ABBEYMAN SITE

ABBEYMAN SITE- EARTHWORKS


Bill Item DESCRIPTION UNIT QTY RATE AMOUNT
No

BILL:EARTHWORKS,

1 Earthworks

2 Site Clearing,stripping and grubbing of non-stable topsoil to a maximum


2
depth of 200mm (incl. rubbles,weeds and unsuitable material removal) m 125 35 4,375.00

3 Borrow to fill, place & compact to 93% Mod AASHTO into 200mm (loose) layers, including
hauling from within 17km haul distance truck 8.00 850.00 6,800.00

4 Scarify, water, mix, prepare & compact fill (including fill slopes) of a 150mm layer to
finished levels, 95% ModAASHTO (imported selected material). m3 125.00 12.50 1,562.50

5 Spread, scarify, water, mix, prepare and compaction of 150mm imported selected
base to 98% ModAASHTO (unstabilised, including hauling from within 17km haul distance ). m3 125.00 14.50 1,812.50

CARRIED FORWARD TO SUMMARY 14,550.00

CLIENT: Mr. Kennedy Ewuntomah

BoQ SUMMARY
BILL DESCRIPTION AMOUNT ()

1 Earthworks 14,550.00

2 Labour/Man hour 2,500.00

Sub-total:

GRAND TOTAL 17,050.00

ABBEYMAN SITE 1 PKO Consulting Engineers