You are on page 1of 13

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/313594426

Using post-occupancy evaluation of housing projects to generate value for


municipal governments

Article  in  AEJ - Alexandria Engineering Journal · June 2018


DOI: 10.1016/j.aej.2017.01.015

CITATIONS READS

13 420

5 authors, including:

Xavier Brioso Antonio Humero


Pontifical Catholic University of Peru Universidad Politécnica de Madrid
36 PUBLICATIONS   127 CITATIONS    10 PUBLICATIONS   28 CITATIONS   

SEE PROFILE SEE PROFILE

Danny Murguía Jaclyn Corrales


Loughborough University Pontifical Catholic University of Peru
9 PUBLICATIONS   45 CITATIONS    1 PUBLICATION   13 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

A systemic BIM diffusion model View project

Information Resilience in a Digital Built Environment View project

All content following this page was uploaded by Xavier Brioso on 05 November 2018.

The user has requested enhancement of the downloaded file.


Alexandria Engineering Journal (2018) 57, 885–896

H O S T E D BY
Alexandria University

Alexandria Engineering Journal


www.elsevier.com/locate/aej
www.sciencedirect.com

ORIGINAL ARTICLE

Using post-occupancy evaluation of housing


projects to generate value for municipal
governments
Xavier Brioso a,*, Antonio Humero b, Danny Murguia a, Jaclyn Corrales a,
Johana Aranda a

a
Construction Management & Technology Research Group (GETEC), Pontifical Catholic University of Peru, Av. Universitaria
1801, Lima 32, Peru
b
School of Architecture, Technical University of Madrid, Av. Juan de Herrera, 4, 28040 Madrid, Spain

Received 15 July 2015; revised 23 December 2016; accepted 16 January 2017


Available online 10 February 2017

KEYWORDS Abstract This article presents a value-generation framework for municipalities through the adap-
Lean construction; tation of the Lean Project Delivery System (LPDS) to the municipal management process. Said pro-
Lean project delivery system; cess includes the use of learning loops from previous projects to revamp municipal management
Value generation; during design revision, construction supervision and commissioning, and taking into account the
Municipality value; final user’s needs and values. This framework allows the municipal management to investigate
Post-occupation informa- the user’s value requirements and proposes the Number of Claims per Housing Unit (NCHU) as
tion; a performance indicator. A case study describing this method is presented. We analyze the post-
Learning loop occupation information recorded by the Peruvian National Bureau of Consumer Protection
(INDECOPI from its acronym in Spanish), classifying the claims according to their root cause. This
approach allows us to separate claims originating in the design phase from those originating in the
production phase. This paper proposes learning loops for improved project review in the licensing
system, with the aim of increasing the value in design, improving site inspection and control, and
optimizing the issue of ordinances. This article also includes a critique of current standards and reg-
ulations, since in some cases they do not allow municipalities to fulfill the value-in-design require-
ments.
Ó 2017 Faculty of Engineering, Alexandria University. Production and hosting by Elsevier B.V. This is an
open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).

1. Introduction

* Corresponding author. Kotler [1,2] defined marketing as a mix of art and science,
E-mail addresses: xbrioso@pucp.edu.pe (X. Brioso), a.humero@upm. devoted to creating, communicating, and delivering value.
es (A. Humero), dmurguia@pucp.pe (D. Murguia), j.corrales@pucp. Marketing aims to generate long-term relationships with cli-
pe (J. Corrales), j.aranda@pucp.pe (J. Aranda).
ents, while being as cost-effective for the company as possible.
Peer review under responsibility of Faculty of Engineering, Alexandria
Hence, value is the most important concept for the company,
University.
http://dx.doi.org/10.1016/j.aej.2017.01.015
1110-0168 Ó 2017 Faculty of Engineering, Alexandria University. Production and hosting by Elsevier B.V.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
886 X. Brioso et al.

Nomenclature

BIM Building Information Modeling DTI Department of Trade and Industry


CAPECO Peruvian Construction Chamber INDECOPI Peruvian National Bureau of Consumer Pro-
CDT Chile’s Technological Development Corporation tection
CD-D Claim of Design - Definition LPDS Lean Project Delivery System
CD-DD Claim of Design - Definitive Design NCHU Number of claims per housing unit
CD-U Claim of Delivery - Use PRINCE2 Managing Successful Projects with PRINCE2
CII Construction Industry Institute (Manual)
CP-A Claim of Production - Assembly TFV Transformation-Flow-Value
CP-S Claim of Production - Supply VDC Virtual Design Construction
Eq. Equation VFE Value for Engineers
DETR Department of Environment, Transport and VFM Value for Municipalities
Regions

