Resource Usage as of Wed 6/30/21

IBSS Proposed Project Schedule_PHASE III_210611.mpp

7/4/21 7/11/21 7/18/21 7/25/21 8/1/21 8/8/21 8/15/21 8/22/21 8/29/21 9/5/21 9/12/21 9/19/21 9/26/21 10/3/21 10/10/21 10/17/21 10/24/21 10/31/21 11/7/21 11/14/21 11/21/21 11/28/21 12/5/21 12/12/21 12/19/21 12/26/21 1/2/22 1/9/22 1/16/22 1/23/22 1/30/22 2/6/22 2/13/22 2/20/22 2/27/22 3/6/22 3/13/22 3/20/22 3/27/22 4/3/22 4/10/22 4/17/22 4/24/22 5/1/22 5/8/22 5/15/22 5/22/22 5/29/22 6/5/22 6/12/22 6/19/22 6/26/22 7/3/22 7/10/22 7/17/22 7/24/22 7/31/22 8/7/22 8/14/22 8/21/22 8/28/22 9/4/22 9/11/22 9/18/22 9/25/22 10/2/22 10/9/22 10/16/22 10/23/22 Total
Architect Principal
Architect Senior
Architect 1
Architect 2
Designer Principal 40 hrs 40 hrs 26 hrs 28 hrs 40 hrs 48 hrs 22 hrs 40 hrs 20 hrs 20 hrs 20 hrs 20 hrs 8 hrs 8.8 hrs 380.8 hrs
Presentation of Concept Design 8 hrs 8 hrs
Review & Comments on Concept Design 2 hrs 4 hrs 6 hrs
Revise Concept Based on Comment 24 hrs 24 hrs
Revised Concept Design For Approval 8 hrs 8 hrs
Perspectives & Material Board Specifications from Approved Concept Plans 32 hrs 40 hrs 72 hrs
Presentation of Schematic Design & Material Boards 8 hrs 8 hrs
Review & Comments of Schematic Design 6 hrs 6 hrs
Revise Schematic Based on Comment 16 hrs 32 hrs 48 hrs
Revised Schematic Design For Approval 8 hrs 8 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Designer Senior 40 hrs 40 hrs 26 hrs 28 hrs 40 hrs 48 hrs 22 hrs 40 hrs 20 hrs 20 hrs 20 hrs 20 hrs 12.8 hrs 12.8 hrs 9.6 hrs 8 hrs 4 hrs 4 hrs 4.8 hrs 4 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 624 hrs
Presentation of Concept Design 8 hrs 8 hrs
Review & Comments on Concept Design 2 hrs 4 hrs 6 hrs
Revise Concept Based on Comment 24 hrs 24 hrs
Revised Concept Design For Approval 8 hrs 8 hrs
Perspectives & Material Board Specifications from Approved Concept Plans 32 hrs 40 hrs 72 hrs
Presentation of Schematic Design & Material Boards 8 hrs 8 hrs
Review & Comments of Schematic Design 6 hrs 6 hrs
Revise Schematic Based on Comment 16 hrs 32 hrs 48 hrs
Revised Schematic Design For Approval 8 hrs 8 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Fit-Out Construction Bidding Documents 4 hrs 4 hrs
Fit-Out Construction Invitation To Bid 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Preparation 4 hrs 4 hrs 4 hrs 4 hrs 16 hrs
Fit-Out Construction Submission of Bids 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Negotiation 4 hrs 4 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
Designer 1 40 hrs 40 hrs 26 hrs 28 hrs 40 hrs 48 hrs 22 hrs 40 hrs 20 hrs 20 hrs 20 hrs 20 hrs 8 hrs 8.8 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 580.8 hrs
Presentation of Concept Design 8 hrs 8 hrs
Review & Comments on Concept Design 2 hrs 4 hrs 6 hrs
Revise Concept Based on Comment 24 hrs 24 hrs
Revised Concept Design For Approval 8 hrs 8 hrs
Perspectives & Material Board Specifications from Approved Concept Plans 32 hrs 40 hrs 72 hrs
Presentation of Schematic Design & Material Boards 8 hrs 8 hrs
Review & Comments of Schematic Design 6 hrs 6 hrs
Revise Schematic Based on Comment 16 hrs 32 hrs 48 hrs
Revised Schematic Design For Approval 8 hrs 8 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
Designer 2 40 hrs 40 hrs 26 hrs 28 hrs 40 hrs 48 hrs 22 hrs 40 hrs 20 hrs 20 hrs 20 hrs 20 hrs 8 hrs 8.8 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 580.8 hrs
Presentation of Concept Design 8 hrs 8 hrs
Review & Comments on Concept Design 2 hrs 4 hrs 6 hrs
Revise Concept Based on Comment 24 hrs 24 hrs
Revised Concept Design For Approval 8 hrs 8 hrs
Perspectives & Material Board Specifications from Approved Concept Plans 32 hrs 40 hrs 72 hrs
Presentation of Schematic Design & Material Boards 8 hrs 8 hrs
Review & Comments of Schematic Design 6 hrs 6 hrs
Revise Schematic Based on Comment 16 hrs 32 hrs 48 hrs
Revised Schematic Design For Approval 8 hrs 8 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
3D Senior Architect 40 hrs 40 hrs 16 hrs 32 hrs 20 hrs 20 hrs 20 hrs 20 hrs 208 hrs
