TOP BAR SHORT TOP BAR


1. ALL CONC.BEAM, COLUMN, FOOTING & SUSPENDED SLAB SHALL BE 3,000PSI L1/4 (L1+L2)/4 L2/4

2. SLAB ON GRADE SHALL BE 2,000PSI B


STIRRUP TORSIONAL BAR
3. REINFORCING BARS SHALL BE GRADE 40KSI
4. STRUCTURAL STEEL SHALL CONFORM TO ASTM A=36
D
5. FOUNDATIONS WERE DESIGNED TO THE PRESUMPTIVE
SOIL PRESSURE OF 144KPa, CONTRACTORS SHALL VERIFY L1/5 L2/5
CONT. BOT. BAR SHORT BOT. BAR
AND COORDINATE WITH THE DESIGNERS FOR ANY
DISCREPANCIES
3 BEAM DETAIL
S-3 NOT TO SCALE

STRUCTURAL NOTES CONCRETE BEAM SCHEDULE


NOT TO SCALE LEGEND: BAR TOP-
BAR BOT.- BEAM STEEL REINFORCEMENTS
DIMENSION STEEL STIRRUPS
FLOOR BEAM
(mm) REBAR AT SUPPORT AT MID SPAN Ø10mm
LEVEL MARK
Ly Ly DIAMETER ( UNLESS NOTED OTHERWISE )
B D TOP BAR BOT. BAR TOP BAR BOT. BAR
Lx/4 Ly-Lx/2 Lx/4
RB1 200 250 Ø12mm 5 2 2 3 1@ 50mm, 8@ 75mm, REST @100mm

LEVEL
ROOF
RB2 200 250 Ø12mm 2 2 2 2 1@ 50mm, 8@ 75mm, REST @100mm
Lx/4 Lx-Ly/2 Lx/4

RB3 200 250 Ø12mm 4 2 2 3 1@ 50mm, 8@ 75mm, REST @100mm

LEVEL
2B1 250 300 Ø16mm 4 2 2 2 1@ 50mm, 8@ 75mm, REST @120mm

2NDF
X2 Y2
Y1
Y1 2B2 250 300 Ø16mm 3 2 2 3 1@ 50mm, 8@ 75mm, REST @120mm
Lx

Lx

FTB 200 300 Ø16mm 4 2 2 4 1@ 50mm, 8@ 75mm, REST @120mm


Y3 Y2

X1 X3 X1 X2
4 CONCRETE BEAM SCHDULE
S-3 NOT TO SCALE
S-1 S-2
COLUMN SCHEDULE
LEVEL C-1
1 2NDF SLAB DETAIL 250mm

2ND FLOOR LEVEL


S-3 NOT TO SCALE

ROOF LEVEL

300mm
TO
SLAB REINFORCEMENT
MAIN BAR:6-Ø16mm
REBAR SHORT DIRECTION - X (mm) LONG DIRECTION - Y (mm) TIES: Ø10mm
LEVEL NAME THK. DIAMETER 1@50, 8@100, REST
(mm) X1 X2 X3 X4 Y1 Y2 Y3 Y4

S-1 100 10mmØ 300 300 300 - 300 300 300 - LEVEL
@200mm TO CENTER
5 COLUMN SCHEDULE
S-3 NOT TO SCALE
LEVEL

S-2 100 10mmØ 300 300 - - 300 300 - -


2NDF

- - - - - - - -

- - - - - - - -

2 2NDF SLAB REINFORCEMENT


S-3 NOT TO SCALE

PRC REG. NO. PRC REG. NO. 0120204 DESIGNED BY : PROJECT TITLE PROJECT OWNER REVISIONS SHEET CONTENTS
NO. DESCRIPTION DATE
PTR NO. PTR NO. 4708006 DRAWN BY : PROPOSED HOUSE EXT., 2NDF SLAB DETAIL
ROBERTO NOLLORA JR ISSUED ON MS. MAUREEN DELA CRUZ DIEGO 2NDF SLAB REINFORCEMENT
PLANNER
ISSUED ON
CIVIL ENGINEER
02-24-2020 CHECKED BY : PERIMETER FENCE & GATE
BEAM DETAIL S-3
LOCATION BLOCK 15 LOT 06
ISSUED AT
T.I.N.
ISSUED AT BALIWAG BUL. APPROVED BY :
T.I.N.
PASEO DE SAN ROQUE PHASE 2
ADDRESS

BRGY. SAN ROQUE, SAN RAFAEL BULACAN


CONCRETE BEAM SCHEDULE
COLUMN SCHEDULE
6 8
411-463-424 DATE :