Professional Documents
Culture Documents
ml&RmkaG#dhmmfl
Indian Standard
GUIDE TO TEROTECHNOLOGY
PART 1 INTRODUCTION TO TEROTECHNOLOGY
Ics 03.100.01
0 BIS 2003
‘1’his Indian Standard ([’art 1) was adopted by the BL]retIUof’ indian Standards, after the draft finalized by the
hlanagcmcn( and l’roductivity Sectional Co~lln~ittee had been approved by the Management and Systems Division
~’ouncil.
Itl an>’ organization it is necessary to identify and then choose between the investment options open to it and to
lnahc LIccisions on how best to invest the capital available. Once a decision has been made to make an investment
)n $omc form of physical asset or project, then the application of tcrotechnolo:y should assist in the object of
~c[[ill~ [he [?cst Va[Llefor money from that investment and thuSjuStify it.
I“cr(ltecllnology is a combination of management, financial, engineering, building and other practices applied to
ph} sical wsets in pusuit of economic life cycle costs. It is concerned with the specification and design for reliability
a)ld tll:ii]lt:litl:ibility of physical assets such as plant, machinery, equipment, buildings and structures. The application
()]’tcrotechnology also takes into account the processes of installation, commissioning, operation, maintenance,
]nodification and replacement. Decisions are influenced by feedback of information on design, performance and
CO$(S.throughout the life cycle of’s project. 1[applies equally to both assets and products because the product of
one organization often becomes the asset of another. Even if the product is a simple consumer item its design and
cus[onlcr appeal will beneht from terotechnology and this will reflect in improved mark& security for the producer.
‘1’cI-[)tccl)I]cJl[>gy
was developed in the context of larger organizations, with the objective of making them more
eficicnt and competitive. Throughout this standard the applicability to a larger organization is used as a basis as
this \vill represent the more complex situations. However the objective of maximizing value for money spent and
the principles involved in achieving this, are equally applicable to small organizations. Small organizations face
problems as nlLIch as those faced by the larger; more complex organizations. Their problems maybe simpler but
the principles of problem solving remain the same. The small organization can therefore benefit from this guidance
by selecting those parts of the decision-making process that can help them.
‘1’llisstandard sets out in detail all the activities that should be carried out to ensure that the organization, which
uses terotechnology, could compete successfully and, at the same time, achieve consumer satisfaction.
‘1his standard is largely based on BS 3843 (Part 1) :1992 ‘Guide to terotechnology (the economic management of
assc[s) : Part 1 Introduction to tero[echnology ’.
in addition to this pw-t, this standard has the following two parts which are referred in the text:
Indian Standard
GUIDE TO TEROTECI-INOLOGY
PART 1 INTRODUCTION TO TEROTECHNOLOGY
-.
“7
IS 15363 (Part l) :2003
mass-produced item may have no direct personal a) Selection and provision of permanent (that is,
involvement with the eventual purchaser. In order to not consumable) physical resources used in the
establish the best market for his product he may production of goods and services;
therefore have to rely on techniques such as market b) Caring for those resources effectively and
research to identify the life cycle costs and reliability efficiently;
which will ensure satisfactory value for money. There
c) Coordinating them to help achieve overall
will also be variations between those two extremes.
minimum costs over their life cycle; and
4.3.3 Nevertheless, in all cases there should be a need d) Feeding back information to improve them.
to identify the options which may be available in the
procurement of the asset so that the most economic 5.1.2 The successful application of terotechnolo.gy
solution may be chosen which best fits the user’s depends upon ability to-balance factors which a~e
requirement. This solution will largely depend on a uniquely important for a particular situation. R requires
price/cost equation or a cost benefit analysis. an understanding of management and accounting
sciences and a general knowledge of engineering
4.3.4 The full terotechnology cycle begins at the associated with the technological expertize appropriate
investment appraisal stage and ends with the disposal to a particular industry.
of the asset, but the application of terotechnology can
be made at any stage in the life of a physical asset and 5.1.3 In more specific terms, the application of
continue for some or all of the remaining life cycle terotechnology brings together the whole or parts of a
periods until disposal or replacement. number of techniques and disciplines. The blend and
depth required of each will depend on the particular
4.3.5 Maximum benefit will be obtained from applying circumstances in which terotechnology is being applied.
the complete principles of terotechnology. However, These techniques and disciplines include the following:
many aspects of terotechnology are already being very
a) Investment appraisal;
successful ly practiced by many organizations under
different names. The following list, which is not b) Operational research;
exhaustive, may help managers to identify those parts c) Replacement analysis;
ofterotechnology with which they are already familiar:
d) Marketing;
a) Asset management (including physical asset
e) Purchasing;
management);
b) Resource management; 8 Accounting;
c) Life cycle costing; i%) Design for reliability and maintainability;
d) Cost of ownership; h) Preparation of specifications;
e) Total commitment for life; j) Installation;
f) Womb to tomb costing; k) Commissioning;
2
‘1
i’
terotechnologist). Save in exceptional circumstances, decisions are made on the basis of achieving the best
the range of skills and breadth of knowledge and balance of cost and performance for the organization
experience necessary for its full implementation is as a whole.
unlikely to be acquired by any one individual.
