Professional Documents
Culture Documents
net/publication/245282021
CITATIONS READS
8 321
6 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Monique Head on 16 July 2014.
Abstract: The performance of a new full-depth precast overhang panel system for concrete bridge decks is investigated experimentally.
In contrast to conventional cast-in-place deck overhangs, the proposed full-depth precast overhang system has the potential to speed up
construction, reduce costs, and improve safety. Load-deformation behavior up to factored design load limits is first investigated. The panel
is then loaded near its edge to examine the collapse capacity and the associated failure modes—particularly the influence of panel-to-panel
connections that exist, transverse to the bridge deck axis. Comparative tests are also conducted with a conventional cast-in-place overhang
system. When compared to the conventional cast-in-place overhang behavior, the experimental results show that the precast full-depth
overhang introduces different behavior modes, largely due to the influence of the partial depth panel-to-panel connection, which reduces
the capacity by some 13%.
DOI: 10.1061/共ASCE兲BE.1943-5592.0000098
CE Database subject headings: Bridges, concrete; Bridge decks; Prestressed concrete; Panels; Load factors.
Author keywords: Precast bridge panels; Concrete bridge overhang; Accelerated construction; Monotonic loading.
Introduction and Background deck overhang once the deck concrete has been placed and gained
sufficient strength. To address this concern, many studies have
Approximately 85% of new concrete bridge decks in the State of examined SIP precast, prestressed concrete panels with the first
Texas use stay-in-place 共SIP兲, precast, prestressed panels span- interior precast panel extended to include the overhang to elimi-
ning between adjacent beams. SIP precast panels were first used nate field forming of the overhang. Some examples include the
in the 1950s in Illinois, and became incorporated for use in other NUDECK system 共Badie et al. 1998, 1999; Yamane et al. 1998兲
states in the late 1960s and early 1970s 共Goldberg 1987兲. SIP and deck replacement using full-depth precast, concrete deck pan-
precast panels have exhibited comparable strength to conven- els with deck continuity over immediate support 共Babaei et al.
tional bridge decks, while adding value in accelerated construc- 2001兲. Moreover, full-depth, 200-mm-thick, precast panels placed
tion, increased safety, and reduced construction costs through less adjacent to one another, spanning transverse beams have also
on-site labor requirements 共Buth et al. 1972兲. Research has shown been investigated previously by Yamane et al. 共1998兲 and Fallaha
the added value of SIP concrete deck panels to be stronger, stiffer, et al. 共2004兲. These full-depth bridge decks are precast off-site,
and more crack-resistant when compared to fully cast-in-place requiring no steel placement or concrete deck placement on-site.
共CIP兲 concrete decks 共Tsui et al. 1986兲. The panels achieve shear transfer with the girders similar to the
However, construction of bridge overhangs can be a time- system developed in the research presented herein via composite
consuming, costly, and potentially dangerous operation, as the pockets with a mechanical connector 共threaded rod or stud兲. To
formwork and falsework have to be removed from beneath the achieve continuity between adjacent panels, grouted shear keys
are used in transverse joints. These shear keys are typically
1
Graduate Assistant Researcher, Zachry Dept. Civil Engineering, female-female connections 共Issa et al. 1995兲. Joints need to be
Texas A&M Univ., College Station, TX 77843-3136. designed such that grout can freely flow, while not leaking
2
Captain, U.S. Air Force; formerly, Graduate Student, Zachry Dept. through the small gap 共typically 12.5 mm兲 between adjacent pan-
Civil Engineering, Texas A&M Univ., College Station, TX. 77843-3136. els. Ideally, vertical faces of the panels must be roughened so that
3
Graduate Assistant Researcher, Zachry Dept. Civil Engineering,
sufficient bond is achieved between the panels and grout 共Issa et
Texas A&M Univ., College Station, TX 77843-3136.
4
Assistant Professor, Zachry Dept. Civil Engineering, Texas A&M al. 2003兲. Full-depth panel systems also require a finishing sur-
Univ., College Station, TX 77843-3136 共corresponding author兲. face as the grouted joints and shear pockets may cause an unac-
5 ceptable riding surface. Such a system requires a low tolerance of
Inaugural Zachry Professor I, Zachry Dept. Civil Engineering, Texas
A&M Univ., College Station, TX 77843-3136. error for precast panel construction and on-site panel placement.
