PROJECT: A-11180-REINFORCEMENT OF 33KV NETWORK IN AL AIN CITY AREA.

Client AADC Site Ref.


Consultant OLP Feeder No.
Contractor Lindenberg Emirates LLC Date of Test
SAT REPORT FOR TOUCH VOLTAGE MEASUREMENT

Voltage Actual
measured Voltage measured with voltage
Sl. Touch Voltage
Test Location without resistance across
No# resistance 1kΩ
V (V) V0 (V) V1 (V) V2 (V) Vrb (V) Vt = K × Vrb (V)

NOTE
Tolerable Touch Voltage for Gravel = ______ V ; Tolerable Touch Voltage for concrete = ______ V
Injected current, Ir = 100A ; Shock time Duration = ____ sec
Max. Earth fault current, If = ______A, as per earthing calculations; K factor = If/Ir = ______

TEST CARRIED OUT BY TEST WITNESSED BY TEST APPROVED BY


Signature: Signature: Signature:
Name: Name: Name:

Date: Date: Date:

Contractor: LINDENBERG – EMIRATES Consultant: OLP Client: AADC

A11180 SAT report Page 1 of 1