Professional Documents
Culture Documents
MINISTRY OF COMMUNICATIONS
GENERAL SPECIFICATIONS
FOR
ROAD AND BRIDGE CONSTRUCTION
November 1998
PART THREE
AGGREGATE SUBBASE AND BASE COURSES
PART THREE
AGGREGATE SUBBASE AND BASE COURSES
TABLE OF CONTENTS
Requirements set forth herein shall apply whether the source be ledge rock, talus,
gravel, sand, or a combination thereof.
3.01.2 MATERIALS.
3.01.2.1 Sources. Materials sources may be shown on the plans, described in the
special specifications, or established by the Contractor after approval by the Engineer.
The Contractor shall furnish the Engineer, not less than thirty (30) days prior to the
scheduled date for beginning crushing operations, information on the source of
aggregates, the method of production to be employed, types and capacity of equipment
to be used and a schedule showing rates of production for the several types of
aggregate to be produced.
Whether or not the materials sources are shown on the plans, specified in the
special specifications, or established by the Contractor after approval by the Engineer,
the Contractor shall determine for himself the types and numbers of equipment and
extent of work needed to remove overburden and produce the volumes of aggregates
required for the work within the contract time, and produce aggregates having the
fracture, gradation and quality conforming to the specifications.
The Engineer may require procurement of aggregate from any portion of a source
and may reject portions of the source as being unacceptable.
3.01.2.2 Definitions.
3. Crushed stone consists of rock and stone fragments or gravel having one (1)
or more mechanically fractured faces. Every fractured face shall have a minimum
dimension from edge to edge across the fractured face which is not less than one-third
(1/3) the minimum dimension of the aggregate particle.
1
MOC General Specifications – November 1998
5. Sand consists of aggregate particles passing a 4.75 millimeter (No. 4) sieve and
retained on a 0.075 millimeter (No. 200) sieve and may be naturally occurring,
manufactured or combinations thereof.
6. Material passing a 0.075 mm (No. 200) sieve may be referred to as silt or clay
or dust depending on other characteristics.
3.01.3.1 Preparation of Site. The portion of the quarry or pit site to be used shall
be cleared and grubbed as specified in Section 2.01, "Clearing and Grubbing" in these
General Specifications.
When clearing and grubbing is completed, all surface materials which are
unsatisfactory for the kind of aggregate to be produced shall be stripped and removed.
Materials from clearing, grubbing and stripping which are removed as unsatisfactory
for producing specified aggregates shall be disposed of at locations not visible from the
roadway, in a manner that precludes erosion by wind or water and the form and
contours of the finished disposal area blends with adjacent terrain.
The costs involved in preparing the site, clearing, grubbing, stripping and removing
overburden and other operations shall be incidental to the production of aggregate and
shall be included by the Contractor in the contract unit price for the specific aggregate
produced.
When the percent fracture and other requirements cannot be obtained by using the
natural material, portions of the material may be rejected to the extent necessary to
produce aggregates conforming to the requirements of the specifications.
Rejected materials may be used in other portions of the work and locations when it
conforms to the specified requirements for said other portions and locations.
2
MOC General Specifications – November 1998
Washing and reclaiming of rejected material and subsequent addition to any finished
aggregate shall not be allowed unless authorized in writing by the Engineer.
When producing screened gravel or sand materials, the Contractor shall remove all
oversize material by screening at the source. Operations at the source shall be such
that the grading of aggregates in each hauling unit is reasonably uniform within
tolerances that are specified for individual materials. The Contractor shall use the most
suitable materials available at the source. He shall move his loading equipment as
many times as may be necessary to fulfill these requirements.
3
MOC General Specifications – November 1998
3.01.4.2 Preliminary Testing. The Contractor shall submit to the Engineer all
results of testing as may be necessary to confirm that the source of materials,
equipment and production methods to be employed by the Contractor will produce
aggregates conforming to the requirements of the specifications. No installation of
equipment or production shall start at any materials source until the Engineer has
approved the source, and the dimensions of the area to be excavated. The equipment
and methods proposed by the Contractor shall also be approved by the Engineer.
The approval of the Engineer shall not be construed as final acceptance of the
aggregate to be produced.
3.01.4.3 Production Testing. The Contractor shall arrange all testing necessary
to control specified aggregate fracture, gradation and quality during production as
specified in Paragraphs 3.02.5.1, 3.03.5.1 and 3.04.8 all entitled "Contractor Quality
Control Procedures" in these General Specifications. The results of such testing shall
be promptly delivered to the Engineer. Such test results are intended to be used to
guide the Contractor operations and shall not be used to infer that the aggregates being
produced are acceptable and in conformance to the specifications.
3.01.5.1 Sites. The site for constructing stockpiles shall be approved by the
Engineer and located in a manner that the stockpiled materials will not be contaminated
with other aggregates or altered by dust, dune sand or other natural or processed
material. Stockpiling on private property shall be permitted with the written consent of
the owner or lessee. The Engineer shall be afforded access to the stockpiled materials
at all times.
4
MOC General Specifications – November 1998
Stockpiles in excess of two hundred (200) cubic meters shall be built up in layers not
more than one and one-half (1.5) meters in depth using methods and equipment
approved by the Engineer. Pushing aggregate into a stockpile using dozers will not be
permitted. Each layer shall be completed over the entire area of the pile before
depositing aggregate in the succeeding layer. Any method of placing aggregate in a
stockpile which, in the opinion of the Engineer, results in segregation, breaks, degrades
or otherwise damages the aggregate will not be permitted.
When removing aggregate from stockpiles, the removal equipment shall be operated
in such a manner as to face-load from the floor to the top of the stockpile to obtain
maximum uniformity of aggregate.
The Contractor shall remove only such aggregate quantities as are necessary to
complete work under the contract.
3.01.5.5 Site Cleanup. If a surplus remains in the stockpile, the Contractor shall
leave said surplus in neat, regular shaped piles, free of foreign matter and equipment.
3.01.7 PAYMENT. Full compensation for performing all of the work specified in this
section shall be considered as subsidiary to other items of work appearing in the Bill of
Quantities unless otherwise provided for in the Special Specifications and listed in the
Bill of Quantities.
5
MOC General Specifications – November 1998
3.02.2 MATERIALS. Aggregate used for aggregate subbase shall be free from
vegetation matter and other deleterious substances and, when compacted under
watering and rolling, form a firm, stable subbase. Coarse aggregate shall be crushed
stone, crushed slag, or crushed gravel. Fine aggregate, material passing the 4.75 mm
(No. 14) sieve, shall consist of natural or crushed sand and fine material particles.
The Contractor shall furnish, produce, stockpile, blend and mix all necessary
materials using such equipment and procedures as will produce specified aggregate
subbase. Aggregate shall conform to one of the following grading and quality
requirements on the road bed after all blending and mixing and spreading and before
compacting:
TABLE 3.02-1
AGGREGATE SUBBASES GRADATION REQUIREMENTS - MTDTM 204
25 mm (1 inch) - 55-85
6
MOC General Specifications – November 1998
QUALITY REQUIREMENTS
Sand Equivalent (MRDTM 313) 25 Min.
Plasticity Index (MRDTM 208) 6 Max.
Abrasion Loss (MRDTM 309) 50 Max.
California Bearing Ratio (CBR) 50 Min.
(MRDTM 213)
Aggregate for Grading III aggregate subbase shall conform to the requirements
specified in the Special Specifications.
3.02.3.1 Job Mix Design Proposal. A proposed Job Mix Formula (JMF) shall be
formulated by the Contractor and submitted to the Engineer for approval. The JMF
shall be prepared by the Contractor in precise compliance with procedures and
requirements set forth in the Materials and Research Department Manual of Materials
and Tests and all current letters issued by the Ministry of Communications.