and by extension, for all of those participating in the business bors. Later, a case study is presented that includes the determi-
activity. According to Kotler [2], ‘‘In terms of marketing, the nation of root causes and the definition of corrective actions in
product or offering will be successful if it delivers value and the municipal-management system, with emphasis on the root
satisfaction to the target buyer. The buyer chooses between causes linked to value in design.
different offerings on the basis of which is perceived to deliver
the most value. This value is defined as a ratio between what 2. Generating value for municipalities
the customer gets and what he gives. The customer gets bene-
fits and assumes costs, as shown in this equation.” Eq. (1) is
2.1. Lean Project Delivery System (LPDS)
shown below.
Benefits
VALUE ¼ LPDS is an organized implementation of the Lean Principles
Costs
and Tools, combined to allow a team to operate in unison
Functional benefits þ emotional benefits
¼ [3]. LPDS was developed as a philosophy, a set of interdepen-
Monetary costs þ time costs þ energy costs þ psychic costs
dent functions; it includes rules for decision making, proce-
ð1Þ dures for execution of functions, and implementation aids
Abstract and subjective formulas such as the one above are and tools, including software when appropriate. The domain
numerous; they all represent value, and are linked to quality. A for LPDS is defined by the intersection of projects and produc-
lot has been said about quality, with investors, designers, or tion systems [5].
constructors defined as the main stakeholders. Lean Construc- LPDS uses an approach to project delivery that works to
tion Institute [3] defines value as ‘‘what the customer wants analyze the interaction of design and construction in order
from the process.” On the other hand, according to PRINCE2 to remove waste and create value in each component [6]. LPDS
[4], ‘‘The challenge that faces all organizations, whether they consists of 13 modules, nine organized in four interconnecting
be public or private sector, large or small, is to deliver change triads or phases extending from project definition to design to
through managing projects successfully and consistently. It supply and assembly, plus two production-control modules
proposes that the project-management method adds real value, and the work-structuring module, both conceived to extend
as the globally recognized standard for delivering successful through all project phases. The post-occupancy-evaluation
projects.” (learning-loops) module links the end of one project to the
Frequently, we refer to value exclusively in terms of the beginning of the next [7] (see Fig. 1).
user, the final stakeholder in the supply chain in construction. LPDS allows sequences and the adaptation of processes to
However, we often forget the entity responsible for authorizing be carried out in a flexible way. For example, in the Project-
the building license, and for inspecting its correct construction: Definition Phase, the movement through three modules is nec-
the municipality. This stakeholder has the duty of ensuring essarily iterative, and does not need to follow any specific
that the standards, codes, and regulations are complied with sequence, although the project’s needs and values seem to be
to protect the final user, namely society. In other terms, if the logical starting point. What’s important is to bring all three
we forget the municipality, we also forget that one of the key into alignment. Only then should the Lean Design phase be
values for clients lies in the building’s proper operation and launched. But even then, it is possible that subsequent develop-
maintenance. This paradox suggests that the needs and values ment might lead back to project definition and an upgrading of
of the users should be aligned with the needs and values of the purposes (stakeholder needs and values), criteria, or concepts
municipality. [8].
This paper proposes a municipal-management system based LPDS uses a new strategy applied to the Operating System
on Lean Project Delivery System (LPDS). Its main objective that in turn calls for, but does not require, a different set of
was to introduce a value-generation methodology for munici- organizational communication and authority protocols and
palities, through the adaptation of tools and techniques based new forms of contract [9]. ‘‘To implement LPDS successfully,
on LPDS and the analysis of post-occupation claims of neigh- collaboration, early involvement, aligned incentives, and inte-
Using post-occupancy evaluation of housing projects 887

Figure 1 Lean project delivery system [6].

gration of the project stakeholders are required” [10]. The free- other words, the cost is also partly funded by contributors’
dom to choose tools and techniques and the flexibility to spec- taxes or fees and/or central government contributions.
ify the processes’ inputs and outputs help overcome the typical The cost of time and energy invested by the municipality
psychological barriers of specialists with deep-rooted prefer- must be minimized through a proper management system for
ences for a certain management system. [11]. license approval, inspection, and standard compliance. This sys-
In the words of Diekmann [12], ‘‘Lean cannot be reduced to tem must guarantee the maximum benefit for both the munici-
a set of rules or tools. It must be approached as a system of pality and the neighbors—that is to say, it must generate value
thinking and behavior that is shared throughout the value in design. Therefore, if there are defects detected by the user in
stream.. . .If successfully applied, however, Lean has the poten- the post-occupation phase, and their claims are not adequately
tial to improve the cost structure, value attitudes, and delivery addressed by the seller and/or builder, the post-occupation
times of the construction industry.” user-municipality relationship would suffer, and the benefit por-
tion in the proposed value formula would decrease. Additional
2.2. Municipality value problems could arise from the administrative, civil, or penal
damages that could be charged to the municipality due to user
To provide an answer to the main aim of this study, an adap- claims, alleging an inadequate management of the license-
tation of Kotler’s mathematical expression (Eq. (2)) was approval or project-inspection processes. This would also affect
selected and applied: the municipality as a brand, reducing its benefit, and therefore
the final value in the formula.

