AVIDA ATRIA TOWER 3 FIT-OUT PROJECT

Atria, Mandurriao, Iloilo City

PROGRESS REPORT
AS OF JULY 10-16, 2021
1. Painting works of wall 95% completed (retouch works outstanding)
2. Painting works on ceiling 95% completed (retouch works outstanding)
3. Painting works on Powder Room Door and Jamb 100% completed
4. Painting works on conwood 100%
5. Painting works on ACU enclosure 100% completed
6. Tile works on powder room wall 100% completed
7. Tile works on powder room floor 100% completed
8. On-going Lobby tile floor repair
9. Electrical works 80% completed
10. Installation of Tissue Despenser
11. Installation of Wallsconce at powder room
12. Installation of powder room cabinet
13. Installation of WC
14. Installation of Urinal
15. Picture.

1
2
3
Prepared by Noted by:
Engr. Jeremiah V. Gilbolinga Engr. Paul Lorenz Carmelo