You are on page 1of 7

TUNNELS IN CLOSE PROXIMITY

K W l.D - SENIOR LEGTURER, DEPT. OF CIVIL ENGINEERING, NATIONAL UNIVERSITY OF SINGAPORE


S L LEE - PROFESSOR AND HEAD, DEPT. OF CIVIL ENGINEERING, NATIONAL UNIVERSITY OF SINGAPORE
H MAKINO - PROJEGT MANAGER, KAJIMA-KEPPEL JOINT VENTURE
L K CHANG - RESEARCH ASSISTANT, DEPT. OF CIVIL ENGINEERING, NATIONAL UNIVERSITY OF SINGAPORE
C F LEUNG - LEGTURER, DEPT. OF CIVIL ENGINEERING, NATIONAL UNIVERSITY OF SINGAPORE
T MIHARA - MANAGER DESIGNING, KAJIMA-KEPPEL JOINT VENTURE

SUMMARY their Technology Transfer Unit, to understudy the tunnel


A field instrumentation programme has been carried instrumentation work.
out in the vicinity of Connaught Drive under joint The following discussion is mainly concerned with the
research funding by the National University of Singapore findings of this field instrumentation research project.
and Kajima Corporation. The research project has Due to various contractual constraints, it has not been
provided a unique opportunity to study the nature of possible to include measurement data collected for a
multiple tunnel-ground interaction resulting from wide range of ground conditions and interacting tunnel
excavations for an intricate pattern of 4 interweaving configurations in the remaining MRT system. Fortunately,
tunnels. Each of the mass rapid transit (MRT) tunnels some surface settlement measurements for the twin
were of 5.85m diameter, excavated in generally stiff tunnel drive between Somerset and Dhoby Ghaut
ground conditions. However, part of the tunnels passed Stations constructed in similar ground conditions as the
·through a pre-grouted buried channel. Another set of Connaught Drive site could be released by the MRTC.
surface settlement data made available for this study The results of these measurements will also be briefly
was for the twin tunnel drive between Somerset and dealt with.
Dhoby Ghaut Stations constructed in· similar ground
conditions as the Connaught Drive site. GROUND CONDITIONS
In the following discussion, some results of lining
thrusts and bending moments as well as ground surface A preliminary site investigation was carried out during
settlements arising from multiple tunnel interactions in the initial geotechnical study for the MRT system. More
the two stretches of alignment are presented, with detailed investigations were subsequently performed
particular emphasis on the instrumentation project at soon before and at various stages of construction,
Connaught Drive and current design practices. including standard penetration, electrical cone
penetration, piezocone and pressuremeter tests. The
longitudinal subsoil profile along NB tunnel is shown in
Fig. 1. In general, subsurface conditions along the
INTRODUCTION transitional alignment consist of layers of fill and/or loose
The Singapore MRT system, which comprises a natural deposits of up to 5m overall thickness overlying
north-south and an east-west branch of some 65km the Old Alluvium formation. In the vicinity of the site
overall length is presently in an advanced stage of spanning between instrumentation Sections C-C and D-
construction. About one-third of the system will run O however, an old buried channel was present which
underground, often as interacting twin tunnels in either reached a maximum depth of about 17m. The buried
horizontal or vertical configuration or transitions thereof, channel generally comprised intercalating layers of
and encountering a wide range of materials from very marine clay (M), beach sand (B), and fluvial sand (F1) or
soft waterlogged estuarine clays to rock formations of clay (F2), all of the Kallang formation. The clays in the
varying consistencies. The stretch between Raffles Place buried channel, as encountered during tunnelling were
and City Hall Stations is of particular interest from the generally very soft to soft. The sandy soils on
point of view of a tunnel interaction study in that the the other hand are loose to medium dense, consisting
changeover from north-south to east-west branches of of coarse sand with fine gravel. The Old Alluvium (0)
the system and vice-versa will take place within an mainly consists of stiff to hard clayey sands, the latter
approximate 1 km transition between stations, resulting having high standard penetration blow counts in excess
in an intricate pattern of 4 interweaving tunnels. of 50, penetration resistances tending as a whole to
In March 1985, the National University of Singapore increase rapidly with depth. Pressuremeter tests
and Kajima Corporation agreed, in principle, to establish performed in boreholes indicated that the deformation
a joint research project to carry out detailed tunnel modulus of the buried channel clays is about 1.2 MPa
instrumentation along a 90m stretch of the transitional whereas in the case of the sandy soils, it is in the order
alignment in the vicinity of Connaught Drive. of 6.0 MPa. For the Old Alluvium corresponding values
Subsequently, in view of their interest, the Singapore average 50 MPa. Consolidation tests carried out on
MRT Coropration (MRTC) was invited to participate in undisturbed samples indicated that a coefficient of
the research project. Latterly, a staff Engineer of the permeability of about 10' to 10-s em s·1 for both buried
MRTC was seconded to the research team, through channel clays as well as the Old Alluvium. For the
275
sandy soils of the buried channels on the other hand, embedded in the ground. In view of the requirement for
grain size analyses indicated a corresponding value of daily readings in 11 inclinometer tubings of some 40m
about 4 x 11J2 em s-1 • length each, an automatic data-logger was essential. For
corresponding vertical ground point displacements,
spider magnet extensometers were adopted, individual
REID INSTRUMENTATION AND TUNNEL magnets being spaced at 3m to 5m intervals along
tubings. Ground surface settlements were determined by
CONSTRUCTION levelling metal studs set in concrete blocks cast in-situ,
A wide variety of field instruments were installed and pore water pressures at selected ground locations
along lateral Sections A-A to D-D shown in Fig 2 to measured with pneumatic piezometers. The groundwater
monitor tunnel-ground and tunnel-tunnel interactions table was monitored by a dipmeter inserted in a
during excavations. The sections were approximately perforated PVC standpipe installed in sand surround.
30m apart, covering a total longitudinal stretch of some In the case of precast concrete segmental linings,
90m of alignment. To determine horizontal ground point strain gauge type stress-meters welded co-axially with
displacements along and perpendicular to the direction top and bottom reinforcement bars were used to
of tunnel drives, a servo-accelerometer type inclinometer determine bending moments and axial thrusts at
was used. Measurements were taken at prescribed selected points along each ring. To determine effective
intervals along vertical as well as inclined PVC tubing pressures around the extrados, complementary pairs of