Benefitðapproval of a quality product þ user-municipality relationship during the use of the product
þ municipality’s brandÞ
VFM ¼
Costðtime and energy invested in approving the project þ time and energy invested in monitoring the construction
þ time and energy invested in obtaining the compliance certificateÞ
ð2Þ

where VFM means ‘‘value for municipalities.” Since the aforementioned mathematical expression is sub-
The cost is partly covered by the fees that builders must pay jective, in order to correctly calculate it, we need an indicator.
for their projects to be approved and later inspected by the In 2013, King Saud University did an exhaustive review of the
municipality throughout the process. Likewise, the municipal- most common indicators worldwide [13]. The Construction
ity allocates part of its budget to cover the remaining costs. In Industry Institute (CII), the Department of Environment,
888 X. Brioso et al.

Transport and Regions (DETR), the Department of Trade and of use. The formula connects the claims in a one-year term
Industry (DTI), and Chile’s Technological Development Cor- with the housing projects approved two years before that.
poration (CDT from its acronym in Spanish) were studied, However, this formula must be adapted to the specifics of each
along with other leading institutions, and it was determined type of project and to the characteristics of each country.
that the number of complaints is a key indicator for measuring
customer satisfaction in the post-occupancy phase of a build- 2.3. Municipal value management system based on Lean Project
ing [13]. Delivery System (LPDS)
According to this, for the building projects, we have the fol-
lowing expression (Eq. (3)): This approach uses the number of post-occupation claims per
Number of claimsðpost occupancyÞ housing unit as an indicator. After analyzing and defining the
NCHU ¼ ð3Þ root causes of those claims for the building projects approved
Number of housing units already finished
and constructed within a certain time frame, it will be possible
Bølviken et al. [14] call for a two-dimensional view of value to take corrective actions to improve the management system.
and waste from a TFV (transformation-flow-value) perspec- As a consequence of those corrective actions, the indicator
tive. Value is a desired output, and waste is the use of more would be expected to decrease in the next time frame.
materials than needed or an unwanted output. As such, it is
possible to correlate the value formula (2) with the perfor- 2.3.1. Value during the project definition
mance indicator NCHU (3). The greater the number of claims,
In the LPDS, the first triad is the Project Definition. At this
the greater the waste. The lower the number of claims, the
stage, projects are developed out of a conversation between
lower the waste—and the greater the value. For this reason,
needs and values, constraints and design criteria [6]. It is impor-
we propose that the value improvement for the municipality’s
tant to make sure that the project fulfills all the users’ needs and
management is a reduction in NCHU (fewer claims, fewer
values, which in turn must be guaranteed by standards and reg-
resources, less waste).
ulations. Needs and values must be met in accordance with
Consequently, it is essential for municipalities to compile
property-value and client-satisfaction criteria. Orihuela and Ori-
the claims filed by the users within a certain time frame and
huela [15] have proposed a list of quality requirements, which
connect them to projects that were approved and carried out
are actually value requirements, grouped into three criteria: (1)
during a previous term. By doing so, we obtain the following
quality for the city; (2) quality for the neighborhood; and (3)
indicator (Eq. (4)):
quality for the building itself. By the time the construction
Number of claimsðTtime þ KÞ license is requested, the analysis of the city-level requirements
NCHU ¼
Number of housing units already finishedðTtimeÞ is already finished. We propose a simple methodology or check-
ð4Þ list to allow the municipality to perform a quick verification of
the remaining requirements, using Table 1.
NCHU: Number of claims per housing unit We can score each of the second-level factors above on the
Ttime: Time considered for the case study, one year Likert Scale (1–5) according to the performance on rules and
K: Time elapsed between the housing project’s finish, and regulation compliance and the level of detail of each require-
the start of occupancy and claims filed the following year ment on both drawings and specifications. Based on the results
obtained, the municipality may request more design specifica-
This formula takes into account that housing projects are tions for the investors from two points of view: according to
usually executed in an average time frame of 18 months, and the required level stated by the relevant legislation [16], and
that claims generally start to appear during the first 6 months according to the level developed in the project. This could min-

Table 1 Matrix of municipality evaluation of housing-value requirements (adapted from [15]).


Housing-quality requirements Performance on rules Performance on level of
and regulations compliance detail of said requirement
First level Second level Score (1–5) Score (1–5)
Regarding the neighborhood Security from natural events
Urban conditions
Regarding the building itself Structural safety
Fire safety
Salubrity
Functionality
Aesthetics
Safety in use
Property security
Legal security
Thermal, acoustic, luminance comfort
Durability
Impermeability
Environmental impact
After-sale guidance
Using post-occupancy evaluation of housing projects 889

