Sat

7/31/2021
Sr# Task Description Responsible team

1 Pepare Chiller for Chemical Cleaning WTP team & York Do


2 Conduct Chemical Cleaning for the Condenser Pipes (Flusing ) WTP team
3 Conduct Brushing for the Condenser Pipes York
4 Conduct eddy current test York
8/1/2021

Do
Sun
8/2/2021

Do
Mon
8/3/2021

Do
Tue

8/4/2021

Do
Wed