5.5 Collection and Analysis of Data
5.2.3 Although terotechnology can be easily
5.5.1 To action the optimization objectives described
understood and applied by line management, engineers,
in 4.2 to 4.4, it will be clear that each individual
accountants and others, in their daily working lives,
department will require suitable quantitative data from
the subject can be applied successfully at company level
all other interacting departments. These data need tu
on Iy with the active participation and understanding
be those required for the department to optimize its own
of senior management.
decisions in the overall interest of the organization as a
5.3 Interprofessional Cooperation whole.
5.3.1 The application of terotechnology demands that 5.5.2 It is essential that there are communication
all those involved have abroad recognition of their own channels between departments (see 4.3). It shou Id be
contribution together with that of their colleagues in emphasized that part of the communications through
other disciplines and its success is dependent upon these channels needs to be the data needed by other
effective communication between all parties. It requires departments to carry out their own optimization
an understanding of management and accounting and exercises, on an organization-wide basis.
knowledge of the technology associated with the
5.5.3 Furthermore, this can, and frequently does,
particular industry or asset.
require a department to collect data not required for its
The following are two examples which may help to own purposes but necessary for proper use by other
illustrate this principle: departments.
a) The designer of a product should take into 5.5.4 This collection, analysis and dissemination of
account the feasibility of producing his design data does not necessarily remain within the organization
and its cost to the consumer in operation and but can and should extend to the suppliers of the assets
maintenance. used by the organization. Only in this way, can the
b) When assessing the proposed design of a product supplier organization refine its designs in the overall
the management will require feedback data on interests of its customer organizations.
the price the market may be prepared to pay for
5.5.5 Data may be required for central decision making.
the product and the cost of producing it.
These may be central data or they maybe departmental
5.3.2 However, it should be remembered that these data, but they should be collected in a form which
are only two examples of a wide range of satisfies both the central and the departmental needs.
interrelationships and each member of the team should
5.5.6 Experience to date has shown that in many
endeavour to prepare his own list of the ways in which
his role should interact with the whole team. This is organizations there is an advantage in appointing a
senior person to oversee adoption of the principles of
discussed in more detail in Section 3.
terotechnology throughout the organization. This
5.4 Interdepartmental Cooperation person should be appointed by and be responsible to,
the Board of Management. Ideally he should be
5.4.1 Itis common practice for senior management of independent of any particular department, but in any
an organization to require individual departments to case he needs to be free to cut across departmental
optimize their individual activities. Unfortunately if
boundaries.
this is taken as the primary objective of departments it
can result in a less than optimum performance of the 5.6 Minimum Activities Necessary for Implementing
organization as a whole. This arises from the inevitable Terotechnology
interaction of decisions between departments.
5.6.1 The minimum activities necessary for the
Examples of this are not hard to find. If a purchasing
implementation of terotechnology are the following
department acquires the cheapest possible asset it is
Iikely that the operating and/or maintenance costs will a) Decide what production and cost targets are to
tend to be higher. Similarly inadequate maintenance, be met;
to reduce maintenance costs, invariably results in b) Decide what physical assets are needed and how
penalties in the cost of operation and/or a shorter to use them to achieve the targets over a specified
working life of the asset. period, taking into account their forecast cost of
ownership and use;
5.4.2 Consequent upon the above, the primary
objective of all departments working under the c) Specify the performance of the assets to be
principles of terotechnology, is that their individual acquired;
3
IS 15363 (Part 1) :2003
O Monitor their use; and 7.1 One of the principal obstacles to the implementation
g) Replace and improve the assets and improve their of terotechnology has been the lack of data. Data are
care, using information from them to help an essential input for implementing terotechnology, and
minimize total life cycle costs. this may include detailed cost, performance [see Note
to 6,1 (b)] and marketing information.
6 BENEFITS FROM INTRODUCING
TEROTECHNOLOGY 7.2 The main costs associated with terotechnology data
are:
The benefits which may be gained by the use of
a) Cost of collecting additional data, not already
terotechnology maybe broadly described as:
collected for management purposes;
a) Improved control by the client or senior
b) Cost of making existing data compatible with
management in the making of vital decisions;
leading to; the needs of terotechnology;
b) Better investment decisions arising from : c) Cost of any additional analysis; and
..