imize post-occupation claims with root causes in project- process is very similar to those in Peru, Chile, Spain [17–19],
review failures, and therefore generate more value in the and other countries.
design. The claims filed by users can follow three routes: (1) The
claim can be filed against the property developer and/or con-
2.3.2. Value in lean design, supply, and assembly tractor. (2) If the user is not satisfied with the resolution, he
In LPDS, the municipal-management system begins with the or she can file a further claim with a consumer-protection
review and approval of the preliminary design, between the bureau or consumer-arbitration system. (3) In the last instance,
modules of Process Design and Product Design. In this first con- a claim can be filed with a court of law. The fastest and most
tribution, some of the value-in-design requirements can already economical way to solve conflicts is (2). Obviously, only a part
be verified. After this approval, the design team finalizes the of the initial claims will reach this stage, and for many claims
design and executes the Detailed Engineering stage. Once the are addressed by the developer or constructor. In any case, the
drawings and specifications have been completed, they are sub- user can request to impute blame to the municipality for poor
mitted to the municipality for final review and the issue of the performance in the project approval, during the work inspec-
work permit. At this point, the municipality must have com- tion, and/or with the compliance certificate.
pleted the review of the value-in-design requirements. Subse- We here propose a taxonomy of claims according to three
quently, the municipality inspects the job site during the types: (1) Design claims: These generate Learning Loops in
structural work and the finishing phase. During these stages, the triads of Project Definition & Lean Design; (2) Production
the inspector checks that the work is proceeding in accordance Claims: These generate Learning Loops in the triads of Lean
with the building permit and oversees the construction relation- Supply & Lean Assembly; and (3) Delivery Claims: These gen-
ship within the neighborhood. At this point, the supervisor needs erate Learning Loops in the triads of Use, implying adminis-
a tool such as a checklist to monitor the construction process trative and legal issues related to the delivery. This can be
and inspect critical products and processes, measuring them observed in both Fig. 3 and Table 2.
against what was learned from previous projects.
During the commissioning phase, the municipality supervi- 2.5. Root-cause analysis in the LPDS
sor inspects the finished work and issues the compliance certifi-
cate, a document that confirms the project has been Root-Cause Analysis can be summed up as an attempt to dis-
constructed according to the approved proposal. This docu- cover the fundamental causes of a problem, and so resolve it
ment declares that any changes introduced throughout the [20,21]. This method is based on the premise that problems
process have been correctly performed and supervised. This are solved more efficiently by treating their original causes,
document guarantees to the final user and other stakeholders rather than their symptoms [22] (see Fig. 4).
(such as insurance companies or banks) that the project meets We must note that each level of causal analysis brings with
all relevant construction codes and product-quality require- it a new potential solution. However, note that first-level solu-
ments. Municipal involvement is illustrated in Fig. 2. tions are often not permanent. We must keep in mind, that
each successive level of inquiry brings with it a greater chance
2.4. Post-occupation claims management for a long-term solution. We can apply this methodology to
any problem [20,21]. The procedure of Root-Cause Analysis
During the post-occupancy phase, once the housing unit has can be shown through a flowchart [23]. Based on LPDS, this
been delivered, users may file claims due to lack of product fit- analysis is reflected in Fig. 5, showing the root-cause flow to
ness of use. It has been assumed in the present paper that this determine the source of a lack of value. Likewise, the type of

Figure 2 Municipal actions and learning loops in the LPDS (adapted from [6]).
890 X. Brioso et al.

Figure 3 Classification of user claims related to the project’s process.

Table 2 Codes for different types of claims. claim is determined from its code: CD-D, CD-DD, CP-S, CP-
Claim Type Code A, or CP-U, as indicated in Table 2.
Design Claim of Design - Definition CD-D
Rosenfield proposes that Root-Cause Analysis is not
Claim of Design - Definitive Design CD-DD merely an arbitrary expression, but instead a well-structured
methodology that can be used as part of the total quality-
Production Claim of Production - Supply CP-S management approach [24]. In this way, the causes of the main
Claim of Production - Assembly CP-A
problems in different stages of the project can be established,
Delivery Claim of Delivery - Use CD-U and preventive measures are devised to avoid them [22]. In
future projects, this method can be adopted as a corrective
measure for the management system.
Root-Cause Analysis can be done based on the data col-
lected in interviews with different participants in a project, in
which said participants are asked about the problems they
encountered [25,26]. Similarly, it can be done with documents
that explicitly detail the possible causes, including the judicial,
sentencing, or administrative resolutions of a Consumer Pro-
tection Bureau, as shown in Fig. 6. This is the procedure we’ll
be using for the present research.

2.6. Rules and regulations

First off, the municipality needs to review all the information


Figure 4 Root-cause analysis [22]. given by the owner, contractor, or the company representative
in the request for the license. The department in charge of

Figure 5 Root-cause flow in LDPS.


Using post-occupancy evaluation of housing projects 891

Figure 6 Procedure for root-cause analysis (adapted from [22]).

