Progress Matrix

(Comprehensive)
31st March 2021

Reference Number Activity Status as @ 15/03/2021 Dashboard


(Procurement Indicator
Plan)
ZONES 2&3
COMPONENT 1: WATER SUPPLY INVESTMENT
Refurbishment of Boreholes in Zone 2 and 3 (Maputsoe Pre contract meeting was on the 07/01/2021
Boreholes) Method Statement from Contractor received on 02/02/2021, and
the ESMP received on the 08/02/2021.
Contract signed by both the Contractor and the PS Water.
Kick-Off meeting between Contract Management Team and
Consultant to be held on 03/03/2021
Sod-Turning ceremony held and officiated by the Right
Honourable The Prime Minister of Lesotho, Dr. Majoro.
Contract Management Team holding Site Visitations. Current
activities include:
1. Hydrological surveyors in line with the Method Statement
There are issues that need to be addressed and cleared
immediately:
1. Sharing of Servitudes with other Service-Providers;
2. Permission to use Roads Directorate Assets;
3. Replacement of the current Hydrologist.
Environmental Flow assessment (EFA) and water quality Contract signed on 11/12/2020.
modelling within the LLWDP II Hlotse River Kickoff meeting held on 17/12/2020
Climate Data Reports from the Lesotho Meteorological Services
(LMS) sent to the Consultant on 03/02/2021.
Draft Inception Report received on 08/02/2021
There has been noted discrepancies in the report, especially on

1
timing. This to be discussed with the Consultant. The Final
Inception Report only due in April 2021.
Stakeholder Engagement conducted on week of 22/02/2021, with
specific consultation of the Local Councilors from the
participating districts.
All requested historic climate data from LMS submitted to
consultant. (Only left with acquiring the evapotranspiration data
from LMS).
Consultant has done physical selection of Sites for Water Quality
Monitoring and report to be provided by Consultant.
Final Inception Report expected on 28/04/2021.

Asset verification mapping and development of geo- Contract signed on 05/11/2020


referenced asset register within the LLWDP II Kick Off meeting with Consultant held on 19/11/2020.
Field reconnaissance visit with Consultant undertaken on
20/11/2020.
Draft Inception report submitted on 15/12/2020, and reviewed
with comments.
Final inception report received on the 4 th January 2021 and
cleared review by PIU-Acceptance letter sent.
1st Milestone (10%) Invoice received and paid to the tune of
M695,290
Received Stakeholder Engagement Plan Draft on 17/02/2021
Consultations of Projected Affected Persons programme has
commenced:
a. Local Authority (Chiefs and Councillors) consultations
complete;
b. Asset verification mapping on-going. Exercise complete in
Ha Lesiamo-Sebothoane; and now currently on the
Hlotse-Maputsoe path.
Heritage (Archaeological and paleontology) impact Contract signed on 07/09/2020.
assessment (HIA) within the LLWDP II Mobilization period ( Ended 16/10/2020)
Inception Report & Stakeholder Engagement Plan Report (Final)
received on 17/12/2020 and approved.
Finalized the Announcements (in Sesotho and English) of the HIA

2
and have been published in local newspapers on 25/02/2021
Field trips commenced on 15/03/2021, ending 24/03/2021,
where an preliminary list shall be submitted.
Revised schedule submitted (10/03/2021) that takes into account
how the 2 weeks lost due to Covid-19 is to be recovered.
Design Review and Construction Supervision Consultant TORs complete
EOI Assessment complete
Revised EOI Assessment Report cleared by World Bank on
12/11/2020
RFP complete and approved on 14/12/2020
RFPs sent to Shortlisted consultants on 16/12/2020.
Due on 28/01/2020 (Extended to 10/03/2021)
Clarifications Responses sent to the World Bank on 02/02/2021.
TORs and RFP revised and updated to incorporate clarifications
from Applicants. Updated TORs and RFP sent to the World Bank
for Approval
No-Objection received from the World Bank on 08/03/2021; and
the Revised RFPs sent to the Firms on 09/03/2021
Water Quality Monitoring On-going
Rehabilitation of Hydrometric Stations Sites identified
Plan & Budget complete
Sourcing of Quotations for Material(s)
Consultations with the local community on-going on possible
development assistance in their area
Need to complete community consultations at Hlobola
Procurement of materials under GoL underway.
To update the Procurement Plan to include Equipment to be
sourced under World Bank.
Procurement of materials on-going after delays caused by the
National Lockdown.
Material being received.
Water Security Proposal complete and shared with the LHWC
Initial Information meeting held between LHWC, CoW & PIU
Pending follow-up meeting to discuss detailed water

