You are on page 1of 7

DHAKA 

ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016


SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR

N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
1 DAKHA  1
2 MILESTONES  2
3 GENERAL MILESTONES  3
4 Performance Security submission  4 28/03
5 Commencement date  5 01/05
6 Evidence of insurance Policy  6 13/05
7 beginning the Insurance policy  7 27/05
8 EMPLOYER'S RESPONSABILITIES  8
9 Letter of acceptance  9 01/03
10 Contract signed  10 14/03
11 Down payment or advance payment  11 28/03
12 Free and Uninterrupted Access To Intake Site, Pipeline Corridor (60%) and WTP Site  12 01/05
13 Free and Uninterrupted Access To Pipeline Corridor (100%)  13 30/06
14 Validation of the Selected Pipes Suppliers by the Employer 14 28/07
15 Environment Permit, EIA  15 25/04
16 Revised Seismic Design Report (delivery from Engineer) 16 29/07
17 BWDB & BITWA permits (Intake)  17 16/11
18 Available utilities  18
19 Electricity Available For Testing  19 09/09
20 Water Available for Testing  20 03/06
21 Gas Available for Testing  21 13/01
22 Fuel Available for Testing  22 13/01
23 PERMITS  23
24 Administrative Permit Delivery  24 Administrative Permit Delivery 
25 Excavation Permit Delivery 25 23/09
26 Construction Permit Delivery 26 Construction Permit Delivery
27 CIVIL WORKS SUBCONTRACTOR'S RESPONSIBILITIES  27
28 Subcontract signature 28 04/04
29 Advance Paiement Bond from CW Sub‐Contractor 29 28/03
30 Performance Bond from CW Sub‐Contractor 30 28/03
31 Evidence of insurance Policy  from CW Sub‐Contractor 31 13/05
32 DESIGN  32
33 BASIC DESIGN  33
34 Prepare Preliminary P&ID's  34 Prepare Preliminary P&ID's 
35 DATA AND CALCULATIONS  35 DATA AND CALCULATIONS 
36 DIAGRAMS & GRAPHS  36 DIAGRAMS & GRAPHS 
37 General Arrangement Drawings  37 General Arrangement Drawings 
38 Specification  38 Specification 
39 ELECTRICAL  39 ELECTRICAL 
40 HVAC  40 HVAC 
41 Architectural  41 Architectural 
42 Civil Guide drawing by JV & Approval in Principle by Employer  42
43 Intake off shore  43 Intake off shore 
44 Inlet Pumping Station 44 Inlet Pumping Station
45 22kms RWP route and typical 45 22kms RWP route and typical
46 TWR treated water reservoir & treated water pumping station  46 TWR treated water reservoir & treated water pumping station 
47 Other process zone  47 Other process zone 
48 Building  48 Building 
49 Preliminary Civil Calculation and Drawing by CW Design Engineering and Approval in  49
principle by Employer
50 Complementary detailed site investigation (topographic/geomechanical surveys,  50 Complementary detailed site investigation (topographic/geomechanical surveys, hydrology, occupation by existings, …), including Specific Permits Delivery by Authorities (if needed)
hydrology, occupation by existings, …), including Specific Permits Delivery by Authorities 
(if needed)
51 Ground improvement, Ground dewatering, ELS and Special foundation 51 Ground improvement, Ground dewatering, ELS and Special foundation
52 Intake preliminary design 52 Intake preliminary design
53 Pumping station  preliminary design 53 Pumping station  preliminary design
54 22kms RWP temporary works preliminary calculations 54 22kms RWP temporary works preliminary calculations
55 TWR treated water reservoir & treated water pumping station  preliminary design 55 TWR treated water reservoir & treated water pumping station  preliminary design
56 Other process zone  preliminary design 56 Other process zone  preliminary design
57 Buildings  preliminary design 57 Buildings  preliminary design
58 DETAIL DESIGN  58
59 DRAWINGS & PLANS  59 DRAWINGS & PLANS 
60 LISTS & SCHEDULES EAI  60 LISTS & SCHEDULES EAI 

