You are on page 1of 271

Proposed Harare Apartments: Bills of Quantities

ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT

BILL 1

PRELIMINARIES

BUILDING AGREEMENT AND PRELIMINARIES

FIXED CHARGE ITEMS

Establishment of Facilities on the Site

Facilities for Contractor

1 Offices and Storage SUM 1

2 Scaffolding SUM 1

3 Ablution and latrine facilities SUM 1

4 Water supplies, Electric power and Communications SUM 1

5 Complying with Health and Safety Specifications SUM 1

6 Samples Preparation and Provision SUM 1

7 Removal of Site Establishment SUM 1

TIME RELATED ITEMS

Operation and Maintenance of Facilities on Site, for Duration of Construction.

Facilities for Contractor

8 Offices and Storage MONTHS

9 Communications MONTHS

10 Scaffolding MONTHS

11 Ablution and latrine facilities MONTHS

12 Water supplies and Electric power MONTHS

13 Supervision for the duration of the work MONTHS

14 Complying with Health and Safety Specifications MONTHS

15 Company and Head Office Overhead Costs for the duration of the Work MONTHS

16 Complying with the Environmental Management Programme Act and all other Statutory Environmental requirements MONTHS

17 Plant MONTHS

VALUE RELATED ITEMS

Facilities for Contractor

18 Contractual requirements SUM 1

BILL 2

EARTHWORKS

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

Nature of ground

Use "assumed to be" if no trial holes, soils investigations, etc have been carried out

Nature of ground

A soil investigation is yet to be carried out on site by an Engineer

Carting away of excavated material

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the
excavations or, alternatively, from stock piles situated on the building site

SITE CLEARANCE

Site clearance

1 Digging up and removing rubbish, debris, vegetation, hedges, shrubs and trees not exceeding 200mm girth, bush, etc m2 892 $ 1.30 $ 1,159.60

EXCAVATION, FILLING, ETC

Bulk excavation in earth

2 Bulk excavations m3 1719 $ 26.78 $ 46,029.91

Excavation in earth not exceeding 2m deep

3 For ground beams m3 47 $ 18.74 $ 880.97

4 For holes m3 124 $ 23.43 $ 2,905.32

Extra over trench and hole excavations in earth for excavation in

5 Soft rock m3 378 $ 43.45 $ 16,424.86

6 Hard rock m3 189 $ 284.62 $ 53,793.56


Extra over all excavations for carting away

7 Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor m3 1890 $ 8.05 $ 15,214.50

Risk of collapse of excavations

8 Sides of bulk excavations m2 376 $ 2.14 $ 803.91

9 Sides of trench and hole excavations not exceeding 1,5m deep m2 203 $ 2.14 $ 434.42

Keeping excavations free of water

10 Keeping excavations free of all water other than subterranean water Item 1 $ 500.00 $ 500.00

SOIL POISONING

Soil insecticide

11 Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming m2 770 $ 1.00 $ 770.00

12 To bottoms and sides of trenches etc m2 203 $ 1.00 $ 203.00

$ 139,120.04
BILL 3

LATERAL SUPPORT

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

GENERAL

Removal of lateral support

Precautions to be taken and procedures to be followed when removing lateral support shall be given only if prescribed

Insurance

1 Allow for Insurance against possible claims arising from the removal of lateral support SUM 1 $ -

Movement monitoring

2 Establish bench marks, pegs, etc for prescribed movement monitoring Item 1 $ -

3 Periodic movement surveys No 4 $ -

BILL 4

CONCRETE, FORMWORK AND REINFORCEMENT

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

Cost of tests

The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SANS 1200 G shall include the cost of
providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the Engineer. The testing shall be
undertaken by an independent firm or institution nominated by the contractor to the approval of the Engineer. (Test cubes are measured
separately)

Formwork

Description of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together
in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for
reconditioning as necessary before re-use

The vertical strutting shall be carried down to such construction as is sufficiently strong to afford the required support without damage and shall
remain in position until the newly constructed work is able to support itself.

Formworks to soffits of solid etc shall be deemed to be slabs not exceeding 250mm thick unless otherwise described

Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons.
Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in
the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"

UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

10MPa/19mm concrete

1 Surface blinding under beams and bases m3 20 $ 128.00 $ 2,560.00

REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

25MPa/19mm concrete

2 Surface bed m3 79 $ 164.00 $ 12,956.00

3 Bases m3 63 $ 164.00 $ 10,332.00

4 Ground beams m3 31 $ 164.00 $ 5,084.00

REINFORCED CONCRETE

25MPa/19mm concrete

5 Beams m3 164 $ 164.00 $ 26,896.00

6 Slab m3 67 $ 164.00 $ 10,988.00

7 Stairs and landings m3 70 $ 164.00 $ 11,480.00

8 Walls m3 122 $ 164.00 $ 20,008.00

9 Columns m3 67 $ 164.00 $ 10,988.00


TEST BLOCKS

10 Making and testing 150 x 150 x 150mm concrete strength test cube (Provisional) No 0 $ 36.00 $ -

CONCRETE SUNDRIES

Wood float finish to top of concrete

11 Ground beams, bases etc. m2 102 $ 8.40 $ 856.80

12 Steps, etc m2 294 $ 8.40 $ 2,469.60

13 To top finishes of concrete walls not exceeding 300mm high or wide m 94 $ 8.40 $ 789.60

Finishing top surfaces of concrete smooth with power float

14 Surface beds, slabs, etc to falls m2 394 $ 12.92 $ 5,090.48

SMOOTH FORMWORK (DEGREE OF ACCURACY I)

Smooth formwork to sides and soffits of slabs, beams, etc

15 Beams propped up not exceeding 3.5m high m2 1547 $ 29.15 $ 45,095.05

16 Slabs propped up not exceeding 3.5m high m2 394 $ 29.15 $ 11,485.10

17 Stairs with sloping soffits m2 168 $ 29.15 $ 4,897.20

18 Landings m2 126 $ 29.15 $ 3,672.90

19 Walls m2 1105 $ 29.15 $ 32,210.75

20 Rectangular columns with total height not exceeding 3.5m above bearing level m2 911 $ 29.15 $ 26,555.65

MOVEMENT JOINTS ETC

Expansion joints with 20mm softboard between vertical concrete and brick surfaces

21 10mm Joints not exceeding 300mm high m 200 $ 18.76 $ 3,752.00

Vertical construction joints in concrete cast in panels

22 Surface beds not exceeding 300mmm thick m 50 $ 18.76 $ 938.00

REINFORCEMENT

High tensile steel reinforcement to structural concrete work

23 Rebar in varying sizes t 70 $ 1,800.00 $ 126,000.00

Fabric reinforcement

24 Type 245 fabric reinforcement in concrete surface bed m2 394 $ 65.00 $ 25,610.00

$ 400,715.13
BILL 5

PRECAST CONCRETE

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

SLAB PAVING

Precast reinforced concrete finished smooth on exposed surfaces including bedding, jointing and pointing

1 250mm thick pre stressed hollow core slab flooring m2 2362 $ 68.75 $ 162,387.50

Cornice

2 50 mm Fibre cement coved cornice planted on including mitres m 1011 $ 3.50 $ 3,538.50

Total carried to summary $ 165,926.00

BILL 6

MASONRY

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

BRICKWORK

Sizes in descriptions

Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick

Face bricks

Bricks shall be ordered timeously to obtain uniformity in size and colour

Pointing

Descriptions of recessed pointing to fair face brickwork and face brickwork shall be deemed to include square recessed, hollow recessed,
weathered pointing, etc

SAMPLES

Samples of all masonry building units, except those for walls described as "load bearing", shall consist of a minimum of 6 units. Samples of
building units to be used in walls described as "load bearing" shall consist of 30 units from every 30 000 units delivered to site

SUPERSTRUCTURE
Brickwork of NFP bricks in class II mortar

1 Half brick walls m2 118 $ 21.50 $ 2,537.00

2 One brick walls m2 2067 $ 40.50 $ 83,713.50

BRICKWORK SUNDRIES

Brickwork reinforcement

3 75mm Wide reinforcement built in horizontally m 472 $ 0.25 $ 118.00

4 150mm Wide reinforcement built in horizontally m 8268 $ 0.25 $ 2,067.00

Prestressed fabricated lintels

5 150 x 75mm Lintels in lengths not exceeding 3m m 120 $ 20.96 $ 2,515.20

FACE BRICKWORK

Corobrick Agate Travertine FBX face or similar approved bricks pointed with recessed horizontal and vertical joints

6 Extra over brickwork for face brickwork m2 1167 $ 40.00 $ 46,680.00

Brick-on-edge header course copings, sills, etc of Corobrick Agate Travertine FBX face bricks pointed with recessed joints on all exposed faces

7 Sill set sloping and slightly projecting m 80 $ 21.50 $ 1,720.00


$ 139,350.70
BILL 7

WATERPROOFING

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

Waterproofing

Waterproofing of roofs, basements, etc shall be laid under a ten year guarantee. Waterproofing to roofs shall be laid to even falls to outlets etc
with necessary ridges, hips and valleys. Descriptions of sheet or membrane waterproofing shall be deemed to include additional labour to turn- Periodic movement surveys
ups and turn-downs

DAMP-PROOFING OF WALLS AND FLOORS

One layer of 375 micron "Polyolefin DPC" (SABS 952 type B) embossed damp proof course or other approved

1 In walls m2 263 $ 1.53 $ 402.39

One layer of 250 micron "Polyolefin waterproof sheeting" (SABS 952 type C) sealed at laps with PVC self-adhesive tape or other approved

2 Under surface bed m2 394 $ 5.00 $ 1,970.00

4mm "Derbigum SP" fully bonded waterproofing

3 On retaining wall m2 360 $ 28.50 $ 10,260.00

Derbigum SP4 waterproofing with 75mm sidelaps and 100mm end laps, sealed to primed surface to falls and cross falls by "torch-fusion".
Finish with two coats bituminous aluminium paint. Installation to manufacturers details and specifications

4 To flat roof m2 394 $ 28.50 $ 11,229.00

Tal Sureproof or other approved flexible and seamless rapid-drying two-part liquid waterproofing applied according to manufacturers
specifications

5 On shower floors and walls m2 200 $ 4.12 $ 824.00

JOINT SEALANTS ETC

Compriband bitumen impregnated foam plastic joint sealing strips

6 10 x 10mm Polyurethane sealant m 200 $ 4.50 $ 900.00

PROTECTIVE ROOFING PAINT

Two coats bituminous aluminium paint

7 On waterproofing to roof m2 394 $ 8.60 $ 3,388.40

$ 28,973.79
BILL 8

CARPENTRY AND JOINERY

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

Particle board:

Particle board shall comply with the following specifications: a) SANS 1300 Particle board: exterior and flooring type b) SANS 1301 Particle board:
interior type

Joinery:

Descriptions of frames shall be deemed to include frames, transomes, mullions, rails, etc

Descriptions of hardwood joinery shall be deemed to include pelleting of bolt holes

Fixing

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or shot pins to brickwork or concrete

Decorative laminate finish:

Laminate finish shall be glued under pressure. Edge strips shall be butt jointed at junctions with adjacent similar finish
DOORS ETC

44mm thick "Swartland" or similar approved timber hollow core door

1 Door 813 x 2 125mm high No 80 $ 23.48 $ 1,878.40

44mm thick "Swartland" or similar approved timber solid core door

2 Door 813 x 2 125mm high No 40 $ 234.63 $ 9,385.20

3 Two leaf door size 1 626 x 2 125mm high No 2 $ 320.28 $ 640.56

Purpose made timber doors to ducts

4 Door 510 x 2 125mm high No 40 $ 60.00 $ 2,400.00

FITTINGS

General

The following cupboard fittings have been measured as complete units i.e. the components of the units have not been separately measured. The
descriptions, therefore, of such units shall be deemed to include all components, assembling, housing, notching, glueing, blocking, planting on
and screwing with countersunk screws, edge strips, decorative plastic finish, glass, ironmongery, metalwork, paint or varnish finishes, etc

Kitchen cupboards etc

5 2 400mm kitchen one box complete with Candy hood, Oven, Ceramic hob, Sink, Tap and Worktop, Doors, Cupboard, Hinges and Handles No 40

Bedroom cupboards etc

6 2 500 x 620mm Allure white bedroom wardrobe with sliding doors 1/2 mirrors No 40

Bathroom vanity etc

7 600mm Essential gloss white single basin cabinet complete with two door vanity and led mirror No 40

SUNDRY JOINERY

Wrought meranti skirting

8 75 x 19mm skirting complete with 19mm quadrant bead nailed m 1011

$ 14,304.16
BILL 9

IRONMONGERY

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

Finishes to ironmongery

Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following list: BS Satin bronze lacquered CH Chromium
plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodised silver AB Anodised bronze AG Anodised gold ABL Anodised
black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded

LOCKS

Note: The following locks are in one set with a master key:

COMPONENTS

'Assa Abloy' or similar approved locks

1 5 lever mortice lock No 80 $ 35.64 $ 2,851.20

2 3 lever mortice lock No 40 $ 18.15 $ 726.00

PELMETS AND CURTAIN TRACKS

Curtain rails

3 Double curtain track for face fixing with 100mm projection including 14 rollers per metre, brackets, stopped ends, etc m 160 $ 9.28 $ 1,484.80

BATHROOM FITTINGS

Towel rail

4 30mm diameter chrome plated towel rail 600mm long complete No 40 $ 4.75 $ 190.00

Franke or similar and equally approved

5 Toilet paper holder No 40 $ 30.61 $ 1,224.40

SUNDRIES

Union or equally approved door stopper

6 Door stopper No 120 $ 4.58 $ 549.60


$ 7,026.00
BILL 10

METALWORK

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

Descriptions

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork
or concrete

Metalwork described as "holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

STEEL HANDRAILS, BALUSTRADES, ETC.

Handrail complete with 50mm diameter stainless top rail and seven 16mm diameter mild steel intermediate rails welded to 50mm diameter
posts at maximum 1 000mm centres fixed to top of concrete

1 Horizontal handrail to balustrade m 240 $ 3.24 $ 777.60

2 Raking handrail on top of stairs m 56 $ 3.24 $ 181.44

PRESSED STEEL DOOR FRAMES

1,2mm Rebated frames suitable for half brick walls

3 Frame suitable for door size 813 x 2125mm high No 80 $ 43.37 $ 3,469.60

1,2mm Double rebated frames suitable for one brick walls

4 Frame suitable for door size 813 x 2 125mm high No 40 $ 66.04 $ 2,641.60

5 Frame for double door 1 626 x 2125mm high No 2 $ 98.07 $ 196.14

ALUMINIUM WINDOWS

Note: All windows to be matt charcoal powder coated aluminium frame windows complete with standard hinges and window furniture as per
manufacturer. All glazing to comply with SANS 10400 Part N. Provide monolithic annealed glass at all panes higher than 500mm above finished
floor level. Provide laminated annealed safety glass at all doors and panes lower than 500mm above finished door level.

Powder coated hollow extruded aluminium windows complete including 4mm thick monolithick annealed glass as per window schedule.
Colour - Matt Charcoal (Code -3055)

6 Window type W01, 500 x 1 300mm high including all necessary ironmongery as per Architect's specification No 40 $ 175.00 $ 7,000.00

7 Window type W02, 1 500 x 1 300mm high including all necessary ironmongery as per Architect's specification No 40 $ 175.00 $ 7,000.00

ALUMINIUM DOORS AND SHOPFRONTS

Powder coated hollow extruded aluminium shopfronts complete including 6mm thick safety shield sunergy clear glass with U-value of 3.4 &
SHGC 0.60 as per window schedule. Colour - Matt Charcoal (Code -3055)

Double door size 1 626 x 2 125mm high including 2 No. "Union" door closer code "737SC", 1 No. "Union" narrow stile four lever dead lock code
8 "21313-40SS", 2 No. "Union" pull handle code "Dove AL5512-300BBAS", 2 No. "Union" narrow stile escutcheon code "AL582RT-24AS" and 2 No. No 2 $ 546.68 $ 1,093.36
flush bolts by manufacturer all as detailed on the architectural drawings attached to these bills of quantities

9 Shop front with sliding door, 4 000 x 3 000mm high overall size, complete with all necessary ironmongery as per Architect's specification No 40 $ 2,100.00 $ 84,000.00

10 Curtain wall system 38 152 x 15 000mm high overall size as per Architect's specification m2 572 $ 534.75 $ 305,877.00

WELDED SCREENS, GATES, ETC

Maxidor or similar and equally approved mild steel angle framed and welded burglar guards of 12mm solid rods at 125mm centres with paint
finish fixed to brick walls:

11 Burglar guard to suit door, size 813 x 2125mm High No 40 $ 107.80 $ 4,312.00

Mild steel angle framed and welded burglar guards of 12mm solid rods at 125mm centres with powder coated finish fixed to brick walls:
Colour: Matt Chorcoal

12 Burglar guard to suit window, size 500 x 1 300mm High No 40 $ 107.80 $ 4,312.00

13 Burglar guard to suit window, size 1 500 x 1 300mm High No 40 $ 107.80 $ 4,312.00

$ 425,172.74
BILL 11

PLASTERING

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

INTERNAL PLASTER

Cement plaster on brickwork

1 On walls m2 3397 $ 7.50 $ 25,477.50

EXTERNAL PLASTER

Cement plaster on brickwork

2 On walls m2 550 $ 7.50 $ 4,125.00


$ 29,602.50
BILL 12

TILING

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"


Descriptions

Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be
deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

WALL TILING

600mm x 300mm Ital tile glazed ceramic tiles or similar and equally approved laid on plastered walls to approved pattern using approved
adhesive and grout in strict accordance to manufacturers recommendations.

1 On walls m2 1078 $ 35.67 $ 38,452.26

2 On walls in splashbacks m2 20 $ 45.65 $ 913.00

SUNDRIES TO WALL TILING

Vaal similar or equally approved

3 Single soap dish No 40 $ 20.32 $ 812.80

FLOOR TILING

600mm x 600mm Ital tile hard body ceramic tiles or similar and equally approved laid to approved pattern using approved adhesive and grout
in strict accordance to manufacturers recommendations

4 On floors m2 1968 $ 35.67 $ 70,198.56

$ 110,376.62
BILL 13

PLUMBING AND DRAINAGE

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

SANITARY FITTINGS

Vaal or similar approved

1 Vitreous china close coupled 90 degree outlet rim wash down toilet pan and matching 7 litre push button to dual flush cistern complete with lid No 40 $ 115.62 $ 4,624.80
and fitments, supplied with seat

Vaal or similar approved

2 1 200 x 1 200mm Shower door complete with tray No 40 $ 84.88 $ 3,395.20

TAPS, VALVES, ETC

Cobra Watertech or siilar approved

3 Wash hand basin mixer tap No 40 $ 84.78 $ 3,391.20

4 Shower complete with mixer No 40 $ 140.85 $ 5,634.00

Italtile or similar and equally approved

5 Angle Valve No 200 $ 5.80 $ 1,160.00

GEYSERS, INCLUDING INSTALLATION COMPLETE

150 Litre 'Kwikot Megaflow' high pressure vertically wall mounted water heater with 2 Kw 220 V heating element, drain cock, air relief valve and
6 brackets, bolts, etc No 40 $ 17,970.00 $ 718,800.00

$ 737,005.20
BILL 14

PAINTWORK

PREAMBLES: For Preambles, refer to "Model Preambles for Trades"

PAINTWORK TO NEW WORK

ON FLOATED PLASTER

One coat primer undercoat and two coats PEM 1000 paint for interiors

1 On walls m2 4398 $ 8.50 $ 37,383.00

ON SMOOTH CONCRETE

One coat primer and two coats interior quality paint

2 On soffits and beams m2 2756 $ 8.50 $ 23,426.00

ON METAL

Prepare new frame and apply primer for mild steel, u/c for all surfaces and gloss enamel to cover surface sufficiently all in accordance to
manufacturer specifications. Colour to Architect's approval

3 On internal door frames m2 65 $ 8.50 $ 552.50

4 On external door frames m2 50 $ 8.50 $ 425.00

ON WOOD

Sanded and sealed with Wooddoc 30 or other approved as per Architect's specification

5 On doors m2 152 $ 9.50 $ 1,444.00

One coat Plascon Professional wood primer with two coats of Plascon Velvaglo
6 On internal doors m2 276 $ 9.40 $ 2,594.40

$ 65,824.90
BILL 15

EXTERNAL WORKS

PAVING

EXCAVATION, FILLING, ETC

Open face excavation in earth

1 Open face excavation under paving m3 138 $ 18.74 $ 2,586.12

Extra over all excavations for carting away

2 Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor m3 138 $ 25.00 $ 3,450.00

Earth filling supplied by the contractor under pavings etc

3 150mm Subgrade G9 material compacted to 93% MOD. AASTHO density m3 46 $ 25.00 $ 1,150.00

4 150mm Subgrade G7 material compacted to 93% MOD. AASTHO density m3 46 $ 25.00 $ 1,150.00

5 150mm Sub base imported G5 material stabilized with 3% OPC (including stabilisation) and compacted to 95% MOD. AASHTO density m3 46 $ 25.00 $ 1,150.00

Compaction of surfaces

6 Compaction of ground surface under pavings etc including scarifying for a depth of 150mm, breaking down oversize material, adding suitable m2 306 $ 1.50 $ 459.00
material where necessary and compacting to 90% Mod AASHTO density

Soil insecticide

7 Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming m2 306 $ 0.50 $ 153.00

PAVING

80mm Interlocking precast concrete paving blocks laid with butt joints on 20mm thick river sand bed with sand swept into joints including
preparation of ground or filling

8 Paving m2 306 $ 15.00 $ 4,590.00

KERBS

Precast concrete kerbs

Kerb (SABS 927 fig 7) 180 x 280mm high with 150 x 150 x 300mm unreinforced concrete haunching at back of each joint including excavation,
9 m 127 $ 4.85 $ 615.95
backfilling, etc

BOUNDARY FENCING

STEEL PALISADE FENCE

NOTE: All steel palisade to be finished with one coat zinc chromate primer and two coats alkyd enamel paint on steel

10 Steel palisade fence overall 2 400mm high above ground level as per Architects specification, complete including foundations, ground beam, etc. m 125 $ 40.35 $ 5,043.75
as per detail

Gates

NOTE: All gates to be finished with one coat zinc chromate primer and two coats alkyd enamel paint on steel

11 Single pedestrian gate overall 900 x 2 400mm high including foundations etc complete as per detail No 1 $ 460.00 $ 460.00

12 Double sliding gate overall 6 000 x 2400mm high including motor, foundations, sliding track complete as per detail No 1 $ 884.62 $ 884.62
$ 21,692.44
BILL NO. 16

PROVISIONAL SUMS

SUPPLEMENTARY PREAMBLES

Provisional sums are for materials and equipment supplied and installed complete by Specialist firms. Provisional sums are NET. Under no
circumstances may any Provisional Sum be extended at an amount other than the amount given in the Bill. Provisional sums will be deducted in
whole or in part if not required without any compensation for loss or profit on the said allowances.

Reimbursement

Unless otherwise stated, the Profit and Attendance will be calculated on the final agreed installation value

Attendance on subcontractors

Attendance by the Contractor for provisional sum for Subcontractors' work, shall be deemed to cover all the Contractor's costs incurred in
providing free of charge to the nominated subcontractors, the following: 1. Services such as offices, water, electricity, latrines, laydown areas,
transport, security, scaffolding, hoisting, etc. as necessary and agreed between the Subcontractor and Contractor to complete the works. 2.
Making good in all trades and cleaning down and removal of rubbish on completion. No additional claims whatsoever in this regard will be
entertained.

Builder's work in connection with specialist services

Builder's work in connection with specialist services is given elsewhere in these bills of quantities.

ELECTRICAL INSTALLATION

1 Provide the sum of US $ for the Supply and Installation of a complete Electrical Installation Item

2 Profit and Attendance %

LIFT INSTALLATION

3 Provide the sum of US $ for the Supply and Installation of a Lift Item
4 Profit and Attendance %

LP GAS TANK AND RETICULATION INSTALLATION

5 Provide the sum of US $ for the Supply and Installation of a complete LP Gas System Item

6 Profit and Attendance %

FIRE PROTECTION INSTALLATION

7 Provide the sum of US $ for the Supply and Installation of a complete Fire Protection Installation Item

8 Profit and Attendance %

PLUMBING PIPEWORK

9 Provide the sum of US $ 400 000.00 for the Supply and Installation of all Plumbing Pipework Item

DSTV INSTALLATION

10 Provide the sum of US $ for a Centralised DStv Installation Item

11 Profit and Attendance %

LANDSCAPING

12 Provide the sum of US $ for Landscaping Item

13 Profit and Attendance %

SUMMARY

1 Preliminaries $ 228,509.02

2 Earthworks $ 139,120.04

3 Lateral Support $ -

4 Concrete, Formwork and Reinforcement $ 400,715.13

5 Precast Concrete $ 165,926.00

6 Masonry $ 139,350.70

7 Waterproofing $ 28,973.79

8 Carpentry and Joinery $ 14,304.16

9 Ironmongery $ 7,026.00

10 Metalwork $ 425,172.74

11 Plastering $ 29,602.50

12 Tiling $ 110,376.62

13 Plumbing and Drainage $ 737,005.20

14 Paintwork $ 65,824.90

15 External Works $ 21,692.44

16 Provisional Sums $ -

Sub-total

Add: Value Added Tax @ 15% $ 364,471.89

TOTAL $ 2,878,071.13
SUMMARY OF RATES AS AT

NB:THE RATES BELOW ARE EXCLUSIVE OF THE CONTRACTOR'S PROFIT AND ATTENDANCE

ITEM DESCRIPTION UNIT RATES(US$)


1 Earthwork Rates

1.01 Clear site of rubbish, grass, trees etc sq.m 1.21

1.02 Fell, stump & remove main roots of trees exceeding 0.5m girth no. 281.16

1.03 Excavate borrow pit material and stockpile on site cu.m 4.93

1.04 Excavate in all material for trenches 950x1000mm deep compact and
spread spoil on site cu.m 35.38

1.05 Excavate in pickable mat.to formation level and pile on site cu.m 4.93

1.06 Extra within formation width and dispose and compact sq.m 39.46

1.07 Extra within formation width and dispose sq.m 6.72

1.08 Extra over excavation in pickable material for excava in hard material. cu.m 28.12

1.09 Excavate over site to remove vegetable soil and pile cu.m 2.19

1.10 Excavate in pickable mat.for Vee drains incl trimming and disposal. cu.m 42.85

1.11 Extra over for hauling exceeding 1km. cu.m 4.46

1.12 Scarify ground surfaces and compact to 93% HCE 100mm depth cu.m 3.30

1.13 Compact existing grnd to 93% Mod.AASHTO sq.m 4.96

1.14 Allow for rehabilitation of borrow pit area, access road and car park with sq.m 0.39
topsoil from site

1.15 Redig from spoil heap, return, fill and compact excavated material. cu.m 36.10

1.16 Approved imported inert granular material spread, level and compact as

10
described cu.m 79.89

11
ITEM DESCRIPTION UNIT RATES(US$)

1.17 Approved imported inert granular material around & under drain pipes cu.m 48.34

1.18 Supply crusher run, spread and compact 150 thickness cu.m 84.30

1.19 Supply and lay Municipal type kerbs incl necessary excav, bedding etc m 25.27

1.20 Supply and lay G type kerbs incl necessary excav, bedding etc m 44.62

1.21 Supply and lay Taphalt edging kerbs incl necessary excav, bedding etc m 22.27

1.22 Supply and lay Hollow Mountable type kerbs incl necessary excav,
bedding etc m 31.40

1.23 Supply and lay Heavy duty H3 type kerbs incl necessary excav,
bedding etc m 34.93

1.24 Supply and lay 305mm stormwater pipes incl backfill and ram m 118.54

1.25 Supply and lay 380mm stormwater pipes incl backfill and ram m 121.34

1.26 Supply and lay 450mm stormwater pipes incl backfill and ram m 133.55

1.27 Supply and lay 610mm stormwater pipes incl backfill and ram m 159.36

1.28 Supply and lay 700mm stormwater pipes incl backfill and ram m 164.68

1.29 Supply and lay 915mm stormwater pipes incl backfill and ram m 177.16

1.30 Stone pitching sq.m 51.50

1.31 Supply and lay 1200mm bore class "x"concrete stormwater pipes
incl backfill and ram m 251.61

1.32 Supply,lay. Bed and joint 150mm bore porous concrete pipe m 38.42

1.33 One brick wall in common bricks in cement mortar. sq.m 46.63

1.34 460x460mm piers in common bricks in cement mortar. cu.m 48.57

1.35 One brick wall in light brindles bricks in cement mortar. sq.m 29.51

12
ITEM DESCRIPTION UNIT RATES(US$)
1.36 Supply and fix PCC copings 50x300x600mm to walls. m 13.25

1.37 Supply and fix PCC copings 50x230x600mm square to piers. m 13.25

1.38 Haul, dump, spread and compact approved material around kerbs cu.m 41.59

2 Foundation Rates

2.01 Site clearance sq.m 1.00

2.02 Excavate to remove topsoil - av dpth 150mm sq.m 2.53

2.03 Excavate in pickable mat to reduce levels n.e 2m deep cu.m 12.78

2.04 Excavate in pickable for ground beams n.e 2 m deep. cu.m 18.74

2.05 Excavate in pickable for ground beams ex 2 but n.e. 4m deep. cu.m 26.78

2.06 Excavate in pickable for pile caps n.e 2 metres deep. cu.m 23.43

2.07 Extra over for excavation in hard pickable material cu.m 43.45

2.08 Extra over for excavation in hard rock cu.m 284.62

2.09 Extra over all excavations for excavating in brick walls cu.m 92.50

2.10 Extra over all excavations for excavating in unreinforced concrete cu.m 138.42

2.11 Extra over all excavations for excavating in reinforced concrete cu.m 213.96

2.12 Allow for risk of collapse to sides of excavation cu.m 2.14

2.13 Re-dig from spoil heap &cart away surplus excavated mat to a
dump site -maximum distance n.e 50km cu.m 8.05

2.14 Re-dig from spoil heap and back fill and compact around fnds cu.m
8.51
2.15 Re-dig from spoil heap and backfill to make up levels under floors
93% HCE density cu.m 7.07

13
2.16 Selected stable granular filling of triaxial class 3.9 under floors
compacted to 91% HCE density cu.m 27.02

ITEM DESCRIPTION UNIT RATES(US$)

2.17 Selected stable granular filling of triaxial class 3.6 under floors
compacted to 93% HCE density cu.m 27.02

2.18 Scarify surface of insitu sud soil for a depth of 150mm and
mechanically compact to 89% sq.m 1.77

2.19 Scarify surface of insitu sud soil for a depth of 150mm and
mechanically compact to 95% sq.m 1.23

2.20 Strike off and cure top surface of concrete sq.m 1.28

2.21 One layer 250 micron "Tarcon" polythene DPM sq.m 8.35

2.22 50mm sand blinding under concrete surface beds sq.m 2.04

2.23 Foundation concrete cu.m 174.05

3 Brickwork in foundations
3.01 Brickwork - 230mm (industrials) sq.m 64.53

3.02 Brickwork - 115mm (industrials) sq.m 33.09

3.03 One brick by two bricks pier attached m. 26.22

3.04 One brick wall curved on plan to quick sweep in industrial brickwork sq.m 66.92

3.05 Rough splay cutting and waste to brickwork m. 10.17

3.06 230mm blockwork in concrete hollow blocks (9 inch) sq.m 54.78

3.07 230mm blockwork in concrete hollow blocks (6 inch) sq.m 39.45

3.08 230mm blockwork in concrete hollow blocks (41/2 inch) sq.m 40.04

3.09 105mm /150mm Brickforce to suit 230mm brick wall m. 0.34

14
3.10 105mm /150mm Brickforce to suit 230mm brick wall to quick sweep m. 0.39

3.11 10mm Kaylite joint filler material in expansion joints as described sq.m 9.79

3.12 Two layers of Rubber roid bitumen DPC vertically btwn walls sq.m 4.90

ITEM DESCRIPTION UNIT RATES(US$)


3.13 Galvanised hoop iron ties 25mm wide 700mm long as described no. 1.88

3.14 Leave or form mortice in concrete for box of floor spring & grout no. 14.26

Superstructure

3.15 Brickwork - 230mm(commons) sq.m 52.66

3.16 Brickwork- 115mm (commons) sq.m 27.98

3.17 Half brick wall curved on plan in commom brickwork sq.m 30.22

3.18 One & half brick wall in common brickwork sq.m 67.41

3.19 Half brick wall in Dark Rustic face brickwork sq.m 35.78

3.20 Half brick wall curved on plan in Dark Rustic face brickwork sq.m 38.92

3.21 One brick wall in Dark Rustic face brickwork sq.m 67.83

3.22 One & half brick wall in Dark Rustic face brickwork sq.m 84.00

3.23 230mm blockwork in concrete hollow blocks (9 inch) sq.m 50.32

3.24 230mm blockwork in concrete hollow blocks (6 inch) sq.m 41.67

3.25 230mm blockwork in concrete hollow blocks (41/2 inch) sq.m 44.68

3.26 Rough raking cutting on brickwork m. 37.85

3.27 25mm Cement grout under base plate sq.m 12.64

3.28 Rough cutting squint and bird mouth angle sq.m 4.37

3.29 Set up in position cross brase & bldng in steel window frame/ door

15
frame n.e 5m2. no. 13.95

3.30 Cut 25x25mm horizontal groove in b/work for turn up on asphalt m 3.55

3.31 Set up in position cross brase & bldng in steel window/ door frame
exc 25m2 & n.e 30m2. no. 18.18

3.32 One layer of three ply DPC as described sq.m 3.09


ITEM DESCRIPTION UNIT RATES(US$)
4 Concrete & Rebar
4.01 Concrete grade 40 Mpa cu.m 187.18

4.02 Concrete grade 30 Mpa cu.m 174.05

4.03 Concrete grade 25 Mpa cu.m 163.91

4.04 Concrete grade 20 Mpa cu.m 151.90

4.05 Concrete grade 15 Mpa cu.m 138.68

4.06 Concrete grade 10 Mpa (Mass) cu.m 127.90

4.07 Concrete grade 15 Mpa (blinding) sq.m 138.05

4.08 Concrete grade 10 Mpa (blinding) sq.m 127.27

4.09 Mild steel rod exceeding 12mm diameter & n.e 30mm diameter kg 1.12

4.10 Mild steel rods exceeding 8mm and not exc 12mm diameter kg 1.12

4.11 Mild steel rods not exceeding 8mm diameter kg 1.12

4.12 High yeild deformed bars exceeding 12mm n.e. 30mm diameter kg 1.12

4.13 High yeild deformed bars exceeding 8mm n.e. 12mm diameter kg 1.12

4.14 High yeild deformed bars exceeding 30mm diameter kg 1.12

4.15 Fabric reinforcement; Ref. S193 sq.m 5.23

4.16 Fabric reinforcement; Ref. S245 sq.m 6.47

16
4.17 Fabric reinforcement; Ref. S617 sq.m 15.27

4.18 Precast concrete lintel to opening size 110 x 150mm


(Double dephth prestressed) m. 18.63

4.19 Precast concrete lintel to opening size 110 x 150mm


(Double dephth steel reinforced) m. 40.76

4.20 Precast concrete lintel to opening size 150 x 2490 x 230 mm high m. 57.77

17
ITEM DESCRIPTION UNIT RATES(US$)

5 Joinery & Iron Mongery

* 44mm Semi-solid internal quality flush doors to receive paint

5.01 Size 762 x 2030 mm no. 122.68

5.02 Size 813x 2032 mm no. 160.24

5.03 Size 900 x 2100mm no. 122.68

5.04 Size 1219 x 2125 mm no. 159.70

5.05 Size 1600x 2032mm no. 298.70

* 44mm Semi-solid core flush external quality doors to receive paint

5.06 Size 762 x 2030 mm no. 189.18

5.07 Size 813x 1850 mm no. 153.68

5.08 Size 813x 2030 mm no. 206.18

5.09 Size 813x 2032 mm no. 206.18

5.10 Size 900 x2100 mm no. 227.43

5.11 Size 1600 x2032 mm no. 370.70

* 44mm internal quality built-in cupboard doors to receive paint

5.12 Size 1675 x 495mm no. 80.70

5.13 Size 1675 x 2030mm no. 165.70

5.14 Union CZ 8094 indicactor bolt no. 23.12

5.15 Union No 5538-4-150 Aluminium pull handle no. 17.01

5.16 Union two lever lockset no. 23.53

18
19
ITEM DESCRIPTION UNIT RATES (US$)
5.17 Union three lever lockset no. 33.03

5.18 Flush Bolts no. 34.72

5.19 Union aluminium pull handle no. 18.08

5.20 Union aluminium Dove pull handle (back to back) no. 30.86

5.21 Union nº 5562 aluminium escutcheon no. 15.61

5.22 Over head door closer union 7772 no. 109.37

5.23 Over head door closer union 7836 no. 201.58

5.24 Union Nº 8074 silver anodised rubber buffer hat & coat hook no. 13.89

5.25 Union 8005SS hat & coat hook no. 16.39

5.26 Union 99200CH Door Viewer no. 23.61

5.27 Aluminium kick plate (size 150 x 880mm) no. 36.94

5.28 Aluminium push plates no. 16.14

5.29 RFID Generic Key Cards no. 7.93

5.30 Rubber door stops no. 10.46

5.31 Union No AL8021 75X150MM Male / Female symbol screwed to doors no. 22.67

5.32 Union international disabled sign no. 22.67

5.33 Union SS50066E -06SSE14 Paraplegic Pictogram no. 22.67

5.34 Union SS50066E -06SSE15 Fire Escape Pictogram no. 22.67

5.35 Union SS50066E Stairs Pictogram no. 22.67

5.36 Union SS50066E -06SSE Room Numbers engraving no. 19.94

5.37 Union SS50066E -06SSE House Keeping engraving no. 67.09

20
5.38 Union SS50066E -06SSE Conference Room engraving no. 80.11
ITEM DESCRIPTION UNIT RATES (US$)

