Professional Documents
Culture Documents
Table of Contents
1. INTRODUCTION: .................................................................................................................................... 2
2. WHY WE NEED TO OPT. THIS PROPOSAL? ........................................................................................ 2
3. Elements for Rock Mass Stability: ............................................................................................................ 3
a. Consolidation Grouting within the Tunnel .............................................................................................. 3
Objectives: .................................................................................................................................................. 3
Methodology: .............................................................................................................................................. 4
DRAWINGS ................................................................................................................................................ 6
b. Backfill Grouting within the Tunnel ........................................................................................................ 6
DRAWINGS ................................................................................................................................................ 6
c. Contact Grouting within the Tunnel ....................................................................................................... 6
Objectives: .................................................................................................................................................. 6
Methodology: .............................................................................................................................................. 7
DRAWINGS ................................................................................................................................................ 7
d. Placement of Geomembrane ......................................................................................................................... 7
e. Treatment of the Extreme Poor Rock Zone in theTunnel ................................................................ 8
Two alternatives are suggested as under: ................................................................................................. 8
i. Treatment by Strenghting of the Concrete Suiting worst Geological Condition ...................... 8
DRAWING .................................................................................................................................................. 8
ii. Installation of steel liner ..................................................................................................................... 8
4. ABSTRACT OF COST: ............................................................................................................................. 9
a. Abstract of Cost with RCC Lining ...................................................................................................... 9
b. Abstract of Cost with Steel Lining ................................................................................................... 10
5. ABSTRACT OF QUANTITIES: .............................................................................................................. 12
6. ROCK MASS CLASSIFICATION – ACTUAL VS FEASIBILITY COMPARISON: ............................ 13
7. GEOLOGICAL MAPPING FOR TUNNEL INLET – SUPPORTING DOCUMENT: .......................... 20
8. GEOLOGICAL MAPPING FOR TUNNEL OUTLET – SUPPORTING DOCUMENT: ....................... 20
9. CONCLUSION: ....................................................................................................................................... 20
10. LIST OF ATTACHMENT................................................................................................................... 20
1. INTRODUCTION:
During the excavation of the Karora HPP Tunnel, it has been noticed that the strata
encompassing the Tunnel is extremely heterogeneous including extreme poor rock
zones at places. Rock of Continental and the Oceanic crusts have been encountered in
highly intermixed position. The continental crust rocks comprising Granite and Granitic
gneiss. The oceanic crust rocks consist of ultrabasic (slabs of dunites, peridodite,
pyroxinite, gabbro and amphibolites etc). Most of these have undergone varying
degrees of alteration like chloritization and serpentinization etc. The two different stuffs
(e.g. crustal and oceanic masses) have come together through severe orogenic
deformation plate movements, resultantly the formational contacts are faulted, sheared
and closely intermingled (see cover Photo). The entire masses around the Tunnel are
water bearing and carry enumerable water passages.
The position of the inflow of water at various reaches has been on very high side. The
record shows up to 5040 Cum of dewatering conducted per day for several months.
This has been a unique case in the history of Tunnels in the world.
Keeping in view the brief summary given above, it is needed to keep in mind the future
operative life of the Tunnel structure. It is known that the seepage from the strata is of
vital importance for the life of the Tunnel. This water has to be controlled. For this
purpose, the leakages have to be sealed. It is mainly done through the consolidation
Grouting.
Methodology:
The methodology to be followed for Karora HPP tunnel is adopted after Norwegian
tunneling society Publication 20 and British Standard the code of practice (BS
5930:2015).
Continuous seepage in the cover rock encompassing the tunnel lead to damaging the
concrete lining. It is essentially required to grout the wall rock to block the undesirable
leakages by filling the joints, fractures, water seepage paths by grouting material,
mainly cement, Bentonite and/or fine sand and accelarator through grout holes already
drilled. The grout with water cement ratio as 1:1, 0:8:1. 0:6:1 will be used. The ratio
can be modified as per site condition depending upon flow of grouting material and final
refusal of grout under particular applied pressure that will be intiated with 0.5 mega
pascal (Mpa) to a maximum of 1.2 Mpa subject to very close watch for noticing and
avoiding hydro fracturing of strata.