6
Zachry Career Development Professor I and Division Head, Con- A disadvantage with a full-depth system is filling the shear
structed Facilities, Texas Transportation Institute, College Station, TX pockets and keys with grout. A large volume of grout is required,
77843-3136. which is a time-consuming process. Durability and strength could
Note. This manuscript was submitted on April 22, 2009; approved on
be compromised when voids are present if the grout is not cor-
December 14, 2009; published online on December 16, 2009. Discussion
period open until February 1, 2011; separate discussions must be submit- rectly placed. Therefore, serviceability of the system can be re-
ted for individual papers. This paper is part of the Journal of Bridge duced as adequate shear transfer between adjacent panels via the
Engineering, Vol. 15, No. 5, September 1, 2010. ©ASCE, ISSN 1084- shear key is imperative. Although these full-depth panel systems
0702/2010/5-503–510/$25.00. have considerable merit, they have only been adopted for field
Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
application on few occasions. Their lack of widespread use is 3 300
11
Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
PRECAST OVERHANG CONVENTIONAL OVERHANG tudinal bridge axis and 5.49 m in the transverse direction. The
setup consisted of two precast panels, 2.44 m long by 2.67 m
wide, cast adjacent to one another and placed on reinforced con-
crete beams that were supported continuously on the laboratory
(a) Prototype precast bridge deck construction showing floor. The concrete beams were rectangular, 300 mm wide, repre-
precast overhang (left) and conventional overhang (right) sentative of an AASHTO Type A girder top flange width. The
beams were 400 mm deep, sufficient to place internal reinforce-
PRECAST OVERHANG CONVENTIONAL OVERHANG
ment and fasteners while providing adequate space to place in-
200 mm strumentation on the deck soffit. Conventional precast panels
spanned the central beam and an external beam for the conven-
STAY-IN-PLACE (SIP) PANEL tional overhang system.
(b) Full-scale experimental set-up
Test Specimen Construction
Fig. 2. Basis of experimental test setup
Fig. 2共a兲 presents a cross section of the prototype bridge system
with the proposed precast, prestressed overhang on the left hand
exterior and interior overhangs. Longitudinal and transverse steel side of the bridge along with a standard conventional TxDOT CIP
is then placed on the remainder of the deck at a designated spac- overhang on the right hand side. Fig. 2共b兲 presents a cross-
ing 共15兲. A final 100-mm concrete placement 共16兲 ties the system sectional view of the experimental representation of the same two
together, after which the haunch and grout pockets are poured. A overhang systems. As these two different construction methods
thin wearing surface can be placed on the exterior bay, concealing only influence the overhang and first interior bay, the transverse
the pockets, in the shoulder area of the bridge. width of the setup can be reduced to three beams. The 2.44 m
wide by 2.67 m long prestressed panels were constructed in a
two-stage casting process at a precast plant.
Experimental Investigation The first stage concrete placement 共100 mm thick兲 for the
overhang panels was performed in the same long-line steel stress-
Two full-scale, double-panel specimens, representative of TxDOT ing bed as used for conventional SIP precast panels. The new
precast concrete bridge decks, were tested to characterize resis- overhang panels were prestressed along their length 共transverse to
tance to factored wheel loads, evaluate load-deformation behav- the bridge axis兲 with 9.5-mm diameter tendons stressed to 1,300
ior, map crack formations, and identify failure modes. Particular MPa and reinforced longitudinally with mesh providing 465 mm2
emphasis was placed on comparing the performance of the pro- of steel per meter. The second stage layer is reinforced orthotro-
posed precast overhang to the conventional CIP overhang system pically with D16 bars longitudinally at 150-mm centers, and D12
as shown in Fig. 2. bars transversely at approximately 150-mm centers. The spacing
Fig. 3 presents the overall experimental setup. Each of the two of the bars was approximate, as bars needed to be configured to fit
specimens has a footprint that measured 4.88 m along the longi- around the composite pockets. After release of the strands, the
BOTTOM STEEL
OVERHANG
C
A
A
SIP
PANEL
B B
TOP STEEL
SIP
OVERHANG
PRECAST
G
E
PANEL
Y Y D F
X
(a) Plan view of deck (d) Plan view of reinforcement details
SIP PANEL
STEEL STEEL TYPE SPACING
305 typ
A 9.5mm dia. tendons 150 mma
915 1830 1830 915
B Welded wire mesh 465 mm2/m
C D12 150 mm
(b) Section Y-Y D D12 150 mmb
E D16 150 mmc
200
F D12 150 mm
G D16 150 mm
a
Gas-cut tendons out of precast pockets once concrete is set
5490 b
Standard hook length on bars around pockets
(c) Section X-X c
Average spacing of 150mm, place around pockets
Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
Table 1. Concrete Cylinder Compression and Splitting Tensile Results
Compressive strength 共MPa兲 Tensile strength 共MPa兲
Specimen
number Component Cast date 3-day 7-day 28-day Time of test Time of test
1 Stage I February 5, 2008 29 41 55 58 6.0
1 Stage II February 8, 2008 41 50 53 62 5.5
1 SIP panel February 12, 2008 30 45 53 62 6.1
1 Deck March 28, 2008 26 45 58 59 5.5
2 Stage I January 31, 2008 37 47 60 66 5.6
2 Stage II February 5, 2008 29 41 47 52 5.2
2 SIP panel February 11, 2008 34 45 48 52 6.0
2 Lab-cast overhang April 14, 2008 32 45 55 58 4.7
2 Deck closure May 19, 2008 20 24 33 31 3.2
Note: Stage I⫽first stage pour of precast overhang panels; Stage II⫽second stage pour of precast overhang panels; and SIP Panel⫽stay-in-place panel for
interior bay.