Construction Pgm_48m‐CD20160501_rev4.mpp  Page 1
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR

N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
61 Detailed Design of 22kms RWP & Approval  61
62 Detail Design for First season 62 Detail Design for First season
63 Detail Design for 2nd and 3rd seasons 63 Detail Design for 2nd and 3rd seasons
64 DETAILED Guide Drawing & STUDIES  64
65 CIVIL GUIDE DRAWING & Approval  65
66 Intake  66 Intake 
67 Pumping station  67 Pumping station 
68 TWR treated water reservoir & treated water pumping station  68 TWR treated water reservoir & treated water pumping station 
69 Other process zone  69 Other process zone 
70 Building  70 Building 
71 CIVIL WORKS FINAL DESIGN (Shop Drawings) & Approval by Employer 71
72 Intake  72 Intake 
73 Pumping station  73 Pumping station 
74 TWR treated water reservoir & treated water pumping station  74 TWR treated water reservoir & treated water pumping station 
75 Other process zones 75 Other process zones
76 Building  76 Building 
77 Control philosophy  77 Control philosophy 
78 GENERAL PROCUREMENT (E/M equipment, pipe, HVAC, Elect...)  78
79 Intake & Pumping  79
80 Screens & pumps  80
81 Issuance Specifications  81 Issuance Specifications 
82 procurement process  82 procurement process 
83 Purchase Order  83 Purchase Order 
84 Manufacturing  84 Manufacturing 
85 Transport  85 Transport 
86 Custom Clearance  86 Custom Clearance 
87 Transport to site and unload  87 Transport to site and unload 
88 Pipeline 22kms  88
89 Issuance of Specifications  89 Issuance of Specifications 
90 procurement process  90 procurement process 
91 Purchase Orders  91
92 1st Purchase Order 92 1st Purchase Order
93 Last Purchase Orders 93 Last Purchase Orders
94 Manufacturing  94
95 Manufacturing 1st season 95 Manufacturing 1st season
96 Manufacturing 2nd season 96 Manufacturing 2nd season
97 Manufacturing 3rd season 97 Manufacturing 3rd season
98 Transport & Custom Clearance  98
99 1st season ‐ Transport  99 1st season ‐ Transport 
100 1st season ‐ Custom Clearance  100 1st season ‐ Custom Clearance 
101 2nd season ‐ Transport  101 2nd season ‐ Transport 
102 2nd season ‐ Custom Clearance  102 2nd season ‐ Custom Clearance 
103 3rd season ‐ Transport  103 3rd season ‐ Transport 
104 3rd season ‐ Custom Clearance  104 3rd season ‐ Custom Clearance 
105 WTP for 525000 m3/day  105
106 Clarification / flocculation  106
107 Lamellas & scrapers  107
108 Issuance Specifications (Update)  108 Issuance Specifications (Update) 
109 procurement process  109 procurement process 
110 Purchase Order  110 Purchase Order 
111 Manufacturing  111 Manufacturing 
112 FAT  112 FAT 
113 Transport  113 Transport 
114 Custom Clearance  114 Custom Clearance 
115 Transport to site and unload  115 Transport to site and unload 
116 Filtration  116
117 Blower, media and air compressor  117
118 Issuance Specifications (Update)  118 Issuance Specifications (Update) 
119 procurement process  119 procurement process 
120 Purchase Order  120 Purchase Order 
121 Manufacturing  121 Manufacturing 
122 Transport  122 Transport 

Construction Pgm_48m‐CD20160501_rev4.mpp  Page 2
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR

