I FOUNDATION WORKS
Layout, Batterboards & Excavation
Site cleared from unsuitable materials and disposed of legally __________ _______________________________ _________
Boundary monuments set by Surveyor __________ _______________________________ _________
Finish elevation set __________ _______________________________ _________
Batterboard set correct to alignment and squareness __________ _______________________________ _________
Excavation dimensions checked __________ _______________________________ _________
Reinforced Concrete Wall Footings
Aggregates used __________ _______________________________ _________
Soil poisoning used, if any __________ _______________________________ _________
Rebar diameter used __________ _______________________________ _________
Rebars and spacings installed and secured __________ _______________________________ _________
Concrete design mix used __________ _______________________________ _________
Reinforced Concrete Zocalo Wall
Zocalo elevation and levelling
Rebar diameter used __________ _______________________________ _________
Rebars and spacings installed and secured __________ _______________________________ _________
Forms installed and secured __________ _______________________________ _________
Concrete design mix used __________ _______________________________ _________
Septic Vault
Excavation dimensions checked __________ _______________________________ _________
Depth of secptic tank __________ _______________________________ _________
Plastered/Waterproofed Interior of Septic Tank __________ _______________________________ _________
VA ROOF FRAMING AND TINSMITHRY
Roof Framing
Purlins protected from rust by paint (primer) __________ _______________________________ _________
Elevation set, slope correct __________ _______________________________ _________
Full welded connections __________ _______________________________ _________
Undersheeting and Roofing
Roofing materials laid correctly __________ _______________________________ _________
Roofing materials fastened mechanically __________ _______________________________ _________
Gutters secured to the building __________ _______________________________ _________
Gutters are free of debris __________ _______________________________ _________
VB MISCELLANEOUS CONCRETE
Concrete Stair Case
Rebar diameter used __________ _______________________________ _________
Rebars and spacings installed and secured __________ _______________________________ _________
Forms installed and secured __________ _______________________________ _________
Concrete design mix used __________ _______________________________ _________
Railings protected from rust by paint (primer) __________ _______________________________ _________
Railings installed plumb and level, accurately fitted and free from distortion or defects __________ _______________________________ _________
Anchors required for connecting railings to structure provided __________ _______________________________ _________
Welds grinded smooth __________ _______________________________ _________
Masonry Walls, 100mm
Rebar diameter used __________ _______________________________ _________
Rebars and spacings installed and secured __________ _______________________________ _________
Cleaned surface on which the first course is to be laid __________ _______________________________ _________
Vertical and horizontal alignment checked, any discrepancy corrected __________ _______________________________ _________
Masonry placed in horizontal courses __________ _______________________________ _________
Bed joints thickness __________ _______________________________ _________
Hollow units filled completely __________ _______________________________ _________
Drypacking
Mortar mixture used __________ _______________________________ _________
Joints filled completely __________ _______________________________ _________
I FOUNDATION WORKS
Layout, Batterboards & Excavation
Site cleared from unsuitable materials and disposed of legally XX CLEARING OF PERIMETER _______________________________
Septic Vault
Dimensions checked _______________________________ _______________________________
Depth of secptic tank _______________________________ _______________________________
Plastered/Waterproofed Interior of Septic Tank _______________________________ _______________________________
Sanitary fittings of Septic Tank _______________________________ _______________________________
II GROUND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _______________________________
GF Wall Concrete
Ground Floor Wall are aligned, smooth, and clean from crack √ PASSED _______________________________
