Professional Documents
Culture Documents
Introduction
Oil and gas projects are some of the most technically complex engineering
challenges undertaken in modern history and yet despite the intense focus on
delivering such projects, many have not delivered the expected return on investment.
Stepping forward from the previous article, this article highlights the areas where
production chemistry is required to integrate into the overall engineering design and
furthermore identifies some examples of the pitfalls and consequences of not doing
so.
Project production chemists are often assigned as “system owners” and provide the
functional specification of assigned packages. Working closely with various
disciplines, including reservoir, process, pipeline and flow assurance disciplines,
production chemists need the competence and technical authority to confirm the
technical requirements and the personal authority and interpersonal skills to ensure
their recommendations are understood and delivered correctly. This is especially
pertinent given the modular approach to project construction and geographical
remoteness, eg: topsides fabrication in SE Asia.
Furthermore, with onshore and offshore commissioning a critical part of the project
phase, additional expertise and knowledge is required to develop key programs and
procedures with relevant vendors and contractors. Onsite supervision in the yard or
offshore is essential to ensure that work is executed correctly.
The following table offers an overview of the role of the production chemist along
with key objectives during the project execution stages of a development, including
some of the interfaces with other engineering disciplines.
System Role of the Produc on Chemist Key Objec ves and Opera onal Impact
Establishes policies, procedures and Supports process op misa on, eg: chemical
prac ces for the monitoring and residuals for treatment e cacy and provides uid
Data Colla on and Repor ng
repor ng of opera onal data for composi onal data for scal and technical
internal and external stakeholders. repor ng.
fl
ti
ti
ti
ti
ti
ti
ti
ft
fi
ti
ti
ti
ti
ff
ti
fl
ti
ti
ti
ff
ti
ff
ti
ti
ti
ti
fi
fi
ti
ti
ti
ti
ti
ti
ti
fi
ti
ffl
ffi
ti
ti
ti
ti
ff
fl
fi
ti
ti
fi
ti
ti
ft
ti
ti
fl
• Concept Select and FEED: Key decisions made during concept select and front
end engineering design can have a significant bearing on production efficiency,
operating costs and overall operability. Cost benefit analysis is often undertaken to
broker decisions using limited information and assumptions.
(i) Failure to identify a suitable wax inhibitor along with limited oil assay analysis
and flow assurance leading to rapid waxing and subsequent blockage of an
infield pipeline during early operations.
(ii) Failure to install suitable water capillary string within the umbilical design and
production string limiting the ability to mitigate salt / halite build up within the
wellbore, resulting in costly well interventions to re-establish gas production.
• Detailed Design: The correct location, orientation and design of chemical injection
points is essential to achieve effective and efficient treatment. This is particularly
true in gas handling systems where the addition of liquid chemicals such as H2S
scavenger has production-impacting consequences. Get this wrong and you not
only fail to meet a gas export specification but this may also result in additional
problems elsewhere in the facility.
(iii) Downstream scaling from unspent H2S scavenger within produced water
treatment facilities, due to poorly located and configured chemical injection
points.
(iv) Splitting of flow downstream of an injection point along with poor piping
design resulting in variable performance due to heterogeneous chemical
distribution and treatment, eg: coagulant application upstream of filter
vessels.
(vii) Failure to commission biocide facilities for water injection ahead of first oil
leading to premature souring of the reservoir with significant operational
implications. The biocide facilities were not considered critical for first oil.
(viii) Failure to manage dehydration facilities and monitor gas export quality on an
offshore facility leading to increased water content within the export pipeline
and subsequent hydrate formation and full bore plug.
(ix) Poor control over water / contaminants entering an oil pipeline export system
leading to premature corrosion at the hot end of the pipeline and furthermore
a detrimental impact on water treatment facilities at the (downstream)
pipeline reception facilities.
It is also worth noting that often the Production Chemist is one of the few disciplines
that on completion of the project role, migrates to operations support. With that
ongoing responsibility, the advice is, better do it right in the project than live with a
lifetime of pain in operations.
Continuing our short summary series, future articles will be on the following:
James Johnstone is a Chartered Scien st, recognised Produc on Chemistry Technical Authority and
a cer ed Lead Auditor in Asset Management. With 30 years diverse experience from Field
Chemist to Senior Consultant, he delivers services of produc on enhancement, infrastructure
integrity, and ow assurance globally to operators of both conven onal and unconven onal
assets.
In addi on, he has led a number of high-value contract delivery teams including a successful track-
record in contract recovery and reten on, enhancing value to both company and client.
Recognised as a subject ma er expert by the Society Petroleum Engineers (SPE), he sits on Global
HSE & Sustainability and Water Handling Technical Commi ees and the Governing Awards
Standing Subcommi ee.
ti
ti
fi
fl
tt
tt
ti
ti
ti
tt
ti
ti
t
ti