5 RH5-RH6 15.5m 6
Girder erected last night
Bearing Type Bearing Size Required Installed Balance
G1/G2/G3 300x250x53 60 60 0 I-girder erected
CONCOURSE LEVEL
LHS(West)-Nagpur Side RHS(East)-Wardha Side
Span No.of
S.No. Span No.
Length Girders B1 B3 B2 B2 B2 B2 B2 B2 B2 B2 B3 B1
1 RH1-RH2 15.5m 12 27-03-2019 22-03-2019 07-03-2019 07-03-2019 07-03-2019 07-03-2019 04-03-2019 04-03-2019 04-03-2019 09-03-2019 09-03-2019 11-03-2019
2 RH2-RH3 15.5m 12 26-03-2019 22-03-2019 16-03-2019 25-02-2019 24-02-2019 25-02-2019 03-03-2019 03-03-2019 10-03-2019 10-03-2019 11-03-2019
3 RH3-RH4 15.5m 12 29-03-2019 20-03-2019 14-03-2019 02-03-2019 02-03-2019 02-03-2019 28-02-2019 28-02-2019 28-02-2019 03-03-2019 10-03-2019 10-03-2019
4 RH4-RH5 15.5m 12 10-03-2019
5 RH5-RH6 15.5m 12