriptions.
In doing this, the team can denote which exact pumps will run, and which valves will need to be
open and closed for each flow movement step. In completing the analysis thus far, minor
adjustments to the P&ID have been made, mainly with the addition and subtraction of
pneumatics control valves. Again this analysis is about 50% complete with an expected
completion during the week after finals.

4.2.3 Vessels

The vessels are an important part of this system. They are connected and without them,
this process and it end goal of producing beer, would not be possible. To create a state of the art
system, the Gifford Brewery will consist of a Mash Tun, Cereal Cooker, Lauter Tun, Wort
Mid-Project Report
Page 11/42

Holding Tank, Kettle, Whirlpool, and Trub Tank on the hot side, and six fermenters on the cold
side.
In order to function, the vessels will constantly rely on smaller subsystems. Examples of
these are steam, glycol, hot and cold water, and instrumentation. Brewing is a standardized and
controlled process which creates the desired results within incredibly finite boundaries.
Instrumentation provides this through data acquisition, and allows for system wide process
control. Vessel instrumentation includes but is not limited to the following; Temperature
transmitters, pressure transmitters, level transmitters and level switches. Two instruments used
specifically for safety, are level switches and inductive proximity sensors for hatchway safety.
The vessel designs were discussed with the customer and Northland Process Piping prior
to CSU Brewery Design and Automation senior design team’s engagement. The vessel drawings
were delivered to the senior design team in the beginning of the project. Using the NPP provided
drawings, the P&ID design began. Once the senior design team further analyzed the system, it
soon became apparent that some vessel specifications, including inlet/outlet sizes, number and
type of instrumentation ports, etc. were not ideal for our customer’s desired system quality and
complexity. Industry guidance was sought out to then further investigate the vessel designs.
Refer to the example of NPPs Cereal Cooker drawing below.

Figure 3:​ Cereal Cooker Vessel Drawing

NBB met with a senior design team member to mentor and demonstrate what industry
calls a red line drawing. Red lines are commonly used in all engineering mark-ups and revisions,
however, will refer to the NPP drawings from here on out. A two-hour revision meeting allowed
for the red lining of the Cereal Cooker drawing. As shown below, every detail was scrutinized,
Mid-Project Report
Page 12/42

in order to ensure that all items aligned with our instrumentation and overall system. This
allowed the P&ID to be designed in accordance with 100% of our customer’s desires. Refer to
the Cereal Cooker red line below.

Figure 4:​ Cereal Cooker Vessel Drawing after red line revision

4.2.4 Power and Electrical

Preliminary electrical work began with the verification of the VFLA architects
schematics for the mandatory power monitoring period required in any instance when an
industrial load is to be supplied to a pre-existing structure with an existing powered load.
Incoming three phase commercial power into the Gifford building is rated at 14.4 kVA. In
cooperation with CSU facilities the team was able to determine that the power monitoring period
had been accomplished in accordance with National Electric Code statutes section 220.87 which
dictates:

If the maximum demand data for a 1-year period is not available, the calculated load shall be permitted to be based
on the maximum demand (measure of average power demand over a 15-minute period) continuously recorded over a
minimum 30-day period using a recording ammeter or power meter connected to the highest loaded phase of the
feeder or service, based on the initial loading at the start of the recording. The recording shall reflect the maximum
demand of the feeder or service by being taken when the building or space is occupied and shall include by
measurement or calculation the larger of the heating or cooling equipment load, and other loads that may be periodic
in nature due to seasonal or similar conditions.

(2) The maximum demand at 125 percent plus the new load does not exceed the ampacity of the feeder or rating of
the service.
Mid-Project Report
Page 13/42

(3) The feeder has overcurrent protection in accordance with 240.4, and the service has overload protection in
accordance with 230.90.

The anticipated rated load of the brewery system after the monitoring period was set to be
185 kVA 480V three phase power on existing 1200 amp service. Once this was accomplished the
team was asked to determine fault current to the laboratory work space. Coming off commercial
power in series with the buildings Delta-Wye step down transformer the 200Amp J-series fuse
rated the workspace at 50kVA, which powers panels F and FA. This design ensures system
stability and longevity, protecting sensitive components and instrumentation.