N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
123 Custom Clearance  123 Custom Clearance 
124 Transport to site and unload  124 Transport to site and unload 
125 chlorine storage & dosing  125
126 Issuance Specifications (Update)  126 Issuance Specifications (Update) 
127 procurement process  127 procurement process 
128 Purchase Order  128 Purchase Order 
129 Manufacturing  129 Manufacturing 
130 Transport  130 Transport 
131 Custom Clearance  131 Custom Clearance 
132 Transport to site and unload  132 Transport to site and unload 
133 Electrical Room & generator  133
134 Issuance Specifications (Update)  134 Issuance Specifications (Update) 
135 procurement process  135 procurement process 
136 Purchase Order  136 Purchase Order 
137 Manufacturing  137 Manufacturing 
138 Transport  138 Transport 
139 Custom Clearance  139 Custom Clearance 
140 Transport to site and unload  140 Transport to site and unload 
141 Process Control (SCADA)  141
142 Technical bid package ready  142 17/02
143 procurement process  143 procurement process 
144 Studies,  144 Studies, 
145 order  145 order 
146 Manufacturing elect panels & panel control  146 Manufacturing elect panels & panel control 
147 FAT  147 FAT 
148 functional Analysis  148 functional Analysis 
149 Programming,  149 Programming, 
150 Custom Clearance  150 Custom Clearance 
151 Transport to site and unload  151 Transport to site and unload 
152 Penstock & handing, Skips, Pumps & valves  152
153 Issuance Specifications (Update)  153 Issuance Specifications (Update) 
154 procurement process  154 procurement process 
155 Purchase Order  155 Purchase Order 
156 Manufacturing  156 Manufacturing 
157 Transport  157 Transport 
158 Custom Clearance  158 Custom Clearance 
159 Transport to site and unload  159 Transport to site and unload 
160 EXECUTION  160
161 SITE WORKS  161
162 Start Works WTP  162 28/09
163 Mobilization / Installation  163 Mobilization / Installation 
164 General Levelling & Temporary Access 164 General Levelling & Temporary Access
165 Employer's, Engineer's & Contractor' s Site Offices  165 Employer's, Engineer's & Contractor' s Site Offices 
166 Laborers Accommodation  166 Laborers Accommodation 
167 Temporary Access Refreshment for JV needs 167 Temporary Access Refreshment for JV needs
168 CONSTRUCTION PHASE  168
169 INTAKE 169
170 Intake off shore  170
171 CW  171
172 Construction of Cofferdam, Excavation 172 Construction of Cofferdam, Excavation
173 Piling 173 Piling
174 Under dewatering : concrete plug & base slab  174 Under dewatering : concrete plug & base slab 
175 Structure  175 Structure 
176 Watertightness Tests 176 Watertightness Tests
177 CW finishing 177 CW finishing
178 CR A‐01 ‐ Civil Works Construction Readiness CR A‐01 17/01
179 Installation equipment, Elect, piping etc.  179
180 big E/M equipment placing  180 big E/M equipment placing 
181 E/M equipment and piping installation  181 E/M equipment and piping installation 
182 Electricity / Automation  182 Electricity / Automation 
183 E/M tests  183 E/M tests 
184 Pumping station and ancillary building ‐on Shore  184

Construction Pgm_48m‐CD20160501_rev4.mpp  Page 3
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR

N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
185 CW  185
186 Overall Platform Embankment 186 Overall Platform Embankment
187 Ground improvement 187 Ground improvement
188 Excavation 188 Excavation
189 Piling, foundations  189 Piling, foundations 
190 infrastructures  190 infrastructures 
191 Watertightness Tests 191 Watertightness Tests
192 Superstructures  192 Superstructures 
193 End of CW finishes and big E/M equipment placing  193 End of CW finishes and big E/M equipment placing 
194 CR A‐02 ‐ Civil Works Construction Readiness CR A‐02 31/07
195 Installation equipment, Elect, piping etc.  195
196 E/M equipment and piping installation  196 E/M equipment and piping installation 
197 Electricity / Automation  197 Electricity / Automation 
198 E/M tests  198 E/M tests 
199 Off shore pipe laying  199
200 CW  200
201 Temporary access bund, sheet piling  201 Temporary access bund, sheet piling 
202 Ground improvement 202 Ground improvement
203 Piling, foundations for metal footbridge 203 Piling, foundations for metal footbridge
204 Footbridge installation, removal of Access bund 204 Footbridge installation, removal of Access bund
205 CR A‐03 ‐ Civil Works Construction Readiness CR A‐03 26/04
206 Excavation  206 Excavation 
207 Laying of pipelines 207 Laying of pipelines
208 Pipelines connection on up/down‐stream structures and watertproof testing 208 Pipelines connection on up/down‐stream structures and watertproof testing
209 Backfilling and finishing of anti‐erosion protecting system 209 Backfilling and finishing of anti‐erosion protecting system
210 External WORKS  210
211 Boundary Wall Fencing 211 Boundary Wall Fencing
212 Buried Interconnection Pipes and Cables Sleeves 212 Buried Interconnection Pipes and Cables Sleeves
213 CR A‐04 ‐ Civil Works Construction Readiness CR A‐04 21/11
214 Road works, including storm drainage network & Outdoor Lighting  214 Road works, including storm drainage network & Outdoor Lighting 
215 Landscaping and Ending of Anti‐erosion Protective System 215 Landscaping and Ending of Anti‐erosion Protective System
216 22kms RWP pipeline  216
217 1st season  217
218 Picketing and mark‐up, Layout of the track  218 Picketing and mark‐up, Layout of the track 
219 Temporary Access Road (included stripping of topsoil)  219
220 Front of attack n°1 ; 3670 m (60 m/day)  220 Front of attack n°1 ; 3670 m (60 m/day) 
221 Front of attack n°2 ; 3670 m (60 m/day)  221 Front of attack n°2 ; 3670 m (60 m/day) 
222 Opening of trenches, pipe laying and backfilling, accessories (32 m/day/team) :  222
223 JVP B‐01 ‐ Pipes and Accessories Delivery from JV at Chittagong: 1st package JVP B‐01 22/12
224 Transport to site and unload  224 Transport to site and unload 
225 Front of attack n°1 ; 2480 m/74500 m (32 m /day)  225 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 
226 Front of attack n°2 ; 2480 m/74500 m (32 m /day)  226 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 
227 Front of attack n°3 ; 2480 m/74500 m (32 m /day)  227 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 
228 Final Access Track (32 m/day/team), including embankment and slope protection 228
229 Front of attack n°1 ; 2480 m/74500 m (32 m /day)  229 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 
230 Front of attack n°2 ; 2480 m/74500 m (32 m /day)  230 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 
231 Front of attack n°3 ; 2480 m/74500 m (32 m /day)  231 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 
232 Inspection and testing  232
233 Fronts n°1,2 & 3  233 Fronts n°1,2 & 3 
234 CR B‐01 ‐ Civil Works Construction Readiness CR B‐01 04/05
235 2nd season  235
236 Picketing and mark‐up, Layout of the track  236 Picketing and mark‐up, Layout of the track 
237 Temporary Access Road (included stripping of topsoil)  237
238 Front of attack n°1 ; 3670 m (60 m/day)  238 Front of attack n°1 ; 3670 m (60 m/day) 
239 Front of attack n°2 ; 3670 m (60 m/day)  239 Front of attack n°2 ; 3670 m (60 m/day) 
240 Opening of trenches, pipe laying and backfilling, accessories (32 m/day/team) :  240
241 JVP B‐02 ‐ Pipes and Accessories Delivery from JV at Chittagong: 1st package JVP B‐02 03/08
242 Transport to site and unload, including intermediate storage (if any) 242 Transport to site and unload, including intermediate storage (if any)
243 Front of attack n°1 ; 2480 m/74500 m (32 m /day)  243 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 
244 Front of attack n°2 ; 2480 m/74500 m (32 m /day)  244 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 
245 Front of attack n°3 ; 2480 m/74500 m (32 m /day)  245 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 
246 Final Access Track (32 m/day/team), including embankment and slope protection 246

Construction Pgm_48m‐CD20160501_rev4.mpp  Page 4
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR

N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
247 Front of attack n°1 ; 2480 m/74500 m (32 m /day)  247 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 
248 Front of attack n°2 ; 2480 m/74500 m (32 m /day)  248 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 
249 Front of attack n°3 ; 2480 m/74500 m (32 m /day)  249 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 
250 Inspection and testing  250
251 Fronts n°1,2 & 3  251 Fronts n°1,2 & 3 
252 CR B‐02 ‐ Civil Works Construction Readiness CR B‐02 20/04
253 3rd season  253
254 Picketing and mark‐up, Layout of the track  254 Picketing and mark‐up, Layout of the track 
255 Temporary Access Road (included stripping of topsoil)  255
256 Front of attack n°1 ; 3670 m (60 m/day)  256 Front of attack n°1 ; 3670 m (60 m/day) 
257 Front of attack n°2 ; 3670 m (60 m/day)  257 Front of attack n°2 ; 3670 m (60 m/day) 
258 Opening of trenches, pipe laying and backfilling, accessories (32 m/day/team) :  258
259 JVP B‐03 ‐ Pipes and Accessories Delivery from JV at Chittagong: 1st package JVP B‐03 02/08
260 Transport to site and unload, including intermediate storage (if any) 260 Transport to site and unload, including intermediate storage (if any)
261 Front of attack n°1 ; 2480 m/74500 m (32 m /day)  261 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 
262 Front of attack n°2 ; 2480 m/74500 m (32 m /day)  262 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 
263 Front of attack n°3 ; 2480 m/74500 m (32 m /day)  263 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 
264 Final Access Track (32 m/day/team), including embankment and slope protection 264
265 Front of attack n°1 ; 2480 m/74500 m (32 m /day)  265 Front of attack n°1 ; 2480 m/74500 m (32 m /day) 
266 Front of attack n°2 ; 2480 m/74500 m (32 m /day)  266 Front of attack n°2 ; 2480 m/74500 m (32 m /day) 
267 Front of attack n°3 ; 2480 m/74500 m (32 m /day)  267 Front of attack n°3 ; 2480 m/74500 m (32 m /day) 
268 Inspection and testing  268
269 Fronts n°1,2 & 3  269 Fronts n°1,2 & 3 
270 CR B‐03 ‐ Civil Works Construction Readiness CR B‐03 19/04
271 WTP for 525000 m3/day  271
272 TWR treated water reservoir & treated water pumping station  272
273 excavation & back filling  273
274 Ground improvement 274 Ground improvement
275 excavation  275 excavation 
276 Back filling  276 Back filling 
277 CW  277
278 Deep foundations (piles)  278 Deep foundations (piles) 
279 Bottom slab ‐ main part  279 Bottom slab ‐ main part 
280 Bottom slab ‐ remaining parts  280 Bottom slab ‐ remaining parts 
281 Walls & columns  281 Walls & columns 
282 Cover slab  282 Cover slab 
283 Finishes in side the tank  283 Finishes in side the tank 
284 Water test  284 Water test 
285 CR C‐01 ‐ Civil Works Construction Readiness (First Areas) CR C‐01 20/08
286 Installation equipment, Elect, piping etc.  286
287 Installation Equipment & pumping  287 Installation Equipment & pumping 
288 Electricity  288 Electricity 
289 Clarifiers / flocculation  289
290 CW  290
291 Super structure  291 Super structure 
292 Finishes  292 Finishes 
293 Water test  293 Water test 
294 CR C‐02 ‐ Civil Works Construction Readiness CR C‐02 18/12
295 Installation equipment, Elect, piping etc.  295
296 Installation Equipment  296 Installation Equipment 
297 Electricity  297 Electricity 
298 Sand Filtration  298
299 CW  299
300 Super structure  300 Super structure 
301 Water test  301 Water test 
302 Finishes  302 Finishes 
303 CR C‐03 ‐ Civil Works Construction Readiness (First Areas) CR C‐03 22/10
304 Installation equipment, Elect, piping etc.  304
305 Installation Equipment  305 Installation Equipment 
306 Electricity  306 Electricity 
307 Chlorine storage/dosing rooms  307
308 CW  308

Construction Pgm_48m‐CD20160501_rev4.mpp  Page 5
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR

