Professional Documents
Culture Documents
On a rapid transit system, centerline of track and centerline of tunnel are normally not identical because
of clearance requirements. The centerline of track should be the basis for the control during overall layout of
the work. During construction of the tunnel, however, it may be desirable from a practical standpoint that the
centerline of tunnel rather than centerline of track be used as the basis of construction control.
The vertical and horizontal offset from centerline of track to centerline of tunnel will vary with the
superelevation of track. The resulting tunnel centerline is a curve of complex mathematical definition and
cannot be produced in the field using standard survey procedures.
Therefore, a tunnel centerline should be developed which is composed of tangent, circular, and
transition spiral sections and approximates the complex theoretical tunnel centerline within a specified
tolerance as, for example, 1/4 in. (6 mm). This centerline should be incorporated into the contract
drawings, and all tunnel control should be based on this line. A computer printout listing the coordinates of
points, tangent bearings, elevations of points, and slope at 5-ft (1.5-m) intervals on the tunnel centerline
should also be incorporated into the contract documents.
Since the stationing along the centerline of tunnel and centerline of track will not agree because of
different curve radii, station equations between centerline of tunnel and centerline of track should be
incorporated at the beginning and the end of each construction contract, at tangent-to-spiral, at spiral-to-curve
points, and at such points as vent shafts or cross passages. Stationing along the centerline of tunnel should
start at Station 0+00 for each tunnel contract. Stationing of track proceeds through the entire system, which
may comprise several tunnel contracts. If the rapid-transit system has a major junction from which several
lines branch out in different directions, the Station 0+00 should be assigned to this junction point. Stationing
then proceeds to the outlying areas, and future extensions of the system can be added without upsetting the
sequence in stationing.
The working line is the survey line used by the contractor’s field personnel to establish shield or
tunneling machine guidance in the tunnel. The working line may coincide with the centerline of tunnel or may
run through the laser position points for the laser setup. Selection of the working line must be left to the
contractor to suit his tunnel equipment and methods.