Perspectives & Material Board Specifications from Approved Concept Plans 40 hrs 40 hrs 80 hrs
Revise Schematic Based on Comment 16 hrs 32 hrs 48 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
3D Architect 1 40 hrs 40 hrs 16 hrs 32 hrs 20 hrs 20 hrs 20 hrs 20 hrs 208 hrs
Perspectives & Material Board Specifications from Approved Concept Plans 40 hrs 40 hrs 80 hrs
Revise Schematic Based on Comment 16 hrs 32 hrs 48 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
3D Architect 2 40 hrs 40 hrs 16 hrs 32 hrs 20 hrs 20 hrs 20 hrs 20 hrs 208 hrs
Perspectives & Material Board Specifications from Approved Concept Plans 40 hrs 40 hrs 80 hrs
Revise Schematic Based on Comment 16 hrs 32 hrs 48 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Manager Senior
Manager 1
Manager 2
QS Senior 40 hrs 40 hrs 40 hrs 40 hrs 66 hrs 46 hrs 54 hrs 50 hrs 10 hrs 10 hrs 12 hrs 40 hrs 448 hrs
Prepare General Plan, Finishes & Elevations 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Prepare Detailed Construction Drawings 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 20 hrs 20 hrs 40 hrs
Value-Design & Update Vetting Plans 16 hrs 16 hrs
Revised Design Development For Approval
Fit-Out Construction Bidding Documents 40 hrs 40 hrs
Fit-Out Construction Invitation To Bid 2 hrs 2 hrs
Fit-Out Construction Bid Preparation 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Fit-Out Construction Submission of Bids 2 hrs 2 hrs
Fit-Out Construction Bid Negotiation 40 hrs 40 hrs
QS 1 40 hrs 40 hrs 40 hrs 40 hrs 66 hrs 46 hrs 54 hrs 50 hrs 10 hrs 10 hrs 12 hrs 40 hrs 448 hrs
Prepare General Plan, Finishes & Elevations 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Prepare Detailed Construction Drawings 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 20 hrs 20 hrs 40 hrs
Value-Design & Update Vetting Plans 16 hrs 16 hrs
Revised Design Development For Approval
Fit-Out Construction Bidding Documents 40 hrs 40 hrs
Fit-Out Construction Invitation To Bid 2 hrs 2 hrs
Fit-Out Construction Bid Preparation 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Fit-Out Construction Submission of Bids 2 hrs 2 hrs
Fit-Out Construction Bid Negotiation 40 hrs 40 hrs
QS 2 40 hrs 40 hrs 40 hrs 40 hrs 66 hrs 46 hrs 54 hrs 50 hrs 10 hrs 10 hrs 12 hrs 40 hrs 448 hrs
Prepare General Plan, Finishes & Elevations 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Prepare Detailed Construction Drawings 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 20 hrs 20 hrs 40 hrs
Value-Design & Update Vetting Plans 16 hrs 16 hrs
Revised Design Development For Approval
Fit-Out Construction Bidding Documents 40 hrs 40 hrs
Fit-Out Construction Invitation To Bid 2 hrs 2 hrs
Fit-Out Construction Bid Preparation 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Fit-Out Construction Submission of Bids 2 hrs 2 hrs
Fit-Out Construction Bid Negotiation 40 hrs 40 hrs
CAD Senior 20 hrs 20 hrs 20 hrs 20 hrs 4 hrs 84 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
CAD 1 20 hrs 20 hrs 20 hrs 20 hrs 4 hrs 84 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
CAD 2 40 hrs 40 hrs 40 hrs 40 hrs 4 hrs 164 hrs
Prepare General Plan, Finishes & Elevations 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Prepare Detailed Construction Drawings 20 hrs 20 hrs 20 hrs 20 hrs 80 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
CAD Junior 1 20 hrs 20 hrs 20 hrs 20 hrs 4 hrs 84 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
CAD Junior 2 20 hrs 20 hrs 20 hrs 20 hrs 4 hrs 84 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Structural Senior 4 hrs 4 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Structural Designer 8 hrs 20 hrs 20 hrs 20 hrs 20 hrs 12.8 hrs 12.8 hrs 9.6 hrs 8 hrs 4 hrs 4 hrs 4.8 hrs 4 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 348 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Fit-Out Construction Bidding Documents 4 hrs 4 hrs
Fit-Out Construction Invitation To Bid 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Preparation 4 hrs 4 hrs 4 hrs 4 hrs 16 hrs