second stage concrete placement 共100 mm thick兲 was cast on top versity. The precast panels were constructed with TxDOT Class H
of the first stage concrete. Over the panel width, there were three concrete with a specified 28-day compressive strength of 34 MPa.
full-depth rectangular pockets that provide a location for shear Type H concrete, with a specified target strength of 34 MPa, was
connectors between the panel and bridge girder 共Fig. 3兲. also used for the laboratory beams. A TxDOT Type S concrete,
with a target strength of 28 MPa, was used for the deck. Both
concrete types have a maximum water-to-cement ratio of 0.45.
Specimen Layout, Materials, and Reinforcing Details
Type S concrete has larger coarse aggregates than a type H mix
Specimen 1 was designed to provide a comparison between the 共Texas DOT 2004兲. A slump of 100 mm was specified for all
performance of the precast overhang and the conventional CIP concrete mixtures. Cylinders were cast from each concrete batch
overhang systems. The main difference in the reinforcement de- in accordance with standard practice 共see ASTM C192 Standard兲.
tails was the existence of continuous bottom prestress from the Compression tests 共according to ASTM C39兲 were conducted at
first interior girder to the overhang in the precast panel, as well as 3, 7, and 28 days after casting and at the time of testing of the test
the effect of the seam between the panels. As shown in Fig. 2共b兲 specimens. Splitting tensile tests were also conducted on the day
the specimen consisted of a conventional overhang and a precast of testing in accordance with ASTM C496. Table 1 shows the
overhang. Composite action was provided between the girder and compressive strengths of the different concretes used in the re-
precast overhang panel through the grout in the haunch and the search at 3, 7, and 28 days after casting, and also the measured
threaded rod connectors at each pocket. The conventional over- compressive strength on the day of each experiment. Splitting
hang had the customary D12 R-bar stirrups at 300-mm centers tensile strengths at the time of specimen testing are also given in
extending above the beam surface by 130 mm. Details are given Table 1. Tensile tests were also conducted to characterize the mild
in Fig. 3. steel and prestressing strands used in the panels and CIP decks.
Specimen 2 was designed and tested with the dual objective: Table 2 shows key values from the tension tests.
共1兲 to confirm the findings of the precast overhang system tested Specimens 1 and 2 had a 50-mm haunch. A high performance
on Specimen 1 and 共2兲 to investigate an alternative approach for grout was used to fill the haunch. A water-to-powder 共w/p兲 ratio
constructing full-depth overhang panels. The latter objective was of 0.19 was used for all grouts placed in the haunch area. The
achieved by constructing a conventional panel system, referred to pockets of Specimen 1 were filled with the same high perfor-
as “lab-cast” panels. This consisted of a second stage concrete mance grout except the w/p ratio was 0.16. After less than 12 h,
placement on top of a standard precast, prestressed SIP panel to after the grout placement subsidence, cracks were observed
achieve a full-depth overhang panel. The reinforcement details for around the pocket perimeter of Specimen 1. As a result of this,
this system are similar to the precast overhang system, with the TxDOT Class S concrete was used in the pockets for Specimen 2.
exception that the bottom layer of prestressing strands were re- No visible cracks were observed when concrete was placed in the
placed with conventional reinforcement. As with the conventional pockets in Specimen 2.