The Contractor shall select his sources of aggregate and, after sufficient quantities
have been stockpiled or are available for use , obtain representative samples of the
materials and test to determine if they conform to the requirements of these
specifications. At least thirty (30) days before producing aggregate subbase mixtures,
the Contractor shall submit in writing to the Engineer detailed information for each mix
which he proposes to furnish. The information shall include, but not be limited to the
following:
1. The source and gradation of the aggregate for each mix to be furnished. If the
aggregate (coarse, fine, supplemental fine) is separated into two (2) or more sizes, the
information provided shall consist of gradations for all individual sizes, the proportions
of each individual size to be used, and the mathematically combined gradation for each
mix to be furnished. Such combined gradation shall meet the applicable grading
requirements shown in Subsection 3.03.2, "Materials" in these General Specifications
and show the percentage passing each of the specified sieve sizes.
2. Pertinent test data and a written certification that the aggregates to be furnished
conform to all quality requirements shown in Subsection 3.03.2, Materials in these
General Specifications.
7
MOC General Specifications – November 1998
The Engineer shall be provided access to the materials sampling and testing
operations at all times. The combined aggregate, including mineral additives, shall
conform to the approved JMF grading within the following tolerances:
9.75 mm (3/8") and larger sieves, 11 percentage points
4.75 mm (No. 4) sieve, 10 percentage points
2.36 mm (No. 8) sieve, 9 percentage points
0.300 mm (No. 50) sieve, 8 percentage points
0.075 mm (No. 200) sieve, 8 percentage points
At the same time the above information is provided, the Contractor shall supply to
the Engineer fifty (50) kilogram samples of each individual aggregate size, when used,
ten (10) kilogram samples of mineral filler and chemical admixture, all representing the
materials which the Contractor proposes to furnish.
3.02.3.2 Acceptance of Job Mix Formula. The Engineer shall review the JMF to
determine that it contains all required information. If it does not contain all required
information, it shall be returned within seven (7) days to the Contractor for further action
and resubmission by the Contractor.
If the proposed JMF contains all required information but fails to meet all the
requirements specified, it shall not be accepted by the Engineer and will be returned to
the Contractor within fourteen (14) days. The Contractor shall prepare and submit to
the Engineer a new JMF conforming to the requirements specified and propose a new
date for beginning production.
When the Engineer is satisfied that the JMF proposed by the Contractor conforms
to all the requirements of the specifications, he shall order the Contractor to construct
a minimum two hundred (200) meter long field control strip. The Engineer shall
evaluate the control strip as to its constructability and compactability and conformance
to the laboratory tested JMF. Split samples of the aggregate subbase mix for and
components raw material along with the field laboratory test results are to be sent to the
Materials and Research Departments Central Laboratory for a one (1) point check and
documentation. If the Engineer is not satisfied with the results of the control strip, he
shall state his objections in writing and request a revised JMF and a new control strip.
When the Engineer is satisfied that the JMF proposed by the Contractor conforms
to all requirements of the specifications and the control strip results are acceptable, he
will issue written acceptance to the Contractor to begin producing the mixes proposed.
Production of aggregate subbase mixes shall not begin until the Engineer has given
written acceptance of the Job Mix Formula.
Acceptance of the JMF by the Engineer does not relieve the Contractor of his
obligation to produce aggregate subbase mixes conforming to all specified
requirements.
8
MOC General Specifications – November 1998
3.02.3.3 Job Mix Formula Revisions. The Contractor shall not alter his methods
of crushing, screening, blending, or stockpiling from that used to produce materials for
the approved JMF. Changes to the JMF will not be permitted without retesting and
resubmission of a proposed (revised) JMF in accordance with all the steps in Paragraph
3.02.3.1, "Job Mix Design Proposal" in these General Specifications. Significant
changes may include, but not be limited to, changes in the amount or type of materials
rejected or wasted, changes in the amount of materials crushed, reductions in the
amount of crushed fines, changes in the amount and type of mineral filler.
Should the Contractor change his source of aggregate, he shall furnish a new job
mix design proposal and samples of materials, as described in Paragraph 3.02.3.1, "Job
Mix Design Proposal" in these General Specifications, as determined by the Engineer
to be necessary, at least twenty-one (21) days before their intended use.
At any time after the JMF is approved the Contractor may submit a new JMF for
approval by the Engineer. If the revised JMF is approved it shall become the approved
JMF.
3.02.4 EQUIPMENT. The Contractor shall furnish all necessary equipment for
production, stockpiling and hauling aggregate, preparing the subgrade and placing,
compacting, finishing and maintaining the aggregate subbase according to the minimum
type and number outlined in the contractor's detailed Program of Work as approved by
the Engineer.
Blending and mixing aggregates and adjusting the moisture content as required for
compaction shall be performed in a central mixing plant or on the grade by means that
insure uniformity.
The blended and mixed aggregates shall be placed and spread to the width and
thickness specified.
3.02.5 CONSTRUCTION.
The Contractor shall perform the following minimum types and number of tests:
1. Gradation, sand equivalent and plasticity index - One (1) test each per two
thousand (2000) cubic meters of aggregates produced but no less than one (1) test per
production day.
9
MOC General Specifications – November 1998
2. Abrasion Loss - One (1) test for the first, second and third five hundred (500)
cubic meters of aggregate produced and one (1) test for each twenty-five hundred
(2500) cubic meters thereafter.
3. CBR Value - One (1) test for each five thousand (5,000) cubic meters placed.
When test data indicate that the aggregate subbase does not conform to specified
requirements, the Contractor shall take effective action to correct his production
methods to assure that subbase aggregate will conform to all specified requirements.
Such action shall include halting production, changing the source of aggregate supply,
altering amount of aggregated scalped and rejected, increasing degree of crushing, and
revising blending and handling methods. Such material if already placed, shall be
removed and modified or replaced to produce material conforming to the specified
requirements.
The Contractor shall correct, at his own expense, any deviation from specified
elevation and compaction in the surface to receive aggregate subbase.
When surfaces to receive aggregate subbase are lower than specified, the low areas
may be filled with aggregate subbase. The volume of aggregate subbase so placed
shall not be measured for payment under any item listed in the Bill of Quantities.
Where the subbase thickness is twenty (20) centimeters or less, the aggregate
subbase may be spread and compacted in one (1) layer. Where the required thickness
is more than twenty (20) cm, the aggregate subbase shall be spread in two (2) or more
layers of approximately equal thickness.
3.02.5.4 Compacting. Each layer of subbase material, after being shaped to the
required lines and cross section, shall be compacted to a uniform density with no
individual test being less than ninety-five percent (95%) of the maximum dry unit weight
determined from MRDTM 212. Each of lot of subbase material as described in
10
MOC General Specifications – November 1998
When there are delays in constructing the remaining pavement structure over a
granular course, the compaction of the granular course shall be reverified and deficient
areas corrected or replaced to the satisfaction of the Engineer. Such corrections or
replacement shall be at the Contractor's expense.
The Contractor shall plan the work and handle the various operations so that the
least amount of water will be lost by evaporation from uncompleted surfaces. If the
Contractor delays placing or succeeding layers of material to the extent that additional
water must be applied to prevent raveling or excessive drying, the application of such
water shall be at the Contractor's expense and will not be considered as the basis for
a claim for additional compensation.
11
MOC General Specifications – November 1998
3.02.5.5 Finishing. All subbase material shall be placed, trimmed and finished in
a neat and workmanlike manner in compliance with the lines, grades and typical cross
sections shown on the plans or staked by the Engineer within the tolerances listed in
Paragraph 3.02.6.5, "Surface Tolerances" in these General Specifications.
The Engineer shall determine when the surface of the subbase is in the proper
condition to permit the placement of aggregate subbase course or the bituminous prime
and/or surfacing to be applied. The Contractor must continue to maintain the surface
of the base course, including the application of necessary water, at his expense until
such time as the bituminous prime or the subsequent layer is applied. Any additional
expense incurred by the Contractor because of delay in placing subsequent layers or
applying the bituminous prime when so permitted by the Engineer will not be considered
as the basis for a claim for additional compensation.