Zm zo zo
Qm Q() Qo

~~
t;
~I mt
CPT qc' (MPa) SPT 'N'

0 5 10 0 20 40
105 r-r-

W:O:///(::(/(//(///// -z::,.
- - _ . _ ~,, _ ,.,, - _ Y'' _-
V/mL ///1\ V////L
"''" - - M -_- .w,
- - --
.. ~ .. v . . " . . . " . v c: ?- . ( . " ."
95

90
]:
c
.Q 85
~
iii
80
Horizontal scale
75 0 5 10 (m)
==-- 0 40 80 100

FIG. 1 LONGITUDINAL SOIL PROFILE

Ee lnclinometer/Extensometer • Piezometer
? Settlement Point 0 S1andpipe

..,
., .....-N ".oL-
L~
(l_

L"' 0 10 20 (m)

FIG. 2 INSTRUMENTATION LAYOUT


276
total pressure cells and pneumatic piezometers were be necessary. In the case of tunnel lining
jacked out through prefabricated openings and set flush instrumentation on the other hand, measurements were
with the outer lining surface, or occasionally to bear on made once every other day from the date of installation,
the excavated peripheral ground surface. The distortion as well as whenever other tunnels were within
of lining rings was determined by convergence influencing distance of monitoring sections. Otherwise,.
measurements with a tape extensometer anchored at readings were taken at least once a fortnight. Selected
opposite end reference studs. Fig 3 shows a typical results from the foregoing instrumentation are presented
monitoring section. in the following discussion.
All four headings were advanced by conventional
semi-mechanical shield tunnelling. The basic sequence
of construction consisted of first excavating the tunnel RESULTS Of MONITORING
face with a backactor, followed by a forward shove of
the shield by circumferential jacks reacting against Lining Loads
installed lining. Additional lining segments were then Fig 4 provides a comparison between axial thrust
erected in the vacated space at the tail end of the interaction factors based on Peck's (1969) empirical
shield. Generally, five standard segments, each of approach and as determined from stress meter readings
approximately 3.5m extrados length and 1m width, and at various locations of different tunnels. Accordingly, the
one key segment of about 1m extrados length and factors obtained from measurements were generally
similar width were interconnected to form a complete within two times of those obtained empirically.
ring. To reduce the peripheral take, low pressure primary Corresponding intereaction factors for bending moments
grout of bentonite-cement mix was injected through pre- in linings have also been plotted in Fig 5 as a function
formed holes in the lining so as to fill the annular gap of tunnel separation. In this case, generally better
between excavated ground surface and lining shortly agreement is obtained between factors although some
after removal of shield support. Some 2 weeks after extreme variations may also be noted. These
completion of primary grouting, high pressure secondary discrepancies may be partly associated with the
grouting was carried out via the same holes to fill in presence of nearby joints, staggered in both longitudinal
any persistent voids in the grouted annulus. Where the and transverse directions, at which significant local re-
shallower westbound (WB) and northbound (NB) tunnels distribution of bending moments can take place. The
were partially and totally constructed through buried other source of differences is the rotations that occur at
channel deposits respectively, pre-treatment by cement contact faces between adjacent lining segments
and chemical grouting was carried out. To further resulting in eccentricity of thrust loading. Nevertheless,
minimise ground movements during excavations, Fig 6 shows that, even after interactions between SB
compressed air pressure support of up to 1.5 bars was and other tunnels had taken place, combined loadings
applied in headings together with face timber boarding from thrusts and bending moments at various stress
support as required. meter locations in the tunnel kept well within safe
Construction works for SB tunnel began in February design capacities of precast concrete segments. The
1985, the heading arriving at monitoring Section A-A in load capacity envelopes shown constitute an upper
mid-June of that year and passing Section D-D some 4 bound on plots of empirically-determined bending
weeks thereafter. The general sequence of tunnelling in moments and axial thrusts based on assumed
the monitoring zone was SB, EB, WB and finally NB, interaction factors (Kajima-Keppel J.V., 1985) applied to
the latter tunnel passing Section D-D in early June Curtis' (1976) single tunnel design loading. For the
1986. Throughout this period, ground instrumentation purpose of comparison, those empirical plots
measurements were made on a daily basis once tunnel corresponding to the measurement results have been
excavations came within 30m of monitoring sections. At included in the figure, as also the results of finite
wider separations, only weekly readings were found to element analyses based on Kajima-Keppel J.V. (1984)