overhang system, D12 deformed reinforcing bars were placed at
150-mm centers. The shear connections for this system were simi-
Specimen Loading Plan
lar to the Specimen 1 connectors with the exception of the pock-
ets, which were reduced from 250⫻ 175 mm to 150-mm square Hydraulic jacks with 2,200 kN capacity were used to apply the
pockets. Smaller composite pockets allowed for the main top steel vertical loads that represent the dual wheels of a truck. The loads
over the cantilever portion to be consistently spaced at the
150-mm uniform spacing. It was anticipated that by evaluating Table 2. Stress-Strain Values for Steel Reinforcement
the lab-cast panels, information could be obtained on the effect of Yield stress Yield Strain at onset
the prestress in the bottom layer. Moreover, as the reinforcement Specimen 共MPa兲 strain of strain-hardening
details were also the same as the conventional overhang, this CIP D12 434 0.00185 0.0095
enabled the effects of the transverse seam to be investigated. CIP D16 504 0.00255 0.0140
All precast panels for the research program were fabricated at
Precast wire mesh 434 0.00215 0.0025
a precast plant, using the long-line pretensioning methods, while
Precast D12 455 0.00250 0.0055
all other specimen components were constructed in the High-Bay
Precast D16 434 0.00230 0.0025
Structural and Materials Testing Laboratory at Texas A&M Uni-
Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
250
Load Case
200
Experimental Results
Fig. 4. Loading positions for both deck specimens
For all 16 loading conditions, force-displacement data were ob-
tained based on the wheel load and the vertical displacement
below the center of the load plate. String pots were placed along
were applied via steel load plates, 75 mm thick, seated on a 12.5- the beam face to obtain the true panel deflection by allowing for
mm-thick neoprene pad 共Shore 70, similar in hardness to a tire compression and “bedding in” of the beam to the strong floor.
tread兲 over a rectangular tire footprint measuring 250 mm long by Longitudinal and transverse displacement profiles were electroni-
500 mm wide. The magnitude of the applied loads was measured cally recorded in the axis of the wheel load.
via an in-series load cell placed above the load plates. To repre-
sent the most adverse design scenarios required by the AASHTO
LRFD Bridge Design Specification 共AASHTO 2004兲, loads were AASHTO Overhang Seam Load
placed on the concrete deck surface at various locations on the Both precast overhang panel setups and lab-cast panels behaved
deck, as shown in Fig. 4. in a similar fashion for Load Cases 1.1, 1.4, 2.1, and 2.5. For the
Fig. 4共a兲 presents the load cases tested on Specimen 1. Load precast overhang, some hairline cracks were only observed at
Cases 1.1 and 1.2 are the required AASHTO factored load at the loads of 267 kN at the seam above the exterior beam face. The
longitudinal midpoint 共or seam兲, and the longitudinal quarter- conventional overhang had three cracks on the underside of the
point 共center of a panel兲, respectively. For the overhang, this po- deck propagating from the beam face. The cracks were continu-
sitioned the center of the load plate 150 mm off the beam face, ous to the overhang free edge. Top surface cracks were observed
resulting in 50 mm of the load plate bearing over the beam. This above the beam face and along the beam centerline.
load location is referenced in Section 3.6.1.3 of the AASHTO Fig. 5 presents the results for the AASHTO overhang wheel
LRFD Bridge Design Specifications 共AASHTO 2004兲. Load Case load at the longitudinal midpoint of the bridge deck 共the
1.3 is the edge failure load, where the wheel load edge is on the transverse seam between precast panels兲. Vertical displacements
edge of the panel. This may be representative of a crash load, with obtained were small, with the largest displacement being approxi-
an increased moment due to the overturning force from the barrier mately 0.3 mm, corresponding to a slab transverse rotation of
resistance. The shear force will be the same as the AASHTO 0.002 radians at the beam face.
