N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
1 DAKHA 1
2 MILESTONES 2
3 GENERAL MILESTONES 3
4 Performance Security submission 4 28/03
5 Commencement date 5 01/05
6 Evidence of insurance Policy 6 13/05
7 beginning the Insurance policy 7 27/05
8 EMPLOYER'S RESPONSABILITIES 8
9 Letter of acceptance 9 01/03
10 Contract signed 10 14/03
11 Down payment or advance payment 11 28/03
12 Free and Uninterrupted Access To Intake Site, Pipeline Corridor (60%) and WTP Site 12 01/05
13 Free and Uninterrupted Access To Pipeline Corridor (100%) 13 30/06
14 Validation of the Selected Pipes Suppliers by the Employer 14 28/07
15 Environment Permit, EIA 15 25/04
16 Revised Seismic Design Report (delivery from Engineer) 16 29/07
17 BWDB & BITWA permits (Intake) 17 16/11
18 Available utilities 18
19 Electricity Available For Testing 19 09/09
20 Water Available for Testing 20 03/06
21 Gas Available for Testing 21 13/01
22 Fuel Available for Testing 22 13/01
23 PERMITS 23
24 Administrative Permit Delivery 24 Administrative Permit Delivery
25 Excavation Permit Delivery 25 23/09
26 Construction Permit Delivery 26 Construction Permit Delivery
27 CIVIL WORKS SUBCONTRACTOR'S RESPONSIBILITIES 27
28 Subcontract signature 28 04/04
29 Advance Paiement Bond from CW Sub‐Contractor 29 28/03
30 Performance Bond from CW Sub‐Contractor 30 28/03
31 Evidence of insurance Policy from CW Sub‐Contractor 31 13/05
32 DESIGN 32
33 BASIC DESIGN 33
34 Prepare Preliminary P&ID's 34 Prepare Preliminary P&ID's
35 DATA AND CALCULATIONS 35 DATA AND CALCULATIONS
36 DIAGRAMS & GRAPHS 36 DIAGRAMS & GRAPHS
37 General Arrangement Drawings 37 General Arrangement Drawings
38 Specification 38 Specification
39 ELECTRICAL 39 ELECTRICAL
40 HVAC 40 HVAC
41 Architectural 41 Architectural
42 Civil Guide drawing by JV & Approval in Principle by Employer 42
43 Intake off shore 43 Intake off shore
44 Inlet Pumping Station 44 Inlet Pumping Station
45 22kms RWP route and typical 45 22kms RWP route and typical
46 TWR treated water reservoir & treated water pumping station 46 TWR treated water reservoir & treated water pumping station
47 Other process zone 47 Other process zone
48 Building 48 Building
49 Preliminary Civil Calculation and Drawing by CW Design Engineering and Approval in 49
principle by Employer
50 Complementary detailed site investigation (topographic/geomechanical surveys, 50 Complementary detailed site investigation (topographic/geomechanical surveys, hydrology, occupation by existings, …), including Specific Permits Delivery by Authorities (if needed)
hydrology, occupation by existings, …), including Specific Permits Delivery by Authorities
(if needed)
51 Ground improvement, Ground dewatering, ELS and Special foundation 51 Ground improvement, Ground dewatering, ELS and Special foundation
52 Intake preliminary design 52 Intake preliminary design
53 Pumping station preliminary design 53 Pumping station preliminary design
54 22kms RWP temporary works preliminary calculations 54 22kms RWP temporary works preliminary calculations
55 TWR treated water reservoir & treated water pumping station preliminary design 55 TWR treated water reservoir & treated water pumping station preliminary design
56 Other process zone preliminary design 56 Other process zone preliminary design
57 Buildings preliminary design 57 Buildings preliminary design
58 DETAIL DESIGN 58
59 DRAWINGS & PLANS 59 DRAWINGS & PLANS
60 LISTS & SCHEDULES EAI 60 LISTS & SCHEDULES EAI
Construction Pgm_48m‐CD20160501_rev4.mpp Page 1
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR
N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
61 Detailed Design of 22kms RWP & Approval 61
62 Detail Design for First season 62 Detail Design for First season
63 Detail Design for 2nd and 3rd seasons 63 Detail Design for 2nd and 3rd seasons
64 DETAILED Guide Drawing & STUDIES 64
65 CIVIL GUIDE DRAWING & Approval 65