5.39 Union SS50066E -06SSE Cashier engraving no. 42.73

5.40 Union SS50066E -06SSE CCTV Room engraving no. 46.19

5.41 Union SS5506E -06SSE08 Directional Pictogram no. 22.67

5.42 Steel hinges no. 15.44

6 Plastering and wall linings


6.01 One coat wood float plaster to walls externally sq.m 8.40

6.02 One coat wood float plaster to walls in n. w. sq.m 12.92

6.03 One coat wood float plaster on concrete soffits sq.m 10.41

6.04 One coat wood float plaster on concrete walls sq.m 10.93

6.05 One coat wood float plaster on soffits of beams in narrow width sq.m 14.67

6.06 One coat cement plaster with steel float and set in Rhinoset internal sq.m 11.61

6.07 Ditto in narrow width sq.m 19.29

6.08 "FIX ONLY" 150x150x6mm glazed ceramic wall tiles as described sq.m 41.15

6.09 Ditto in narrow width sq.m 65.69

6.10 Extra for exposed edges m. 4.22

6.11 Cut and fit tiling around small pipes m. 6.37

6.12 Cut and fit tiling around large pipes m. 9.08

6.13 "FIX ONLY" Ceramic skirting as described sq.m 2.40

7 Screed & Floor Covering Rates

7.01 60mm screed grading to falls on top of concrete slab sq.m 15.13

21
7.02 Dress grading into 100mm diameter full bore sq.m 22.49

7.03 35mm screed laid on concrete to receive tiles sq.m 9.67


ITEM DESCRIPTION UNIT RATES (US$)

7.04 40mm granolithic paving steel trowelled to concrete floors sq.m 10.34

7.05 75mm High skirting with cove at junction as described. sq.m 3.08

7.06 Mosaic tiles on screeds as described sq.m 91.71

7.08 Mosaic tiles on screeds as described in n.w sq.m 112.80

7.09 Fair pointed exposed edges sq.m 4.22

7.10 Cut & Fit tiles around shower outlet m. 9.04

7.11 Cut & Fit tiles around shower trap m. 6.44

7.12 300X300X6mm Ceramic floor tiles on floors as described. sq.m 35.75

7.13 300X300X6mm Ceramic floor tiles on floors as described in n.w. sq.m 56.66

7.14 Raking & cutting on tiles m. 4.22

7.15 Circular cutting on tiles m. 6.33

7.16 Skirting 150mm high as described. m. 8.53

7.18 500 x 500mm Nexbac Berber Point 650 Carpet tiles sq.m 45.42

7.19 Rubber Floor Tiles 500x500 incl. 1:4 screed as described. sq.m 66.09

7.20 Ditto 75mm Skirting m. 7.22

7.21 38mm screed to floors to receive carpet tiles. sq.m 10.04

7.22 40mm granolithic paving steel trowelled to concrete floors. sq.m 12.13

7.23 300x300x8mm Non slip Ceramic floor tiles finished with two coats sq.m 45.68
of wax polish

22
7.24 150x150x8mm Terra-coat red quary tiles on floors sq.m 47.13

7.25 Raking cutting and waste on Terra-coat red quary tiles m. 7.28

7.26 6x40mm Aluminium dividing strip m. 3.58


ITEM DESCRIPTION UNIT RATES(US$)
7.27 40mm granolithic paving steel trowelled laid on cills. sq.m 14.04

7.28 100mm High skirting with cove at junction as described. m. 7.28

7.29 300X300X9mm Non-Slip Ceramic floor tiles on floors as described. sq.m 38.29

7.30 Ditto 100mm high skirting m. 2.41

7.31 600 x 600mm - Metallic Porcelain Floor Tiles sq.m 73.25

7.32 230x115x30mm Mult coloured quary tiles as described sq.m 47.25

7.33 50mm screed to floors to receive carpet. sq.m 11.54

7.34 38mm screed to concrete floors. sq.m 10.04

7.35 40mm screed to concrete floors to receive ceramic tiles. sq.m 10.29

7.36 40mm screed to concrete floors to receive grano. sq.m 10.86

7.37 50mm granolithic paving steel trowelled to floors sq.m 18.93

7.38 20x75mm High skirting with cove at junction as described. sq.m 3.73

7.39 400 x 400mm Ceramic floor Tiles sq.m 36.83

7.40 40mm granolithic paving steel trowelled to floors sq.m 16.20

7.41 40mm granolithic paving steel trowelled to floors laid to falls sq.m 17.68
and across falls

7.42 20mm cement grout under mild steel base plate , bearing sq.m 6.14
plates etc

8 Painting Rates

23
8.01 Clean down and apply 3 coats internal quality PVA paint exterior sq.m 9.61
quality on; Plasterered walls [wood float]

8.02 Clean down and apply one undercoat and two finishing coats sq.m 9.33
internal quality PVA emulsion paint on; Plastered steel trowel finish

8.03 Ditto to raking soffits sq.m 9.33


ITEM DESCRIPTION UNIT RATES (US$)
8.04 Ditto to sides of concrete beams sq.m 9.33

8.05 Ditto to soffits woodfloat finish sq.m 9.61

8.06 Clean down touch up manufacturer's priming, apply one undercoat


and two finishing coats enamel paint on; Steel door frames sq.m 6.37

8.07 Ditto to general surfaces of doors sq.m 6.37

8.08 Ditto to steel windows [both sides measured flat] sq.m 6.37

8.09 Ditto to steel balustrading [both sides measured flat] sq.m 6.32

8.10 Prepare and apply one coat metal primer ,one undercoat and
finishing coats enamel paint on; Small copper pipes sq.m 6.32

8.11 Ditto to large pipe sq.m 6.32

8.12 Prepare , apply self etching primer ,one undercoat and two finishing
coats enamel paint on; Flashings sq.m 6.32

8.13 Ditto on small mild steel pipes sq.m 6.32

8.14 Ditto on large mild steel pipes sq.m 6.32

8.15 Prepare ,seal and apply one undercoat and two finishing coats enamel sq.m 6.32
paint on;Pvc small pipes

8.16 Ditto on pvc large pipes sq.m 6.32

8.17 Prepare ,knot ,prime,stop and apply one undercoat and two finishing
coats enamel paint on;General surfaces of doors sq.m 6.32

24
8.18 Ditto on general surfaces in narrow widths sq.m 6.32

8.19 Prepare ,stain and apply two coats polyurathane varnish on


General surfaces of doors sq.m 6.34

8.20 Clean down,remove loose and flaking paint ,stop and apply three coats
PVA emulsion paint exterior quality on previously painted surfaces on;
steel trowel plastered walls sq.m 5.07

8.21 Ditto to steel plastered soffits sq.m 5.07


ITEM DESCRIPTION UNIT RATES (US$)
8.22 Clean down,remove loose and flaking paint ,stop and apply one
undercoat and two finishing coats coats enamel paint on previously sq.m 5.07
steel trowel plastered walls

8.23 Clean down,remove loose and flaking paint ,stop and apply one
undercoat and two finishing coats coats enamel paint on previously
painted surfaces to pressed steel door frames sq.m 5.07

8.24 Ditto , to steel windows(both sides measured) sq.m 5.07

8.25 Clean down ,prepare , apply one coat sanding sealer and two coats
clear polyurethene varnish on previously varnished surfaces sq.m 6.34

Clean down fine wood float plasterd walls & apply one coat primer,trowel 1mm
8.26 Marmosaic & apply one coat of Marmoran
universal glaze sq.m #REF!

9 Demolition Rates

9.01 Excavate in earth n.e 2 m deep and remove reinforced concrete base
size 2000 x2000 x 400 mm cu.m 122.00

9.02 Excavate in earth n.e 2 m deep and remove reinforced concrete base
size 3500 x3500 x 400 mm cu.m 373.63

9.03 Extra over all excavations for excavating in reinforced concrete cu.m 76.25

9.04 Demolish reinforced concrete suspended slab including


integral beams under cu.m 22.88

9.05 Demolish existing reinforced concrete column ,size 350 x350 mm cu.m 9.34

25
9.06 Demolish existing reinforced column 350 mm diameter cu.m 7.34

9.07 Demolish existing reinforced concrete beam size 600 x 230 mm cu.m 10.52

9.08 Demolish existing reinforced concrete beam size 450 x230 mm cu.m 7.93

9.09 Demolish reinforced concrete staircase ,complete including steel balustrade


and timber hand rail [Main Staircase] cu.m 694.20

9.10 Demolish reinforced concrete staircase ,complete including steel balustrade


and timber hand rail [External Staircases] cu.m 654.78
ITEM DESCRIPTION UNIT RATES (US$)
9.11 Break through 150 mm thick reinforced concrete to make hole 400 mm
diameter cu.m 1.45

9.12 Break through 150 mm thick reinforced concrete to make way for column
bases including reinstating slab, with and including Ref S193 mesh cu.m 11.44
reinforcement

9.13 Break through 150 mm thick curved reinforced concrete slab at 7.5-10 m
height from floor level ,and make good exposed edge cu.m 18.71

9.14 Cut back existing 150 mm thick reinforced concrete to expose


reinforcement for new slab m. 12.41

9.15 Cut back portal frames at height 7.5 -10 m above floor level and make no. 60.68
good both ends

9.16 Demolish half brickwall cu.m 4.34

9.17 Demolish 230 mm brickwall cu.m 8.67

9.18 Demolish 345 mm cavity wall cu.m 13.01

9.19 Hack off cement plaster on walls and prepare to receive new plaster sq.m 0.25

9.20 Hack off ceramic wall tiling and screeed dacking on walls and prepare
to receive new tiling sq.m 0.45

9.21 Remove pinboards on walls [various sizes] no. 0.36

26
9.22 Take up 50 mm thick precast concrete paving slabs including mortar sq.m 0.89
bed under

9.23 Ditto and prepare concrete to receive new screed sq.m 0.89

9.24 Take up tarmacadam paving sq.m 1.88

9.25 Take up existing ''Fidia Index'' waterproofing to concrete flat roofs including
cement screed under and prepare concrete to receive new screed sq.m 1.88

9.26 Ditto parquet woodblock flooring including screed under,total 40 mm


thick and prepare concrete to receive new screed sq.m 1.88

ITEM DESCRIPTION UNIT RATES (US$)

9.27 Hack up vinyl asbestos tile flooring including screed under,total 40 mm thick
and prepare concrete to receive new screed sq.m 1.88

9.28 Hack up ceramic tile flooring including screed under,total 40 mm thick and
prepare concrete to receive new screed sq.m 1.88

9.29 Remove pine slate cladding from concrete colunms. sq.m 0.89

9.30 Hack up 40 mm thick granolithic paving on floors and


prepare concrete to receive new screed sq.m 1.88

9.31 Take down demountable timber partitions sq.m 0.25

9.32 Remove steel mesh security screens to windows sq.m 0.25

9.33 Remove steel grille partition to existing restaurant area sq.m 0.25

9.34 Take down shopfronts sq.m 0.25

9.35 Take down mineral fibre accoustic ceiling tile and support structure
Take down timber lattice ceiling sq.m 0.30

9.36 Remove sheet iron roofing fixed on steel purlins


Remove sheet iron roofing fixed on timber purlins sq.m 0.50

9.39 Remove broken glass from steel window frame and prepare rebates to

27
receive new glass sq.m 0.74

9.40 Remove broken glass louvre blade 150 mm wide [In no. 2] sq.m 0.74

9.41 Remove 20 x76 mm hardwood skirtings including quadrants from walls m. 0.18

9.42 Remove timber servery counter approximately 500 mm wide complete


including framing sq.m 0.22

9.43 Remove 100 x100 x 6 mm mild steel angle section corner protectors from m. 0.30
concrete colunms

9.44 Remove balustrading 1000 mm high m. 0.25

9.45 Form opening in existing half brickwall for ,set up in position and build in
pressed steel door frame [elsewhere measured] for door size 815 x2030 mm no. 9.84
ITEM DESCRIPTION UNIT RATES (US$)
9.46 Ditto in existing one brickwall ditto for door size 815 x2030 mm no. 17.01

9.47 Ditto in existing one brickwall ditto for door size 1615 x 2030 mm no. 30.96

9.48 Remove timber door hung to existing pressed steel door frame, size
815 x2030 mm no. 1.48

9.49 Take out from half brickwall to be demolished 815 x2030 mm timber door
in and pressed steel door frame m. 1.48

9.50 Ditto from half brickwall to be demolished 1370 x2030 mm pair of timber
doors ditto m. 1.48

9.51 Ditto from half brickwall to be demolished 1615 x 2030 mm pair of timber m. 1.48
doors ditto

9.52 Ditto from one brickwall to be demolished 815 x 2030 mm pair of timber m. 1.48
doors ditto

9.53 Take out from half brick wall 815 x2030 mm timber door in and including
pressed steel door frame and prepare jambs to receive new brickwork no. 1.62
[elsewhere measured]

9.54 Ditto from one brickwall 815 x2030 mm timber door ditto no. 2.23

28
9.55 Ditto from one brickwall 1370 x2030 mm pair of timber door ditto no. 2.23

9.56 Take out from one brickwall to be demolished steel window n.e 5m2 no. 2.23

9.57 Take out from one brickwall to be demolished steel window exceeding 5m2 no. 1.48
but not exceeding 10 m2

9.58 Take out from one brickwall to be demolished steel window not exceeding
5m2m brick up opening,and plaster to match existing no. 1.48

9.59 Take out from 230 mm thick reinforced concrete wall to be demolished
'Chubb'' strongroom door and frame size overall 1100 x2050 mm no. 2.97

9.60 Take out from 115 mm brick wall timber door in and including pressed
steel door frame size 815 x2030 mm and set up in position
and build in new pressed steel door frame for door size 815 x 2030 mm no. 1.48

ITEM DESCRIPTION UNIT RATES (US$)


9.61 Disconnect and stop off cold water supply and waste pipework to wash hand
basin and remove basin and supporting brackets from wall no. 1.48

9.62 Disconnect and stop off cold water supply and waste pipework to wash hand
basin and remove basin and supporting brackets from wall
opening within 155 mm brickwall with plaster to match existing no. 7.91

9.63 Remove W.C suite and remove W.C suite and cistern no. 2.97

9.64 Disconnect and stop off all water supply and soil pipework to stainless steel
urinal 700 mm long x 1250 mm high and remove urinal and cistern no. 4.45

9.65 Excavation, removal of pipes of all types and backfilling in 150mm layers pipe
trenches up to two metres deep and compacting to 91% Mod AASHTO
for pipe up to 100mm diameter. no. 6.67

9.66 Extra over in excavating in depths exceeding 2metres for pipes up to cu.m 7.44
100mm dia

9.67 Extra over in excavating in depths exc. 2metres for pipes b/twn 100 & cu.m 6.30
200mm dia.

9.68 Excavation , removal of manhole rings and backfilling in 150mm layers

29
compacting to 91% Mod AASHTO for man holes up to 1500mm diameter
for depths not exceeding 1000mm cu.m 9.02

9.69 Excavation , removal of manhole rings and backfilling in 150mm layers


compacting to 91% Mod AASHTO for man holes up to 1500mm diameter
for depths not exceeding 2000mm cu.m 9.39

10 Roof Covering Rates

10.01 To roofs in single Asbestos sheets fixed to purlins to 45 degree pitch sq.m 16.42

10.02 To roofs in single IBR fluted sheets fixed to purlins to 45 degree pitch sq.m 9.62

10.03 To roofs in Concrete Roofing tiles fixed to purlins to 45 degree pitch sq.m 2.56

10.04 To roofs in Chromadek roof sheets fixed to purlins tO 45 degree pitch sq.m 29.89

10.05 Labor only cranking down roof sheets across width of sheets at sq.m 0.28

10.06 Cover flashing at junction of four hip flashings at apex of pyramid roof sq.m 0.28

30
ITEM DESCRIPTION UNIT RATES (US$)

10.07 Cover flashing at junction of three hip flashings at apex of pyramid roof sq.m 0.28

10.08 Extra for raking cutting and waste to chromadek roof sheeting sq.m 0.28

10.09 Hip capping 450 mm girth three times bent along the length ,cut to
profile of roof sheeting along both edges and fixed with roof sheeting sq.m 0.28

10.10 Cover flashing at roof gables circular on elevation to flat sweep sq.m 0.28

10.11 Ridge capping 450 mm girth three times bent along the length, cut to
profile of roof sheeting along both edges and fixed with roof sheeting sq.m 0.28

10.12 Clear acrylic roof coverings in single sheets fixed vertically to steel rails sq.m 0.28

10.13 Hulabond roof coverings in single sheets fixed vertically to steel rails sq.m 0.28

11 Roadworks Rates
11.01 Supply and lay Mountable kerbs incl all necessary bedding,
jointing etc m 23.06

11.02 Supply and lay Municipal kerbs incl all necessary bedding,
jointing etc m 13.81

11.03 Supply and lay Taphalt Edging kerbs incl all necessary bedding,
jointing etc m 11.08

11.04 Supply and lay Bullnosed kerbs incl all necessary bedding,
jointing etc m 11.34

11.05 Supply and lay Lightduty Barrier (H2) kerbs incl all necessary bedding,
jointing etc m 15.36

11.06 Supply and lay Heavyduty Barrier (H3)kerbs incl all necessary bedding,
jointing etc m 21.26

11.07 20mm sand layer for preparation for paving bricks sq.m 31.67

11.08 Common excavation for the kerbs foundation cu.m 1.50

11.09 Supply all materials and Gee Type paving bricksurfacing

31
Size (200x100mm) sq.m 15.13

ITEM DESCRIPTION UNIT RATES (US$)

11.10 Supply all materials and Tee paving bricksurfacing sq.m 11.01
Size (230x140mm)

11.11 Scrap off a 0.5m width strip of existing surfacing for the kerbs
and waste deposited within 2km radious of site cu.m 19.13

12 Formwork Rates
12.01 To sides of sides of ground beams sq.m

12.02 To sides of sides of ground beams circular in plan to quick sweep sq.m

12.03 To sides of square or rectangular columns sq.m

12.04 To sides of 300mm diameter columns sq.m

12.05 To sides of walls sq.m

12.06 To edges in narrow widths sq.m

12.07 Block in to form sump 300x300x300mm deep in top of


450mm deep concrete base no

12.08 Steel formwork to edge of surface bed 150mm high incl perforations
for 12mm incl perforations for 12mm dia dowel bar
(elsewhere measured) @ 600mm c/c m

12.09 To sides of beams sq.m

12.10 To sides of upstand beams sq.m

12.11 To sides of circular columns 300mm diameter sq.m

12.12 To edges of slabs in narrow widths sq.m

12.13 To edges of slabs curved in plan to quick sweep sq.m

12.14 To raking and stepped outer edge of stairs in narrow widths sq.m

32
12.15 To soffits of suspended slabs sq.m

12.16 To soffits of landings sq.m

ITEM DESCRIPTION UNIT RATES (US$)

12.17 To raking soffits of stairs sq.m

12.18 To soffits of beams sq.m

12.19 Block in to form openning for 400mm dia steel column through
150mm thk slab no

12.20 Block in to form opening size 2000x1500mm through 150mm thk slab no

12.21 Block in to form opening size 2000x2100mm through 150mm thk slab no

33
34
ESTIMATING DATA:
RATE BUILD UP
2012

Riddell Qs

EARTHWORKS

DATA
SKILLED WORKER ONE
SKILLED WORKER TWO
SKILLED WORKER THREE
SKILLED WORKER FOUR
WORKER EXEMPTED
WORKER GRADE FOUR
WORKER GRADE THREE
WORKER GRADE TWO
WORKER GRADE ONE

DATA
Excavation Gang
WX Gang Boss 2.84 p day x 9hrs x 1
WG1 Labourer 2.84 p day x 9hrs x 10

Excavation Gang
WX Gang Boss 2.84 p day x 9hrs x 1
WG1 Labourer 2.84 p day x 9hrs x 8

Carpentry Team
Capenter
SW1 4.72 p hr x 9 hrs x 1
SW2 4.42 p hr x 9 hrs x 2
SW3 4.17 p hr x 9 hrs x 3
SW4 3.88 p hr x 9 hrs x 3
= applied Factor / 9

Carpenter &Team (C + 1)
Carpenter 37.71 per day
Assistant 2.84 x 9 hrs per day

Carpenter &Team (C + 2)
Carpenter 37.71 per day
Assistants 2.84 x 9 hrs per day x 2 No

Excavation Machinery team


WG4 Gang Boss 3.100 p day x 9hrs x 1
WG1 Labourers 2.840 p day x 9hrs x 6

EARTHWORK RATES
35
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Tipper 765.00 per day


Diesel 1.30 p Lt x 10Lt p day
Operator WX 2.840 x 9hrs p day

Plate compactor 450.00 per day x1


Petrol 1.35 p Lt x 5litres per day
Operator WG3 2.94 p hrx9hrs p day

Bomag 90 Roller 200.00 p day x 1


Diesel 1.30 p lt x10ltr p day
Operator WG3 2.94 p hrx9hrs p day

350 c.f.m - compressor


350 c.f.m - compressor 130.00 per day
Diesel 1.30 per ltr x 10ltrs per day
Operator WG3 2.94 p hrx9hrs p day

Dozer - NER E/movers


Dozer - NER E/movers 765.00 per day
Diesel 1.30 per ltr x 10ltrs per day
Operator WG3 2.94 p hrx9hrs p day

Heavy compaction equipment


Grader 855.00 per hr x 9hrs x 0.5
Bowser 585.00 per hr x 9hrs
Vibratory roller 585.00 per hr x 9hrs
Pneumatic roller 585.00 per hr x 9hrs

Hyundai excavator
Hire 1,530.00 x 2 No
Diesel 1.30 per litre x 10 x 5 x 4.33
Hydraulic oil 5.00 per litre x 5 x 5 x 4.33
Turbomax oil 6.00 per litre x 1 x 5 x 4.33
Operator SW1 4.72 p hr x 9 x 5 x 4.33

Cost per day = 4,932.29 per month / 4.33 x 5

River Sand cost per m3 (Including transport)

EARTHWORK RATES
36
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Pit sand cost per m3 (Including Transport)

EARTHWORK RATES
37
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Gravel cost per m3 (Including tranport)

Crusher run cost per m3 (Including transport)

RATE BUILD UP
1 Clear site of rubbish, grass, trees etc
Dozer - NER E/movers 765.00 per day / 5000m2 p day
Excavator 227.82 per day / 1800m2 per day
Tipper 803.56 p day / 900m2 per day
Excav mach team 181.26 p day / 5000m2 per day

P 1.17 L 0.04

2 Fell, stump & remove main roots of trees exceeding 0.5m girth
Excavation Gang (G.B&1 281.16 p day / 1 No per day

L 281.16

3 Excavate borrow pit material and stockpile on site


Dozer - NER E/movers 804.46 per day / 200m3 per day
Excav mach team 181.26 per day / 200m3 per day

L 0.91 P 4.02

4 Excavate in all material for trenches 950x1000mm


deep compact and spread spoil on site
Excavation Gang G.B & 281.16 p day / 15 m3 p day bulking
Excavation Gang G.B & 281.16 p day / 75 m3 p day deposit
Plate compactor 483.21 p day x 2No / 75 m3 p day

L 22.49 P 12.89

5 Excavate in pickable mat.to formation level and pile on site


Dozer - NER E/movers 804.46 per day / 200m3 per day
Excav mach team 181.26 per day / 200m3 per day

L 0.91 P 4.02

6 Extra within formation width and dispose and compact


Dozer - NER E/movers 804.46 per day / 300m2 per day
Excavator 227.82 per day / 300m2 per day
Tipper 2No 803.56 per day / 300m2 per day
Excav mach team 181.26 per day / 300m2 per day
Heavy compaction eqpm 19,642.50 per day / 600m2 per day

EARTHWORK RATES
38
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 0.60 P 38.86

EARTHWORK RATES
39
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

7 Extra within formation width and dispose


Dozer - NER E/movers 804.46 per day / 300m2 per day
Excavator 227.82 per day / 300m2 per day
Tipper 2No 803.56 per day / 300m2 per day
Excav mach team 181.26 per day / 300m2 per day

L 0.60 P 6.12

8 Extra over excavation in pickable material for excava in


hard material.
Excavation Gang G.B & 281.16 p day / 10 cu m p day

L 28.12

9 Excavate over site to remove vegetable soil and pile


Dozer - NER E/movers 804.46 per day / 450m3 per day
Excav mach team 181.26 per day / 450m3 per day

L 0.40 P 1.79

10 Excavate in pickable mat.for Vee drains incl trimming


and disposal.
Excavation Gang G.B & 281.16 p day / 15 cu m p day
Excavation Gang G.B & 281.16 p day / 55 cu m p day
Tipper 803.56 p day / 55 cu m p day x 1.3

L 23.86 P 18.99

11 Extra over for hauling exceeding 1km.


Tipper hire 803.56 p day / 36 loads / 5m3 per l

L P 4.46

12 Scarify ground surfaces and compact to 93% HCE


100mm depth
Excav mach team 181.26 p day / 600 cu m p day
Heavy compaction mach 19,642.50 p day / 600 cu m p day
Applied factor x 0.1
L 0.03 P 3.27

EARTHWORK RATES
40
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

13 Compact existing grnd to 93% Mod.AASHTO


Excav mach team 181.26 p day / 4000 sq m p day
Heavy compaction mach 19,642.50 p day / 4000 sq m p day

L 0.05 P 4.91

14 Allow for rehabilitation of borrow pit area, access road


and car park with topsoil from site
Excav mach team 181.26 p day / 2500 sq m p day
Dozer 804.46 p day / 2500 sq m p day

L 0.07 P 0.32

15 Redig from spoil heap, return, fill and compact


excavated material.
Heavy compaction mach 19,642.50 p day / 600 cu m p day
Excavator 227.82 p day / 600 cu m p day
Tipper 2No 803.56 per day x 2 / 600 m3 per da
Excav mach team 181.26 p day / 600 cu m p day

L 0.30 P 35.80
16 Approved imported inert granular material spread, level
and compact as described
Heavy compaction mach 19,642.50 p day / 600 cu m p day
Excavator 227.82 p day / 600 cu m p day
Tipper 2No 803.56 per day x 2 / 200 m3 per da
Excav mach team 181.26 p day / 600 cu m p day
Gravel 28.90 per m3 x 1.33 bulk

L 0.30 P 41.15 M

17 Approved imported inert granular material around &


under drain pipes
Excavation Gang G.B & 281.16 p day / 55 cu m p day
Gravel 32.50 p m3 x 1.33 bulk

L 5.11 M 43.23

18 Supply crusher run, spread and compact 150 thickness


Heavy compaction mach 19,642.50 p day / 600 cu m p day
Tipper 2No 803.56 per day x 2 / 200 m3 per da
Excav mach team 181.26 p day / 600 cu m p day
Crusher run 32.50 p m3 x 1.33 bulk

EARTHWORK RATES
41
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 0.30 P 40.77 M 43.23

EARTHWORK RATES
42
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

19 Supply and lay Municipal type kerbs incl necessary excav,


bedding etc
Carpenter & team 88.83 p day / 30 m p day
H7 Kerbs 7.25 p m x 1.05waste
1.3 mortar 118.81 p m3 x 0.001m3/m x 1.25wa
Gr 25 concrete 163.91 per m3 x 0.06 x 1.15 waste
Excavation gang 281.16 per day '/ 15m3 x 0.135
Backfilling gang 281.16 per day '/ 30m3 x 0.075

L 6.19 M 19.07

20 Supply and lay G type kerbs incl necessary excav, bedding etc
Carpenter & team 88.83 p day / 30 m p day
GType Kerbs 25.68 p m x 1.05waste
1.3 mortar 118.81 p m3 x 0.001m3/m x 1.25wa
Gr 25 concrete 163.91 per m3 x 0.06 x 1.15 waste
Excavation gang 281.16 per day '/ 15m3 x 0.135
Backfilling gang 281.16 per day '/ 30m3 x 0.075

L 6.19 M 38.42

21 Supply and lay Taphalt edging kerbs incl necessary


excav, bedding etc
Carpenter & team 88.83 p day / 30 m p day
Taphalt edging Kerbs 4.40 p m x 1.05waste
1.3 mortar 118.81 p m3 x 0.001m3/m x 1.25wa
Gr 25 concrete 163.91 per m3 x 0.06 x 1.15 waste
Excavation gang 281.16 per day '/ 15m3 x 0.135
Backfilling gang 281.16 per day '/ 30m3 x 0.075

L 6.19 M 16.08

22 Supply and lay Hollow Mountable type kerbs incl necessary


excav, bedding etc
Carpenter & team 88.83 p day / 20 m p day
H5 Kerbs 11.68 p m x 1.05waste
1.3 mortar 118.81 p m3 x 0.001m3/m x 1.25wa
Gr 25 concrete 163.91 per m3 x 0.06 x 1.15 waste
Excavation gang 281.16 per day '/ 15m3 x 0.135
Backfilling gang 281.16 per day '/ 30m3 x 0.075

L 7.67 M 23.72

EARTHWORK RATES
43
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

23 Supply and lay Heavy duty H3 type kerbs incl necessary


excav, bedding etc
Carpenter & team 88.83 p day / 20 m p day
H5 Kerbs 15.04 p m x 1.05waste
1.3 mortar 118.81 p m3 x 0.001m3/m x 1.25wa
Gr 25 concrete 163.91 per m3 x 0.06 x 1.15 waste
Excavation gang 281.16 per day '/ 15m3 x 0.135
Backfilling gang 281.16 per day '/ 30m3 x 0.075

L 16.45 M 15.94 P 2.53

24 Supply and lay 305mm stormwater pipes incl backfill and ram
Carpenter & team 88.83 p day / 20 m p day
305mm pipe 65.86 p m x 1.05waste
1;3 mortar 118.81 p m3 x 0.004m3/m x 1.15wa
Excav gang GB&8 281.16 p day / 30m p day
Plate compactor 483.21 p day x2/30m per day
Trimming gang 281.16 p day / 100m per day

L 16.63 M 69.70 P 32.21

25 Supply and lay 380mm stormwater pipes incl backfill and ram
Carpenter & team 88.83 p day / 20 m p day
380mm pipe 68.53 p m x 1.05waste
1;3 mortar 118.81 p m3 x 0.004m3/m x 1.15wa
Excav gang GB&8 281.16 p day / 30m p day
Plate compactor 483.21 p day x2/30m per day
Trimming gang 281.16 p day / 100m per day

L 16.63 M 72.50 P 32.21

26 Supply and lay 450mm stormwater pipes incl backfill and ram
Carpenter & team 88.83 p day / 20 m p day
450mm pipe 80.16 p m x 1.05waste
1;3 mortar 118.81 p m3 x 0.004m3/m x 1.15wa
Excav gang GB&8 281.16 p day / 30m p day
Plate compactor 483.21 p day x2/30m per day
Trimming gang 281.16 p day / 100m per day

L 16.63 M 84.71 P 32.21

EARTHWORK RATES
44
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

27 Supply and lay 610mm stormwater pipes incl backfill and ram
Carpenter & team 88.83 p day / 20 m p day
610mm pipe 104.74 p m x 1.05waste
1;3 mortar 118.81 p m3 x 0.004m3/m x 1.15wa
Excav gang GB&8 281.16 p day / 30m p day
Plate compactor 483.21 p day x2/30m per day
Trimming gang 281.16 p day / 100m per day

L 16.63 M 110.52 P 32.21

28 Supply and lay 700mm stormwater pipes incl backfill and ram
Carpenter & team 88.83 p day / 20 m p day
700mm pipe 109.80 p m x 1.05waste
1;3 mortar 118.81 p m3 x 0.004m3/m x 1.15wa
Excav gang GB&8 281.16 p day / 30m p day
Plate compactor 483.21 p day x2/30m per day
Trimming gang 281.16 p day / 100m per day

L 16.63 M 115.84 P 32.21

29 Supply and lay 915mm stormwater pipes incl backfill and ram
Carpenter & team 88.83 p day / 20 m p day
915mm pipe 121.69 p m x 1.05waste
1;3 mortar 118.81 p m3 x 0.004m3/m x 1.15wa
Excav gang GB&8 281.16 p day / 30m p day
Plate compactor 483.21 p day x2/30m per day
Trimming gang 281.16 p day / 100m per day

L 16.63 M 128.32 P 32.21

30 Stone pitching
Bricklayer and Team 88.83 /4m2 pday
Commons 22.05 p m2x1.05 waste
1;3 mortar 118.81 x0.053m3/m2x1.15waste

L 22.21 m 29.29

EARTHWORK RATES
45
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

31 Supply and lay 1200mm bore class "x"concrete stormwater


pipes incl backfill and ram
Carpenter & team 88.83 p day / 10 m p day
1200mm pipe 168.51 p m x 1.05waste
1;3 mortar 118.81 p m3 x 0.01m3/m x 1.15was
Excav gang GB&8 230.04 p day / 20m p day
Plate compactor 483.21 p day x2/20m per day
Trimming gang 230.04 p day / 50m per day

L 24.99 M### P 48.32

32 Supply,lay. Bed and joint 150mm bore porous concrete pipe


Carpenter & team 88.83 p day / 50 m p day
150mm pipe 31.98 p m x 1.05waste
Bedding gang GB&8 230.04 p day / 75m p day

L 4.84 M 33.58

33 One brick wall in common bricks in cement mortar.


Bricklayer and Team 88.83 /450bricks pdayx105bricks
Commons 180.00 /1000x105bricks pm2x1.05
1:4 Cement & sand mor 105.39 x0.05m3/m2x1.15waste

L 20.73 m 25.91

34 460x460mm piers in common bricks in cement mortar.


Bricklayer and Team 88.83 /350bricks pdayx96bricks ea
Commons 180.00 /1000x96bricks pm3x1.05 w
1:4 Cement & sand mor 105.39 x0.05m3/m2x1.15waste

L 24.36 M 24.20

35 One brick wall in light brindles bricks in cement mortar.


Bricklayer and Team 88.83 /250bricks pdayx105bricks
Brindles 330.00 /1000x105bricks pm2x1.05
1:4 Cement & sand mor 105.39 x0.05m3/m2x1.15waste
Apllied factor x 0.370
L 13.80 m 15.70

36 Supply and fix PCC copings 50x300x600mm to walls.


Carpenter and Team 88.83 per day / 15m per day
copings 6.71 per m x 1.05 waste
1:4 Cement & sand mor 105.39 per m3 x 0.023m3/mx1.15w

EARTHWORK RATES
46
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 5.92 M 7.32

EARTHWORK RATES
47
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

37 Supply and fix PCC copings 50x300x600mm square to piers.


Carpenter and Team 88.83 per day / 15m per day
copings 6.71 per m x 1.05 waste
1:4 Cement & sand mor 105.39 per m3 x 0.023m3/mx1.15w

L 5.92 M 7.32

38 Haul, dump, spread and compact approved material


around kerbs
Excav gang 281.16 per day / 30m3 per day
Plate compactor 483.21 per day x 2 No / 30m3 per d

L 9.37 P 32.21

EARTHWORK RATES
48
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

4.72
4.42
4.17
3.88
2.84
3.10
2.94
2.94
2.84

25.56
255.60
281.16

25.56
204.48
230.04

4.72
8.84
12.51
11.64
37.71

37.71
25.56
63.27

37.71
51.12
88.83

27.90
153.36
181.26

EARTHWORK RATES
49
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

765.00
13.00
25.56
803.56

450.00
6.75
26.46
483.21

200.00
13.00
26.46
239.46

130.00
13.00
26.46
169.46

765.00
13.00
26.46
804.46

3,847.50
5,265.00
5,265.00
5,265.00
19,642.50

3,060.00
281.45
541.25
129.90
919.69
4,932.29

227.82

25.00

EARTHWORK RATES
50
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

25.00

EARTHWORK RATES
51
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

30.00

32.50

0.15
0.13
0.89
0.04
1.21

ding 0.5m girth


281.16
281.16

4.02
0.91
4.93

18.74
3.75
12.89
35.38

pile on site
4.02
0.91
4.93

2.68
0.76
2.68
0.60
32.74

EARTHWORK RATES
52
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

39.46

EARTHWORK RATES
53
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

2.68
0.76
2.68
0.60
6.72

28.12
28.12

1.79
0.40
2.19

18.74
5.11
18.99
42.85

4.46
4.46

0.03
3.27
3.30

EARTHWORK RATES
54
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

0.05
4.91
4.96

0.07
0.32
0.39

32.74
0.38
2.68
0.30
36.10

32.74
0.38
8.04
0.30
38.44
79.89
38.44

5.11
43.23
48.34

32.74
8.04
0.30
43.23
84.30

EARTHWORK RATES
55
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

EARTHWORK RATES
56
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

2.96
7.61
0.15
11.31
2.53
0.70
25.27

v, bedding etc
2.96
26.96
0.15
11.31
2.53
0.70
44.62

2.96
4.62
0.15
11.31
2.53
0.70
22.27

cl necessary

4.44
12.26
0.15
11.31
2.53
0.70
31.40

EARTHWORK RATES
57
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

4.44
15.79
0.15
11.31
2.53
0.70
34.93

ackfill and ram


4.44
69.15
0.55
9.37
32.21
2.81
118.54

ackfill and ram


4.44
71.96
0.55
9.37
32.21
2.81
121.34

ackfill and ram


4.44
84.17
0.55
9.37
32.21
2.81
133.55

EARTHWORK RATES
58
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

ackfill and ram


4.44
109.98
0.55
9.37
32.21
2.81
159.36

ackfill and ram


4.44
115.29
0.55
9.37
32.21
2.81
164.68

ackfill and ram


4.44
127.77
0.55
9.37
32.21
2.81
177.16

22.21
22.05
7.24
51.50

EARTHWORK RATES
59
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

stormwater

8.88
176.94
1.37
11.50
48.32
4.60
251.61

oncrete pipe
1.78
33.58
3.07
38.42

20.73
19.85
6.06
46.63

24.36
18.14
6.06
48.57

13.80
13.46
2.24
29.51

5.92
7.05
0.28
13.25

EARTHWORK RATES
60
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

EARTHWORK RATES
61
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

uare to piers.
5.92
7.05
0.28
13.25

9.37
32.21
41.59

EARTHWORK RATES
62
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

WG1 hr 2.84 2.84


WG2 hr 2.94 2.94
WG3 hr 2.94 2.94
WG4 hr 3.10 3.10
SW1 hr 4.72 4.72
SW2 hr 4.42 4.42
SW3 hr 4.17 4.17
SW4 hr 3.88 3.88
Watchman hr 3.11 3.11
Driver hr 5.38 5.38
Grader Operato hr #VALUE! #VALUE!
Operator hr 7.48 7.48
Operator's Assi hr 4.33 4.33
Surfacing Fore hr #VALUE! #VALUE!
Foreman hr #VALUE! #VALUE!