T
9.2 The principal function of the chief executive in need to be some changes in individuals’ attitudes to
any organization is to examine investment options and their responsibilities. These changes should be towards
to make choices between them. He needs to consider a more collective corporate attitude and away from
the availability or cost of raising funds and the various narrow departmental or professional allegiances.
opportunity costs and make judgments on the best
11 INCORPORATION OF TEROTECHNOLOGY
courses of action that are available. He needs to
INTO ACTIVITIES
remember that the best economic solution may need to
be used. He maybe faced with conflicting advice from 11.1 Modification of and Additions to Existing
various advisers and a decision has to be made. Activities in the Organization
9.3 Senior managers have to consider and evaluate all 11.1.1 Terotechnology involves understanding and
the various available options in acquisition, operation, CO1Iaboration between functions to be effective. An
maintenance and disposal of all assets. All the financial organization will be said to be practicing terotechnology
answers need to be converted to a common base and when it is consciously managing the cost of owning its
any government or customer incentives or disincentives assets. The concepts of ‘cost of ownership’ involves
evaluated. The results of all of the findings of senior the appreciation oftrade-offs between acquisition costs
managers have to be in a simple and consistent format and running costs. It is easy to understand, but not
to enable the options to be evaluated in the light of the necessarily easy to apply.
organization’s overall policy and strategy to come to a
decision on the best course of action to follow. More 11.1.2 The application of terotechnology requires
details of this are given in Part 2 of this standard. senior management to have a thorough understanding
of each specialist’s role. This also means that specialists
9A The role of the senior manager in an organization need to have a broad recognition of their own
seeking to apply terotechnology is fivefold as follows: contribution plus that of their colleagues in other
a) To encourage departmental managers to work disciplines. If senior management has to make decisions
together, and provide each other with all the on the purchase : f new plant with little or no
information that each requires; information on past performance and operating costs,
this can lead to wasted resources, high costs, higher
b) To foster friendly rivalry between departments downtime and lost orders. The till terotechnology cycle
and to encourage ideas on economies to come begins at the investment appraisal stage and ends with
from the shop floor (possibly by incentive the disposal of the asset, but the circle can be entered at
schemes); any point. For example, a company may decide to
c) To coordinate the departmental managers to improve maintenance and reduce downtime on existing
arrive at a number of possible options (all plant; although the trade-off between initial capital
prepared using the same ground rules to allow costs and subsequent costs cannot be taken into account,
correct comparisons to be made); the company’s decision will have a very real effect on
the cost of ownership. The fact that terotechnology
d) To decide on which option to adopt (see 4.1);
cannot be applied from the beginning of the life cycle
and
of a piece of plant should not deter a company from
e) To ensure that the departmental managers attempting to improve reliability, or to improve or
implement the decision which is made. design out maintenance.
10 ORGANIZATIONAL FRAMEWORK 11.1.3 Experience to date has shown that in many
organizations there is an advantage in appointing a
10.1 The introduction of terotechnology into an
senior person to oversee adoption of the principles of
organization does not require any significant changes
terotechnology throughout the organization. This
in the organization’s functional and departmental
person should be appointed by and be responsible to,
framework. There will still be a need for the individual
the Board of Management. Preferably he shou!d be
specialized activities; all that will be changed will be
independent of any particular department, thus being
the basis of the primary objectives of the individual
capable of cutting across departmental boundaries
departments.
without ‘bias.
10.2 The principal change will be in the extent and
content of interdepartmental communications, and also 11.2 Modification to Customer/Supplier
in the relationship between the organization and the Relationship
suppliers of its principal assets, whether these be 11.2.1 Many of the problems which arise at a late stage
buildings, plant or both. in the life of physical assets stem from inadequate
10.3 With the changes in internal and external specification of requirements and poor communication
communications there will inevitably be some between customer and supplier. It is important to
modification to individual responsibilities and there distinguish between specification for function and
,,.
‘7
IS 15363 (Part 1) :2003
specification of reliability, maintainability and its own objectives and a plant to meet these, broken
continuity of optimum performance of the assets in down into a series of individual projects. The steps in
question. the process are as follows:
11.2.2 Terotechnology is not concerned with the first a) Identify each project including the total market
(for example, the process), but it does include the latter. demand for the product or service and the
This is a fundamental distinction which helps to national target share of this demand to be met
illustrate the relationship between terotechnology and by the organization. Both of these aspects need
other management techniques. to be determined against a time scale.
b) Identify the scenario against which these market
11.2.3 Only the user is able to specify the overall
predictions are being made.
requirement but the supplier can and should have
responsibility for much of the detail. Equipment c) Identify and agree the probable ranges of
suppliers make an important contribution to the variations in this scenario and both the
efficiency of industry because they determine the probabilities of such variations and the
reliability and fitness for purpose; of the assets they consequences on the national output and time
supply and management in this area has a particular sensitivities on the project objectives.
responsibility to ensure that the customer takes delivery d) Identi& any performance requirements such as
of plant which meets his requirements, both in terms of availability or reliability of output and any
technical parameters and predicted life cycle costs. product quality targets and the consequences
11.2.4 In certain industries, there has developed an (including penalties) of not meeting these
understanding that the customer/supplier relationship requirements.