66 Intake 66 Intake
67 Pumping station 67 Pumping station
68 TWR treated water reservoir & treated water pumping station 68 TWR treated water reservoir & treated water pumping station
69 Other process zone 69 Other process zone
70 Building 70 Building
71 CIVIL WORKS FINAL DESIGN (Shop Drawings) & Approval by Employer 71
72 Intake 72 Intake
73 Pumping station 73 Pumping station
74 TWR treated water reservoir & treated water pumping station 74 TWR treated water reservoir & treated water pumping station
75 Other process zones 75 Other process zones
76 Building 76 Building
77 Control philosophy 77 Control philosophy
78 GENERAL PROCUREMENT (E/M equipment, pipe, HVAC, Elect...) 78
79 Intake & Pumping 79
80 Screens & pumps 80
81 Issuance Specifications 81 Issuance Specifications
82 procurement process 82 procurement process
83 Purchase Order 83 Purchase Order
84 Manufacturing 84 Manufacturing
85 Transport 85 Transport
86 Custom Clearance 86 Custom Clearance
87 Transport to site and unload 87 Transport to site and unload
88 Pipeline 22kms 88
89 Issuance of Specifications 89 Issuance of Specifications
90 procurement process 90 procurement process
91 Purchase Orders 91
92 1st Purchase Order 92 1st Purchase Order
93 Last Purchase Orders 93 Last Purchase Orders
94 Manufacturing 94
95 Manufacturing 1st season 95 Manufacturing 1st season
96 Manufacturing 2nd season 96 Manufacturing 2nd season
97 Manufacturing 3rd season 97 Manufacturing 3rd season
98 Transport & Custom Clearance 98
99 1st season ‐ Transport 99 1st season ‐ Transport
100 1st season ‐ Custom Clearance 100 1st season ‐ Custom Clearance
101 2nd season ‐ Transport 101 2nd season ‐ Transport
102 2nd season ‐ Custom Clearance 102 2nd season ‐ Custom Clearance
103 3rd season ‐ Transport 103 3rd season ‐ Transport
104 3rd season ‐ Custom Clearance 104 3rd season ‐ Custom Clearance
105 WTP for 525000 m3/day 105
106 Clarification / flocculation 106
107 Lamellas & scrapers 107
108 Issuance Specifications (Update) 108 Issuance Specifications (Update)
109 procurement process 109 procurement process
110 Purchase Order 110 Purchase Order
111 Manufacturing 111 Manufacturing
112 FAT 112 FAT
113 Transport 113 Transport
114 Custom Clearance 114 Custom Clearance
115 Transport to site and unload 115 Transport to site and unload
116 Filtration 116
117 Blower, media and air compressor 117
118 Issuance Specifications (Update) 118 Issuance Specifications (Update)
119 procurement process 119 procurement process
120 Purchase Order 120 Purchase Order
121 Manufacturing 121 Manufacturing
122 Transport 122 Transport
Construction Pgm_48m‐CD20160501_rev4.mpp Page 2
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR
N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
123 Custom Clearance 123 Custom Clearance
124 Transport to site and unload 124 Transport to site and unload
125 chlorine storage & dosing 125
126 Issuance Specifications (Update) 126 Issuance Specifications (Update)
127 procurement process 127 procurement process
128 Purchase Order 128 Purchase Order
129 Manufacturing 129 Manufacturing
130 Transport 130 Transport
131 Custom Clearance 131 Custom Clearance
132 Transport to site and unload 132 Transport to site and unload
133 Electrical Room & generator 133
134 Issuance Specifications (Update) 134 Issuance Specifications (Update)
135 procurement process 135 procurement process
136 Purchase Order 136 Purchase Order
137 Manufacturing 137 Manufacturing
138 Transport 138 Transport
139 Custom Clearance 139 Custom Clearance
140 Transport to site and unload 140 Transport to site and unload
141 Process Control (SCADA) 141
142 Technical bid package ready 142 17/02
143 procurement process 143 procurement process
144 Studies, 144 Studies,
145 order 145 order
146 Manufacturing elect panels & panel control 146 Manufacturing elect panels & panel control
147 FAT 147 FAT
148 functional Analysis 148 functional Analysis
