CONSTRUCTION OF AL GARAFFA AREA SEWERAGE - PHASE 2

CP 745/2
Data Date: 01st January 2015

Progress Summary
% of Works

Description of Work Area Up to Previous Week This Week To-Date Remarks


Variance to Delay / Ahead
Date Days
Planned Actual Planned Actual Planned Actual

General General 14.69% 13.86% 0.00% 0.16% 14.69% 14.03% -0.66% -161

Line V 34/1/27/56/1 (320Lm, 4MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0

Line AE 34/1/27/51/1 (828LM, 17MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0

Line AD1 34/1/27/46/11(493LM, 9MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0

Line AC 34/1/27/45/19/1 (431LM, 8MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0

Line U 34/1/27/60/1 (779LM, 12MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0

Line AB3 34/1/27/45/15/2 (2417LM, 91MH) 100.00% 99.37% 0.00% 0.00% 100.00% 99.37% -0.63% -129 TMP Approvals Delaying.

Line AB2 34/1/27/45/18/1 (479LM, 21MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0
Construction
Line AB1 34/1/27/45/20/1 (1672 LM, 50MH) 100.00% 99.60% 0.00% 0.00% 100.00% 99.60% -0.40% -128 TMP Approvals Delaying.

Line AK 34/1/27/33/2 (4102LM, 120MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0 TMP Approvals Delaying.

Line AJ 34/1/27/38/1 (750LM, 18MH) 100.00% 99.92% 0.00% 0.00% 100.00% 99.92% -0.08% -129 Invert Level Issue

Line AI 34/1/27/40/2 (3348LM, 123MH) 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0 TMP Approvals Delaying.

Line AL 34/1/27/30/1 (603LM, 18MH) 100.00% 97.05% 0.00% 0.00% 100.00% 97.05% -2.95% -161

Line AN1 34/1/27/24 (1324LM, 32MH) 100.00% 99.05% 0.00% 0.00% 100.00% 99.05% -0.95% -161

Found water table high delaying excavation works &


Line AM 34/1/27/27 (7003LM, 227MH) 100.00% 99.20% 0.00% 0.21% 100.00% 99.41% -0.59% -141
TMP Approvals Delaying.