has a very real effect on the efficiency and prosperity The second part of this phase involves the identification
of all concerned. In such cases there is a deeper and selection of a specific asset plant proposal. The
appreciation of each other’s role and requirements than steps are as follows:
would be the case with purely formal and procedural
relationships. a) Identify the technically feasible way of meeting
the project targets, within any restraints, financial
11.2.5 Not only are the customer and supplier better or otherwise.
able to plan their respective operations, but the early
b) Estimate outline costs of alternatives (life time
and crucial stages in the life of a plant develop more
costs).
smoothly and logically than would otherwise be the
case. Benefits resulting from a closer customer/supplier c) Estimate cost variations within the identified
relationship are as follows: ranges of scenarios.
a) Planning made easier and with a better chance d) Select best option or options for further detailed
of success; study after taking into account the assessed
b) Easier transition from specification to probabilities and risks.
production; e) Refine assessments to reduce best options to a
c) Production schedules more readily met; and single proposal and communicate this in full
detail.
d) Increased company effectiveness and greater
chance of meeting market requirements. 11.3.2 Acquisition Phase
11.2.6 This situation may not come about if the 11.3.2.1 In this phase the first task is to specify the
customer does not know how to specify exactly what assets needed for the project. The steps include the
he wants, and the supplier does not feel it is his following:
responsibility to rkk for a precise specification or there
a) Obtain inputs from all parts of the organization
may be complete ignorance of the fact that there is a
regarding the assets needed and the probable
communication gap. Equipment is sometimes bought
future resource needs during the project lifetime. .
and modified by the customer who, perhaps because
of fear of disclosing commercial secrets, does not b) Identify and evaluate potential trade-offs, for
inform the supplier, with the result that more plant of example, automation versus manpower, inherent
the same type will be designed and built with the same ~eliability versus maintenance.
shortcomings. c) Either specify assessed optimum of trade-offs
11.3 Example of Application of Terotechnology in or demand information in tenders on which to
Different Project Phases in a User Organization determine the optimum.
d) Fully specify requirements in all particulars
11.3.1 Concept and Investment Appraisal Phase
including contract documentation, manuals and
11.3.1.1 Initially the organization will have to establish support during the life cycle of the asset.
6
‘1
e) Finally issue the enquiry specification to all the operation and maintenance of the current assets but
viable tenders. also for use by the user’s planning and project staff in
future projects. To this should be added such data
11.3.2.2 When tenders have been received, these will
which, when fed back to the manufacturers or suppliers,
have to be assessed and compared. The essential enables them to improve their performance in serving
elements of the assessment to be included areas follows:
the terotechnological needs of future users.
a) Ensure all specification requirements, including
11.3.5 Disposal Phase
data, have been met.
b) Identify shortcomings or alternatives and This terminal phase of the life cycle will have to be
estilmate the consequential penalties to the user optimized as part of the life cycle management.
organization. Therefore, the data and costs associated with this phase
should be considered for use in the studies of future
c) Identify options offered, then determine and
projects.
select best option for the user.
d) Identify further pothtial shortcomings (not 11.4 Effect on Supplier Organizations
necessary outside-specification) and evaluate a 11.4.1 In so far as supplier will normally also be a user
reasonable notional penalty based upon risk and of assets acquired from another supplier, he will have
consequence estimates. an interest in terotechnology applied to his own assets.
e) Identify guarantees being offered. But his consideration should also extend to the assets
he is supplying to his customers. To do this he needs
11.3.2.3 Competitive tenders should be compared and to consider in his own operations the terotechnology
tenders then selected for all the contracts for the various needs of his customers, as users, by viewing matters
assets in the total project. Before proceeding it will of from their points of view.
course be necessary to check that the tendered data does
not invalidate the chosen asset plan or the original 11.4.2 In particular his designs for assets to be supplied
market plan proposals. Finally contracts are let or to a customer should make the user’s terotechnology
orders placed for the assets needed. needs the priority consideration. Having done so, it
will be equally essential that the supplier markets his
11.3.3 Commissioning Stage product with due emphasis on how the customer’s
During the commissioning stage of the assets further terotechnology needs have been considered and catered
detailed examination needs to be given to all the options for. This aspect goes beyond the design of the product
regarding policies, strategies and the support resources and extends to both contractual conditions (guarantees,
needed for operation and maintenance of the assets. etc) and support for the service phase. This latter could
The objective is to identify the optimum position include both spares and specialist advisory services.
viewed overall with respect to the project targets. 12 MODIFICATIONS TO INDIVIDUAL
Further refinement should be made of estimates of
FUNCTIONAL ACTIVITIES
resources needed for operation and maintenance during
the asset life cycle particularly in the light of any 12.1 Management
variations within the scenario ranges agreed, from time
to time, by senior management. 12.1.1 The decisions made by management can only
be as good as the information which is made available
11.3.4 Useful Life Phase to them. At management level the primary function of
terotechnology is as an information and control system
11.3.4.1 During the useful life phase, in which
and as an aid to communication and appraisal.