149 Programming, 149 Programming,
150 Custom Clearance 150 Custom Clearance
151 Transport to site and unload 151 Transport to site and unload
152 Penstock & handing, Skips, Pumps & valves 152
153 Issuance Specifications (Update) 153 Issuance Specifications (Update)
154 procurement process 154 procurement process
155 Purchase Order 155 Purchase Order
156 Manufacturing 156 Manufacturing
157 Transport 157 Transport
158 Custom Clearance 158 Custom Clearance
159 Transport to site and unload 159 Transport to site and unload
160 EXECUTION 160
161 SITE WORKS 161
162 Start Works WTP 162 28/09
163 Mobilization / Installation 163 Mobilization / Installation
164 General Levelling & Temporary Access 164 General Levelling & Temporary Access
165 Employer's, Engineer's & Contractor' s Site Offices 165 Employer's, Engineer's & Contractor' s Site Offices
166 Laborers Accommodation 166 Laborers Accommodation
167 Temporary Access Refreshment for JV needs 167 Temporary Access Refreshment for JV needs
168 CONSTRUCTION PHASE 168
169 INTAKE 169
170 Intake off shore 170
171 CW 171
172 Construction of Cofferdam, Excavation 172 Construction of Cofferdam, Excavation
173 Piling 173 Piling
174 Under dewatering : concrete plug & base slab 174 Under dewatering : concrete plug & base slab
175 Structure 175 Structure
176 Watertightness Tests 176 Watertightness Tests
177 CW finishing 177 CW finishing
178 CR A‐01 ‐ Civil Works Construction Readiness CR A‐01 17/01
179 Installation equipment, Elect, piping etc. 179
180 big E/M equipment placing 180 big E/M equipment placing
181 E/M equipment and piping installation 181 E/M equipment and piping installation
182 Electricity / Automation 182 Electricity / Automation
183 E/M tests 183 E/M tests
184 Pumping station and ancillary building ‐on Shore 184
Construction Pgm_48m‐CD20160501_rev4.mpp Page 3
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR
N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
185 CW 185
186 Overall Platform Embankment 186 Overall Platform Embankment
187 Ground improvement 187 Ground improvement
188 Excavation 188 Excavation
189 Piling, foundations 189 Piling, foundations
190 infrastructures 190 infrastructures
191 Watertightness Tests 191 Watertightness Tests
192 Superstructures 192 Superstructures
193 End of CW finishes and big E/M equipment placing 193 End of CW finishes and big E/M equipment placing
194 CR A‐02 ‐ Civil Works Construction Readiness CR A‐02 31/07
195 Installation equipment, Elect, piping etc. 195
196 E/M equipment and piping installation 196 E/M equipment and piping installation
197 Electricity / Automation 197 Electricity / Automation
198 E/M tests 198 E/M tests
199 Off shore pipe laying 199
200 CW 200
201 Temporary access bund, sheet piling 201 Temporary access bund, sheet piling
202 Ground improvement 202 Ground improvement
203 Piling, foundations for metal footbridge 203 Piling, foundations for metal footbridge
204 Footbridge installation, removal of Access bund 204 Footbridge installation, removal of Access bund
205 CR A‐03 ‐ Civil Works Construction Readiness CR A‐03 26/04
206 Excavation 206 Excavation
207 Laying of pipelines 207 Laying of pipelines
208 Pipelines connection on up/down‐stream structures and watertproof testing 208 Pipelines connection on up/down‐stream structures and watertproof testing
209 Backfilling and finishing of anti‐erosion protecting system 209 Backfilling and finishing of anti‐erosion protecting system
210 External WORKS 210
211 Boundary Wall Fencing 211 Boundary Wall Fencing
212 Buried Interconnection Pipes and Cables Sleeves 212 Buried Interconnection Pipes and Cables Sleeves
213 CR A‐04 ‐ Civil Works Construction Readiness CR A‐04 21/11
214 Road works, including storm drainage network & Outdoor Lighting 214 Road works, including storm drainage network & Outdoor Lighting
