The document is a technical bid tabulation for supplying and delivering a cooling tower for the Sta. Lucia Mall project in Davao City, Philippines. It compares specifications from four cooling tower manufacturers - Liang Chi Industry, CTHVAC, Dunham Bush, and New Bac Cooline. The specifications include capacity, power supply, ambient temperatures, and warranty details. Liang Chi Industry and New Bac Cooline offer 3-5 month and 16-18 week lead times respectively, while CTHVAC and Dunham Bush offer 12-14 weeks and 14-16 weeks. Payment terms including downpayments and retentions are also specified.
The document is a technical bid tabulation for supplying and delivering a cooling tower for the Sta. Lucia Mall project in Davao City, Philippines. It compares specifications from four cooling tower manufacturers - Liang Chi Industry, CTHVAC, Dunham Bush, and New Bac Cooline. The specifications include capacity, power supply, ambient temperatures, and warranty details. Liang Chi Industry and New Bac Cooline offer 3-5 month and 16-18 week lead times respectively, while CTHVAC and Dunham Bush offer 12-14 weeks and 14-16 weeks. Payment terms including downpayments and retentions are also specified.
The document is a technical bid tabulation for supplying and delivering a cooling tower for the Sta. Lucia Mall project in Davao City, Philippines. It compares specifications from four cooling tower manufacturers - Liang Chi Industry, CTHVAC, Dunham Bush, and New Bac Cooline. The specifications include capacity, power supply, ambient temperatures, and warranty details. Liang Chi Industry and New Bac Cooline offer 3-5 month and 16-18 week lead times respectively, while CTHVAC and Dunham Bush offer 12-14 weeks and 14-16 weeks. Payment terms including downpayments and retentions are also specified.
Location: Ponte Verde, Brgy. Communal, Davao City Subject: Technical Bid Tabulation for Supply and Delivery of Cooling Tower Date: July 5, 2021 As per plan LIANG CHI INDUSTRY Item No. Description Specification Quantity Specification 1.00 Capacity 450TR at 5110LPM 5110 LPM, 30HP 2.00 Power Supply 400V, 3Ø, 60Hz 380V, 3Ø, 60Hz 3.00 Ambient Wet Bulb Temperature 26.7°C 3.00 26.7°C 4.00 Inlet Temperature 35°C 35°C 5.00 Outlet Temperature 29.4°C 29.4°C
ORIGIN TAIWAN / CHINA
BRAND LIANG CHI COOLING TOWER LEAD TIME 3-5 MONTHS DELIVERY UNLOADING AT SITE
50% Downpayment, 50% after
Payment Installation
Warranty 1 Year (Upon Acceptance before
release of 10% Retention) NG CHI INDUSTRY CTHVAC DUNHAM BUSH NEW BAC COOLINE Quantity Specification Quantity Specification Quantity Specification 500TR 5110 LPM 450TR (85.17 L/S) 380V, 60Hz 380V, 3Ø, 60Hz 29.84kW, 400Volts 3.00 26.7°C 3.00 26.7°C 3.00 35°C 35°C 35°C 29.4°C 29.4°C 29.4°C 26.7°C
AIWAN / CHINA MALAYSIA CHINA
CHI COOLING TOWER NEWIN TRUWATER BALTIMORE 3-5 MONTHS 12-14 Weeks 16 - 18 weeks 14 - 16 weeks at project site from NLOADING AT SITE Including Unloading receipt of PO. / Downpayment / Including Unloading 60% Approval of Shopdrawings Downpayment upon receipt of P.O. thru telegraphic transfer; 40% wnpayment, 50% after 20% Downpayment ; 70% Upon Balance by irrevocable Domestic LC Installation Delivery ; 10% Retention in full upon submission of packing list / 13months 1 Year upon start-up pon Acceptance before from date of delivery whichever 1 Year (Upon Acceptance before se of 10% Retention) comes first release of 10% Retention) EW BAC COOLINE Quantity