reviewing this information needs to be comprised of specialists ness of use. Claims are initially submitted to the property
in their fields, such as architects, structural engineers, and san- developer and/or constructor. If the claim is not satisfactorily
itary engineers. They need to verify that the drawings and all addressed, the user can appeal to the consumer protection
the information registered in the municipality comply with bureau (in this case, INDECOPI). Municipalities can compile
the national rules and regulations. these claims within a certain time frame and connect them to
As a second step, this department needs to review in depth projects that were approved and carried out during a previous
all the information, giving each project the time it requires (this term. Claims are classified according to type (design, produc-
does not always happen, due to lack of personnel or tion, delivery).
resources). The department should also be able to give recom-
mendations for improvements to design or construction 3.2. Root-cause analysis of such claims is performed
methodology. Having professionals with enough background
experience in real projects, in different settings and environ- Based on the post-occupancy claims, and using Root-Cause
ments, is an immeasurable benefit for the department as a Analysis, we determine the true reason behind the claim, in
whole. order to rectify the situation, taking into consideration the
In developing countries, the lack of research and develop- type of claim (design, production, or delivery), as well as the
ment could mean that national codes are not the same as those corrective measure.
in developed countries, which must comply with numerous
quality regulations regarding materials and construction com- 3.3. NCHU baseline is calculated
ponents during both specification and installation. In addition,
very often such legislation ensures the user’s comfort or pro-
Calculate NCHU according to Eq. (4). This indicator will be
duct quality, among other needs and values. In this situation,
the baseline for the municipality for a specific time frame.
municipalities in developing countries may approve projects
The expectation is that this value will be reduced, and thus that
that do not comply with these obligations, thus affecting users
the value for the municipality will be increased.
and causing value to be lost. Municipal ordinances cannot
modify regulations; they are only allowed to control their
3.4. Optimization of project review
implementation at the level of parameters. Rules and regula-
tions can be improperly framed, and thus be prone to generate
designs that reduce value. Designers, municipalities, and con- All the reviews led by the municipality could be optimized by
tractors can easily comply with only the minimum require- scheduling group meetings with designers. Moreover, an intra-
ments, and argue that they have not broken the law. net system could be implemented to group all the latest regu-
Henceforth, it is essential to urge authorities to ensure regula- lations to be considered during the design, and to register
tions that truly protect the user in accordance with the latest the progress reports filed by each specialist [16]; this would
international standards. In the present paper, it is assumed reveal the identity of the person responsible for delaying the
that rules and regulations are adequate and do not affect the process, and for jeopardizing the quality of the review due to
claims registered. However, future research must analyze poor planning and rushed work as the deadline approaches.
whether national codes meet international standards in build- ‘‘Restructuring the internal mechanisms of the permit-
ing construction. issuing authorities to bring about efficiency in the processing
of permits can bring about elimination in a number of non-
3. The municipality framework value adding steps to speed up the process and enhance the
flow of construction project delivery.” [27]. Also, the phrase
‘‘making-do” refers to a situation where a task or processing
We propose the following steps to enhance the municipality’s
is started with incomplete information, without all its standard
value:
inputs. Here the term ‘‘input” refers not only to materials, but
to all other inputs such as machinery, tools, personnel, external
3.1. Municipalities compile user claims on finished projects after
conditions, and instructions [28]. Making-do must be analyzed
one year of use
and eliminated.
Considering the municipality’s participation and responsi-
During the post-occupancy phase, once the housing unit has bility as a supervisory agent in the design and construction
been delivered, users may file claims due to lack of product fit- process, it should have every available tool in order to do
892 X. Brioso et al.