215 Landscaping and Ending of Anti‐erosion Protective System 215 Landscaping and Ending of Anti‐erosion Protective System
216 22kms RWP pipeline 216
217 1st season 217
218 Picketing and mark‐up, Layout of the track 218 Picketing and mark‐up, Layout of the track
219 Temporary Access Road (included stripping of topsoil) 219
220 Front of attack n°1 ; 3670 m (60 m/day) 220 Front of attack n°1 ; 3670 m (60 m/day)
221 Front of attack n°2 ; 3670 m (60 m/day) 221 Front of attack n°2 ; 3670 m (60 m/day)
222 Opening of trenches, pipe laying and backfilling, accessories (32 m/day/team) : 222
223 JVP B‐01 ‐ Pipes and Accessories Delivery from JV at Chittagong: 1st package JVP B‐01 22/12
224 Transport to site and unload 224 Transport to site and unload
225 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 225 Front of attack n°1 ; 2480 m/74500 m (32 m /day)
226 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 226 Front of attack n°2 ; 2480 m/74500 m (32 m /day)
227 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 227 Front of attack n°3 ; 2480 m/74500 m (32 m /day)
228 Final Access Track (32 m/day/team), including embankment and slope protection 228
229 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 229 Front of attack n°1 ; 2480 m/74500 m (32 m /day)
230 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 230 Front of attack n°2 ; 2480 m/74500 m (32 m /day)
231 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 231 Front of attack n°3 ; 2480 m/74500 m (32 m /day)
232 Inspection and testing 232
233 Fronts n°1,2 & 3 233 Fronts n°1,2 & 3
234 CR B‐01 ‐ Civil Works Construction Readiness CR B‐01 04/05
235 2nd season 235
236 Picketing and mark‐up, Layout of the track 236 Picketing and mark‐up, Layout of the track
237 Temporary Access Road (included stripping of topsoil) 237
238 Front of attack n°1 ; 3670 m (60 m/day) 238 Front of attack n°1 ; 3670 m (60 m/day)
239 Front of attack n°2 ; 3670 m (60 m/day) 239 Front of attack n°2 ; 3670 m (60 m/day)
240 Opening of trenches, pipe laying and backfilling, accessories (32 m/day/team) : 240
241 JVP B‐02 ‐ Pipes and Accessories Delivery from JV at Chittagong: 1st package JVP B‐02 03/08
242 Transport to site and unload, including intermediate storage (if any) 242 Transport to site and unload, including intermediate storage (if any)
243 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 243 Front of attack n°1 ; 2480 m/74500 m (32 m /day)
244 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 244 Front of attack n°2 ; 2480 m/74500 m (32 m /day)
245 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 245 Front of attack n°3 ; 2480 m/74500 m (32 m /day)
246 Final Access Track (32 m/day/team), including embankment and slope protection 246
Construction Pgm_48m‐CD20160501_rev4.mpp Page 4
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR
N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
247 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 247 Front of attack n°1 ; 2480 m/74500 m (32 m /day)
248 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 248 Front of attack n°2 ; 2480 m/74500 m (32 m /day)
249 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 249 Front of attack n°3 ; 2480 m/74500 m (32 m /day)
250 Inspection and testing 250
251 Fronts n°1,2 & 3 251 Fronts n°1,2 & 3
252 CR B‐02 ‐ Civil Works Construction Readiness CR B‐02 20/04
253 3rd season 253
254 Picketing and mark‐up, Layout of the track 254 Picketing and mark‐up, Layout of the track
255 Temporary Access Road (included stripping of topsoil) 255
256 Front of attack n°1 ; 3670 m (60 m/day) 256 Front of attack n°1 ; 3670 m (60 m/day)
257 Front of attack n°2 ; 3670 m (60 m/day) 257 Front of attack n°2 ; 3670 m (60 m/day)
258 Opening of trenches, pipe laying and backfilling, accessories (32 m/day/team) : 258
259 JVP B‐03 ‐ Pipes and Accessories Delivery from JV at Chittagong: 1st package JVP B‐03 02/08
