Professional Documents
Culture Documents
~anbiganbapan
Quezon City
FOURTH DIVISION
Promulgated on:
DECISION
•
JACINTO, J:
offense in relation to his official duty and taking advantage of his official
position, conspiring and confederating together with accused Allan D. Yaphokun,
contractor and owner of Yap Mabuhay Enterprises, Inc., through evident bad
faith, did then and there willfully, unlawfully and feloniously cause the violation
of the provisions of the Contract of Agreement for Water Development at the
Municipal Development Project at Barangay Benitez entered on March 19, 2001
by and between Yap Mabuhay Enterprises and the Municipality of Banga, by
undertaking an unapproved variation order which downgraded the project's
standard resulting to the use of substandard materials and submitting an
inspection report which is over the actual accomplishment causing the
unwarranted stoppage of the project thereby causing undue injury to the
municipal government of Banga, South Cotabato in the amount of more or less
P651,373.40.
CONTRARY LA W.2
The People's case is built on the testimonies of four (4) witnesses: (1)
Vicenta A. Cagang;' State Auditor III at the Provincial Auditor's Office in
Koronadal City; (2) Engr. Claro Fernando," Registered Agricultural
Engineer; (3) Isidro .Ianita," Municipal Mayor of Banga, South Cotabato;
and, (4) Engr. Eduardo Leafio," Regional Manager of the National Housing
Authority (NHA) Region XIII, whose testimonies were summarized by the
trial court accordingly:
The filing of the cases against the accused stemmed or originated from
the letter of Mayor lsidro J. Janita, the Mayor of Banga, South Cotabato, dated,
October 23, 200 I which was referred to the Provincial Auditor of the province of
South Cotabato by the Director Ill, Assistant Director, Commission on Audit,
Davao City under CPL-MlN-O 1-273. The Provincial Auditor upon receipt of said
referral, Nenita F. Servafiez, State Auditor IV and the Provincial Auditor issued a
PAO Special A udit Office Order No. 2002-00 I dated, June 3, 2002 directing Ms.
Vicenta G. Cagang, State Auditor III to conduct the necessary audit/investigation
on the alleged unfinished projects mentioned in the letter of Mayor Janita.
Ms. Viceuta G. Cagang conducted the audit and investigation as she was
directed and submitted the result of it to the Regional Legal and Adjudication
Cluster Director, Commission on Audit, Regional Office No. XII, Davao City on
December 12, 2002. Her findings and recommendation regarding the
construction of the Water Development at the Municipal Resettlement Project at
Benitez, Banga, South Cotabato, the subject of Criminal Case No. 4650-B are as
follows:
r
cheaper materials than specified, the municipal engineer,
--
Original Plan Implemented
_Wideflange W8x28 column 6" dia B.I. Pipe
COMPUTATIONS:
Foundation
Material Cost: 3. P23,254.60
l.abor Cost: 8,500.00
4. P31,654.60
27% OCM 8,546.74
VAT 850.00
5. P41,051.34
P 115,OOO.00/200=575/FTx 80 FT = 80,500.00
It is clear from the evidence of the prosecution that what has been
allegedly awarded to Yap Mabuhay Enterprises, lnc, was the construction of the
Water Development at the Municipal Resettlement Project at barangay Benitez,
Banga, South Cotabato worth P926,720 and as shown by the Contract of
Agreement (exhibit "A"), the works that are to be done are those mentioned in
the work description, as follows:
The Contract and Agreement does not provide the period on how long
will the construction take place up to its completion. Mrs. Cagang however in her
audit and investigation report said that when she conducted said audit and
investigation in the months of from June 4, 2002 the construction of said project
had stopped.
xxx xxx xx
rr
DECISION
People of the Philippines v. Jerome B. Rendon
SB-J6-AlR-OOOl (Crirn. Case No. 4S60-B)
Page 5 of 15
As shown by the above assignment of the funds, P962,464.27 was for the
construction 0 f the Water system, P83 7.535.73 for the construction of the
drainage system (not subject of the cases) or for a total of PI,800,0.00. After the
projects were bidded, the construction of the water system was awarded to Yap
Mabuhay Enterprises, Inc. for a winning bid of P926,nO.00 and the construction
of the drainage system to Glynn Construction and Supply also for a winning bid
7
of P81 0,633.00.
On 4 November 2009, plaintiff rested its case with the filing of its
formal offer of evidence." In an Order dated 14 April 2010,10 the Court
admitted all its documentary exhibits, save for Exh. "P ," for lack of proper
identification during trial.
Specific to Crim. Case No. 4560-B, appellant testified in his
defense.11 The essence of his testimony, as found by the trial court, may be
summarized as follows:
\0 Id., p. 178.
11 TSN, 19 February 20 I0, 5 March 20 I0, and 17 January 2011.
t
DECISION
People of the Philippines v. Jerome B. Rendon
SB-16-A/R-000I (Crim. Case No. 4560-B)
Page 6 of 15
Accused, Jerome Rendon admitted the fact that he revised and altered the
plan for the construction of the Water System. He altered it for allegedly the
materials that are to be used in the construction are not available locally or even
in General Santos City. His revision of the plan was not however approved by
NHA and did not ask its approval. He likewise admitted to have recommended
on April 4, 200 I a 52.88% work completion for which the total amount
P651,373.40 including mobilization fee were paid the contractor.
On 16 February 2011, appellant rested his case with the filing of his
formal offer of evidence.13 All his documentary exhibits were admitted, save
for Exh. "11," which according to the court a quo "does not exist in the list
of exhibits offered.,,14
Upon the evidence submitted by the parties, the court a quo rendered
the assailed Joint Decision, the dispositive portion of which reads:
In Criminal Case No. 4560-B, the court finds the evidence (sic) of the
prosecution as against accused, Allan Yaphockun Iikewise insufficient and
wanting to criminally declare him responsible as he is charged. Said accused is
also hereby "ACQUITTED" and the bail bond posted for his provisional liberty
is likewise cancelled and returned to his bondsman.