The Contractor may proceed with aggregate subbase work only after the methods
and procedures established in the compaction trial has been approved by the Engineer.
12
MOC General Specifications – November 1998
The Engineer shall perform or supervise the performance of all quality assurance
sampling and testing. The location of all samples and tests shall be recorded by
roadway, lane and centerline station (kilometer). Quality assurance sampling and
testing for each lot shall include:
1. Compaction
2. Thickness
5. Surface Tolerances
3.02.6.1 Compaction. The compacted density for each layer of aggregate subbase
shall be determined by the sand cone method, MRDTM 215, or by nuclear method,
MRDTM 218 using full depth penetration, at the option of the Engineer.
When the sand cone method is used, unless otherwise stated in the Special
Specifications, the tests shall be made at a minimum of five (5) randomly selected
locations in each lot.
When the nuclear method is used, unless otherwise stated in the Special
Specifications, the tests shall be made at a minimum of eight (8) randomly selected
locations in each lot. Three nuclear gauge readings shall be made at each test location
within a radius of two (2) meters. The three (3) readings shall be averaged and the
average considered to be the density for that test location.
Percent relative compaction shall be computed by comparing the average actual in-
place compacted density from the nuclear gauge or sand cone test results with the
maximum density determined by MRDTM 212. MRDTM 212 maximum density shall be
determined from samples of aggregate subbase obtained from the roadbed at a
sampling frequency of one (1) test per three (3) lots. The maximum density used for
determining percent relative compaction shall be the running average for three (3)
consecutive tests.
Any lot of aggregate subbase that has a percent relative compaction below the
minimum percent compaction specified in Paragraph 3.02.5.4, "Compacting," in these
General Specifications resulting in a reduced pay factor of 0.75 or higher determined
in accordance with Subsection 1.08.5, "Statistical Evaluation of Work for Acceptance
and Determination of Pay Factor (Value of Work)" in these General Specifications may
be accepted on the basis of a reduced payment if requested in writing by the
Contractor. Otherwise the lot shall be removed and replaced by the Contractor at his
expense. Lots that have percent relative compaction resulting in a reduced pay factor
less than 0.75 shall be removed and replaced by the contractor at his expense.
13
MOC General Specifications – November 1998
A lot shall be accepted when the average total thickness is not less than the planned
thickness.
Any lot of aggregate subbase course with an average thickness less than shown in
the plans but resulting in a reduced pay factor of 0.75 or higher determined in
accordance with Subsection 1.08.5, "Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value of Work)," in these General Specifications may be
accepted on the basis of reduced payment if requested in writing by the Contractor,
otherwise additional material shall be provided as specified in the preceding paragraph.
When the average thickness of a lot of aggregate subbase course is less than the
planned thickness by an amount resulting in a reduced pay factor below 0.75 the
Contractor, at his own expense, shall place and remix additional aggregate subbase
material with the original aggregate subbase material and recompact before new test
holes are dug.
Every sample of aggregate subbase shall be taken on a random time basis from
each uncompacted lot during each one-half ( ) day of work, or portion thereof. The
initial sample shall be randomly selected from within one and one-half (1 ) meters
either side of the centerline of and weigh at least twenty-five (25) kilograms. The initial
sample shall be thoroughly mixed and quartered to obtain a test sample weighing at
least six (6) kilograms. The test sample shall be forwarded to the project laboratory and
the aggregate gradation, and sand equivalent and plastic light determined.
When the aggregate gradation, sand equivalent or plasticity index test results for any
lot produce a reduced pay factor of 0.75 or higher determined in accordance with above
referenced Subsection 1.08.5, "Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value or Work)" in these General Specifications, the lot
may be accepted on the basis of a reduced pay factor if requested in writing by the
Contractor. Otherwise said lot shall be removed and replaced by Contractor at his
expense.
When the gradation, sand equivalent or plasticity index pay factor determined in
accordance with above referenced Subsection 1.08.5, "Statistical Evaluation of Work
for Acceptance and Determination of Pay Factor (Value or Work)" in these General
14
MOC General Specifications – November 1998
Specifications, for any lot whose pay factor is less than 0.75 the aggregate subbase
shall be removed and replaced by the Contractor at his expense.
3.02.6.4 California Bearing Ratio and Abrasion. Random samples shall be taken
and tested for California Bearing Ratio and Abrasion from the first three (3) lots and
every fifth lot thereafter unless test results indicate failure to conform to the values
specified in Subsection 3.02.2, "Materials" in these General Specifications. In such a
case, increased sampling and testing shall be performed.
3.02.6.5 Surface Tolerances. The surface layer of the aggregate subbase shall
be evaluated for compliance with the following surface tolerances:
The cross section of the finished subbase surface shall be checked by the
Contractor in the presence of the Engineer at maximum intervals of twenty-five (25)
meters and at intermediate points as directed by the Engineer. The deviation of the
elevation of the surface above the design elevation shall be not more than twenty (20)
millimeters. Deviations above the design elevation shall not result in the diminished
thickness of any subsequent pavement course. The deviation of the elevation below
the design elevation shall not be more than twenty (20) millimeters. Isolated deviations
below the design elevation shall be compensated by additional thickness of the
subsequent pavement layer. Additional cost and materials resulting from deviations
from the design elevation shall be borne by the Contractor. Contractor shall furnish all
devices necessary to check the surface, such as stringlines, straightedges, etc., and
the labor necessary to handle the task.
15
MOC General Specifications – November 1998
3.02.8 PAYMENT. Aggregate subbase shall be paid for at the contract unit price or
adjusted contract unit price per cubic meter for the aggregate subbase item(s) shown
on the plans and listed in the Bill of Quantities. Such price and payment shall be full
compensation for furnishing all materials, equipment, labor, tools and incidentals and
all other items necessary to complete the work as specified in Subsection 1.07.2,
"Scope of Payment" in these General Specifications.
When a lot of aggregate subbase course is accepted with a deficiency, the adjusted
contract unit price for said lot shall be the product of the contract unit price of aggregate
subbase, and the lowest quality and quantity pay factors specified in Subsection 3.02.6,
"Quality Assurance Procedures," in these General Specifications.
16
MOC General Specifications – November 1998
3.03.2 MATERIALS. Aggregates used for aggregate base shall be hard durable
particles or fragments free from vegetation matter and other deleterious substances
and, when compacted under watering and rolling, form a firm, stable base. Aggregate
shall consist of crushed stone, crushed slag, or crushed gravel.
Crushed stone aggregate shall contain not more than eight (8) percent, by weight,
flat, elongated, soft, or disintegrated pieces. Aggregate retained on the 2.36 mm (No.
8) sieve shall consist of stone particles of which at least ninety percent (90%), by
weight, shall have at least two (2) mechanically fractured faces.
If additional fine material, in excess of that already present in the base course
material, is necessary for correcting the gradation properties, for satisfactory bonding
of the base material, or for adjusting the material characteristics of the fraction passing
the 0.425 mm (No. 40) sieve, it shall be uniformly blended and mixed with the crushed
aggregates. Such mixing shall take place at the crusher, at an approved stationary
proportioning and mixing plant or on a traveling plant. Reworking of the base course
material in place to obtain the specified requirements shall not be permitted. The
additional fine material, if any, shall be obtained from crushing stones, gravel, or slag,
and shall be of a gradation as required to accomplish the specified gradation of the final
mixture.
Aggregate shall conform to one of the following grading and quality requirements on
the road bed after all blending and mixing and spreading and before compacting:
17
MOC General Specifications – November 1998
TABLE 3.03-1
AGGREGATE BASES
GRADING REQUIREMENTS
MRDTM 204
PERCENTAGE PASSING
SIEVE SIZES Grading I Grading II Grading III
50 mm (2 inch) 100 - -
37.5 mm (1 inch) - 100 -
25 mm (1 inch) 55-85 70-95 100
19 mm ( inch) 50-80 55-85 70-100
4.75 mm (No. 4) 30-60 30-60 35-65
0.425 mm (No. 40) 10-25 10-25 15-25
0.075 mm (No. 200) 3-10 3-10 3-10
The fraction passing the No. 200 sieve shall not exceed the fraction passing the
0.425 mm (No. 40) sieve.
