TYPE 1, PRAGMATIC RECTANGLE Tank gusset thickness Ø ANHOR A Share Tensile Placement STEEL FIBER

HEIGHT 100 cm 15 mm (mm) (cm²) (kg) (kg) (kg) s t s+ s-


BASE DIMENSION 400 cm 12 1.13 903 1583 1285 Mpa Mpa
100 cm 16 2.01 1604 2815 1713 216 70
PLACEMENT 6 nos 19 2.84 2263 3969 2034 (kg/cm²) (kg/cm²) (kg/cm²) (kg/cm²)
Ø ANCHOR 12 mm 1400 798 2202.595 713.804
VOLUME 4 m³
Max SEISMIC Energy
Speed 3 m/s
Volume 50% 2 m³
Force (Momentum) 9000 N

Look at anchor section share force, cause of momentum


Active placement amount 6 nos

USE 6 PLACEMENT @ 2 ANCHOR


Needed 2 pcs

Look at anchor section tensile foce, cause of rolling moment


Active placement amount 3 nos
Needed 1 pc

Look at tank base thickness 15 mm, cause of momentum


Active placement amount 6 nos

Ø 12 mm
Needed 1 pc

TYPE 2, PRAGMATIC RECTANGLE


HEIGHT 65 cm
BASE DIMENSION 80 cm
40 cm
PLACEMENT 4 nos
VOLUME 0.208 m³
Max SEISMIC Energy
Speed 3 m/s
Volume 50% 0.104 m³
Force (Momentum) 468 N

Look at anchor section share force, cause of momentum


USE 4 PLACEMENT @ 1 ANCHOR

Active placement amount 4 nos


Needed 1 pc

Look at anchor section tensile foce, cause of rolling moment


Active placement amount 2 nos
Needed 1 pc

Look at tank base thickness 15 mm, cause of momentum


Ø 12 mm

Active placement amount 4 nos


Needed 1 pc

TYPE 3, TUBE
HEIGHT 175 cm
BASE DIMENSION Ø 175 cm
PLACEMENT 4 nos

VOLUME 4.209 m³
Max SEISMIC Energy
Speed 3 m/s
Volume 50% 2.105 m³
Force (Momentum) 9470.797 N

Look at anchor cutting share force, cause of momentum


USE 4 PLACEMENT @ 3 ANCHOR

Active placement amount 4 nos


Needed 3 pcs

Look at anchor cutting tensile foce, cause of rolling moment


Active placement amount 2 nos
Needed 2 pcs

Look at tank base thickness 15 mm, cause of momentum


Ø 12 mm

Active placement amount 4 nos


Needed 2 pcs
PROJECT
BBIL LABORATORY BUILDING
MATARAM - LIPI A3
LOMBOK

STEEL STRUCTURE

TOP ELEVATION
TOP ELEVATION

TOP ELEVATION

FRONT ELEVATION SIDE ELEVATION


FRONT ELEVATION SIDE ELEVATION

FRONT ELEVATION SIDE ELEVATION

TANK TYPE 1 TANK TYPE 2 TANK TYPE 3


SCALE 1:50 SCALE 1:50
SCALE 1:50

TOP ELEVATION TOP ELEVATION TOP ELEVATION

FRONT ELEVATION SIDE ELEVATION FRONT ELEVATION SIDE ELEVATION FRONT ELEVATION SIDE ELEVATION

TANK TYPE 4 TANK TYPE 5 TANK TYPE 6


SCALE 1:50 SCALE 1:50 SCALE 1:50