ID Task 

Task Name Duration Start Finish Resource Names Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
Mode 23 D24 D25 D26 D27 D28 D29 D30 D31 D01 J 02 J 03 J 04 J 05 J 06 J 07 J 08 J 09 J 10 J 11 J 12 J 13 J 14 J 15 J 16 J 17 J 18 J 19 J 20 J 21 J 22 J 23 J 24 J 25 J 26 J 27 J 28 J 29 J 30 J 31 J 01 F02 F03 F04 F05 F06 F07 F08 F09 F10 F11 F12 F13 F14 F15 F16 F17 F18 F19 F20 F21 F22 F23 F24 F25 F26 F27 F2
1

2 POX II Feluwa Pump Installation Plan 64 days? Sat 26/12/20 Sat 27/02/21

3 Trial fit pumps on to the plinths to confirm pump &  1 day Sat 26/12/20 Sat 26/12/20 Mech ‐ Project Mech ‐ Project


hold down bolts centre 

4 Mark pump centre & hold down blots centre then  1 day Sun 27/12/20 Sun 27/12/20 Mech ‐ Project Mech ‐ Project


remove the pumps to store in safe area

5 Drill concrete hold down bolts holes  4 days Mon 28/12/20 Thu 31/12/20 Civil ‐ Project Civil ‐ Project

6 Install hold down bolts & fill with adhesive 1 day? Fri 01/01/21 Fri 01/01/21 Civil ‐ Project Civil ‐ Project

7 Concrete plints & slab coating 7 days Sat 02/01/21 Fri 08/01/21 Trepax Trepax

8 Install feluwa pump, levelness and alignment ‐ To be  12 days Wed 13/01/21 Sun 24/01/21 Mech‐Maint Mech‐Maint


done by Chris team

9 Form works and grout 5 days Mon 25/01/21 Fri 29/01/21 Civil ‐ Project Civil ‐ Project

10 Install pipeworks (Charge & Feed pipe) 20 days Thu 21/01/21 Tue 09/02/21 Mech ‐ Project Mech ‐ Project

11 Install cable tray & cables 15 days Thu 21/01/21 Thu 04/02/21 Elect ‐ Project Elect ‐ Project

12 Install VSD panel  4 days Mon 25/01/21 Thu 28/01/21 Elect ‐ Project Elect ‐ Project

13 Install platform, walk way, VSD roof and feed pump  30 days Fri 29/01/21 Sat 27/02/21 Mech ‐ Project


roof

14 Feed pipe tie‐in (TBA) Mech ‐ Project

15 Commissioning (TBA Lately Feb 2021)

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish‐only


Project: POX2 Feluwa pump insta
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Wed 23/12/20
Milestone External Tasks Inactive Milestone Duration‐only Start‐only Progress

Page 1