operation and maintenance are the primary activities,
Information fedback from all functions within the
the policies and strategies, initially forecast during the
organization will enable better evaluation of the
commissioning stage, will be reviewed and modified
performance of physical assets and so improve
in the light of experience and circumstances, As time
corporate planning and forecasting.
progresses, reviews need to be held inter alia to clearly
“ define the project targets, particularly regarding the 12.1.2 Management style is important in the
duration of the life cycle and the associated costs in application of terotechnology and a policy which
respect of disposal of the assets and/or their replacement encourages communication and information exchange
if this is appropriate. will facilitate this. The acquisition, processing and
transmission of relevant data is a fundamental requisite
Routinely, the performance of the asset and associated for the full practice of terotechnology and although this
costs should be reviewed and be improved if this is may sometimes call for sophisticated data systems based
possible. on computers, this should not automatically be assumed
11.3.4.2 A major feature of this phase will however be to be the case. The type of information required should
the collection and analysis of data not only for use in be specified first, and then the methods of recording it.
,-.
IS 15363 (Part l): 2003
Care needs to be taken to ensure that cost of gathering 1) Identifying for any new acquisition the full
and evaluating the information does not out weigh its requirements of the user groups in the
usefulness. organization; and
12.3 Designers and Project Engineers 12.5.1 The production manager and engineer should
have the responsibility to:
The designer and project engineer should have the a) Provide information on reliability,
responsibility to: maintainability, safety, costs and failure or
a) Ensure the availability of feedback information malfunction, etc, of plant and equipment in use;
from users on such items as: b) Provide the relevant information enabling clear
1) Cost of installation and commissioning; and complete specifications of requirements to
be prepared when consideration is being given
2) Reliability;
to the purchase of new or replacement assets;
3) Maintainability;
c) Make available relevant data when considering
4) Functional performance including numbers production programmed and how they would be
and types of failure or malfunction; and affected by maintenance schedules;
5) Consequences of failure and use of failure d) Receive and act on feedback of information from
modes, effects and criticality analysis. the users of the product on failures, reliability,
b) Enable the whole life cycle costs including maintainability and safety; and
manufacture, installation, commissioning, e) Assist in the preparation of valid estimates of
operation, overhaul, repair and disposal to be delivery time and price when responding to a
considered at the design and development stage; prospective purchaser’s enquiry.
c) Become more fully aware of the cost
implications of their design decisions; 12.5.2 The better information and cooperation resulting
from the use of terotechnology will often result in an
d) Facilitate the preparation and presentation of overall improvement in costs and efficiency.
technical manuals and brochures on the product;
and 12.6 Maintenance Managers and Plant Engineers
e) Show, if required, the need for specialist The maintenance manager and plant engineer should
personnel and their required skills, and identify have the responsibility to:
how these can be employed. Decide on how
a) Encourage the provision of proper maintenance”
this need can be satisfied by the time these skills
schedules;
are required and consider recruitment or training.
b) Provide a fault recording and analyzing system
12.4 Purchasing Executives as part of a maintenance strategy, giving
information on spares requirements, reliability,
The purchasing executive should have the responsibility
maintainability, maintenance costs, safety, etc;
to strengthen communication bridges with the suppliers:
a) Internally by: c) Make available information on the total costs of
8
IS 15363 (Part 1) :2003
maintenance including both direct and indirect are identified and some solutions to them suggested
costs, which would assis~ in assessing the right in 13.2 to 13.5.
time for equipment replacement;
13.1.2 The problems discussed may be divided into
d) Provide the means of checking that forecast four broad categories:
reliability and maintainability figures are
a) Concept;
achieved in practice;
b) Technical and economic;
e) Evaluate condition-based maintenance
techniques as part of terotechnology to optimize c) Management organization; and
maintenance costs and improve plant d) Personnel management.
availability; and
13.2 Concept
f) Highlight to top management how poor~r
inadequate maintenance can result in poor 13.2.1 A reluctance to accept the concept of
delivery performance, and consequently terotechnology is often a problem within an
dissatisfied customers and lost markets. organization for a variety of reasons. In order to deal
12.7 Marketing Executives with the problem these reasons shobld bd identified.
Depending on the cause of the problem consideration
The marketing executive should have the responsibility should be given to the following suggested solutions:
to:
a) Where the problem is due to a lack of
-4
a ) Provide information to enable the competitive understanding of the meaning of the term
features of the product to be presented to the terotechnology a solution may be found in
prospective purchaser and particularly the trade- seeking forms of the term which are familiar and
off between initial cost and total life cycle costs; therefot-e meaningful to the person(s) concerned.
b) Consider such factors as delivery, performance, The list given in 4.3.5 maybe helpful.