Overall Progress 100.00% 98.76% 0.00% 0.23% 100.00% 99.00% -1.00% -161

Weekly Report CP 745/2 Progress Summary


Planned Percentage Of Completion Data Date: 01st January 2015

Weight Weight Progress Progress


Activity ID Activity Name Budgeted Total Cost Area Overall PCT % Area Overall
CONSTRUCTION OF AL GARAFFA AREA SEWERAGE - PHASE 2 6-9-2012 52,101,812 100.00% 100.00%
General 7,652,093 100.00% 14.69%
DN068GALPTPI700 Third Party Insurance 0 0.00% 0.00% 100.00% 0.00% 0.00%
DN068GALPSIO200 Supply and Installation of Site Offices 395,298 5.17% 0.76% 100.00% 5.17% 0.76%
DN068GALPALO100 Site Mobilisation 901,296 11.78% 1.73% 100.00% 11.78% 1.73%
DN068GALPTPI720 Contract Administration 5,331,554 69.67% 10.23% 100.00% 69.67% 10.23%
DN068GALPTPI730 Site offices maintain 842,670 11.01% 1.62% 100.00% 11.01% 1.62%
DN068GALPTPI710 Site Survey 181,274 2.37% 0.35% 100.00% 2.37% 0.35%
Construction 44,449,719 85.313%
Line 34/1/27/56/1 (320Lm, 4MH) 312,287 100.00% 100.00% 0.60%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS380 Obtaining RO from authorities 56/1, 51/1, 46, 46/11, 45/19 and 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA280 Traffic Diversion 56/1, 51/1 and 46 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET180 Setting out 56/1, 51/1 and 46 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (320 LM) 147,513 100.0%
DN068CPIPEXC220 Excavation for sewer pipeline 56/1 44,254 14.17% 0.08% 100.0% 14.17% 0.08%
DN068CPIPBED320 Geotextile and Bedding for sewer pipeline 56/1 25,077 8.03% 0.05% 100.0% 8.03% 0.05%
DN068CPIPLAY420 Pipe Laying for sewer pipeline 56/1 44,254 14.17% 0.08% 100.0% 14.17% 0.08%
DN068CPIPPBF520 Partial Backfill for sewer pipeline 56/1 17,702 5.67% 0.03% 100.0% 5.67% 0.03%
DN068CPIPTES620 Test for sewer pipeline 56/1 7,376 2.36% 0.01% 100.0% 2.36% 0.01%
DN068CPIPFBF720 Final Backfill for sewer pipeline 56/1 8,851 2.83% 0.02% 100.0% 2.83% 0.02%
Manhole Works (4 M.H.) 130,165 100.0%
DN068CMHLEXC230 Excavation works for manhole 56/1 6,309 2.02% 0.01% 100.0% 2.02% 0.01%
DN068CMHLBLI330 Blinding for manhole 56/1 1,147 0.37% 0.00% 100.0% 0.37% 0.00%
DN068CMHLTAP430 Tanking membrane and protection for manhole 56/1 574 0.18% 0.00% 100.0% 0.18% 0.00%
DN068CMHLBAS530 Base slab for manhole 56/1 11,472 3.67% 0.02% 100.0% 3.67% 0.02%
DN068CMHLGRP930 GRP liner for manhole 56/1 13,192 4.22% 0.03% 100.0% 4.22% 0.03%
DN068CMHLWCP630 Wall concrete and pipe for manhole 56/1 14,340 4.59% 0.03% 100.0% 4.59% 0.03%
DN068CMHLCOV730 Cover slab for manhole 56/1 1,721 0.55% 0.00% 100.0% 0.55% 0.00%
DN068CMHLDIC190 DI cover for manhole 56/1 1,147 0.37% 0.00% 100.0% 0.37% 0.00%
DN068CMHLDIC100 Ladder for manhole 56/1 1,147 0.37% 0.00% 100.0% 0.37% 0.00%
DN068CMHLEMB130 External tanking membrane and protection for manhole 56/1 1,721 0.55% 0.00% 100.0% 0.55% 0.00%
DN068CMHLBAC150 Backfilling for manhole 56/1 4,589 1.47% 0.01% 100.0% 1.47% 0.01%
DN068CMHLDIC110 Reinstatement works 56/1 72,807 23.31% 0.14% 100.0% 23.31% 0.14%
House Connection Works (8D) 34,609 100.0%
DN068CHCOEXC330 Excavation for pipeline for house connection 56/1 11,434 3.66% 0.02% 100.0% 3.66% 0.02%
DN068CHCOPIP430 Pipe laying for house connection 56/1 14,700 4.71% 0.03% 100.0% 4.71% 0.03%
DN068CHCOBAC830 Backfilling for Pipe for house connection 56/1 6,534 2.09% 0.01% 100.0% 2.09% 0.01%
DN068CHCOREN930 Marker post for house connection 56/1 1,941 0.62% 0.00% 100.0% 0.62% 0.00%
Line 34/1/27/51/1 (828LM, 17MH) 940,955 100.00% 100.00% 1.81%
PipeLine Works (828 LM) 348,389 100.0%
DN068CPIPEXC190 Excavation for sewer pipeline 51/1 104,517 11.11% 0.20% 100.0% 11.1% 0.2%
DN068CPIPBED290 Geotextile and Bedding for sewer pipeline 51/1 59,226 6.29% 0.11% 100.0% 6.3% 0.1%
DN068CPIPLAY390 Pipe Laying for sewer pipeline 51/1 104,517 11.11% 0.20% 100.0% 11.1% 0.2%
DN068CPIPPBF490 Partial Backfill for sewer pipeline 51/1 41,807 4.44% 0.08% 100.0% 4.4% 0.1%
DN068CPIPTES590 Test for sewer pipeline 51/1 17,420 1.85% 0.03% 100.0% 1.9% 0.0%
DN068CPIPFBF690 Final Backfill for sewer pipeline 51/1 20,903 2.22% 0.04% 100.0% 2.2% 0.0%
Manhole Works (17 M.H.) 440,242 100.0%
DN068CMHLEXC200 Excavation works for manhole 51/1 27,961 2.97% 0.05% 100.0% 3.0% 0.1%
DN068CMHLBLI300 Blinding for manhole 51/1 5,084 0.54% 0.01% 100.0% 0.5% 0.0%
DN068CMHLTAP400 Tanking membrane and protection for manhole 51/1 2,542 0.27% 0.00% 100.0% 0.3% 0.0%
DN068CMHLBAS500 Base slab for manhole 51/1 50,839 5.40% 0.10% 100.0% 5.4% 0.1%
DN068CMHLGRP900 GRP liner for manhole 51/1 58,465 6.21% 0.11% 100.0% 6.2% 0.1%
DN068CMHLWCP600 Wall concrete and pipe for manhole 51/1 63,549 6.75% 0.12% 100.0% 6.8% 0.1%
DN068CMHLCOV700 Cover slab for manhole 51/1 7,626 0.81% 0.01% 100.0% 0.8% 0.0%
DN068CMHLDIC1000 DI cover for manhole 51/1 5,084 0.54% 0.01% 100.0% 0.5% 0.0%
DN068CMHLDIC1010 Ladder for manhole 51/1 5,084 0.54% 0.01% 100.0% 0.5% 0.0%
DN068CMHLEMB100 External tanking membrane and protection for manhole 51/1 7,626 0.81% 0.01% 100.0% 0.8% 0.0%
DN068CMHLBAC120 Backfilling for manhole 51/1 20,336 2.16% 0.04% 100.0% 2.2% 0.0%
DN068CMHLDIC1020 Reinstatement works 51/1 186,048 19.77% 0.36% 100.0% 19.8% 0.4%
House Connection Works (11D,5ABC) 152,324 100.0%
DN068CHCODEM200 Demolition for existing underground structure 51/1 24,704 2.63% 0.05% 100.0% 2.6% 0.0%
DN068CHCOEXC300 Excavation for pipeline and inspection chamber 51/1 23,016 2.45% 0.04% 100.0% 2.4% 0.0%
DN068CHCOPIP400 Pipe laying for house connection 51/1 29,592 3.14% 0.06% 100.0% 3.1% 0.1%
DN068CHCOBAS500 Base for inspection chamber 51/1 6,057 0.64% 0.01% 100.0% 0.6% 0.0%
