soil)
>each set of compaction soil test will do 3 test
for moisture content<
Proctor mould
Compaction hammer
Analytical balance
Soil pass 37.5 mm 20 mm sieve
Water
Moisture content cans
Trimming knife
Metal scoop
Knife
Oven
Extruder
1)Remove the collar
2)Make sure mould and base is clean. Take the
weight for body + base. Then mark it as M1
3)Measure the volume the mould.
4)Add adequate amount of water into soil that
already pass 37.5 mm and 20 mm sieve . Then
mix it using metal scoop.
5) Attach collar to the body and base and tight
it.
6) Put adequate amount of soil into mould to
get ready for first layer to be compacted.
7)Compact the soil using compaction hammer.
8)Put soil again into mould for second layer and
third layer and compact it again.
Permeameter
Water tank
CONTAINER FOR WATER COLLECTION
Stop watch