EARTHWORK RATES
63
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA
RATE BUILD
2012

TN ZUNZANYIKA ASSOCIATES

DATA
SKILLED WORKER ONE 0.38
SKILLED WORKER TWO 0.35
SKILLED WORKER THREE 0.33
SKILLED WORKER FOUR 0.30
WORKER EXEMPTED 0.30
WORKER GRADE FOUR 0.23
WORKER GRADE THREE 0.23
WORKER GRADE TWO 0.22
WORKER GRADE ONE 0.22

Carpenter and Team


Carpenter
SW1 0.38 p hr x 9 hrs x 1 0.38
SW2 0.35 p hr x 9 hrs x 2 0.70
SW3 0.33 p hr x 9 hrs x 3 0.98
SW4 0.30 p hr x 9 hrs x 3 0.90
= applied Factor / 9 2.96

Carpenter and Team


Carpenter 2.96 per day 2.959404
Assitant 0.22 x9hrsx2No 1.98
4.94

Carpenter &Team (C + 2)
Carpenter 2.96 per day 2.96
Assistants 0.22 x 9 hrs per day x 2 No 3.97
6.93
Materials Cost

3.6m long asbestos sheets/mt 15.30


Concrete Roofing Tiles 0.89
IBR fluted roofing sheets/mt 15.30
Chromadek roof sheets/m2 28.46
Asbestos Ridge/pr 28.05
End finials 5.10
Hook bolts 0.32
Washer 0.17
Screws 0.20
100mm Wire nails/kg 2.13
Dpc/mt 0.38

ROOF COVERING RATES


64
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA
RATE BUILD
2012

RATE BUILD UP

1 To roofs in single Asbestos sheets fixed to purlins to 45 degree pitch

Carpenter and Team 6.93 / 25 m2 per day 0.28


Asbestos sheets 15.30 /sht /3.24m2 / sht x 1.05 waste 7.57
Asbestos ridge 7.79 per mtr x 1.05waste 8.18
100mm wire nails 0.11 each x 3 per m x 1.05 waste 0.39
L 0.28 M 16.14 16.42

2 To roofs in single IBR fluted sheets fixed to purlins to 45 degree pitch


Carpenter and Team 6.93 / 25 m2 per day 0.28
IBR fluted roofing sheets 15.30 /sht / 2.44m2 / sht x 1.05 waste 7.57
Hook bolts 0.32 each x 3 per m x x 1.05 waste 1.16
Washers 0.17 each x 3 per m x 1.15 x 1.05 waste 0.62
Bituminous felt/Dpc 0.38 per m x 1.05 waste 0.46
9.62

3 To roofs in Concrete Roofing tiles fixed to purlins to 45 degree pitch


Carpenter and Team 0.32 / 25 m2 per day 0.01
Concrete Roof Coverings 0.17 x15 no. per m2 x 1.05 waste 2.55
2.56
4 To roofs in Chromadek roof sheets fixed to purlins tO 45 degree pitch
Carpenter and Team 0.28 / 25 m2 per day 0.01
Chromadek roof sheets 28.46 per m2 x 1.05 waste 29.88
29.89

5 Labor only cranking down roof sheets across width of sheets at


change in roof pitch [approximatel / 150 m per day 0.00
Carpenter and Team 6.93 / 25 m2 per day 0.28
0.28
L 0.28 M 0.00

6 Cover flashing at junction of four hip flashings at apex of pyramid roof


Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

8 Cover flashing at junction of three hip flashings at apex of pyramid roof


Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

ROOF COVERING RATES


65
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA
RATE BUILD
2012

9 Extra for raking cutting and waste to chromadek roof sheeting


Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

10 Hip capping 450 mm girth three times bent along the length ,cut to profile
of roof sheeting along both edges and fixed with roof sheeting
Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

11 Cover flashing at roof gables circular on elevation to flat sweep


Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

12 Ridge capping 450 mm girth three times bent along the length, cut to
profile of roof sheeting along both edges and fixed with roof sheeting
Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

13 Clear acrylic roof coverings in single sheets fixed vertically to steel rails
Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

14 Hulabond roof coverings in single sheets fixed vertically to steel rails


Carpenter and Team 6.93 / 25 m2 per day 0.28
0.00
0.28
L 0.28 M 0.00

ROOF COVERING RATES


66
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA
RATE BUILD
2012

ROOF COVERING RATES


67
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Riddell Qs

EXCAVATIONS -DEMOLITION RATES


0.38
DATA
SKILLED WORKER ONE 0.38
SKILLED WORKER TWO 0.35
SKILLED WORKER THREE 0.33
SKILLED WORKER FOUR 0.30
WORKER EXEMPTED 0.30
WORKER GRADE FOUR 0.23
WORKER GRADE THREE 0.23
WORKER GRADE TWO 0.22
WORKER GRADE ONE 0.22

DATA
Excavation Gang
WX Gang Boss 0.30 p day x 9hrs x 1 2.70
WG1 Labourer 0.22 p day x 9hrs x 10 19.83
22.53
Excavation Gang
WX Gang Boss 0.30 p day x 9hrs x 1 2.70
WG1 Labourer 0.22 p day x 9hrs x 8 15.86
18.56

Tractor & Trailer per day -


Diesel 1.30 p Lt x 10Lt p day 117.00
Operator WG3 1.31 9hrs p day 11.79
128.79

Plate compactor 40.25 per day x1 40.25


Petrol 1.40 p Lt x 5Ltrs p day 11.34
Operator WG3 1.31 p hrx9hrs p day 11.79
63.38

Bomag 90 Roller 200.00 p day x 1 200.00


Diesel 1.30 p lt x10ltr p day 13.00
Operator WG3 1.31 p hrx9hrs p day 11.79

224.79
350 c.f.m - compressor
350 c.f.m - compressor 130.00 per day 130.00
Diesel 1.30 per ltr x 10ltrs per day 13.00
Operator WG3 1.31 p hrx9hrs p day 11.79
154.79

Sand cost per m3 15.30

Pit sand cost per m3 13.60

Gravel cost per m3 28.90

Decomposed granite 42.00

CEMENT & SAND MORTOR MIX 1:4

Labourer 0.22 /120bags per day x8.9m3 handle 0.02


OPC Cement bagged 50kg 9.80 x8.9bgsx1.01 waste 88.09
Pit Sand 13.60 pm3x1.50m3x1.15 wa 23.46
111.57

DEMOLISHING RATES
68
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

DEMOLISHING RATES
69
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

DEMOLITIONS

DATA

SKILLED WORKER ONE 0.38


SKILLED WORKER TWO 0.35
SKILLED WORKER THREE 0.33
SKILLED WORKER FOUR 0.30
WORKER EXEMPTED 0.30
WORKER GRADE FOUR 0.23
WORKER GRADE THREE 0.23
WORKER GRADE TWO 0.22
WORKER GRADE ONE 0.22

Carpentry Team
Capenter
SW1 0.38 p hr x 9 hrs x 1 0.38
SW2 0.35 p hr x 9 hrs x 2 0.70
SW3 0.33 p hr x 9 hrs x 3 0.98
SW4 0.30 p hr x 9 hrs x 3 0.90
= applied Factor / 9 2.96

Carpenter &Team (C + 1)
Carpenter 2.96 per day 2.96
Assistant 0.22 x 9 hrs per day 1.98
4.94

DEMOLISHING RATES
70
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Carpenter &Team (C + 2)
Carpenter 2.96 per day 2.96
Assistants 0.22 x 9 hrs per day x 2 No 3.97
6.93

Carpenter &Team (C + 6)
Carpenter 2.96 per day 2.96
Assistants 0.22 x 9 hrs per day x 6 No 11.90
14.86
DEMOLISHING GANG

Bricklayer 2.96
Assistant 0.22 x9 hrs per day x 3 No 5.95
8.91

* Excavate over site to remove vegetable soil and cart away

Excavation Gang G.B & 10 22.53 p day / 200 M2 p day bulking 0.11
Excavation Gang G.B & 10 22.53 p day / 250 m2 p day deposit 0.09
0.20
L 0.20
RATE BUILD UP

1 Excavate in earth n.e 2 m deep and remove reinforced concrete base


size 2000 x2000 x 400 mm

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 14.42
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 8.52
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 99.07
= Applied factor x 1.6
122.00
L 22.94 P 99.07

2 Excavate in earth n.e 2 m deep and remove reinforced concrete base


size 3500 x3500 x 400 mm

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 44.15
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 26.09
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 303.39

= Applied factor x 4.90


373.63
L 70.24 P 303.39

DEMOLISHING RATES
71
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
3 Extra over all excavations for excavating in reinforced concrete

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 9.01
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 5.32
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 61.92

76.25
L 14.34 P 61.92

4 Demolish reinforced concrete suspended slab including


integral beams under
Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 2.70
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 1.60
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 18.57

= Applied factor x 0.30


22.88
L 4.30 P 18.57

5 Demolish existing reinforced concrete column ,size 350 x350 mm

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 1.10
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 0.65
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 7.58

= Applied factor x 0.1225


9.34
L 1.76 P 7.58

6 Demolish existing reinforced column 350 mm diameter

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 0.87
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 0.51
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 5.96

= Applied factor x 0.0962


7.34
L 1.38 P 5.96
7 Demolish existing reinforced concrete beam size 600 x 230 mm

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 1.24
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 0.73
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 8.54

DEMOLISHING RATES
72
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
= Applied factor x 0.138
10.52
L 1.98 P 8.54

8 Demolish existing reinforced concrete beam size 450 x230 mm

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 0.94
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 0.55
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 6.44

= Applied factor x 0.104


7.93
L 1.49 P 6.44

9 Demolish reinforced concrete staircase ,complete including steel balustrade


and timber hand rail [Main Staircase]

Excavation Gang G.B & 10 22.53 p day /1.0 cu m p day Breaking 118.27
Excavation Gang G.B & 10 22.53 p day / 4.5 cu m x1.3 bulk up 34.17
350 c.f.m - compressor 154.79 p day /1.5 cu m p day 541.77

= Applied factor x 5.25


694.20
L 152.43 P 541.77

10 Demolish reinforced concrete staircase ,complete including steel balustrade


and timber hand rail [External Staircases]

Excavation Gang G.B & 10 22.53 p day /1.5 cu m p day Breaking 78.85
Excavation Gang G.B & 10 22.53 p day / 4.5 cu m x1.3 bulk up 34.17
350 c.f.m - compressor 154.79 p day /1.5 cu m p day 541.77

= Applied factor x 5.25


654.78
L 113.01 P 541.77

11 Break through 150 mm thick reinforced concrete to make hole 400 mm


diameter

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 0.17
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 0.10
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 1.18

= Applied factor x 0.019


1.45
L 0.27 P 1.18

DEMOLISHING RATES
73
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

12 Break through 150 mm thick reinforced concrete to make way for column
bases including reinstating slab, with and including Ref S193 mesh
reinforcement
Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Breaking 1.35
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk up 0.80
350 c.f.m - compressor 154.79 p day /2.5 cu m p day 9.29

= Applied factor x 0.150


11.44
L 2.15 P 9.29

0
13 Break through 150 mm thick curved reinforced concrete slab at 7.5-10 m
height from floor level ,and make good exposed edge

Excavation Gang G.B & 10 22.53 p day / 1.5 cu m p day Breaking 2.25
Excavation Gang G.B & 10 22.53 p day / 4.5 cu m x1.3 bulk up 0.98
350 c.f.m - compressor 154.79 p day /1.5 cu m p day 15.48

= Applied factor x 0.150


18.71
L 3.23 P 15.48

14 Cut back existing 150 mm thick reinforced concrete to expose reinforcement


for new slab
Excavation Gang G.B & 10 22.53 p day / 15m p day Breaking 1.50
Excavation Gang G.B & 10 22.53 p day / 50 m x1.3 bulk up 0.59
350 c.f.m - compressor 154.79 p day /15m p day 10.32

12.41
L 2.09 P 10.32

15 Cut back portal frames at height 7.5 -10 m above floor level and make
good both ends

Excavation Gang G.B & 10 22.53 p day / 3no p day Breaking 7.51
Excavation Gang G.B & 10 22.53 p day / 3 x 1.3 bulk up 9.76
350 c.f.m - compressor 154.79 p day /15p day 10.32
Concrete 30 Mpa to make go 174.05 p m3 x 0.02 m2 3.48
B/Layer & Team 88.83 p day / 3no p day 29.61

F M 60.68
L 46.88 P 10.32 - 3.48

DEMOLISHING RATES
74
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

16 Demolish half brickwall


Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaking 0.52
Excavation Gang G.B & 10 22.53 p day / 10cu m p day Bulking 0.26
350 c.f.m - compressor 154.79 p day /5 cu m p day 3.56
= Applied factor x 0.1150

4.34
L 0.78 P 3.56

17 Demolish 230 mm brickwall

Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaking 1.04


Excavation Gang G.B & 10 22.53 p day / 10cu m p day Bulking 0.52
350 c.f.m - compressor 154.79 p day /5 cu m p day 7.12
= Applied factor x 0.230

8.67
L 1.55 P 7.12

18 Demolish 345 mm carvity wall

Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaking 1.55


Excavation Gang G.B & 10 22.53 p day / 10cu m p day Bulking 0.78
350 c.f.m - compressor 154.79 p day /5 cu m p day 10.68
= Applied factor x 0.345
13.01
L 2.33 P 10.68

20 Hack off cement plaster on walls and prepare to receive new plaster

Demolishing gang 8.91 p day / 35 m2 p day 0.25

L 0.25 0.25

19 Hack off ceramic wall tiling and screeed dacking on walls and prepare
to receive new tiling
Demolishing gang 8.91 p day / 20 m2 p day 0.45

L 0.45 0.45

20 Remove pinboards on walls [various sizes]

Demolishing gang 8.91 p day / 25 no p day 0.36

L 0.36 0.36

DEMOLISHING RATES
75
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
21 Take up 50 mm thick precast concrete paving slabs including mortar
bed under
Demolishing gang 8.91 p day /10 m2 p day 0.89

L 0.89 0.89

22 Ditto and prepare concrete to receive new screed

Demolishing gang 8.91 p day /10 m2 p day 0.89

L 0.89 0.89

23 Take up tarmacadam paving

Excavation Gang G.B & 10 22.53 p day /30 m2 p day 0.75


Excavation Gang G.B & 10 22.53 p day / 20 cu m p day bulk up 1.13

L 1.88 1.88

24 Take up existing ''Fidia Index'' waterproofing to concrete flat roofs


including cement screed under and prepare concrete to receive
new screed

Excavation Gang G.B & 10 22.53 p day /30 m2 p day 0.75


Excavation Gang G.B & 10 22.53 p day / 20 cu m p day bulk up 1.13

L 1.88 1.88

25 Ditto parquet woodblock flooring including screed under,total


40 mm thick and prepare concrete to receive new screed

Excavation Gang G.B & 10 22.53 p day /30 m2 p day 0.75


Excavation Gang G.B & 10 22.53 p day / 20 cu m p day bulk up 1.13

L 1.88 1.88

26 Hack up vinyl asbestos tile flooring including screed under,total


40 mm thick and prepare concrete to receive new screed

Excavation Gang G.B & 10 22.53 p day /30 m2 p day 0.75


Excavation Gang G.B & 10 22.53 p day / 20 cu m p day bulk up 1.13

L 1.88 1.88

DEMOLISHING RATES
76
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

27 Hack up ceramic tile flooring including screed under,total


40 mm thick and prepare concrete to receive new screed
Demolishing gang 22.53 p day /30 m2 p day 0.75
Excavation Gang G.B & 10 22.53 p day / 20 cu m p day bulk up 1.13

L 1.88 1.88

28 Remove pine slate cladding from concrete colunms.

Demolishing gang 8.91 p day /10 m2 p day 0.89

L 0.89 0.89

29 Hack up 40 mm thick granolithic paving on floors and


prepare concrete to receive new screed

Demolishing gang 22.53 p day /30 m2 p day 0.75


Excavation Gang G.B & 10 22.53 p day / 20 cu m p day bulk up 1.13

L 1.88 1.88

30 Take down demountable timber partitions

Demolishing gang 8.91 p day / 35 m2 p day 0.25

L 0.25 0.25

31 Remove steel mesh security screens to windows

Demolishing gang 8.91 p day / 35 m2 p day 0.25

L 0.25 0.25

32 Remove steel grille partition to existing restaurant area

Demolishing gang 8.91 p day / 35 m2 p day 0.25

L 0.25 0.25

DEMOLISHING RATES
77
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
33 Take down shopfronts

Demolishing gang 8.91 p day / 35 m2 p day 0.25

L 0.25 0.25

34 Take down mineral fibre accoustic ceiling tile and support structure
Take down timber lattice ceiling
Demolishing gang 8.91 p day / 30 m2 p day 0.30

L 0.30 0.30

35 Remove sheet iron roofing fixed on steel purlins


Remove sheet iron roofing fixed on timber purlins

Demolishing gang (C+6) 14.86 p day / 30 m2 p day 0.50

L 0.50 0.50

36 Remove broken glass from steel window frame and prepare


rebates to receive new glass

Demolishing gang 8.91 p day / 12 m2 p day 0.74

L 0.74 P 0.74

37 Remove broken glass louvre blade 150 mm wide [In no. 2]

Demolishing gang 8.91 p day / 12 m2 p day 0.74

L 0.74 0.74

38 Remove 20 x76 mm hardwood skirtings including quadrants from walls

Demolishing gang 8.91 p day / 50m p day 0.18

L 0.18 0.18

39 Remove timber pelmets to windows [various lengths]

Demolishing gang 8.91 p day /45m p day 0.20

L 0.20 0.20

DEMOLISHING RATES
78
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

40 Remove timber servery counter approximately 500 mm wide


complete including framing

Demolishing gang 8.91 p day /40m p day 0.22


L 0.22 P 0.22

41 Remove 100 x100 x 6 mm mild steel angle section corner protectors from
concrete colunms

Demolishing gang 8.91 p day /30m p day 0.30

L 0.30 0.30

42 Remove balustrading 1000 mm high


Demolishing gang 8.91 p day /35m p day 0.25

L 0.25 0.25

43 Form opening in existing half brickwall for ,set up in position and


build in pressed steel door frame [elsewhere measured]
for door size 815 x2030 mm

Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaking 0.86


Excavation Gang G.B & 10 22.53 p day / 10cu m p day Bulking 0.43
350 c.f.m - compressor 154.79 p day /5 cu m p day 5.88
= Applied factor x 0.19

Carpenter and Team 4.94 /10Nº set up 0.49


Bricklayer and Team 4.94 /30Nº pday set up 0.16
1:5Cement & sand morta 100.91 x0.02m3 per frame 2.02

L 1.94 M 2.02 P 5.88 9.84

44 Ditto in existing one brickwall ditto for door size 815 x2030 mm

Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaking 1.71


Excavation Gang G.B & 10 22.53 p day / 10cu m p day Bulking 0.86
350 c.f.m - compressor 154.79 p day /5 cu m p day 11.76
= Applied factor x 0.38

Carpenter and Team 4.94 /10Nº set up 0.49


Bricklayer and Team 4.94 /30Nº pday set up 0.16
1:5Cement & sand morta 100.91 x0.02m3 per frame 2.02

L 3.23 M 2.02 P 11.76 17.01

DEMOLISHING RATES
79
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

45 Ditto in existing one brickwall ditto for door size 1615 x 2030 mm

Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaking 3.38


Excavation Gang G.B & 10 22.53 p day / 10cu m p day Bulking 1.69
350 c.f.m - compressor 154.79 p day /5 cu m p day 23.22
= Applied factor x 0.75

Carpenter and Team 4.94 /10Nº set up 0.49


Bricklayer and Team 4.94 /30Nº pday set up 0.16
1:5Cement & sand morta 100.91 x0.02m3 per frame 2.02

L 5.73 M 2.02 P 23.22 30.96

46 Remove timber door hung to existing pressed steel door frame, size
815 x2030 mm

Demolishing gang 8.91 p day /6m p day 1.48

L 1.48 P 1.48

47 Take out from half brickwall to be demolished 815 x2030 mm timber


door in and pressed steel door frame

Demolishing gang 8.91 p day /6m p day 1.48

L 1.48 P 1.48

48 Ditto from half brickwall to be demolished 1370 x2030 mm pair of


timber doors ditto

Demolishing gang 8.91 p day /6m p day 1.48

L 1.48 P 1.48

49 Ditto from half brickwall to be demolished 1615 x 2030 mm pair of


timber doors ditto
Demolishing gang 8.91 p day /6m p day 1.48

L 1.48 P 1.48

50 Ditto from one brickwall to be demolished 815 x 2030 mm pair of


timber doors ditto

Demolishing gang 8.91 p day /6m p day 1.48


L 1.48 P 1.48

DEMOLISHING RATES
80
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

51 Ditto from one brickwall to be demolished 1615 x 2030 mm pair of


timberdoors ditto

Demolishing gang 8.91 p day /5m p day 1.78

L 1.78 P 1.78

52 Take out from 345 mm brick cavity wall to be demolished


815 x2030 mm timber door ditto

Demolishing gang 8.91 p day /5m p day 1.78

L 1.78 P 1.78

53 Take out from half brick wall 815 x2030 mm timber door in and
including pressed steel door frame and prepare jambs to receive
new brickwork [elsewhere measured]

Demolishing gang 8.91 p day /5.5No p day 1.62

L 1.62 P 1.62

54 Ditto from one brickwall 815 x2030 mm timber door ditto

Demolishing gang 8.91 p day /4No p day 2.23

L 2.23 P 2.23

55 Ditto from one brickwall 1370 x2030 mm pair of timber door ditto

Demolishing gang 8.91 p day /4No p day 2.23

L 2.23 P 2.23

56 Ditto from one brickwall 1615 x 2030 mm pair of timber door ditto

Demolishing gang 8.91 p day /4No p day 2.23

L 2.23 P 2.23

57 Take out from one brickwall to be demolished steel window n.e 5m2

Demolishing gang 8.91 p day /6No p day 1.48

L 1.48 P 1.48

DEMOLISHING RATES
81
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
58 Take out from one brickwall to be demolished steel window
exceeding 5m2 but not exceeding 10 m2

Demolishing gang 8.91 p day /6No p day 1.48

L 1.48 P 1.48

59 Take out from one brickwall to be demolished steel window


not exceeding 5m2 brick up opening,and plaster to match existing

Demolishing gang 8.91 p day /6No p day 1.48

Plastering and gang 4.94 / 14 m2 pday first ct 3.53


1:5 cement morta 100.91 x.020m3pm2x1.25 25.23
Plastering and gang 4.94 / 20m2 pday first ct 2.47
Rhinoset 25kg 0.60 /14 m2 p bag including waste 0.43
Applied factor x 10
L 7.49 M 25.66 33.14

60 Take out from 230 mm thick reinforced concrete wall to be


demolished ''Chubb'' strongroom door and frame size overall
1100 x2050 mm

Demolishing gang 8.91 p day /3No p day 2.97

L 2.97 P 2.97

61 Take out from 115 mm brick wall timber door in and including pressed
steel door frame size 815 x2030 mm and set up in position
and build in new pressed steel door frame for door size 815 x 2030 mm

Demolishing gang 8.91 p day /6No p day 1.48

L 1.48 P 1.48

62 Disconnect and stop off cold water supply and waste pipework to
wash hand basin and remove basin and supporting brackets from wall

Demolishing gang 8.91 p day /6No p day 1.48

L 1.48 P 1.48

DEMOLISHING RATES
82
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
63 Take out from 115 mm brick wall timber door in and including pressed
steel door frame size 815 x2030 mm and set up in position and build up
opening within 155 mm brickwall with plaster to match existing

Demolishing gang 8.91 p day /6No p day 1.48

Plastering and gang 4.94 / 14 m2 pday first ct 3.53


1:5 cement morta - x.020m3pm2x1.25 -
Plastering and gang 4.94 / 20m2 pday first ct 2.47
Rhinoset 25kg 0.60 /14 m2 p bag including waste 0.43
Applied factor x 10
L 7.49 M 0.43 7.91

64 Remove W.C suite and remove W.C suite and cistern

Demolishing gang 8.91 p day /3No p day 2.97

L 2.97 P 2.97

65 Disconnect and stop off all water supply and soil pipework to
stainless steel urinal 700 mm long x 1250 mm high and remove
urinal and cistern

Demolishing gang 8.91 p day /2No p day 4.45

L 4.45 P 4.45

66 Excavation, removal of pipes of all types and backfilling in


150mm layers pipe trenchesup to two metres deep and compacting
to 91% Mod AASHTO for pipe up to 100mm diameter.

Demolition gang(Gang boss 22.53 /20 m3 pd (excavate) 1.13


Demolition gang(Gang boss 22.53 /25m3 pr d (backfill) 0.90
Plate compactor 63.38 pr dy x 2/55m3 pr dy 2.30
Tractor & trailer 128.79 pr dy/55m3 p dy 2.34
6.67
L 2.03 P 4.65

67 Extra over in excavating in depths exceeding 2metres for


pipes up to 100mm dia

Demolition gang(Gang boss 22.53 /50m pr dy(handling) 0.45


Plate compactor 63.38 pr dy x2/55m3 pt dy 2.30
Tractor & trailer 128.79 pr dy x2/55m3 pt dy 4.68
7.44
L 0.45 P 6.99

DEMOLISHING RATES
83
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
68 Extra over in excavating in depths exc. 2metres for pipes
exceeding up to 200mm dia. and over
Demolition gang(Gang boss 22.53 /30m pr da (handle) 0.75
Demolition gang(Gang boss 22.53 /25m3 pr dy (back fill) 0.90
Plate compactor 63.38 pr dyx2/55m2 pr dy 2.30
Tractor & trailer 128.79 pr dy/55m3 pr dy 2.34
6.30
L 1.65 P 4.65

69 Excavation , removal of manhole rings and backfilling in 150mm layers


compacting to 91% Mod AASHTO for man holes up to 1500mm diameter
for depths not exceeding 1000mm
Demolition gang(Gang boss 22.53 /20m pr da (excavate) 1.13
Demolition gang(Gang boss 22.53 /25m3 pr dy (back fill) 0.90
Plate compactor 63.38 pr dyx2/55m2 pr dy 2.30
Tractor & trailer 128.79 pr dyx2/55m3 pr dy 4.68
9.02
L 2.03 P 6.99

70 Excavation , removal of manhole rings and backfilling in 150mm layers


compacting to 91% Mod AASHTO for man holes up to 1500mm diameter
for depths not exceeding 2000mm
Demolition gang(Gang boss 22.53 /15m pr da (excavate) 1.50
Demolition gang(Gang boss 22.53 /25m3 pr dy (back fill) 0.90
Plate compactor 63.38 pr dyx2/55m2 pr dy 2.30
Tractor & trailer 128.79 pr dyx2/55m2 pr dy 4.68
L 2.40 P 6.99 9.39

DEMOLISHING RATES
84
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Riddell Qs

EXCAVATIONS

SKILLED WORKER ONE 4.72


SKILLED WORKER TWO 4.42
SKILLED WORKER THREE 4.17
SKILLED WORKER FOUR 3.88
WORKER EXEMPTED 2.84
WORKER GRADE FOUR 3.10
WORKER GRADE THREE 2.94
WORKER GRADE TWO 2.94
WORKER GRADE ONE 2.84

DATA
Excavation Gang
WX Gang Boss 2.84 p day x 9hrs x 1 25.56
WG1 Labourer 2.84 p day x 9hrs x 10 255.60
281.16
Excavation Gang
WX Gang Boss 2.84 p day x 9hrs x 1 25.56
WG1 Labourer 2.84 p day x 9hrs x 8 204.48
230.04

Tractor & Trailer 85.00 per day 85.00


Diesel 1.30 p Lt x 10Lt p day 13.00
Operator WG3 2.94 9hrs p day 26.46
124.46

Plate compactor 60.00 per day x1 60.00


Petrol 1.40 p Lt x 5Lts p day 7.00
Operator WG3 2.94 p hrx9hrs p day 26.46
93.46

Vibratory roller 65.00 p day x 1 65.00


Diesel 1.30 p lt x20ltr p hr x9 hrs spd 26.00
Operator WG3 2.94 p hrx9hrs p day 26.46
117.46

Bomag 90 Roller 85.00 p day x 1 85.00


Diesel 1.30 p lt x10ltr p day 13.00
Operator WG3 2.94 p hrx9hrs p day 26.46

124.46

EXCAVATION RATES
85
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
350 c.f.m - compressor
350 c.f.m - compressor 95.00 per day 95.00
Diesel 1.30 per ltr x 10ltrs per a day 13.00
Operator WG3 2.94 p hrx9hrs p day 26.46
134.46

350 c.f.m - compressor


350 c.f.m - compressor 95.00 per day 95.00
Diesel 1.30 per ltr x 10ltrs per a day 13.00
Operator WG3 2.94 p hrx9hrs p day 26.46
134.46

Sand cost per m3 20.00

Pit sand cost per m3 15.00

Gravel cost per m3 15.00

Decomposed granite 30.00

1 Clear site of rubbish, grass, trees etc

Excavation Gang G.B & 10 281.16 p day / 280m2 per day 1.00
L 1.00

2 Excav over site ave. 150mm for vegetable soil and deposit on site not
exceeding 100m
Excavation Gang (G.B&10) (bulking) 281.16 p day / 200 sq m per day 1.41
Excavation Gang (G.B&10) (deposit) 281.16 p day / 250 sq m per day 1.12
2.53
L 2.53

3 Excavate over site to remove vegetable soil and cart away

Excavation Gang G.B & 10 281.16 p day / 200 M2 p day bulking 1.41
Excavation Gang G.B & 10 281.16 p day / 250 m2 p day deposit 1.12
2.53

L 2.53

RATE BUILD UP

EXCAVATION RATES
86
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
4 Excavate to remove vegetable soil average depth 150mm

Excavation Gang G.B & 10 281.16 p day / 200 M2 p day bulking 1.41
Excavation Gang G.B & 10 281.16 p day / 250 m2 p day deposit 1.12
2.53

L 2.53
Excavation Gang G.B & 10 281.16 p day / 12 cu m p day 23.43
L 23.43

5 Excavate in pickable mat to reduce levels n.e 2 m deep


Excavation Gang G.B & 10 281.16 p day / 12 cu m p day 12.78 -

L 12.78

6 Excavate in pickable for ground beams n.e 2 metres deep.

Excavation Gang G.B & 10 281.16 p day / 15 cu m p day 18.74

L 18.74 18.74

7 Excavate in pickable for ground beams exc. 2 but n.e. 4mmetres deep.

Excavation Gang G.B & 10 281.16 p day / 10.50m p day 26.78

L 26.78 26.78

8 Excavate in pickable for pile caps n.e 2 metres deep.


Excavation Gang G.B & 10 281.16 p day / 12 cu m p day 23.43

L 23.43 23.43

9 Excavate back from face of ground beam n.e 300mm wide for
working space,for the erection and striking off of formwork
Excavation Gang G.B & 10 281.16 p day / 15 cu m p day excavating 18.74
Excavation Gang G.B & 10 281.16 p day / 55 cu m p day back fill 5.11
Plate compactor 93.46 p day x 2 / 55 cu m p day 3.40
27.25
L 23.86 P 3.40

10 Extra over for excavation in hard pickable material

EXCAVATION RATES
87
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
Excavation Gang G.B & 10 281.16 p day / 5 cu m p day Breaking 56.23
Excavation Gang G.B & 10 281.16 p day / 22 cu m p day Bulking {-} (12.78)
43.45
L 43.45

11 Extra over for excavation in hard rock

Excavation Gang G.B & 10 281.16 p day / 1.5 cu m p day Breaking 187.44
Excavation Gang G.B & 10 281.16 p day / 4 cu m p day Bulking 70.29
350 c.f.m - compressor {DIESEL} 134.46 p day /5cu m p day 26.89

284.62
L 257.73 P 26.89

12 Extra over all excavations for excavating in brick walls

Excavation Gang G.B & 10 281.16 p day / 5 cu m p day Breaking 56.23


Excavation Gang G.B & 10 281.16 p day / 10cu m p day Bulking 28.12
350 c.f.m - compressor {DIESEL} 134.46 p day /5 cu m p day 26.89
Excavation Gang G.B & 10 281.16 p day / 15 cu m p day [-] (18.74)

92.50
L 65.60 P 26.89

13 Extra over all excavations for excavating in unreinforced concrete

Excavation Gang G.B & 10 281.16 p day / 3 cu m p day Breaking 93.72


Excavation Gang G.B & 10 281.16 p day /10 cu m x1.3 bulk up 36.55
350 c.f.m - compressor {DIESEL} 134.46 p day /5 cu m p day 26.89
Excavation Gang G.B & 10 281.16 p day / 15 cu m p day [-] (18.74)

138.42
L 111.53 P 26.89

14 Extra over all excavations for excavating in reinforced concrete

Excavation Gang G.B & 10 281.16 p day / 2.5 cu m p day Breaking 112.46
Excavation Gang G.B & 10 281.16 p day / 5.5 cu m x1.3 bulk up 66.46
350 c.f.m - compressor {DIESEL} 134.46 p day /2.5 cu m p day 53.78
Excavation Gang G.B & 10 281.16 p day / 15 cu m p day [-] (18.74)

213.96
L 160.18 P 53.78

EXCAVATION RATES
88
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
15 Allow for risk of collapse to sides of excavation

Excavation Gang G.B & 10 281.16 p day / 10 cu m p day 1.41


Excavation Gang G.B & 10 281.16 p day / 25 cu m p day 0.56
Plate compactor 93.46 p day x 2 / 55 cu m p day 0.17
= applied Factor x 0.05 2.14
L 1.97 P 0.17

16 Re-dig from spoil heap &cart away surplus excavated mat to a


to a dump site to be located by a Contractor max distance 50KM

Excavation Gang G.B & 10 281.16 p day / 55 cu m p day load 5.11


Tractor and trailer 124.46 per day / 55 cu m p day x 1.30 Bul 2.94
8.05
L 5.11 P 2.94

17 Re-dig from spoil heap and back fill and compact around fnds
Excavation Gang G.B & 10 281.16 p day / 55 cu m p day Redig 5.11
Plate compactor 93.46 p day x 2 / 55 cu m p day 3.40
8.51
L 5.11 P 3.40

18 Re-dig from spoil heap and backfill to make up levels under floors
93% HCE density
Excavation Gang G.B & 10 281.16 p day / 75 cu m p day 3.75
Bomag Roller 124.46 p day / 75m3 p day x 2 3.32
7.07

L 3.75 P 3.32

19 Selected stable granular filling of triaxial class 3.9 under floors


compacted to 91% HCE density
Excavation Gang G.B & 10 281.16 p day / 75 cu m p day 3.75
Bomag Roller 124.46 p day / 75m3 p day x 2 3.32
Gravel 15.00 p m3 x 1.33 bulk 19.95
27.02

L 3.75 P 3.32 M 19.95

20 Selected stable granular filling of triaxial class 3.6 under 1,463.00


floors compacted to 93% HCE density
Excavation Gang G.B & 10 281.16 p day / 75 cu 202.996096391012 3.75 0.14
Bomag Roller 124.46 p day / 75m3 179.72 3.32 0.12
Gravel 15.00 p m3 x 1.33 b 1,080.28 19.95 0.74
27.02