3
requirements to 2045
Communication sent to LHWC to revive talks under this
programme
COMPONENT 2: PROJECT MANAGEMENT& INSTITUTIONAL CAPACITY BUILDING
Project Management Consultant No-Objection issued for EOI Assessment Report
RFP complete and under review by the EIB
The RFP for PMC being finalized (Version 8).
Revised RFP sent to the EIB for their review and approval.
Email approval received on 15/03/2021. Waiting for the signed
clearance from the EIB, so to issue out the RFPs by 17/03/2021.
Procurement of ICT Equipment Delivery of equipment complete (First & second batch of
equipment received on 13/11/2020 and 04/12/2020)
Lot 2 (Networking) complete
LEWA TA on Compliance & Auditing TORs complete
EOI Assessment complete
RFP issued to qualifying Consultant on 08/12/2020
RFPs received and opened on 29/01/2020.
Technical Evaluations completed on 19/02/2021.
Financial Opening done on 10/03/2021.
Establishment of institutional framework for the Lesotho TORs under revision
Bulk water operation (BWA) Revised TORs updated into STEP and sent to the World Bank for
clearance to the 31/01/2021.
No-Objection received on 09/02/2021
Request for EOI published on 11/02/2021 and 13 EOIs received by
the Tender Panel on 25/02/2021.
Assessment complete, and 1 firm shortlisted; RFP also completed
(12/03/2021)
TA support for development of sanitation investment plan Proposal & TORs development complete
including WASH Programme. 21 Stakeholder organizations identified and written formal letters
for participation in Stakeholders Review Workshop proposed for
end of February 2021.
2nd Sanitation Deep-Dive with the World Bank held on
24/02/2021 to discuss the tools for Rapid Assessment. Agreed
that: A. Stakeholder Consultation to be held at later stage. 2.
Mehta (World Bank) to review current TORs (05/03/2021); C.

4
Lesotho Team to update the current TORs & Proposal in
preparation for the Stakeholder consultations. D. Rapid
Assessment timing and scope will be advised by the TORs/
Proposal.
Compensation Policy and the Grievances Redress Draft policy complete
Mechanism (GRM) Local Consultations on the Compensation with local community
structures held in Leribe, Mafeteng and Mohale’s Hoek
RFB for Compensation Information Systems (CIMS) complete;
CIMS RFB opening on
Project Indicators and baseline data Complete with 2017,2018 & 2019 data
World Bank M&E Review Team has requested updating of the
baseline data, specifically the WASCO Financial Performance
Indicator. Will also be including a Sanitation data-for reporting
purposes only.
Consolidated 2021/22 Annual Work-plan & Budget Draft 2021/22 Budget for GoL , World Bank and EIB/EU
developed, and shared with the Planning Unit (MoW)
2021/22 Implementation Plans complete and to be shared with
World Bank and EIB by 17/03/2021.
COMPONENT 3: WASCO IMPROVEMENTS
Preparation of WASCo Asset valuation TORs complete
EOI Assessment complete
RFP issued to qualifying Consultant on 16/11/2020).
RFPs received on 15/12/2020 and Technical Evaluation complete.
Financial evaluation on-going-pending clarification requested
from Consultant. Letter of Request for clarification sent on
01/02/2021. Submission received from Consultant16/02/2020.
Financial Evaluation complete, and Combined report done.
Contract Negotiation scheduled for 17/03/2021
Computerized Maintenance Management System Development of Proposal & Terms of Reference
(Formerly the Operations & Maintenance) Proposal and TORs being developed with assistance from World
Bank TA)
Draft Proposal Complete
WASCO in the process of Estimating level of Effort (Time & Cost)
WASCO reviewing the TORs based on comments from the World