DN068CHCOWAL600 Wall for inspection chamber 51/1 15,144 1.61% 0.03% 100.0% 1.6% 0.0%
DN068CHCOFIN1000 Finishing for inspection chamber 51/1 4,543 0.48% 0.01% 100.0% 0.5% 0.0%
DN068CHCOCOV700 Cover for inspection chamber 51/1 4,543 0.48% 0.01% 100.0% 0.5% 0.0%
DN068CHCOBAC800 Backfilling for house connection 51/1 13,152 1.40% 0.03% 100.0% 1.4% 0.0%
DN068CHCOREN900 Reinstatement work for house connection 51/1 31,573 3.36% 0.06% 100.0% 3.4% 0.1%
Line 34/1/27/46/11(493LM, 9MH) 406,563 100.00% 100.00% 0.78%
Traffic Management and Setting Out 0 0.0%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CGENTRA300 Traffic Diversion 46/11 0 0.00% 0.00% 100.0% 0.0% 0.0%
DN068CGENSET200 Setting out 46/11 0 0.00% 0.00% 100.0% 0.0% 0.0%
PipeLine Works (493 LM) 145,902 100.0%
DN068CPIPEXC200 Excavation for sewer pipeline 46/11 43,771 10.77% 0.08% 100.0% 10.8% 0.1%
DN068CPIPBED300 Geotextile and Bedding for sewer pipeline 46/11 24,803 6.10% 0.05% 100.0% 6.1% 0.0%
DN068CPIPLAY400 Pipe Laying for sewer pipeline 46/11 43,771 10.77% 0.08% 100.0% 10.8% 0.1%
DN068CPIPPBF500 Partial Backfill for sewer pipeline 46/11 17,508 4.31% 0.03% 100.0% 4.3% 0.0%
DN068CPIPTES600 Test for sewer pipeline 46/11 7,295 1.79% 0.01% 100.0% 1.8% 0.0%
DN068CPIPFBF700 Final Backfill for sewer pipeline 46/11 8,754 2.15% 0.02% 100.0% 2.2% 0.0%
Manhole Works (9 M.H.) 195,505 100.0%
DN068CMHLEXC210 Excavation works for manhole 46/11 9,227 2.27% 0.02% 100.0% 2.3% 0.0%
DN068CMHLBLI310 Blinding for manhole 46/11 1,678 0.41% 0.00% 100.0% 0.4% 0.0%
DN068CMHLTAP410 Tanking membrane and protection for manhole 46/11 839 0.21% 0.00% 100.0% 0.2% 0.0%
DN068CMHLBAS510 Base slab for manhole 46/11 16,777 4.13% 0.03% 100.0% 4.1% 0.0%
DN068CMHLGRP910 GRP liner for manhole 46/11 19,293 4.75% 0.04% 100.0% 4.7% 0.0%
DN068CMHLWCP610 Wall concrete and pipe for manhole 46/11 20,971 5.16% 0.04% 100.0% 5.2% 0.0%
DN068CMHLCOV710 Cover slab for manhole 46/11 2,517 0.62% 0.00% 100.0% 0.6% 0.0%
DN068CMHLDIC1030 DI cover for manhole 46/11 1,678 0.41% 0.00% 100.0% 0.4% 0.0%
DN068CMHLDIC1040 Ladder for manhole 46/11 1,678 0.41% 0.00% 100.0% 0.4% 0.0%
DN068CMHLEMB1010 External tanking membrane and protection for manhole 46/11 2,517 0.62% 0.00% 100.0% 0.6% 0.0%
DN068CMHLBAC1030 Backfilling for manhole 46/11 6,711 1.65% 0.01% 100.0% 1.7% 0.0%
DN068CMHLDIC1050 Reinstatement works 46/11 111,622 27.46% 0.21% 100.0% 27.5% 0.2%
House Connection Works (15D) 65,157 100.0%
DN068CHCOEXC310 Excavation for pipeline for house connection 46/11 21,531 5.30% 0.04% 100.0% 5.3% 0.0%
DN068CHCOPIP410 Pipe laying for house connection 46/11 27,683 6.81% 0.05% 100.0% 6.8% 0.1%
DN068CHCOBAC810 Backfilling for Pipe for house connection 46/11 12,303 3.03% 0.02% 100.0% 3.0% 0.0%
DN068CHCOREN910 Marker Post for house connection 46/11 3,640 0.90% 0.01% 100.0% 0.9% 0.0%
Line 34/1/27/45/19/1 (431LM, 8MH) 390,220 100.00% 100.00% 0.75%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA310 Traffic Diversion 45/19/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET210 Setting out 45/19/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (431 LM) 139,802 100.0%
DN068CPIPEXC210 Excavation for sewer pipeline 45/19/1 41,941 10.75% 0.08% 100.0% 10.75% 0.08%
DN068CPIPBED310 Geotextile and Bedding for sewer pipeline45/19/1 23,766 6.09% 0.05% 100.0% 6.09% 0.05%
DN068CPIPLAY410 Pipe Laying for sewer pipeline 45/19/1 41,941 10.75% 0.08% 100.0% 10.75% 0.08%
DN068CPIPPBF510 Partial Backfill for sewer pipeline 45/19/1 16,776 4.30% 0.03% 100.0% 4.30% 0.03%
DN068CPIPTES610 Test for sewer pipeline 45/19/1 6,990 1.79% 0.01% 100.0% 1.79% 0.01%
DN068CPIPFBF710 Final Backfill for sewer pipeline 45/19/1 8,388 2.15% 0.02% 100.0% 2.15% 0.02%
Manhole Works (8 M.H.) 188,363 100.0%
DN068CMHLEXC220 Excavation works for manhole 45/19/1 10,015 2.57% 0.02% 100.0% 2.57% 0.02%
DN068CMHLBLI320 Blinding for manhole 45/19/1 1,821 0.47% 0.00% 100.0% 0.47% 0.00%
DN068CMHLTAP420 Tanking membrane and protection for manhole 45/19/1 910 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CMHLBAS520 Base slab for manhole 45/19/1 18,209 4.67% 0.03% 100.0% 4.67% 0.03%
DN068CMHLGRP920 GRP liner for manhole 45/19/1 20,940 5.37% 0.04% 100.0% 5.37% 0.04%
DN068CMHLWCP620 Wall concrete and pipe for manhole 45/19/1 22,761 5.83% 0.04% 100.0% 5.83% 0.04%
DN068CMHLCOV720 Cover slab for manhole 45/19/1 2,731 0.70% 0.01% 100.0% 0.70% 0.01%
DN068CMHLDIC1060 DI cover for manhole 45/19/1 1,821 0.47% 0.00% 100.0% 0.47% 0.00%
DN068CMHLDIC1070 Ladder for manhole 45/19/1 1,821 0.47% 0.00% 100.0% 0.47% 0.00%
DN068CMHLEMB1020 External tanking membrane and protection for manhole 45/19/ 2,731 0.70% 0.01% 100.0% 0.70% 0.01%
DN068CMHLBAC1040 Backfilling for manhole 45/19/1 7,284 1.87% 0.01% 100.0% 1.87% 0.01%
DN068CMHLDIC1080 Reinstatement works 45/19/1 97,319 24.94% 0.19% 100.0% 24.94% 0.19%
House Connection Works (10D, 1ABC) 62,055 100.0%
DN068CHCODEM220 Demolition for existing underground structure 45/19/1 4,941 1.27% 0.01% 100.0% 1.27% 0.01%
DN068CHCOEXC320 Excavation for pipeline and inspection chamber 45/19/1 14,997 3.84% 0.03% 100.0% 3.84% 0.03%
DN068CHCOPIP420 Pipe laying for house connection 45/19/1 19,282 4.94% 0.04% 100.0% 4.94% 0.04%
DN068CHCOBAS520 Base for inspection chamber 45/19/1 1,212 0.31% 0.00% 100.0% 0.31% 0.00%
DN068CHCOWAL620 Wall for inspection chamber 45/19/1 3,029 0.78% 0.01% 100.0% 0.78% 0.01%
DN068CHCOFIN1020 Finishing for inspection chamber 45/19/1 909 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CHCOCOV720 Cover for inspection chamber 45/19/1 909 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CHCOBAC820 Backfilling for house connection 45/19/1 8,570 2.20% 0.02% 100.0% 2.20% 0.02%