QUALITY REQUIREMENTS
Sodium Sulphate Soundness (MRDTM 311), & Loss 12 Max.
Abrasion Loss (MRDTM 309) 45 Max.
Sand Equivalent (MRDTM 313) 45 Min.
Liquid Limit (MRDTM 209) 25 Max.
Plasticity Index (MRDTM 208) 6 Max.
California Bearing Ratio (MRDTM 213) Grading I 100 Min.
18
MOC General Specifications – November 1998
3.03.3.1 Job Mix Design Proposal. A proposed Job Mix Formula (JMF) shall be
formulated by the Contractor and submitted to the Engineer for approval. The JMF
shall be prepared by the Contractor in precise compliance with procedures and
requirements set forth in the Materials and Research Department Manual of Materials
and Tests and all current letters issued by the Ministry of Communications.
The Contractor shall select his sources of aggregate and, after sufficient quantities
have been stockpiled or are available for use , obtain representative samples of the
materials and test to determine if they conform to the requirements of these
specifications. At least thirty (30) days before producing aggregate base mixtures, the
Contractor shall submit in writing to the Engineer detailed information for each mix
which he proposes to furnish. The information shall include, but not be limited to the
following:
1. The source and gradation of the aggregate for each mix to be furnished. If the
aggregate (coarse, fine, supplemental fine) is separated into two (2) or more sizes, the
information provided shall consist of gradations for all individual sizes, the proportions
of each individual size to be used, and the mathematically combined gradation for each
mix to be furnished. Such combined gradation shall meet the applicable grading
requirements shown in Subsection 3.03.2 "Materials" in these General Specifications
and show the percentage passing each of the specified sieve sizes.
2. Pertinent test data and a written certification that the aggregates to be furnished
conform to all quality requirements shown in Subsection 3.03.2,"Materials" in these
General Specifications.
The Engineer shall be provided access to the materials sampling and testing
operations at all times. The combined aggregate, including mineral additives, shall
conform to the approved JMF grading within the following tolerances:
9.75 mm (3/8") and larger sieves, 9 percentage points
4.75 mm (No. 4) sieve, 8 percentage points
2.36 mm (No. 8) sieve, 7 percentage points
0.300 mm (No. 50 sieve, 6 percentage points
0.075 mm (No. 200) sieve, 4 percentage points
At the same time the above information is provided, the Contractor shall supply to
the Engineer fifty (50) kilogram samples of each individual aggregate size, when used,
ten (10) kilogram samples of mineral filler and chemical admixture, all representing the
materials which the Contractor proposes to furnish.
19
MOC General Specifications – November 1998
3.03.3.2 Acceptance of Job Mix Formula. The Engineer shall review the JMF to
determine that it contains all required information. If it does not contain all required
information, it shall be returned within seven (7) days to the Contractor for further action
and resubmission by the Contractor.
If the proposed JMF contains all required information but fails to meet all the
requirements specified, it shall not be accepted by the Engineer and will be returned to
the Contractor within fourteen (14) days. The Contractor shall prepare and submit to
the Engineer a new JMF conforming to the requirements specified and propose a new
date for beginning production.
When the Engineer is satisfied that the JMF proposed by the Contractor conforms
to all the requirements of the specifications, he shall order the Contractor to construct
a minimum two hundred (200) meter long field control strip. The Engineer shall
evaluate the control strip as to its constructability and compactability and conformance
to the laboratory tested JMF. Split samples of the aggregate base mix for and
components raw material along with the field laboratory test results are to be sent to
the Materials and Research Departments Central Laboratory for a one (1) point check
and documentation. If the Engineer is not satisfied with the results of the control strip,
he shall state his objections in writing and request a revised JMF and a new control
strip.
When the Engineer is satisfied that the JMF proposed by the Contractor conforms
to all requirements of the specifications and the control strip results are acceptable, he
will issue written acceptance to the Contractor to begin producing the mixes proposed.
Production of aggregate base mixes shall not begin until the Engineer has given
written acceptance of the Job Mix Formula.
Acceptance of the JMF by the Engineer does not relieve the Contractor of his
obligation to produce aggregate base mixes conforming to all specified requirements.
3.03.3.3 Job Mix Formula Revisions. The Contractor shall not alter his methods
of crushing, screening, blending, or stockpiling from that used to produce materials for
the approved JMF. Changes to the JMF will not be permitted without retesting and
resubmission of a proposed (revised) JMF in accordance with all the steps in
Paragraph 3.03.3.1, "Job Mix Design Proposal" in these General Specifications.
Significant changes may include, but not be limited to, changes in the amount or type
of materials rejected or wasted, changes in the amount of materials crushed, reductions
in the amount of crushed fines, changes in the amount and type of mineral filler.
Should the Contractor change his source of aggregate, he shall furnish a new job
mix design proposal and samples of materials, as described in Paragraph 3.03.3.1, "Job
Mix Design Proposal" in these General Specifications as determined by the Engineer
to be necessary, at least twenty-one (21) days before their intended use.
20
MOC General Specifications – November 1998
At any time after the JMF is approved the Contractor may submit a new JMF for
approval by the Engineer. If the revised JMF is approved it shall become the approved
JMF.
3.03.4 EQUIPMENT. The Contractor shall furnish all necessary equipment for
producing, stockpiling, moisture conditioning, and hauling aggregate, preparing the
surface on which the aggregate base will be placed, and placing, spreading,
compacting, finishing and maintaining the aggregate base in accordance with the
minimum type and number outlined in the Contractor's Program of Work as approved
by the Engineer. Blending and mixing aggregates and adjusting the moisture content
as required for compaction shall be performed in a central mixing plant.
The blended and mixed aggregates shall be placed and spread to the width and
thickness specified using approved mechanical spreading equipment. Motor graders
shall not be used for spreading.
3.03.5 CONSTRUCTION.
The Contractor shall perform the following minimum types and number of tests:
1. Gradation, sand equivalent and plasticity index - One (1) test each per one
thousand (1000) cubic meters of aggregates produced but not less than one (1) per
production day.
2. Abrasion Loss - One (1) test for first, second and third five hundred (500) cubic
meters of aggregate produced and one (1) test for each twenty-five hundred (2500)
cubic meters thereafter.
3. Percent Crushed Faces - One (1) test for each five hundred (500) meters of
aggregate produced.
4. CBR Value - One (1) test for each five thousand (5000) cubic meters.
When test data indicate that the aggregate base does not conform to specified
requirements, the Contractor shall take effective action to correct his production
methods to assure that the materials produced will conform to all specified
requirements. Such action shall include halting production, changing the source of
aggregate supply, altering amount of aggregate scalped and rejected, increasing
degree of crushing, and revising blending and handling methods.
21
MOC General Specifications – November 1998
3.03.5.3 Mixing. The aggregate and the water shall be thoroughly mixed in a twin
shaft pugmill type mixer, unless another type of mixer is approved. The amount of
water added to the aggregate shall be an amount which will provide the mixture with a
satisfactory moisture content for compaction to the specified in-place density. The rate
of flow of the water to the pugmill shall be controlled by valves or other devices which
can be easily reset when a change in the rate of flow is desirable. The water supply
system shall be equipped with a positive cut-off control which will stop the flow of water
simultaneously with any stoppage in the flow of aggregate into the pugmill.