the best possible job. The lack of the necessary tools slows inspections in future projects. The NCHU indicator was calcu-
down the process, making it ever more difficult for both the lated to set the baseline for future municipal management.
workers and the representatives from the companies in the Lima has 43 districts of different socioeconomic strata. To
construction process. Municipalities do not use any type of achieve a representative sample, it was recommendable to group
methodology in their process, and make do with what little municipalities with similar characteristics. The municipalities of
tools they have. The use of Building Information Modeling San Isidro, San Borja, Miraflores, and Santiago de Surco, are
(BIM) cannot be excluded; it is closer to the present than to roughly comparable [29], so their householders’ claims were
the future, in both public and private projects. the ones studied in this paper. Claims data were collected from
After the initial approval, the design team concludes the the Peruvian National Bureau of Consumer Protection during
final design and executes the Detailed Engineering phase. Once the period from August 2013 to September 2014 [30]. The num-
the drawings and specifications have been completed, it is sub- ber of housing units 24 months prior to this time frame
mitted to the municipality once again for final review, and the (18 months of construction plus six months of use) was 8632,
work permit is finally issued. according to the official statistics from the 2012 Peruvian Con-
struction Chamber [29] (CAPECO from its acronym in Spanish),
3.5. Optimization of project inspection and compliance the country’s official constructors’ guild. This includes all the
housing units whose construction was initiated from August
Once construction starts, the municipality is required to 2011 through July 2012 in the aforementioned municipalities.
inspect the job site during the structural work and the finishing
phase. During these stages, the inspector checks the work’s 5. Results and discussion
compliance relative to the initial project approved and oversees
the construction relationship with the neighborhood. Finally, Taking the former claim description as an example—‘‘Onset of
during the commissioning phase, the municipal supervisor structural and non-structural cracks and/or fissures”—we have
inspects the finished construction and issues the compliance to ask why these claims occurred, with the answer being, ‘‘there
certificate, a declaration that confirms that the project has been was probably an error in the construction.” Here we again have
constructed according to the specifications initially approved. to ask why, and the answer is ‘‘there wasn’t enough supervision
Also, said document declares that any changes introduced into on site.” Again, we ask why, with the answer being ‘‘it was prob-
the project throughout the process have been correctly per- ably an error in either architecture or in the engineering design.”
formed and supervised. This leads us to conclude that the municipality should have
Project inspections are scheduled based on the available reviewed the proposed project with trained professionals, in both
budget; the purposes of these visits were to inspect the quality architecture and civil engineering, with enough background
of the execution and to request proof of quality control of knowledge to note any errors found in the design. In other cases,
materials and components. As suggested by the analysis of too, the type of claim can be determined from its code: CD-D,
the claims, visits and quality-control inspections could be reor- CD-DD, CP-S, CP-A, or CP-U. Fig. 7 presents a flow model
ganized to increase their frequency during the project stage of the different types of root causes.
and activities in which problems commonly arise, while main- In our sample, 19 claims were filed under the heading of
taining the same cost. Making-do must be analyzed and elim- ‘‘Onset of structural and non-structural cracks and/or fis-
inated. After optimizations, we would expect to see a reduction sures.” After analyzing each one, we found ten claims of the
in the NCHU during the subsequent measuring, and hence an type CD-DD with the root cause of ‘‘Deficient structural
increased value for the user and the municipality. design” and nine claims of the type CP-A with the root cause
It is important to emphasize that the municipal procedure of ‘‘Deficient construction process.” As a corrective measure
must guarantee the maximum benefit for both the municipality for future projects, it is recommended that ‘‘the municipality
and the neighbors, in terms of value in design. This, in turn, will review the proposed design with professionals trained in
will reduce the number of complaints lodged in the post- structural design and inspect the quality of the execution.”
occupancy phase. This analysis was repeated with the remaining claims.
Based on the proposed method, and the information given
3.6. Repeat the cycle, with regular updates to NCHU throughout the present paper, Table 3 shows the compilation
of claims registered in INDECOPI [30], their root causes,
This cycle should be continuous, incorporating the lessons and their corrective measures.
learned into future projects. In this way, the needs of the final
users are continuously accommodated by the municipality. As 5.1. Calculation of the indicator
a consequence of the corrective actions taken, the NCHU
would be expected to decrease in the next time frame. After the analysis of the root causes of the claims in our study,
we found that 39 of these (15%) were related to design require-
4. The case study ments (value in design), 170 (67%) to production, and 44
(17%) to delivery. Using Eq. (4):
The research strategy is a case study in the capital city of Lima, 253
Peru. To assess the feasibility of the recommendations of the pre- NCHU%ðTotalÞ ¼ ¼ 2:93%
8632
vious section, claims data were collected, analyzed and classified
according to their nature. Root causes were then determined, 39
NCHU%ðDesignÞ ¼ ¼ 0:45%
and their analysis will be the learning loop for the municipal 8632
Using post-occupancy evaluation of housing projects 893

Figure 7 Root-cause flow of onset of structural and non-structural cracks and/or fissures.