As a first step pneumatic down hole hammer or rotary drilling will be carried out. Upon
drilling, the holes will be cleared of residue and debris with compressed air or clean
water.
The orientation of the holes and the drilling tools should be checked prior and during
the drilling process. The allowable tolerance of hole location should not be more than
0.10 m.
As stated earlier, the tunnel rock comprise extreme sheared and shattered zones. It is
believed that drilling in such zones may lead to collapsing of the drill holes. Under such
conditions drilling will be done with casing and perporated grouting pipes inserted and
sealed by proper flexable grout mix of cement and 2-3% bentonite, subject of
adjustment before removing the casing.
Grouting in a hole can be terminated when the injection rate of grout material becomes
no more than 2 litres per minute for 20 minutes under specified pressure.
When the pressure for grouting keeps stable and injection rate decreases gradually, or
the injection rate keeps stable and the pressure increasing gradually, the ratio of
water/cement should not be changed.
1. Drilling of 40-75mm diameter hole to required length and inclination as per the
site condition.
2. The ascending method involves the advancement of the hole to full depth in one
drilling operation, followed by washing the complete length of the hole in one
washing operation.
3. The length of the hole is divided into 1.5m stages. The packer will be locked at
1.5m in the hole and release the grout in hole under specific pressure. The pressure
of grout will be maintained according to the rock condition.
4. Packer being moved to the next higher 1.5m stage after grouting has been
completed in the prior stage and the stage reached to the refusal pressure.
5. The various items of drilling, washing, water testing, and grouting equipment are
mobilized to the hole only one time.
6. The grouting machine will not be kept more than 25 meters away from the hole
being grouted.
Drawings
The proposed drawings are attached under Annex - 3.1
This phenomenon is more valid at the central part of the crown of the tunnel and areas
containing cavities on the side wall. Such areas are undesirable to exist. These
voids/gevoids need to be filled with grout so as to save and protect the tunnel structure.
Backfill grouting reduces permeability around the tunnel also helps in minimising
corrosion in the concrete lining.
The methodolgy to be adopted for the backfill grouting will remain the same as that for
the contact grouting however the depth of holes will be increased by about 15cm
beyond the contact grouting holes depth or to a depth when the rock wall of the outer
shell is reached.
Drawings
The proposed drawings are attached under Annex - 3.2
Objectives:
Underground structures have two shells; (a) the inner concrete / steel lining that
provide for smooth passage for water from the reservoir to the powerhouse and (b) the
outer shell of excavated structure of tunnel which provide space for construction of the
inner shell.
The outer shell passes through strata consisting of rocks of different lithologies and
varying physical characteristics. Conventional type of excavations, involving drilling and
blasting never leaves a smooth surface behind. Similarly the concrete emplaced for
construction of the inner shell cannot fill the uneven surface of the outer shell
completely.
There always occur open spaces in between the two shells of the tunnel structure. It is
essentially required to fill the gap between the two shells. The open spaces are bound
to serve as channels for seepage water and as voids for permeating water. The water
may ultimately cause damage to the inner shell.
The gap is filled by contact grouting which prolongs the life of the inner shell. It also
consolidates the inward surface of the outer shell. The contact grouting forms an anti-
seepage membrane whereby the routes of the seepage water is diverted away from
the inner shell. The grouting, between the inner and outer shells is internationally
termed as contact grouting.
Methodology:
Contact grouting will be conducted subsequently to the concrete lining of the tunnel. It
has been experienced that a thin line is left in between the concrete lining and the rock
wall. The cement concrete also develops open spaces all along the outer boundary of
the concrete lining of tunnel which work as paths for incoming water from rock wall. In
order to stop water, this thin but almost continues space all around the tunnel lining is
sealed by contact grouting.
The thickness of the concrete lining of Karora HPP tunnel is 23cm. for the purpose of
grouting, 23cm deep holes will be drilled through concrete lining and temporary support
structure as per the drawing shown in the annex - 3.3. Through which the grout
material will be injected to fill the empty annulus.
