Project : PROPOSED IRRIGATION SYSTEM

Location : BRGY. NAPU BADOC, ILOCOS NORTE


Owner : DEPARTMENT OF AGRICULTURE
Subject : Planned Direct Manpower Requirement (CIVIL WORKS)

ITEM DESCRIPTION UOM Total Qty Marginal Planned Qty Per Hr Manhour/Unit Marginal Planned Person Manpower Description Qty Labor Cost Total Amount

1.0 Supervision Team 8.00 4.00


Project Manager 1
Site Engineer 1
Foreman 1
Leadman 1

1.0 Formworks sq.m 158.71 80.00 2.54 5.00


Skilled 3
Helper 2

2.0 Rebar kgs 6422.67 80.00 0.07 6.00


Skilled 4
Helper 2

3.0 Concreting/ Stone works cu.m 311.44 80.00 8.54 10.00


Skilled 6
Helper 4

4.0 Tinsmithry( welding works)


16.00 40-50 2.00
Skilled 1
Helper 1
TOTAL MANPOWER 27.00

Prepared by:

Princess Joan Ulit


Site Engineer/Estimator

Noted by:

Project Manager