DN068CHCOREN920 Reinstatement work for house connection 45/19/1 8,207 2.10% 0.02% 100.0% 2.10% 0.02%
Line 34/1/27/60/1 (779LM, 12MH) 750,241 100.00% 100.00% 1.44%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA330 Traffic Diversion 60/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET230 Setting out 60/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (779 LM) 320,547 100.0%
DN068CPIPEXC230 Excavation for sewer pipeline 60/1 96,164 12.82% 0.18% 100.0% 12.82% 0.18%
DN068CPIPBED330 Geotextile and Bedding for sewer pipeline 60/1 54,493 7.26% 0.10% 100.0% 7.26% 0.10%
DN068CPIPLAY430 Pipe Laying for sewer pipeline 60/1 96,164 12.82% 0.18% 100.0% 12.82% 0.18%
DN068CPIPPBF530 Partial Backfill for sewer pipeline 60/1 38,466 5.13% 0.07% 100.0% 5.13% 0.07%
DN068CPIPTES630 Test for sewer pipeline 60/1 16,027 2.14% 0.03% 100.0% 2.14% 0.03%
DN068CPIPFBF730 Final Backfill for sewer pipeline 60/1 19,233 2.56% 0.04% 100.0% 2.56% 0.04%
Manhole Works (12 M.H.) 355,992 100.0%
DN068CMHLEXC240 Excavation works for manhole 60/1 19,773 2.64% 0.04% 100.0% 2.64% 0.04%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMHLBLI340 Blinding for manhole 60/1 3,595 0.48% 0.01% 100.0% 0.48% 0.01%
DN068CMHLTAP440 Tanking membrane and protection for manhole 60/1 1,798 0.24% 0.00% 100.0% 0.24% 0.00%
DN068CMHLBAS540 Base slab for manhole 60/1 35,951 4.79% 0.07% 100.0% 4.79% 0.07%
DN068CMHLGRP940 GRP liner for manhole 60/1 41,343 5.51% 0.08% 100.0% 5.51% 0.08%
DN068CMHLWCP640 Wall concrete and pipe for manhole 60/1 44,939 5.99% 0.09% 100.0% 5.99% 0.09%
DN068CMHLCOV740 Cover slab for manhole 60/1 5,393 0.72% 0.01% 100.0% 0.72% 0.01%
DN068CMHLDIC1120 DI cover for manhole 60/1 3,595 0.48% 0.01% 100.0% 0.48% 0.01%
DN068CMHLDIC1130 Ladder for manhole 60/1 3,595 0.48% 0.01% 100.0% 0.48% 0.01%
DN068CMHLEMB1040 External tanking membrane and protection for manhole 60/1 5,393 0.72% 0.01% 100.0% 0.72% 0.01%
DN068CMHLBAC1060 Backfilling for manhole 60/1 14,380 1.92% 0.03% 100.0% 1.92% 0.03%
DN068CMHLDIC1140 Reinstatement works 60/1 176,238 23.49% 0.34% 100.0% 23.49% 0.34%
House Connection Works (17D) 73,703 100.0%
DN068CHCOEXC340 Excavation for pipeline for house connection 60/1 24,352 3.25% 0.05% 100.0% 3.25% 0.05%
DN068CHCOPIP440 Pipe laying for house connection 60/1 31,310 4.17% 0.06% 100.0% 4.17% 0.06%
DN068CHCOBAC840 Backfilling for Pipe for house connection 60/1 13,916 1.85% 0.03% 100.0% 1.85% 0.03%
DN068CHCOREN940 Marker Post for house connection 60/1 4,125 0.55% 0.01% 100.0% 0.55% 0.01%
Line 34/1/27/45/15/2 (2417LM, 91MH) 4,592,315 100.00% 100.00% 8.81%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS340 Obtaining RO from authorities for 45 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA240 Traffic Diversion 45/15/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET140 Setting out 45/15/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (2417 LM) 830,892 100.0%
DN068CPIPEXC140 Excavation for sewer pipeline 45/15/2 249,268 5.43% 0.48% 100.0% 5.43% 0.48%
DN068CPIPBED240 Geotextile and Bedding for sewer pipeline 45/15/2 141,252 3.08% 0.27% 100.0% 3.08% 0.27%
DN068CPIPLAY340 Pipe Laying for sewer pipeline 45/15/2 249,268 5.43% 0.48% 100.0% 5.43% 0.48%
DN068CPIPPBF440 Partial Backfill for sewer pipeline 45/15/2 99,707 2.17% 0.19% 100.0% 2.17% 0.19%
DN068CPIPTES540 Test for sewer pipeline 45/15/2 41,545 0.90% 0.08% 100.0% 0.90% 0.08%
DN068CPIPFBF640 Final Backfill for sewer pipeline 45/15/2 49,854 1.09% 0.10% 100.0% 1.09% 0.10%
Manhole Works (91 M.H.) 1,756,950 100.0%
DN068CMHLEXC150 Excavation works for manhole 45/15/2 134,626 2.93% 0.26% 100.0% 2.93% 0.26%
DN068CMHLBLI250 Blinding for manhole 45/15/2 24,478 0.53% 0.05% 100.0% 0.53% 0.05%
DN068CMHLTAP350 Tanking membrane and protection for manhole 45/15/2 12,239 0.27% 0.02% 100.0% 0.27% 0.02%
DN068CMHLBAS450 Base slab for manhole 45/15/2 244,775 5.33% 0.47% 100.0% 5.33% 0.47%
DN068CMHLGRP850 GRP liner for manhole 45/15/2 281,491 6.13% 0.54% 100.0% 6.13% 0.54%
DN068CMHLWCP550 Wall concrete and pipe for manhole 45/15/2 305,968 6.66% 0.59% 100.0% 6.66% 0.59%
DN068CMHLCOV650 Cover slab for manhole 45/15/2 36,716 0.80% 0.07% 100.0% 0.80% 0.07%
DN068CMHLDIC850 DI cover for manhole 45/15/2 24,478 0.53% 0.05% 100.0% 0.53% 0.05%
DN068CMHLEMB950 External tanking membrane and protection for manhole 45/15/ 36,716 0.80% 0.07% 100.0% 0.80% 0.07%
DN068CMHLDIC860 Ladder for manhole 45/15/2 24,478 0.53% 0.05% 100.0% 0.53% 0.05%
DN068CMHLBAC970 Backfilling for manhole 45/15/2 97,910 2.13% 0.19% 100.0% 2.13% 0.19%
DN068CMHLDIC870 Reinstatement works 45/15/2 533,076 11.61% 1.02% 100.0% 11.61% 1.02%
House Connection Works (48D,86ABC) 2,004,473 100.0%
DN068CHCODEM150 Demolition for existing underground structure 45/15/2 424,913 9.25% 0.82% 100.0% 9.25% 0.82%
DN068CHCOEXC250 Excavation for pipeline and inspection chamber 45/15/2 192,441 4.19% 0.37% 100.0% 4.19% 0.37%
DN068CHCOPIP350 Pipe laying for house connection 45/15/2 247,425 5.39% 0.47% 100.0% 5.39% 0.47%
DN068CHCOBAS450 Base for inspection chamber 45/15/2 104,188 2.27% 0.20% 100.0% 2.27% 0.20%
DN068CHCOWAL550 Wall for inspection chamber 45/15/2 260,470 5.67% 0.50% 100.0% 5.67% 0.50%
DN068CHCOFIN950 Finishing for inspection chamber 45/15/2 78,141 1.70% 0.15% 100.0% 1.70% 0.15%
DN068CHCOCOV650 Cover for inspection chamber 45/15/2 78,141 1.70% 0.15% 100.0% 1.70% 0.15%
DN068CHCOBAC750 Backfilling for house connection 45/15/2 109,967 2.39% 0.21% 100.0% 2.39% 0.21%
DN068CHCOREN850 Reinstatement work for house connection 45/15/2 508,787 11.08% 0.98% 100.0% 11.08% 0.98%