Consequently, accused
Jerome Rendon Y Bangonon is found
"GUILTY" beyond reasonable doubt of violating Section 3( e) of R.A. 3019 and
is hereby sentenced to undergo the penalty of imprisonment of SIX (6) YEARS
and ONE (I) rvl0NTH, the minimum penalty provided by law which the court
12
IJ
Joint Decision, p. 19; Rollo, p. 62.
Records, Vol.l, SB-16-A/R-OOOl, pp. 215-219.
14 Order dated 16 March 201 I.
t
DECISION
People of the Philippines v. Jerome B. Rendon
SB-16-A/R-000l (Crim. Case No. 4560-B)
Page 7 of 15
SO ORDERED. IS
It is from the said judgment that accused has interposed the present
appeal based on the following assignment of errors:
On the other hand, the appellee argues that the trial court did not err in
finding appellant gu ilty beyond reasonable doubt of violation of Sec. 3(e) of
R.A. No. 3019.
--------.-
15
hereby declared la be unlawful:
3. That his action caused undue lnJury to any party, including the
government, or giving any private party unwarranted benefits,
advantage or preference in the discharge of his functions. 19
First Element
Second Element
Appellant is accused of having acted with evident bad faith, which has
been defined by the Supreme Court as follows:20 '
A simple reading of the text shows that the law pertains to a detailed
engineering plan and the basic requirements for the same. It does not refer to
project implementation, but indicates the need for such a plan prior to
--------.-
22
23
Id.
G.R. No. 169251,20
--
...
December 2006.
r
DECISION
People of the Philippines v. Jerome B. Rendon
SB-16-A/R-000l (Crim. Case No. 4560-B)
Page 10 of 15
disparity between the preconstruction plans used for purposes of bidding and the
"as staked plans" or construction drawings prepared after a joint survey by the
contract and the government after the award of the contract. THE
ADDITIONIDELETION OF WORKS SHOULD BE WITHIN THE
GENERAL SCOPE OF THE PROJECT AS BID AND AWARDED. A
VARIATION ORDER MAY EITHER BE IN THE FORM OF A CHANGE
ORDER, EXTRA WORK ORDER OR A SUPPLEMENTAL
AGREEMENT.
________ o· _
24 Which provides: "Section 9. Change Order and Extra Work Order. A change order or extra work order
may be issued only for works necessary for the completion of the project and, therefore, shall be within the
general scope of the contract as bidded and awarded. All change orders and extra work orders shall be
subject to the approval of the Minister of Public Works, Transportation and Communications, the Minister
of Public Highway" or the Min ister of Energy, as the CO" may be." (
DECISION
People of the Philippines v. Jerome B. Rendon
SB-16-A/R-OOOI (Crirn. Case No. 4560-B)
Page 11 of 15
a. Where there are additional works needed and necessary for the
completion improvement or protection of the project which were not
inc luded as items of work in the original contract.
b. Where there are subsurface or latent physical conditions at the site
dif.ering materially from those indicated in the contract.
c. Where there are unknown physical conditions at the site of an
1II111sllalnature differing materially from those ordinarily encountered
and generally recognized as inherent in the work or character
provided for in the contract.
d. Where there are duly approved construction drawing or any
instruction issued by the implementing office/agency during the term
of contract which involve extra cost.
5. Change Orders or Extra Work Orders may be issued on a contract upon the
approval of competent authorities provided that the cumulative amount of such
Change Orders or Extra Work Orders does not exceed the limits of the former's
authority to approve original contracts.
r
Director of office/agency/corporation concerned.
DECISION
People of the Philippines v. Jerome B. Rendon
SB-16-NR-000I (Crim. Case No. 4560-B)
Page 12 of 15 .
d. If, after review of the plans, quantities and estimated unit cost of
the items of work involved, the proper office/agency/corporation
committee empowered to review and evaluate Change Order, Extra
Work Order or Supplemental Agreements recommends approval
thereof the head of office//agency/corporation, believe the Change
Order, Extra Work Order or Supplemental Agreement to be in order,
shall approve the same. The limits of approving authority for any
individual, and the aggregate of, Change Orders, Extra Work Orders or
Supplemental Agreements for any project of the head of
office/agency/corporation shall not be greater than those granted for an
original project.
The law and IRR are clear-cut as to the process by which variation
orders may be legally approved. They likewise unmistakably provide that
variations in materials pertain to increase or decrease in quantity not quality
- as in this case - unless a change in field conditions justifies additional
work items to be accomplished. /
---------_._--
r
25 Emphases in the original.
DECISION
People of the Philippines v. Jerome B. Rendon
SB-16-A/R-000l (Crim. Case No. 4560-B)
Page 13 of15
Third Element
There are 1'1\/0 modes of violating Section 3(e) of R.A. No. 3019: (1)
by causing undue injury to a private individual or the Government, or (2) by
giving unwarranted benefits to another. As noted earlier, appellant is being
charged under the f rst mode.
SO ORDERED. ...
BA YA . JACINTO
As ociate Justice
WE CONCUR:
RE~.aCRUZ
Associate Justice / Associate Justice
Chairperson
ATTESTATION
I attest that the conclusions in the above Decision had been reached in
consultation with the Justices of the Court's Division.
~~.
Associate Justice
Chairperson, Fourth Division
DECISION
People of the Philippines v. Jerome B. Rendon
SB-16-A/R-000l (Crim. Case No. 4560-B)
Page 15 of 15
CERTIFICATION
"l-AlltllV ustice