Software Development Progress Report

Team Members Name: Team member 1


Team member 2

Email: test@test.com
Test2@test.com

Date Started: 05/25/2021


Targeted Date: 08/29/2021

How much work is completed?


As we just started we are done with 20% of work i.e. we have developed the software project
proposal, project model. We have marked out the main requirements of the system and have
decided the tools and technologies that we are going to use in the development of the system. We
have also selected the software methodology and the architecture structure that we are going to
use.

Remaining work items


We are done with system analysis and requirement phase. Now we need to move to construction
phase where we have to develop the working modules of the system. After construction phase is
done we need to do testing of the system. We will perform unit testing and system testing once
the system is developed.
Experienced Challenges
We had to decide the features and architecture structure for our project, which are most crucial in
the development phase. In development one issue we might have to face is that current library
system has very large historical data maintain in paper files we have to log it in our database as
well.
How challenges were handled?
After studying different library system and documents, we decided the top features which
handled and were most suitable for our problem analysis. We decided the architecture on the
basis of programming language we used and how our system functionality will be.
The issue of historical data will be handled by creating an excel file for the data and simply
importing it in our database.

Gantt Chart
The gantt chart displays our overall estimated system progress.