required load point; however, a greater moment at the beam face
makes it more critical. Load Cases 1.4 and 1.5 are similar to 1.1
AASHTO Overhang Midpanel „Quarter Point… Loads
and 1.2, while Load Case 1.6 differs from Load Case 1.3, as it is
on the seam edge. Load Case 1.7 is an axle load 共two-wheel load兲 The design AASHTO loading was applied at the longitudinal
at the midpoint of each panel. Load Case 1.8 is the interior failure quarter point of both specimens. For the precast overhang, this
load for an axle. Axle wheel loads were spaced at 1.83-m centers. corresponded to the longitudinal midpoint of a precast panel. No
Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
500
400
(b) Specimen 1 precast, prestressed overhang(Load 1.6) Fig. 7. Force-deformation for overhang failure
600
and 2.7 are shown in Fig. 7. The curves indicate that the initial
stiffness was similar for the precast panels and CIP overhang with
400
a single applied load up to approximately 133 kN. Up to approxi- Load Case
mately 200 kN the force-deformation behavior is similar for the 1.7 CIP 1.7 PC
precast and conventional overhangs loaded at the seam. For 200
1.8 CIP 1.8 PC
Specimen 1, the ultimate load capacities were 440 and 374 kN for
2.4 2.8
the CIP and precast overhangs, respectively. The 13% reduction 0
in load carrying capacity, in the full-depth precast system is at- 0 5 10 15 20 25
tributed in part to the presence of the seam in the precast system. Vertical displacement (mm)
However, it should be noted that both ultimate capacities signifi-
cantly exceed the AASHTO truck load of 71 kN. Fig. 8. Force-deformation for interior failure cases
Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
Table 3. Peak Loads and Factors of Safety for Tested Double-Panel Bridge Deck System
Peak wheel load Reserve capacity factor
Load case Description 共kN兲 共ultimate/load factor兲
Exterior
1.3 Conventional midspecimen edge load 440 2.20
1.6 Precast overhang seam edge load 374 1.40
2.3 Precast overhang trailing wheel load 360 1.35
2.7 Lab-cast overhang seam edge load 302 1.13
Interior
1.8 Interior trailing axle load midpoint 859 3.22
2.4 Precast interior trailing wheel single panel 565 2.12
2.8 Lab-cast interior trailing wheel straddling seam 667 2.50
Note: 200 kN design load= wheel load+ multiple presence factor+ live load+ impact factor 33%; and 267 kN design load= wheel load+ multiple
presence factor+ live load+ impact factor 75% for joints.
Discussion load is within 4.5 kN of the single wheel seam load, the stiffness
was reduced for this load case. A folding mechanism along the
Results from the overhang tests indicate that the precast overhang beam face was observed, resulting in larger ultimate vertical dis-
system exhibits sufficient capacity for a 900-mm overhang. placements of 20 mm compared to 12 mm for the singular seam
Table 3 lists the observed load factors 共factors of safety兲 obtained load.
from the double-panel testing. Note that these are only for the
capacity of the precast overhang system, not the bridge as a
whole. The 13% decrease in carrying capacity in the precast over- Conclusions
hang panel compared to the conventional overhang cannot be
solely attributed to the seam. First, it should be noted that al- Based on the results from the two full-scale double-panel speci-
though constructed to be similar, the properties of the materials mens, the following conclusions can be drawn:
used in the two overhangs were different. The yield stress of 1. The concept of using conventional SIP panels and a precast
the D16 top transverse reinforcing steel bars was 504 MPa for overhang panel to construct a concrete deck system was veri-
the CIP overhang compared to 434 MPa in the precast overhang. fied. Current AASHTO-based designs have substantial re-
Second, the precast system had a considerably smaller posi- serve strength over the required AASHTO design factored
tive moment in the longitudinal direction at the seam 共M y loads. In spite of minor 共13%兲 weakening being introduced
= 25.6 kN-m/ m for precast and M y = 81.8 kN-m/ m for CIP兲. via the transverse panel-to-panel seam, the full-depth, pre-
This was due to the conventional overhang using bottom longitu- stressed precast panels also showed sufficient strength in
dinal D16 steel reinforcement while the precast side used a both interior and exterior bays.
welded wire mesh of R10 rounded bars providing 465 mm2 of 2. Overhang failure loads were made critical by loading at the
steel per meter. edge of the panel and seam joint. It is evident that the intro-
A further reduction in ultimate capacity was observed when duction of the seam decreases the overall strength, but only
loading the lab-cast overhang when compared with the pre- the bottom longitudinal steel is discontinuous. Nevertheless,
stressed precast overhang. The effect of transverse prestressing in some positive 共and negative兲 moment strength is still pro-
the lower half of the precast overhang is small in the negative vided due to the CIP panel-to-panel joint that has a single
moment overhang region. The main contribution in strength is layer of C-bars. Although this is weaker than the full-depth
from the top transverse D16 steel in this region. Reduction in the overhang, the overall reduction of load carrying capacity is
ultimate capacity in the lab-cast specimen was likely due to the only some 13%, and based on this research is considered safe
bottom reinforcement layout. The D16 steel reinforcing bars were for general implementation.
designed and placed to mimic the conventional section and not 3. Under normal service loads 共including overloads兲, the stiff-
the steel mesh used in the prestressed precast overhang panels. ness of the full-depth precast-prestressed panels was compa-
The development length of the reinforcing thus increases at the rable to the conventional CIP decks. Under normal service
transverse seam where the steel is terminated in each panel. loads deck cracking should not be expected.