Connaught Drive

Fill
Marine Clay M
Beach Sand B
~
0
3
Old Alluvium 0

1 Inclinometer/
extensometer
2 Settlement
point
3 Piezometer
4 Stress meter
5 Total pressure
cell
6 Tape
7 extensometer
7 Inclinometer

FIG. 3 SECTION B-B

277
1m = le
2.0

_, 1.6
~
0
13 1.2
~ 0 Initial Tunnel: Final Tunnel:
]
+ SB WB
""' 0.8• A
""'
::;; A EB WB
0.4 + [] EB WB
0 WB WB

0.0 0.4 0.8 1.2 1.6 2.0

Empirical Factors le

FIG. 4 INTERACTION FACTORS fOR THRUSTS

Initial Tunnel: Final Tunnel:


X SB NB

+ SB WB

0 WB NB
3 WB NB

4.0

2.0
al Relationship'
+
0

0.0 1.0 2.0 3.0

No. of Tunnel Diameters Clearance

FIG. 5 INTERACTION FACTORS FOR MOMENTS

278


WB/NB

SB/EB ®
® I
2000 "--....Empirical points

()
Stress
1500 Meter
Locations
NB Ef\:D EB & WB
EB & ,.,.® NB
WB '<>
1000 Finite Element
I I I
SB WB NB
.. .. + Design
Curves:
moment
500 @Joint
- moment
@Joint

concrete
section

0 50 100 150

Moment M (kN m)

Note: Measurement plots unless otherwise stated

FIG. 6 COMBINED THRUST AND MOMENT


LOADING AT SECTION A-A

parameters. It is notable that although, as for the case EB tunnels respectively. In current practice, surface
of measurement plots, the results of the analyses and settlement profiles associated with individual tunnels are
empirical predictions show a trend towards increasing superimposed to obtain cumulative effects of multiple
bending moments with further tunnel interaction, tunnel excavations. Since SB and EB tunnels are
measurement results show a tendency for significantly reasonably level and located in similar soils, ground
greater thrusts to develop in these circumstances than response to initial SB tunnel drive may, according to
either method of prediction, so that the overall margin of Peck's empirical approach (1969a), also be attributed to
safety will be greatly enhanced. EB tunnel in determining their cumulative effect.
However, field measurements superimposed on the
Ground surface settlements same plot indicate greater cumulative settlements, by
Fig 7 shows an empirical ground surface profile for some 18% at maximum value, than determined
cumulative ground losses from excavations for SB and empirically. Such a tendency is commonly observed and

q,
0.0

tic Empirical
10.0
c Approach
"E c
.s \
E Measured
.,"E 20.0 .c c · c / results
~
en
30.0 L_--.----,r-l--~_l~---.----.----1
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0
Horizontal Distance (m)

