1.

0 INSTALLATION OF SELF SUPPORTING COMMUNICATION TOWER IN SHAH ALAM


DURATION
TASK
(DAYS)

1.1 DESIGN
1.1.1 Project Kick Off Meeting 3
1.1.2 Preparation of programme submittal 14
1.1.3 Review meeting 1
1.1.4 Cost analysis 7
1.1.5 Cost estimation 3
1.1.6 Substructure Design 30
1.1.7 Superstructure Design 30
1.1.8 Submission to Local Authority 1

1.2 SUPPLY
1.2.1 Pre Construction Meeting 3
1.2.2 Quantity Taking Off 7
1.2.3 Making order 7
1.2.4 Supply segment/element 21
1.2.5 Quality checking 7

1.3 INSTALLATION
1.3.1 Foundation construction 21
1.3.2 Electrical Services 7
1.3.3 Perform wrough work 7
1.3.4 Installation 21
1.3.5 Finishing 7
ER IN SHAH ALAM

COST (RM)

1000
3000
1000
5000
1000
5000
15000
2000

3000
10000
30000
100000
7000

25000
15000
20000
20000
10000