Line 34/1/27/45/18/1 (479LM, 21MH) 853,192 100.00% 100.00% 1.64%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA230 Traffic Diversion 45/18/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET130 Setting out 45/18/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (479 LM) 144,658 100.0%
DN068CPIPEXC130 Excavation for sewer pipeline 45/18/1 43,398 5.09% 0.08% 100.0% 5.09% 0.08%
DN068CPIPBED230 Geotextile and Bedding for sewer pipeline 45/18/1 24,592 2.88% 0.05% 100.0% 2.88% 0.05%
DN068CPIPLAY330 Pipe Laying for sewer pipeline 45/18/1 43,398 5.09% 0.08% 100.0% 5.09% 0.08%
DN068CPIPPBF430 Partial Backfill for sewer pipeline 45/18/1 17,359 2.03% 0.03% 100.0% 2.03% 0.03%
DN068CPIPTES530 Test for sewer pipeline 45/18/1 7,233 0.85% 0.01% 100.0% 0.85% 0.01%
DN068CPIPFBF630 Final Backfill for sewer pipeline 45/18/1 8,680 1.02% 0.02% 100.0% 1.02% 0.02%
Manhole Works (21 M.H.) 300,607 100.0%
DN068CMHLEXC140 Excavation works for manhole 45/18/1 21,482 2.52% 0.04% 100.0% 2.52% 0.04%
DN068CMHLBLI240 Blinding for manhole 45/18/1 3,906 0.46% 0.01% 100.0% 0.46% 0.01%
DN068CMHLTAP340 Tanking membrane and protection for manhole 45/18/1 1,953 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CMHLBAS440 Base slab for manhole 45/18/1 39,059 4.58% 0.07% 100.0% 4.58% 0.07%
DN068CMHLGRP840 GRP liner for manhole 45/18/1 44,917 5.26% 0.09% 100.0% 5.26% 0.09%
DN068CMHLWCP540 Wall concrete and pipe for manhole 45/18/1 48,823 5.72% 0.09% 100.0% 5.72% 0.09%
DN068CMHLCOV640 Cover slab for manhole 45/18/1 5,859 0.69% 0.01% 100.0% 0.69% 0.01%
DN068CMHLDIC820 DI cover for manhole 45/18/1 3,906 0.46% 0.01% 100.0% 0.46% 0.01%
DN068CMHLDIC830 Ladder for manhole 45/18/1 3,906 0.46% 0.01% 100.0% 0.46% 0.01%
DN068CMHLEMB940 External tanking membrane and protection for manhole 45/18/ 5,859 0.69% 0.01% 100.0% 0.69% 0.01%
DN068CMHLBAC960 Backfilling for manhole 45/18/1 15,623 1.83% 0.03% 100.0% 1.83% 0.03%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMHLDIC840 Reinstatement works 45/18/1 105,314 12.34% 0.20% 100.0% 12.34% 0.20%
House Connection Works (17D, 16ABC) 407,926 100.0%
DN068CHCODEM140 Demolition for existing underground structure 45/18/1 79,054 9.27% 0.15% 100.0% 9.27% 0.15%
DN068CHCOEXC240 Excavation for pipeline and inspection chamber 45/18/1 47,368 5.55% 0.09% 100.0% 5.55% 0.09%
DN068CHCOPIP340 Pipe laying for house connection 45/18/1 60,902 7.14% 0.12% 100.0% 7.14% 0.12%
DN068CHCOBAS440 Base for inspection chamber 45/18/1 19,384 2.27% 0.04% 100.0% 2.27% 0.04%
DN068CHCOWAL540 Wall for inspection chamber 45/18/1 48,460 5.68% 0.09% 100.0% 5.68% 0.09%
DN068CHCOFIN940 Finishing for inspection chamber 45/18/1 14,538 1.70% 0.03% 100.0% 1.70% 0.03%
DN068CHCOCOV640 Cover for inspection chamber 45/18/1 14,538 1.70% 0.03% 100.0% 1.70% 0.03%
DN068CHCOBAC740 Backfilling for house connection 45/18/1 27,067 3.17% 0.05% 100.0% 3.17% 0.05%
DN068CHCOREN840 Reinstatement work for house connection 45/18/1 96,616 11.32% 0.19% 100.0% 11.32% 0.19%
Line 34/1/27/45/20/1 (1672 LM, 50MH) 2,820,436 100.00% 100.00% 5.41%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA220 Traffic Diversion 45/20/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET120 Setting out 45/20/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (1672 LM) 764,925 100.0%
DN068CPIPEXC120 Excavation for sewer pipeline 45/20/1 229,477 8.14% 0.44% 100.0% 8.14% 0.44%
DN068CPIPBED220 Geotextile and Bedding for sewer pipeline 45/20/1 130,037 4.61% 0.25% 100.0% 4.61% 0.25%
DN068CPIPLAY320 Pipe Laying for sewer pipeline 45/20/1 229,477 8.14% 0.44% 100.0% 8.14% 0.44%
DN068CPIPPBF420 Partial Backfill for sewer pipeline 45/20/1 91,791 3.25% 0.18% 100.0% 3.25% 0.18%
DN068CPIPTES520 Test for sewer pipeline 45/20/1 38,246 1.36% 0.07% 100.0% 1.36% 0.07%
DN068CPIPFBF620 Final Backfill for sewer pipeline 45/20/1 45,896 1.63% 0.09% 100.0% 1.63% 0.09%
Manhole Works (50 M.H.) 1,253,247 100.0%
DN068CMHLEXC130 Excavation works for manhole 45/20/1 97,039 3.44% 0.19% 100.0% 3.44% 0.19%
DN068CMHLBLI230 Blinding for manhole 45/20/1 17,644 0.63% 0.03% 100.0% 0.63% 0.03%
DN068CMHLTAP330 Tanking membrane and protection for manhole 45/20/1 8,822 0.31% 0.02% 100.0% 0.31% 0.02%
DN068CMHLBAS430 Base slab for manhole 45/20/1 176,435 6.26% 0.34% 100.0% 6.26% 0.34%
DN068CMHLGRP830 GRP liner for manhole 45/20/1 202,900 7.19% 0.39% 100.0% 7.19% 0.39%
DN068CMHLWCP530 Wall concrete and pipe for manhole 45/20/1 220,543 7.82% 0.42% 100.0% 7.82% 0.42%
DN068CMHLCOV630 Cover slab for manhole 45/20/1 26,465 0.94% 0.05% 100.0% 0.94% 0.05%
DN068CMHLDIC790 DI cover for manhole 45/20/1 17,644 0.63% 0.03% 100.0% 0.63% 0.03%
DN068CMHLEMB930 External tanking membrane and protection for manhole 45/20/ 26,465 0.94% 0.05% 100.0% 0.94% 0.05%
DN068CMHLDIC800 Ladder for manhole 45/20/1 17,644 0.63% 0.03% 100.0% 0.63% 0.03%
DN068CMHLBAC950 Backfilling for manhole 45/20/1 70,574 2.50% 0.14% 100.0% 2.50% 0.14%
DN068CMHLDIC810 Reinstatement works 45/20/1 371,073 13.16% 0.71% 100.0% 13.16% 0.71%
House Connection Works (26D, 33ABC) 802,265 100.0%
DN068CHCODEM130 Demolition for existing underground structure 45/20/1 163,048 5.78% 0.31% 100.0% 5.78% 0.31%
DN068CHCOEXC230 Excavation for pipeline and inspection chamber 45/20/1 84,787 3.01% 0.16% 100.0% 3.01% 0.16%
DN068CHCOPIP330 Pipe laying for house connection 45/20/1 109,012 3.87% 0.21% 100.0% 3.87% 0.21%
DN068CHCOBAS430 Base for inspection chamber 45/20/1 39,979 1.42% 0.08% 100.0% 1.42% 0.08%
DN068CHCOWAL530 Wall for inspection chamber 45/20/1 99,948 3.54% 0.19% 100.0% 3.54% 0.19%
DN068CHCOFIN930 Finishing for inspection chamber 45/20/1 29,984 1.06% 0.06% 100.0% 1.06% 0.06%