L 3.75 P 3.32 M 19.95

EXCAVATION RATES
89
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

21 Scarify surface of insitu sub soil for a depth of 150mm and


mechanically compact to 89% MODASHTO
Excavation Gang G.B & 10 281.16 p day / 300 sq m p day 0.94
Bomag 124.46 p day x 2 No / 300 m2 p day 0.83
1.77
L 0.94 P 0.83

22 Scarify surface of insitu sud soil for a depth of 150mm and


mechanically compact to 95% MODASHTO with a vibratory roller
Excavation Gang G.B & 10 281.16 p day / 300 sq m p day 0.94
Vibratory 117.46 p day x 2 No / 800 m2 p day 0.29
1.23
L 0.94 P 0.29

23 Strike off and cure top surface of concrete


1.28
Strike off 25.56 p day/20m2 p day

L 1.28

Trimming pile average 450-600mm diameter

Excavation Gang G.B & 10 281.16 p day / 50no p day 5.62

L 5.62

Trimming pile average 625-750mm diameter

Excavation Gang G.B & 10 281.16 p day / 40 no p day 7.03

L 7.03

Trimming pile average 800 -950mm diameter

Excavation Gang G.B & 10 281.16 p day / 30 no p day 9.37

L 9.37

One layer250 micron "Tarcon" polythene DPM laid on and including


50mm sand blinding under concrete surface beds

Labourer 25.56 p hr x 9 x 2/150m2 p day 3.07


Polythene 0.250mm thick 4.80 per m2 x 1.1 waste 5.28
8.35
L 3.07 M 5.28
dpm 1.0224

EXCAVATION RATES
90
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
blinding 2.0448

EXCAVATION RATES
91
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Riddell Qs

PLASTERING & WALL LININGS

DATA
SKILLED WORKER ONE 4.72
SKILLED WORKER TWO 4.42
SKILLED WORKER THREE 4.17
SKILLED WORKER FOUR 3.88
WORKER EXEMPTED 2.84
WORKER GRADE FOUR 3.10
WORKER GRADE THREE 2.94
WORKER GRADE TWO 2.94
WORKER GRADE ONE 2.84

Plasterer and Team


Plasterer
SW1 4.72 p hr x 9 hrs x 1 4.72
SW2 4.42 p hr x 9 hrs x 2 8.84
SW3 4.17 p hr x 9 hrs x 3 12.51
SW4 3.88 p hr x 9 hrs x 3 11.64
= applied Factor / 9 37.71

Plasterer and Team (1+3)


Plasterer Rate per day 37.71
Assitant 2.84 x9 25.56
63.27

* Cement per 50kg bag 9.00


9.00

* Pit Sand 12.00


12.00
1:4 Cement and Sand mortar
Labourer 25.56 /120bags per day x8.9m3 handle 1.90
Cement 50kg 9.00 x8.9bgsx1.01 waste 80.90
River Sand 12.00 pm3x1.50m3x1.15 waste 20.70
103.50

PLASTERING RATES
92
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

1:3 Cement mortar Build up


Labourer 25.56 /120bagsx10.60 2.26
Cement 9.00 pbagx10.60x1.01waste 96.35
Sand 12.00 pm3x1.30x1.15 waste 17.94
116.55

1:6 Cement mortar Build up


Labourer 25.56 /120bagsx6.40 1.36
Cement 9.00 pbagx6.4x1.01waste 58.18
Sand 12.00 pm3x1.69x1.15 waste 23.32
82.86
1:5 Cement mortar Build up
Labourer 25.56 /120bagsx13.10 2.79
Cement 9.00 pbagx7.5x1.01waste 68.18
Sand 12.00 pm3x1.69x1.15 waste 23.32
94.29

1:2 Cement mortar Build up


Labourer 25.56 /120bagsx13.10 2.79
Cement 9.00 pbagx13.10x1.01waste 119.08
Sand 12.00 pm3x1.69x1.15 waste 23.32
145.19

MATERIALS
Rhinoset 15.00 (25kg) 0.60
Rhinobond 10.50 (25kg) 0.42
Tylon adhesive 6.00 p 20kg 0.30
Tiling Grout 5.95 p 20kg 0.30
Tile spacers(wall) 4.00 /100 p pack 0.04
Tile spacers(floor) 4.00 /100 p pack 0.04
Cemprover 17.00 /5litre 3.40

RATE BUILD UP

1 One coat wood float plaster to walls externally


Plastering and gang 63.27 / 14 m2 pday first ct 4.52
1:4 cement mortar 103.50 x.030m3pm2x1.25 3.88
8.40
L 4.52 m 3.88

2 One coat wood float plaster to walls in n. w.


Plastering and gang 63.27 / 7 m2 pday first ct 9.04
1:4 cement mortar 103.50 x.030m3pm2x1.25 3.88

12.92
L 9.04 m 3.88

PLASTERING RATES
93
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

3 One coat wood float plaster on concrete soffits

Labourer 11.43 / 15m2 p day slashing 0.76


Cement slash (1:2) 145.19 /0.005 m3 p m2 x1.25 waste 0.91
Cemprover 17.00 p 5 ltr/ 10m2 p ltr 0.34
Plastering and gang 63.27 / 14 m2 pday first ct 4.52
1:4 cement mortar 103.50 x.030m3pm2x1.25 3.88
10.41
L 5.28 m 5.13

4 One coat wood float plaster on concrete walls

Labourer 25.56 / 20m2 p day slashing 1.28


Cement slash (1:2) 145.19 /0.005 m3 p m2 x1.25 waste 0.91
Cemprover 17.00 p 5 ltr/ 10m2 p ltr 0.34
Plastering and gang 63.27 / 14 m2 pday first ct 4.52
1:4 cement mortar 103.50 x.030m3pm2x1.25 3.88
10.93
L 5.80 m 5.13

5 One coat wood float plaster on soffits of beams in narrow width

Labourer 11.43 / 7m2 p day slashing 1.63


Cement slash (1:2) 145.19 .0.005 m3 p m2 x1.25 waste 0.91
Cemprover 17.00 p 5 ltr/ 10m2 p ltr 0.34
Plastering and gang 63.27 / 8m2 pday first ct 7.91
1:4 cement mortar 103.50 x.030m3pm2x1.25 3.88
14.67
L 9.54 m 5.13

6 One coat cement plaster with steel float and set in Rhinoset internal
Plastering and gang 63.27 / 14 m2 pday first ct 4.52
1:4 cement mortar 103.50 x.030m3pm2x1.25 3.88
Plastering and gang 63.27 / 20m2 pday first ct 3.16
Rhinoset 25kg 0.60 /14 m2 p bag including waste 0.04

11.61
L 7.68 M 3.92

7 Ditto in narrow width


Plastering and gang 63.27 / 7m2 pday first ct 9.04
1:4 cement mortar 103.50 x.030m3pm2x1.25 3.88
Plastering and gang 63.27 / 10m2 pday first ct 6.33
Rhinoset 25kg 0.60 /14 m2 p bag including waste 0.04

19.29
L 15.37 M 3.92

PLASTERING RATES
94
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

8 "FIX ONLY" 150x150x6mm glazed ceramic wall tiles as described


Tiler and team 63.27 /3m2 pday 21.09
Ceramic wall tiles 10.00 /m2 x 1.05 waste 10.50
Screed gang 88.83 p day / 15 m2 p day 5.92
Screed (1:3) 121.04 p m3 x 0.010m3 per m2 x 1.15 w 1.39
Tylon adhesive 6.00 p 20kg /4x1.15 waste 1.73
Tile grout pointing 5.95 /20kgx5/10m2 p 5kgx1.15 wst 0.17
Tile spacers floor 0.04 p ea,x88 p m2/10 uses 0.35
41.15
L 27.01 M 14.14

9 Ditto in narrow width


Tiler and team 63.27 /1.5m2 pday 42.18
Ceramic wall tiles 15.00 /m2 x 1.05 waste 15.75
Screed gang 88.83 p day / 15 m2 p day 5.92
Screed (1:3) 121.04 p m3 x 0.010m3 per m2 x 1.15 w 1.39
Tylon adhesive 0.30 p 20kg /4x1.15 waste 0.09
Tile grout pointing 0.30 /20kgx5/10m2 p 5kgx1.15 wst 0.01
Tile spacers floor 0.04 p ea,x88 p m2/10 uses 0.35
65.69
L 48.10 M 17.59

10 Extra for exposed edges


Tiler and team 63.27 /15m pday 4.22
4.22
L 4.22 M 0.00

11 Cut and fit tiling around small pipes

Tiler & team (T & T) 63.27 p day / 10 no p day 6.33


Tiles 10.00 /m2x1.05x0.045x0.045x2 0.04
6.37
L 6.327 M 0.043
12 Cut and fit tiling around large pipes

Tiler & team (T & T) 63.27 p day / 7 no p day 9.04


Tiles 10.00 /m2x1.05x0.045x0.045x2 0.04
9.08
L 9.039 M 0.041
13 "FIX ONLY" Ceramic skirting as described
Tiler and team 63.27 /3m2 pday 1.58
Ceramic wall tiles 10.00 /m2 x 1.05 waste 0.79
Tylon adhesive 0.30 p 20kg /4x1.15 waste 0.01
Tile grout pointing 0.30 /20kgx5/10m2 p 5kgx1.15 wst 0.00
Tile spacers floor 0.04 p ea,x88 p m2/10 uses 0.03
Applied Factor x 0.075 2.40
L 1.58 M 0.82

PLASTERING RATES
95
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2014

B AND S MCHEKEN CONTRACTORS

BRICKWORK

DATA
SKILLED WORKER ONE 4.72
SKILLED WORKER TWO 4.42
SKILLED WORKER THREE 4.17
SKILLED WORKER FOUR 3.88
WORKER EXEMPTED 2.84
WORKER GRADE FOUR 3.10
WORKER GRADE THREE 2.94
WORKER GRADE TWO 2.94
WORKER GRADE ONE 2.84

Bricklayer and Team

SW1 4.72 p hr x 9 hrs x 1 4.72


SW2 4.42 p hr x 9 hrs x 2 8.84
SW3 4.17 p hr x 9 hrs x 3 12.51
SW4 3.88 p hr x 9 hrs x 3 11.64
= applied Factor /9 37.71

Bricklayer/Carpenter and Team

Bricklayer 37.71
Assistants 2.84 x 9 hrs per day 51.12
88.83
Material cost
* Bricks
Commons hard burnt (Price as per Beta Bricks) per thousand 200.00

200.00

Dark Rustic bricks (Price as per Beta Bricks) per thousand 300.00

300.00

Industrial bricks (Price as per Beta Bricks) per thousand 270.00

* Blocks 270.00

Concrete Hollow Blocks 9inch ( Price as per Precast Concrete)-each 4.03


Size (450x230x230mm)
4.03

BRICKWORK RATES
96
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2014

Concrete Hollow Blocks 6inch ( Price as per Precast Concrete) 1.71


Size (450x230x150mm)
1.71

Concrete Hollow Blocks 41/2inch ( Price as per Precast Concrete) 1.21


Size (450x230x110mm)
1.21

* Cement per 50kg bag (transport included) 9.00


9.00

* Pit Sand 25.00


25.00

1:4 Cement and Sand morta 37.72


Labourer 51.12 /120bags per day x8.9m3 han 1.36 3.79 0.04
OPC Cement bagged 50kg 9.00 x8.9bgsx1.01 waste 28.95 80.90 0.77
Pit Sand 12.00 pm3x1.50m3x1.15 w 7.41 20.70 0.20
105.39
1:3 Cement and Sand morta
Labourer 51.12 /120bags per day x10.6m3 handle 4.52
OPC Cement bagged 50kg 9.00 x10.6bgsx1.01 waste 96.35
Pit Sand 12.00 pm3x1.30m3x1.15 waste 17.94
118.81
One brick by two bricks pier attached
Bricklayer and Team 88.83 /350bricks pdayx50bricks pm 12.69
Commons 200.00 /1000x50bricks pmx1.05 waste 10.50
1:4 Cement & sand morta 105.39 x0.025m3/m2x1.15waste 3.03
26.22
L 12.69 M 13.53
47.93
1:5 Cement and Sand morta
Labourer 51.12 /120bags per day x10.6m3 ha 2.14 4.52 0.04
OPC Cement bagged 50kg 9.00 x7.8bgsx1.01 waste 33.68 70.90 0.70
Pit Sand 13.60 pm3x1.63m3x1.15 w 12.11 25.49 0.25
100.91

326.89
1:1 Cement and Sand morta
Labourer 51.12 /120bags per day x10.6m3 ha 6.32 4.52 0.02
OPC Cement bagged 50kg 9.00 x22.40bgsx1.01 wast 284.90 203.62 0.87
Pit Sand 13.60 pm3x1.63m3x1.15 w 35.67 25.49 0.11
233.62

BRICKWORK RATES
97
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2014

Foundations

1 One brick wall in industrial brickwork


Bricklayer and Team 88.83 /325bricks pdayx105bricks pm2 28.70
Industrial bricks 270.00 /1000x105bricks pm2x1.05 waste 29.77
1:4 Cement & sand mort 105.39 x0.05m3/m2x1.15waste 6.06
64.53

L 28.70 M 35.83

2 Half brick wall in industrial brickwork


Bricklayer and Team 88.83 /325bricks pdayx55bricks pm2 15.03
Industrial bricks 270.00 /1000x53bricks pm2x1.05 waste 15.03
1:4 Cement & sand mort 105.39 x0.025m3/m2x1.15waste 3.03
33.09
L 15.03 M 18.06

3 One brick wall curved on plan to quick sweep in industrial brickwork


Bricklayer and Team 88.83 /300bricks pdayx105bricks pm2 31.09
Industrial bricks 270.00 /1000x105bricks pm2x1.05 waste 29.77
1:4 Cement & sand mort 105.39 x0.05m3/m2x1.15waste 6.06
66.92

L 31.09 M 35.83

4 Rough splay cutting and waste to brickwork


Bricklayer and Team 88.83 / 20m p day 4.44
Loadbearing 270.00 /1000x20bricks pm x1.05 waste 5.67
1:4 Cement & sand mort 105.39 x0.0005m3/mx1.15waste 0.06

10.17
L 4.44 M 5.73

5 230mm blockwork in concrete hollow blocks (9 inch)


Bricklayer and Team 88.83 /150blocks pdayx10blocks pm2 5.92
450x230x230mm blocks 4.03 eax10blocks pm2x1.05 waste 42.32
1:4 Cement & sand mort 105.39 x0.054m3/m2x1.15waste 6.54
54.78

L 5.92 M 48.86

6 230mm blockwork in concrete hollow blocks (6 inch)


Bricklayer and Team 88.83 /150blocks pdayx15blocks pm2 8.88
450x230x150mm blocks 1.71 eax15blocks pm2x1.05 waste 26.93
1:4 Cement & sand mort 105.39 x0.03m3/m2x1.15waste 3.64
39.45

L 8.88 M 30.57

BRICKWORK RATES
98
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2014

7 230mm blockwork in concrete hollow blocks (41/2 inch)


Bricklayer and Team 88.83 /150blocks pdayx20blocks pm2 11.84
450x230x110mm blocks 1.21 eax20blocks pm2x1.05 waste 25.41
1:4 Cement & sand mort 105.39 x0.023m3/m2x1.15waste 2.79
40.04

L 11.84 M 28.20

8 105mm Brickforce to suit 230mm brick wall


Brick Layer and team 88.83 /500m pday 0.18
105/150mm Brickforce 2.83 proll /19m per rollx1.10 waste 0.16
0.34
L 0.18 M 0.16

9 150mm Brickforce to suit 230mm brick wall to quick sweep


Brick Layer and team 88.83 /400m pday 0.22
105/150mm Brickforce 2.83 proll /19m per rollx1.10 waste 0.16
0.39
L 0.22 M 0.16

10 10mm Kaylite joint filler material in expansion joints as described

Carpenter & team (C & 1) 88.83 p day/ 12 m2 p day 7.40


10mm Kaylite 2.08 p sq m x1.15 wst 2.39
9.79
L 7.40 M 2.39

11 Two layers of Rubber roid bitumen DPC vertically btwn walls


Brick layer and Team 88.83 /70m2pday 1.27
"Ruberoid" DPC 7.60 /20x0.23/m2x2x1.10 waste 3.63
4.90
L 1.27 M 3.63

12 Galvanised hoop iron ties 25mm wide 700mm long as described


Bricklayer and Team 88.83 /60 p dy fix 1.48
Hoop iron 25x700mm lo 0.35 x 1.15waste 0.40
1.88
L 1.48 M 0.40

13 Leave or form mortice in concrete for box of floor spring & grout
Bricklayer and Team 88.83 /10 no p day 8.88
Grouting(1:1) 233.62 x 0.020 x1.15 waste 5.37
14.26
L 8.883 M 5.373

14 Take delivery and cast in H.D. boults

Bricklayer and Team 88.83 /15 no p day 5.92

5.92
L 5.92

BRICKWORK RATES
99
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2014

Superstructure

15 Half brick wall in common brickwork


Bricklayer and Team 88.83 /350bricks pdayx53bricks pm2 13.45
Common bricks 200.00 /1000x53bricks pm2x1.05 waste 11.13
1:4 Cement & sand mort 105.39 x0.028m3/m2x1.15waste 3.39
27.98
L 13.45 M 14.52

16 Half brick wall curved on plan in commom brickwork


Bricklayer and Team 88.83 /300bricks pdayx53bricks pm2 15.69
Common bricks 200.00 /1000x53bricks pm2x1.05 waste 11.13
1:4 Cement & sand mort 105.39 x0.028m3/m2x1.15waste 3.39
30.22
L 15.69 M 14.52

17 One brick wall in common brickwork


Bricklayer and Team 88.83 /380bricks pdayx105bricks pm2 24.55
Commons 200.00 /1000x105bricks pm2x1.05 waste 22.05
1:4 Cement & sand mort 105.39 x0.05m3/m2x1.15waste 6.06
52.66

L 24.55 M 28.11

18 One & half brick wall in common brickwork


Bricklayer and Team 88.83 /400bricks pdayx105bricks pm2 23.32
Commons 200.00 /1000x158bricks pm2x1.05 waste 33.18
1:4 Cement & sand mort 105.39 x0.09m3/m2x1.15waste 10.91
67.41
L 23.32 M 44.09

19 Half brick wall in Dark Rustic face brickwork


Bricklayer and Team 88.83 /300bricks pdayx53bricks pm2 15.69
Face bricks 300.00 /1000x53bricks pm2x1.05 waste 16.70
1:4 Cement & sand mort 105.39 x0.028m3/m2x1.15waste 3.39
35.78
L 15.69 M 20.09

BRICKWORK RATES
100
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2014

1,224.49
20 Half brick wall curved on plan in Dark Rustic face brickwork
Bricklayer and Team 88.83 /250bricks pdayx53bricks pm2 18.83
Face bricks 300.00 /1000x53bricks pm2x1.05 waste 16.70
1:4 Cement & sand mort 105.39 x0.028m3/m2x1.15waste 3.39
38.92
L 18.83 M 20.09
2,429.43
21 One brick wall in Dark Rustic face brickwork
Bricklayer and Team 88.83 /325bricks pdayx105bricks pm2 28.70
Face bricks 300.00 /1000x105bricks pm2x1.05 waste 33.08
1:4 Cement & sand mort 105.39 x0.05m3/m2x1.15waste 6.06
67.83

L 28.70 M 39.14

22 One & half brick wall in Dark Rustic face brickwork


Bricklayer and Team 88.83 /400bricks pdayx105bricks pm2 23.32
Facebricks 300.00 /1000x158bricks pm2x1.05 waste 49.77
1:4 Cement & sand mort 105.39 x0.09m3/m2x1.15waste 10.91
84.00
L 23.32 M 60.68

23 230mm blockwork in concrete hollow blocks (9 inch)


Bricklayer and Team 88.83 /120blocks pdayx10blocks pm2 7.40
450x230x230mm blocks 4.03 eax10blocks pm2x1.05 waste 42.32
1:4 Cement & sand mort 105.39 x0.05m3/m2x1.15waste 0.61
50.32

L 7.40 M 42.92

24 230mm blockwork in concrete hollow blocks (6 inch)


Bricklayer and Team 88.83 /120blocks pdayx15blocks pm2 11.10
450x230x150mm blocks 1.71 eax15blocks pm2x1.05 waste 26.93
1:4 Cement & sand mort 105.39 x0.03m3/m2x1.15waste 3.64
41.67

L 11.10 M 30.57

25 230mm blockwork in concrete hollow blocks (41/2 inch)


Bricklayer and Team 88.83 /120blocks pdayx20blocks pm2 14.81
450x230x110mm blocks 1.29 eax20blocks pm2x1.05 waste 27.09
1:4 Cement & sand mort 105.39 x0.023m3/m2x1.15waste 2.79
44.68

L 14.81 M 29.88

BRICKWORK RATES
101
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2014

26 Rough raking cutting on brickwork


Bricklayer and Team 88.83 / 20m p day 19.32
Commons 200.00 /1000x20bricks pm x1.05 waste 18.27
1:4 Cement & sand mort 105.39 x0.0005m3/mx1.15waste 0.26
Applied Factor x 4.35
37.85
L 19.32 M 18.53

27 25mm Cement grout under base plate 415.77

Bricklayer and Team 88.83 /15 m2 p day 5.92


Grouting(1:1) 233.62 x 0.025 x1.15 waste 6.72
12.64
L 5.92 M 6.72

28 Rough cutting squint and bird mouth angle


Bricklayer assistant 51.12 / 15m2 pday 3.41
Commons 200.00 /1000x20bricks pm2x1.05 waste 0.97
=Applied factor x 0.23 4.37
L 3.41 M 0.97
18.65
29 75mm Brickforce to suit 115mm brick wall
Brick Layer and team 88.83 /500m pday 0.18
75mm Brickforce 2.83 proll /19m per rollx1.10 waste 0.16
0.34
L 0.18 M 0.16

30 75mm Brickforce to suit 115mm brick wall curved on plan


Brick Layer and team 88.83 /400m pday 0.22
75mm Brickforce 2.83 proll /19m per rollx1.10 waste 0.16
0.39
L 0.22 M 0.16

31 Set up in position cross brase & bldng in steel window frame/ door frame n.e
5m2.
Carpenter and Team 88.83 /10Nº set up 8.88
Bricklayer and Team 88.83 /30Nº pday set up 2.96
1:4 Cement & sand morta 105.39 x0.02m3 per frame 2.11
13.95
L 11.84 M 2.11

32 Cut 25x25mm horizontal groove in b/work for turn up on asphalt

Bricklayer and Team 88.83 /25m p day 3.55

L 3.55

BRICKWORK RATES
102
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2014

1,177.07
33 Set up in position cross brase & bldng in steel window/ door frame ex
c 25m2 & n.e 30m2.
Carpenter and Team 88.83 /8Nº set up 11.10
Bricklayer and Team 88.83 /20Nº pday set up 4.44
1:4 Cement & sand morta 105.39 x0.025m3 per frame ? 2.63
18.18
L 15.55 M 2.63

34 Set up in position cross brase & bldng in steel window/ door frame
exc 70m2 & n.e 75m2.
Carpenter and Team 88.83 /4Nº set up 22.21
Bricklayer and Team 88.83 /6Nº pday set up 14.81
1:4 Cement & sand morta 105.39 x0.03125m3 per frame ? 3.29
40.31
L 37.01 M 3.29

35 One layer of three ply DPC as described


Brick layer and Team 88.83 /70m2pday 1.27
"Ruberoid" DPC 7.60 /20x0.23/m2x1.10 waste 1.82
3.09
L 1.27 M 1.82

BRICKWORK RATES
103
B AND S MCHEKEN CONTRACTORS
ESTIMATING DATA:
RATE BUILD UP
2012
Riddell Qs

CONCRETE RATES

1.PLANT
DATA
A. Concrete volume per day 15.00 m3
B. Mixer (14/10 Electrical) & Weigh batcher Hire Rate per day 120.00
C. Diesel price per litre 1.30
D. Oil price per litre 5.00
E. Diesel used per day 5.00 Litres
F. Oil used per month 5.00 Litres

COST
Mixer & Weigh batcher Hire 120.00 x 1 120.00
Diesel 1.30 p Ltr x 20 Ltrs p day 6.50
Oil 5.00 p Ltr x 5 Ltrs p day/22 1.14
Total cost 127.64

Unit Allow 127.64 p day /15 cu m p day 8.51

2.WAGES
DATA
A. Concrete Volume per day 15.00 m3
B. WG1 Rate per day 2.84 p hr x 9 hrs p day 25.56
C. WG3 Rate per day 2.94 p hr x 9 hrs p day 26.46
D. WG4 Rate per day 2.84 p hr x 9 hrs p day 25.56

* Total Volume of Concrete Approximately >>>>> 15 m3 p day

Generations
104
ESTIMATING DATA:
RATE BUILD UP
2012
WG.1
2Nº on stone
2Nº on sand
2Nº on cement
5Nº on wheel barrows
5Nº on placing
1Nº on curing
17 Nº TOTAL

WG. 3
1Nº Mixer operator (In P & G)
1Nº Vibrator operator
2Nº Screeder
4 Nº TOTAL

WG. 4
1Nº Gang Boss
1 Nº TOTAL

3. LABOUR COST
WG1 2.84 p day x 17 434.52
WG3 2.94 p day x 4 105.84
WG4 2.84 x 1 25.56
Total Cost 565.92
Unit Allow 565.92 / 15 cu m p day 37.73

Generations
105
ESTIMATING DATA:
RATE BUILD UP
2012
4. CEMENT
DATA
A. WG1 Rate per hour 2.84
B Price ( including transport per bag) 10.00
COST
Cement 10.00 p bg x 1 10.00
Loading
Offloading
Total cost 10.00
Add waste 1% 10.00 x 1.01 waste 10.10

5. STONE
DATA
A. WG1 Rate per hour 2.84
B. Price ex works per m3 25.00

COST
Stone (Including Transport and Loading) 25.00 per m3 25.00
Total Cost 25.00

6. RIVER SAND
DATA
A. WG1 Rate per hour 2.84
B. Price ex works per m3 15.00

Generations
106
ESTIMATING DATA:
RATE BUILD UP
2012
COST
Sand (Including transport) 15.00 per m3 15.00
Loading -
Offloading -
Total cost 15.00

7.VIBRATION
DATA
A 48mm Poker 46.00
B. 63mm Poker 46.00
C. Petrol Vibrator 46.00
D. Petrol price per litre 1.45
E, Petrol used per day 5.00 Litre
F. Concrete volume per day 15.00 m3
COST
Pokers 46.00 0.07
Vibrator 46.00 0.07
Petrol 1.45 p Lt x 2Lts pdy / 20 cu m pdy 0.48
Total Cost 0.63

Generations
107
ESTIMATING DATA:
RATE BUILD UP
2012
T N ZUNZANYIKA ASSOCIATES
NET RATES
GRADE OF CONCRETE
RESOURCE WASTAGE GRADE GRADE GRADE GRADE GRADE GRADE GRADE GRADE
40 30 25 20 15 15 blinding 10 mass 10 blinding
1.PLANT 1.00 8.51 8.51 8.51 8.51 8.51 8.51 8.51 8.51

2.WAGES 1.00 37.73 37.73 37.73 37.73 37.73 37.73 37.73 37.73

3.CEMENT 1.10 106.66 95.32 84.44 71.77 59.11 59.11 46.44 46.44

4.STONE 1.075 23.11 20.99 20.99 20.99 20.53 20.53 20.99 20.99

5.SAND 1.20 10.44 10.76 11.52 12.17 12.08 12.08 13.50 13.50

6.WASTAGE
ON MAT 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10

7.VIBRATION 1.00 0.63 0.63 0.63 0.63 0.63 - 0.63 -


`
TOTAL COST 187.18 174.05 163.91 151.90 138.68 138.05 127.90 127.27

Generations
108
ESTIMATING DATA:
RATE BUILD UP
2012
UNIT ALLOWABLES
GRADE OF CONCRETE =APPLD FCTRx0.075x1.10 =APPLD FCTRx0.05x1.10
RESOURCE GRADE GRADE GRADE GRADE GRADE GRADE GRADE GRADE
40 30 25.00 20.00 15 15 blinding 10 mass 10 blinding
1.PLANT 9.14 9.14 9.14 9.14 8.51 0.75 9.14 0.47

2.LABOUR 37.73 37.73 37.73 37.73 37.73 3.11 37.73 2.08

3.MATERIAL 140.21 127.08 122.79 104.93 91.72 7.57 80.93 4.46

4.FORMWORK - - - 8.00 - - - -

5.SUBS - - - - - - - -

TOTAL COST 187.08 173.95 169.66 159.80 137.95 11.43 127.80 7.00
6252.13 5653.36 4648.08 232.40

54.87
6877.343 - - 0 0 5112.888 255.64

479,981.25
115,500.00
1,295,481.25
1,489,803.44

Generations
109
ESTIMATING DATA:
RATE BUILD UP
2012

Generations
110
ESTIMATING DATA:
RATE BUILD UP
2012
Riddell Qs

REINFORCEMENT

DATA
SKILLED WORKER ONE 4.72
SKILLED WORKER TWO 4.42
SKILLED WORKER THREE 4.17
SKILLED WORKER FOUR 3.88
WORKER EXEMPTED 3.88
WORKER GRADE FOUR 3.10
WORKER GRADE THREE 2.94
WORKER GRADE TWO 2.94
WORKER GRADE ONE 2.84

Steel Fixer and Team


Steel Fixer
SW 4.72 p hr x 9 hrs x 1 4.72
SW 4.42 p hr x 9 hrs x 2 8.84
SW 4.17 p hr x 9 hrs x 3 12.51
SW 3.88 p hr x 9 hrs x 3 11.64
= applied Factor / 9 37.71

Steel Fixer & Team


(Steel Fixing Gang)
Steel Fixers 37.71 pdx4 150.84
Assistants 2.84 p hr x9 hrs p day x 8 nº 204.48
355.32

Steel handling team (GB&10)


Steel handling team 37.71 p day x 1 37.71
Assistants 2.84 p hr x9 hrs p day x 10 255.60
293.31
MATERIALS

* Mild steel rods exc 12mm diameter n.e 30mm diameter 950.00 p ton
* Mild steel rods exc 8mm diameter n.e 30mm diameter 950.00 p ton
* Mild steel rods not exc 8mm diameter 950.00 p ton
* High yield deformed bars exc 12mm diameter but n.e exc 30mm diameter 950.00 p ton
* High yield deformed bars exc 8mm diameter but n.e exc 12mm diameter 950.00 p ton
* High yield deformed bars exc 30 mm diameter 950.00 p ton
* High yield deformed bars exc 6mm diameter but n.e exc 8mm diameter 950.00 p ton
* Fabric reinforcement; Ref. S193 42.55 p m2
* 1.6mm Bailing wire 2,000.00 p ton
* Fabric reinforcement; Ref. S245 54.05 p m2

REBAR RATES
111
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
RATE BUILD UP

REBAR RATES
112
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
1 Mild steel rod exceeding 12mm diameter & n.e 30mm diameter 47.47

Steel hangling team (GB&10) 293.31 p day / 15 tons p day 0.83 0.02 0.02
Steel Fixers & Team(4&8) 355.32 p day /3.15 tons p da 4.76 0.11 0.10
Reinforcement 950.00 p ton x 1 40.11 0.95 0.84
1.6mm Bailing wire 2,000.00 p ton x 0.02 x 1.05 1.77 0.04 0.04
=APPLIED FACTOR / 1000 in a ton 1.12
L 0.13 M 0.99

2 Mild steel rods exceeding 8mm and not exc 12mm diameter

Steel hangling team (GB&10) 293.31 p day / 15 tons p day 0.02


Steel Fixers & Team(4&8) 355.32 p day /3.15 tons p day 0.11
Reinforcement 950.00 p ton x 1 0.95
1.6mm Bailing wire 2,000.00 p ton x 0.02 x 1.05 0.04
=APPLIED FACTOR / 1000 in a ton 1.12
L 0.13 M 0.99

3 Mild steel rods not exceeding 8mm diameter

Steel hangling team (GB&10) 293.31 p day / 15 tons p day 0.02


Steel Fixers & Team(4&8) 355.32 p day /3.15 tons p day 0.11
Reinforcement 950.00 p ton x 1 0.95
1.6mm Bailing wire 2,000.00 p ton x 0.02 x 1.05 0.04
=APPLIED FACTOR / 1000 in a ton 1.12
L 0.13 M 0.99

4 High yeild deformed bars exceeding 12mm n.e. 30mm diameter

Steel hangling team (GB&10) 293.31 p day / 15 tons p day 0.02


Steel Fixers & Team(4&8) 355.32 p day /3.15 tons p day 0.11
Reinforcement 950.00 p ton x 1 0.95
1.6mm Bailing wire 2,000.00 p ton x 0.02 x 1.05 0.04
=APPLIED FACTOR / 1000 in a ton 1.12
L 0.13 M 0.99

5 High yeild deformed bars exceeding 8mm n.e. 12mm diameter

Steel hangling team (GB&10) 293.31 p day / 15 tons p day 0.02


Steel Fixers & Team(4&8) 355.32 p day /3.15 tons p day 0.11
Reinforcement 950.00 p ton x 1 0.95
1.6mm Bailing wire 2,000.00 p ton x 0.02 x 1.05 0.04
=APPLIED FACTOR / 1000 in a ton 1.12
L 0.13 M 0.99

REBAR RATES
113
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
6 High yeild deformed bars exceeding 30mm diameter

Steel hangling team (GB&10) 293.31 p day / 15 tons p day 0.02


Steel Fixers & Team(4&8) 355.32 p day /3.15 tons p day 0.11
Reinforcement 950.00 p ton x 1 0.95
1.6mm Bailing wire 2,000.00 p ton x 0.02 x 1.05 0.04
=APPLIED FACTOR / 1000 in a ton 1.12
L 0.13 M 0.99

7 Fabric reinforcement; Ref. S193

Steel hangling team (GB&10) 293.31 p day / 250m2 p day 1.17


Mesh reinforcement S193 3.38 p m2x1.20 waste & laps 4.06
5.23
L 1.17 M 4.06

8 Fabric reinforcement; Ref. S245

Steel hangling team (GB&10) 293.31 p day / 250m2 p day 1.17


Mesh reinforcement S245 4.41 p m2x1.20 waste & laps 5.29
6.47
L 1.17 M 5.29

9 Fabric reinforcement; Ref. S617

Steel hangling team (GB&10) 293.31 p day / 250m2 p day 1.17


Mesh reinforcement S617 11.75 p m2x1.20 waste & laps 14.10
15.27
L 1.17 M 14.10
573.60
10 Precast concrete lintel to opening size 110 x 150mm(Double dephth prestressed)
Bricklayer a 88.83 /50 m p day fix 54.71 1.78 0.10
Lintel 14.45 per metre x 1.01 waste 449.47 14.59 0.78
16mm rod 950.00 p t x 0.001577 t p m x 1.10 wst 50.75 1.65 0.09
1:4 Cement 105.39 x0.005m3/m2x1.15waste 18.66 0.61 0.03

L 1.78 M 16.85 18.63

11 Precast concrete lintel to opening size 110 x 150mm (Double dephth steel reinforced)
Bricklayer and Team 88.83 /50 m p day fix 1.78
Lintel 36.37 per metre x 1.01 wast 36.73
16mm rod 950.00 p t x 0.001577 t p m x 1.10 wst 1.65
1:4 Cement & sand morta 105.39 x0.005m3/m2x1.15waste 0.61

L 1.78 M 38.99 40.76

REBAR RATES
114
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012
12 Precast concrete lintel to opening size 150 x 2490 x 230 mm high ( cast on site)
Bricklayer a 88.83 /50 m p day fix 1.78
Lintel 53.21 p each x 1.01 waste 53.74
16mm rod 950.00 p t x 0.001577 t p m x 1.10 wst 1.65
1:4 Cement 105.39 x0.005m3/m2x1.15waste 0.61

L 1.78 M 56.00 57.77

REBAR RATES
115
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

REBAR RATES
116
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Riddell Qs

JOINERY & IRON MONGERY

DATA
SKILLED WORKER ONE 4.72
SKILLED WORKER TWO 4.42
SKILLED WORKER THREE 4.17
SKILLED WORKER FOUR 3.88
WORKER EXEMPTED 2.84
WORKER GRADE FOUR 3.10
WORKER GRADE THREE 2.94
WORKER GRADE TWO 2.94
WORKER GRADE ONE 2.84

Carpentry Team
Carpenter
SW1 4.72 p hr x 9 hrs x 1 4.72
SW2 4.42 p hr x 9 hrs x 2 8.84
SW3 4.17 p hr x 9 hrs x 3 12.51
SW4 3.88 p hr x 9 hrs x 3 11.64
= applied Factor / 9 37.71

Carpenter &Team (C + 1)
Carpenter 37.71 per day 37.71
Assistant 2.94 x 9 hrs per day 26.46
64.17

Carpenter &Team (C + 2)
Carpenter 37.71 per day 37.71
Assistants 2.84 x 9 hrs per day x 2 No 51.12
88.83

RATE BUILD UP

1 44mm Semi-solid internal quality flush doors to receive paint

Size 762 x 2030 mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 95.00 each 95.00
40mm wood screw 0.24 eachx8nº x1.05 2.02
. 122.68
L 25.67 m 97.02