260 Transport to site and unload, including intermediate storage (if any) 260 Transport to site and unload, including intermediate storage (if any)
261 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 261 Front of attack n°1 ; 2480 m/74500 m (32 m /day)
262 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 262 Front of attack n°2 ; 2480 m/74500 m (32 m /day)
263 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 263 Front of attack n°3 ; 2480 m/74500 m (32 m /day)
264 Final Access Track (32 m/day/team), including embankment and slope protection 264
265 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 265 Front of attack n°1 ; 2480 m/74500 m (32 m /day)
266 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 266 Front of attack n°2 ; 2480 m/74500 m (32 m /day)
267 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 267 Front of attack n°3 ; 2480 m/74500 m (32 m /day)
268 Inspection and testing 268
269 Fronts n°1,2 & 3 269 Fronts n°1,2 & 3
270 CR B‐03 ‐ Civil Works Construction Readiness CR B‐03 19/04
271 WTP for 525000 m3/day 271
272 TWR treated water reservoir & treated water pumping station 272
273 excavation & back filling 273
274 Ground improvement 274 Ground improvement
275 excavation 275 excavation
276 Back filling 276 Back filling
277 CW 277
278 Deep foundations (piles) 278 Deep foundations (piles)
279 Bottom slab ‐ main part 279 Bottom slab ‐ main part
280 Bottom slab ‐ remaining parts 280 Bottom slab ‐ remaining parts
281 Walls & columns 281 Walls & columns
282 Cover slab 282 Cover slab
283 Finishes in side the tank 283 Finishes in side the tank
284 Water test 284 Water test
285 CR C‐01 ‐ Civil Works Construction Readiness (First Areas) CR C‐01 20/08
286 Installation equipment, Elect, piping etc. 286
287 Installation Equipment & pumping 287 Installation Equipment & pumping
288 Electricity 288 Electricity
289 Clarifiers / flocculation 289
290 CW 290
291 Super structure 291 Super structure
292 Finishes 292 Finishes
293 Water test 293 Water test
294 CR C‐02 ‐ Civil Works Construction Readiness CR C‐02 18/12
295 Installation equipment, Elect, piping etc. 295
296 Installation Equipment 296 Installation Equipment
297 Electricity 297 Electricity
298 Sand Filtration 298
299 CW 299
300 Super structure 300 Super structure
301 Water test 301 Water test
302 Finishes 302 Finishes
303 CR C‐03 ‐ Civil Works Construction Readiness (First Areas) CR C‐03 22/10
304 Installation equipment, Elect, piping etc. 304
305 Installation Equipment 305 Installation Equipment
306 Electricity 306 Electricity
307 Chlorine storage/dosing rooms 307
308 CW 308
Construction Pgm_48m‐CD20160501_rev4.mpp Page 5
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR
N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
309 Superstructure 309 Superstructure
310 First finishes 310 First finishes
311 CR C‐04 ‐ Civil Works Construction Readiness (First Areas) CR C‐04 19/10
312 Secondary finishes 312 Secondary finishes
313 Installation equipment, Elect, piping etc. 313
314 Installation Equipment 314 Installation Equipment
315 Electricity 315 Electricity
316 Electricity building 316
317 CW 317
318 Super structure 318 Super structure
319 secondary finishes 319 secondary finishes
320 CR C‐05 ‐ Civil Works Construction Readiness CR C‐05 07/11
321 Installation equipment, Elect, piping etc. 321
322 Installation electrical 322 Installation electrical
323 test 323 test
324 Workshop building 324
325 CW 325
326 Superstructure ‐ ground level 326 Superstructure ‐ ground level
327 superstructure ‐ first level 327 superstructure ‐ first level
328 CW finishes 328 CW finishes
329 structure closing (area free for finishes) 329 structure closing (area free for finishes)
330 secondary finishes 330 secondary finishes
331 CR C‐06 ‐ Civil Works Construction Readiness CR C‐06 07/03
332 Installation equipment, Elect, piping etc. 332
333 equipment/Electricity 333 equipment/Electricity
334 tests 334 tests
