Professional Documents
Culture Documents
TM
Delivering distributed,
utility-scale, renewable energy
TM
The hydroEngine
01 Introduction Index 02
TM
TM
The hydroEngine
The hydroEngine
03 Operation Operating envelope 04
How the hydroEngine™ works SLH system rated capacity
65.6 20
net head
16.4 5
13.1 4 10 kW CURRENT
PRODUCT:
SLH100-L
9.8 3
6.6 2
TM
TM
The hydroEngine
The hydroEngine
Head measurment
head example
18 Tot stream flow
flow [cms]
10
for your site yet.
0.9 6
yes SLH100 flow
2
0.8 Head loss estimate Net head = 4 m SLH10 flow
0% 25% 50% 75% 100%
We have not developed % of time flow exceeded
0.7 is 2 m < hn < 18 m ? no
Efficiency, / *
Flow, Q/Q*
Data quantity
flow 40
30
6.6
9.5
6.6
9.5
70
100
0.8
1
152.3
250.2
133,379
219,158
20 11.5 9.6 100 1 252.6 221,258
Figure 3 Have you collected Please, gather as 10 13.7 9.6 100 1 252.6 221,258
no
TM
TM
a minimum of a full much data as possible. 0 18.8 9.6 100 1 252.6 221,257
The hydroEngine
The hydroEngine
season of data? 5-10 seasons are ideal. Annual energy generated: 1,016,309
T
Data frequency Q/Q* = unit flow/unit flow at best efficiency point
he hydroEngineTM maintains high efficiency At certain heads (see Figure 3), the machine : efficiency = derived from efficiency curve
h/ *
across a wide range of operating flows. is capable of operating at flow rates up to 120% the Do you have daily no Please, gather as P: power = * g * hnet * Qu
or weekly flow much data as possible. E: energy = P * time
peak-efficiency flow rate. At these larger flow rates, data? Daily to weekly data = x x x
h/ * h mech elec
Internal guidevanes, similar to wicket gates, control the engine will produce more power (and generate are ideal.
both the rate of flow while keeping efficiency high. more revenue), but the efficiency will be slightly lower yes
than its peak value.
To determine the efficiency curve of an SLH unit The example above shows a site with a maximum
at a particular site, the above figure can be utilized.
Peak hydraulic efficiency is about 78%.
The flow rate can also be reduced to a value as low as
20% of peak-efficiency flow before the efficiency falls
below 60% of its peak value.
D etermining the correct size and number of
hydroEnginesTM for each project starts with
determining the flow and head duration curves for
flow of 600 cfs (17 m3/s cms). The flow duration curve
for the site, represented by the “Total Available Flow”
line, was constructed from several years of historical
Using its internal guidevanes, the engine can the site in question. This data is input into a model flow data, and for this example, the head is constant
modulate flow rates to values both greater than which optimizes the power generated versus because the site is in a regulated water canal. This site
and less than the peak-efficiency flow rate (Q*). investment required. has adequate flow to take 1 SLH100.
07 A water-to-wire offering 08
Equipment and weight
Control Panel
Gearbox
Generator
Items included
Penstock SLH
Intake Adaptor Figure 5
Items included in water-to-wire package Items not included Available Engineering services
Hydro‐mechanical equipment Instrumentation and control equipment The following items are not included in the Supplier • Penstock and draft tube optimization analysis
TM
TM
The hydroEngine
• SLH hydroEngineTM, including: • Local plant electrical and control panel
The hydroEngine
• Plant layout
• Construction of weir or dam, powerhouse
- Removable lid
• SCADA plant remote‐control system (hardware and any associated civil works
- Removable cassette module SLH100-L
and software) allowing access to the following:
- SLH case • Furnishing and delivering of gates (except wicket COMPONENT KG LB
- hydroEngineTM, including remote startup gate), stop logs, and trash racks
• Intake adapter Intake Adapter ** 1,270 2,800
and shutdown
• Intake adapter flange • Furnishing and delivering of main transformers SLH Cassette 2,800 6,173
- Intake and bypass gates, and water level
• Gearing - Utility interconnect • Furnishing and delivering of overhead traveling SLH Total 4,300 9,480
• Hydraulic power unit and pressure supply system cranes Gearbox 1,050 2,300
• Special assembly tools • Sensors integrated into control system:
• Construction of temporary facilities and Generator 1,640 3,600
- hydroEngineTM tachometer services including electric power, communication Draft Tube TBD*
Electrical equipment - Hydraulic pressure facilities, water supply, sanitary facilities,
* Based on material
- Water level, upstream and downstream construction camp, etc.
• Generator ** Actual mass depends on pipe dia
- Water static pressure
• Switchgear • Penstock and draft tube
- Vibration Table 2
09 Typical plant layout 10
Configuring the hydroEngine™ system for your site
B 617 15,677
• Draft tube outlet must be submerged at all times
C 138 3,494
of expected operation. It is recommended to
D 169 4,300
submerge the upper edge of the draft tube * Minimum Clear Height
outlet a minimum of 12 inches, or 1/4 draft tube E 43 1,100
= 0.25*J if cassette removed to the side.
outlet height, below the lower pool surface. ≥ 1.25*J if cassette removed vertically. F 87 2,200
G 63 1,600
Side View SLH100
The hydroEngine™ allows for reduction in civil H 49 1,240
works cost because it is not at risk for cavitation.