III SECOND FLOOR SUSPENDED SLAB
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _______________________________
2F Slab Concrete
2ndf slab are aligned, smooth, and clean from crack XX _______________________________ _______________________________
IV SECOND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _______________________________
2FWall Concrete
2ndf wall are aligned, smooth, and clean from crack √ PASSED _______________________________
VB ROOFING & ACCESSORIES
Prepainted GI Roof and Accessories
Roofing materials laid correctly √ PASSED _______________________________
Roofing accessories installed correctly √ PASSED _______________________________
PVC Downspouts & Catchbasins are completely installed √ PASSED _______________________________
VC MISCELLANEOUS CONCRETE
Concrete Stair Case
Dimensions checked √ PASSED _______________________________
Concrete stair are aligned, smooth, and clean from crack √ PASSED _______________________________
RC Kitchen Counter
Dimensions checked √ PASSED _______________________________
Concrete kitchen counter are aligned, smooth, and clean from crack √ PASSED _______________________________
Concrete Pads, 100x300x1000mm
Dimensions checked √ PASSED _______________________________
Concrete pad elevation are set correctly √ PASSED _______________________________
VD MASONRY FINISHES
Exterior Steel Doors & Jambs
Steel Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _______________________________
CHB Wall Masonry/ CR Flooring
Dimensions checked √ PASSED _______________________________
Concrete kitchen counter are aligned, smooth, and clean from crack & stain √ PASSED _______________________________
Wall & Concrete Finishes
Wall finishes @ comport room are smooth and clean from crack & stain √ PASSED _______________________________
Concrete Mouldings & Canopy
Dimensions checked √ PASSED _______________________________
Concrete moulding are aligned, smooth, and clean from crack √ PASSED _______________________________
VI SLAB ON FILL
Slab-on-Fill
Slab on Grade concrete are aligned, smooth, and clean from crack & stain √ PASSED _______________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _______________________________
VII CARPENTRY
Ceilings, Eaves & Vents
Ceilings, Eaves & Vents are complete & properly installed √ PASSED _______________________________
Dry Wall Partitions(Double-walled)
Dry Wall Partitions are complete & properly installed √ PASSED _______________________________
Cabinet Doors
Dimension Check √ PASSED _______________________________
Dry Wall Partitions are complete & properly installed including Cabinet Handle √ PASSED _______________________________
Interior PVC Doors & Jambs
Interior PVC Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _______________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _______________________________
VIIIA FINISHING WORKS
Stair Railings
Dimensions checked √ PASSED _______________________________
Railings protected from rust by paint (primer) √ PASSED _______________________________
Tileworks
Page 4 of 15
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
Page 5 of 15
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
I FOUNDATION WORKS
Layout, Batterboards & Excavation
Site cleared from unsuitable materials and disposed of legally XX CLEARING OF PERIMETER PASSED
Septic Vault
Dimensions checked √ PASSED _____________________________
Depth of secptic tank √ PASSED _____________________________
Plastered/Waterproofed Interior of Septic Tank √ PASSED _____________________________
Sanitary fittings of Septic Tank √ PASSED _____________________________
II GROUND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
GF Wall Concrete
Ground Floor Wall are aligned, smooth, and clean from crack XX
√ CLEANING PASSED
III SECOND FLOOR SUSPENDED SLAB
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
2F Slab Concrete
2ndf slab are aligned, smooth, and clean from crack WITH CRACKED PASSED
IV SECOND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
2FWall Concrete
2ndf wall are aligned, smooth, and clean from crack X CORRECTING EDGE OF WALL PASSED
VB ROOFING & ACCESSORIES
Prepainted GI Roof and Accessories
Roofing materials laid correctly √ PASSED _____________________________
Roofing accessories installed correctly √ PASSED _____________________________
PVC Downspouts & Catchbasins are completely installed √ PASSED _____________________________
VC MISCELLANEOUS CONCRETE
Concrete Stair Case
Dimensions checked √ PASSED _____________________________
Concrete stair are aligned, smooth, and clean from crack √ PASSED _____________________________
RC Kitchen Counter