DN068CHCOCOV630 Cover for inspection chamber 45/20/1 29,984 1.06% 0.06% 100.0% 1.06% 0.06%
DN068CHCOBAC730 Backfilling for house connection 45/20/1 48,450 1.72% 0.09% 100.0% 1.72% 0.09%
DN068CHCOREN830 Reinstatement work for house connection 45/20/1 197,072 6.99% 0.38% 100.0% 6.99% 0.38%
Line 34/1/27/33/2 (4102LM, 120MH) 6,765,910 100.00% 100.00% 12.99%
Trunk Sewer 34/1/27/33/2 To 34/27/33/18 (1087 LM, 20 MH) 6,765,910 100.0%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS350 Obtaining RO from authorities 33/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA250 Traffic Diversion 33/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET150 Setting out 33/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (1087 LM) 468,560 100.0%
DN068CPIPEXC150 Excavation for sewer pipeline 33/2 140,568 2.08% 0.27% 100.0% 2.08% 0.27%
DN068CPIPBED250 Geotextile and Bedding for sewer pipeline 33/2 79,655 1.18% 0.15% 100.0% 1.18% 0.15%
DN068CPIPLAY350 Pipe Laying for sewer pipeline 33/2 140,568 2.08% 0.27% 100.0% 2.08% 0.27%
DN068CPIPPBF450 Partial Backfill for sewer pipeline 33/2 56,227 0.83% 0.11% 100.0% 0.83% 0.11%
DN068CPIPTES550 Test for sewer pipeline 33/2 23,428 0.35% 0.04% 100.0% 0.35% 0.04%
DN068CPIPFBF650 Final Backfill for sewer pipeline 33/2 28,114 0.42% 0.05% 100.0% 0.42% 0.05%
Manhole Works (20 M.H.) 550,350 100.0%
DN068CMHLEXC160 Excavation works for manhole 33/2 33,909 0.50% 0.07% 100.0% 0.50% 0.07%
DN068CMHLBLI260 Blinding for manhole 33/2 6,165 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLTAP360 Tanking membrane and protection for manhole 33/2 3,083 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLBAS460 Base slab for manhole 33/2 61,652 0.91% 0.12% 100.0% 0.91% 0.12%
DN068CMHLGRP860 GRP liner for manhole 33/2 70,900 1.05% 0.14% 100.0% 1.05% 0.14%
DN068CMHLWCP560 Wall concrete and pipe for manhole 33/2 77,065 1.14% 0.15% 100.0% 1.14% 0.15%
DN068CMHLCOV660 Cover slab for manhole 33/2 9,248 0.14% 0.02% 100.0% 0.14% 0.02%
DN068CMHLDIC880 DI cover for manhole 33/2 6,165 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLDIC890 Ladder for manhole 33/2 6,165 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLEMB960 External tanking membrane and protection for manhole 33/2 9,248 0.14% 0.02% 100.0% 0.14% 0.02%
DN068CMHLBAC980 Backfilling for manhole 33/2 24,661 0.36% 0.05% 100.0% 0.36% 0.05%
DN068CMHLDIC900 Reinstatement works 33/2 242,088 3.58% 0.46% 100.0% 3.58% 0.46%
House Connection Works (16D, 4ABC) 153,089 100.0%
DN068CHCODEM180 Demolition for existing underground structure 33/2 19,763 0.29% 0.04% 100.0% 0.29% 0.04%
DN068CHCOEXC280 Excavation for pipeline and inspection chamber 33/2 28,732 0.42% 0.06% 100.0% 0.42% 0.06%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CHCOPIP380 Pipe laying for house connection 33/2 36,940 0.55% 0.07% 100.0% 0.55% 0.07%
DN068CHCOBAS480 Base for inspection chamber 33/2 4,846 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CHCOWAL580 Wall for inspection chamber 33/2 12,115 0.18% 0.02% 100.0% 0.18% 0.02%
DN068CHCOFIN980 Finishing for inspection chamber 33/2 3,635 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CHCOCOV680 Cover for inspection chamber 33/2 3,635 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CHCOBAC780 Backfilling for house connection 33/2 16,418 0.24% 0.03% 100.0% 0.24% 0.03%
DN068CHCOREN880 Reinstatement work for house connection 33/2 27,005 0.40% 0.05% 100.0% 0.40% 0.05%
Foul 34/1/27/33/12 (2304 LM, 84 MH) 4,756,500 100.0%
PipeLine Works (2304 LM) 993,723 100.0%
DN068CPIPEXC400 Excavation for sewer pipeline 33/12 298,117 4.41% 0.57% 100.0% 4.41% 0.57%
DN068CPIPBED500 Geotextile and Bedding for sewer pipeline 33/12 168,933 2.50% 0.32% 100.0% 2.50% 0.32%
DN068CPIPLAY600 Pipe Laying for sewer pipeline 33/12 298,117 4.41% 0.57% 100.0% 4.41% 0.57%
DN068CPIPPBF700 Partial Backfill for sewer pipeline 33/12 119,247 1.76% 0.23% 100.0% 1.76% 0.23%
DN068CPIPTES800 Test for sewer pipeline 33/12 49,686 0.73% 0.10% 100.0% 0.73% 0.10%
DN068CPIPFBF900 Final Backfill for sewer pipeline 33/12 59,623 0.88% 0.11% 100.0% 0.88% 0.11%
Manhole Works (84 M.H.) 1,807,861 100.0%
DN068CMHLEXC410 Excavation works for manhole 33/12 142,388 2.10% 0.27% 100.0% 2.10% 0.27%
DN068CMHLBLI510 Blinding for manhole 33/12 25,889 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CMHLTAP610 Tanking membrane and protection for manhole 33/12 12,944 0.19% 0.02% 100.0% 0.19% 0.02%
DN068CMHLBAS710 Base slab for manhole 33/12 258,888 3.83% 0.50% 100.0% 3.83% 0.50%
DN068CMHLGRP1110 GRP liner for manhole 33/12 297,721 4.40% 0.57% 100.0% 4.40% 0.57%
DN068CMHLWCP810 Wall concrete and pipe for manhole 33/12 323,610 4.78% 0.62% 100.0% 4.78% 0.62%
DN068CMHLCOV910 Cover slab for manhole 33/12 38,833 0.57% 0.07% 100.0% 0.57% 0.07%
DN068CMHLDIC1630 DI cover for manhole 33/12 25,889 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CMHLEMB1210 External tanking membrane and protection for manhole 33/12 38,833 0.57% 0.07% 100.0% 0.57% 0.07%
DN068CMHLDIC1640 Ladder for manhole 33/12 25,889 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CMHLBAC1230 Backfilling for manhole 33/12 103,555 1.53% 0.20% 100.0% 1.53% 0.20%
DN068CMHLDIC1650 Reinstatement works 33/12 513,421 7.59% 0.99% 100.0% 7.59% 0.99%
House Connection Works (27D, 88ABC) 1,954,916 100.0%
DN068CHCODEM160 Demolition for existing underground structure 33/12 434,795 6.43% 0.83% 100.0% 6.43% 0.83%
DN068CHCOEXC260 Excavation for pipeline and inspection chamber 33/12 165,135 2.44% 0.32% 100.0% 2.44% 0.32%
DN068CHCOPIP360 Pipe laying for house connection 33/12 212,316 3.14% 0.41% 100.0% 3.14% 0.41%