N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
309 Superstructure  309 Superstructure 
310 First finishes  310 First finishes 
311 CR C‐04 ‐ Civil Works Construction Readiness (First Areas) CR C‐04 19/10
312 Secondary finishes  312 Secondary finishes 
313 Installation equipment, Elect, piping etc.  313
314 Installation Equipment  314 Installation Equipment 
315 Electricity  315 Electricity 
316 Electricity building  316
317 CW  317
318 Super structure  318 Super structure 
319 secondary finishes  319 secondary finishes 
320 CR C‐05 ‐ Civil Works Construction Readiness CR C‐05 07/11
321 Installation equipment, Elect, piping etc.  321
322 Installation electrical  322 Installation electrical 
323 test  323 test 
324 Workshop building  324
325 CW  325
326 Superstructure ‐ ground level  326 Superstructure ‐ ground level 
327 superstructure ‐ first level  327 superstructure ‐ first level 
328 CW finishes  328 CW finishes 
329 structure closing (area free for finishes)  329 structure closing (area free for finishes) 
330 secondary finishes  330 secondary finishes 
331 CR C‐06 ‐ Civil Works Construction Readiness CR C‐06 07/03
332 Installation equipment, Elect, piping etc.  332
333 equipment/Electricity  333 equipment/Electricity 
334 tests  334 tests 
335 Administrative building 

336 CW  336


337 Superstructure ‐ ground level  337 Superstructure ‐ ground level 
338 superstructure ‐ first floor  338 superstructure ‐ first floor 
339 superstructure ‐ second floor  339 superstructure ‐ second floor 
340 CW finishes  340 CW finishes 
341 structure closing (area free for finishes)  341 structure closing (area free for finishes) 
342 secondary finishes  342 secondary finishes 
343 CR C‐07 ‐ Civil Works Construction Readiness (First Areas) CR C‐07 05/04
344 Installation of SCADA & Laboratory equipment  344
345 Laboratory equipment  345 Laboratory equipment 
346 Scada installation & preliminary testing  346 Scada installation & preliminary testing 
347 Scada tests completion 347 16/08
348 Chemical Buildings and GenSet facilities 348
349 CW  349
350 earthworks + ground improvement + special foundations 350 earthworks + ground improvement + special foundations
351 Superstructure  351 Superstructure 
352 first finishes  352 first finishes 
353 CR C‐08 ‐ Civil Works Construction Readiness (First Areas) CR C‐08 30/07
354 secondary finishes  354 secondary finishes 
355 Installation equipment, Elect, piping etc.  355
356 Installation Equipment  356 Installation Equipment 
357 Electricity  357 Electricity 
358 Power Generators building  358
359 CW  359
360 Earthworks + Ground Improvement + Special Foundations 360 Earthworks + Ground Improvement + Special Foundations
361 Superstructure  361 Superstructure 
362 Finishes  362 Finishes 
363 CR C‐09 ‐ Civil Works Construction Readiness CR C‐09 13/10
364 Install Generators & piping  364
365 Install Generators & piping  365 Install Generators & piping 
366 Electricity Test  366 Electricity Test 
367 Sludge Drying Beds  367
368 CW  368
369 Earthworks + Ground Improvement 369 Earthworks + Ground Improvement
370 Super structure  370 Super structure 

Construction Pgm_48m‐CD20160501_rev4.mpp  Page 6
DHAKA ENVIRONMENTALLY SUSTAINABLE WATER PROVISIONNAL PROGRAMME OF WORKS REV IV ‐ 13/01/2016
SUPPLY PROJECT ‐ NEW WTP AT GANDHARBPUR