price quality, reliability, maintainability, after- b) Where there is doubt regarding the benefits to
sales service, spares availability, the quality of be gained from the adoption of terotechnology,
technical manuals, etc, and whether: it may be profitable to undertake some back of
an envelope sensitivity analysis before
1) he is fully equipped to respond to the
embarking on an in-depth “investigation. it is
customer’s requirements;
often surprising how valuable such an
2) he has information to assist in detailed introductory exercise can be and what it leads
comparisons with rival products; and to.
c) Establish feedback from customers on product c) Where there are no specific reasons for the
performance problem other than the natural reluctance to
accept change, a trial in one trade-off situation
12.8 Effect on Training can often be convincing as It will demonstrate
To achieve the maximum benefits from terotechnology how using terotechnology leads to more
it will be necessary to introduce the concept into the informed decision making.
staff training of the organization. This should lead, in
13.2.2 Whilst the concept of terotechnology may be
turn, to a level of training sufficient to allow each
acceptable in an organization there may be opposition
participant to understand his own contribution and the
to the implementation of terotechnology in the
contribution to be expected or required from all other
organization because the costs are thought to be
members of the organization. The greater appreciation
prohibitively high.
by individuals of the work and contributions of others
should lead to smoother relationships within the However, much of the data required in the application
organization, less friction and disturbances and a greater of terotechnology can be derived from data which
identification of each individual with the corporate should already be collected for normal management
entity of the organization. purposes and the analysis of the data can use the existing
facilities. The solution to the problem therefore is to
13 PROBLEMS EXPERIENCED IN
convince the objectors that the additional cost to an
INTRODUCING TEROTECHNOLOGY AND
efficient organization will be minimal.
SOLUTIONS FOUND EFFECTIVE
,..
IS 15363 (Part 1) :2003
cooperation amongst me]mbers of the organization will assumptions. In case of doubt it will be wise to apply
impede the effective application ofterotechnology. sensitivity analysis to establish the degree of accuracy
required of the data and the extent to which any
This problem is gradually disappearing because of the
assumption will affect the solution.
following:
a) Terotechnology, often under the guise of other 13.3.4 Certain external constraints may affect the
names, is accepted by the professions and is now solution to a terotechnology problem and a sub-optional
being taught by many technical colleges, solution may have to be adopted in preference to the
ideal solution (In this context, external constraints are
polytechnics, etc. [n-house training can also
be effective in further eliminating the problem. constraints imposed by the organization’s policies and
may include the cost of initial financing, the imposition
b) In many organizations today it is recognized that of cost limits or a requirement to accept the lowest
liaison and cooperation between the different tender).
professions is @sential for the efficient running
of the business and this can easily be extended The great merit of terotechnology is that it identifies
to the application of terotechnology. the benefits that may be gained. These may produce
powerful arguments for revising the constraints
13.3 Technical and Economic Problems imposed and certainly allow more informed decisions
to be taken.
13.3.1 The most common problem in this area is that
there is an apparent non-availability of data in a form 13.3.5 When compared with the life of the production
suitable for use in terotechnology. run, the duration of the promotional advertising of a
product may be relatively short. If the degree of success
This problem is less serious today than in earlier times
is appraised at the end of the advertising period the full
it should gradually disappear for two reasons:
benefits ofterotechnology maybe underestimated.
a) Recent explosive developments in information
technology allow the derivation of data suitable Since it obviously takes time for clients and customers
for terotechnological purposes. to assess the benefits of total life costs, the mll benefits
will normally only materialize in the Iongerterm. This
b) Efficient management now recognizes the need
aspect should be borne in mind in setting up the
for data to allow the preparation of programmed,
promotional programme; in subsequent promotions
control budgets and the monitoring of
results can be quoted.
performance. It is not difficult for such data to
be collected in a form which will also allow them 13.4 Management Organization
to be used for terotechnology. The wider
availability of personal computers in offices of 13.4.1 Terolechnology requires inputs from a number
all sizes makes this collection of data possible. of different disciplines which may be located in
In some cases the required data can be derived different functional divisions within an organization.
from hypotheses and/or published information. This may create a problem. Normally the problem does
not apply to small organizations or to larger
13.3.2 Another problem which has discouraged the organizations which are split up into small groupings
use of terotechnology is the belief that there are no by region or type of operation. Nonetheless, in many
suitable techniques for the processing of data. cases some overall guidance may be essential.
