You are on page 1of 2

CONFIDENTIAL

UNIVERSITI
TEKNOLOGI
MARA
KAMPUS JENGKA CAW.PAHANG

PROJECT: CIVIL ENGINEERING QUANTITIES AND ESTIMATION (ECM 366)


COURSE : CIVIL ENGINEERING QUANTITIES AND ESTIMATION

COURSE CODE : ECM 366

GROUP :

LECTURER :

NAME MATRIX NO.

QUESTION MARKS

a) FORMAT 10 /10

b) CONTENTS 50 /50

c) WRITING SKILLS 20 /20

d) REFERENCE 5 /5

e) CONCLUSION 15 /15

TOTAL 100 /100

Report: Presentation: Total:

30

70
APPENDIX 1

ITEM DESCRIPTION UNIT UNIT RATE


(RM)
1 Mild Steel Bar
Nominal diameter 6mm kg 4.50
Nominal diameter 8mm kg 4.20
Nominal diameter 10mm kg 4.00
Nominal diameter 12mm kg 4.00
Nominal diameter 16mm kg 3.80
Nominal diameter 20mm kg 3.80
Nominal diameter 25mm kg 3.70

High-Tensile bar
Nominal diameter 10mm kg 4.00
Nominal diameter 12mm kg 4.00
Nominal diameter 16mm kg 3.90
Nominal diameter 20mm kg 3.90
Nominal diameter 25mm kg 3.80
Nominal diameter 32mm kg 3.80

High Tensile Steel fabric


BRC No. C5 (100mm x 400mm) (1.93kg/m2) m2 11.20
BRC No. C6(100mm x 400mm) (2.61kg/m2) m2 17.10
BRC No. A6(100mm x 400mm) (2.22kg/m2) m2 23.80
BRC No. B7(100mm x 400mm) (4.53kg/m2) m2 26.20
BRC No. A9(100mm x 400mm) (4.99kg/m2) m2 63.00
BRC No. A10(100mm x 400mm) (6.16kg/m2) m2 44.70

Data for Estimating Works:

Material Cost:

Cement RM 18.00/ bag


Sand RM 36.00/ m3
Aggregates RM 48.00/ m3
Diesel RM 2.20/ litre
Lubricating oil RM 15.00/ litre
Timber RM 3500.00/ m3
Nails RM 5.30/ kg

Labour Cost:

Skilled Worker RM 75.00/ day


Unskilled Worker RM 40.00/ day

Concrete Mixer 10/7

Initial Cost RM 5500.00


Interest rate 10% per year
Life Span 5 years