335 Administrative building
Construction Pgm_48m‐CD20160501_rev4.mpp Page 6
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR
N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
371 Finishes (Impermeable membranes, Pipe works, Draining layers…) 371 Finishes (Impermeable membranes, Pipe works, Draining layers…)
372 CR C‐10 ‐ Civil Works Construction Readiness CR C‐10 27/09
373 Installation equipment 373
374 Installation equipment 374 Installation equipment
375 Lagoon 375
376 CW 376
377 Earthworks (Embankment) 377 Earthworks (Embankment)
378 Cuting of the pre‐loaded Embankment 378 Cuting of the pre‐loaded Embankment
379 Miscellaneous Civil Works including Finishes 379 Miscellaneous Civil Works including Finishes
380 CR C‐11 ‐ Civil Works Construction Readiness CR C‐11 01/07
381 Installation Elect, piping etc. 381
382 Installation & Testing 382 Installation & Testing
383 Residential Buildings 383
384 CW 384
385 Embankment up to level +8.50 and Ground Improvement 385 Embankment up to level +8.50 and Ground Improvement
386 Special Foundations (if necesary) 386 Special Foundations (if necesary)
387 Superstructure ‐ ground level 387 Superstructure ‐ ground level
388 superstructure ‐ all levels 388 superstructure ‐ all levels
389 CW finishes 389 CW finishes
390 structure closing (area free for finishes) 390 structure closing (area free for finishes)
391 secondary finishes 391 secondary finishes
392 Guardhouse 392
393 CW 393
394 Embankment up to level +8.50 and Ground Improvement 394 Embankment up to level +8.50 and Ground Improvement
395 Superstructure ‐ ground level 395 Superstructure ‐ ground level
396 CW finishes 396 CW finishes
397 structure closing (area free for finishes) 397 structure closing (area free for finishes)
398 secondary finishes 398 secondary finishes
399 Electrical & miscellaneous 399 Electrical & miscellaneous
400 External WORKS 400
401 Boundary Wall Fencing 401 Boundary Wall Fencing
402 Buried Interconnection Pipes and Cables Sleeves 402 Buried Interconnection Pipes and Cables Sleeves
403 CR C‐12 ‐ Civil Works Construction Readiness CR C‐12 01/01
404 Road works, including storm drainage network & Outdoor Lighting 404 Road works, including storm drainage network & Outdoor Lighting
405 Landscaping and Ending of Anti‐erosion Protective System 405 Landscaping and Ending of Anti‐erosion Protective System
406 Construction Completion Certificate delivery Construction Completion Certificate delivery 16/08
407 PRE COMMISSIONING 407
408 Inspection 408
409 Inspection (Conformity Check) 409 Inspection (Conformity Check)
410 Mechanical Tests 410 Mechanical Tests
411 Electrical Tests 411 Electrical Tests
412 Energization ‐ Electrical Buildings 412 Energization ‐ Electrical Buildings
413 Inspection by Third Parties 413 Inspection by Third Parties
414 Dry Tests 414
415 Dry Tests ‐ Pumping Station 415 Dry Tests ‐ Pumping Station
416 Dry Tests ‐ Clarification 416 Dry Tests ‐ Clarification
417 Dry Tests / Media Loading ‐ Filtration 417 Dry Tests / Media Loading ‐ Filtration
418 Dry Tests ‐ Disinfection System 418 Dry Tests ‐ Disinfection System
419 Functional Tests 419
420 Functional Tests ‐ Pumping Station 420 Functional Tests ‐ Pumping Station
421 Functional Tests ‐ Clarification 421 Functional Tests ‐ Clarification
422 Functional Tests ‐ Filtration 422 Functional Tests ‐ Filtration
423 Functional Tests ‐ Disinfection System 423 Functional Tests ‐ Disinfection System
424 Cleaning & Disinfection System ‐ treated Water Reservoir 424 Cleaning & Disinfection System ‐ treated Wat
425 COMMISSIONING (Trial Operation) 425
426 Verification 426 Verification
427 Optimization and Proving 427 Optimization and Proving
428 Tests on Completion 428 Tests on Completion
429 Certificate of Completion ‐ Taking Over Certificate Certificate of Completion ‐ Taking Over Certificate 30/04
Construction Pgm_48m‐CD20160501_rev4.mpp Page 7