4.3 Automation

In order to teach future fermentation science students, the Gifford brewery should be able
to run both manually and automatically. This is accomplished by creating automation software
that can run predefined “recipes” while at the same time accepting manual overrides from the
on-site HMI screen(s). Students will be able to gain hands-on experience with a real system by
manually controlling the brewing process with the manual functionality. This will allow them to
become more intimately familiar with the brewing process.
However, a main focus on this system is the automation of as much of the process as
possible when desired. This will allow students to write programs that will be executed
autonomously. These programs will allow the students to specify different parameters in order
to easily see how they can affect the brew. Modern breweries are moving towards more and
more automation, so this will be valuable experience in the industry.
So far, the team has been working towards automation as much as possible without a
designed system. System topology has been designed and virtual machines were also created.
The rockwell software was then installed on the virtual machines and building of the simulation
environment has commenced. All this is done alongside and under the guidance of Malisko
Engineering.

4.3.1 Integration

The automatic and manual control is implemented using Malisko Engineering custom
BatchBrew software, which itself is built off of Rockwell Automation’s PlantPAx system. The
software provides the environment in which the system will be programmed.
The system topology is shown in ​Fig 4.3. Users will be able to remotely access a process
VM where they can create the recipes that will be processed automatically. These recipes can
then be uploaded to an on-site machine with an HMI screen that will allow users to select recipe
program to run and will allow for manual control. The recipes or manual control signals will be
sent to a PLC which will in turn control all of the brewing hardware.
The virtual machines used to host this software are set up and ready for use with the
software installed and operational. The system has not yet been customized to reflect the final
design, in part because that design itself is not finished.
Mid-Project Report
Page 14/42

Figure 3​: System Topology Diagram

Chapter 5 – Future Work

5.1 Infrastructure

5.1.1 Piping and Instrumentation and Vessels

When looking towards the future of the project and the team’s projected responsibilities
with regards to infrastructure, the design portion looks to be approaching completion--what
remains is physical assembly of the equipment.
For the LSC Brewery, P&ID’s are approved and finalized; barring any unforeseen
required design change they will remain as-is. For the Gifford Brewery, process and
instrumentation diagrams (P&ID’s) will need to undergo a final set of revisions to ensure the
best possible plant configuration prior to arrival of the vessels and other equipment; specifically,
cold-side processes (read: FV’s, BBT’s, filters, etc.) will need a thorough evaluation to
determine appropriate impact on microbiological resistance and vitality and any design changes
will be finalized. Once the equipment is assembled in-house, the P&ID’s will be given a final
quality check to ensure consistency between the document and field-side establishments and any
last-minute edits will be made.
For both the LSC and Gifford Breweries, vessels still need to be received and installed.
Once constructed, the breweries will also required the installation of all motors, valves, and
instrumentation. This work will be done by Northland Process and Piping and the team will be
overseeing and observing the installation.
Mid-Project Report
Page 15/42

5.1.2 Power and Electrical

Future electrical work will largely focus on troubleshooting and systems integration with
the Batch automation software. Panel design moving forward will involve working closely with
an Encore Electric engineer to design both the control and power systems. The control panels
will be 24VDC input/output panels designed to integrate the instrumentation with the physical
control side automation equipment. Connected to the PLC the control side will receive signals
from the user interface to automate every process of the brewery and will be used for
troubleshooting procedures during the commissioning process. Expected instrumentation
controlled by the panels will be temperature transmitters, motor VFDs, automated processes
valves, and user side I/O checkouts.
The power panel design will contain three phase commercial power used to control pump
motors for transporting liquids from the brewing process. As such, housed within will be fuses
rated for equipment protection, power distribution, motor cutouts and wiring to various
equipment items. Most of these will be limited life components designed to be replaced when
power spikes and other electrical faults occur, protecting the more sensitive and expensive
equipment items they power.
Additionally component research will be needed in cooperation with the mechanical
engineers to ensure motors and pumps are powerful enough to operate the brewery without
exceeding system specifications. Other areas of power that could be of concern will be future
modifications to the system requiring additional loads; panel design will have to take these future
modifications into consideration when being drafted. The last step will involve drawing up
wiring and power schematics for the entire system. Both the power schematics and wiring
schematics will show the entirety of the system and its interconnectivity in detail. Parts lists will
need to written with parts numbers and ordering information to ensure ease of replacement as
parts wear out and break.

