You are on page 1of 11

COST PLANNING

TOPIC4
DCQ5212 CONSTRUCTION ECONOMICS
PREPARED BY: NURUL
AQILAH IBRAHIM
POLITEKNIK SULTAN AZLAN SHAH

QIL/PKK/2016
REFER:
CONSTRUCTION ECONOMICS
2nd EDITION
By KHAIRANI HJ AHMAD

COST PLANNING (refer pg 43)

•The use of the term “cost planning” starts from the inception
stage of the project until the project is handed over to the
construction.
•The post contract is known as cost control stage.
•It is quite common that the terms cost planning and cost control
overlap and is used simultaneously.
QIL/PKK/2016
REFER:
CONSTRUCTION ECONOMICS
2nd EDITION
By KHAIRANI HJ AHMAD

COST PLANNING (refer pg 43)

•It is a system that requires total coordination of the project from


its commencement to completion.
•It involves a systematic framework procedure and demands high
commitment from the design team to cooperate with the QS to
ensure that the objectives in terms of cost, time and quality are
achieved
QIL/PKK/2016
A GOOD COST PLANNING SHOULD:

•Ensure the tender figure is as close as possible to the first


estimate, or that any likely differences between the two is
anticipated and within an acceptable range
•Ensure that the funds available for the project are allocated
effectively and economically to the various elements and sub-
elements
•Always involve the measurement and pricing of approximate qty
at some stages of the process
•Aim to achieve good value at the desired level of expenditure
QIL/PKK/2016
PURPOSE OF COST PLANNING

1. Ensuring the client receive 2. Ensuring both the client


value for money, not and designer are aware of
necessarily lower than the the implications of their
initial cost. There must be a decision on cost.
balance between quality, 3. Providing advice to the
Usage suitability, initial cost designer to enable him to
and life-cycle-cost for the design within the budget.
entire lifespan of the element. QIL/PKK/2016
PURPOSE OF COST PLANNING

4. To ensure the tender sum 5. A reasonable expenditure


could be within the budget of between sections of the
the client. This will avoid building by relating the
project being aborted. design and specification to
the client’s budget so that a
more balanced design is
obtained.
QIL/PKK/2016
In addition, cost planning is important to control building cost at
the design stages. The Tender cost should be lower than the
planning cost.

•This ensure that client and the •Budget and value accountability
design team knew the design of •Improved relationships between all
proposed building within cost limit. project participants
•Greater satisfaction with end •Design problems identified and solved
results earlier
•Better value for money •Early identification of high-cost
•Improved building quality and elements
performance
QIL/PKK/2016
METHODS IN COST PLANNING

1.Elemental cost planning 2. Comparison cost planning


- Cost Planning by Element - Cost Planning by Comparatively
- Cost Target Plan - Cost to Design
- Design to Cost

QIL/PKK/2016
QIL/PKK/2016
ELEMENTAL COST PLANNING

It is a system of cost planning Elemental cost planning is


& cost control, typically for often referred to as 'designing
buildings; which enables the to a cost' or 'target cost
cost of a scheme to be planning' since a cost limit is
monitored during design fixed for the scheme and the
development. architect must then prepare a
design not to exceed this cost.
QIL/PKK/2016
COMPARATIVE COST PLANNING
•Different design will give different cost implication

•The object is to achieve economy of •Also known as ‘pricing according to


design by investigating a range of design’, where cost plan are prepared
design according to the design that have
•Proposals and establishing a been made/selected.
combination of element designs •Usually, architect will design more
which best meet the clients than one alternative to meet the
réquirements for standard etc. client requirement.
QIL/PKK/2016

You might also like