170 the compliance certificate at the end of the project. Learning


NCHU%ðProductionÞ ¼ ¼ 1:97%
8632 loops from this methodology are essential for continuous
improvement and value generation. The post-occupational
44
NCHU%ðDeliveryÞ ¼ ¼ 0:51% information must be recorded, analyzed, and taken as a base-
8632 line for the continuous improvement of the license-approval
In fact, the total number of claims is substantially higher, and project-inspection systems, as well as for the issuance of
but a good portion of them is addressed by the property devel- optimized ordinances. In this context, the municipality
oper and/or constructors. As previously stated, the 253 claims revamps its management to reduce the number of claims, thus
are just the tip of the iceberg. From the consumer’s perspec- increasing the benefits in the value formula. As a result, the
tive, these claims could be classified as relevant, since if they relationship between user and municipality is reinforced
weren’t, the users wouldn’t have filed with the Consumer Pro- throughout the use of the product, and the municipality’s
tection Bureau, knowing these administrative procedures were brand is protected. The method could also be optimized and
going to take up time and energy. A future study could develop adapted to national realities or different project types.
a methodology to estimate the total number of claims that It is possible to correlate an increase in value in the munic-
users file with either investors or constructors and compare ipal management with the reduction in claims per number of
them with the number of ‘‘relevant claims,” which are claims housing units, as the two variables are interconnected. The
that are not processed, but which the users consider important. reduction in claims means a reduction in energy expended
and cost, which means a reduction in waste and thus an
6. Conclusions increase in value.
This article argues that rules and regulations could be ill-
established, thus generating a lack of value from the design
This article proposes a value-generation framework for munic-
itself. Designers, municipalities, and contractors could easily
ipal management, based on LPDS tools and techniques. Said
comply with only the minimum requirements and argue that
process includes the use of learning loops from previous pro-
they have not broken the law. However, this article has devel-
jects to revamp municipal management in design revision, con-
oped research that consists only the identification of design
struction supervision, and commissioning, taking into account
claims. Future research projects may include a deeper analysis
the final user’s needs and values. This framework allows the
on the suitability of rules and standards, with the purpose of
municipal management to investigate the user’s value require-
defining the responsibilities of designers, municipalities, con-
ments and proposes the Number of Claims per Housing Unit
structors, and/or the State, in their duty of properly regulating
(NCHU) as a performance indicator. The case study suggests
building construction. Therefore, it is essential to urge author-
that the municipality does not have a methodology to assess
894
Table 3 Claims registered in INDECOPI, root causes, and corrective measures (August 2013 – July 2014).
Claims time frame From 2013 to 2014
Building delivery time frame From 2011 to 2013
Municipalities under study Miraflores/San Borja/San Isidro/S. Surco
Total sample 253 claims
Claim description Total Claim type Root cause/Corrective measures (Learning loops)
CD-D CD-DD CP-S CP-A CD-U
Flooring defects in the building 14 12 2 0 0 0 Quality control of design materials/The municipality will perform a general review
of the material samples
Onset of structural and non-structural cracks and/or 19 0 10 0 9 0 Deficient structural design and/or deficient construction process/The municipality
fissures will review the proposed design with professionals trained in structural design and
inspect the quality of the execution
Delivery delay of the building relative to the due date 19 0 0 0 0 19 Administrative and legal issues related to the delivery
Water filtration in walls, floors, and ceilings. Onset of 13 0 0 0 13 0 Lack of quality control over equipment, materials, or supervised elements/The
saltpeter municipality will inspect the quality of the execution and request proof of quality
control of materials and components
Non-compliance with building partition. Factory 17 0 0 0 0 17 Administrative and legal issues related to the delivery
declaration
Non-compliance with the delivery of documents and 8 0 0 0 0 8 Administrative and legal issues related to the delivery
blueprints
Non-compliance with the regulations regarding 2 0 2 0 0 0 Non-compliance with standards and regulations/The municipality will review the
mechanical facilities for handicapped people proposed design with professionals trained in mechanical facilities
Finishing has different characteristics and conditions 40 0 0 0 40 0 Lack of quality control over equipment, materials, or supervised elements/The
than those indicated in the Descriptive Report and municipality will inspect the quality of the execution and request proof of quality
approved blueprints control of materials and components
Finishing performed with materials of lower quality 19 0 0 19 0 0 Lack of quality control over equipment, materials, or supervised elements/The
than those agreed upon municipality will inspect the quality of the execution and request proof of quality
control of materials and components
Deficient finishing, with flaws or gaps, which do not 37 0 0 0 37 0 Lack of quality control over equipment, materials, or supervised elements/The
provide the durability and esthetic quality that was municipality will inspect the quality of the execution and request proof of quality
promised control of materials and components
Dimensions, measurements, or areas smaller than 6 0 0 0 6 0 Lack of quality control over supervised elements/The municipality will inspect the
those offered quality of the execution
Ramp dimensions do not comply with the building 2 2 0 0 0 0 Non-compliance with standards and regulations/The municipality will review the
regulations proposed design with professionals trained in building regulations
Installation of gas tank and other facilities without 2 0 2 0 0 0 Non-compliance with standards and regulations/The municipality will review the
informing the user (specifications, blueprints, etc.) proposed design with professionals trained in building regulations
Poor installation of equipment, materials and/or 46 0 0 0 46 0 Lack of quality control over equipment, materials, or supervised elements/The

X. Brioso et al.
elements in the building municipality will inspect the quality of the execution and request proof of quality
control of materials and components
Claims for elements in the building that defy the 5 0 5 0 0 0 Non-compliance with standards and regulations/The municipality will review the
national construction regulations proposed design with professionals trained in building regulations
Using post-occupancy evaluation of housing projects 895

ities to estipulate regulations that better protect the user, fol-


Non-compliance with standards and regulations/The municipality will review the

Non-compliance with standards and regulations/The municipality will review the lowing the latest international standards that generate value.

References

[1] P. Kotler, Kotler on Marketing: How to Create, Win and


proposed design with professionals trained in building regulations

proposed design with professionals trained in building regulations

Dominate Markets, Free Press, New York, 1999.


[2] P. Kotler, Marketing Management, Millenium Edition, Pearson
Custom Publishing, Boston, 2002.
[3] Lean Construction Institute, LCI Lean Project Delivery
Glossary 2014. Available at: <http://www.leanconstruction.
org/> [accessed 15 January 2015].
[4] Office of Government Commerce, Managing Successful
Projects with PRINCE2TM, The Stationery Office, Norwich,
UK, 2009.
[5] G. Ballard, Lean Project Delivery System. Lean Construction
Institute. White Paper-8 (Revision 1). Lean Construction
Institute, 2000.
[6] G. Ballard, The lean project delivery system, Update Lean
Construct. J. (2008) 1–19.
[7] R. Smith, A. Mossman, S. Emmitt, Lean and Integrated project
delivery, Lean Construct. J. (2011) 1–16.
[8] G. Ballard, T. Zabelle, Project Definition. Lean Construction
Institute. White Paper-9. Lean Construction Institute, 2000.
[9] L.F. Alarcon, H. Mesa, G. Howell, Characterization of Lean
Project Delivery, in: C.T. Formoso, P. Tzortzopoulos (Eds.),
21th Annual Conference of the International Group for Lean
Construction, Fortaleza, Brazil, 31–2 Aug 2013.
[10] A. Schöttle, What is the Lean Project Delivery System? Lean
Construction Blog, 2015. Available at: <http://
delivery
Claims

leanconstructionblog.com/> (September 30, 2015).


