PROJECT CHARTER

Project Title: 5 Stars Hotel

Project Sponsor: Al Rajhi Bank Date Prepared: Sunday, 01 – 04 – 2018

Project Manager: Eng. Waleed Elbasyouni Project Customer: WAQF


‫ﺴﻢ ﷲ اﻟﺮﲪﻦ اﻟﺮﺣﲓ‬
Project Description: ( Project boundaries, and key deliverables)
 Construct of 5 stars Hotel Content of 3 basement +Ground Floor+ Miz Floor + 14 typical Floor
and Upper Roof.
 Land Area of 2500 m2
 Building Construction area (60%) 1500 m 2
 Project location: Medina - Saudi Arabia

Business Case:
 Business need (Customer Request )
 Cost Benefit Analysis ( Project Cost To Project Benefits )

Initial Risks:
 Price of Steel Bars May Be Change.
 Project Soil May Be Hard Rocky
 Available of Resources ( Man Power – Material – Equipment )

Acceptance Criteria:
 We should perform all the work, according to the Saudi Arabia Construction Code.
 We Cannot Accept Low-Grade Material We Should Use First Grade Raw Material.
 We cannot terminate the Contract unilaterally, only after discuss with all Project Party.

Summary Milestones Due Date


 Site Receiving 15-04-2018
 Finalize Skeleton 15-11-2018

 Finalize Finishing Work 15-01-2020


 Project Handing Over 30-04-2020

ELBASYOUNI, WALEED PMP,PMI-RMP, TOT, MSc


PROJECT CHARTER

Summery Budget:

 Project Total Budget 285.000.000 S.R


o 92.000.000 S.R Skeleton ( Concrete Work )
o 193.000.000 S.R Finishing

Project Manager Authority Level

 Manage The Project Budget.

 Manage And Select His Team Work.

 Can Takes Any Decision Making About Project Time Schedule.

 Manage and Defined The Project Quality Standers and Measurements.

 He don’t Have any authority to approve to Project Change Requests without Coordinates with

C.C.B (Change Control Board).

Approvals:

Project Manager Signature Sponsor or Originator Signature


Waleed ElBasyouni Al Rajhi Bank