JOINERY IRON MONGERY RATES


117
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

2 Size 813x 2032 mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 132.56 each 132.56
40mm wood screw 0.24 eachx8nº x1.05 2.02
. 160.24
L 25.67 m 134.58

3 Size 900 x 2100mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 95.00 each 95.00
40mm wood screw 0.24 eachx8nº x1.05 2.02
. 122.68
L 25.67 m 97.02

4 Size 1219 x 2125 mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 130.00 each 130.00
40mm wood csrews 0.24 eachx16nº x1.05 4.03
. 159.70
L 25.67 m 134.03

5 Size 1600x 2032mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 269.00 each 269.00
40mm wood csrews 0.24 eachx16nº x1.05 4.03
. 298.70
L 25.67 m 273.03

6 44mm Semi-solid core flush external quality doors to receive paint

Size 762 x 2030 mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 161.50 each 161.50
40mm wood screw 0.24 eachx8nº x1.05 2.02
. 189.18
L 25.67 m 163.52

7 Size 813x 1850 mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 126.00 each 126.00
40mm wood screw 0.24 eachx8nº x1.05 2.02
. 153.68
L 25.67 m 128.02

8 Size 813x 2030 mm


Carpenter and team 64.17 / 2.5 No per day 25.67

JOINERY IRON MONGERY RATES


118
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Door 178.50 each 178.50


40mm wood screw 0.24 eachx8nº x1.05 2.02

JOINERY IRON MONGERY RATES


119
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

. 206.18
L 25.67 m 180.52

9 Size 813x 2032 mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 178.50 each 178.50
40mm wood screw 0.24 eachx8nº x1.05 2.02
. 206.18
L 25.67 m 180.52

10 Size 900 x2100 mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 199.75 each 199.75
40mm wood screw 0.24 eachx8nº x1.05 2.02
. 227.43
L 25.67 m 201.77

11 Size 1600x 2032mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 341.00 each 341.00
40mm wood screw 0.24 eachx16nº x1.05 4.03
. 370.70
L 25.67 m 345.03

12 44mm internal quality built-in cupboard doors to receive paint

Size 1675 x 495mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 51.00 each 51.00
40mm wood screw 0.24 eachx16nº x1.05 4.03
. 80.70
L 25.67 m 55.03

13 44mm internal quality built-in cupboard doors to receive paint

Size 1675 x 2030mm


Carpenter and team 64.17 / 2.5 No per day 25.67
Door 136.00 each 136.00
40mm wood screw 0.24 eachx16nº x1.05 4.03
. 165.70
L 25.67 m 140.03

14 Union CZ 8094 indicactor bolt


Carpenter and team 64.17 / 12No per day 5.35
Ironmongery 17.60 eachx 1.01waste 17.78
23.12

JOINERY IRON MONGERY RATES


120
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 5.35 M 17.78

JOINERY IRON MONGERY RATES


121
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

15 Union No 5538-4-150 Aluminium pull handle


Carpenter and team 64.17 / 12No per day 5.35
Ironmongery 11.55 eachx 1.01waste 11.67
17.01
L 5.35 M 11.67

16 Union two lever lockset


Carpenter and team 64.17 / 12No per day 5.35
Ironmongery 18.00 eachx 1.01waste 18.18
23.53
L 5.35 M 18.18

17 Union three lever lockset


Carpenter and team 64.17 / 5 No per day 12.83
Ironmongery 20.00 eachx 1.01 waste 20.20
33.03
L 12.83 m 20.20

18 Flushbolts
Carpenter and team 64.17 / 5 No per day 12.83
Ironmongery 21.67 eachx 1.01 waste 21.89
34.72
L 12.83 m 21.89

19 Union aluminium pull handle


Carpenter and team 64.17 / 10 No per day 6.42
Ironmongery 11.55 eachx 1.01 waste 11.67
18.08
L 6.42 m 11.67

20 Union aluminium Dove pull handle (back to back)


Carpenter and team 64.17 / 10 No per day 6.42
Ironmongery 24.20 eachx 1.01 waste 24.44
30.86
L 6.42 m 24.44

21 Union nº 5562 aluminium escutcheon


Carpenter and team 64.17 / 5 No per day 12.83
Ironmongery 2.75 eachx 1.01 waste 2.78
15.61
L 12.83 m 2.78

22 Over head door closer union 7772


Carpenter and team 64.17 / 4 No per day 16.04
Ironmongery 92.40 eachx 1.01 waste 93.32

JOINERY IRON MONGERY RATES


122
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

109.37
L 16.04 m 93.32

JOINERY IRON MONGERY RATES


123
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

23 Over head door closer union 7836


Carpenter and team 64.17 / 4 No per day 16.04
Ironmongery 183.70 eachx 1.01 waste 185.54
201.58
L 16.04 m 185.54

24 Union Nº 8074 silver anodised rubber buffer hat & coat hook
Carpenter and team 64.17 / 7No per day 9.17
Ironmongery 4.68 eachx 1.01 waste 4.73
13.89
L 9.17 M 4.73

25 Union 8005SS hat & coat hook


Carpenter and team 64.17 / 7No per day 9.17
Ironmongery 7.15 eachx 1.01 waste 7.22
16.39
L 9.17 M 7.22

26 Union99200CH Door Viewer


Carpenter and team 64.17 / 7No per day 9.17
Ironmongery 14.30 eachx 1.01 waste 14.44
23.61
L 9.17 M 14.44

27 Aluminium kick plate (size 150 x 880mm)


Carpenter and team 64.17 / 7No per day 9.17
Ironmongery 27.50 eachx 1.01 waste 27.78
36.94
L 9.17 M 27.78

28 Aluminium push plates


Carpenter and team 64.17 / 10No per day 6.42
Ironmongery 9.63 eachx 1.01 waste 9.73
16.14
L 6.42 M 9.73

29 RFID Generic Key Cards


Carpenter and team 64.17 / 10No per day 6.42
Ironmongery 1.50 eachx 1.01 waste 1.52
7.93
L 6.42 M 1.52

JOINERY IRON MONGERY RATES


124
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

30 Rubber door stops


Carpenter and team 64.17 / 10 No per day 6.42
Ironmongery 3.85 eachx 1.05 waste 4.04
10.46
L 6.42 m 4.04

31 Union No AL8021 75X150MM Male / Female symbol screwed to


doors
Carpenter and team 64.17 / 12 No per day 5.35
Signage 16.50 eachx 1.05 waste 17.33
22.67
L 5.35 m 17.33

32 Union international disabled sign


Carpenter and team 64.17 / 12 No per day 5.35
Signage 16.50 eachx 1.05 waste 17.33
22.67
L 5.35 m 17.33

33 Union SS50066E -06SSE14 Paraplegic Pictogram


Carpenter and team 64.17 / 12 No per day 5.35
Signage 16.50 eachx 1.05 waste 17.33
22.67
L 5.35 m 17.33

34 Union SS50066E -06SSE15 Fire Escape Pictogram


Carpenter and team 64.17 / 12 No per day 5.35
Signage 16.50 eachx 1.05 waste 17.33
22.67
L 5.35 m 17.33

35 Union SS50066E Stairs Pictogram


Carpenter and team 64.17 / 12 No per day 5.35
Signage 16.50 eachx 1.05 waste 17.33
22.67
L 5.35 m 17.33

36 Union SS50066E -06SSE Room Numbers engraving


Carpenter and team 64.17 / 12 No per day 5.35
Signage 13.90 eachx 1.05 waste 14.60
19.94
L 5.35 m 14.60

JOINERY IRON MONGERY RATES


125
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

37 Union SS50066E -06SSE House Keeping engraving


Carpenter and team 64.17 / 12 No per day 5.35
Signage 58.80 eachx 1.05 waste 61.74
67.09
L 5.35 m 61.74

38 Union SS50066E -06SSE Conference Room engraving


Carpenter and team 64.17 / 12 No per day 5.35
Signage 71.20 eachx 1.05 waste 74.76
80.11
L 5.35 m 74.76

39 Union SS50066E -06SSE Cashier engraving


Carpenter and team 64.17 / 12 No per day 5.35
Signage 35.60 eachx 1.05 waste 37.38
42.73
L 5.35 m 37.38

40 Union SS50066E -06SSE CCTV Room engraving


Carpenter and team 64.17 / 12 No per day 5.35
Signage 38.90 eachx 1.05 waste 40.85
46.19
L 5.35 m 40.85

41 Union SS5506E -06SSE08 Directional Pictogram


Carpenter and team 64.17 / 12 No per day 5.35
Signage 16.50 eachx 1.05 waste 17.33
22.67
L 5.35 m 17.33

42 Hinges
Carpenter and team 64.17 / 10No per day 6.42
Ironmongery 8.93 eachx 1.01 waste 9.02
15.44
L 6.42 M 9.02

JOINERY IRON MONGERY RATES


126
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Riddell Qs

SCREEDS

DATA
SKILLED WORKER ONE
SKILLED WORKER TWO
SKILLED WORKER THREE
SKILLED WORKER FOUR
WORKER EXEMPTED
WORKER GRADE FOUR
WORKER GRADE THREE
WORKER GRADE TWO
WORKER GRADE ONE

Cement per 50kg bag

River Sand

Pit Sand

Plastering Team
Plasterer
SW1 4.72 p hr x 9 hrs x 1
SW2 4.42 p hr x 9 hrs x 2
SW3 4.17 p hr x 9 hrs x 3
SW4 3.88 p hr x 9 hrs x 3
= applied Factor /9

Plasterer & Team

Plasterer & Team (P & 1) - (Tiler Gang)


Assitant 2.84 p hr x9 hrs p day

OR

Plasterer & Team (P & 2) - (Screed Gang)


Assitant 2.84 p hr x9 hrs p day x 2

SCREED (1:2)

Labourer 25.56 p day / 120 bgs p d x 7.50 bg p m3 Handl


Cement 9.00 p bg x 7.50 bgs x 1.01 waste

SCREED RATES
127
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Sand 15.00 p m3 x 1.30 m3 x 1.15 waste

SCREED RATES
128
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

SCREED (1:3)

Labourer 25.56 p day / 120 bgs p d x 10.6 bg p m3 Handl


Cement 9.00 p bg x 10.6 bgs x 1.01 waste
Sand 15.00 p m3 x 1.30 m3 x 1.15 waste

SCREED (1:4)
Labourer 25.56 /120bags per day x8.9m3 handle
Cement 9.00 x8.9bgsx1.01 waste
Sand 15.00 pm3x1.50m3x1.15 waste

SCREED (1:5)
Labourer 25.56 /120bagsx7.8
Cement 9.00 pbagx7.8x1.01waste
Sand 15.00 pm3x1.63x1.15 waste

Grano
Labourer 25.56 p day / 120 bgs p d x 11.4 bg p m3 offloa
Cement 9.00 p bg x 11.4 bgs x 1.01 waste
Sand 15.00 p m3 x 1.30 m3 x 1.15 waste

RATE BUILD UP

1 60mm screed grading to falls on top of concrete slab


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 15 m2 p day
Screed (1:3) 121.04 p m3 x 0.060m3 per m2 x 1.15

L 6.77 M 8.35

2 Dress grading into 100mm diameter full bore


Labourer 25.56 p day / 9 p d scrabbing
Screed gang 88.83 p day /7 no p day
Screed (1:3) 121.04 p m3 x 0.050m3 per m2 x 1.15

L 15.53 M 6.96

3 35mm screed laid on concrete to receive tiles


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day

SCREED RATES
129
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Screed (1:4) 108.67 p m3 x 0.035m3 per m2 x 1.15

L 5.29 M 4.37
4 40mm granolithic paving steel trowelled to concrete floors Floors
Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p d x 0.038x 1.15 waste
Grano. 128.48 p m3 x 0.002m3 per m2 x 1.15

L 5.29 M 5.04

5 75mm High skirting with cove at junction as described.

Labourer 25.56 p day / 60m p d scrabbing


Screed gang 63.27 p day /25 m p day
Screed (1:4) 108.67 p m3 x 0.001m3 per m2 x 1.15
Grano. 128.48 p m3 x 0.00002 x 1.15waste

L 2.96 M 0.13

6 Mosaic tiles on screeds as described

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p m3 x 0.038m3 per m2 x 1.15

Tiler & team (T & T) 63.27 p day / 3 m2 p day


Mosaic tiles 55.55 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /100x88 p m2/10 uses

L 26.38 M 65.33

7 Mosaic tiles on screeds as described in n.w

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p m3 x 0.038m3 per m2 x 1.15

Tiler & team (T & T) 63.27 p day / 1.5 m2 p day


Mosaic tiles 55.55 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /100x88 p m2/10 uses

SCREED RATES
130
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 47.47 M 65.33

8 Fair pointed exposed edges

Tiler & team (T & T) 63.27 p day / 15m p day

L 4.22 M 0.00

9 Cut & Fit tiles around shower outlet

Tiler & team (T & T) 63.27 p day / 7m p day

L 9.04 M 0.00

10 Cut and fill around shower trap

Tiler & team (T & T) 63.27 p day / 10 no p day


19 x 19 mm mosaic tiles 55.55 x 0.019x0.019

L 6.33 M 0.112

11 300X300X6mm Ceramic floor tiles on floors as described.

Tiler & team (T & T) 63.27 p day / 3m2 p day


Ceramic tiles 11.82 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /100x88 p m2/10 uses

L 21.09 M 14.66

12 Raking & cutting on tiles

Tiler & team (T & T) 63.27 p day /15 p day

L 4.22 M 0.00

13 Circular cutting on tiles

Tiler & team (T & T) 63.27 p day /10 p day

SCREED RATES
131
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 6.33 M 0.00

SCREED RATES
132
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

14 Skirting 150mm high as described.

Tiler & team (T & T) 63.27 p day / 1.5 p day x 0.15m2 per
Ceramic tiles 11.82 /m2 x 1.05 waste x 0.15m2 per
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst x
Tile spacers floor 4.00 /100x88 p m2/10 uses x 0.15m2
Applied Factor x 0.15
L 6.33 M 2.20

15 300X300X6mm Ceramic floor tiles on floors as described in n.w.

Tiler & team (T & T) 63.27 p day / 1.5 p day


Ceramic tiles 11.82 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /200x88 p m2/10 uses

L 42.18 M 14.48

16 500 x 500mm Nexbac Berber Point 650 Carpet tiles

Tiler & team (T & T) 63.27 p day / 30 p day


Carpet tiles 41.25 /m2 X1.05wst

L 2.11 P.C. Sum 43.31

17 Circular cutting on tiles

Tiler & team (T & T) 63.27 p day /10 p day

L 6.33 M 0.00

18 Raking & cutting on tiles

Tiler & team (T & T) 63.27 p day /15 p day

L 4.22 M 0.00

19 Rubber Floor tiles 500x500 incl. 1:4 screed as described.

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p m3 x 0.038m3 per m2 x 1.15

SCREED RATES
133
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Tiler & team (T & T) 63.27 p day / 3 m2 p day


Rubber tiles 40.00 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /100x88 p m2/10 uses

L 21.49 M 44.61

20 Ditto 75mm Skirting

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p m3 x 0.038m3 per m2 x 1.15

Tiler & team (T & T) 63.27 p day / 1.5 p day


Rubber tiles 40.00 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /200x88 p m2/10 uses
Applied Factor x 0.075
L 3.56 M 0.51

21 Raking & cutting on tiles

Tiler & team (T & T) 63.27 p day /15 p day

L 4.22 M 0.00

22 Circular cutting on tiles

Tiler & team (T & T) 63.27 p day /10 p day

L 6.33 M 0.00

23 38mm screed to floors to receive carpet tiles.


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p m3 x 0.038m3 per m2 x 1.15

L 5.29 M 4.75

24 40mm granolithic paving steel trowelled to concrete floors.

SCREED RATES
134
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day

SCREED RATES
135
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Screed (1:4) 108.67 p d x 0.050 x 1.15 waste


Grano. 128.48 p m3 x 0.004m3 per m2 x 1.15

L 5.29 M 6.84

25 75mm High skirting with cove at junction as described.

Labourer 25.56 p day / 60m p d scrabbing


Screed gang 63.27 p day /50 m p day
Screed (1:4) 108.67 p m3 x 0.004m3 per m2 x 1.15
Grano. 128.48 p m3 x 0.004 x 1.15waste
= x applied factor x0.075

L 0.13 M 0.42

26 300x300x8mm Non slip Ceramic floor tiles finished with two coats
of wax polish
Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:5) 100.68 p m3 x 0.040m3 per m2 x 1.15

Tiler & team (T & T) 63.27 p day / 1.5 m2 p day


Ceramic tiles 11.82 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /100x88 p m2/10 uses

L 26.38 M 19.29

27 Raking cutting and waste on ceramic tiles

Labourer 25.56 p day / 60m p d scrabbing


Screed gang 63.27 p day /50 m p day
Screed (1:4) 108.67 p m3 x 0.004m3 per m2 x 1.15
Grano. 128.48 p m3 x 0.004 x 1.15waste

L 1.69 M 5.59

28 150x150x8mm Terra-coat red quary tiles on floors

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:5) 100.68 p m3 x 0.040m3 per m2 x 1.15

Tiler & team (T & T) 63.27 p day / 3 m2 p day

SCREED RATES
136
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Quarry tile 15.00 /m2 x 1.05 waste


1:3 mortar pointing 92.20 x0.00345x1.15

SCREED RATES
137
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 21.94 M 25.19

29 Raking cutting and waste on Terra-coat red quary tiles

Labourer 25.56 p day / 60m p d scrabbing


Screed gang 63.27 p day /50 m p day
Screed (1:4) 108.67 p m3 x 0.004m3 per m2 x 1.15
Grano. 128.48 p m3 x 0.004 x 1.15waste

L 1.69 M 5.59

30 6x40mm Aluminium dividing strip

Screed gang 63.27 p day /25 m p day


Dividing strip 1.00 x1.05 waste

L 2.53 M 1.05

31 40mm granolithic paving steel trowelled laid on cills.


Labourer 25.56 p day / 20m2 p d scrabbing
Screed gang 88.83 p day / 15 m2 p day
Screed (1:4) 108.67 p d x 0.050 x 1.15 waste
Grano. 128.48 p m3 x 0.004m3 per m2 x 1.15

L 7.20 M 6.84

32 100mm High skirting with cove at junction as described.

Labourer 25.56 p day / 60m p d scrabbing


Screed gang 63.27 p day /50 m p day
Screed (1:4) 108.67 p m3 x 0.004m3 per m2 x 1.15
Grano. 128.48 p m3 x 0.004 x 1.15waste

L 1.69 M 5.59

33 300X300X9mm Non-Slip Ceramic floor tiles on floors as described.

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:5) 100.68 p m3 x 0.040m3 per m2 x 1.15

SCREED RATES
138
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Tiler & team (T & T) 63.27 p day / 3m2 p day


Ceramic tiles 10.90 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /200x88 p m2/10 uses

L 26.38 M 11.90

34 Ditto 100mm high skirting

Tiler & team (T & T) 63.27 p day / 6 m2 p day


Ceramic tiles 10.90 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /200x88 p m2/10 uses
= APP FA x0.10
L 1.05 M 1.35

35 600 x 600mm - Metallic Porcelain Floor Tiles

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:5) 100.68 p m3 x 0.040m3 per m2 x 1.15

Tiler & team (T & T) 63.27 p day / 3.0 m2 p day


Metallic Porcelain Tiles 38.25 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /200x88 p m2/10 uses

L 26.38 M 46.87

36 150x150mm Quary tiles as described


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:5) 100.68 p m3 x 0.040m3 per m2 x 1.15

Tiler & team (T & T) 63.27 p day / 3 m2 p day


Quarry tile 15.00 /m2 x 1.05 waste
1:3 mortar pointing 121.04 x0.00345x1.15

L 21.94 M 25.30

SCREED RATES
139
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

37 50mm screed to floors to receive carpet.


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p m3 x 0.050m3 per m2 x 1.15

L 5.29 M 6.25

38 38mm screed to concrete floors.


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 121.04 p m3 x 0.038m3 per m2 x 1.15

L 5.29 M 4.75

39 40mm screed to concrete floors to receive ceramic tiles.

Labourer 25.56 p day / 30m2 p d scrabbing


Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p m3 x 0.040m3 per m2 x 1.15

L 5.29 M 5.00

40 40mm screed to concrete floors to receive grano.


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 121.04 p m3 x 0.04m3 per m2 x 1.15 w

L 5.29 M 5.57

41 50mm granolithic paving steel trowelled to floors


Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p d x 0.050 x 1.15 waste
Grano. 128.48 p m3 x 0.050m3 per m2 x 1.15

L 5.29 M 13.64

42 20x75mm High skirting with cove at junction as described.

Labourer 25.56 p day / 60m p d scrabbing


Screed gang 63.27 p day /20 m p day
Screed (1:4) 108.67 p d x 0.01 x0.075x 1.15 waste
Grano. 128.48 p m3 x 0.004 x 0.075m3 per m2

L 3.59 M 0.14

SCREED RATES
140
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

43 400 x 400mm Ceramic floor Tiles

Tiler & team (T & T) 63.27 p day / 3 m2 p day


Ceramic tiles 13.02 /m2 x 1.05 waste
Tylon adhesive 6.00 p 20kg /4 m covered x1.15 wst
Tile grout pointing 6.00 /20kgx5/10m2 p 5kgx1.15 wst
Tile spacers floor 4.00 /200x88 p m2/10 uses

L 21.09 M 15.74

44 40mm granolithic paving steel trowelled to floors


Labourer 25.56 p day / 30m2 p d scrabbing
. Screed gang 88.83 p day / 20 m2 p day
Screed (1:4) 108.67 p d x 0.040 x 1.15 waste
Grano. 128.48 p m3 x 0.040m3 per m2 x 1.15

L 5.29 M 10.91

45 40mm granolithic paving steel trowelled to floors laid to falls


and across falls
Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 88.83 p day / 15m2 p day
Screed (1:4) 108.67 p d x 0.040 x 1.15 waste
Grano. 128.48 p m3 x 0.040m3 per m2 x 1.15

L 6.77 M 10.91

46 20mm cement grout under mild steel base plate , bearing


plates etc
Labourer 25.56 p day / 30m2 p d scrabbing
Screed gang 63.27 p day / 20 m2 p day
Grout (1:2) 92.20 p d x 0.020 x 1.15 waste

L 4.02 M 2.12

SCREED RATES
141
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

4.72
4.42
4.17
3.88
2.84
3.10
2.94
2.94
2.84

9.00

15.00

12.00

4.72
8.84
12.51
11.64
37.71

37.71
25.56
63.27

37.71
51.12
88.83

1.60
68.18

SCREED RATES
142
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

22.43
92.20

SCREED RATES
143
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

2.26
96.35
22.43
121.04

1.90
80.90
25.88
108.67

1.66
70.90
28.12
100.68

2.43
103.63
22.43
128.48

0.85
5.92
8.35
15.13

2.84
12.69
6.96
22.49

0.85
4.44

SCREED RATES
144
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

4.37
9.67

0.85
4.44
4.75
0.30
10.34

0.43
2.53
0.12
0.00

3.08

0.85
4.44
4.75

21.09
58.33
1.73
0.17
0.35
91.71

0.85
4.44
4.75

42.18
58.33
1.73
0.17
0.35

SCREED RATES
145
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

112.80

4.22
4.22

9.04
9.04

6.33
0.11
6.44

21.09
12.41
1.73
0.17
0.35
35.75

4.22
4.22

6.33
6.33

SCREED RATES
146
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

SCREED RATES
147
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

6.33
1.86
0.26
0.03
0.05
8.53

42.18
12.41
1.73
0.17
0.18
56.66

2.11
43.31
45.42

6.33
6.33

4.22
4.22

0.06
0.33
0.36

SCREED RATES
148
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

21.09
42.00
1.73
0.17
0.35
66.09

0.06
0.33
0.36

3.16
3.15
0.13
0.01
0.01
7.22

4.22
4.22

6.33
6.33

0.85
4.44
4.75
10.04

SCREED RATES
149
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

0.85
4.44

SCREED RATES
150
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

6.25
0.59
12.13

0.03
0.09
0.37
0.04

0.55

0.85
4.44
4.63

21.09
12.41
1.73
0.17
0.35
45.68

0.43
1.27
5.00
0.59
7.28

0.85
4.44
4.63

21.09

SCREED RATES
151
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

15.75
0.37

SCREED RATES
152
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

47.13

0.43
1.27
5.00
0.59
7.28

2.53
1.05
3.58

1.28
5.92
6.25
0.59
14.04

0.43
1.27
5.00
0.59
7.28

0.85
4.44
4.63

SCREED RATES
153
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

21.09
5.71
1.38
0.12
0.18
38.29

1.05
1.14
0.17
0.02
0.02
2.41

0.85
4.44
4.63

21.09
40.16
1.73
0.17
0.18
73.25

0.85
4.44
4.63

21.09
15.75
0.48

47.25

SCREED RATES
154
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

0.85
4.44
6.25
11.54

0.85
4.44
4.75
10.04

0.85
4.44
5.00
10.29

0.85
4.44
5.57
10.86

0.85
4.44
6.25
7.39
18.93

0.43
3.16
0.09
0.04
3.73

SCREED RATES
155
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

21.09
13.67
1.73
0.17
0.18
36.83

0.85
4.44
5.00
5.91
16.20

0.85
5.92
5.00
5.91
17.68

0.85
3.16
2.12

6.14

SCREED RATES
156
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

Riddell Qs

PAINTING

DATA
SKILLED WORKER ONE 4.72
SKILLED WORKER TWO 4.42
SKILLED WORKER THREE 4.17
SKILLED WORKER FOUR 3.88
WORKER EXEMPTED 2.84
WORKER GRADE FOUR 3.10
WORKER GRADE THREE 2.94
WORKER GRADE TWO 2.94
WORKER GRADE ONE 2.84

Painter and Team


Painter
SW1 4.72 p hr x 9 hrs x 1 4.72
SW2 4.42 p hr x 9 hrs x 2 8.84
SW3 4.17 p hr x 9 hrs x 3 12.51
SW4 3.88 p hr x 9 hrs x 3 11.64
= applied Factor / 9 37.71

Painter and Team 37.71


Assistant 2.84 x p hr 9 hrs p day 25.56
63.27
MATERIALS

* External quality PVA 20litres 65.00


* Internal quality PVA 20litres 65.00
* Undercoat white 20litres 75.00
* High gloss White 5L 35.00
* Pink primer 5L 28.00
* Universal clear vanish 5L 35.30
* Eggshell paint 5L 38.64
* Sand sealer L 9.10
* Paraffin L 1.00
* Ceiling white 20litres 48.00

RATE BUILD UP

PAINTING RATES
157
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

1 Clean down and apply 3 coats internal quality PVA paint exterior quality
on; Plasterered walls [wood float]
Painter and Team 63.27 /20m2 p day first coat 3.16
Painter and Team 63.27 25m2 p day x 2seco and 3rd coat 5.06
Paint first coat 75.00 p lit/20/6m2 plit x1.05 waste 0.66
Paint 2nd and 3rd coat 65.00 p lit/20/10m2 plitx2 x1.05 waste 0.68
Paraffin 1.00 p lit/0.04lit pm2x1.15 0.05
9.61
L 8.23 M 1.38

2 Clean down and apply one undercoat and two finishing coats internal quality
PVA emulsion paint on; Plastered steel trowel finish
Painter and Team 63.27 /20m2 p day first coat 3.16
Painter and Team 63.27 25m2 p day x 2seco and 3rd coat 5.06
Paint first coat 75.00 p lit/20/8m2 plit x1.05 waste 0.49
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.05 waste 0.57
Paraffin 1.00 p lit/0.04lit pm2x1.15 0.05
9.33
L 8.23 M 1.11

3 Ditto to raking soffits

Painter and Team 63.27 /20m2 p day first coat 3.16


Painter and Team 63.27 25m2 p day x 2seco and 3rd coat 5.06
Paint first coat 75.00 p lit/20/8m2 plit x1.05 waste 0.49
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.05 waste 0.57
Paraffin 1.00 p lit/0.04lit pm2x1.15 0.05
9.33
L 8.23 M 1.11

4 Ditto to sides of concrete beams


Painter and Team 63.27 /20m2 p day first coat 3.16
Painter and Team 63.27 25m2 p day x 2seco and 3rd coat 5.06
Paint first coat 75.00 p lit/20/8m2 plit x1.05 waste 0.49
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.05 waste 0.57
Paraffin 1.00 p lit/0.04lit pm2x1.15 0.05
9.33
L 8.23 M 1.11

PAINTING RATES
158
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

5 Ditto to concrete walls woodfloat finish


Painter and Team 63.27 /20m2 p day first coat 3.16
Painter and Team 63.27 25m2 p day x 2seco and 3rd coat 5.06
Paint first coat 75.00 p lit/20/6m2 plit x1.05 waste 0.66
Paint 2nd and 3rd coat 65.00 p lit/20/10m2 plitx2 x1.05 waste 0.68
Paraffin 1.00 p lit/0.04lit pm2x1.15 0.05
9.61
L 8.23 M 1.38

6 Ditto to soffits woodfloat finish


Painter and Team 63.27 /20m2 p day first coat 3.16
Painter and Team 63.27 25m2 p day x 2seco and 3rd coat 5.06
Paint first coat 75.00 p lit/20/6m2 plit x1.05 waste 0.66
Paint 2nd and 3rd coat 65.00 p lit/20/10m2 plitx2 x1.05 waste 0.68
Paraffin 1.00 p lit/0.04lit pm2x1.15 0.05
9.61
L 8.23 M 1.38

7 Clean down touch up manufacturer's priming, apply one undercoat and two
finishing coats enamel paint on; Steel door frames
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.25m2 plitx1.15 0.51
6.37
L 3.52 M 2.86

2.25
8 Ditto to general surfaces of doors
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.25m2 plitx1.15 0.51
6.37
L 3.52 M 2.86

PAINTING RATES
159
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

9 Ditto to steel windows [both sides measured flat]


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.25m2 plitx1.15 0.51
6.37
L 3.52 M 2.86

10 Ditto to steel balustrading [both sides measured flat]


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2 plitx1.15 0.46
6.32
L 3.52 M 2.81

11 Prepare and apply one coat metal primer ,one undercoat and finishing coats
enamel paint on; Small copper pipes
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/20/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/20/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2 plitx1.15 0.46
6.32
L 3.52 M 2.81

12 Ditto to large pipe


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2 plitx1.15 0.46
6.32
L 3.52 M 2.81

PAINTING RATES
160
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

13 Prepare , apply self etching primer ,one undercoat and two finishing
coats enamel paint on; Flashings
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.32
L 3.52 M 2.81

14 Ditto on small mild steel pipes


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.32
L 3.52 M 2.81

15 Ditto on large mild steel pipes


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.32
L 3.52 M 2.81

16 Prepare ,seal and apply one undercoat and two finishing coats enamel paint
on;Pvc small pipes
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.32
L 3.52 M 2.81

PAINTING RATES
161
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

17 Ditto on pvc large pipes


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.32
L 3.52 M 2.81

18 Prepare ,knot ,prime,stop and apply one undercoat and two finishing coats
enamel paint on;General surfaces of doors
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.32
L 3.52 M 2.81

19 Ditto on general surfaces in narrow widths


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.00 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.00 p lit/5/12m2 plitx2 x1.15 waste 1.34
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.32
L 3.52 M 2.81

20 Prepare ,stain and apply two coats polyurathane varnish on


General surfaces of doors
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd coat 2.11
Paint first coat 35.30 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd coat 35.30 p lit/5/12m2 plitx2 x1.15 waste 1.35
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.34
L 3.52 M 2.83

PAINTING RATES
162
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

21 Clean down,remove loose and flaking paint ,stop and apply three coats
PVA emulsion paint exterior quality on previously painted surfaces on;
steel trowel plastered walls
Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 65.00 p lit/20/8m2 plit x1.15 waste 0.47
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.15 waste 0.62
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
5.07
L 3.52 M 1.55

22 Ditto to steel plastered soffits


Painter and Team 63.27 /45m2 p day first coat 1.41
Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 65.00 p lit/20/8m2 plit x1.15 waste 0.47
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.15 waste 0.62
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
5.07
L 3.52 M 1.55

23 Clean down,remove loose and flaking paint ,stop and apply one undercoat
and two finishing coats coats enamel paint on previously painted surfaces on;
steel trowel plastered walls

Painter and Team 63.27 /45m2 p day first coat 1.41


Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 65.00 p lit/20/8m2 plit x1.15 waste 0.47
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.15 waste 0.62
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
5.07
L 3.52 M 1.55

24 Clean down,remove loose and flaking paint ,stop and apply one undercoat
and two finishing coats coats enamel paint on previously painted surfaces
to pressed steel door frames

Painter and Team 63.27 /45m2 p day first coat 1.41


Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 65.00 p lit/20/8m2 plit x1.15 waste 0.47
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.15 waste 0.62
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46

PAINTING RATES
163
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

5.07

PAINTING RATES
164
T.N.ZUNZANYIKA ASSOCIATES
ESTIMATING DATA:
RATE BUILD UP
2012

L 3.52 M 1.55

25 Ditto , to steel windows(both sides measured)

Painter and Team 63.27 /45m2 p day first coat 1.41


Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 65.00 p lit/20/8m2 plit x1.15 waste 0.47
Paint 2nd and 3rd coat 65.00 p lit/20/12m2 plitx2 x1.15 waste 0.62
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
5.07
L 3.52 M 1.55

26 Clean down ,prepare , apply one coat sanding sealer and two coats clear
polyurethene varnish on previously varnished surfaces

Painter and Team 63.27 /45m2 p day first coat 1.41


Painter and Team 63.27 /30m2 p day 2nd and 3rd coat 2.11
Paint first coat 35.30 p lit/5/8m2 plit x1.15 waste 1.01
Paint 2nd and 3rd coat 35.30 p lit/5/12m2 plitx2 x1.15 waste 1.35
Paraffin 1.00 p lit/2.5m2pltr 2x1.15 0.46
6.34
L 3.52 M 2.83

PAINTING RATES
165
T.N.ZUNZANYIKA ASSOCIATES
B AND S MCHEKEN CONTRACTORS 46 KWAME NKRUMAH
LINTAS HOUSE
PLUMBING RATE BUILD UP HARARE

ITEM DESCRIPTION UNIT MATERIAL LABOUR RATE IN SUPPLIERS OF


COST IN US$ COST @ US$ MATERIALS
(excl VAT) 20%

A. Plumbing Works

External Water Reticulation


Allow for locating,excavate and connection nto
existing supply pipework incl any fitting Item $ 100.00 Plumbing Africa (Pvt) Ltd

Rainwater Disposal in PVC Piping


1 110mm Diameter PVC-Pipe CL16 m $ 14.03 $ 2.81 $ 16.83 P.G Building Suppliers
2 110mm PVC Bend no. $ 31.45 $ 6.29 $ 37.74 P.G Building Suppliers
3 100mm Diameter PVC Adaptor no. $ 15.30 $ 3.06 $ 18.36 P.G Building Suppliers
4 GI gutter,100 x 75mm (2400mm) Lgth $ 21.25 $ 4.25 $ 25.50 P.G Building Suppliers
5 GI down pipe, 100 x 75mm (2400mm) Lgth $ 21.25 $ 4.25 $ 25.50 P.G Building Suppliers
6 Concrete drip stone no. $ 17.00 $ 3.40 $ 20.40 P.G Building Suppliers
7 GI gutter shoe,100 x 75mm no. $ 5.10 $ 1.02 $ 6.12 P.G Building Suppliers
8 0.6mm galvanised sheet iron m2 $ 42.50 $ 8.50 $ 51.00 P.G Building Suppliers
Sanitary Plumbing
75mm Diameter Waste Pipe - PVC m $ 59.50 $ 11.90 $ 71.40 P.G Building Suppliers
10 50mm Diameter Waste Pipe - PVC m $ 14.03 $ 2.81 $ 16.83 P.G Building Suppliers
11 50mm PVC bend no. $ 3.40 $ 0.68 $ 4.08 P.G Building Suppliers
12 110mm PVC Bend no. $ 31.45 $ 6.29 $ 37.74 P.G Building Suppliers
13 110mm PVC UB42 no. $ 7.65 $ 1.53 $ 9.18 P.G Building Suppliers
14 110mm PVC UB41 no. $ 7.65 $ 1.53 $ 9.18 P.G Building Suppliers
15 50mm Y-junction no. $ 5.95 $ 1.19 $ 7.14 P.G Building Suppliers
16 50mm square junction no. $ 4.25 $ 0.85 $ 5.10 P.G Building Suppliers
17 15mm coupling no. $ 2.98 $ 0.60 $ 3.57 P.G Building Suppliers

]
166
18 22mm coupling no. $ 4.25 $ 0.85 $ 5.10 P.G Building Suppliers
Cap Reducers,Cap Tees, Cap Elbow and
inspection eyes