DN068CHCOBAS460 Base for inspection chamber 33/12 106,611 1.58% 0.20% 100.0% 1.58% 0.20%
DN068CHCOWAL560 Wall for inspection chamber 33/12 266,528 3.94% 0.51% 100.0% 3.94% 0.51%
DN068CHCOFIN960 Finishing for inspection chamber 33/12 79,958 1.18% 0.15% 100.0% 1.18% 0.15%
DN068CHCOCOV660 Cover for inspection chamber 33/12 79,958 1.18% 0.15% 100.0% 1.18% 0.15%
DN068CHCOBAC760 Backfilling for house connection 33/12 94,363 1.39% 0.18% 100.0% 1.39% 0.18%
DN068CHCOREN860 Reinstatement work for house connection 33/12 515,252 7.62% 0.99% 100.0% 7.62% 0.99%
Foul 34/1/27/33/5 (482 LM, 10 MH) 547,505 100.0%
PipeLine Works (482 LM) 207,836 100.0%
DN068CPIPEXC410 Excavation for sewer pipeline 33/5 62,351 0.92% 0.12% 100.0% 0.92% 0.12%
DN068CPIPBED510 Geotextile and Bedding for sewer pipeline 33/5 35,332 0.52% 0.07% 100.0% 0.52% 0.07%
DN068CPIPLAY610 Pipe Laying for sewer pipeline 33/5 62,351 0.92% 0.12% 100.0% 0.92% 0.12%
DN068CPIPPBF710 Partial Backfill for sewer pipeline 33/5 24,940 0.37% 0.05% 100.0% 0.37% 0.05%
DN068CPIPTES810 Test for sewer pipeline 33/5 10,392 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CPIPFBF910 Final Backfill for sewer pipeline 33/5 12,470 0.18% 0.02% 100.0% 0.18% 0.02%
Manhole Works (10 M.H.) 261,420 100.0%
DN068CMHLEXC420 Excavation works for manhole 33/5 16,944 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CMHLBLI520 Blinding for manhole 33/5 3,081 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLTAP620 Tanking membrane and protection for manhole 33/5 1,540 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLBAS720 Base slab for manhole 33/5 30,808 0.46% 0.06% 100.0% 0.46% 0.06%
DN068CMHLGRP1120 GRP liner for manhole 33/5 35,429 0.52% 0.07% 100.0% 0.52% 0.07%
DN068CMHLWCP820 Wall concrete and pipe for manhole 33/5 38,510 0.57% 0.07% 100.0% 0.57% 0.07%
DN068CMHLCOV920 Cover slab for manhole 33/5 4,621 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLDIC1660 DI cover for manhole 33/5 3,081 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLDIC1670 Ladder for manhole 33/5 3,081 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLEMB1220 External tanking membrane and protection for manhole 33/5 4,621 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLBAC1240 Backfilling for manhole 33/5 12,323 0.18% 0.02% 100.0% 0.18% 0.02%
DN068CMHLDIC1680 Reinstatement works 33/5 107,382 1.59% 0.21% 100.0% 1.59% 0.21%
House Connection Works (18D) 78,249 100.0%
DN068CHCOEXC500 Excavation for pipeline for house connection 33/5 25,858 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CHCOPIP600 Pipe laying for house connection 33/5 33,246 0.49% 0.06% 100.0% 0.49% 0.06%
DN068CHCOBAC1000 Backfilling for pipe for house connection 33/5 14,776 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CHCOREN1100 Marker Post for house connection 33/5 4,368 0.06% 0.01% 100.0% 0.06% 0.01%
Foul 34/1/27/33/3A (229 LM, 6 MH) 289,906 100.0%
PipeLine Works (229 LM) 98,700 100.0%
DN068CPIPEXC420 Excavation for sewer pipeline 33/3A 29,610 0.44% 0.06% 100.0% 0.44% 0.06%
DN068CPIPBED520 Geotextile and Bedding for sewer pipeline 33/3A 16,779 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CPIPLAY620 Pipe Laying for sewer pipeline 33/3A 29,610 0.44% 0.06% 100.0% 0.44% 0.06%
DN068CPIPPBF720 Partial Backfill for sewer pipeline 33/3A 11,844 0.18% 0.02% 100.0% 0.18% 0.02%
DN068CPIPTES820 Test for sewer pipeline 33/3A 4,935 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CPIPFBF920 Final Backfill for sewer pipeline 33/3A 5,922 0.09% 0.01% 100.0% 0.09% 0.01%
Manhole Works (6 M.H.) 143,455 100.0%
DN068CMHLEXC430 Excavation works for manhole 33/3A 10,171 0.15% 0.02% 100.0% 0.15% 0.02%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMHLBLI530 Blinding for manhole 33/3A 1,849 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLTAP630 Tanking membrane and protection for manhole 33/3A 925 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS730 Base slab for manhole 33/3A 18,492 0.27% 0.04% 100.0% 0.27% 0.04%
DN068CMHLGRP1130 GRP liner for manhole 33/3A 21,266 0.31% 0.04% 100.0% 0.31% 0.04%
DN068CMHLWCP830 Wall concrete and pipe for manhole 33/3A 23,115 0.34% 0.04% 100.0% 0.34% 0.04%
DN068CMHLCOV930 Cover slab for manhole 33/3A 2,774 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1690 DI cover for manhole 33/3A 1,849 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLDIC1700 Ladder for manhole 33/3A 1,849 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLEMB1230 External tanking membrane and protection for manhole 33/3A 2,774 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLBAC1250 Backfilling for manhole 33/3A 7,397 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLDIC1710 Reinstatement works 33/3A 50,995 0.75% 0.10% 100.0% 0.75% 0.10%
House Connection Works (11D) 47,751 100.0%
DN068CHCOEXC510 Excavation for pipeline for house connection 33/3A 15,779 0.23% 0.03% 100.0% 0.23% 0.03%
DN068CHCOPIP610 Pipe laying for house connection 33/3A 20,287 0.30% 0.04% 100.0% 0.30% 0.04%
DN068CHCOBAC1010 Backfilling for Pipe for house connection 33/3A 9,016 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CHCOREN1110 Marker post for house connection 33/3A 2,669 0.04% 0.01% 100.0% 0.04% 0.01%
Line 34/1/27/38/1 (750LM, 18MH) 729,448 100.00% 100.00% 1.40%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS360 Obtaining RO from authorities 38/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA260 Traffic Diversion 38/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET160 Setting out 38/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (750 LM) 248,235 100.0%