This is not the case. The normal techniques used for The problem has to be solved by identifying and
investment appraisal can be used, including statistical eliminating the root cause, such as the following:
analysis and discounted cash flow techniques. The skill a) In some cases different departments or different
lies in applying these techniques to terotechnological disciplines in an organiza~ion find it difficult to
problems and interpreting the results. cooperate for the common good due to the fact
that the departments are considered to be
13.3.3 A problem to be faced in the application of
separate accounting units, each of which has to
terotechnology is how to deal with uncertainties about
show a profit. In such cases it should be made
the future.
clear that each department should consider all
In order to deal with uncg-tainties, assumptions about the options open to it and take into account the
the future have to be made. Every form of investment effect these will have on other departments.
analysis is based on such assumptions. In Someone should then be appointed to consider
terotechnology these may include the likely life of the all the options and to recommend to the senior
product, the rate of inflation, the discount rate to be manager the solution most beneficial to the
used, and tax incentives. These aspects are dealt with organization as a whole.
in some detail in Parts 2 and 3 of this standard. There b) Departments may not recognize that some of
are well-tried techniques available for choosing the best their data have the potential of serving the needs
10
. .
1
IS 15363 (Part l) :2003
of other departments. Everybody needs to be may concern possible loss of status if not loss of
made aware that information is available in the employment altogether. Management generally must
various departments. In order to make this ensure that they recognize when or where such concerns
information useful to other departments it will are arising and take such steps as are necessary to
be necessary to open up and maintain counter them. These fears may concern possible
interdepartmental channels of communication. misapplication and consequent loss of status.
[n addition, departmental isolation and loyalties have Monetary incentives for specialist skills may be
to be redirected to secure the wider aims of appropriate and a sharing in the increased profitability
terotecbnology. However, this objective should not or savings maybe the best method of applying incentive
prevail to the extent that specialist skills become too for cooperative efforts. However, a sense of person
dilute, resulting in a staff knowing a little about appreciation may be even more important.
everything but nothing in depth.
14 APPLICATION OF PROCEDURES AND
13.5.2 For most organizations staff represent their TECHNIQUES
most valuable resource and organizations which fail to
14.1 General
recognize this, and do not strive constantly to enhance
their quality, rarely prosper. The application of terotechnology demands that all
those involved have a broad recognition of their own
The introduction of terotechnology demands re-
contribution together with that of their colleagues in
education and restraining of personnel throughout the
other disciplines and its success is dependent upon
organization and career development along
effective communications between all parties. It
terotechnology lines needs to form an integral part of
requires an understanding of management and
the personnel management policy.
accounting and a knowledge of the engineering
Care needs to be taken to update specialist knowledge associated with the particular industry or asset.
and staff need to be encouraged to absorb all the
The full terotechnology cycle begins. at the investment
technological changes witbin their own specialism.
appraisal stage and ends with the disposal of the asset,
The career development strategy of the organization
should be to overlay management training and multi- but the application of terotechnology can be made at
any stage in the life of a physical asset and continue for
disciplinary awareness on in-depth specialist
knowledge. Senior management needs to be trained in some or all of the remaining life cycle periods until
the necessary corporate decision-making skills. disposal or replacement.
Top management will need to delegate specialist tasks 14.2 Procedures and Techniques
and require constituent branches of the organization to
The procedures and techniques available for the
present progress r’eports, financial information, etc,
implementation ofterotechnology are many and varied.
using the techniques in Part 3 of this standard, in such
Some examples of these techniques in relation to life
a form that corporate decisions can easily be made,
cycle cost functions are given in Table 1. For full details
justified and explained.
of these techniques and their application see Parts 2
The acquisition of staff can be treated to some extent and 3 of this standard.
like the acquisition of other assets. A similar life cycle/
14.3 Terotechnology Checklists
cost approach can be taken and career management and
progression are in many respects sim ilar to the processes Terotechnology checklists have been prepared for use
outlined for maintenance and improved of other assets. by various functions within organizations. As an
13.5.3 in certain circumstances specialists may fear example, the checklist aimed at managers in user
the implications of revealing their special skills to organizations is included as Annex B. The full set of
colleagues outside their own discipline. These fears checklists is reproduced in Part 3 of this standard.
II
Table 1 Some Examples of Relationships Betw’een Life Cycle Functions and Relevant Techniques
(Clause 14.2)
F
Life Cycle Functions System
;0. Specification Design Operation
.
l’a ble 1 (Cone/zf&C/)
—. ~
SI I Life Cycle Functions S}stem Plant Plant Commission, Plant llainterran~e Replaccmcnt
No. Specification Design }Ianufacture InsPall Operation
.,_.
IS 15363 (Part 1) :2003
ANNEX A
(Clause 6)
SUMMARY OF THE BENEFITS FROM USING TEROTECHNOLOGY
A- I The use of terotechnology can provide benefits in A-2 The use of terotechnology can have the following
the following areas: beneficial results:
a) Improved profitability, with appropriate balance
1) Reduction in total cost of ownership of between short and long term goals;
physical asset and hence increased b) Improved communications and sense of
profitability; common purpose between company functions
2) Demonstrable balance between long and enabling greater delegati& of asset management
short term profit goals; and tasks, encouraging junior management to
develop healthy attitudes;
3) Identifies future penalties associated with
expedient short term actions. c) Reduction in time spent on asset management
by senior managers, whilst, demonstrably
b) Communications and Control:
improving control and asset management
1) Improved understanding between senior activities; and
management and other business functions d) Lower development and production costs
(on topic of asset management) using through:
common language of total cost of ownership;
1) Limited performance improvement
2) Cross-fertilization of good ideas and data objectives
across traditional functional boundaries;
2) Elimination of non-essential functions;
3) Greater scope for delegation of asset 3) Design simplicity;
management tasks to junior staf~ leaving
4) Greater use of design inheritance;
time for more important decision making.