Minimum J 104 2,650
TM
TM
The hydroEngine
K 535 13,600
The hydroEngine
above the lower pool, reducing the need for Draft tube can be shorter
Inlet L 52 1,322
excavation. In addition, the hydroEngineTM H
than shown
Submergence
can be placed in a small vault, with all control Shut-off gate Ø pipe K M ≥ (5 · L · E) / (L + E)
≥ ø Pipe
G
and electrical equipment on a higher floor, J Table 4
further reducing civil works costs (figure 7).
10° Draft tube can be positioned Outlet
at angles other than shown Submergence
≥ 12”
L M
Figure 7 Figure 6
In Pipeline
Types of site
SLH100-L
11 The SLH can be easily installed in low-pressure pipeline
in mm 12
A See Table #3
settings. For example, it can be integrated as an energy-
recovery device in parallel with pressure-reducing valves. B 169 4,300 Installing the hydroEngine™
For the most efficient performance, the divergence angle C 87 2,200 in constructed or natural waterways
on the engine’s outlet should not exceed 10 degrees. E 63 1,600
F 49 1,240
914 mm
G 104 2,650
T Run of river
[36”]
he hydroEngine™ can be integrated into any kind
Table 5
of low head hydropower setting, including in-
conduit, run-of-river, in-dam, and directly in pipelines. dam, weir, or
drop structure
16.7°
B
Where possible, the run-of-river approach is favored,
C 10° as it provides inherently more protection from debris,
allows straightforward maintenance when necessary,
Access envelope: 3 ft clearance from the machine in each direction.
and has less impact on the main water channel during
In case of multiple installations the clearance is reduced.
A construction. trash rack
Note: PTO position can be mirrored
about flow centerline and SLH shaft axis
E For any application except for in-pipe flows, it is
pipe SLH draft tube
D critical to properly design the plant trashrack to
F
screen debris, while minimizing maintenance and
ø Pipe
head losses. Placing the trashrack at an angle to the In-dam
main stream flow, as illustrated in Figure 10, can allow
Figure 8 most floating debris to passively bypass the plant.
The trashrack can be additionally protected by an dam
upstream float or boom.
Generator options Figure 9
TM
TM
The hydroEngine
The hydroEngine
Gearbox
Generator
Gearbox SLH Gearbox Generator SLH trash rack SLH draft tube
Drop structures and check-drop structures represent
SLH ideal opportunities for energy recovery. Power plants
Gearbox
Generator built on irrigation drops with Natel hydroEngines™
SLH
Generator
generate clean energy and profits with only small In pipe
modifications to the existing infrastructure.
pressure reducing valve
SLH
Generator
pipe SLH draft tube
Figure 10
13 Grid interconnection Plant safety 14
Grid-connected induction Ensuring safe operations
generator hydroelectric station for man and machine
TM
TM
TVSS1
flow rate, using its adjustable guidevanes. Under
The hydroEngine
The hydroEngine
Life cycle Debris management and water quality gates or valves, inspect all surfaces for fouling and A chainfall or similar type of hoist can be utilized
clean or apply countermeasures as necessary, ensure to remove the cassette for maintenance that
The SLH system is designed for a 20-25 year Large, rigid debris should be passively bypassed with
plant ingress and egress in good condition, ensure cannot be performed in-situ.
project life with regularly scheduled maintenance on good plant design, or screened out of the intake with
plant maintenance equipment such as hoists are
the powertrain every 3 to 5 years, depending on a trashrack. Abrasive particulates should be settled
in good operating condition).
the capacity factor of the specific project. prior to the hydroEngine™ intake. Cavitation
The main power transmission belts inside the The hydroEngineTM is not at risk of cavitation when
For sites with high debris loading, and risk of debris applied in its normal range of operation. This
Materials of construction hydroEngine™, along with the wear faces of the main
entrainment within the hydroEngine™, the upstream improves long term maintenance and operation,
shaft seals, are designed for a 15,000 hour life at
Submersible components in the hydroEngine™ cascade of guidevanes will be kept clean by an and provides good environmental performance.
full load. For a plant with a 50% capacity factor and
are composed of galvanically compatible, corrosion automatic cleaning rake module, which physically
running at full rated head, this works out to a overhaul
resistant materials with high fatigue strength. removes any foreign objects which might become
interval of about 3.5 years. Temperature changes
For example, most structural components are entrained on the leading edges. The moving blades
manufactured from 304, 316, or 17-4PH within the hydroEngine™ are self-cleaning, as the The hydroEngineTM has been designed to
All moving components in the hydroEngine™ are
stainless steels. blades’ leading edges become their trailing edges accommodate a wide range of temperature
contained in an easily-removed cassette module.
once per revolution. fluctuations. Water temperatures can range from
Figure 13 To access the cassette module, the hydroEngine’s™
sideplates and cover plate are removed. freezing up to 80F (27C) with no deleterious
The hydroEngine™ is capable of operating impact on operations.
in brackish water.
Figure 14
Maintenance
TM
(annual) inspection and periodic overhauls, to keep
TM
The hydroEngine
The hydroEngine
1.77 atm
TM
TM
The hydroEngine
The hydroEngine
1 atm
0.42 atm
Contact us
980
880
Oakland
e
ub
St T
be
y Tu
ter
bs
e
Pos
We
Alameda
Ma
in
Monarch St.
St.
Constitution Way
Webster St.
W Tower Ave
Natel
Energy Atlantic Ave
TM
Pacific Ave
Tel. 510.342.5269
www.natelenergy.com
info@natelenergy.com
v8- Oct2014