Drawings
The proposed drawings are attached under Annex - 3.3
d. Placement of Geomembrane
Normally the undesired leakages of water gets controlled by consolidation grouting in
fractured strata. However use of geomembrane become necessary in diverting / routing
of dripping water so that the concrete tunnel lining is saved from future demages. Most
of the ophiolitic rocks e.g gabbros and associated matel bearing rocks in the tunnel
are sulphide bearing. These tend to create acidic conditions. Such conditions are
injurious to steel and cement structures in the tunnel in the long run.
Geomembrane will be fastened to the excavated rock surface through widely spaced
wire mesh. The membrane sheets are avaliable in about one meter wide sheets of
different length. These are binded to one another by epoxy glue. Dripping water will be
collected/ routed to particular points and finally brought into the main water conduit/
tunnel or then to the dranige system of the tunnel.
It is important to mention here that, though in small quantity, the dripping water in long
terms add to the outer pressure of the tunnel. It is required that the outer and inner
pressure of the tunnel must remain in equilibrium. Once blocked the water can find its
natural pathes outwards of the water-conduit and avoid to enter the bed of the tunnel
so as not to exert extra pressure on the bed. On the contrary the slow but continuous
increase in this pressure ultimately decomposition of the concrete structure.
Keeping the above in view it is earnestly recommended that strong rigid Rock Support
measures be got designed to cater for worst conditions. In engineering works,
reinforced concrete is believed to be strong, rigid and durable construction material.
Drawing:
The proposed drawings are placed at Annex - 3.4
b. Outlet Side:
i. RD 75-110
ii. RD 485-540 90 Meters
These poor zones were provided strong rock support during excavation; e.g. at inlet
side Lattice girders and solid steel arches, duly fastened to one another through 25-
35mm thick steel bars, properly rock bolted and thickly shotcreted, were installed at RD
417—431 and RD 760—780. at respective dates of 2nd March.2017to 14th May 2017
and 2nd March 2018—28th March 2018.
Convergence ranging between 0.2 m to 0.7m has been noted up till now. This rate of
deformation is undesirable.
The bed level of the liner will remain the same as the level of the concreted bed.
The liner will be concrete-embedded.
4. ABSTRACT OF COST:
Summary of the cost is being presented over here. The details of the cost are
being referred to attached Annex-1.
ABSTRACT OF COST
PROPOSAL NO - 1 Annex-1
S.no Description Unit Quantity Rate Amount Remarks
Drilling required for
A
grouting
Length of
Rate Analysis
Drilling for M
1.0 12,845.9 6,090.4 78,236,891.7 GHT 2
Grouting
Qty of Cement
B
required for grouting
D Geomembrane
with Labour
Geomembrane Sqm
4.0 4,265.0 953.0 4,064,545.0 Cost
Rate Analysis
Steel Ton
8.0 76.0 132,750.0 10,088,395.8 GHT 4
E Total (E)
35,024,581.4
Total
(A+B+C+D+E) 493,392,799
Overhead &
21%
Profit (21)% 493,392,799
ABSTRACT OF COST
PROPOSAL NO - 2 Annex-1
D Geomembrane
with Labour
Geomembrane Sqm
4.0 4,265.0 953.0 4,064,545.0 Cost
Rate Analysis
Steel Lining KG
5.0 327,685.2 491.0 160,893,443.8 GHT 6
5. ABSTRACT OF QUANTITIES:
The details of the Quantaties are being referred to attached Annex-2.
Rock Categorization Along the Tunnel Route (As Per Rock Categorization Along the Tunnel Route (Final Feasibility
Actual) Report Chapter-3)
S Chain age Rock Chain age Rock Rock
Rock Type Length Rock Type Length
No. From To Category From To Description Category
Poor to
Highly Jointed
1 0+00 0+30 30 Very
Granitic Gneiss
Poor
Highly Jointed
2 0+30 0+120 90 Fair
Granitic Gneiss
Highly Jointed
Granitic Gneiss, Poor to Massive, blocky,
3 Deformed Ultrabasic, 0+120 0+240 120 Very Granite
0+000 0+300 300 strong, tunnel Good
Gneiss
Diorite, Amphibolite Poor drive with dip
Quartz-PG Intrusions
Diorite, Quartz-PG
4 0+240 0+265 25 Fair
Intrusion
Deformed Sheared Poor to
5 Ultrabasic, Granitic 0+265 0+300 35 Very
Gneiss, Diorite Poor
Granitic Gneiss, Tectonized Closely jointed, Poor to V.