3.03.5.5 Placing and Spreading. The mixture shall be placed on the existing
roadway, approved subgrade or approved subbase, as the case may be, in a uniform
layer or layers not exceeding fifteen (15) centimeters in compacted depth. Where the
required thickness is greater than fifteen (15) centimeters, the material shall be placed
in layers of equal thickness. However, if heavy duty vibratory compaction equipment
approved by the Engineer is used, the maximum compacted layer thickness may be
increased to twenty (20) centimeters provided test trial compaction tests indicate
compliance with these General Specifications including the following:
1. Compaction samples are taken from the entire layer including the lower part of
the increased thickness.
2. The coarse aggregates on the top of the Aggregate Base layers are not
damaged or crushed.
The increased thickness approval will be rescinded by the Engineer if more than
fifteen percent (15%) of the subsequent field density tests taken on the thicker layer
initially fail, necessitating retesting after additional compaction.
The mixture course shall be placed on the roadbed to the required width and
uncompacted thickness as follows:
2. In a sized windrow from which a paving machine or travel plant will pickup and
spread the aggregate base.
22
MOC General Specifications – November 1998
3. To protect the underlayer and to allow proper drainage, the spreading of the
base course material shall begin along the centerline on stretches with a crowned
section or on the high side of stretches with a one-way slope.
The approved spreader shall deliver the mixture in such a condition that the material
will be ready for compaction without further shaping. Unless otherwise permitted by the
Engineer, the aggregate shall be spread not more than two thousand (.2000) square
meters ahead of the rollers. Any necessary sprinkling shall be kept within this limit.
3.03.5.6 Compacting. Each layer of aggregate base material, after being shaped
to the required lines and cross section, shall be compacted to a uniform density with no
individual test being less than ninety-five percent (95%) of the maximum dry unit weight
determined from MRDTM 212. Each lot of base material as described in Subsection
3.03.6, "Quality Assurance Procedures" in these General Specifications shall have a
percent relative compaction of no less than one hundred percent (100%) of the
maximum dry unit weight determined from MRDTM 212. The aggregate base shall be
watered or dried as may be necessary to obtain a moisture content suitable for
compaction. Material which has dried prior to final compaction or which has dried and
decompacted subsequent to final compaction shall be watered and recompacted using
equipment and procedures approved by the Engineer. Should the Contractor be
unable to return the material to its original or specified condition with respect to
compaction, thickness, and surface tolerances, the Contractor shall remove the material
and reconstruct the course on a reapproved subgrade.
When there are delays in constructing the remaining pavement structure over a
granular course, the compaction of the granular course shall be reverified and deficient
areas corrected or replaced to the satisfaction of the Engineer. Such corrections or
replacement shall be at the Contractor's expense.
The Contractor shall plan the work and handle the various operations so that the
least amount of water will be lost by evaporation from uncompleted surfaces. If the
Contractor delays placing or succeeding layers of material to the extent that additional
23
MOC General Specifications – November 1998
water must be applied to prevent raveling or excessive drying, the application of such
water shall be at the Contractor's expense and will not be considered as the basis for
a claim for additional compensation.
Prior to placing a succeeding layer of granular material, the surface of the underlayer
shall be made sufficiently moist, to insure bond between the layers. The edges and
edge slopes of the base course shall be bladed or otherwise dressed to conform to the
lines and dimensions shown on the plans, and present straight, neat and workmanlike
lines and slopes as free of loose material as practicable.
3.03.5.7 Finishing. All aggregate base material shall be placed, trimmed and
finished in a neat and workmanlike manner in compliance with the lines, grades and
typical cross sections shown on the plans or staked by the Engineer.
Grade control shall be accomplished by means of grade stakes, steel pins or forms,
placed in lanes parallel to the centerline of the road and at intervals sufficiently close
to permit placing of string lines or straightedges for checking purposes.
24
MOC General Specifications – November 1998
full authority to require the suspension of all other work on the project to insure the
proper maintenance of previously compacted material.
Any damage to the base course, or any layer thereof, caused from routing of
construction or other equipment over completed stretches shall be repaired by the
Contractor at his own expense and as approved by the Engineer.
The Engineer shall determine when the surface of the base course is in the proper
condition to permit the bituminous prime and/or surfacing to be applied. The Contractor
must continue to maintain the surface of the base course, including the application of
necessary water, at his expense until such time as the bituminous prime and/or
surfacing is applied. Any additional expense incurred by the Contractor because of
delay in applying the bituminous prime and/or surfacing when so permitted by the
Engineer will not be considered as the basis for a claim for additional compensation.
The Contractor may proceed with aggregate base Work only after the methods and
procedures established in the compaction trial has been approved by the Engineer.
The Engineer shall perform or supervise the performance of all quality assurance
sampling and testing. The location of all samples and tests shall be recorded by
roadway, lane and centerline station (kilometer). Quality assurance sampling and
testing for each lot shall include:
25
MOC General Specifications – November 1998
1. Compaction
2. Thickness
5. Surface Tolerances
3.03.6.1 Compaction. The compacted density for each layer of aggregate base
shall be determined by the sand cone method, MRDTM 215, or by nuclear method,
MRDTM 218 using full depth penetration, at the option of the Engineer.
When the sand cone method is used, unless otherwise stated in the Special
Specifications, the tests shall be made at a minimum of five (5) randomly selected
locations in each lot.
When the nuclear method is used, unless otherwise stated in the Special
Specifications, the tests shall be made at a minimum of eight (8) randomly selected
locations in each lot. Three nuclear gauge readings shall be made at each test location
within a radius of two (2) meters. The three (3) readings shall be averaged and the
average considered to be the density for that test location.
Percent relative compaction shall be computed by comparing the average actual in-
place compacted density from the nuclear gauge or sand cone test results with the
maximum density determined by MRDTM 212. For example, MRDTM 212 maximum
density shall be determined from samples of aggregate base obtained from the roadbed
at a sampling frequency of one (1) test per three (3) lots. The maximum density used
for determining percent relative compaction shall be the running average for three (3)
consecutive tests.
Any lot of aggregate base that has a percent relative compaction below the minimum
percent compaction specified in Subsection 3.03.5.6, "Compacting," in these General
Specifications, resulting in a reduced pay factor of 0.75 or higher determined in
accordance with Subsection 1.08.5 "Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value of Work)" in these General Specifications may be
accepted on the basis of a reduced payment if requested in writing by the Contractor.
Otherwise the lot shall be removed and replaced by the Contractor at his expense.
Lots that have percent relative compaction resulting in a reduced pay factor less than
0.75 shall be removed and replaced by the contractor at his expense.
26
MOC General Specifications – November 1998
A lot shall be accepted when the average total thickness is not less than the plan
thickness.
Any lot of aggregate base course with an average thickness less than the plan
thickness but resulting in a reduced pay factor of 0.75 or higher determined in
accordance with Subsection 1.08.5 "Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value of Work)" in these General Specifications may be
accepted on the basis of reduced payment if requested in writing by the Contractor,
otherwise the lot shall be overlaid as specified in the preceding paragraph.
When the average thickness of a lot of aggregate base course is less than the plan
thickness by an amount resulting in a reduced pay factor below 0.75 the Contractor, at
his own expense, shall place and remix additional aggregate base material with the
original aggregate base material and recompact before new test holes are dug.
Every sample of aggregate base shall be taken on a random time basis from each
uncompacted lot during each one-half ( ) day of work, or portion thereof. The initial
sample shall be randomly selected from within one and one-half (1 ) meters either side
of the centerline of and weigh at least twenty-five (25) kilograms. The initial sample
shall be thoroughly mixed and quartered to obtain a test sample weighing at least six
(6) kilograms. The test sample shall be forwarded to the project laboratory and the
aggregate gradation, sand equivalent and plasticity index determined.
When the aggregate gradation, sand equivalent or plasticity index for any lot results
in a reduced pay factor of 0.75 or higher, determined in accordance with above
referenced Subsection 1.08.5, "Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value of Work)" in these General Specifications the lot
may be accepted on the basis of a reduced pay factor if requested in writing by the
Contractor, otherwise said lot shall be removed and replaced by Contractor at his
expenses.