Fit-Out Construction Submission of Bids 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Negotiation 4 hrs 4 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
Structural Junior
Mechanical Senior 4 hrs 4 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Mechanical Designer 16 hrs 20 hrs 20 hrs 20 hrs 20 hrs 12.8 hrs 12.8 hrs 9.6 hrs 4 hrs 4 hrs 4 hrs 4.8 hrs 4 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 352 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Fit-Out Construction Bidding Documents 4 hrs 4 hrs
Fit-Out Construction Invitation To Bid 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Preparation 4 hrs 4 hrs 4 hrs 4 hrs 16 hrs
Fit-Out Construction Submission of Bids 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Negotiation 4 hrs 4 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
Mechanical Junior
Electrical Senior 4 hrs 4 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Electrical Designer 16 hrs 20 hrs 20 hrs 20 hrs 20 hrs 12.8 hrs 12.8 hrs 9.6 hrs 8 hrs 4 hrs 4 hrs 4.8 hrs 4 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 356 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Fit-Out Construction Bidding Documents 4 hrs 4 hrs
Fit-Out Construction Invitation To Bid 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Preparation 4 hrs 4 hrs 4 hrs 4 hrs 16 hrs
Fit-Out Construction Submission of Bids 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Negotiation 4 hrs 4 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
Electrical Junior
Plumbing Senior 4 hrs 4 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Plumbing Designer 16 hrs 20 hrs 20 hrs 20 hrs 20 hrs 12.8 hrs 12.8 hrs 9.6 hrs 8 hrs 4 hrs 4 hrs 4.8 hrs 4 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 356 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Fit-Out Construction Bidding Documents 4 hrs 4 hrs
Fit-Out Construction Invitation To Bid 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Preparation 4 hrs 4 hrs 4 hrs 4 hrs 16 hrs
Fit-Out Construction Submission of Bids 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Negotiation 4 hrs 4 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
Plumbing Junior
Fire Senior 4 hrs 4 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Fire Designer 16 hrs 20 hrs 20 hrs 20 hrs 20 hrs 12.8 hrs 12.8 hrs 9.6 hrs 8 hrs 4 hrs 4 hrs 4.8 hrs 4 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 196 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Fit-Out Construction Bidding Documents 4 hrs 4 hrs
Fit-Out Construction Invitation To Bid 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Preparation 4 hrs 4 hrs 4 hrs 4 hrs 16 hrs
Fit-Out Construction Submission of Bids 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Negotiation 4 hrs 4 hrs
EXECUTION PHASE 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 2 hrs 40 hrs
Fire Junior
Electronics Senior 4 hrs 4 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Electronics Designer 16 hrs 20 hrs 20 hrs 20 hrs 20 hrs 12.8 hrs 12.8 hrs 9.6 hrs 8 hrs 4 hrs 4 hrs 4.8 hrs 4 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 356 hrs
Prepare General Plan, Finishes & Elevations 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Prepare Detailed Construction Drawings 10 hrs 10 hrs 10 hrs 10 hrs 40 hrs
Submission of Design Development & Vetting Plans 4 hrs 4 hrs
QS Review & Bulletin on Design Development 4 hrs 4 hrs 8 hrs
Value-Design & Update Vetting Plans 4 hrs 4 hrs
Revised Design Development For Approval 0.8 hrs 0.8 hrs
Fit-Out Construction Bidding Documents 4 hrs 4 hrs
Fit-Out Construction Invitation To Bid 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Preparation 4 hrs 4 hrs 4 hrs 4 hrs 16 hrs
Fit-Out Construction Submission of Bids 0.8 hrs 0.8 hrs
Fit-Out Construction Bid Negotiation 4 hrs 4 hrs
EXECUTION PHASE 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 10 hrs 200 hrs
Electronics Junior
Total 248 hrs 160 hrs 104 hrs 112 hrs 280 hrs 312 hrs 136 hrs 256 hrs 500 hrs 500 hrs 500 hrs 500 hrs 311.6 ... 298 hrs 229.2 ... 202 hrs 58 hrs 58 hrs 69.6 hrs 148 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 82 hrs 6,622.4 hrs