6 0+300 0+335 35 Fair 0+300 0+600 300
Diorite Zone moderately to poor
PROPOSAL FOR CONSOLIDATION, BACKFILL AND CONTACT GROUTING, EMPLACEMENT OF GEOMEMBRANE & STEEL LINER
OR ENHANCED RCC LINING FOR TUNNEL
Highly schistose,
moderately to
Moderately Jointed closely jointed
Graphitic
20 Granitic Gniess, 1+427 1+433 6 Fair 1+400 1+450 50 with highly V. Poor
Schist
Quartz-PG Intrusion sheared zones,
tunnel drive
against dip
Moderately Jointed
21 Granitic Gniess, 1+433 1+588 155 Good
Quartz-PG Intrusion
Sheared Ultrabasics
Poor to
22 rocks, Quartz-PG 1+588 1+592 4
Fair
Intrusions
Granitic Gniess, Massive, blocky,
23 1+592 1+607 15 Fair Granite
Quartz-PG Intrusions 1+450 2+300 850 strong, tunnel Good
Gneiss
Granitic Gniess, drive against dip
Ultrabasics rocks,
24 Recrystallization 1+607 1+717 110 Fair
Limestone, Quartz-
PG Intrusions
Granitic Gniess, Fair to
25 1+717 1+768 51
Quartz-PG Intrusions Good
Granitic Gniess, Fair to
26 1+768 1+774 6
Quartz-PG Intrusions Poor
Granitic Gniess,
27 1+774 1+801 27 Fair
Quartz-PG Intrusions
Highly schistose,
Highly jointed moderately to
Granitic Gniess, Poor to closely jointed
Graphitic
40 Deformed Ultrabasic 2+516 2+546 30 Very 2+500 2+600 100 with highly V. Poor
Schist
Rocks, Quartz-PG Poor sheared zones,
Intrusion tunnel drive
against dip
Highly Sheared Poor to
41 Ultrabasic Rocks, 2+546 2+681 135 Very
Quartz-PG Intrusion Poor
Highly Sheared
Fair to
42 Ultrabasic Rocks, 2+681 2+696 15
Poor
Quartz-PG Intrusion
Sheared Ultrabasics
43 rocks, Quartz-PG 2+696 2+716 20 Fair
Intrusions
Sheared Ultrabasics
Blocky to closely
44 rocks, Quartz-PG 2+716 2+771 55 Fair Granite
2+600 2+980 380 jointed, Fair
Intrusions Gneiss
fractured,
Deformed and Highly
Sheared Ultrabasics,
Extremely
45 Hornblendite, 2+771 2+806 35
Poor
Serpentinites, Qz-PG
Intuarsion
Deformed and Highly
Sheared Ultrabasics,
Extremely
46 Hornblendite, 2+806 2+831 25
Poor
Serpentinites, Qz-PG
Intuarsion
9. CONCLUSION:
Since the stability of the tunnel is most important therefore, our recommendation is to
get the decision for such proposal at earliest. Upon acceptance of such proposal, detail
drawings/design and study may be submitted for your kind approval along with the
variation order.
ABSTRAT OF
2 ANNEX-2
QUANTATIES
PROPOSAL
3 ANNEX-3
DRAWINGS
CONSOLIDATION
I ANNEX-3.1
GROUTING DRAWINGS
BACK FILL GROUTING
II ANNEX-3.2
DRAWINGS
CONTACT GROUTING
III ANNEX-3.3
DRAWINGS
RCC LINING FOR CRITICAL
IV ANNEX-3.4
ZONE IN TUNNEL
GEOLOGICAL
4 ANNEX-4
MAPPING
CNTRACT
5 ANNEX-5
REQUIRMENT
TUNNEL IFC
6 ANNEX-6
DRAWINGS