N° Name
2016 2017 2018 2019 2020
‐6 ‐5 ‐4 ‐3 ‐2 ‐1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 5
371 Finishes (Impermeable membranes, Pipe works, Draining layers…) 371 Finishes (Impermeable membranes, Pipe works, Draining layers…)
372 CR C‐10 ‐ Civil Works Construction Readiness CR C‐10 27/09
373 Installation equipment  373
374 Installation equipment  374 Installation equipment 
375 Lagoon  375
376 CW  376
377 Earthworks (Embankment) 377 Earthworks (Embankment)
378 Cuting of the pre‐loaded Embankment 378 Cuting of the pre‐loaded Embankment
379 Miscellaneous Civil Works including Finishes 379 Miscellaneous Civil Works including Finishes
380 CR C‐11 ‐ Civil Works Construction Readiness CR C‐11 01/07
381 Installation Elect, piping etc.  381
382 Installation & Testing 382 Installation & Testing
383 Residential Buildings 383
384 CW  384
385 Embankment up to level +8.50 and Ground Improvement 385 Embankment up to level +8.50 and Ground Improvement
386 Special Foundations (if necesary) 386 Special Foundations (if necesary)
387 Superstructure ‐ ground level  387 Superstructure ‐ ground level 
388 superstructure ‐ all levels  388 superstructure ‐ all levels 
389 CW finishes  389 CW finishes 
390 structure closing (area free for finishes)  390 structure closing (area free for finishes) 
391 secondary finishes  391 secondary finishes 
392 Guardhouse  392
393 CW  393
394 Embankment up to level +8.50 and Ground Improvement 394 Embankment up to level +8.50 and Ground Improvement
395 Superstructure ‐ ground level  395 Superstructure ‐ ground level 
396 CW finishes  396 CW finishes 
397 structure closing (area free for finishes)  397 structure closing (area free for finishes) 
398 secondary finishes  398 secondary finishes 
399 Electrical & miscellaneous  399 Electrical & miscellaneous 
400 External WORKS  400
401 Boundary Wall Fencing 401 Boundary Wall Fencing
402 Buried Interconnection Pipes and Cables Sleeves 402 Buried Interconnection Pipes and Cables Sleeves
403 CR C‐12 ‐ Civil Works Construction Readiness CR C‐12 01/01
404 Road works, including storm drainage network & Outdoor Lighting  404 Road works, including storm drainage network & Outdoor Lighting 
405 Landscaping and Ending of Anti‐erosion Protective System 405 Landscaping and Ending of Anti‐erosion Protective System
406 Construction Completion Certificate delivery  Construction Completion Certificate delivery  16/08
407 PRE COMMISSIONING  407
408 Inspection  408
409 Inspection (Conformity Check)  409 Inspection (Conformity Check) 
410 Mechanical Tests  410 Mechanical Tests 
411 Electrical Tests  411 Electrical Tests 
412 Energization ‐ Electrical Buildings  412 Energization ‐ Electrical Buildings 
413 Inspection by Third Parties  413 Inspection by Third Parties 
414 Dry Tests  414
415 Dry Tests ‐ Pumping Station  415 Dry Tests ‐ Pumping Station 
416 Dry Tests ‐ Clarification  416 Dry Tests ‐ Clarification 
417 Dry Tests / Media Loading ‐ Filtration  417 Dry Tests / Media Loading ‐ Filtration 
418 Dry Tests ‐ Disinfection System  418 Dry Tests ‐ Disinfection System 
419 Functional Tests  419
420 Functional Tests ‐ Pumping Station  420 Functional Tests ‐ Pumping Station 
421 Functional Tests ‐ Clarification  421 Functional Tests ‐ Clarification 
422 Functional Tests ‐ Filtration  422 Functional Tests ‐ Filtration 
423 Functional Tests ‐ Disinfection System  423 Functional Tests ‐ Disinfection System 
424 Cleaning & Disinfection System ‐ treated Water Reservoir  424 Cleaning & Disinfection System ‐ treated Wat
425 COMMISSIONING (Trial Operation)  425
426 Verification  426 Verification 
427 Optimization and Proving  427 Optimization and Proving 
428 Tests on Completion  428 Tests on Completion 
429 Certificate of Completion ‐ Taking Over Certificate  Certificate of Completion ‐ Taking Over Certificate  30/04

Construction Pgm_48m‐CD20160501_rev4.mpp  Page 7

You might also like