17%
44
44

[11] X. Brioso, Integrating ISO 21500 guidance on project


of
0

management. Lean construction and PMBOK, Proc. Eng. 123


(2015) (2015) 76–84.
151

[12] J.E. Diekmann, et al., Application of Lean Manufacturing


production
0

Claims of

Principles to Construction. Construction Industry Institute -


The University of Texas at Austin, 2004.
67%
170

[13] H.E. Ali, I.A. Al-Sulaihi, K.S. Al-Gahtani, Indicators for


19
0

measuring performance of building construction companies in


Kingdom of Saudi Arabia, J. King Saud Univ. – Eng. Sci. 25 (2)
Claims of design

(2013) 125–134.
25

[14] T. Bølviken, J. Rooke, L. Koskela, The Wastes of Production in


2

Construction–a TFV Based Taxonomy, in: B. Kalsaas, L.


Koskela, T. Saurin, 22nd Annual Conference of the
15%

International Group for Lean Construction, Oslo, Norway,


14
39
0

2014.
[15] P. Orihuela, J. Orihuela, Needs, values and post-occupancy
253

evaluation of housing projects customer: a pragmatic view, in:


2

M. Skibniewski, M. Hajdu, Creative Construction Conference


2014, Prague, Czech Republic, 2014.
[16] P. Orihuela, J. Orihuela, K. Ulloa, Tools for design management
in building projects, in: J. Rooke, B. Dave, 19th Annual
Design of adjoining sanitary and electrical

Conference of the International Group for Lean Construction,


Lack of slope protection against rockfall

Lima, Peru, 2011.


[17] Ley N° 29571, Código de Protección y Defensa del Consumidor,
Diario Oficial El Peruano, Perú, 02 septiembre 2010.
[18] Ley N° 19.496, Ley de protección de los derechos de los
installations in the same wall

consumidores. Biblioteca del Congreso Nacional de Chile. Chile.


Promulgada el 07 febrero 1997.
[19] Real Decreto Legislativo 1/2007, Texto refundido de la Ley
General para la Defensa de los Consumidores y Usuarios.
Boletı́n Oficial del Estado (BOE) No. 287. España, 2007. 30/11/
2007.
[20] J. Liker, The Toyota Way: 14 Management Principles from the
World’s Greatest Manufacturer, McGraw-Hill, 2004.
Total

[21] Z.K. Rybkowski, The application of Root Cause Analysis and


Target Value Design to Evidence-Based Design in the Capital
896 X. Brioso et al.

Planning of Healthcare Facilities. PhD thesis. University of [27] E.Z. Kpamma, T. Adjei-Kumi, Construction Permits and Flow
California, Berkeley, CA, 2009. of Projects Within the Sunyani Municipality Ghana, in: C.T.
[22] R. Garcı́a, Factores de riesgo que inciden negativamente en los Formoso, P. Tzortzopoulos (Eds.), 21th Annual Conference of
cumplimientos de tiempo y coste programados en la ejecución de the International Group for Lean Construction, Fortaleza,
proyectos de edificios de uso hotelero en España. PhD thesis. Brazil, 2013.
Technical University of Madrid, Spain, 2015. [28] L. Koskela, Making-Do - the Eighth Category of Waste, in: S.
[23] L. Spitler, T. Feliz, N. Wood, R. Sacks, Constructible BIM Bertelsen, C.T. Formoso (Eds.), 12th Annual Conference of the
Elements –a Root Cause Analysis of Work Plan Failures, in: O. International Group for Lean Construction, Helsingør,
Seppänen, V.A. González, P. Arroyo (Eds.), 23rd Annual Denmark, 2004.
Conference of the International Group for Lean Construction. [29] Cámara Peruana de la Construcción CAPECO, El Mercado de
Perth, Australia, 29–31 Jul 2015, 2015, pp 351–360. Edificaciones Urbanas en Lima Metropolitana y el Callao –
[24] Y. Rosenfeld, Root-cause analysis of construction-cost XVII Estudio, CAPECO, Lima, Perú, 2012.
overruns, J. Construct. Eng. Manage. 140 (1) (2014). [30] Instituto Nacional de Defensa de la Competencia y de la
[25] M. Ammerman, The Roots Cause Analysis Handbook, Taylor Protección de la Propiedad Intelectual del Perú INDECOPI,
& Francis, 1998. 2015. Available at: <http://aplicaciones.indecopi.gob.
[26] G. Noordzy, R. Whitfield, Root causes of hotel opening delays pe/portalSAE/> [Accessed 21 February 2015].
in Greater China, Cornell Hospitality Report 14 (10) (2014) 6–
18.

View publication stats

You might also like