You are on page 1of 127

By : Ir Lee Wei Thiam

1
AGENDA FOR TODAY

2
3
Sydney Opera House

4
J-Cube, Singapore

5
KL Tower

6
JKR HQ Block G

7
Taylor’s Lake Side Campus, Sunway

8
Micron Project, Singapore

9
Public Building

10
Commercial Building
11
Industrial Building
12
Highrise Residential Building

13
Carpark

14
WHAT IS PRECAST CONCRETE SYSTEM

15
WHAT ARE THE OBJECTIVES TO ACHIEVE
USING PRECAST CONCRETE SYSTEM?

16
PRECAST CONCRETE COMPONENTS FOR BUILDINGS

Precast Beams

Loading bearing Wall Precast Columns 17


PRECAST CONCRETE COMPONENTS FOR BUILDINGS

Hollow Core Slabs Double Tee Slabs

Precast Half Slabs Planks


18
PRECAST CONCRETE COMPONENTS FOR BUILDINGS

Pile Cap & Socket Waffle Slab

Staircases 19
20

End of Part 1
21
INSTALLATION

PRODUCTION

DESIGN

22
1. Modular Coordination in Precast Building
2. Structural Building System Used
3. Building Stability
4. Structural Ties
5. Floor Diaphargm Action
6. Precast Hollow Core Slab Design
7. Precast Beam Design
8. Precast Column Design
9. Example
10. Typical Connection
23
24
 MS 1064: PART 10:2001
 Modular grids
 Modular sizes

25
 Grid Layout

Insert layout and section

26
 Vertical Grid

27
 Modular grids
 Preferred plan grid dimension to be 10M –
120M at increment of 3M.
I.e: 6000mm, 7200mm, 8400m, 9600mm, etc
 Preferred vertical grid dimension to be 28M –
36M at increment of 1M and 36M – 48M at
increment of 3M.
I.e: 2800mm, 3600mm, 3900mm, 4200mm, etc

*Note: M is the symbol for the basic module defined in


MS 1064: Part 1 and having the value of 100mm
28
29
 Unbraced Skeletal Frame System
 Braced Skeletal Frame System
 Bearing Wall Frame System
 Hybrid System

30
 Precast Column
 Precast Beam
 Precast Slab
 Unbraced
 Rigid joint

31
 Precast Column
 Precast Beam
 Precast Slab
 Precast wall/ In-situ
Stabalizing frame
 Pinned joint

32
 Precast Wall
 Precast Beam
 Precast Slab

33
 Precast slab with in-situ concrete
column and beam
 Precast beam, precast slab with in-situ
concrete column
 Precast slab with steel beam and
column
 Precast slab with masonry wall

34
35
36
37
 Design for progressive collapse
 Peripheral Ties
 Internal Ties
 Column and Wall Horizontal Ties
 Vertical Ties

38
39
40
 Horizontal loads on the structure are
transmitted to the vertical stabilising
core, shear walls, structural frames or
bracings, etc by the floors and roofs
which act as rigid horizontal diaphragm

41
42
43
44
Wind: wk = 1.0 kPa
Floor to floor: H = 3.6m
wd = 1.4*1.0 kPa*3.6m = 5.0 kN/m
Span: L = 72m
Width of building:B = 19.2m
Topping concrete:t = 75mm

Moment: Md = w*L2/8 = 3240 kNm


Lever arm: z = 0.8*B = 0.8*19.2m = 15.4m
Reinforcement: As = M/(z*0.95*fy) = 481 mm2
2 T 20 at beam top

Shear: Vd = wd*L/2 = 180 kN


Concrete shear stress: vc = Vd/(t*B) = 0.13 MPa

45
46
 Simply supported for ultimate condition

 Continuous for service condition

 Design Loading : Live Load & Super

Imposed Dead Load

 Normally with 75mm thick concrete topping

 Seating(Normally 75~150mm)

 9.6mm(S) & 12.9mm(M) dia strands

 Class 2 design
47
48
49
50
51
52
53
54
55
56
OPENINGS
FOR
HOLLOW
CORE
SLAB

57
HANGER FOR
HOLLOW CORE
SLAB

58
X
• Avoid Notches
• Introduce Beam Wider
than Column 59
60
 2 stage design

 Reinforced concrete beam (Propped)

 Reinforced concrete beam (Unpropped)

 Prestressed concrete beam (Propped)

 Prestressed concrete beam (Unpropped)

 Continuous spans (half beam)

 Simply supported spans (full beam)

61
Installation Stage

Final Stage

62
63
64
65
66
 Braced column
 Unbraced column
 Reinforced concrete column
 Single Tier or Multi Tier
 Corbel support