Dimensions checked √ PASSED _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack X NOT YET COMPLETED PASSED
Concrete Pads, 100x300x1000mm
Dimensions checked √ PASSED _____________________________
Concrete pad elevation are set correctly √ PASSED _____________________________
VD MASONRY FINISHES
Exterior Steel Doors & Jambs
Steel Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _____________________________
CHB Wall Masonry/ CR Flooring
Dimensions checked √ PASSED _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack & stain √ PASSED _____________________________
Wall & Concrete Finishes
Wall finishes @ comport room are smooth and clean from crack & stain √ PASSED _____________________________
Concrete Mouldings & Canopy
Dimensions checked √ PASSED _____________________________
Concrete moulding are aligned, smooth, and clean from crack √ PASSED _____________________________
VI SLAB ON FILL
Slab-on-Fill
Slab on Grade concrete are aligned, smooth, and clean from crack & stain X CLEANING PASSED
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
VII CARPENTRY
Ceilings, Eaves & Vents
Ceilings, Eaves & Vents are complete & properly installed √ PASSED _____________________________
Dry Wall Partitions(Double-walled)
Dry Wall Partitions are complete & properly installed √ PASSED _____________________________
Cabinet Doors
Dimension Check √ PASSED _____________________________
Dry Wall Partitions are complete & properly installed including Cabinet Handle √ PASSED _____________________________
Interior PVC Doors & Jambs
Interior PVC Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _____________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
VIIIA FINISHING WORKS
Stair Railings
Dimensions checked √ PASSED _____________________________
Railings protected from rust by paint (primer) √ PASSED _____________________________
Tileworks
Page 6 of 15
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
Page 7 of 15
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
I FOUNDATION WORKS
Layout, Batterboards & Excavation
Site cleared from unsuitable materials and disposed of legally XX CLEARING OF PERIMETER PASSED
Septic Vault
Dimensions checked √ PASSED _____________________________
Depth of secptic tank √ PASSED _____________________________
Plastered/Waterproofed Interior of Septic Tank √ PASSED _____________________________
Sanitary fittings of Septic Tank √ PASSED _____________________________
II GROUND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
GF Wall Concrete
Ground Floor Wall are aligned, smooth, and clean from crack √ PASSED _____________________________
III SECOND FLOOR SUSPENDED SLAB
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
2F Slab Concrete
2ndf slab are aligned, smooth, and clean from crack XX WITH CRACKED PASSED
IV SECOND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
2FWall Concrete
2ndf wall are aligned, smooth, and clean from crack XX CLEANING PASSED
VB ROOFING & ACCESSORIES
Prepainted GI Roof and Accessories
Roofing materials laid correctly √ PASSED _____________________________
Roofing accessories installed correctly √ PASSED _____________________________
PVC Downspouts & Catchbasins are completely installed √ PASSED _____________________________
VC MISCELLANEOUS CONCRETE
Concrete Stair Case
Dimensions checked √ PASSED _____________________________
Concrete stair are aligned, smooth, and clean from crack √ PASSED _____________________________
RC Kitchen Counter
Dimensions checked √ PASSED _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack √ PASSED _____________________________
Concrete Pads, 100x300x1000mm
Dimensions checked √ PASSED _____________________________
Concrete pad elevation are set correctly √ PASSED _____________________________
VD MASONRY FINISHES
Exterior Steel Doors & Jambs
Steel Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _____________________________
CHB Wall Masonry/ CR Flooring
Dimensions checked √ PASSED _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack & stain √ PASSED _____________________________
Wall & Concrete Finishes
Wall finishes @ comport room are smooth and clean from crack & stain √ PASSED _____________________________
Concrete Mouldings & Canopy
Dimensions checked √ PASSED _____________________________
Concrete moulding are aligned, smooth, and clean from crack √ PASSED _____________________________
VI SLAB ON FILL
Slab-on-Fill
Slab on Grade concrete are aligned, smooth, and clean from crack & stain √ PASSED _____________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
VII CARPENTRY
Ceilings, Eaves & Vents
Ceilings, Eaves & Vents are complete & properly installed √ PASSED _____________________________
Dry Wall Partitions(Double-walled)