]
167
19 67 to 28mm Cap reducer no $ 18.28 $ 3.66 $ 21.94 J . Mann & Company
ITEM DESCRIPTION UNIT MATERIAL LABOUR RATE IN SUPPLIERS OF
COST IN US$ COST @ US$ MATERIALS
(excl VAT) 20%
20 54 to 42 mm Reducer no $ 13.95 $ 2.79 $ 16.74 Copper King P\L
21 54 to 28 mm Reducer no $ 32.38 $ 6.48 $ 38.86 Copper King P\L
22 42 to 35 mm Reducer no $ 12.30 $ 2.46 $ 14.76 Copper King P\L
23 42 to 28 mm Reducer no $ 19.22 $ 3.84 $ 23.06 Copper King P\L
24 35 to 28 mm Reducer no $ 5.40 $ 1.08 $ 6.48 J . Mann & Company
25 35 to 22 mm Reducer no $ 5.00 $ 1.00 $ 6.00 J . Mann & Company
26 22 x 22 x 15 mm Reducing tee no $ 20.00 $ 4.00 $ 24.00 J . Mann & Company
27 54 x 42 mm Reducing tee no $ 32.36 $ 6.47 $ 38.83 Copper King P\L
28 42 x 35 mm Reducing tee no $ 12.30 $ 2.46 $ 14.76 Copper King P\L
29 54 mm Equal tee no $ 4.00 $ 0.80 $ 4.80 Copper King P\L
30 42 mm Equal tee no $ 17.51 $ 3.50 $ 21.01 Copper King P\L
31 28 mm Equal tee no $ 3.68 $ 0.74 $ 4.42 J . Mann & Company
32 32 mm Equal tee no $ 10.53 $ 2.11 $ 12.64 Copper King P\L
33 54 mm Elbow no $ 13.45 $ 2.69 $ 16.14 J . Mann & Company
34 42 mm Elbow no $ 7.57 $ 1.51 $ 9.08 Copper King P\L
35 35 mm Elbow no $ 3.75 $ 0.75 $ 4.50 Copper King P\L
36 22 mm Elbow no $ 0.40 $ 0.08 $ 0.48 Copper King P\L
37 White Tape no $ 0.22 $ 0.04 $ 0.26 Copper King P\L
38 28mm Masterbats no $ 16.00 $ 3.20 $ 19.20 Copper King P\L
39 Brass holder bat no $ 7.71 $ 1.54 $ 9.25 J . Mann & Company

Pvc Fittings
40 40mm IE Bend no. $ 4.25 $ 0.85 $ 5.10 P.G Building Suppliers
41 110mm Bend Access Heel 135 deg no. $ 7.65 $ 1.53 $ 9.18 P.G Building Suppliers
42 110mm Bend Plain 135 deg no. $ 7.65 $ 1.53 $ 9.18 P.G Building Suppliers
43 110mm Bend Plain 95 deg no. $ 7.65 $ 1.53 $ 9.18 P.G Building Suppliers
44 50mm Bend Plain 135 deg no. $ 7.65 $ 1.53 $ 9.18 P.G Building Suppliers
45 50mm Bend Plain 95 deg no. $ 4.25 $ 0.85 $ 5.10 P.G Building Suppliers

]
168
ITEM DESCRIPTION UNIT MATERIAL LABOUR RATE IN SUPPLIERS OF
COST IN US$ COST @ US$ MATERIALS
(excl VAT) 20%
46 50mm PVC Bend I/E no. $ 4.25 $ 0.85 $ 5.10 P.G Building Suppliers
47 50-100mm PVC Junction 135 deg no. $ 20.40 $ 4.08 $ 24.48 P.G Building Suppliers
48 100mm Junction 45* - PVC no. $ 10.20 $ 2.04 $ 12.24 P.G Building Suppliers
49 110mm Straight Pan Connector - PVC no. $ 5.10 $ 1.02 $ 6.12 P.G Building Suppliers
50 110mm Junction 95* - PVC no. $ 10.20 $ 2.04 $ 12.24 P.G Building Suppliers
51 100mm Gulley trap - PVC no. $ 5.95 $ 1.19 $ 7.14 P.G Building Suppliers
52 100mm Gulley head and grating - PVC no. $ 5.95 $ 1.19 $ 7.14 P.G Building Suppliers
53 40mm Rubber "P" Trap no. $ 8.50 $ 1.70 $ 10.20 P.G Building Suppliers
54 100mm CI Gulley trap no. $ 5.78 $ 1.16 $ 6.94 Proscheme Hardware
55 40mm copper P-trap no. $ 7.81 $ 1.56 $ 9.37 Proscheme Hardware
56 110mm EW 45"-Y-junction no. $ 4.25 $ 0.85 $ 5.10 Proscheme Hardware
57 110mm Plain stop end no. $ 4.25 $ 0.85 $ 5.10 Pro Plastics
58 600 x 1200mm Culvert pipes no. $ 186.49 $ 37.30 $ 223.79 Ascend Concrete
59 450 x 1200mm Culvert pipes no. $ 119.85 $ 23.97 $ 143.82 Ascend Concrete
60 375mm Culvert Pipe no. $ 104.75 $ 20.95 $ 125.70 Ascend Concrete

Sanitary Fittings
61 1200mm Long Single Bowl Sink no. $ 170.85 $ 34.17 $ 205.02 P.G Building Suppliers
62 1200mm Long Double Bowl Sink no. $ 198.90 $ 39.78 $ 238.68 P.G Building Suppliers
63 1600mm Long Single Bowl Sink no. $ 195.50 $ 39.10 $ 234.60 P.G Building Suppliers
64 150 x 150mm Toilet Roll Holder no. $ 15.30 $ 3.06 $ 18.36 P.G Building Suppliers
65 15mm Pillar Tap no. $ 25.16 $ 5.03 $ 30.19 Macro Plumbers
66 Vaal Lotus WHB Basin no. $ 67.15 $ 13.43 $ 80.58 P.G Building Suppliers
67 Universal Pedestal no. $ 51.00 $ 10.20 $ 61.20 P.G Building Suppliers
68 Chanel White Bath with handles no. $ 102.00 $ 20.40 $ 122.40 House of Tiles
69 Albion basin mixer no. $ 68.00 $ 13.60 $ 81.60 House of Tiles
70 Cobra sink mixer no. $ 74.80 $ 14.96 $ 89.76 House of Tiles
71 Single Sink mixer no. $ 144.55 $ 28.91 $ 173.46 Macro Plumbers

]
169
ITEM DESCRIPTION UNIT MATERIAL LABOUR RATE IN SUPPLIERS OF
COST IN US$ COST @ US$ MATERIALS
(excl VAT) 20%
72 Shower rose ballpoints no. $ 31.45 $ 6.29 $ 37.74 House of Tiles
73 Shower arm no. $ 27.20 $ 5.44 $ 32.64 House of Tiles

Copper Tubing
74 15mm Diameter Pipe m $ 45.05 $ 9.01 $ 54.06 P.G Building Suppliers
75 22mm Diameter Pipe m $ 49.30 $ 9.86 $ 59.16 P.G Building Suppliers
76 15mm Cap Elbow no. $ 5.10 $ 1.02 $ 6.12 P.G Building Suppliers
77 22mm Cap Elbow no. $ 5.95 $ 1.19 $ 7.14 P.G Building Suppliers
78 15mm Cap Tee no. $ 4.25 $ 0.85 $ 5.10 P.G Building Suppliers
79 22mm Cap Tee no. $ 5.10 $ 1.02 $ 6.12 P.G Building Suppliers
80 Cobra Ref P.A 13ZPK Geyser Valve Pack no. 172.50 $ 34.50 $ 207.00 UBM
81 110mm PVC Access Junction SY42 no. 7.48 $ 1.50 $ 8.98 UBM
82 110mm PVC Access Double Junction SY404 no. 13.05 $ 2.61 $ 15.66 UBM
83 20mm Brass Gate Valve F/F no. 16.17 $ 3.23 $ 19.40 UBM
84 20mm c/mi Capillary Coupling no. 1.67 $ 0.33 $ 2.00 UBM
85 28-22mm C/C/C Capillary Reducing Tee no. 6.08 $ 1.22 $ 7.30 UBM
86 22-15mm C/C Capillary Reducing Tee no. 2.45 $ 0.49 $ 2.94 UBM
87 PTFE Thread Tape no. 0.18 $ 0.04 $ 0.22 UBM
88
35-28mm C/C Capillary Reducing Coupling no. 15.00 $ 3.00 $ 18.00 UBM
89 22-15mm C/C /C Capillary Reducing Tee no. 2.45 $ 0.49 $ 2.94 UBM
90 110mm PVC Vent Valve SAV110 no. 6.09 $ 1.22 $ 7.31 UBM
91 32mm Brass Gate Valve F/F no. 23.16 $ 4.63 $ 27.79 UBM
92 28mm C/MI Capillary Coupling no. 3.71 $ 0.74 $ 4.45 UBM
93 110mm PVC Access Junction SY42 no. 7.48 $ 1.50 $ 8.98 UBM
94 20mm CMI Capillary Coupling no. 1.67 $ 0.33 $ 2.00 UBM
95
28-22mm C/C Capillary Reducing Coupling no. 7.00 $ 1.40 $ 8.40 UBM
96 Soldering Wire roll 39.00 $ 7.80 $ 46.80 UBM

]
170
ITEM DESCRIPTION UNIT MATERIAL LABOUR RATE IN SUPPLIERS OF
COST IN US$ COST @ US$ MATERIALS
(excl VAT) 20%

98 15mm C/C Capillary Elbow no. 2.61 $ 0.52 $ 3.13 UBM


99 22mm C/C Capillary Coupling no. 0.73 $ 0.15 $ 0.88
100 35mm C/C Capillary Elbow no. 5.00 $ 1.00 $ 6.00 UBM
101 500ml Plumbers Delight no. 6.09 $ 1.22 $ 7.31 UBM
102 PTFE Thread Pipe roll 0.18 $ 0.04 $ 0.22 UBM
103 15mm Brass Stop Cock no. $ 15.30 $ 3.06 $ 18.36 P.G Building Suppliers
104 22mm Brass Stop Cock no. $ 17.00 $ 3.40 $ 20.40 P.G Building Suppliers
105 15mm Brass Gate Valve no. $ 14.45 $ 2.89 $ 17.34 P.G Building Suppliers
106 22mm Brass Gate Valve no. $ 16.15 $ 3.23 $ 19.38 P.G Building Suppliers
107 32mm Brass Gate Valve no. $ 20.57 $ 4.11 $ 24.68 Copper King P\L
108 40mm Brass Gate Valve no. $ 25.20 $ 5.04 $ 30.24 Copper King P\L
109 65mm Brass Gate Valve no. $ 72.31 $ 14.46 $ 86.77 UBM
110 15mm Copper Connector (300mm long) no. $ 12.75 $ 2.55 $ 15.30 P.G Building Suppliers
111 22mm Copper Connector (300mm Long) no. $ 15.30 $ 3.06 $ 18.36 P.G Building Suppliers
112 15mm CP Undertile Stopcock no. $ 31.45 $ 6.29 $ 37.74 P.G Building Suppliers
113 solvent cement 500ml no. $ 10.20 $ 2.04 $ 12.24 P.G Building Suppliers
114 15mm brass stop cork no. $ 15.30 $ 3.06 $ 18.36 P.G Building Suppliers
115 10mm Galvanised thread bar no. $ 8.00 $ 1.60 $ 9.60 UBM
116 10mm Galvanised nuts no. $ 0.18 $ 0.04 $ 0.22 UBM
117 12mm masonry drill bits no. $ 3.48 $ 0.70 $ 4.18 UBM
118 Minimal Float Control for high and low water
level no. $ 48.75 $ 9.75 $ 58.50 UBM

GEYSERS
119 100 Litre Roof Geyser no. $ 380.00 $ 76.00 $ 456.00 Union Hardware
120 50 Litre pressure type geyser no. $ 493.00 $ 98.60 $ 591.60 P.G Building Suppliers
121 100 Litre pressure type geyser no. $ 532.95 $ 106.59 $ 639.54 P.G Building Suppliers

]
171
ITEM DESCRIPTION UNIT MATERIAL LABOUR RATE IN SUPPLIERS OF
COST IN US$ COST @ US$ MATERIALS
(excl VAT) 20%
122 200 Litre pressure type geyser no. $ 671.50 $ 134.30 $ 805.80 P.G Building Suppliers
123 50 Litre Horizontal Pressure Geyser no. $ 885.00 $ 177.00 $ 1,062.00 UBM
124 100 Litre Horizontal Pressure Geyser no. $ 1,066.13 $ 213.23 $ 1,279.36 UBM
125 200 Litre Horizontal Pressure Geyser no. $ 1,575.00 $ 315.00 $ 1,890.00 UBM
126 6000 Litres Low profile tanks no. $ 765.00 $ 153.00 $ 918.00 UBM
127 200 Litre Copper Floats no. $ 58.22 $ 11.64 $ 69.86 UBM
128 65mm kent water meter no. $ 990.15 $ 198.03 $ 1,188.18 UBM

Fire Services Installations


Fire Appliances
129 Jet Master Fire Place no. $ 750.00 $ 150.00 $ 900.00 DST
130 200 x 200mm Asbestos Cement flue liners 4m $ 14.60 $ 2.92 $ 17.52 Union Hardware

Sundry Items
131 500mm Prodorite Solvent Cement tin $ 10.20 $ 2.04 $ 12.24 P.G Building Suppliers
132 Silicone Sealant tube $ 5.10 $ 1.02 $ 6.12 P.G Building Suppliers

B. Glazing
133 3mm Clear sheet glass m2 $ 7.65 $ 1.53 $ 9.18 City Glass
134 3mm obscure glass m2 $ 3.00 $ 0.60 $ 3.60 P G Glazing / DST Glass
135 Mirror m2 $ 12.00 $ 2.40 $ 14.40 P G Glazing / DST Glass
136 4mm clear glass m2 $ 14.45 $ 2.89 $ 17.34 Sprittler Hardware
137 6mm polished glass 2400 x750mm no. $ 229.50 $ 45.90 $ 275.40 P G Glazing / DST Glass
138 5mm Mirror ,450*600 no. $ 68.00 $ 13.60 $ 81.60 City Glass
139 8mm clear glass m2 $ 56.10 $ 11.22 $ 67.32 Sprittler Hardware
140 Putty kg $ 3.00 $ 0.60 $ 3.60 City Glass
141 Turps litr $ 2.55 $ 0.51 $ 3.06 P G Building Suppliers

]
172
Riddell Qs

EXCAVATIONS- SEWEAGE RETICULATION RATES

DATA
SKILLED WORKER ONE 0.38
SKILLED WORKER TWO 0.35
SKILLED WORKER THREE 0.33
SKILLED WORKER FOUR 0.30
WORKER EXEMPTED 0.30
WORKER GRADE FOUR 0.23
WORKER GRADE THREE 0.23
WORKER GRADE TWO 0.22
WORKER GRADE ONE 0.22

DATA
Excavation Gang
WX Gang Boss 0.30 p day x 9hrs x 1 2.70
WG1 Labourer 0.22 p day x 9hrs x 10 19.83
22.53
Excavation Gang
WX Gang Boss 0.30 p day x 9hrs x 1 2.70
WG1 Labourer 0.22 p day x 9hrs x 8 15.86
18.56

Tractor & Trailer 670.23 per day 670.23


Diesel 1.30 p Lt x 10Lt p day 13.00
Operator WG3 1.31 9hrs p day 11.79
695.02

Plate compactor 40.25 per day x1 40.25


Petrol 1.40 p Lt x 5Ltrs p day 7.00
Operator WG3 1.31 p hrx9hrs p day 11.79
59.04

Bomag 90 Roller 200.00 p day x 1 200.00


Diesel 1.30 p lt x10ltr p day 13.00
Operator WG3 1.31 p hrx9hrs p day 11.79

224.79

350 c.f.m - compressor


350 c.f.m - compressor 130.00 per day 130.00
Diesel 1.30 per ltr x 10ltrs per day 13.00

173
Operator WG3 1.31 p hrx9hrs p day 11.79
154.79

174
Sand cost per m3 15.30

Pit sand cost per m3 13.60

Gravel cost per m3 28.90

Decomposed granite 42.00

1 Clear site of rubbish, grass, trees etc

Excavation Gang G.B & 10 22.53 p day / 250m2 per day 0.09
L 0.09

2 Excav over site ave. 150mm for vegetable soil and deposit on site
not exceeding 100m

Excavation Gang (G.B&10) 22.53 p day / 200 sq m per day 0.11


Excavation Gang (G.B&10) 22.53 p day / 250 sq m per day 0.09
0.20
L 0.20

3 Excavate over site to remove vegetable soil and cart away

Excavation Gang G.B & 10 22.53 p day / 200 M2 p day bulkin 0.11
Excavation Gang G.B & 10 22.53 p day / 250 m2 p day deposi 0.09
0.20

L 0.20

RATE BUILD UP

4 Excavate to remove vegetable soil average depth 150mm

Excavation Gang G.B & 10 22.53 p day / 200 M2 p day bulkin 0.11
Excavation Gang G.B & 10 22.53 p day / 250 m2 p day deposi 0.09
0.20

L 0.20
Excavation Gang G.B & 10 22.53 p day / 12 cu m p day 1.88

175
L 1.88

5 Excavate in pickable mat to reduce levels n.e 2 m deep


Excavation Gang G.B & 10 22.53 p day / 22 cu m p day 1.02

L 1.02

6 Excavate in pickable for ground beams n.e 2 metres deep.

Excavation Gang G.B & 10 22.53 p day / 15 cu m p day 1.50


Excavation Gang G.B & 10 22.53 p day / 15 cu m p day excav 1.50
Excavation Gang G.B & 10 22.53 p day / 55 cu m p day back fi 0.41
Plate compactor 59.04 p day x 2 / 55 cu m p day 2.15

L 3.41 P 2.15 5.56

7 Excavate in pickable for ground beams exc. 2 but n.e. 4metres dp.

Excavation Gang G.B & 10 22.53 p day / 10.50m p day 2.15


Excavation Gang G.B & 10 22.53 p day / 15 cu m p day excav 1.50
Excavation Gang G.B & 10 22.53 p day / 55 cu m p day back fi 0.41
Plate compactor 59.04 p day x 2 / 55 cu m p day 2.15

L 4.06 P 2.15 6.20

8 Excavate in pickable for pile caps n.e 2 metres deep.


Excavation Gang G.B & 10 22.53 p day / 12 cu m p day 1.88

L 1.88

9 Excavate back from face of ground beam n.e 300mm wide for
working space,for the erection and striking off of formwork
Excavation Gang G.B & 10 22.53 p day / 15 cu m p day excav 1.50
Excavation Gang G.B & 10 22.53 p day / 55 cu m p day back fi 0.41
Plate compactor 59.04 p day x 2 / 55 cu m p day 2.15
4.06
L 1.91 P 2.15

10 Extra over for excavation in hard pickable material

Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaki 4.51

176
Excavation Gang G.B & 10 22.53 p day / 22 cu m p day Bulkin (1.02)
Excavation Gang G.B & 10 22.53 p day / 15 cu m p day excav 1.50
Excavation Gang G.B & 10 22.53 p day / 55 cu m p day back fi 0.41

177
Plate compactor 59.04 p day x 2 / 55 cu m p day 2.15

L 5.39 P 2.15 7.54

11 Extra over for excavation in hard rock

Excavation Gang G.B & 10 22.53 p day / 1.25 cu m p day Bre 18.02
Excavation Gang G.B & 10 22.53 p day / 3.75 cu m p day Bulk 6.01
350 c.f.m - compressor {DIESEL 154.79 p day /2.5cu m p day 61.92
Excavation Gang G.B & 10 22.53 p day / 15 cu m p day [-] (1.50)

84.44
L 22.53 P 61.92

12 Extra over all excavations for excavating in brick walls

Excavation Gang G.B & 10 22.53 p day / 5 cu m p day Breaki 4.51


Excavation Gang G.B & 10 22.53 p day / 10cu m p day Bulkin 2.25
350 c.f.m - compressor {DIESEL 154.79 p day /5 cu m p day 30.96
Excavation Gang G.B & 10 22.53 p day / 15 cu m p day [-] (1.50)

36.21
L 5.26 P 30.96

13 Extra over all excavations for excavating in unreinforced concrete

Excavation Gang G.B & 10 22.53 p day / 3 cu m p day Breaki 7.51


Excavation Gang G.B & 10 22.53 p day /10 cu m x1.3 bulk up 2.93
350 c.f.m - compressor {DIESEL 154.79 p day /5 cu m p day 30.96
Excavation Gang G.B & 10 22.53 p day / 15 cu m p day [-] (1.50)

39.89
L 8.94 P 30.96

14 Extra over all excavations for excavating in reinforced concrete

Excavation Gang G.B & 10 22.53 p day / 2.5 cu m p day Brea 9.01
Excavation Gang G.B & 10 22.53 p day / 5.5 cu m x1.3 bulk u 5.32
350 c.f.m - compressor {DIESEL 154.79 p day /2.5 cu m p day 61.92
Excavation Gang G.B & 10 22.53 p day / 15 cu m p day [-] (1.50)

74.75
L 12.83 P 61.92

178
15 Allow for risk of collapse to sides of excavation

179
Excavation Gang G.B & 10 22.53 p day / 10 cu m p day 0.11
Excavation Gang G.B & 10 22.53 p day / 25 cu m p day 0.05
Plate compactor 59.04 p day x 2 / 55 cu m p day 0.11
= applied Factor x 0.05 0.27
L 0.16 P 0.11

16 Re-dig from spoil heap &cart away surplus excavated mat


to a dump site to be located by a Contractor max distance 50KM

Excavation Gang G.B & 10 22.53 p day / 55 cu m p day load 0.41


Tractor and trailer 695.02 per day / 55 cu m p day x 1. 16.43
16.84
L 0.41 P 16.43

17 Re-dig from spoil heap and back fill and compact around fnds
Excavation Gang G.B & 10 22.53 p day / 55 cu m p day Redig 0.41
Plate compactor 59.04 p day x 2 / 55 cu m p day 2.15
2.56
L 0.41 P 2.15

18 Re-dig from spoil heap and backfill to make up levels under


floors 93% HCE density

Excavation Gang G.B & 10 22.53 p day / 75 cu m p day 0.30


Bomag Roller 224.79 p day / 75m3 p day x 2 5.99
6.29

L 0.30 P 5.99

19 Selected stable granular filling of triaxial class 3.9 under floors


compacted to 91% HCE density
Excavation Gang G.B & 10 22.53 p day / 75 cu m p day 0.30
Bomag Roller 224.79 p day / 75m3 p day x 2 5.99
Gravel 28.90 p m3 x 1.33 bulk 38.44
44.73

L 0.30 P 5.99 M 38.44

20 Selected stable granular filling of triaxial class 3.6 under floors


mechanically compacted to 93% HCE density
Excavation Gang G.B & 10 22.53 p day / 75 cu m p day 0.30
Bomag Roller 224.79 p day / 75m3 p day x 2 5.99
Gravel 28.90 p m3 x 1.33 bulk 38.44
44.73

180
L 0.30 P 5.99 M 38.44

181
21 Scarify surface of insitu sud soil for a depth of 150mm and
compact to 89% Mod AASHOT
Excavation Gang G.B & 10 22.53 p day / 300 sq m p day 0.08
Bomag 224.79 p day x 2 No / 300 m2 p day 1.50
1.57
L 0.08 P 1.50

22 Strike off and cure top surface of concrete


0.10
Strike off 1.98 p day/20m2 p day
L 0.10

23 Trimming pile average 450-600mm diameter

Excavation Gang G.B & 10 22.53 p day / 50no p day 0.45


L 0.45

24 Trimming pile average 625-750mm diameter

Excavation Gang G.B & 10 22.53 p day / 40 no p day 0.56


L 0.56

25 Trimming pile average 800 -950mm diameter

Excavation Gang G.B & 10 22.53 p day / 30 no p day 0.75

L 0.75

26 One layer250 micron "Tarcon" polythene DPM laid on and including


50mm sand blinding under concrete surface beds

Labourer 672.34 p hr x 9 x 2/150m2 p day 80.68


Polythene 0.250mm thick 0.70 per m2 x 1.15 waste 0.81
81.49
L 80.68 M 0.81

182
Riddell Qs

BRICKWORK

DATA
SKILLED WORKER ONE 0.38
SKILLED WORKER TWO 0.35
SKILLED WORKER THREE 0.33
SKILLED WORKER FOUR 0.30
WORKER EXEMPTED 0.30
WORKER GRADE FOUR 0.23
WORKER GRADE THREE 0.23
WORKER GRADE TWO 0.22
WORKER GRADE ONE 0.22

Bricklayer or Carpenter Team


Carpenter/B.Layer
SW1 0.379596 p hr x 9 hrs x 1 0.38
SW2 0.35 p hr x 9 hrs x 2 0.70
SW3 0.326928 p hr x 9 hrs x 3 0.98
SW4 0.300 p hr x 9 hrs x 3 0.90
= applied Factor / 9 2.96

Bricklayer/Carpenter and Team

Bricklayer 2.96
Assistant 0.220332 x9 hrs per day(2) 3.97
6.93

EXCAVATIONS

DATA
Excavation Gang
WX Gang Boss 0.30 p day x 9hrs x 1 2.70
WG1 Labourer 0.22 p day x 9hrs x 10 19.83
22.53

Tractor & Trailer 670.23 per day 670.23


Diesel 1.00 p Lt x 10Lt p day 10.00
Operator WG3 0.23 x 9hrs p day 2.07
682.30

Labourer 0.22 x9hrs p day 1.98

183
Bomag 90 Roller 200.00 p day x 1 200.00
Diesel 1.30 p lt x5ltr p day 14.63
Operator WG3 1.31 p hrx9hrs p day 11.79

226.42

1:4 Cement and Sand morta


Labourer 1.98 /120bags per day x8.9m3 handle 0.15
OPC Cement bagged 50kg 9.80 x8.9bgsx1.01 waste 88.09
Pit Sand 13.60 pm3x1.50m3x1.15 was 23.46
111.70

MATERIAL COST

Mountable Kerbs (80/280x300x600mm) 15.41


Municipal Kerbs (310x50/100x910mm) 6.60
Taphalt edging kerbs (230x50/75x910mm) 4.00
Bulnosed kerbs (230x50/55x610mm) 4.24
Light Duty Barrier Kerbs (310x75/100x910mm) 8.07
Heavy Duty Barrier Kerbs (310x100/150x910mm) 13.69
Gee Type Paving Bricks (200x100x60mm) 0.28
Tee Paving bricks (230x140x65mm) 0.32
One bag cement 9.80
Pit sand (per m3) 13.60

RATE BUILD UP

1 Supply and lay Mountable kerbs incl all necessary bedding,


jointing etc
Carpenter & team (T & T) 6.93 p day / 15m p day 0.46
Mountable kerbs 15.41 each x 1.05 waste 16.18
Mortar 111.70 /m3 x 0.05m3/m x 1.1 6.42
23.06
L 0.46 M 22.60

2 Supply and lay Municipal kerbs incl all necessary bedding,


jointing etc
Carpenter & team (T & T) 6.93 p day / 15m p day 0.46
Municipal kerbs 6.60 each x 1.05 waste 6.93
Mortar 111.70 /m3 x 0.05m3/m x 1.1 6.42
13.81
L 0.46 M 13.35

184
3 Supply and lay Taphalt Edging kerbs incl all necessary bedding,
jointing etc
Carpenter & team (T & T) 6.93 p day / 15m p day 0.46
Taphalt Edging kerbs 4.00 each x 1.05 waste 4.20
Mortar 111.70 /m3 x 0.05m3/m x 1.1 6.42
11.08
L 0.46 M 10.62

4 Supply and lay Bullnosed kerbs incl all necessary bedding,


jointing etc
Carpenter & team (T & T) 6.93 p day / 15m p day 0.46
Bullnosed kerb 4.24 each x 1.05 waste 4.45
Mortar 111.70 /m3 x 0.05m3/m x 1.1 6.42
11.34
L 0.46 M 10.87

5 Supply and lay Lightduty Barrier (H2) kerbs incl all necessary bedding,
jointing etc
Carpenter & team (T & T) 6.93 p day / 15m p day 0.46
Lightduty Barrier (H2) kerbs 8.07 each x 1.05 waste 8.47
Mortar 111.70 /m3 x 0.05m3/m x 1.1 6.42
15.36
L 0.46 M 14.90

6 Supply and lay Heavyduty Barrier (H3)kerbs incl all necessary bedding,
jointing etc
Carpenter & team (T & T) 6.93 p day / 15m p day 0.46
Heavyduty Barrier (H3)kerbs 13.69 each x 1.05 waste 14.37
Mortar 111.70 /m3 x 0.05m3/m x 1.1 6.42
21.26
L 0.46 M 20.80

7 20mm sand layer for preparation for paving bricks


Tractor & Trailer 682.30 p day /55m3 p day 12.41
Excavation gang 22.53 /300m2 p day 0.08
Sand 13.60 p m3 x 1.30 bulk 17.68
Bomag roller 226.42 p day /150m2 p day 1.51
31.67
L 0.08 M 17.68 P 13.91

8 Common excavation for the kerbs foundation


Excavation gang 22.53 /15m3 p dy 1.50

L 1.50

185
186
9 Supply all materials and Gee Type paving bricksurfacing
Size (200x100mm)
Tiler & Team 6.93 p day /7m2 per day 0.99
Gee Type paving bricks 0.28 eax50 p m2x1.01 wste 14.14
15.13
L 0.99 M 14.14

10 Supply all materials and Tee paving bricksurfacing


Size (230x140mm)
Tiler & Team 6.93 p day /7m2 per day 0.99
Tee paving bricks 0.32 eax31 pm2x1.01 wst 10.02
11.01
L 0.99 M 10.02

11 Scrap off a 0.5m width strip of existing surfacing for the kerbs
and waste deposited within 2km radious of site

Excavation gang 22.53 /15m3 pr day 1.50


Excavation gang(deposit) 22.53 /15m3 pr day 1.50
Tractor & Trailer 682.30 /55m3 pr dy 16.13
19.13
L 3.00 M 16.13

187
FORMWORK

RATES BUILD-UP

LABOUR RATES

WG1 2.84
SW1 4.72
SW2 4.42
SW3 4.17
SW4 2.84
TAKE AVERAGE FOR SKILLED WORKER =
4.04
TEAM (C+2)
1 SW 4.04
2 WG1 5.68
9.72

SUBSTRUCTURE: SAWN FORMWORK

1 To sides of sides of ground beams

AREA OF 53m OF GROUND BEAMS = 53 {53*0.5*2}


MATERIALS FOR 53m LENGTH
1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 3000 x 600 ECONOMY PANEL -
2 900 x 150 ECONOMY PANEL -
3 900 x 75 CHANNEL SOLDIER -
4 150 x 150 x 900 INTERNAL CORNER -
5 75 x 75 x 900 INTERNAL CORNER -
6 FERRULE (DOLLY) -
7 R. S. CHANNEL -
8 EXT CORNER ANGLE -
9 TEES & WEDGES -
10 C-CLAMPS -
11 U JACKS -
12 1500 Q/S UPRIGHTS -

TOTAL COST PER WEEK >>> -


DURATION = 5 WEEKS
COST PER m2 = -
2 TIMBER

188
ITEM DESCRIPTION QTY RATE AMOUNT
1 0.60m x 76x50 TIMBER 3 67.90 203.69

203.69
COST PER m =
2
3.85
3 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 25 3 75.00
2 100 x 4mm WIRE NAILS (KG) 10 156.15 1,561.50
3 STEEL PEGS ALLOW -
1,636.50
COST PER m =
2
30.88
MATERIALS COST PER m2 = 34.73
LABOUR
TO ERECT 1 GANG 10 m2 PER DAY
TO STRIP 1 GANG 20 m2 PER DAY

LABOUR PER m2 = 13.13

NET RATE = 47.86

2 To sides of sides of ground beams circular in plan to quick sweep

MATERIALS
1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 1000 W/L STANDARDS 10 6.44 64.40
2 U JACKS 20 9.48 189.60
3 RADIUSING TUBE 10 15.10 151.00

TOTAL COST PER WEEK >>> 405.00

AREA = 7.3 m2
COST PER m2 = 55.48
2 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 50x38 R/S TIMBER 15 67.90 1,018.44
2 19mm PLYWOOD 7.5 2,739.44 20,545.82

21,564.26
COST PER m =
2
2,954.01
3 SUNDRIES

189
ITEM DESCRIPTION QTY RATE AMOUNT
1 USED OIL 15 3 45.00
2 100 x 4mm WIRE NAILS (KG) 10 156.15 1,561.50
3 STEEL PEGS ALLOW -
1,606.50
COST PER m =
2
220.07
MATERIALS COST PER m2 = 3,229.56
LABOUR
TO ERECT 1 GANG 7.5 m2 PER DAY
TO STRIP 1 GANG 15 m2 PER DAY

LABOUR PER m2 = 17.50

NET RATE = 3,247.06

3 To sides of square or rectangular columns


{GOKWE RATES}
Nº OF COLS POURED PER DAY = 3
COLS PER WK = 15
TOTAL AREA OF 15 COLS = 69 {15*2.5*(0.46*2+0.23*4)}
MATERIALS FOR 15 COLS 2.5m HIGH
1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 230x2700 ECONOMY PANEL 90 -
4 990 W/L BEAM YOKE 150 -
5 TEES & WEDGES 500 -
6 EXT CORNER ANGLE (m) 150 -
7 C- CLAMPS 600 -
8 U JACKS 120 -
9 2000 K/S STANDARDS 60 -
TOTAL COST PER WEEK >>> -
COST PER m2 = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 100 -
2 STEEL PEGS ALLOW -

-
COST PER m =
2
-

MATERIALS COST PER m2 = -

LABOUR
USE 1 GANG @ 3 COLS PER DAY
SAY TO STRIP = 50% TO ERECT
LABOUR = TO ERECT + TO STRIP

190
LABOUR PER m2 = 19.02

NET RATE = 19.02

4 To sides of 300mm diameter columns

MATERIALS (850mm high stub column)


1 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 19mm PLYWOOD 0.81 -
2 50x50 R/S TIMBER 3.4 -
3 76x50 R/S TIMBER 8.24 -
4 19mm BLOCKBOARD 0.5 -

TOTAL COST PER WEEK >>> -

AREA = 0.81 m2
COST PER m2 = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 5 -
2 100 x 4mm WIRE NAILS (KG) 5 -
3 STEEL PEGS ALLOW -

-
COST PER m =2
-
MATERIALS COST PER m2 = -
LABOUR
TO ERECT 1 GANG 4.86 m2 PER DAY
TO STRIP 1 GANG 9.72 m2 PER DAY

LABOUR PER m2 = 27.00

NET RATE = 27.00

To sides of walls

MATERIALS (L= 23.18m h=3m w=0.23)


1 STEEL EQUIPMENT

191
ITEM DESCRIPTION QTY RATE AMOUNT
1 600x3000 WALLFORM PANELS 57 -
2 100x3000 CHANNEL SOLDIER 32 -
3 75x75x1200 INT CORNER 8 -
4 100x100x1200 INT CORNER 8 -
5 300x3000 WALLFORM PANEL 3 -
6 230x3000 WALLFORM PANEL 6 -
7 500x3000 WALLFORM PANEL 12 -
8 75x3000 CHANNEL SOLDIER 2 -
9 EXT CORNER 24 -
10 TEES AND WEDGES 1159 -
10 FERRULE (DOLLY) 16 -
11 3000 STANDARD 46 -
12 U JACKS 92 -
13 4"x2" R.S.C 94 -
14 C CLAMP 78 -
15 3000 STRONGBACK 46 -

TOTAL COST PER WEEK >>> -


AREA = 139.1 m2
COST PER m2 = -
2 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 19mm BLOCKBOARD ( ALLOW) 2 -
-

-
COST PER m =
2
-
3 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 25 -
2 100 x 4mm WIRE NAILS (KG) 10 -
3 PVC CONDUCTS (ALLOW) 1,000.00
3 STEEL PEGS ALLOW -
1,000.00
COST PER m2 = 7.19
MATERIALS COST PER m2 = 7.19
LABOUR
TO ERECT 1 GANG 36 m2 PER DAY
TO STRIP 1 GANG 72 m2 PER DAY

LABOUR PER m2 = 3.65

NET RATE = 10.84

192
5 To edges in narrow widths

MATERIALS (h=3m w=0.23)


1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 230x3000 WALLFORM PANEL 1 -
2 BEAM YOKES 6 -
3 3000 W/L STANDARDS 1 -
4 TEES AND WEDGES 20 -
5 U JACKS 2 -
6 C CLAMPS 12 -
-

TOTAL COST PER WEEK >>> -


AREA = 0.69 m2
COST PER m2 = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 1 -
2 100 x 4mm WIRE NAILS (KG) 0 -
3 PVC CONDUCTS (ALLOW) 0
3 STEEL PEGS ALLOW -
-
COST PER m2 = -
MATERIALS COST PER m2 = -
LABOUR
TO ERECT 1 GANG 4.14 m2 PER DAY
TO STRIP 1 GANG 8.28 m2 PER DAY

LABOUR PER m2 = 31.70

NET RATE = 31.70

6 Block in to form sump 300x300x300mm deep in top of 450mm deep concrete base

MATERIALS
1 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 19mm BLOCKBOARD 0.36 -
2 50x228 R/S TIMBER 1 -
-
-

TOTAL COST PER WEEK >>> -

193
Nº = 1
COST PER ea = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 0.5 -
2 100 x 4mm WIRE NAILS (KG) 1 -
3 STEEL PEGS ALLOW -

-
COST PER ea = -
MATERIALS COST PER ea = -
LABOUR
TO ERECT 1 GANG 10 Nº PER DAY
TO STRIP 1 GANG 20 Nº PER DAY

LABOUR PER ea = 13.13

NET RATE = 13.13

SUPERSTRUCTURE: SAWN FORMWORK

7 Steel formwork to edge of surface bed 150mm high incl perforations for 12mm
incl perforations for 12mm dia dowel bar (elsewhere measured) @ 600mm c/c