FIG. 7 SURFACE SETTLEMENT AT SECTION A-A


279
may be attributed to weakening of the ground in the empirically determined. These differences in respective
vicinity of an initial tunnel (SB) causing relatively greater site responses may be attributed to the weaker ground
ground losses during excavations lor a subsequent conditions of the north-south alignment, where a layer of
tunnel arrival (EB) than the single tunnel case. Fig 8 estuarine clay of some 3m thickness was present
shows the only other available source of ground surface Furthermore, unlike the Connaught Drive site, but
settlement data on MRT construction, which was following a common observation (Hansmire, 1975), a
supplied by the MRTC. Ground conditions in this stretch significant bias of the measured settlement profile
of alignment between Somerset and Dhoby Ghaut towards the first arrival tunnel may be noted in Fig 8.
Stations are similar to those at the transitional alignment Such a tendency may be attributed to effective
including Connaught Drive site, to which it is weakening of the ground in the vicinity of the first arrival
contiguous, thereby providing a basis for comparison of tunnel resulting in relatively more ground loss there
respective ground responses. The cumulative ground when excavations for the second arrival tunnel became
loss surface profile associated with the twin tunnel effective.
drives between Somerset and Dhoby Ghaut Stations Figs 9 and 10 show longitudinal surface settlement
was also obtained by superimposing individual profiles associated with excavations for WB and NB
excavation effects of the two tunnels. However, tunnels respectively. Since each tunnel had already
compared to Fig 7 for Connaught Drive, cumulative as been preceded by others, these profiles reflect not only
well as relative (to the single tunnel case) interaction ground losses due to the respective tunnel excavations,
settlements were substantially greater than determined but also their interactions with existing tunnels.
empirically, as indicated by the average surface According to the figures, an error function provides a
settlement profiles inferred from measurements made at good fit to the incremental settlement data, as hitherto
similar lateral section. For instance, the maximum only assumed in practice for single tunnel ground
cumulative field settlement was some 100% more than surface response (Yoshikoshi et al, 1978).

Distance (m)

80 70 60 50 40 30 20 10 0

--- ---
0

+ Measurement for
Field
SB alone 25
Measurement for SB & NB Settlement
" Curve for SB
(/)
Empirical 50 11
GL
Settlement Curve
for SB & NB X "33
~

75
Fill '
3 It\
Estuarine Clay E -- .2.
Sedimentary
'"
3 NB SB
100
'
Residual Soil Field Settle-
S4 ment Curve for
fL SB & NB 125
'i
-
NB SB
Tunnel Tunnel

FIG. 8 SURFACE SETTLEMENT BETWEEN SOMERSET


AND DHOBY GHAUT STATIONS

-10.0 . - - - - - - - - - - - - - - - - - - - - - ,
Maximum Settlement = 19.0mm
Standard Deviation = 10.5m

0.0
c
"E
.s
E 10.0 c c
E "
"i c
(f) c c
20.0

-20.0 -10.0 0.0 10.0 20.0 30.0 40.0 50.0

Distance from Excavation Face (m)

FIG. 9 LONGITUDINAL PROFILE FOR WB TUNNEL


280
-5.0 , . - - - - - - - - - - - - - - - - - - ,
Maximum Settlement = 12.5mm
Standard Deviation = 9.0m

0.0
D
D
D

5.0

10.0

D
15.0 '----~-~-~--~-~-~-~----"
- 30.0 - 20.0 -10.0 0.0 10.0 20.0 30.0 40.0 50.0

Distance from Excavation Face (m)

FIG. 10 LONGITUDINAL PROFILE FOR NB TUNNEL

REFERENCES PECK, R.B., Design of Tunnel Liners and Support


Systems, Final Report for Office of. High Speed
CURTIS, D.J., Discussion on "The Circular Tunnel in Ground Transporation, Washington D.C. 20591, 1969.
Elastic Ground", Geotechnique, Vol. 26, No. 1, 1976, PECK, R.B., Deep Excavation and Tunnelling in Soft
pp. 231-237. Ground, State of the Art Report, 7lh Int. Cont. on Soil
HANSMIRE, W.H., Field Measurement of Ground Mech. and Found. Engg., Mexico City, 1969a, pp.
Displacement about a Tunnel in Soil, PhD Thesis, 255-290.
Univ. of Illinois at Urbana Champaign, 1975. YOSHIKOSHI, W., WATANABE, 0 and TAKAGI, N.,
KAJIMA-KEPPEL JV., Finite Element Analysis of Bored Prediction of Ground Settlements Associated with
Tunnels, Report for Singapore MRT Contract, 107, Shield Tunnelling, Soils and Foundations, Vol. 18, No.
1984. 4, 1978, pp. 47-59.
KAJIMA-KEPPEL J.V., Design Calculation for Bored
Tunnels, Report No. C/MC/107/CB for Singapore MRT
Contract 107, 1985.

ACKNOWLEDGEMENTS
The research upon which this paper is based was funded in part by the Science Council of Singapore under
RDAS Grant No. C/81/04-06 which is gratefully acknowledged. The authors also wish to express their thanks to the
Mass Rapid Transit Corporation of Singapore, in particular Mr S Doran for providing the settlement data between
Dhoby Ghaut and Somerset Stations and Engineer Chow Peng Wah for his keen contribution to the tunnel
instrumentation work. Our thanks are also due to Messrs P Copsey and R A Gee for their assistance in expediting
the installation work.
281

You might also like