Strength is compromised as the D16 bars are not developed
within the failure plane of the lab-cast panels. Due to the increase
in development length there is effectively no positive reinforce- Acknowledgments
ment in the longitudinal direction 共M y = 0 kN-m/ m兲 at the point
of failure. An increase in strength would be expected, had the D16 This research was conducted under a contract from TxDOT
reinforcing bars had standard hook length, or a mesh had been to TTI 共Project 0-46100兲 in collaboration with Dr. Tyler Ley of
used in the lab-cast panels. Oklahoma State University. Dr. Ley provided the initial design
Greater ductility was observed in the precast overhang panel for the precast panels. This support is gratefully acknowledged.
when compared to the conventional panel and lab-cast systems. The research team also acknowledges the assistance of Ricardo
In terms of total loads on a panel, Load Case 2.3, which repre- Gonzalez, TxDOT project director, Graham Bettis, Ralph
sented trailing wheels on a single panel, does not appear to ad- Browne, Loyl Bussell, Robert Cochran, Lewis Gamboa, John
versely affect the ultimate capacity. Although the ultimate failure Holt, Michael Hyzack, Manuel Padron, and Alfredo Valles, all
Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
project advisors from TxDOT. The findings and opinions are 145-3, Texas Transportation Institute, College Station, Tex.
those of the writers. Fallaha, S., Sun, C., Lafferty, M., and Tadros, M. 共2004兲. “High perfor-
mance precast concrete NUDECK panel system for Nebraska’s sky-
line bridge.” PCI J., 49共5兲, 40–50.
References Goldberg, D. 共1987兲. “Precast prestressed concrete bridge deck panels.”
PCI J., 32共2兲, 26–45.
Issa, M., Idriss, A., Kaspar, I., and Khayyat, S. 共1995兲. “Full-depth pre-
AASHTO. 共2004兲. LRFD bridge design specifications, 3rd Ed., Washing-
cast, prestressed concrete bridge deck panels.” PCI J., 40共1兲, 74–85.
ton, D.C.
Issa, M., Riberio do Valle, C. L., Abdalla, H. A., and Islam, S. 共2003兲.
Babaei, K., Fouladgar, A., and Nicholson, R. T. 共2001兲. “Nighttime
“Performance of transverse joint grout materials in full-depth precast
bridge deck replacement with full depth precast concrete panels at
concrete bridge deck systems.” PCI J., 48共4兲, 92–103.
Route 7 over Route 50, Fairfax County, Virginia.” Transportation
Texas DOT. 共2004兲. “Standard specifications for construction and main-
Research Board, 80th Annual Meeting, Transportation Research
Board, Washington, D.C. tenance of highways, streets and bridges.” Item 421, Austin, Tex.,
Badie, S. S., Baishya, M. C., and Tadros, M. K. 共1998兲. “NUDECK-An 516–535.
efficient and economical precast bridge deck system.” PCI J., 43共5兲, Tsui, C. K., Burns, N. H., and Klinger, R. E. 共1986兲. “Behavior of
56–74. Ontario-type bridge deck on steel girders: Negative moment region
Badie, S. S., Baishya, M. C., and Tadros, M. K. 共1999兲. “Innovative and load capacity.” Center for Transportation Research Rep. 350-3,
bridge panel system a success: Concrete international 共CI兲.” J. Am. Univ. of Texas at Austin, Austin, Tex.
Concr. Inst., 21共6兲, 51–54. Yamane, T., Tadros, M., Badie, S., and Baishya, M. 共1998兲. “Full depth
Buth, E., Furr, H. L., and Jones, H. L. 共1972兲. “Evaluation of a pre- precast, prestressed concrete bridge deck system.” PCI J., 43共3兲, 50–
stressed panel, cast-in-place concrete bridge.” TxDOT Research Rep. 66.
View publication stats Downloaded 25 Jan 2011 to 118.97.186.66. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org