When the gradation, sand equivalent or plasticity index pay factor determined in
accordance with above referenced Subsection 1.08.5, "Statistical Evaluation of Work
for Acceptance and Determination of Pay Factor (Value of Work)" in these General
Specifications for any lot is less than 0.75 the aggregate base shall be removed and
replaced by the Contractor, at his expense.
3.03.6.4 California Bearing Ratio and Abrasion. Random samples shall be taken
and tested for California Bearing Ratio and Abrasion from a minimum of the first three
(3) lots and every fifth lot thereafter unless test results indicate failure to conform to the
quality requirements specified in Subsection 3.03.2 "Materials" in these General
Specifications. In such a case, increased sampling and testing shall be performed.
27
MOC General Specifications – November 1998
3.03.6.5 Surface Tolerances. The surface layer of the aggregate base shall be
evaluated for compliance with the following surface tolerances:
1. The cross section of the finished aggregate base surface shall be checked by
the Contractor in the presence of the Engineer at maximum intervals of twenty-five (25)
meters and at intermediate points as directed by the Engineer. The deviation of the
elevation of the surface above the design elevation shall be not more than ten (10)
millimeters. Deviations above the design elevation shall not result in the diminished
thickness of any subsequent pavement course. The deviation of the elevation below
the design elevation shall not be more than ten (10) millimeters. Isolated deviations
below the design elevation shall be compensated by additional thickness of the
subsequent pavement layer. Additional cost and materials resulting from deviations
from the design elevation shall be borne by the Contractor.
2. The surface shall also be checked with a four (4) meter straightedge in all areas
of apparent roughness as directed by the Engineer. The finished surface of the base
course shall not deviate from the straightedge between any two (2) contact points more
than ten (10) millimeters when the straightedge is placed parallel to centerline or twelve
(12) millimeters when the straightedge is placed perpendicular to centerline. The
Contractor shall furnish all devices necessary to check the surface, such as stringlines,
straightedges, etc., and the labor necessary to handle the task.
28
MOC General Specifications – November 1998
3.03.8 PAYMENT. Aggregate base shall be paid for at the contract unit price or
adjusted contract unit price per cubic meter for the aggregate base item(s) shown on
the plans and listed in the Bill of Quantities. Such price and payment shall be full
compensation for furnishing all materials, equipment, labor, tools, incidentals and all
other work necessary to complete the work as specified in Subsection 1.07.2, "Scope
of Payment," in these General Specifications.
When a lot of aggregate base course is accepted with a deficiency, the adjusted
contract unit price for said lot shall be the product of the contract unit price of aggregate
base course and the lowest calculated quality and quantity pay factors specified in
Subsection 3.03.6, "Quality Assurance Procedures," in these General Specifications.
29
MOC General Specifications – November 1998
3.04.1 DESCRIPTION. This work shall consist of furnishing and placing one (1) or
more courses of a mixture of aggregate, Portland cement and water, mixing the
materials in a central plant and spreading and compacting the mixture in conformity with
the lines, grades and thickness shown on the plans all as specified or approved by the
Engineer.
3.04.2 MATERIALS.
3.04.2.2 Aggregate. Aggregate for Grading I cement treated base shall be of such
quality that when mixed with Portland cement in an amount not to exceed five percent
(5%) by weight of dry aggregate and compacted at optimum moisture content in
accordance with MRDTM 212, the compressive strength of the compacted mixture will
not be less than fifty (50) kilograms per square centimeter after seven (7) days curing
in a sealed metal container per MRDTM 528.
Aggregate for Grading II and Grading III cement treated base shall be of such quality
that when mixed with Portland cement in an amount not to exceed three and one-half
percent (3.5%) by weight of dry aggregate and compacted at optimum moisture content
in accordance with MRDTM 212, the compressive strength of the compacted mixture
will not be less than fifty (50) kilograms per square centimeter after seven (7) days
curing in a sealed metal container per MRDTM 528.
The minimum cement content for both Grading I and Grading II shall be two percent
(2%) by weight of dry aggregate. The minimum cement content for Grading III shall be
specified in the Special Specifications.
Aggregate for cement treated base, immediately prior to mixing, shall be hard,
durable, clean and free from vegetation matter and have a plasticity index no greater
than six (6). The aggregate shall be graded as follows:
30
MOC General Specifications – November 1998
3. Grading III cement treated base - Aggregate shall conform to the requirements
specified in the Special Specifications.
3.04.2.3 Water. Water for mixing shall be free of injurious quantities of oil, alkali,
vegetable matter and salt as determined by the Engineer. It shall be reasonably clear
and shall contain not more than twenty-five hundredths percent (0.25%) total solids by
weight. It shall be capable of producing the specified cement treated material strength
as confirmed by laboratory testing. Water shall be tested in accordance with MRDTM
514.
3.04.2.5 Bituminous Curing Seal. Bituminous material for curing seal shall be SS-
1h or CSS-1h conforming to Tables 4.01-3 and 4.01-4 in Section 4.01, "Bituminous
Materials," in these General Specifications.
3.04.3 MIX DESIGN. The Contractor shall select his sources of aggregate and, after
sufficient quantities have been stockpiled or are available for use, obtain representative
samples of the aggregate and test to determine if they conform to the requirements of
these specifications. At least thirty (30) days before producing cement treated base
mixtures, the Contractor shall forward to the Engineer not less than fifty (50) kilograms
of aggregate and five (5) kilograms Portland cement representing materials the
Contractor proposes to furnish. The Contractor shall also inform the Engineer of his
proposed date for beginning producing cement treated base.
The Contractor shall perform all testing required to establish the proportions of each
material to be combined to produce the cement treated base mixture. Cylinders shall
be molded in accordance with ASTM F134 and shall be cured in accordance with
MRDTM 523. Load rate application for compression testing at twenty-eight (28) days
shall be in accordance with MRDTM 528.
After completion of laboratory testing the Contractor shall submit a solid-volume mix
design to the Engineer for review. The information submitted for review shall include:
31
MOC General Specifications – November 1998
5. The compressive strength optimum moisture content and CBR test results as
they may apply.
6. Every mix design furnished by the Contractor shall be identified with a code
number.
The Contractor may submit mix designs from previous or concurrent projects where
the same materials were furnished.
The Contractor shall prepare trial batches of cement treated base mixture using
materials, mixing equipment, procedures, and batch sizes which are the same as those
to be used in the work. The number of trial batches will be established by the Engineer,
who may waive the requirements for trial batches at any time.
The Contractor shall sample and test the trial batches when requested by the
Engineer. When test results for samples from trial batches indicate the proposed mix
will not meet the specified compressive strength or CBR requirements, the Contractor
shall submit a new mix design for review.
The Contractor shall make no changes in the mix design without approval of the
Engineer. A new mix design shall be submitted for the Engineer's review any time the
Contractor proposes a change in materials or material proportions.
The Engineer's review of mix design and test information shall not be construed as
relieving the Contractor of the responsibility to provide cement treated base conforming
to the specified properties or material contents.
3.04.4 WEATHER LIMITATIONS. Cement treated base shall not be mixed or placed
when the air temperature is below five (5) degrees Celsius, or during hot weather when
the air temperature is expected to reach thirty-five (35) degrees Celsius or higher, or
during rain, sand or dust storms, unless otherwise approved by the Engineer.
3.04.5 EQUIPMENT. The Contractor shall furnish all equipment required for producing
aggregates, hauling, mixing, placing, spreading, compacting and curing the cement
treated base in accordance with the minimum type and number outlined in the
Contractor's detailed Program of Work as approved by the Engineer. Said equipment
shall include a central plant of the batch or continuous pugmill type and self-propelled
spreader boxes or finishing machines approved by the Engineer. The mixing plant shall
be capable of uniformly mixing the approved cement content within a tolerance of one-
half percent (0.5%) of the weight of dry aggregates.