MATERIALS (per m)
1 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 50x228 R/S TIMBER 0.5 -
-

TOTAL COST PER WEEK >>> -

LENGTH = 1 m
COST PER m = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 0.5 -
2 100 x 4mm WIRE NAILS (KG) 1 -
3 STEEL PEGS ALLOW -

-
COST PER m = -
MATERIALS COST PER m = -

194
LABOUR
TO ERECT 1 GANG 20 m PER DAY
TO STRIP 1 GANG 40 m PER DAY

LABOUR PER ea = 6.57

NET RATE = 6.57

8 To sides of beams
AREA OF 50m OF INTERMEDIATE BEAMS = 50 {50*0.5*2}

MATERIALS FOR 50m LENGTH

1 STEEL EQUIPMENT
ITEM DESCRIPTION QTY RATE AMOUNT
1 3000 x 500 ECONOMY PANEL 29 -
2 2400x500 ECONOMY PANEL 2 -
3 900x 300 ECONOMY PANEL 2 -
4 1500 x 500 ECONOMY PANEL 3 -
5 75 x 75 x 600 INTERNAL CORNER 2 -
6 990 K/S BEAM YOKES 26 -
7 R. S. CHANNEL 200 -
8 EXT CORNER ANGLE (m) 2 -
9 TEES & WEDGES 126 -
10 C-CLAMPS 121 -
11 U JACKS 52 -
12 1500 Q/S UPRIGHTS 26 -

TOTAL COST PER WEEK >>> -

COST PER m2 = -
2 SUNDRIES
ITEM DESCRIPTION QTY RATE AMOUNT
1 USED OIL 25 -

-
COST PER m = 2
-

MATERIALS COST PER m2 = -


LABOUR
TO ERECT 1 GANG = 5 m2 / DAY
TO STRIP 1 GANG = 8 m2 / DAY

LABOUR PER m2 = 28.43

NET RATE = 28.43

195
9 To sides of upstand beams

AREA OF 5975mm OF EAVES BEAMS = 8.9625 {5.975*2(0.3+0.45)}

MATERIALS FOR 5975mm LENGTH

1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 3000 x 300 ECONOMY PANEL 4 -
2 3000 x 450 ECONOMY PANEL 4 -
3 TEES & WEDGES 30 -
4 FERRULE (DOLLY) 4 -
5 900 x 100 CHANNEL SOLDIER 2 -
6 R. S. CHANNEL 12 -
7 990 BEAM YOKE 8 -
8 C-CLAMPS 20 -

TOTAL COST PER WEEK >>> -

DURATION = 1 WEEK
COST PER m2 = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 25 -
2 PVC TUBE 1,000.00
-
1,000.00
COST PER m2 = 111.58

MATERIALS COST PER m2 = 111.58


LABOUR
TO ERECT 1 GANG = 3 m2 / DAY
TO STRIP 1 GANG = 6 m2 / DAY

LABOUR PER m2 = 43.74

NET RATE = 155.32

10 To sides of circular columns 300mm diameter

MATERIALS (h=3m )
1 STEEL EQUIPMENT

196
ITEM DESCRIPTION QTY RATE AMOUNT
1 300mm CIRCULAR COLUMN BOX 1 -
2 TEES AND WEDGES 20 -
3 3000 W/L STANDARDS 4 -
5 U JACKS 2 -

TOTAL COST PER WEEK >>> -


Nº PER WEEK = 5
AREA = 14.14 m2
COST PER m2 = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 20 -
2 100 x 4mm WIRE NAILS (KG) 0 -
3 PVC CONDUCTS (ALLOW) 0
3 STEEL PEGS ALLOW -
-
COST PER m2 = -
MATERIALS COST PER m2 = -
LABOUR
TO ERECT 1 GANG 12 m2 PER DAY
TO STRIP 1 GANG 24 m2 PER DAY

LABOUR PER m2 = 10.94

NET RATE = 10.94

11 To edges of slabs in narrow widths

MATERIALS (50% SIDES OF INTERMEDIATE BEAM) = -


LABOUR (100% SIDES OF INTERMEDIATE BEAM) = 28.43

NET RATE = 39.37

12 To edges of slabs curved in plan to quick sweep

MATERIALS

ITEM DESCRIPTION QTY RATE AMOUNT


1 19mm PLYWOOD (50% USE) 50% -
2 SCAFF TUBE 2 -
3 STEEL PEGS 1 -
4 USED OIL 2 -
-
AREA OF FORMWORK 1.00544
MATERIALS COST PER m2 = -

197
LABOUR
TIME 1/5
ASSUME 1 TEAMS
LABOUR TO ERECT = 29.16
LABOUR PER m2 = 29.00

NET RATE = 29.00

13 To raking and stepped outer edge of stairs in narrow widths

MATERIALS
1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 500x3000 ECONOMY PANEL 1 -
2 500x1500 ECONOMY PANEL 1 -
3 75x900 CHANNEL SOLDIER 1 -
4 4"x2" R.S.C 13.8 -
5 BEAM YOKES 5 -
6 C CLAMP 21 -
7 TEES AND WEDGES 10 -
8 1000 W/L UPRIGHTS 4 -
9 U JACKS 8 -

TOTAL COST PER WEEK >>> -


DURATION = 2 WEEKS
AREA = 28.6 m2
COST PER m2 = -
2 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 50x228 TIMBER 13.5 -
2 50x76 R/S TIMBER 36 -
3 50x152 R/S TIMBER 36 -

-
COST PER m =2
-
3 SUNDRIES

198
ITEM DESCRIPTION QTY RATE AMOUNT
1 USED OIL 25 -
2 100 x 4mm WIRE NAILS (KG) 15 -
-
-
-
COST PER m2 = -
MATERIALS COST PER m2 = -
LABOUR
TO ERECT 1 GANG 10 DAYS / FLIGHT
TO STRIP 1 GANG 5 DAYS / FLIGHT

LABOUR PER m2 = 45.90

NET RATE = 45.90

14 To soffits of suspended slabs


AREA OF DECK = 61.3872 {15.120*4.060}
MATERIALS FOR 15120x4060 DECK
1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 2000 W/L UPRIGHTS 36 -
2 1800 W/L LEDGERS 108 -
3 1220 W/L LEDGERS 108 -
4 BASE JACKS 36 -
5 U JACKS 36 -
6 R.S. CHANNEL 93.6 -
7 1220 x 457 DECK PANEL 96 -
8 1220 x 457 FILLER PANEL 8 -

TOTAL COST PER WEEK >>> -


DURATION OF HIRE = 3 WKS
COST PER m2 = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 25 -

-
COST PER m =2
-

MATERIALS COST PER m2 = -

LABOUR

199
ASSUM 2 TEAMS
TIME TO ERECT = 5 DAYS
TIME TO STRIP = 2 DAYS
LABOUR PER m2 = 19.95

NET RATE = 19.95

15 To soffits of landings

MATERIALS
1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 600x1500 ECONOMY PANELS 6 -
2 230x1500 ECONOMY PANELS 1 -
3 4"x2" R.S.C 12.6 -
4 1500 W/L STANDARDS 6 -
5 U JACKS 6 -
6 BASE JACKS 6 -
7 1200 W/L LEDGERS 24 -
8 C CLAMPS 14 -
9 TEES AND WEDGES 30 -

TOTAL COST PER WEEK >>> -


DURATION OF HIRE = 2 WKS
AREA = 5.98 m2
COST PER m2 = -
2 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 TIMBER ALLOW 1,000.00

1,000.00
COST PER m =2
#DIV/0!
3 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 10 3 30.00

30.00
COST PER m2 = 5.02

MATERIALS COST PER m2 = #DIV/0!

LABOUR

200
ASSUM 1 TEAMS
TIME TO ERECT = 2 DAYS
TIME TO STRIP = 1 DAYS
LABOUR PER m2 = 43.88

NET RATE = #DIV/0!

16 To raking soffits of stairs

MATERIALS
1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 600x1500 ECONOMY PANELS 6 -
2 230x1500 ECONOMY PANELS 1 -
3 TEES AND WEDGES 35 -
4 4"x2" R.S.C 15.16 -
5 C CLAMPS 22 -
6 1500 W/L STANDARDS 2 1.00 2.00
7 1000 W/L STANDARDS 2 -
8 U JACKS 4 -
9 BASE JACKS 4 -
10 1200 W/L LEDGERS 8 -
-

TOTAL COST PER WEEK >>> 2.00


DURATION OF HIRE = 2 WKS
AREA = 6.87 m2
COST PER m2 = 0.58
2 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 TIMBER ALLOW 1,000.00

1,000.00
COST PER m =
2
1,000.00
3 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 10 -

-
COST PER m =
2
-

201
MATERIALS COST PER m2 = 1,000.58

LABOUR
ASSUM 1 TEAMS
TIME TO ERECT = 2 DAYS
TIME TO STRIP = 1 DAYS
LABOUR PER m2 = 38.20

NET RATE = 1,038.78

17 To soffits of beams

AREA OF 50m OF INTERMEDIATE BEAMS = 11.5 {50*0.23}

MATERIALS FOR 50m LENGTH

1 STEEL EQUIPMENT

ITEM DESCRIPTION QTY RATE AMOUNT


1 3000 x 230 ECONOMY PANEL 16 -
2 EXT CORNER ANGLE (m) 100 -
3 TEES & WEDGES 395 -
4 R. S. CHANNEL (m) 150 -
5 C-CLAMPS 106 -
6 2000 W/L UPRIGHTS 56 -
7 BASE JACKS 56 -
8 U JACKS 56 -
9 1200 W/L LEDGERS 84 -
10 1800 W/L LEDGERS 84 -
-
-

TOTAL COST PER WEEK >>> -


DURATION OF HIRE = 3 WKS
COST PER m2 = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 25 -

-
COST PER m =
2
-

MATERIALS COST PER m2 = -

LABOUR

202
TO ERECT 1 GANG = 5 m2 / DAY
TO STRIP 1 GANG = 10 m2 / DAY
LABOUR PER m2 = 26.24

NET RATE = 26.24

18 Block in to form openning for 400mm dia steel column through 150mm thk slab

MATERIALS
1 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 19mm PLYWOOD 0.188 -
2 38x152 R/S TIMBER 1.1 -
-
-

TOTAL COST PER WEEK >>> -

Nº = 1
c -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 0.5 -
2 100 x 4mm WIRE NAILS (KG) 1 -
3 -

-
COST PER ea = -
MATERIALS COST PER ea = -
LABOUR
TO ERECT 1 GANG 10 Nº PER DAY
TO STRIP 1 GANG 20 Nº PER DAY

LABOUR PER ea = 13.13

NET RATE = 13.13

19 Block in to form opening size 2000x1500mm through 150mm thk slab

MATERIALS
1 TIMBER

203
ITEM DESCRIPTION QTY RATE AMOUNT
1 38x152 R/S TIMBER (2 uses) 7 -
-
-
TOTAL COST PER WEEK >>> -

Nº = 1
COST PER ea = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 0.5 -
2 100 x 4mm WIRE NAILS (KG) 1 -
-

-
COST PER ea = -
MATERIALS COST PER ea = -
LABOUR
TO ERECT 1 GANG 5 Nº PER DAY
TO STRIP 1 GANG 10 Nº PER DAY

LABOUR PER ea = 26.25

NET RATE = 26.25

20 Block in to form opening size 2000x2100mm through 150mm thk slab

MATERIALS
1 TIMBER

ITEM DESCRIPTION QTY RATE AMOUNT


1 38x152 R/S TIMBER (2 uses) 8.2 -
-
-
TOTAL COST PER WEEK >>> -

Nº = 1
COST PER ea = -
2 SUNDRIES

ITEM DESCRIPTION QTY RATE AMOUNT


1 USED OIL 0.5 -
2 100 x 4mm WIRE NAILS (KG) 1 -
-

204
COST PER ea = -
MATERIALS COST PER ea = -
LABOUR
TO ERECT 1 GANG 5 Nº PER DAY
TO STRIP 1 GANG 10 Nº PER DAY

LABOUR PER ea = 26.25

NET RATE = 26.25

TOTAL FORMWORK COST: =

205
43,887.62

206
61,694.14

207
4,831.08

1,674.00

208
1,040.64
12,823.72

209
634.00
1,711.80
p concrete base

210
13.13

s for 12mm
600mm c/c

211
2,549.16

22,289.12

212
5*2(0.3+0.45)}

41,781.08
2,485.12

213
2,538.08

275.59

214
580.00

215
5,186.70

20*4.060}

216
30,683.10

217
#DIV/0!

218
111149.46

219
5,405.44

mm thk slab

105.04

220
52.50

221
52.50

#DIV/0!

222
MATERIAL SCHEDULE BASIC PRICE LIST
2015
Item Description Unit Price Supplier Date

FOUNDATIONS
1 PC Cement( incl transportation cost per bag) bag $ 12.20 Larfage Cement JANUARY 2015
2
PMC15 Cement 22.5 x 50kg bags( incl transportation cost per bag) bag $ 13.00 Larfage Cement JANUARY 2015
3 River Sand m 3
$ 25.00 L & D Logistics JANUARY 2015
4
19 mm graded concrete stone (Including transport and loading) m3 $ 42.00 Pomona Stone Quarry JANUARY 2015
20mm concrete stones m 3
$ 30.00 Lafarge Cements JANUARY 2015
7 3/4 Stone (Including Transport) m3 $ 40.38 Exsodus Sands JANUARY 2015
8 Crusher Run (Including Transport) m 3
$ 32.50 Lafarge Cements JANUARY 2015
9 Pitsand (Including transport) m3 25 L & D Logistics JANUARY 2015
10 Decomposed Fill m 3
$ 17.25 Pomona JANUARY 2015
11 Gravel (Including Transport) m3 $ 20.00 Royal Suppliers JANUARY 2015
12 Black Polythene Sheeting 2400 x 1000mm -125microns m $ 0.20 FABS Hardware JANUARY 2015
13 Black Polythene Sheeting 2400 x 1000mm -250 microns m $ 0.30 Builder's Home JANUARY 2015
14 3 Ply x 115mm Damp Proof Course m $ 0.45 FABS Hardware JANUARY 2015
15 3 Ply x 230mm Damp Proof Course m $ 0.35 FABS Hardware JANUARY 2015
230mm brickforce/ roll no. $ 2.50 FABS Hardware JANUARY 2015
115mm brickforce/ roll no. $ 2.50 FABS Hardware JANUARY 2015
16 Thioflex sealant ltr $ 46.00 Harare Sealants JANUARY 2015
17 Decomposed granite m3 $ 30.00 Pomona Quarry Stones JANUARY 2015
18 40mm crushed stone m3 $ 32.00 Pomona Quarry Stones JANUARY 2015
19 Silicone sealant ltr $ 9.67 Builder's Home JANUARY 2015
5 Litre Termite Poison no. $ 5.00 FABS Hardware JANUARY 2015
230mm dpc/roll roll $ 7.00 Grapnote Steel JANUARY 2015
Reinforcement
20 8-32mm Derfomed Bars kg $ 0.95 Longden steel JANUARY 2015

223
21 Steel fixing kg $ 0.36 Longden steel JANUARY 2015
22 S193 Mesh Wire 2400mm wide x 6000mm long sheet $ 42.55 Longden steel JANUARY 2015

224
23 115mm Brickforce roll $ 2.83 Grapnote Steel JANUARY 2015
24 230mm Brickforce roll $ 2.83 Grapnote Steel JANUARY 2015
25 S245 Mesh Wire 2400mm wide x 6000mm long sheet $ 54.05 Longden steel JANUARY 2015
26 S617 Mesh Wire 2400mm wide x 6000mm long sheet $ 169.27 Longden steel JANUARY 2015
27 1.6mm Black Annelead Tying Wire kg $ 2.30 Longden Steel JANUARY 2015

Brickwork
28 Common Bricks no. $ 0.15 Beta Bricks JANUARY 2015
29 Face Bricks no. $ 0.33 MacDonald Bricks JANUARY 2015
30 Red Industrial bricks no. $ 0.35 Beta Bricks JANUARY 2015
31 Hardburn / Load Bearing Bricks no. $ 0.20 Beta Bricks JANUARY 2015
32 Concrete bricks ( including transport) no. $ 0.26 Espn Quarry & Brickyard JANUARY 2015
33 Red Rustic bricks no. $ 0.29 Beta Bricks JANUARY 2015
34 Wirebrush dark bricks no. $ 0.36 Beta Bricks JANUARY 2015
35 Coral Light face bricks no. $ 0.31 Beta Bricks JANUARY 2015
36 Dark Rustic facebrick no. $ 0.30 Beta Bricks JANUARY 2015
37 Blue rustic facebrick no. $ 0.48 Beta Bricks JANUARY 2015
41 230 x 150mm Exterior Concrete Air Vents no. $ 0.80 FABS Hardware JANUARY 2015
42 230 x 150mm Interior Concrete Air Vents no. $ 0.80 FABS Hardware JANUARY 2015

Expansion Joints
43 10 x 1200 x 2400mm kay lite sheets m2 $ 2.08 Africa Steel JANUARY 2015
44 Thioflex Sealant m2 $ 12.00 Construction services JANUARY 2015

Precast Concrete
45 50 x 230 x 600mm Twice weathered coping no. $ 6.12 Arch Concrete JANUARY 2015

Precast Concrete Dripstones


46 100 x 460 x 460 mm long no. $ 8.00 Arch Concrete JANUARY 2015
47 130 x 350 x 450mm long no. $ 7.00 Arch Concrete JANUARY 2015
48 230 x 150 x 1130mm long no. $ 35.00 Arch Concrete JANUARY 2015
49 230 x 150 x 2960mm long no. $ 68.00 Arch Concrete JANUARY 2015

225
"Fort concrete" or equal approved prestressed
concrete lintels (20 Mpa) jointed in 1:3 cement
mortar nominal size 150 x 230 mm deep
50 1270 mm long no. $ 15.00 Arc Concrete JANUARY 2015
51 1 460 mm long no. $ 17.50 Arc Concrete JANUARY 2015
52 2490 mm long no. $ 30.00 Arc Concrete JANUARY 2015

Heavy Duty Kerbs


53 100/150 x 300 x 1000mm long no. $ 14.02 Ciampi JANUARY 2015
54 100/150 x 300 x 300mm long no. $ 4.25 Ciampi JANUARY 2015

Pavers
55 Gee type pavers finished grey size 200 x 100 x 80mm thick no. $ 0.32 Ciampi JANUARY 2015

Roof Coverings
56 Asbestos Sheet Size 3600 x 900mm no. $ 36.00 PG Building Suppliers JANUARY 2015
57 Asbestos Sheet Size 1500 x 900mm no. $ 17.00 DST JANUARY 2015
58 Structural Steelwork m2 $ 35.73 Scotia Steel JANUARY 2015
59 Chromadek roof covering m $ 7.30 Africa Steel JANUARY 2015
60 Canopy structural steelwork m2 $ 44.66 Scotia Steel JANUARY 2015
61 Allucushion insulation m2 $ 10.49 Africa Steel JANUARY 2015
62 Canopy Chromadek roof covering m $ 7.30 Scotia Steel JANUARY 2015

Carpentry, Joinery & Ironmongery


63 38x38mm brandering m 0.82 DST JANUARY 2015
64 76 x 50 mm wall plate m $ 2.50 Union hardware JANUARY 2015
65 114 x 38mm wall plate m $ 3.57 PG Building Suppliers JANUARY 2015
66 Wire nails 150mm (6 inch) kg $ 2.50 FABS Hardware JANUARY 2015
67 40mm clout nails kg $ 5.00 FABS Hardware JANUARY 2015
68 180 x38mm pine fascia board m $ 8.50 PG Building Suppliers JANUARY 2015
69 114x38 mm fascia boards m $ 2.50 Union hardware JANUARY 2015
70 Galvanised hoop iron ties m $ 0.50 Union hardware JANUARY 2015
71 Carbolineum (1 litre) Tins $ 2.34 Union hardware JANUARY 2015

226
72 76 x 50mm purlins m $ 3.40 PG Building Suppliers JANUARY 2015

227
73 38 x 50mm purlins m $ 1.70 PG Building Suppliers JANUARY 2015
73 22mm Blockboard 2440 x 1220 m $ 83.30 PG Building Suppliers JANUARY 2015
74 19mm Pine Blockboard (2440 x 1220mm) m2 $ 51.00 PG Building Suppliers JANUARY 2015
75 50 x 150mm rafter m $ 6.80 PG Building Suppliers JANUARY 2015

Doors
76 44 x 762 x 2030mm Internal Qlty Semi-Solid Core Door no. $ 127.50 PG Building Suppliers JANUARY 2015
77 44 x 815 x 1880mm Internal Qlty Semi-Solid Core Door no. $ 80.00 PG Building Suppliers JANUARY 2015
78 44 x 895 x 2030mm Internal Qlty Semi-Solid Core Door no. $ 120.00 PG Building Suppliers JANUARY 2015
79 44 x 813 x 2030mm Internal Qlty Semi-Solid Core Door no. $ 136.00 PG Building Suppliers JANUARY 2015
80 44 x 813 x 2032mm Internal Qlty Semi-Solid Core Door no. $ 136.00 PG Building Suppliers JANUARY 2015
81 44 x1219 x 2030mm Internal Qlty Semi-Solid Core Door no. $ 170.00 PG Building Suppliers JANUARY 2015
82 44 x 900 x 2125mm Internal Qlty Semi-Solid Core Door no. $ 153.00 PG Building Suppliers JANUARY 2015
83 44 x 900 x 2100mm Internal Qlty Semi-Solid Core Door no. $ 153.00 PG Building Suppliers JANUARY 2015
84 44 x 762 x 2030mm External Qlty Semi-Solid Core Door no. $ 161.50 PG Building Suppliers JANUARY 2015
85 44 x 813 x 2030mm External Qlty Semi-Solid Core Door no. $ 178.50 PG Building Suppliers JANUARY 2015
86 44 x 813 x 2032mm External Qlty Semi-Solid Core Door no. $ 178.50 PG Building Suppliers JANUARY 2015
87 44 x 900 x 2125mm External Qlty Semi-Solid Core Door no. $ 199.75 PG Building Suppliers JANUARY 2015
88 44 x 900 x 2100mm Internal Qlty Semi-Solid Core Door no. $ 199.75 PG Building Suppliers JANUARY 2015
89 54 x 1613 x 2030mm Internal Qlty Fire Rated Door no. $ 595.00 PG Building Suppliers JANUARY 2015
90 44 x 813 x 2032mm Internal Qlty Fire Rated Door no. $ 552.50 PG Building Suppliers JANUARY 2015
91 44 x 1675 x 495mm Internal Qlty B.I.C Dr no. $ 51.00 PG Building Suppliers JANUARY 2015
92 44 x 1675 x 2030mm Internal Qlty B.I.C Dr no. $ 136.00 PG Building Suppliers JANUARY 2015
93 Fush door 91082 Cape Dutch 2 Pan no. $ 74.75 Union Hardware JANUARY 2015
94 Flush Door Saligna 6 panel no. $ 119.00 Union Hardware JANUARY 2015

Mukwa Doors
95 813 x 2032 Mukwa Double Door with Frame no. $ 520.00 UBM JANUARY 2015
96 1468 x 2336 Mukwa Double Door with Frame no. $ 650.00 UBM JANUARY 2015
97 1468 x 2057 Mukwa Double Door with Frame no. $ 650.00 UBM JANUARY 2015
98 813 x 2032 Mukwa stable Door with Frame no. $ 286.00 UBM JANUARY 2015

Light duty Strong room door & frame JANUARY 2015


99 164mm thick door with frame of size 950 x 1975mm high

228
(inclusive of 12mm
7 lever security key outer
lock &plate,eight 40mm diameter
3 wheel combination lock ,bolts ,
weght:380kgs) no. $ 2,125.00 National Safes P/ L JANUARY 2015

Mongery
100 UNION80941SC INDICATOR BOLT no. $ 17.60 Chubb Locks Union JANUARY 2015
101 AL8722AS HAT & COAT HOOK no. $ 4.68 Chubb Locks Union JANUARY 2015
102 UNION 2209-78SS E/PROFILE CYLINDER no. $ 42.08 Chubb Locks Union JANUARY 2015
103 UNION AL6C20-05AS CEDAR E/PROFILE no. $ 55.00 Chubb Locks Union JANUARY 2015
104 2X19SC E/PROFILE KNOB CYLINDER no. $ 26.40 Chubb Locks Union JANUARY 2015
105 UNION AL8052-150AS FLUSH BOLTS no. $ 17.05 Chubb Locks Union JANUARY 2015
106 UNION 2700SS REBATE SET no. $ 14.03 Chubb Locks Union JANUARY 2015
107 UNION AL8254AS WALL MOUNTED no. $ 14.85 Chubb Locks Union JANUARY 2015
108 UNION 2109-78SS E/PROFILE CYLINDER no. $ 30.25 Chubb Locks Union JANUARY 2015
109 UNION AL5375-05AS E/PROFILE ESCUTCHEON no. $ 2.75 Chubb Locks Union JANUARY 2015
110 UNION AL5D02AS PULL HANDLE no. $ 11.55 Chubb Locks Union JANUARY 2015
111 UNION AL5506-06AS PUSHPLATE no. $ 9.63 Chubb Locks Union JANUARY 2015
112 UNION AL5066-06ASE10 MALE TOILET SIGN no. $ 16.50 Chubb Locks Union JANUARY 2015
113 UNION AL5066-06ASE11 FEMALE TOILET SIGN no. $ 16.50 Chubb Locks Union JANUARY 2015
114 AL5089-150W 150X880MM KICK PLATE no. $ 27.50 Chubb Locks Union JANUARY 2015
115 UNION 7770 O/H D/CLOSER EN2-4 R/ARM SILVER no. $ 49.50 Chubb Locks Union JANUARY 2015
116 UNION 7836 O/H D/CLOSER EN 2-6 R/ARM D/A SILVER no. $ 183.70 Chubb Locks Union JANUARY 2015
117 UNION 9002AS DOOR STOP no. $ 3.85 Chubb Locks Union JANUARY 2015
118 UNION 750 D/ACTION F/SPRING NHO no. $ 440.00 Chubb Locks Union JANUARY 2015
119 UNION 752/754 S/ACTION F/SPRING NHO no. $ 454.30 Chubb Locks Union JANUARY 2015
120 UNION AL5089-150W 150X790MM no. $ 24.20 Chubb Locks Union JANUARY 2015
121 UNION 7772 O/H D/CLOSER no. $ 92.40 Chubb Locks Union JANUARY 2015
122 UNION 802DMG DOUBLE PANIC BOLT no. $ 237.60 Chubb Locks Union JANUARY 2015
123 UNION 8040OUTSIDE ACCESS DEVICE no. $ 198.00 Chubb Locks Union JANUARY 2015
124 UNION 2209-78SS E/PROFILE CYLINDER no. $ 42.08 Chubb Locks Union JANUARY 2015

229
125 UNION AL6C20-05AS CEDAR E/PROFILE no. $ 55.00 Chubb Locks Union JANUARY 2015
126 2X18SC E/PROFILE DOUBLE CYLINDER no. $ 24.48 Chubb Locks Union JANUARY 2015
127 VINGCARD CLASSIC RFID SATIN CHROME no. $ 330.00 Chubb Locks Union JANUARY 2015
128 CYLINDER OVERRIDE no. $ 29.00 Chubb Locks Union JANUARY 2015
129 VISION ADVANCED SOFTWARE UP TO 199 ROOMS no. $ 2,945.00 Chubb Locks Union JANUARY 2015
130 LOCKLINK INCL CONTACT CARD AND IR no. $ 1,695.00 Chubb Locks Union JANUARY 2015
131 RFID ENCODER no. $ 870.00 Chubb Locks Union JANUARY 2015
132 RFID GENERIC KEYCARDS no. $ 1.50 Chubb Locks Union JANUARY 2015
133 UNION 7772 O/H D/CLOSER EN 2-4 R/ARM SILVER no. $ 92.40 Chubb Locks Union JANUARY 2015
134 UNION 7836 O/H D/CLOSER EN 2-6 R/ARM D/ACTION SILVER no. $ 183.70 Chubb Locks Union JANUARY 2015
135 UNION 9002AS DOOR STOP no. $ 3.85 Chubb Locks Union JANUARY 2015
136 UNION 8005SS HAT& COAT HOOK no. $ 7.15 Chubb Locks Union JANUARY 2015
137 UNION 24314-76SC B.ROOM CLAW no. $ 51.70 Chubb Locks Union JANUARY 2015
138 UNION AL5375-73AS BATHROOM INDICATOR SET no. $ 13.75 Chubb Locks Union JANUARY 2015
139 UNION AL5515-200BBAS DOVE PULL HANDLE BACK TO BA no. $ 24.20 Chubb Locks Union JANUARY 2015
140 UNION 22314-76SC BATHROOM LOCK no. $ 19.53 Chubb Locks Union JANUARY 2015
141 UNION ALC20TL/TR-73AS CEDAR BATHROOM FURNITURE no. $ 68.20 Chubb Locks Union JANUARY 2015
142 UNION 99001NP WISHBONE DOOR QUARD no. $ 9.10 Chubb Locks Union JANUARY 2015
143 UNION 99200CH DOOR VIEWER no. $ 14.30 Chubb Locks Union JANUARY 2015
144 UNION SS5066E-06SSE15 FIRE ESCAPE PICTOGRAM no. $ 16.50 Chubb Locks Union JANUARY 2015
145 UNION SS5066E-06SSE16 FIRE ESCAPE PICTOGRAM no. $ 16.50 Chubb Locks Union JANUARY 2015
146 UNION SS5066E-06SSE06 FIRE EXTINGUISHER PICTOGRAM no. $ 16.50 Chubb Locks Union JANUARY 2015
147 UNION SS5506E-06SSE01 ELECTRICAL PICTOGRAM no. $ 16.50 Chubb Locks Union JANUARY 2015
148 UNION SS5506E-06SSE ROOMS ENGRAVING no. $ 55.50 Chubb Locks Union JANUARY 2015
149 UNION SS5506E-06SSE07 DIRECTIONAL PICTOGRAM no. $ 16.50 Chubb Locks Union JANUARY 2015
150 UNION SS5506E-06SSE08 DIRECTIONAL PICTOGRAM no. $ 16.50 Chubb Locks Union JANUARY 2015
151 UNION SS5506E-06SSE D.B ROOM ENGRAVING no. $ 35.60 Chubb Locks Union JANUARY 2015
152 UNION SS5506E-06SSE MAINTAINCE WORKSHOP ENGRAVI no. $ 75.30 Chubb Locks Union JANUARY 2015
153 UNION SS5506E-06SSE SERVER ROOM ENGRAVING no. $ 45.50 Chubb Locks Union JANUARY 2015

230
154 UNION SS5506E-06SSE SWITCH BOARD ROOM ENGRAVING no. $ 65.40 Chubb Locks Union JANUARY 2015
155 UNION SS5506E-06SSE ROOM NUMBERS ENGRAVING no. $ 13.90 Chubb Locks Union JANUARY 2015
156 UNION SS5506E-06SSE HOUSE KEEPING ENGRAVING no. $ 58.80 Chubb Locks Union JANUARY 2015
157 UNION SS5506E-06SSE FUNCTION ROOM ENGRAVING no. $ 58.80 Chubb Locks Union JANUARY 2015
158 UNION SS5506E-06SSE CONFERENCE ROOM ENGRAVING no. $ 71.20 Chubb Locks Union JANUARY 2015
159 UNION SS5506E-06SSE STAFF ONLY ENGRAVING no. $ 42.20 Chubb Locks Union JANUARY 2015
160 UNION SS5506E-06SSE CASHIER ENGRAVING no. $ 35.60 Chubb Locks Union JANUARY 2015
161 UNION SS5506E-06SSE CCTV ROOM ENGRAVING no. $ 38.90 Chubb Locks Union JANUARY 2015
162 UNION SS5506E-06SSE SLOTS MANAGER ENGRAVING no. $ 39.00 Chubb Locks Union JANUARY 2015
163 UNION SS5506E-06SSE TABLE MANAGER ENGRAVING no. $ 55.50 Chubb Locks Union JANUARY 2015
164 UNION SS5506E-06SSE CASINO MANAGER ENGRAVING no. $ 58.80 Chubb Locks Union JANUARY 2015
165 UNION SS5506E-06SSE ADMINISTRATION OFFICE ENGRAVI no. $ 81.90 Chubb Locks Union JANUARY 2015
166 UNION SS5506E-06SSE STAFF CANTEEN ENGRAVING no. $ 55.50 Chubb Locks Union JANUARY 2015
167 UNION SS5506E-06SSE LAUNDRY ENGRAVING no. $ 35.60 Chubb Locks Union JANUARY 2015
168 UNION SS5506E-06SSE HOUSE KEEPER ENGRAVING no. $ 42.20 Chubb Locks Union JANUARY 2015
169 Rubber door stopper no. 1.02 DST JANUARY 2015
170 100mm door hinges/pr no. 4.25 DST JANUARY 2015
171 Union two lever lockset no. $ 18.00 Union Hardware JANUARY 2015
172 Union three lever lockset no. $ 20.00 Union Hardware JANUARY 2015
173 40mm wood screws no. $ 0.24 PG Building Suppliers JANUARY 2015
174 25mm fisher plugs no. $ 0.24 PG Building Suppliers JANUARY 2015
175 150mm wire nails kg $ 2.50 FABS Hardware JANUARY 2015
176 100mm wire nails kg $ 2.50 FABS Hardware JANUARY 2015
177 115mm drive screw & washer no. $ 0.30 PG Building Suppliers JANUARY 2015
178 40mm panel pins kg $ 4.25 PG Building Suppliers JANUARY 2015

CEILINGS
179 6.4 mm Gypsum board no $ 13.00 FABS Hardware JANUARY 2015
180 9mm Gypsum Plasterboards no. $ 15.30 PG Building Suppliers JANUARY 2015
181 Paper Scrim 30m $ 4.00 FABS Hardware JANUARY 2015

231
Metalwork
Pressed Steel Window Frames JANUARY 2015
182 Window type E4H overall size 1511 x 654mm high no. $ 71.40 PG Building Suppliers JANUARY 2015
183 Window type D4FH overall size 1511 x 1248mm high no. $ 129.20 PG Building Suppliers JANUARY 2015
184 Window type C1E overall size 533 x 967mm high no. $ 52.70 PG Building Suppliers JANUARY 2015
185 Window type C2FH overall size 951 x 1022mm high no. $ 72.25 PG Building Suppliers JANUARY 2015
186 Window type DV22FH overall size 1545 x 2000mm high no. $ 143.00 FABS JANUARY 2015
187 Window type E22H overall size 2000 x 654mm high no. $ 79.05 PG Building Suppliers JANUARY 2015
188 Window type DV1H overall size 533 x 1545mm high no. $ 57.80 PG Building Suppliers JANUARY 2015
189 Window type DV7HH overall size 1022 x 1545mm high no. $ 69.70 PG Building Suppliers JANUARY 2015
190 Window type S1D1H overall size 654 x 1248mm high no. $ 83.30 PG Building Suppliers JANUARY 2015
191 Window type C7E overall size 967x 1022mm high no. $ 82.45 PG Building Suppliers JANUARY 2015
192 Window type DV8H overall size 1120 x 2400mm high no. $ 55.25 PG Building Suppliers JANUARY 2015
193 Window type DV4FH overall size 1511 x 1545mm high no. $ 151.30 PG Building Suppliers JANUARY 2015
194 Window frame type NC11F no. $ 110.50 PG Building Suppliers JANUARY 2015
195 Window frame type C1H no. $ 40.80 PG Building Suppliers JANUARY 2015
196 Window frame type C1 no. $ 65.00 FABS JANUARY 2015
197 Window frame type C2H no. $ 59.00 FABS JANUARY 2015
198 Window frame type NC4F no. $ 96.00 FABS JANUARY 2015
199 Window frame type NDV1 no. $ 49.00 FABS JANUARY 2015
200 Window frame type NSADA no. $ 55.25 PG Building Suppliers JANUARY 2015

Pressed Steel Door Frames

On 230mm thick wall

201 Door frame size 762 x 2032mm high $ 59.50 PG Building Suppliers JANUARY 2015
202 Door frame size 1468 x 2336mm high $ 140.25 PG Building Suppliers JANUARY 2015
203 Door frame size 1410 x 2032mm high $ 140.25 PG Building Suppliers JANUARY 2015
204 Door frame size 813 x 2032mm high no. $ 55.00 FABS JANUARY 2015

232
205 Door frame size 1600 x 2032mm high no. $ 95.00 FABS JANUARY 2015
206 Door frame size 1410 x 2032mm high no. $ 56.09 Scotia Steel (PVT) LTD JANUARY 2015
207 Door frame size 813 x 2032mm high with fanlight size 813 x
368mm high no. $ 79.01 FABS JANUARY 2015
208 Door frame size 1468 x 2057mm high with fanlight size 1468 x
368mm high no. $ 153.00 PG Building Suppliers JANUARY 2015
209 Door frame size 1410 x 2032mm high with metal fanlight size 1410
x 368mm high no. $ 153.00 PG Building Suppliers JANUARY 2015
JANUARY 2015
ON 115mm thick wall JANUARY 2015
JANUARY 2015
210 Door frame size 762 x 2032mm high no. $ 32.71 Scotia Steel (PVT) LTD JANUARY 2015
211 Door frame size 813 x 2032mm high no. $ 45.00 FABS JANUARY 2015
212 Door frame size 813 x 2032mm high with fanlight size 813 x
368mm high no. $ 65.00 FABS JANUARY 2015
213 Door frame size 1410 x 2368mm high no. $ 51.41 Scotia Steel (PVT) LTD JANUARY 2015
214 Door frame size 1600 x 2032mm high no. $ 79.01 FABS JANUARY 2015