5
Bank.
Updated TORs received from WASCO, and approved by the PIU
and the World Bank. WASCO yet to confirm level of Effort that
will inform the type of procurement.
Financial Data & Reporting – Develop plan and complete TORs complete
4years EOI Assessment complete
RFP issued to qualifying Consultant on 14/12/2020.
RFP received on 23/01/2021.
Evaluation team met for Briefing to develop criteria.
Technical Evaluation report submitted to Office of Procurement
for review and approval.
WASCO Turn Around Support (Change Management TORs complete
Strategy) EOI Assessment complete
RFP issued to qualifying Consultant on 16/11/2020.
RFP received on 17/12/2020.
Technical Evaluation complete on 12/02/2021.
Financial Proposals opening on 17/03/2021
WASCo Board Coaching/ Capacitation TORs complete
EOI Assessment complete
RFP re-issued to qualifying Consultant on 03/12/2020.
RFP received on 21/01/2021.
RFP Evaluation to commence week of 24/02/2021 (was awaiting
one of the Evaluators to complete the Change Management task)
Evaluation briefing held on 24/02/2021 to develop Criteria.
Technical and Financial Evaluation complete, and Combined
report done-08/03/2021.
Contract Negotiation scheduled for 17/03/2021
Non- Revenue Water Technical Assistance Development of Proposal
Proposal re- developed with assistance from World Bank TA)
TORs (Draft) complete and sent for clearance by the Bank.
Conditional No-Objection received on 27/01/2021.
TA changed from Firm to Individual Consultant and sent into STEP
for approval. Approval received on 03/03/2021
Request for EOI advertised from 05/03/2021 to 19/03/2021

6
WASCO Customer Identification Survey Development of Proposal
Proposal re- developed with assistance from World Bank TA)
TORs (Draft) complete
WASCO completed the estimate level of Effort (Time & Cost).
Received TORs from WASCO. After review, the PIU gave Options
of: 1. WASCO to revise downwards the cost, to fit within the
budget, or 2. WASCO to develop a new proposal with this current
cost estimate-which would be submitted to the World Bank for
approval. Yet to receive confirmed Option from WASCO.
Metolong Panel of Experts An additional Expert added o the initial list.
The Consultancy added to the revised January 2021 Procurement
Plan.
WASCO reviewing and updating the TORs on Dam Hydrologist.
WASCO to update TORs using the World Bank format. To also
include in the TORs for Dam Safety, responsibility of being
Chairperson of Panel of Experts.
ZONES 6&7
Project Management Consultant 17 Applications were received from the EOI stage. These were
evaluated, and eight (8) firms have been shortlisted. The RFP is
being updated based on comments from the EIB, and was sent to
the Bank for review on 24/02/2021.
Email approval received on 15/03/2021. Waiting for the signed
clearance from the EIB, so to issue out the RFPs by 17/03/2021.
It is envisaged that the Contract will be signed by end of
September 2021.

EU-EIB Delegation Agreement EU and EIB have signed their Delegation agreement. This
agreement gives rights to the EIB, to oversee and the coordinate
the funding from the EU, designated for the LLWDP-II Zones 6&7.
This Agreement is yet to be signed by the two (2) parties.
Technical Assistance Implementation Agreement TAIA sets forth the Terms and Obligations of the EIB, the GoL and
the Consultant in relation to the implementation and
management of the technical operation i.e. the Project
Management Consultant (PMC).

7
A draft TAIA has been developed and shared for review by the
GoL. The TAIA will be considered post the signing of the EU Grant
Agreement.
Procurement Plan & 5 year Implementation Plan Developed the 5 year Procurement Plan and high level
Implementation Plan for Zones 6&7
2021/22 Implementation Plan to be shared with the EIB by
19/03/2021