You are on page 1of 2

Bearing/Girder Status at Ujwal Nagar Station as on 23-02-2019

Span No.of LHS(West)-Nagpur side RHS(East)-Wardha Road Side


Girder type Bearing Size
Length Girders Outer Inner Inner Outer

1 UN2-UN3 19.375m G1 4 250X200X53 20-02-2019 19-02-2019 14-02-2019 16-02-2019


2 UN3-UN4 15.675m G2 4 250X200X53 22-02-2019 19-02-2019 14-02-2019 16-02-2019
UN4-UN4
3 (Link Bridge) 7.4m G3 4 250X200X53 22-02-2019 20-02-2019 16-02-2019 17-02-2019
4 UN4-UN5 15.675m G2 4 250X200X53 23-02-2019 21-02-2019 17-02-2019 17-02-2019
5 UN5-UN6 19.375m G1 4 250X200X53 23-02-2019 22-02-2019 11-02-2019 21-02-2019

Item Total Qty Bearing Type Bearing Size Total Installed Balance Stock
R-Girders 20 G1/G2/G3 250X200X53 40 40 0 0
Bearings 40

Total girders erected as on 23/02/2019 (20/20) I-girder erected

Total Bearings Installed as on 23/02/2019 (40/40) I-girder not erected