Professional Documents
Culture Documents
Author: CEPA
Date: 7/11/2016
1. OVERVIEW
This Paper addresses several issues regarding how natural gas-fired generators “should” declare
costs for despatch purposes in Peru. This issue has been somewhat contentious almost since the
introduction of gas-fired generation when (in times prior to the development of the Camisea field)
gas from Aguaytia and Talara was the only gas used.
The principal issue has been (and remains) that electricity generators in the Peruvian system are
required to declare their actual (potentially subject to audit) marginal costs of production (which we
shall refer to as SRMC) for despatch purposes. This becomes problematic when it is recognised that
gas-fired generators generally purchase their gas in Peru through “take or pay” (ToP) contracts and
do not have effective access to short term (or spot) markets for purchases or sales of surplus or
deficit gas supplies. These circumstances are substantially different than those faced by certain
other generators (e.g., liquid-fuelled generators 1), and they lead to debate regarding how to assess
the SRMC of gas for despatch purposes.
We note that while this question is important today, it is probably somewhat less important than it
was in previous years when Osinergmin was fully forecasting the “busbar tariff” which at that time
served as the single benchmark value for passthrough of energy costs into regulated retail tariffs.
Today, when the energy component of regulated retail tariffs is based on actual contract purchase
prices (rather than a forecast of COES spot market prices), at least a portion of the contentiousness
of the gas SRMC question is reduced. Furthermore, in the future if the wholesale energy market is
changed to a more liberalised form, this question might also become irrelevant if all generators face
the same (liberalised, non-cost-reflective) bidding rules.
With this context, it is also necessary to point out that this Paper is not intended to recommend or
design “patches” or improvements to the current COES wholesale market. Instead, it is to analyse
the current approach to gas-generator declarations and to make observations for the future. In one
of the later sections of the Paper (Section 4.2), we do suggest how gas generator declarations might
be handled in each of the various future “Models for future development” set out in our main
Report, though the precise future details of how this issue is handled would of course depend on the
detailed development of whichever Model is chosen.
In the following sections, we first consider several points made in the 1998 report “Pricing Natural
Gas for Power Generation in Peru” (the “PHB Report”), and then summarise several of the key
aspects of today’s situation regarding gas supplies and markets which has of course evolved since
1
Though it is quite possible that limited-storage hydro generators might face some similar issues to gas-fired
generators.
1
the PHB Report was written. We next comment on the likely implications for the bidding by gas
generators, both now (in the context of the current COES spot market and current law) and in the
future when possibly the law and electricity spot market structure will be changed. Finally, we
conclude by noting several issues which should be addressed in the future as the electricity sector
continues to evolve.
The only real market for gas in Peru is, and for some years will be, within the
electricity sector itself. Most of the transactions in this market will be through
contracts (or other business relationships, such as ownership) between gas
producers and generators, and perhaps some limited gas trading among
generators (or other consumers, if a gas pipeline system and market develops).
These transactions and their prices will usually be confidential and complex,
making it impossible for CTE or anybody else to observe “the market price of
gas.” But the final “sale” of gas will take place when the gas is converted into
electricity, and the price of this sale will be directly observable in the dispatch
prices declared by the generators themselves. These dispatch prices provide the
best estimate there is of “the market price of gas” used for power generation in
Peru. (Section 3.4)
2
dispatch price that does not reflect its own assessment of the SRMC of its gas.
Thus, as far as practical, each generator’s declared dispatch prices should be
used as the best estimate of the SRMC for that generator. (Section 7.1.3)
The opinion of the PHB Report regarding how to appropriately reflect the SRMC of gas in despatch
declarations seems quite clear. The next questions to be considered would then be whether today’s
“actual” situation differs in any material way from the views of the PHB Report at the time it was
written, and if so, how that might affect these conclusions. These are addressed in Sections 2 and 3
below.
3
for all of its capacity. Thus, until new gas-fired power generation comes on line, growth of gas
demand is limited to just the smaller consumption sectors 2. We understand also that the Camisea
operator is currently re-injecting gas in response to this and also in order to help manage liquids
production.
2
We understand that there are several current projects in both gas generation expansion and petrochemicals
which have contracted Camisea gas, but which are either not yet started and / or delayed.
3
We observe that the lack of any upper bound at all on gas generator declarations does not immediately seem
consistent with the concept of COES pool as a “true marginal cost declaration” pool. However, there may be
subtleties or other rationale for this that we are not aware of.
4
recommendations) of such future models. Within the context of such general illustrations, we might
anticipate that:
● For Model 1, it is likely that all generators would be free to declare any bid price
(subject probably to an upper limit on bids which would be set substantially above
even liquid-fuelled marginal costs) on a daily (or other appropriate) basis to the
market. This would certainly allow gas generators much more freedom in managing
their ToP obligations. However, we also note that in the medium term there is a
substantial excess of zero marginal cost capacity (i.e., hydro and ToP gas generators)
on the system. This could well lead to quite low energy prices when demand is such
that liquid fuelled generators are not needed. There is nothing intrinsically bad
about this, recognising that the investments which have resulted in this situation are
already “sunk costs”. However, it does highlight the likely importance of having a
forward capacity market acting in parallel to the energy (as opposed to an “energy
only” market with perhaps a VLL / LOLP feature embedded in it) to allow the low-
marginal cost generators an opportunity to secure some forward revenues against
their fixed cost operations.
● For Model 2, it is likely that the current structure of the COES wholesale market
would likely remain in place (though possibly with a reformed or at least reviewed
capacity payment system as speculated about in footnote 3 above). In this case, the
declaration rules would probably stay as they are, although we would prefer to see
the sort of comments made in Section 4.1 above taken into account. Gas generators
would of course continue to depend on their PPA contracts to cover fixed costs.
● For Model 3, we might expect that a more “traditional” approach to the structure of
PPA contracts would be put in place (i.e., contracts with individually cost-reflective
capacity payments and rights to energy output at variable cost vested in the
offtaker) and auctioned to offtakers. This approach would potentially offer the
greatest security to recovery of fixed costs by generators (though at the likely cost of
transferring overcapacity cost risk to consumers) and could (depending on
implementation details of course) provide appropriate price signals for consumption.
In each of these cases, the precise way in which gas generation is handled will depend on the
detailed design of the respective market.
5
o Ensuring as large a potential market as possible, possibly through international
interconnection and promoting adequate export (LNG) capacity accessible to all
producers
o Promoting more players in upstream production, ideally through attracting
more bidding consortia for development of new fields (if they exist), or possibly
through other methods in the longer term (e.g., so-called “gas release” schemes
as applied in various other countries).4
o Ensuring that gas infrastructure and pipeline access are as much as possible
organised along “open access” principles.
These and other possibilities of course are strongly dependent on the existing legal
and contractual arrangements with field developers. We have not reviewed these
arrangements as part of this work.
4
The fact that many upstream development projects – and Camisea is no exception – rely on consortia of
several partners further complicates this. The existence of consortia has practical and valuable business
purposes of sharing both the risks and financial investment burdens of field development. But it also takes
potential players “out of the market” for projects such as gas release schemes. One way to mitigate this
problem in future developments might be to break down developments into multiple lots for bidding and to
award different lots to different consortia, resulting in a diversity of upstream producers. This of course also
offers its own complexities and potential drawbacks, particularly if there are fewer interested or qualified
bidders.
6
style system initially) to allow this sort of trade. Such development, if it occurs,
should be undertaken following consultation with gas generators regarding
feasibility, need and possible alternatives.