Emphasis on more coherent inputs from 5) Greater use of standard and commercial
below (less risk, time saving); products;
4) Provides common goals and language for 6) Use of high volume production parts; and
all functions within the business; 7) Designing to facilitate multiple source
Encourages a multi-disciplinary approach to competition.
5)
management which develops healthy e) Improved reliability through:
attitudes in respect ofi 1) Greater use of proven design;
i) Inter-functional relationships; 2) Greater attention to non-random failures;
ii) Short versus long term effects; 3) Simplified design;
6) Provides a rational approach to asset 4) Improved quality control;
management which will allow senior 5) More efficient development and test
managers to make decisions on the basis of procedures;
a lower volume of more meaningful
6) More representative and stringent
information.
environmental tests; and
c) Management Development:
7) Timely elimination of software errors.
I) Disciplines junior management to develop
f) Improved maintainability through:
appropriate balance between immediate
goals and future penalties or benefits; and 1) More design attention to maintainability;
14
,.
IS 15363 (Part l) :2003
ANNEX B
(Clause 14.3)
EXAMPLE OF A TEROTECHNOLOGY CHECKLIST
15
-.
1S 15363 (Part 1) :2003
.J) Production; P) Use the life cycle plan to monitor and record
4) Maintenance; progress and costs starting from the time when
acquisition was first considered.
5) Quality; and
q) Inform all concerned that changes in the
6) Safety. purchasing specification after the order is placed
c) Ensure that the statement of your requirements: will be prevented.
1) is unambiguous; and r) Ensure that there is a formal procedure for
dealing with proposals for modifications which
2) covers all relevant aspects of life cycle
may result from:
performance.
1) problems in design and manufacture or
d) Check that it will permit intending suppliers to:
construction; and
1) prepare without delay a specification for
2) unavoidable changes in requirements.
comment or agreement; or
2) submit proposals for modifications which B-1.3 After Delivery
they consider will make the asset feasible or
a) Check that those who will be responsible for
more acceptable on grounds of performance
operating and maintaining the unit are satisfied
or costs.
with:
e) Ensure that proposals for modification are
1) Its testing;
communicated to and acted upon without delay
by those who wi II be responsible for installing, 2) Its installation;
operating and maintaining the unit. 3) Availability of documentsimanuals for
operation and maintenance;
f) Ensure that the proposals for modifications made
by the organization are kept to the necessary 4) Its performance; and
minimum and can be justified.
5) Their relationship with the supplier.
@ Check that the effects on cost and delivery of
modifications to the asset in question are fully b) Ensure that all legal, regulatory and commercial
formalities are completed correctly (for example,
communicated.
those relating to safety and warranties).
h) Ensure that decisions on proposals for
modifications are communicated without delay c) Review how promises, estimates or forecasts ofi
to the potential supplier. 1) Functional performance;
j) Review terms of warranties offered by intending 2) Spares;
suppliers when placing the order. Assess their
3) Reliability;
potential value and take this into account in
economic assessments. 4) Maintainability; and
k) Ensure that the purchasing specification has 5) costs;
been agreed by al I those who were consulted on have been substantiated or modified between
acquisition of the unit in question. placing the order and acceptance of the unit.
Ill
) Ensure that the purchasing specification includes
d) Consult with those in the organization who are
adequate data on all aspects of life cycle
responsible for Finance, Marketing, Production,
performance.
Maintenance, Purchasing and Quality on how
n) Ask for confirmation of warranties, price and this review will affect the organizations’ future
delivery. plans.
16
Bureau of Indian Standards
BISisastatutory institution established under tile Bureau oJ/ndian Standards Act, 1986 to promote harmonious
development of the activities of standardization, marking and quality certification of goods and attending to
connected matters in the country.
Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form
without the prior permission in writing of BIS. This does not preclude the free use, in the course of implementing
the standard, of necessary details, such as symbols and sizes, type or grade designations. Enquiries relating to
copyright be addressed to the Director (Publication), BIS.
Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewed
periodically; a standard along with amendments is reaffirmed when such review indicates that no changes are
i
needed; if the review indicates that changes are needed, it is taken up for revision. Users of Indian Standards
should ascertain that they are in possession of the latest amendments or edition by referring to the latest issue of
‘BIS Catalogue’ and ‘Standards: Monthly Additions’.
This Indian Standard has been developed from Dot: No. MSD 4 (223).
,-
Amendments Issued Since Publication