5.2 Automation

Automation controls and hardware will be installed as part of the installation process of
the rest of the infrastructure and machinery. There will be an extensive checkout process to
ensure all the sensors, motors, and valves function properly with the HMI screen and PLC. Each
valve will be checked after it is installed and connected to the panel, this is to verify
functionality. Motors will be tested with water and piping to drain to ensure that they are fully
operational. Additionally, the HMI screens which are needed to operate the system will be
developed.
The next step in the automation process is actually the programming of the PLC. Given
the fact that the PLC is the link between all instrumentation and automation hardware,
programming it correctly will be of the utmost importance to the team. The programmer will be
using the FDSs discussed earlier to develop the PLC. Once the PLC is programmed, the team
will conduct factory acceptance testing within the simulation environment. The goal of this
testing is to run through every single possible scenario to ensure system safety and functionality
of the system.
When FAT is complete, the PLC and the HMI screens will be transferred into and
connected with the production environment, rather than the simulation environment. Once the
Mid-Project Report
Page 16/42

production environment is all set up and IO Check out is complete, a water brew can begin with
the fully installed and functioning system.

5.2.1 Integration

Currently, the software on the virtual machines needs to be programmed to match what
will be the real setup of the Gifford brewery hardware. The framework for this has already been
laid out by Malisko Engineering and the construction of the P&ID will begin at the start of the
semester. With this full system built in simulation, brewing simulations can begin on the virtual
machines and brewing parameters and recipes can be developed. Multiple members of the team
will be responsible for this programming and switchover from the simulation environment to the
production environment.

Chapter 6 – Ethics and Marketability

The Fermentation Science Program in itself focuses heavily on marketability. This focus
is because the program is in its infancy relative to the age of the university. The program is also
incredibly unique because it is one of few schools in the nation to offer a full degree in
fermentation science that is recognized as credible to industry partners and by major industry
players. This uniqueness provides the program with an opportunity to really sell their program
as one of a kind and top notch.
That being said, the Gifford Brewery plays an integral role in this marketing because it
can be considered a major selling point of the degree program to incoming students and also to
companies looking to hire students with some kind of hands on experience. The project
customer Jeff Callaway has been working on a university affiliated branding of the Fermentation
Science Program and as a team who works for him, this senior design team is very much a part
of this branding. The system we are designing is important to future students coming to the
university for the program and also for the quality and excellence of the degree they earn when
they attend CSU for a major in fermentation science.
Marketability has also come in the form of collaboration. The most direct example of
this is working with other departments, specifically the engineering department for this project.
Other examples of outside collaboration that directly tie into the marketing of the brewery is
working with the business school by presenting in marketing class lectures and practicing
management class team dynamic studies. The team has learned that through participation similar
to the exercises that we have already completed, people want to be a part of this project because
it involves making beer and because it involves leaving a lasting impact on the university which
most students are not able to do in their short 4 years here.
The marketability does not directly tie into the ethics of the project. Ethics have been
considered in the project so far by ensuring that student learning and safety have remained at the
center of what we do. After all is said and done, it is students who will be operating this system
primarily. As a team we are responsible for designing a well thought out system that truly
exemplifies and safety as an overall relevant industry concern.
Since students tend to not have as much if any experience as a seasoned professional,
safety will be covered by a lab manager and will be a necessary part of our system. I say
necessary because like any brewing system, we are designing in safety based process methods
Mid-Project Report
Page 17/42

that will need to be explained to operate the system effectively. What this means is that unless
certain safety measures are not taken, the system will not operate. Examples of these are
inductive proximity sensors for entry prevention and also level sensors on vessels to prevent the
system from boilovers. The safety of the future users is of the utmost concern to the team and
the safety is being considered as a design requirement, which in turn is creating a safer more
effective and integrated brewing system.
Other ethical issues that the team must consider when working with a project as this one
are donor relations and industry involvement. These were mentioned because in industry, there
are many precautions taken when dealing with donations and supplies as well as free help from
any sort of business. In no way is this mean to limit or ignore certain businesses, but fairness in
competition is being considered for quotes and bids on work. Donor and supplier relations are
easy to leave in a grey area of misunderstanding however, the team is confident that the customer
is also considering these ethical donation and supplier relational issues similar to how we are.

Chapter 7 – Conclusion

The progress made this semester heavily involved the setup and design of the brewery.
The groundwork was laid for all parts. Some of these mentioned parts include IT system
topology, electrical compliance, automation process based descriptions, and flow system design.
All of these elements were deemed critical to having a system that goes above and beyond what
the customer desires. Anything, including a poorly designed system, can be automated. Thanks
to all of the collaboration the team did with experienced professionals, this will not be the case.
The team is very grateful to be working on such an impactful project that really does
make a difference in future students learning experience. Being able to leave a legacy that
boosts the image of the university and its students is something that the team is very proud of.
As a result of this project and its continuation in the years to come, the caliber of students,
fermentation and engineering will increase. This project is as “real world” as they come because
if it was not the senior design team completing it, it would be a team of engineers from design
and integration firms across the front range. The senior design team has been able to learn an
incredible amount from working with such a variety of industry professionals and outside
vendors, an opportunity which most won’t experience till they are graduated.
Mid-Project Report
Page 18/42

