Module 1 - Project Task 1.

3 - Wall Systems

Part A

Reference –Project No.43324 - ELEVATION B - Ground Floor Plan

Reference - The wall has been specified as needing 9kN of Bracing. No bracing has
been installed.
Reference – 9kN/m wind force

 Write (must be typed, not handwritten) a Site Instruction to the Carpenter


describing all the errors and rectification requirements
Site instruction must include:

m

er as
o Sketch detailing the bracing you would use. This can be hand drawn or
produced electronically. Email format is acceptable.

co
eH w
o.
rs e
ou urc
o
aC s
v i y re
ed d
ar stu
sh is
Th

This study source was downloaded by 100000829148865 from CourseHero.com on 07-21-2021 07:34:57 GMT -05:00

https://www.coursehero.com/file/68711536/13-Wall-system-PART-Adocx/
Based on the span table provided above, See sketch below

m
er as
co
eH w
o.
rs e
ou urc
o
aC s
v i y re
ed d
ar stu
sh is
Th

This study source was downloaded by 100000829148865 from CourseHero.com on 07-21-2021 07:34:57 GMT -05:00

https://www.coursehero.com/file/68711536/13-Wall-system-PART-Adocx/
m
er as
co
eH w
o.
 Describe the fixings that would be required to ensure this bracing meets
rs e
the NCC requirements
ou urc
o
aC s
v i y re
ed d
ar stu
sh is
Th

This study source was downloaded by 100000829148865 from CourseHero.com on 07-21-2021 07:34:57 GMT -05:00

https://www.coursehero.com/file/68711536/13-Wall-system-PART-Adocx/
m
er as
co
eH w
Based on the example pictures above and plus using the span table “table 18 Lentils”

o.
rs e
given. It is complying with AS 1684 span tables and bracing calculations that has been
use to calculate structural adequacy.
ou urc
o

As according to the construction’s plans project no 43324, the wall is requiring a 9kN of
aC s

the wind force for the bracing to support the wall structure and to meet all the
v i y re

compliances with NCC.


ed d
ar stu
sh is

 Include key points required for the window installation once the wall frame
Th

rectification is complete
 Include key points required for the vapour permeable sarking or a waterproof
membrane

Reference - MODULE 1 -LOW RISE BUILDING - GETTING YOUR CONSTRUCTION,


CONTRACTS AND COSTS RIGHT VOLUME 2

Reference - SECTION 20: INSTALLING WINDOWS

Reference – SECTION 20.2 INSTALLATIONS

This study source was downloaded by 100000829148865 from CourseHero.com on 07-21-2021 07:34:57 GMT -05:00

https://www.coursehero.com/file/68711536/13-Wall-system-PART-Adocx/
Timber window frames require flashings under the sill to stop water migrating to the inside
wall linings. Side flashing is also necessary to prevent water migrating to the back of the
stiles. Some manufacturers provide a groove in the stile in which to tuck the flashing.

When the head of a window may be exposed to weather, such as a window in a gable wall,
the head of the window needs to be flashed to stop any water getting in.

Jambs and heads must be plumb and level. The edges should be adjusted to ensure they
are flush with the interior wall lining. When allowing for 10 mm plasterboard internal lining, a
good quality folding rule can be used. Most are 10 mm thick and so are ideal to use as a
gauge when setting a frame in position

Refer page 207

sarking will need to be used behind the timber cladding or under the flooding material to
waterproof and to direct water that might penetrated the cladding back to the outside
structure.

m
er as
co
eH w
o.
rs e
ou urc
o
aC s
v i y re
ed d
ar stu
sh is
Th

This study source was downloaded by 100000829148865 from CourseHero.com on 07-21-2021 07:34:57 GMT -05:00

https://www.coursehero.com/file/68711536/13-Wall-system-PART-Adocx/
Powered by TCPDF (www.tcpdf.org)

You might also like