67
68
69
70
71
Single Tier Column Two Tier Column

72
73
Step 1: Column Positioning
74
Step 2: Framing of precast
beam
75
Step 3: Framing of precast slab
76
77
78
Column - Foundation Joint
GROUTED SLEEVE
JOINT

 Most commonly
used and most
economical

 Design as a moment
resisting joint

79
Column – Foundation Joint
SOCKET CONNECTION

 Economical solution if
foundation design can
accommodate the pocket
projection

 Easy to install

 Design as a moment
resisting joint

80
Column – Foundation Joint
COLUMN SHOE CONNECTION

 Easy to install and


temporary propping not
required

 Less economical

 Commonly designed as a
pinned joint

81
Column - Beam Support
CORBEL CONNECTION
(continuous)

82
Column - Beam Support
CORBEL CONNECTION
(pinned)

83
For Column - Beam Support
CONCEALED STEEL PLATE
CONNECTION

84
Column - Beam Support
PINNED CONNECTION

Beam simply
supported on
column head fixed
with dowel bars

85
HOLLOW CORE SLAB – CONCRETE BEAM
CONNECTION

Concrete topping
with a layer of wire
mesh and negative
bars.

86
HOLLWOC CORE SLAB WITH STEEL BEAM
CONNECTION

Concrete topping
with a layer of wire
mesh and negative
bars.

87
HOLLOW CORE SLAB WITH LOAD BEARING WALL
CONNECTION

88
HOLLOW CORE SLAB WITH MASONRY WALL
CONNECTION

89
 Simplify
 Simplify
 Simplify

90
1. Simplify framing layout
2. Standardise types of elements
3. Simplify connection details
4. Avoid notches for precast slab
5. Minimum size for precast elements
6. Use modular sizes
7. Cost

91
92
93
TENSION

COMPRESSION

???

94
95

End of Part 2
96
Production

• Production of Precast Elements


– Shop Drawings
– Production Planning
– Production Schedule
– Production Facilities
– Stock Yard
– Delivery

97
Precast Concrete Production
Long line prestressing – indoor

Casting Hollow core slabs

98
Precast Concrete Production
Long line prestressing – outdoor

99
Precast Concrete Production
RC precasting – both indoor & outdoor

100
Transports

Cargo Trailer Pole Trailer

Platform Trailer Low Bed Trailer


101
Transports

V-Frame Trailer

102
Transports

Transportation Consideration
• Type of lorry used (Cargo, Pole Trailer, Flat Bed, Low Bed, etc)
• Planning of route
• Size of precast elements (Normal cargo lorry is 2.4m width and
12m length)
• Loading/ unloading time (Day or Night delivery)
• Number of trips required
• Site access condition
• The condition on internal site access
• Unloading area at site

103
104

End of Part 3
105
SITE OPERATIONS

• Precast Site Planning Consideration


• Sequence of Work
• Site Access
• Crane Planning
• Transportation to Site
• Other Cast In-situ Associated Works
• Integration With Other Trades

106
SITE OPERATIONS

• Sequence of Installation
– Floor by Floor
– Pyramid
– Zone by zone
– Critical Zones
– Starting Point & Finishing Point

107
SITE OPERATIONS
APRIL SEQUENCE OF WORK

MAY

108
SITE OPERATIONS
• Crane Planning
• Type of Cranes
• Number of Cranes Required
• Weight of PC Components
• Crane Coverage
• Crane Capacity
• Crane Access/ Path
• Trailer Access
• Closing of Access
109
SITE OPERATIONS

Crawler Crane

110
SITE OPERATIONS

Crawler Tower Crane

111
SITE OPERATIONS

Tower Crane

112
SITE OPERATIONS

Mobile Crane

113
SITE OPERATIONS

114
SITE OPERATIONS

Crane Path 115


SITE OPERATIONS

• Cast In-situ Related Works


• Fixing of beam top reinforcement
• Beam topping concrete
• Fixing of topping reinforcement
• Laying of mesh reinforcement
• Slab topping concrete
• Other items
116
SITE OPERATIONS

117
SITE OPERATIONS

118
SITE OPERATIONS

• Integration with Other Trades


• Roof Truss Contractor
• Façade Contractor
• M&E Contractor
• Finishing Contractor
• Etc.

119
SITE OPERATIONS

120
SITE OPERATIONS

• Site Safety
• Policy Statement and Procedures
• Manpower [training & PPE]
• Equipment [approved]
• Monitoring [enforcement]
• Maintenance [equipment & access]

121
SITE OPERATIONS
• PPE, Walkie Talkie

• Tool box meeting

122
SITE OPERATIONS

Site Access

Poor access condition


Good access condition precaution 123
SITE OPERATIONS

124
End of Part 4

125
Page 126
Contact:

w: www.epmsb.com.my

e : info@epmsb.com.my

t: +603 7980 2728

Page 127

You might also like