APPENDIX A - Abbreviations

AB Anheuser Busch
BBT Bright Beer Tank
CC Cereal Cooker
CIP Clean In Place
CLT Cold Liquor Tank
CSU Colorado State University
ECE Electrical and Computer Engineering
FAT Factory Acceptance Testing
FDS Functional Design Specifications
FST Fermentation Science and Technology
FV Fermentation Vessel
HLT Hot Liquor Tank
HMI Human-Machine Interface
KT Kettle
LSC Lory Student Center
LT Lauter Tun
MT Mash Tun
NBB New Belgium Brewery
NPP Northland Process Piping
P&ID Process and Implementation Diagram
PD Process Description
PLC Programmable Logic Controller
SCADA Supervisory Control And Data Acquisition
TT Trub Tank
VFD Variable Frequency Drive
VM Virtual Machine
WC Wort Cooler
WHT Wort Holding Tank
WP Whirlpool
Mid-Project Report
Page 19/42

APPENDIX B - Budget
For this section of the report, the budget is to be discussed. All values are estimates that
came from conversations with the customer, Jeff Callaway in the Fermentation Science Program.
The project budget is very unique especially to this senior design team. The reason being
because it is all based off pre-approved spending from the FST program combined with an
incredibly large and diverse donation base. Not only that, the project has an unusually large
budget for a senior design project. The senior design team is not directly involved in financial
approvals or decisions. The involvement of the team is to act as a pro bono engineering team
who works for free and is based at the university. Any equipment that the team designs into the
system must be specified and then sent to the customer with costs for approval. When it comes
to smaller equipment purchase, most distributors and manufacturers are selling their products at a
discount to the project for the marketing benefits. The engineering team’s approach is to not
spend more than necessary by paying full price or by purchasing overpriced equipment. The
approach is to design the system to work with state of the art vessels and functional equipment
while remaining within the customer’s cost boundaries.
Donations have come in the form of cash to spend and also through specific brewery
components and equipment. For example New Belgium Brewery and Odell’s Brewery have
each given cash donations of over $100,000 each. Another example is of Atlas Copco has
donated an oil free scroll air compressor to drive the pneumatic valve system and they are also
looking into donating other equipment. Companies such as Malisko Engineering have donated
hundreds of hours of time in creating automation platforms as well as working with Rockwell
Automation to have them donate a software package worth ~$85,000. The donor list is
incredibly long and can be seen in the acknowledgements section.
The majority of the labor costs will be incurred in vessel manufacturing, vessel
installation, and electrical contract design and installation work. All of these are done by
contractors working closely with the senior design team. The design and fabrication of the
vessels will cost approximately ~$200,000. Included in this amount is the packaging and
shipping of the vessels from the Minnesota and California based fabrication shops. Installation
of these vessels as well as the piping materials will cost FST another $85,000. This work will be
done by the piping fitting team Northland Process and Piping who is based in the Denver and
Northern Colorado Leprino food plants. There work is being done at a cost based yet discounted
rate. It is estimated that installation will take approximately 120 hours for a crew of 3-4
contractors. Electrical contract work is estimated around total around $20,000.
The total estimated cost for the project hovers around 0.8 million dollars and this is
subject to change according to the customer. The electrical engineering department also
included $200 for student based need, however, the team has not found a use for this money at
this time. Included in the table are costs covered by the customer and large donations that the
team should be aware in order to get a realistic sense of the total project cost. All costs listed
below are for the Gifford Brewery. The LSC brewery was not discussed in the budgetary talks.
Mid-Project Report
Page 20/42

Figure B.1:​ Total Project Budget Estimate


Mid-Project Report
Page 21/42

APPENDIX C - Project Plan Evolution

The scope of the CSU Brewery Design and Automation team has changed over the
course of the fall 2016 semester. As discussed earlier and as seen below in Figures C1-C2, it
became apparent that it was unlikely for the senior design team to complete the original scope of
one brewery per semester (LSC in the fall and Gifford in the Spring). Due to further
complications with the LSC, the scope of the project was shifted from the automation of the LSC
Brewery, towards the complete design and automation of the Gifford Brewery. This also led to a
team name change in late November from “CSU Brewery Automation” to “CSU Brewery
Design and Automation.”
Team updates were completed each week during Monday night team meetings and
verbally expressed to sponsors during bi-weekly meetings. Design completion was pushed back
due to the necessity for a further investigation into NPP’s vessel designs, and revisions of the
P&ID with NBB. Full project plan revisions, however, were circulated approximately once a
month, resulting in a total of four revisions for the fall-2016 semester, as can be seen below in
C1-C4.
Mid-Project Report
Page 22/42

