Coordination to Area Owner and Proponent for the safety work permits and other
documents needed.
Mobilization and Preparation of Tools and Equipment.
Apply Lototo Procedure.
Removal of grinding roller cover. Including rubber air seal, seal holder and seal to be
taken at spare roler assembly.
Prepare oil container, use empty drums.
Install empty oil container below the grinding roller piping, and see to it that oil spillages
will be contained on the empty drum.
Install swing out cylinder.
Swing-out grinding roller.
Removal of grinding roller assembly.
Swing-in rocker arm assembly.
Removal of rocker arm housing cover, bearing and shafting.
Install feed bushing rocker arm with lifting plate.
Set-up wire rope both ends of upper rocker arm housing, hook it to the electric hoist. This
will remain the lower bearing housing.
Open the manhole of Cylinder
Install chain block to the hydraulic cylinder, this will serve as support, to release and lift
rocker arm assembly.
Remove the hydraulic cylinder clamp yoke.
Rocker arm assembly will be refurbishing by a third-party contractor.
Secure the area.
Install the new refurbished rocker arm assembly using electric hoist.
Secure the rocker arm housing.
Swing-out rocker arm assembly.
Install Hydraulic Cylinder Clamp yoke.
Swing-in rocker arm assembly.
Install the grinding roller.
Swing-in the rocker arm assembly.
HOUSEKEEPING and Turn- over to the area owner.