32
MOC General Specifications – November 1998
treated base so placed shall not be measured for payment under any item listed in the
Bill of Quantities.
When the surface to receive cement treated base does not conform to the specified
materials quality, compaction and elevation tolerances, the Contractor shall correct all
deficiencies.
1. General Requirements - Aggregate and cement for cement treated base shall
be proportioned and mixed in a central mixing plant. The plant shall be a batch-mixing
type using revolving blades, rotary drum mixer or the continuous mixing type. The
aggregate and cement may be proportioned either by weight or volume.
Water shall be proportioned by either weight or volume and there shall be a means
by which the Engineer may readily verify the amount of water per batch, or the rate of
flow for continuous mixers. The time of the addition of water, or the points at which it is
introduced into the mixer shall be as approved by the Engineer.
The charge in the batch mixer, or the rate of feed to the continuous mixer, shall not
exceed that which will permit complete mixing of all materials.
2. Batch Mixing - The batch mixer shall be equipped with a sufficient number of
paddles of a type and arrangement which will produce a uniformly mixed batch.
The mixer shall be equipped with a timing device accurate to within two (2) seconds
which will indicate, by definite audible or visual signal, the expiration of the mixing
period.
The timing of mixing a batch shall begin after all ingredients are in the mixer and
shall end when the mixer is half emptied. Mixing shall continue until a homogeneous
mixture of uniformly distributed and properly coated aggregate of uniform appearance
is produced. The time of mixing shall not be less than thirty (30) seconds.
A control system shall be provided that will automatically halt plant operation when
the material in any storage facility approaches the strike-off capacity of the feed gate.
The plant will not be allowed to operate unless this automatic control is in good working
condition. Storage facilities containing fine aggregate shall be equipped with a vibrating
unit which will effectively vibrate the side walls of the feeder.
33
MOC General Specifications – November 1998
The cement feeder and aggregate feeders shall be equipped with a device by which
the rate of feed can be accurately determined while the plant is in full operation.
Each type of mixing plant shall be equipped with sampling facilities approved by the
Engineer. The sampling facilities shall allow for the convenient and safe collection of
representative samples of aggregate, cement and cement treated base mixture.
3.04.6.3 Transporting and Spreading. The cement treated base mixture shall be
transported in a manner that does not cause segregation and, when required by the
Engineer, shall be protected against moisture loss by approved covers. The mixture
shall be deposited on the roadbed at a quantity per linear meter which will provide the
compacted thickness for the width being spread without resorting to spotting, picking
up or otherwise shifting the mix.
The mixture shall be spread on the roadbed in one (1) operation with a self-propelled
mechanical spreader at a quantity per linear meter which will provide the compacted
thickness without further shaping, spotting or otherwise shifting the mix. Equipment not
propelled by the unloading vehicle will be considered self-propelled. The spreader shall
be provided with a screen that strikes off and distributes the material to the full width
being spread and to the surface tolerances specified. The screed shall be adjustable
to produce the required cross section. Screed action includes any cutting, crowding,
or other practical motion that produces a finished surface texture of uniform
appearance.
In addition, mechanical spreader equipment used to spread and trim cement treated
base shall be equipped with fully automatic screed and grade sensing controls which
shall control the longitudinal grade and transverse slopes of the screed. Screed
controls shall be such that compensation for differences from the slope and grade
established by the Engineer will be completely automatic.
The use of motor graders will not be permitted during spreading and compaction
operations. Motor graders may be used to trim the edges and surface of the cement
treated base after compaction in order to finish the base within the tolerances specified.
Unless traffic conditions are prohibitive, the mixed materials shall be spread in
widths of not less than two (2) lanes, insofar as the width of cement treated base to be
spread permits. Three (3) lane sections may be spread as a two (2) lane width and a
one (1) lane width. Spread widths wider than two (2) lanes will be permitted but are not
34
MOC General Specifications – November 1998
Longitudinal construction joints shall fall within thirty (30) centimeters of lane widths.
When cement treated base is placed in more than one (1) layer, the surface of the
lower layer of compacted material shall be kept moist until covered with the next layer
or with the curing seal. Curing seal shall be applied to the surface of a lower layer
which has not been covered with the next layer on the same day. Full compensation
for keeping lower layers moist and for furnishing and applying curing seal to the lower
layers as specified will be considered as included in the contract price paid for cement
treated base and no separate payment will be made therefore.
When the initial compaction is complete, if the surface of the cement treated base
does not conform to specified finish tolerances, high spots shall be trimmed to produce
the specified tolerances. All trimmed material shall be removed from the surface of the
cement treated base and disposed of as approved by the Engineer. Filling low areas
by drifting or hauling of trimmed material is prohibited. Following trimming, all trimmed
areas shall receive a minimum of one (1) compaction pass. Additional compaction shall
be performed until the entire layer of cement treated cement base conforms to the
specified compaction requirements. Final compaction shall be accomplished in such
a manner that no loose material remains on the surface and all tear marks are
eliminated. Compaction shall proceed without interruption, except as stated above, to
achieve at least ninety-five percent (95%) maximum density as determined by MRDTM
212.
The surface of the cement treated base shall be kept moist at all times until the
curing seal is applied.
3.04.6.5 Operation Time Requirement. The Contractor shall furnish and operate
sufficient equipment or limit the area of work in progress so that not more than two (2)
hours shall elapse between the time water is added to the aggregate and cement and
the time of completion of the final compaction after trimming, unless otherwise approved
by the Engineer.
35
MOC General Specifications – November 1998
3.04.6.6 Construction Joints. At the end of each day's work or when cement
treated base operations are delayed or stopped for more than two (2) hours, a
construction joint shall be made in thoroughly compacted material. The joint shall be
normal to the center line of the roadbed and have a vertical face. Additional mixture
shall not be placed until the construction joint has been approved by the Engineer.
When partial-width construction of cement treated base is allowed and when the
material has been finally compacted more than one (1) hour, a longitudinal joint shall
be constructed by cutting back into the previously placed material to a point where it
meets the proper line and grade, and trimmed to a true vertical face which is free of any
loose or shattered material. Trimmed material shall be removed and disposed of at
locations approved by the Engineer. The face of transverse and longitudinal
construction joints shall be moistened prior to placement of the adjacent base material.
3.04.7 CURING. After final compaction, the cement treated base shall be covered with
a bituminous curing seal, uniformly applied to the surface at a rate between one-half
(0.50) and one (1.00) liter per square meter. The curing seal shall be applied on the
same day that final compaction is achieved and as soon as practical.
After the curing seal has been applied, the cement treated base shall be kept free
of general traffic for a period of at least seven (7) days. Subsequent aggregate base,
or pavement course shall be placed within ten days after the curing seal is applied.
Any damage to the curing seal or the cement treated base shall be promptly
repaired by the Contractor, at his expense and as directed by the Engineer
Process control sampling and testing shall be by lot. A lot shall be five hundred
(500) cubic meters. Contractor process control testing shall include:
1. Aggregate gradation.
2. Compressive strength or (CBR for the mixture).
36
MOC General Specifications – November 1998
The Engineer shall perform or supervise the performance of all quality assurance
sampling and testing. The location of all samples and tests shall be recorded by
roadway, lane and centerline station (kilometer). Quality assurance sampling and
testing for each lot shall include:
1. Compaction
2. Thickness
5. Surface Tolerances
3.04.9.1 Compaction. The compacted density for each layer of each course shall
be determined by the sand cone method, MRDTM 215, or by nuclear method, MRDTM
218 using full depth penetration, at the option of the Engineer.
When the sand cone method is used, unless otherwise stated in the Special
Specifications, the tests shall be made at a minimum of five (5) randomly selected
locations in each lot.
When the nuclear method is used, unless otherwise stated in the Special
Specifications, the tests shall be made at a minimum of eight (8) randomly selected
locations in each lot. Three nuclear gauge readings shall be made at each test location
within a radius of two (2) meters. The three (3) readings shall be averaged and the
average considered to be the density for that test location.