Figure C.1:​ Project Plan 9/16/16 (Page 1/2)


Mid-Project Report
Page 23/42

Figure C.2:​ Project Plan 9/16/16 (Page 2/2)


Mid-Project Report
Page 24/42

Figure C.3:​ Project Plan 9/30/16


Mid-Project Report
Page 25/42

Figure C.4:​ Project Plan 10/26/16


Mid-Project Report
Page 26/42

Figure C.5:​ Project Plan 12/4/16


Mid-Project Report
Page 27/42

APPENDIX D - Design Revisions


Vessels

Figure D.1:​ Cold Liquor Vessel


Mid-Project Report
Page 28/42

Figure D.2:​ Hot Liquor Vessel


Mid-Project Report
Page 29/42

Figure D.3:​ Fermentation Vessel


Mid-Project Report
Page 30/42

Figure D.4:​ Wort Kettle Vessel


Mid-Project Report
Page 31/42

Figure D.5:​ Lauter Tun Vessel


Mid-Project Report
Page 32/42

Figure D.6:​ Lauter Tun Vessel


Mid-Project Report
Page 33/42

Figure D.7:​ Whirlpool Separation Vessel


Mid-Project Report
Page 34/42

Figure D7:​ Wort Holding Vessel


Mid-Project Report
Page 35/42

Figure D8:​ Wort Holding Vessel


Mid-Project Report
Page 36/42

Piping and Instrumentation Diagrams

Given that these diagrams are AutoCAD files, images of the full files will be attached. Details
about the differences in revisions will follow each revision image. Revision 1 started on a large
sticky note with post it notes connecting the “vessels”. Revision 2 was the first time the process
was represented in AutoCAD.

Figure D8:​ Revision 2


Revision 2 included putting the mental image on into AutoCad. Basic lines were connected and
basic subsystems were added and connected to the appropriate vessels.

Figure D9:​ Revision 3


Revision 3 included additions of more extensive cleaning systems and also a distribution swing
link panel to the fermentors. The structure of the chiller was also adjusted and so was the piping
from the hot liquor tank.
Mid-Project Report
Page 37/42

Figure D10:​ Revision 4


For revision 4, a cold liquor tank was added to the system after the decision to not mix building
water directly into the system. Along with the cold liquor tank, a blending scheme was
developed to accurately mix the two water sources and attain the correct temperature.

Figure D11:​ Revision 5


Revision 5 was made to change how process material flowed between the cooking vessels by
adding pump bypasses and allowing flow to occur in both directions.
Mid-Project Report
Page 38/42

Figure D12:​ Revision 6


Revision 6 consisted of adding flow control elements to the system, with a main focus on the
outlet of different vessels. The glycol system was also redone to better match a continuously
flowing system.

Figure D13:​ Revision 7


Revision 7 focused on the restructure and development of the cold side and it’s distribution to the
individual fermentors. Drains combined with block and bleed protection were added as well as
the cold liquor system blending stations were added to the outlet of the whirlpool separator.
Mid-Project Report
Page 39/42

Figure D14:​ Revision 8 and 9


For revisions 8 and 9, the clean in place system was the main focus and at this time, the team
thought that a palletized portable system would be utilized so the original swing link panel was
removed.

Figure D15:​ Revision 10 and 11


For these revisions, they were close enough together that they were combined. The glycol
system was once again overhauled. The clean in place decision came through and the customer
decided that they wanted a panel for the hot side and the cold side. The trub tank was also
connected as a temporary holding vessel
Mid-Project Report
Page 40/42

Figure D16:​ Revision 12


Revision 12 is where the team has left off and will pick back up on revision 13. The design and
flow elements are being analyzed for correct flow. There was also a strong focus again on the
clean in place system, specifically the return system for the chemicals.
Mid-Project Report
Page 41/42

ACKNOWLEDGEMENTS

Dr. Tony Maciejewski- Project Advisor


Olivera Notaros- Senior Design Professor
Jeff Callaway- Fermentation Science and Technology
Dan Malyszko- Malisko Engineering
Chris Mccombs, Jeff Biegert, Chris Keogan- New Belgium Brewing
Toby Eppard- Fermentation Science Faculty, MillerCoors
Rich Rende- Funkwerks Brewing
Northland Process and Piping
Endress and Hauser Instrumentation

You might also like