Dry Wall Partitions are complete & properly installed √ PASSED _____________________________
Cabinet Doors
Dimension Check √ PASSED _____________________________
Cabinet doors are complete & properly installed including Cabinet Handle X NO HANDLE PASSED
Interior PVC Doors & Jambs
Interior PVC Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _____________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
VIIIA FINISHING WORKS
Stair Railings
Dimensions checked √ PASSED _____________________________
Railings protected from rust by paint (primer) √ PASSED _____________________________
Tileworks
Page 8 of 15
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
Page 9 of 15
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
I FOUNDATION WORKS
Layout, Batterboards & Excavation
Site cleared from unsuitable materials and disposed of legally XX CLEANING _____________________________
Septic Vault
Dimensions checked XX FOR VERIFICATION _____________________________
Depth of secptic tank XX FOR VERIFICATION _____________________________
Plastered/Waterproofed Interior of Septic Tank XX FOR VERIFICATION _____________________________
Sanitary fittings of Septic Tank XX FOR VERIFICATION _____________________________
II GROUND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
GF Wall Concrete
Ground Floor Wall are aligned, smooth, and clean from crack √ PASSED _____________________________
III SECOND FLOOR SUSPENDED SLAB
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
2F Slab Concrete
2ndf slab are aligned, smooth, and clean from crack XX CLEANING _____________________________
IV SECOND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
2FWall Concrete
2ndf wall are aligned, smooth, and clean from crack √ PASSED _____________________________
VB ROOFING & ACCESSORIES
Prepainted GI Roof and Accessories
Roofing materials laid correctly √ PASSED _____________________________
Roofing accessories installed correctly √ PASSED _____________________________
PVC Downspouts & Catchbasins are completely installed XX REPAINT DOWNSPOUT _____________________________
VC MISCELLANEOUS CONCRETE
Concrete Stair Case
Dimensions checked XX ADJUST MEASUREMENT OF STAIR _____________________________
Concrete stair are aligned, smooth, and clean from crack XX REMOVE STAIN & REPAINT _____________________________
RC Kitchen Counter
Dimensions checked √ PASSED _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack √ PASSED _____________________________
Kitchen cabinet door Dimensions checked √ PASSED _____________________________
Concrete kitchen Cabinet are aligned, smooth, clean and fully painted XX REPAINT CABINET JAMB _____________________________
Concrete Pads, 100x300x1000mm
Dimensions checked √ PASSED _____________________________
Concrete pad elevation are set correctly √ PASSED _____________________________
VD MASONRY FINISHES
Exterior Steel Doors & Jambs
Steel Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _____________________________
CHB Wall Masonry/ CR Flooring
Dimensions checked √ PASSED _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack & stain √ PASSED _____________________________
Wall & Concrete Finishes
Wall finishes @ comport room are smooth and clean from crack & stain √ PASSED _____________________________
Concrete Mouldings & Canopy
Dimensions checked √ PASSED _____________________________
Concrete moulding are aligned, smooth, and clean from crack √ PASSED _____________________________
VI SLAB ON FILL
Slab-on-Fill
Slab on Grade concrete are aligned, smooth, and clean from crack & stain XX CLEANING _____________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
VII CARPENTRY
Ceilings, Eaves & Vents
Ceilings, Eaves & Vents are complete & properly installed √ PASSED _____________________________
Dry Wall Partitions(Double-walled)
Dry Wall Partitions are complete & properly installed √ PASSED _____________________________
Bedroom Cabinet Doors
Dimension Check √ PASSED _____________________________
Dry Wall Partitions are complete & properly installed including Cabinet Handle XX NO CABINET HANDLE _____________________________
Interior PVC Doors & Jambs
Interior PVC Doors & Jambs are complety Installed including locksets w/o Damage √ PASSED _____________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed √ PASSED _____________________________
VIIIA FINISHING WORKS
Stair Railings
Dimensions checked √ PASSED _____________________________
Page 10 of 15
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
Page 11 of 15
60 30 30 30 30 30
ACU ACU ACU
MAIN REF RANGE
MASTER BR-1 BR-2
30 30 20 20 20 20
GF 2F GF 2F GF 2F
W.HEATER W.HEATER C/O C/O LIGHTING LIGHTING
PROMINENCE PROPERTIES INC.