Any lot of cement treated base that has a percent relative compaction below the
minimum percent compaction specified in Paragraph 3.03.4.6, "Compacting," in these
General Specifications, resulting in a reduced pay factor of 0.75 or higher determined
in accordance with Subsection 1.08.5 "Statistical Evaluation of Work for Acceptance
and Determination of Pay Factor (Value of Work)" in these General Specifications may
be accepted on the basis of a reduced payment if requested in writing by the
Contractor. Otherwise the said lot shall be removed and replaced by the Contractor at
his expense. Lots that have percent relative compaction resulting in a reduced pay
factor less than 0.75 shall be removed and replaced by the contractor at his expense.
37
MOC General Specifications – November 1998
A lot shall be accepted when the average total thickness is not less than the plan
thickness.
Any lot of cement treated base course with an average thickness less than the plan
thickness but resulting in a reduced pay factor of 0.75 or higher determined in
accordance with Subsection 1.08.5, "Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value of Work)" in these General Specifications may be
accepted on the basis of reduced payment if requested in writing by the Contractor.
Otherwise the said lot thickness shall be increased as specified in the following
paragraph.
When the average thickness of a lot of cement treated base course is less than the
planned thickness by an amount resulting in a reduced pay factor below 0.75 the
Contractor, at his own expense, shall place and remix additional cement treated base
material with the original cement treated base material and recompact before new test
holes are dug.
Every sample of cement treated base shall be taken on a random time basis from
each uncompacted base immediately behind the spreader during each one-half ( ) day
of work, or portion thereof. The initial sample shall be randomly selected from within
one and one-half (1 ) meters either side of the centerline of and weigh at least twenty-
five (25) kilograms. The initial sample shall be thoroughly mixed and quartered to
obtain a test sample weighing at least six (6) kilograms. The test sample shall be
forwarded to the project laboratory and the aggregate gradation, cement gradation and
cement content determined.
When the aggregate gradation, sand equivalent or plasticity index for any lot results
in a reduced pay factor of 0.75 or higher, determined in accordance with above
referenced Subsection 1.08.5, "Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value of Work)" in these General Specifications the lot
may be accepted on the basis of a reduced pay factor if requested in writing by the
Contractor, otherwise said lot shall be removed and replaced by the Contractor at his
expense.
When the gradation, sand equivalent or plasticity index pay factor determined in
accordance with above referenced Subsection 1.08.5, "Statistical Evaluation of Work
for Acceptance and Determination of Pay Factor (Value of Work)" in these General
38
MOC General Specifications – November 1998
Specifications for any lot is less than 0.75 the aggregate base shall be removed and
replaced by the Contractor at his own expense.
3.04.9.5 Surface Tolerances. The surface layer of the cement treated base shall
be evaluated for compliance with the following surface tolerances:
1. The cross section of the finished cement treated base surface shall be check ed
by the Contractor in the presence of the Engineer at maximum intervals of twenty-five
(25) meters and at intermediate points as directed by the Engineer. The deviation of
the elevation of the surface above the design elevation shall be not more than ten (10)
millimeters. Deviations above the design elevation shall not result in the diminished
thickness of any subsequent pavement course. The deviation of the elevation below
the design elevation shall not be more than ten (10) millimeters. Isolated deviations
below the design elevation shall be compensated by additional thickness of the
subsequent pavement layer. Additional cost and materials resulting from deviations
from the design elevation shall be borne by the Contractor.
2. The surface shall also be checked with a four (4) meter straightedge in all areas
of apparent roughness as directed by the Engineer. The finished surface of the base
course shall not deviate from the straightedge between any two (2) contact points more
than ten (10) millimeters when the straightedge is placed parallel to centerline or twelve
(12) millimeters when the straightedge is placed perpendicular to centerline. The
Contractor shall furnish all devices necessary to check the surface, such as stringlines,
straightedges, etc., and the labor necessary to handle the task.
39
MOC General Specifications – November 1998
adjusted accordingly. The second stage thickness quantity pay factor will be applied
to all the individual course lots in addition to the first stage lowest quality pay factor
determined in accordance with Subsection 1.08.5, "Statistical Evaluation of Work for
Acceptance and Determination of Pay Factor (Value of Work)" in these General
Specifications.
The volume to be paid for shall be calculated on the basis of the dimensions shown
on the plans, adjusted by the amount of any change ordered by the Engineer. No
allowance will be made for cement treated base placed outside said dimensions unless
ordered by the Ministry. The quantity of cement treated base placed below the grade
established by the Engineer will not be paid for.
When a lot of cement treated base course is accepted with a deficiency, the
adjusted contract unit price for said lot shall be the product of the contract unit price of
cement treated base course and the lowest quality and quantity pay factors specified
in Subsection 3.04.9, "Quality Assurance Procedures," in these General Specifications.
40
MOC General Specifications – November 1998
3.05.1 DESCRIPTION. This Work shall consist of constructing shoulders and laybys
of the types specified hereinafter, in accordance with these specifications and in
conformity to the lines, elevations, thickness and typical cross sections shown on the
plans or established by the Engineer.
3.05.3.1 General. For the purpose of simplification throughout the remainder of the
Section, when the term "shoulders" is used it shall mean "shoulders and/or laybys."
Shoulders shall be constructed as soon as practicable after the construction of the
base/surface course, and/or preparation of the surface area. If shoulders are part of
a resurfacing project, vegetable matter shall be removed from the surface of the original
shoulders and, if shown on the plans or required by the Engineer, from the adjacent
foreslopes upon which the shoulders are to be constructed, and the underlying twenty
(20) millimeters layer shall be scarified and recompacted to at least ninety-five percent
(95%) of maximum dry density as determined by MRDTM 212.
41
MOC General Specifications – November 1998
3.05.3.2 Earth Shoulders and Laybys. The material used for Earth Shoulders and
Earth Laybys shall meet the requirements of Subsection 2.05.5, "Subgrade," in the
General Specifications and shall be obtained from sources approved by the Engineer.
The material shall be deposited and spread in uniform layers not to exceed twenty (20)
centimeters (loose measurement) in thickness and compacted to ninety-eight percent
(98%) of maximum dry density as determined by MRDTM 212.
The material used for Aggregate Shoulders shall be of the grading designated on
the plans and shall be in conformance with the requirements for the same grading of
material used for Aggregate Bases as specified in Subsection 3.03.2, "Materials" in
these General Specifications and listed in the Bill of Quantities.
42
MOC General Specifications – November 1998
The designated compaction shall be obtained at the edge of the pavement, base or
surface, but extreme care shall be exercised to prevent damage to the pavement, base,
or surface edges, due to the rolling operations. If deemed necessary by the Engineer,
he may require planking of the edges to prevent such damage.
When completed, the shoulders shall be smooth, compact and shall conform to the
required cross section.
Bituminous base and wearing course materials used in the construction of shoulders
and laybys shall not be measured under Section 3.05 Shoulders and Laybys but shall
be measured under Section 4.05 Bituminous Concrete Pavement in these General
Specifications
3.05.7 PAYMENT. The amount of completed and accepted Work, as measured above,
will be paid for at the contract unit price(s) or adjusted contract unit price(s) per cubic
meter for Earth Shoulders, Earth Laybys, Aggregate Shoulders, and Aggregate Laybys,
according to the pay items specified in the Special Specifications and listed in the Bill
of Quantities. Those price(s) shall be full compensation for furnishing all materials, for
all labor, equipment, tools, supplies, and all other items necessary for the proper
completion of the Work as specified in Subsection 1.07.2., "Scope of Payment" in these
General Specifications.
Bituminous base and wearing course materials used in the construction of shoulders
and laybys shall not be paid for under Section 3.05 Shoulders and Laybys but shall
43
MOC General Specifications – November 1998
be paid for under Section 4.05 Bituminous Concrete Pavement in these General
Specifications.
44