Roller Shutter Doors


(Installed complete by specialist)
215 Roller shutter doors Chain Operated doors 2400 x 2100 mm high No. $ 1,700.00 Winnerman Engineering JANUARY 2015
216 Roller shutter doors Chain Operated doors 2400 x 2400mm No. $ 1,900.00 Winnerman Engineering JANUARY 2015
217 Roller Shutter door size 2500 x 2500m mm high No. $ 900.00 Spritter Timber & Hardware JANUARY 2015
218 Griil Gate of size 2920 x 900mm, double leaf gate No. $ 591.75 Jenita Engineering JANUARY 2015
219 Griil Gate of size 2135x 900mm, double leaf gate No. $ 432.00 Jenita Engineering JANUARY 2015
220 Griil Gate of size 7500x 900mm, two double leaf gate No. $ 2,160.00 Jenita Engineering JANUARY 2015

Plastering and Wall Linings


221 Rhinoboards 3.6mm x 0.9mm =3.24m2 no. $ 16.00 FABS Hardware JANUARY 2015
222 Rhinoset 25kg $ 10.50 FABS Hardware JANUARY 2015
223 Rhinobond 25kg $ 10.50 FABS Hardware JANUARY 2015
224 Rhino Covebond 25kg $ 20.00 FABS & Builders Home JANUARY 2015
225 Tile Adhesive 20kg $ 5.22 Just Tiles JANUARY 2015
226 Light Grey Tile Grout 5kg $ 4.56 Just Tiles JANUARY 2015

233
227 Tile spacers 2mm ( pack contains 100) pack $ 2.61 Just Tiles JANUARY 2015
228 Tile spacers 3mm ( pack contains 100) pack $ 2.61 Just Tiles JANUARY 2015
229 Bonding Liquid litre $ 4.00 Just Tiles JANUARY 2015
230 Aluminium edge strips m $ 2.50 Tile and Carpet Centre JANUARY 2015
231 Rhino Cornice m $ 5.99 FABS/Builders Home JANUARY 2015
232 Cemprover 5 ltr $ 17.00 Open House JANUARY 2015

Tiling
233 400 x 400mm Ceramic floor Tiles (1 box/1.92m2) m2 $ 14.68 Tile and Carpet Centre JANUARY 2015
234 300 x 300 Ceramic Floor Tiles m2 $ 12.58 Tile and Carpet Centre JANUARY 2015
235 150 x150mm Elaine White glazed wall tiles with non-slip surface
(1 box/1.00m2) m2 $ 10.00 Tile and Carpet Centre JANUARY 2015
236 300 x 200mm ceramic wall tiles m2 $ 9.53 Just Tiles JANUARY 2015
237 full bodied 300 x 300 porcelain floor tiles (1 box/1.80m2) m2 $ 13.00 Tile and Carpet Centre JANUARY 2015
238 speckled 300 x 300 porcelain floor tiles (1 box/1.80m2) m2 $ 18.89 Tile and Carpet Centre JANUARY 2015
239 400 X 400mm - Porcelain floor Tiles m2 $ 17.00 Just Tiles JANUARY 2015
240 600 x 600mm - Porcelain Floor Tiles m2 $ 21.00 Tile and Carpet Centre JANUARY 2015
241 600 x 600mm - Metallic Porcelain Floor Tiles m2 $ 38.25 House of Tiles JANUARY 2015

Carpet
242 Carpet Berber Point 920 m2 $ 26.00 Tile and Carpet Centre JANUARY 2015
243 Nexbac Berber Point 650 Carpet tiles (500 x500) m2 $ 41.25 National Carpets & Curtains JANUARY 2015

Quarry Tiles

245 150 x 150 x 6mm Terra-coat red quary tiles (1 box/1.00m2) m2 $ 15.00 Tile and Carpet Centre JANUARY 2015

Mosaic Wall Tiles


246 19 x 19 x 3 mm (Coloured) Mosaic tiles m2 $ 66.00 Tile and Carpet Centre JANUARY 2015
247 19 x 19 x 3 mm White Rough Mosaic tiles m2 $ 55.55 Tile and Carpet Centre JANUARY 2015

234
Rubber Floor Tiles
248 500 x 500 x 4mm Rubber Floor Tiles m2 $ 40.00 Tile and Carpet Centre JANUARY 2015

Wood Flooring
249 Laminate flooring m2 $ 22.71 Tile and Carpet Centre JANUARY 2015
JANUARY 2015
Plumbing Works

Rainwater Disposal in PVC Piping

250 110mm Diameter PVC-Pipe CL16 m $ 14.03 P.G Building Suppliers JANUARY 2015
251 110mm PVC Bend no. $ 31.45 P.G Building Suppliers JANUARY 2015
252 100mm Diameter PVC Adaptor no. $ 15.30 P.G Building Suppliers JANUARY 2015
253 GI gutter,100 x 75mm (2400mm) Lgth $ 21.25 P.G Building Suppliers JANUARY 2015
254 GI down pipe, 100 x 75mm (2400mm) Lgth $ 21.25 P.G Building Suppliers JANUARY 2015
255 Concrete drip stone no. $ 17.00 P.G Building Suppliers JANUARY 2015
256 GI gutter shoe,100 x 75mm no. $ 5.10 P.G Building Suppliers JANUARY 2015
257 0.6mm galvanised sheet iron m2 $ 42.50 P.G Building Suppliers JANUARY 2015

Sanitary Plumbing
258 75mm Diameter Waste Pipe - PVC m $ 59.50 P.G Building Suppliers JANUARY 2015
259 50mm Diameter Waste Pipe - PVC m $ 14.03 P.G Building Suppliers JANUARY 2015
260 50mm PVC bend no. $ 3.40 P.G Building Suppliers JANUARY 2015
261 110mm PVC Bend no. $ 31.45 P.G Building Suppliers JANUARY 2015
262 110mm PVC UB42 no. $ 7.65 P.G Building Suppliers JANUARY 2015
263 110mm PVC UB41 no. $ 7.65 P.G Building Suppliers JANUARY 2015
264 50mm Y-junction no. $ 5.95 P.G Building Suppliers JANUARY 2015
265 50mm square junction no. $ 4.25 P.G Building Suppliers JANUARY 2015
266 15mm coupling no. $ 2.98 P.G Building Suppliers JANUARY 2015
267 22mm coupling no. $ 4.25 P.G Building Suppliers JANUARY 2015

Cap Reducers,Cap Tees, Cap Elbow and inspection eyes


268 67 to 28mm Cap reducer no $ 18.28 J . Mann & Company JANUARY 2015

235
269 54 to 42 mm Reducer no $ 13.95 Copper King P\L JANUARY 2015
270 54 to 28 mm Reducer no $ 32.38 Copper King P\L JANUARY 2015
271 42 to 35 mm Reducer no $ 12.30 Copper King P\L JANUARY 2015
272 42 to 28 mm Reducer no $ 19.22 Copper King P\L JANUARY 2015
273 35 to 28 mm Reducer no $ 5.40 J . Mann & Company JANUARY 2015
274 35 to 22 mm Reducer no $ 5.00 J . Mann & Company JANUARY 2015
275 22 x 22 x 15 mm Reducing tee no $ 20.00 J . Mann & Company JANUARY 2015
276 54 x 42 mm Reducing tee no $ 32.36 Copper King P\L JANUARY 2015
277 42 x 35 mm Reducing tee no $ 12.30 Copper King P\L JANUARY 2015
278 54 mm Equal tee no $ 4.00 Copper King P\L JANUARY 2015
279 42 mm Equal tee no $ 17.51 Copper King P\L JANUARY 2015
280 28 mm Equal tee no $ 3.68 J . Mann & Company JANUARY 2015
281 32 mm Equal tee no $ 10.53 Copper King P\L JANUARY 2015
282 54 mm Elbow no $ 13.45 J . Mann & Company JANUARY 2015
283 42 mm Elbow no $ 7.57 Copper King P\L JANUARY 2015
284 35 mm Elbow no $ 3.75 Copper King P\L JANUARY 2015
285 22 mm Elbow no $ 0.40 Copper King P\L JANUARY 2015
286 White Tape no $ 0.22 Copper King P\L JANUARY 2015
287 28mm Masterbats no $ 16.00 Copper King P\L JANUARY 2015
288 Brass holder bat no $ 7.71 J . Mann & Company JANUARY 2015

Pvc Fittings
289 40mm IE Bend no. $ 4.25 P.G Building Suppliers JANUARY 2015
290 110mm Bend Access Heel 135 deg no. $ 7.65 P.G Building Suppliers JANUARY 2015
291 110mm Bend Plain 135 deg no. $ 7.65 P.G Building Suppliers JANUARY 2015
292 110mm Bend Plain 95 deg no. $ 7.65 P.G Building Suppliers JANUARY 2015
293 50mm Bend Plain 135 deg no. $ 7.65 P.G Building Suppliers JANUARY 2015
294 50mm Bend Plain 95 deg no. $ 4.25 P.G Building Suppliers JANUARY 2015
295 50mm PVC Bend I/E no. $ 4.25 P.G Building Suppliers JANUARY 2015
296 50-100mm PVC Junction 135 deg no. $ 20.40 P.G Building Suppliers JANUARY 2015
297 100mm Junction 45* - PVC no. $ 10.20 P.G Building Suppliers JANUARY 2015
298 110mm Straight Pan Connector - PVC no. $ 5.10 P.G Building Suppliers JANUARY 2015
299 110mm Junction 95* - PVC no. $ 10.20 P.G Building Suppliers JANUARY 2015

236
300 100mm Gulley trap - PVC no. $ 5.95 P.G Building Suppliers JANUARY 2015
301 100mm Gulley head and grating - PVC no. $ 5.95 P.G Building Suppliers JANUARY 2015
302 40mm Rubber "P" Trap no. $ 8.50 P.G Building Suppliers JANUARY 2015
303 100mm CI Gulley trap no. $ 5.78 Proscheme Hardware JANUARY 2015
304 40mm copper P-trap no. $ 7.81 Proscheme Hardware JANUARY 2015
305 110mm EW 45"-Y-junction no. $ 4.25 Proscheme Hardware JANUARY 2015
306 110mm Plain stop end no. $ 4.25 Pro Plastics JANUARY 2015

Sanitary Fittings
307 1200mm Long Single Bowl Sink no. $ 170.85 P.G Building Suppliers JANUARY 2015
308 1200mm Long Double Bowl Sink no. $ 198.90 P.G Building Suppliers JANUARY 2015
309 1600mm Long Single Bowl Sink no. $ 195.50 P.G Building Suppliers JANUARY 2015
310 150 x 150mm Toilet Roll Holder no. $ 15.30 P.G Building Suppliers JANUARY 2015
311 Toilet pan white no. 22.95 DST JANUARY 2015
312 Toilet Cistern white no. 36.55 DST JANUARY 2015
313 15mm cp pillar taps no. 14.03 DST JANUARY 2015
314 Vaal Lotus WHB Basin no. $ 67.15 P.G Building Suppliers JANUARY 2015
315 Universal Pedestal no. $ 51.00 P.G Building Suppliers JANUARY 2015
316 Chanel White Bath with handles no. $ 102.00 House of Tiles JANUARY 2015
317 Albion basin mixer no. $ 68.00 House of Tiles JANUARY 2015
318 Cobra sink mixer no. $ 74.80 House of Tiles JANUARY 2015
318 15mm sink mixer no. $ 112.20 DST JANUARY 2015
319 Shower rose ballpoints no. $ 31.45 House of Tiles JANUARY 2015
320 Shower arm no. $ 27.20 House of Tiles JANUARY 2015
321 Vaal flatback urinal complete with FJ6000 Flushmaster valve and
tailpipe no. $ 350.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
322 no. $ 250.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
323 Courier wash hand basin complete with universal pedestal,Cp waste
and one pillar tap no. $ 180.00 Plumbing Africa (Pvt) Ltd JANUARY 2015

Copper Tubing
324 15mm Diameter Pipe m $ 45.05 Open House JANUARY 2015
325 22mm Diameter Pipe m $ 49.30 Open House JANUARY 2015

237
326 15mm Cap Elbow no. $ 5.10 Open House JANUARY 2015
327 22mm Cap Elbow no. $ 5.95 Open House JANUARY 2015
328 15mm Cap Tee no. $ 4.25 Open House JANUARY 2015
329 22mm Cap Tee no. $ 5.10 Open House JANUARY 2015
330 Cobra Ref P.A 13ZPK Geyser Valve Pack no. 172.50 The PlumbHouse JANUARY 2015
331 110mm PVC Access Junction SY42 no. 7.48 The PlumbHouse JANUARY 2015
332 110mm PVC Access Double Junction SY404 no. 13.05 The PlumbHouse JANUARY 2015
333 20mm Brass Gate Valve F/F no. 16.17 The PlumbHouse JANUARY 2015
334 20mm c/mi Capillary Coupling no. 1.67 The PlumbHouse JANUARY 2015
335 28-22mm C/C/C Capillary Reducing Tee no. 6.08 The PlumbHouse JANUARY 2015
336 22-15mm C/C Capillary Reducing Tee no. 2.45 The PlumbHouse JANUARY 2015
337 PTFE Thread Tape no. 0.18 The PlumbHouse JANUARY 2015
338 35-28mm C/C Capillary Reducing Coupling no. 15.00 The PlumbHouse JANUARY 2015
339 22-15mm C/C /C Capillary Reducing Tee no. 2.45 The PlumbHouse JANUARY 2015
340 110mm PVC Vent Valve SAV110 no. 6.09 The PlumbHouse JANUARY 2015
341 32mm Brass Gate Valve F/F no. 23.16 The PlumbHouse JANUARY 2015
342 28mm C/MI Capillary Coupling no. 3.71 The PlumbHouse JANUARY 2015
343 110mm PVC Access Junction SY42 no. 7.48 The PlumbHouse JANUARY 2015
344 20mm CMI Capillary Coupling no. 1.67 The PlumbHouse JANUARY 2015
345 28-22mm C/C Capillary Reducing Coupling no. 7.00 The PlumbHouse JANUARY 2015
346 Soldering Wire roll 39.00 The PlumbHouse JANUARY 2015
347 Soldering Flux no. 7.84 The PlumbHouse JANUARY 2015
348 15mm C/C Capillary Elbow no. 2.61 The PlumbHouse JANUARY 2015
349 22mm C/C Capillary Coupling no. 0.73 The PlumbHouse JANUARY 2015
350 35mm C/C Capillary Elbow no. 5.00 The PlumbHouse JANUARY 2015
351 500ml Plumbers Delight no. 6.09 The PlumbHouse JANUARY 2015
352 PTFE Thread Pipe roll 0.18 The PlumbHouse JANUARY 2015
353 C Pack no. 31.45 The PlumbHouse JANUARY 2015
354 40x40mm rubber p trap no. 5.95 The PlumbHouse JANUARY 2015
355 40x32mm rubber p trap no. 5.95 The PlumbHouse JANUARY 2015
356 40x32mm rubber s trap no. 6.80 The PlumbHouse JANUARY 2015
357 50mm waste pipe 6m/len no. 6.80 The PlumbHouse JANUARY 2015
358 40mm brass shower p trap no. 15.30 The PlumbHouse JANUARY 2015

238
359 50mm Pvc ie Elbow no. 1.15 The PlumbHouse JANUARY 2015
360 110mm pvc two vent valve no. 6.38 The PlumbHouse JANUARY 2015
361 110mm pvc pan connector no. 5.53 The PlumbHouse JANUARY 2015
362 110mm pvc ie junction sy42 no. 7.65 The PlumbHouse JANUARY 2015
363 110mm pvc surface pipe / len no. 30.60 The PlumbHouse JANUARY 2015
364 15mm copper tap adaptor no. 3.40 The PlumbHouse JANUARY 2015
365 15mm flex connector no. 5.10 The PlumbHouse JANUARY 2015
366 500ml solvent cement no. 5.10 The PlumbHouse JANUARY 2015
367 Thread Tap roll 0.42 The PlumbHouse JANUARY 2015
368 15mm copper pipe /len no. 27.48 The PlumbHouse JANUARY 2015
369 20mm copper pipe /len no. 41.65 The PlumbHouse JANUARY 2015
370 20mm c/mi coupling no. 2.25 The PlumbHouse JANUARY 2015
371 20mm copper elbow no. 2.98 The PlumbHouse JANUARY 2015
372 20mm copper tee no. 3.40 The PlumbHouse JANUARY 2015
373 20-15mm copper red coupling no. 3.83 The PlumbHouse JANUARY 2015
374 15mm copper tee no. 2.47 The PlumbHouse JANUARY 2015
375 15mm c/mi coupling no. 2.51 The PlumbHouse JANUARY 2015
376 15mm c/fi coupling no. 1.66 The PlumbHouse JANUARY 2015
377 35mm Vsp socket adaptor no. 5.00 The PlumbHouse JANUARY 2015
378 25mm Vsp socket adaptor no. 3.50 Builder's Home JANUARY 2015
379 15mm Brass Stop Cock no. $ 15.30 Builder's Home JANUARY 2015
380 22mm Brass Stop Cock no. $ 17.00 Builder's Home JANUARY 2015
381 15mm Brass Gate Valve no. $ 14.45 Builder's Home JANUARY 2015
382 110mm x 50mm accentric reducer no. $ 17.00 Builder's Home JANUARY 2015
383 22mm Brass Gate Valve no. $ 16.15 The PlumbHouse JANUARY 2015
384 32mm Brass Gate Valve no. $ 20.57 The PlumbHouse JANUARY 2015
385 40mm Brass Gate Valve no. $ 25.20 The PlumbHouse JANUARY 2015
386 65mm Brass Gate Valve no. $ 72.31 The PlumbHouse JANUARY 2015
387 15mm Copper Connector (300mm long) no. $ 12.75 The PlumbHouse JANUARY 2015
388 22mm Copper Connector (300mm Long) no. $ 15.30 The PlumbHouse JANUARY 2015
389 15mm CP Undertile Stopcock no. $ 31.45 The PlumbHouse JANUARY 2015
390 solvent cement 500ml no. $ 10.20 The PlumbHouse JANUARY 2015
391 15mm brass stop cork no. $ 15.30 The PlumbHouse JANUARY 2015

239
392 10mm Galvanised thread bar no. $ 8.00 The PlumbHouse JANUARY 2015
393 10mm Galvanised nuts no. $ 0.18 The PlumbHouse JANUARY 2015
394 12mm masonry drill bits no. $ 3.48 The PlumbHouse JANUARY 2015
395 Minimal Float Control for high and low water level no. $ 48.75 The PlumbHouse JANUARY 2015

Soil Drainage Service


396 110mm dia Pvc pipe UL420 $ 12.00 Open house JANUARY 2015
397 110mm plain bend $ 11.00 Open house JANUARY 2015
398 110mm x 45 plain junction $ 15.00 Open house JANUARY 2015
399 110mm gullley P trap assembly $ 18.00 Open house JANUARY 2015
400 110mm x 45 deg ABC cleaning eye cover $ 12.00 Open house JANUARY 2015

GEYSERS
404 100 Litre Roof Geyser no. $ 380.00 Union Hardware JANUARY 2015
405 50 Litre pressure type geyser no. $ 493.00 P.G Building Suppliers JANUARY 2015
406 100 Litre pressure type geyser no. $ 532.95 P.G Building Suppliers JANUARY 2015
407 200 Litre pressure type geyser no. $ 671.50 P.G Building Suppliers JANUARY 2015
408 50 Litre Horizontal Pressure Geyser no. $ 885.00 UBM JANUARY 2015
409 100 Litre Horizontal Pressure Geyser no. $ 1,066.13 UBM JANUARY 2015
410 200 Litre Horizontal Pressure Geyser no. $ 1,575.00 UBM JANUARY 2015
411 6000 Litres Low profile tanks no. $ 765.00 UBM JANUARY 2015
412 200 Litre Copper Floats no. $ 58.22 UBM JANUARY 2015
413 65mm kent water meter no. $ 990.15 UBM JANUARY 2015

Fire Services Installations


Fire Appliances
414 Jet Master Fire Place no. $ 750.00 DST JANUARY 2015
415 200 x 200mm Asbestos Cement flue liners 4m $ 14.60 Union Hardware JANUARY 2015
416 30mm swing type fire hose reel no. $ 600.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
417 9 litre water gas fire extinguisher no. $ 85.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
418 Fire point signs no. $ 10.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
419 Allow for locating,excavate and connect into existing supplies Item $ 100.00 Plumbing Africa (Pvt) Ltd JANUARY 2015

240
420 28mm dia copper pipe $ 15.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
421 54mm dia copper pipe $ 58.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
422 75mm dia Pvc pipe as sleeve for 54mm dia copper pipe $ 7.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
423 28mm cap elbow $ 3.50 Plumbing Africa (Pvt) Ltd JANUARY 2015
424 54mm cap elbow $ 18.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
425 54mm cap tee $ 30.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
426 54mm cxmi coupling $ 11.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
427 28mm lever operated valve $ 15.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
428 54mm brass gate valve $ 60.00 Plumbing Africa (Pvt) Ltd JANUARY 2015
429 25mm socket union $ 12.00 Plumbing Africa (Pvt) Ltd JANUARY 2015

Glazing
432 3mm Clear sheet glass m2 $ 7.65 City Glass JANUARY 2015
433 3mm obscure glass m2 $ 3.00 P G Glazing / DST Glass JANUARY 2015
434 Mirror m2 $ 12.00 P G Glazing / DST Glass JANUARY 2015
435 4mm clear glass m2 $ 14.45 Sprittler Hardware JANUARY 2015
436 6mm polished glass 2400 x750mm no. $ 229.50 P G Glazing / DST Glass JANUARY 2015
437 5mm Mirror ,450*600 no. $ 68.00 City Glass JANUARY 2015
438 8mm clear glass m2 $ 56.10 Sprittler Hardware JANUARY 2015
439 Putty kg $ 3.00 City Glass JANUARY 2015
440 Turps litr $ 2.55 P G Building Suppliers JANUARY 2015

Paintig
441 External quality PVA 20L $ 65.00 DULUX JANUARY 2015
442 Internal quality PVA 20L $ 65.00 DULUX JANUARY 2015
443 Undercoat White 5L $ 33.54 DULUX JANUARY 2015
444 High gloss White 5L $ 35.99 DULUX JANUARY 2015
445 Pink Wood Primer 5L $ 28.00 DULUX JANUARY 2015
446 Universal clear vanish 5L $ 35.30 DULUX JANUARY 2015
447 Eggshel Enamel White Paint 5L $ 38.64 DULUX JANUARY 2015
448 Sanding sealer L $ 9.10 DULUX JANUARY 2015

241
449 Mineral Turpentine 5L $ 13.00 DULUX JANUARY 2015
450 Ceiling White PVA 20L $ 45.00 DULUX JANUARY 2015
451 Metal Primer 5L $ 48.95 DULUX JANUARY 2015
452 Zinc Phosphate Primer 5L $ 34.00 DULUX JANUARY 2015
453 Crake Filler 2kgs $ 4.00 BUILDER HOME JANUARY 2015
454 Rhinoset 25kgs $ 10.00 FABS Hardware JANUARY 2015
455 Aluminium bituminous paint 20L $ 140.00 DULUX JANUARY 2015
456 Primer Undercoat 25L 25litres $ 80.00 DULUX JANUARY 2015
457 Red Oxide Primer litr $ 8.50 P G Building Suppliers
JANUARY 2015
458 Metal Primer litr $ 10.20 DST JANUARY 2015
459 Thinners litr $ 16.15 P G Building Suppliers
JANUARY 2015
460 Filler Coat
Clean down fine wood float plasterd walls & apply one coat litr $ 7.65 P G Building Suppliers
JANUARY 2015
461 primer,trowel JANUARY 2015
463 Cemprover 5Ltr $ 17.00 Open House JANUARY 2015
464 Silicone Tube clear no. 6.8 DST JANUARY 2015

Fuel/Oils JANUARY 2015


465 Diesel Lt $ 1.30 Total JANUARY 2015
466 Petrol Lt $ 1.40 Total JANUARY 2015
467 Hydraulic Oil Lt $ 5.00 Total JANUARY 2015
468 Engine Oil Lt $ 5.00 Total JANUARY 2015
469 Paraffin Lt $ 1.00 Total JANUARY 2015
470 Turbomax oil Lt $ 6.00 Total JANUARY 2015

Preliminary and General Items


471 Concrete pan Wheelbarrows no. $ 18.70 Building Centre JANUARY 2015
472 Round Nose Shovels no. $ 12.75 Building Centre JANUARY 2015
473 Plastic Builders Buckets 10L no. $ 15.00 Halsted Brothers JANUARY 2015
474 20mm Diameter Rubber Jet Hose Pipe m $ 2.00 Mica Hardware JANUARY 2015
475 Overalls-small each $ 18.50 James North JANUARY 2015
476 Overalls-size 42 to46 each $ 19.50 James North JANUARY 2015
477 Overalls-size 48 to 50 each $ 48.50 James North JANUARY 2015

242
478 Hard Hats each $ 4.50 James North JANUARY 2015
479 Safety shoes each $ 32.00 James North JANUARY 2015
480 Bar of Soap each $ 1.50 T.M JANUARY 2015

Electricals
481 19mm pvc conduit pipe no. $ 1.00 AMANAT JANUARY 2015
482 19mm pvc conduit coupling no. $ 0.03 AMANAT JANUARY 2015
483 19mm pvc conduit nipple no. $ 0.02 AMANAT JANUARY 2015
484 Pvc round boxes no. $ 20.00 AMANAT JANUARY 2015
485 3 x3 pvc flush boxes no. $ 0.30 AMANAT JANUARY 2015
486 6x 3 pvc flush boxes no. $ 0.70 AMANAT JANUARY 2015
487 19mm be saddles no. $ 0.10 AMANAT JANUARY 2015
488 4.0x35mm wood screw each $ 6.00 AMANAT JANUARY 2015
489 2.5mm single core cable roll $ 37.00 AMANAT JANUARY 2015
490 1.5mm single core cable roll $ 24.99 AMANAT JANUARY 2015
491 2.5mm earth wire kg $ 19.99 AMANAT JANUARY 2015
492 14 way db box no. $ 12.00 AMANAT JANUARY 2015
493 60amp single pole mcb no. $ 12.33 AMANAT JANUARY 2015
494 20amp single pole mcb no. $ 9.18 AMANAT JANUARY 2015
495 30amp single pole mcb no. $ 9.18 AMANAT JANUARY 2015
496 5amp single pole mcb no. $ 9.18 AMANAT JANUARY 2015
497 19mm be coupling no. $ 2.25 AMANAT JANUARY 2015
498 19mm pvc adaptor no. $ 0.21 AMANAT JANUARY 2015
499 13amp d/ s/outlet no. $ 5.99 AMANAT JANUARY 2015
500 3 gang 3 way switch no. $ 4.50 AMANAT JANUARY 2015
501 2gang 2 way switch no. $ 3.50 AMANAT JANUARY 2015
502 1 gang 2 way switch no. $ 2.50 AMANAT JANUARY 2015
503 4ft double fitting no. $ 8.99 AMANAT JANUARY 2015

243
Remarks

excluding vat

excluding vat
excluding vat

excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat

244
excluding vat
excluding vat

245
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat

excluding vat

excluding vat
excluding vat
excluding vat
excluding vat

246
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat

excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

247
excluding vat

248
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat

249
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

250
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

251
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat

252
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat

253
excluding vat
excluding vat

excluding vat

excluding vat

excluding vat

excluding vat
excluding vat

excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
Supply and fix
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

254
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat

excluding vat

excluding vat
excluding vat

255
excluding vat

excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat

256
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

257
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat

excluding vat

excluding vat
excluding vat

258
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

259
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

260
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excl vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

261
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

262
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

263
excluding vat
excluding vat
excluding vat

excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat
excluding vat

264
PLANT MATERIAL BASIC PRICE LIST

ITEM DESCRIPTION UNIT RATES SUPPLIER DATE REMARKS

Fuel/Oils
1 Diesel Lt $ 1.30 Total February 2012
2 Petrol Lt $ 1.40 Total February 2012
3 Hydraulic Oil Lt $ 5.00 Total February 2012
4 Engine Oil Lt $ 5.00 Total February 2012
5 Paraffin Lt $ 1.00 Total February 2012
6 Turbomax oil Lt $ 6.00 Total February 2012

7 Plant Hire rates


8 TLB Case Hr $ 60.00 Atlas Earth movers February 2012 dry
9 Concrete Dumper (2.5 tonne) day $ 120.00 Atlas Earth movers February 2012 dry
10 Plate Compactor (60Kgs) day $ 35.00 Atlas Earth movers February 2012 dry
11 Reversible Plate Compactor (305kg) day $ 95.00 Atlas Earth movers February 2012 dry
12 Pedestrian Roller (600kgs) day $ 120.00 Atlas Earth movers February 2012 dry
13 Concrete Mixer 750/500L day $ 120.00 Atlas Earth movers February 2012 dry
14 Concrete Mixer 500/330L day $ 70.00 Atlas Earth movers February 2012 dry
15 Concrete Mixer 230/175L day $ 35.00 Atlas Earth movers February 2012 dry
16 Concrete Mixer 7/10 day $ 40.25 Atlas Earth movers January 2012 dry
17 Diaphragm Water Pump (max 10m) Hr $ 45.00 Atlas Earth movers February 2012 dry
18 Drive unit & Poker set day $ 40.00 Atlas Earth movers February 2012 dry
19 Petrol Generator 5 kva day $ 35.00 Atlas Earth movers February 2012 dry
20 Petrol Generator Welder 7.2 kva day $ 45.00 Atlas Earth movers February 2012 dry
21 Diesel powered concrete mixer Hr $ 23.73 Atlas Earth movers January 2012 dry
22 Powerfloat day $ 35.00 Atlas Earth movers February 2012 dry
23 Jack Hammer day $ 150.00 Atlas Earth movers February 2012 dry

PLANT BASIC PRICE LIST


265
TN ZUNZANYIKA ASSOCIATES
ITEM DESCRIPTION UNIT RATES SUPPLIER DATE REMARKS
24 Magnetic Base Drill day $ 45.00 Atlas Earth movers February 2012 dry
25 Bomag Roller day $ 200.00 Rollem Plant Hire January 2012 dry
26 Poker Vibrator day $ 46.00 Atlas Earth movers January 2012 dry
27 190 c.f.m -compressor day $ 65.00 Roncol Compressor Hire January 2012 wet
28 350 c.f.m - compressor day $ 130.00 Roncol Compressor Hire January 2012 wet
29 Bulldozer hr $ 115.00 Ronndebult Zimbabwe (Pvt) Ltd March 2012 dry
30 Grader hr $ 110.00 Ronndebult Zimbabwe (Pvt) Ltd March 2012 dry
31 Roller hr $ 70.00 Ronndebult Zimbabwe (Pvt) Ltd March 2012 dry
32 Water bowser hr $ 70.00 Ronndebult Zimbabwe (Pvt) Ltd March 2012 dry
33 Tipper Truck km $ 2.50 Ronndebult Zimbabwe (Pvt) Ltd March 2012 dry
34 Front Ent Loader hr $ 70.00 Ronndebult Zimbabwe (Pvt) Ltd March 2012 dry
35 Excavator hr $ 85.00 Ronndebult Zimbabwe (Pvt) Ltd March 2012 dry
36 Tipper (5m3) hr $ 54.81 Heritage Construction Company March 2012
37 Tractor hr $ 74.47 Heritage Construction Company March 2012

PLANT BASIC PRICE LIST


266
TN ZUNZANYIKA ASSOCIATES
PLANT BASIC PRICE LIST
267
TN ZUNZANYIKA ASSOCIATES
RATE BUILLD UP
2021

QS JERE
ALL-IN-LABOUR RATES
EFFECTIVE 01 JANUARY 2021

WORKER CLASSIFICATION CONTRIBUTION CARPENTERS AND PLUMBERS

WORKER GRADE WG1 WG2 WG3 WG4 WX SW4 SW3 SW2


BASIC RATE 1.63 1.63 1.68 1.70 2.22 2.22 2.42 2.60

BASIC WEEKLY WAGE 71.72 71.72 73.92 74.80 97.68 97.68 106.48 114.40
NSSA 0.0248 1.78 1.78 1.78 1.78 1.78 1.78 1.78 1.78
TOOLS ALLOWANCE 0.0700 n/a n/a n/a n/a 3.08 3.08 3.08 3.08
PENSION FUND 0.0500 3.59 3.59 3.70 3.74 4.88 4.88 5.32 5.72
GENERAL FUND 0.0250 1.79 1.79 1.85 1.87 2.44 2.44 2.66 2.86
OVERALLS (2*$12.05/44.8) 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54
RUBBER BOOTS ($13.9/44.8) 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31
HARD HATS ($5.9/44.8} 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
INDUSTRIAL LEAVE DAYS 11 DAYS
LEAVE 30 DAYS
SICK LEAVE 5 DAYS
TOTAL 46 DAYS
IE (9.2 WEEKS x RATE)/44.8 14.73 14.73 15.18 15.36 20.06 20.06 21.87 23.49
SOAP ($1.50*22.4)/44.8 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
TEA 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
WORKERS COMPENSATION 0.0275 1.97 1.97 2.03 2.06 2.69 2.69 2.93 3.15
MANDATA LEVY 0.0100 0.72 0.72 0.74 0.75 0.98 0.98 1.06 1.14
STANDARDS LEVY 0.0015 0.11 0.11 0.11 0.11 0.15 0.15 0.16 0.17
TRANS.ALLOW.$5.00/WEEK 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
TOTALS PER WEEK 108.13 108.13 111.04 112.20 145.46 145.46 157.07 167.52

TOTALS PER SHIFT 2.46 2.46 2.52 2.55 3.31 3.31 3.57 3.81

DAYWORK RATES (+40%) 3.44 3.44 3.53 3.57 4.63 4.63 5.00 5.33

Safety shoes for Carpenters, Painters & Watchmen

ALL IN LABOUR RATES 268


RATE BUILLD UP
2021

WORKER CLASSIFICATION CONTRIBUTION BRICKLAYERS & PLASTERERS PAINTERS


WORKER GRADE SW1 SW2 SW3 SW4 WX SW1 SW2 SW3
BASIC RATE 2.81 2.60 2.42 2.22 2.22 2.81 2.60 2.42

BASIC WEEKLY WAGE 123.64 114.40 106.48 97.68 97.68 123.64 114.40 106.48
NSSA 0.0248 1.78 1.78 1.78 1.78 1.78 1.78 1.78 1.78
TOOLS ALLOWANCE 0.0138 1.71 1.71 1.71 1.71 1.71 1.29 1.29 1.29
PENSION FUND 0.0500 6.18 5.72 5.32 4.88 4.88 6.18 5.72 5.32
GENERAL FUND 0.0250 3.09 2.86 2.66 2.44 2.44 3.09 2.86 2.66
OVERALLS (2*$12.05/44.8) 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54
RUBBER BOOTS ($13.9/44.8) 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31
HARD HATS ($5.9/44.8} 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
INDUSTRIAL LEAVE DAYS 11 DAYS
LEAVE 30 DAYS
SICK LEAVE 5 DAYS
TOTAL 46 DAYS
IE (9.2 WEEKS x RATE)/44.8 25.39 23.49 21.87 20.06 20.06 25.39 23.49 21.87
SOAP ($1.50*22.4)/44.8 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
TEA 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
WORKERS COMPENSATION 0.0275 3.40 3.15 2.93 2.69 2.69 3.40 3.15 2.93
MANDATA LEVY 0.0100 1.24 1.14 1.06 0.98 0.98 1.24 1.14 1.06
STANDARDS LEVY 0.0015 0.19 0.17 0.16 0.15 0.15 0.19 0.17 0.16
TRANS.ALLOW.$5.00/WEEK 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
TOTALS PER WEEK 178.34 166.15 155.70 144.09 144.09 177.92 165.73 155.28

TOTALS PER SHIFT 4.05 3.78 3.54 3.27 3.27 4.04 3.77 3.53

DAYWORK RATES (+40%) 5.67 5.29 4.95 4.58 4.58 5.66 5.27 4.94

ALL IN LABOUR RATES 269


RATE BUILLD UP
2021

SW1
2.81

123.64
1.78
3.08
6.18
3.09
0.54
0.31
0.13

25.39
0.75
5.00
3.40
1.24
0.19
5.00
179.71

4.08

5.72

ALL IN LABOUR RATES 270


RATE BUILLD UP
2021

WATCHMEN
SW4
2.22 11.52

97.68 80.64
1.78 1.78
1.29
4.88 4.03
2.44 2.02
0.54 0.54
0.31 0.31
0.13 0.13

20.06 16.56
0.75 0.75
5.00 5.00
2.69 2.22
0.98 0.81
0.15 0.12
5.00 5.00
143.67 119.90

3.27 17.13

4.57 23.98

ALL IN LABOUR RATES 271

You might also like