Inspection Checklist and House Construction Record
I FOUNDATION WORKS
Layout, Batterboards & Excavation
Site cleared from unsuitable materials and disposed of legally X _____________________ _____________________________
Septic Vault
Dimensions checked XX _____________________ _____________________________
Depth of secptic tank XX _____________________ _____________________________
Plastered/Waterproofed Interior of Septic Tank XX _____________________ _____________________________
Sanitary fittings of Septic Tank XX _____________________ _____________________________
II GROUND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed XX
√ _____________________ _____________________________
GF Wall Concrete
Ground Floor Wall are aligned, smooth, and clean from crack XX
√ _____________________ _____________________________
III SECOND FLOOR SUSPENDED SLAB
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed XX
√ _____________________ _____________________________
2F Slab Concrete
2ndf slab are aligned, smooth, and clean from crack XX _____________________ _____________________________
IV SECOND FLOOR RC WALL
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed XX
√ _____________________ _____________________________
2FWall Concrete
2ndf wall are aligned, smooth, and clean from crack XX
√ _____________________ _____________________________
VB ROOFING & ACCESSORIES
Prepainted GI Roof and Accessories
Roofing materials laid correctly XX
√ _____________________ _____________________________
Roofing accessories installed correctly XX
√ _____________________ _____________________________
PVC Downspouts & Catchbasins are completely installed XX _____________________ _____________________________
VC MISCELLANEOUS CONCRETE
Concrete Stair Case
Dimensions checked XX _____________________ _____________________________
Concrete stair are aligned, smooth, and clean from crack XX _____________________ _____________________________
RC Kitchen Counter
Dimensions checked XX
√ _____________________ _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack XX
√ _____________________ _____________________________
Kitchen cabinet door Dimensions checked XX
√ _____________________ _____________________________
Concrete kitchen Cabinet are aligned, smooth, clean and fully painted XX _____________________ _____________________________
Concrete Pads, 100x300x1000mm
Dimensions checked XX
√ _____________________ _____________________________
Concrete pad elevation are set correctly XX
√ _____________________ _____________________________
VD MASONRY FINISHES
Exterior Steel Doors & Jambs
Steel Doors & Jambs are complety Installed including locksets w/o Damage XX
√ _____________________ _____________________________
CHB Wall Masonry/ CR Flooring
Dimensions checked XX
√ _____________________ _____________________________
Concrete kitchen counter are aligned, smooth, and clean from crack & stain XX
√ _____________________ _____________________________
Wall & Concrete Finishes
Wall finishes @ comport room are smooth and clean from crack & stain XX
√ _____________________ _____________________________
Concrete Mouldings & Canopy
Dimensions checked XX
√ _____________________ _____________________________
Concrete moulding are aligned, smooth, and clean from crack XX
√ _____________________ _____________________________
VI SLAB ON FILL
Slab-on-Fill
Slab on Grade concrete are aligned, smooth, and clean from crack & stain XX
√ _____________________ _____________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed XX
√ _____________________ _____________________________
VII CARPENTRY
Ceilings, Eaves & Vents
Ceilings, Eaves & Vents are complete & properly installed XX
√ _____________________ _____________________________
Dry Wall Partitions(Double-walled)
Dry Wall Partitions are complete & properly installed XX
√ _____________________ _____________________________
Bedroom Cabinet Doors
Dimension Check XX
√ _____________________ _____________________________
Dry Wall Partitions are complete & properly installed including Cabinet Handle XX
√ _____________________ _____________________________
Interior PVC Doors & Jambs
Interior PVC Doors & Jambs are complety Installed including locksets w/o Damage XX
√ _____________________ _____________________________
Wires & Conduits
Wires & Other rough-in electrical materials are completely installed XX
√ _____________________ _____________________________
VIIIA FINISHING WORKS
Stair Railings
Dimensions checked XX
√ _____________________ _____________________________