DN068CPIPEXC160 Excavation for sewer pipeline 38/1 74,471 10.21% 0.14% 100.0% 10.21% 0.14%
DN068CPIPBED260 Geotextile and Bedding for sewer pipeline 38/1 42,200 5.79% 0.08% 100.0% 5.79% 0.08%
DN068CPIPLAY360 Pipe Laying for sewer pipeline 38/1 74,471 10.21% 0.14% 100.0% 10.21% 0.14%
DN068CPIPPBF460 Partial Backfill for sewer pipeline 38/1 29,788 4.08% 0.06% 100.0% 4.08% 0.06%
DN068CPIPTES560 Test for sewer pipeline 38/1 12,412 1.70% 0.02% 100.0% 1.70% 0.02%
DN068CPIPFBF660 Final Backfill for sewer pipeline 38/1 14,894 2.04% 0.03% 100.0% 2.04% 0.03%
Manhole Works (18 M.H.) 376,962 100.0%
DN068CMHLEXC170 Excavation works for manhole 38/1 22,956 3.15% 0.04% 100.0% 3.15% 0.04%
DN068CMHLBLI270 Blinding for manhole 38/1 4,174 0.57% 0.01% 100.0% 0.57% 0.01%
DN068CMHLTAP370 Tanking membrane and protection for manhole 38/1 2,087 0.29% 0.00% 100.0% 0.29% 0.00%
DN068CMHLBAS470 Base slab for manhole 38/1 41,737 5.72% 0.08% 100.0% 5.72% 0.08%
DN068CMHLGRP870 GRP liner for manhole 38/1 47,998 6.58% 0.09% 100.0% 6.58% 0.09%
DN068CMHLWCP570 Wall concrete and pipe for manhole 38/1 52,172 7.15% 0.10% 100.0% 7.15% 0.10%
DN068CMHLCOV670 Cover slab for manhole 38/1 6,261 0.86% 0.01% 100.0% 0.86% 0.01%
DN068CMHLDIC910 DI cover for manhole 38/1 4,174 0.57% 0.01% 100.0% 0.57% 0.01%
DN068CMHLDIC920 Ladder for manhole 38/1 4,174 0.57% 0.01% 100.0% 0.57% 0.01%
DN068CMHLEMB970 External tanking membrane and protection for manhole 38/1 6,261 0.86% 0.01% 100.0% 0.86% 0.01%
DN068CMHLBAC990 Backfilling for manhole 38/1 16,695 2.29% 0.03% 100.0% 2.29% 0.03%
DN068CMHLDIC930 Reinstatement works 38/1 168,276 23.07% 0.32% 100.0% 23.07% 0.32%
House Connection Works (24D) 104,251 100.0%
DN068CHCOEXC270 Excavation for pipeline for house connection 38/1 34,449 4.72% 0.07% 100.0% 4.72% 0.07%
DN068CHCOPIP370 Pipe laying for house connection 38/1 44,292 6.07% 0.09% 100.0% 6.07% 0.09%
DN068CHCOBAC770 Backfilling for Pipe for house connection 38/1 19,685 2.70% 0.04% 100.0% 2.70% 0.04%
DN068CHCOREN870 Marker post for house connection 38/1 5,824 0.80% 0.01% 100.0% 0.80% 0.01%
Line 34/1/27/40/2 (3348LM, 123MH) 6,527,860 100.00% 100.00% 12.53%
Trunk sewer 34/1/27/40/2 To 34/1/27/40/32 6,527,860 100.0%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS370 Obtaining RO from authorities 40/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA270 Traffic Diversion 40/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET170 Setting out 40/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (1186 LM) 474,437 100.0%
DN068CPIPEXC170 Excavation for sewer pipeline 40/2 142,331 2.18% 0.27% 100.0% 2.18% 0.27%
DN068CPIPBED270 Geotextile and Bedding for sewer pipeline 40/2 80,654 1.24% 0.15% 100.0% 1.24% 0.15%
DN068CPIPLAY370 Pipe Laying for sewer pipeline 40/2 142,331 2.18% 0.27% 100.0% 2.18% 0.27%
DN068CPIPPBF470 Partial Backfill for sewer pipeline 40/2 56,932 0.87% 0.11% 100.0% 0.87% 0.11%
DN068CPIPTES570 Test for sewer pipeline 40/2 23,722 0.36% 0.05% 100.0% 0.36% 0.05%
DN068CPIPFBF670 Final Backfill for sewer pipeline 40/2 28,466 0.44% 0.05% 100.0% 0.44% 0.05%
Manhole Works (32 M.H.) 745,339 100.0%
DN068CMHLEXC180 Excavation works for manhole 40/2 53,688 0.82% 0.10% 100.0% 0.82% 0.10%
DN068CMHLBLI280 Blinding for manhole 40/2 9,762 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CMHLTAP380 Tanking membrane and protection for manhole 40/2 4,881 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLBAS480 Base slab for manhole 40/2 97,615 1.50% 0.19% 100.0% 1.50% 0.19%
DN068CMHLGRP880 GRP liner for manhole 40/2 112,257 1.72% 0.22% 100.0% 1.72% 0.22%
DN068CMHLWCP580 Wall concrete and pipe for manhole 40/2 122,019 1.87% 0.23% 100.0% 1.87% 0.23%
DN068CMHLCOV680 Cover slab for manhole 40/2 14,642 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLDIC940 DI cover for manhole 40/2 9,762 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CMHLEMB980 External tanking membrane and protection for manhole 40/2 14,642 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLDIC950 Ladder for manhole 40/2 9,762 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CMHLBAC1000 Backfilling for manhole 40/2 39,046 0.60% 0.07% 100.0% 0.60% 0.07%
DN068CMHLDIC960 Reinstatement works 40/2 257,264 3.94% 0.49% 100.0% 3.94% 0.49%
House Connection Works (7D, 20ABC) 448,195 100.0%
DN068CHCODEM470 Demolition for existing underground structure 40/2 98,817 1.51% 0.19% 100.0% 1.51% 0.19%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CHCOEXC570 Excavation for pipeline and inspection chamber 40/2 38,821 0.59% 0.07% 100.0% 0.59% 0.07%
DN068CHCOPIP670 Pipe laying for house connection 40/2 49,913 0.76% 0.10% 100.0% 0.76% 0.10%
DN068CHCOBAS770 Base for inspection chamber 40/2 24,230 0.37% 0.05% 100.0% 0.37% 0.05%
DN068CHCOWAL870 Wall for inspection chamber 40/2 60,575 0.93% 0.12% 100.0% 0.93% 0.12%
DN068CHCOFIN1270 Finishing for inspection chamber 40/2 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOCOV970 Cover for inspection chamber 40/2 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOBAC1070 Backfilling for house connection 40/2 22,183 0.34% 0.04% 100.0% 0.34% 0.04%
DN068CHCOREN1170 Reinstatement work for house connection 40/2 117,312 1.80% 0.23% 100.0% 1.80% 0.23%
Foul 34/1/27/40/24 (88LM, 5MH) 260,084 100.0%
PipeLine Works (88LM) 35,094 100.0%
DN068CPIPEXC430 Excavation for sewer pipeline 40/24 10,528 0.16% 0.02% 100.0% 0.16% 0.02%
DN068CPIPBED530 Geotextile and Bedding for sewer pipeline 40/24 5,966 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CPIPLAY630 Pipe Laying for sewer pipeline 40/24 10,528 0.16% 0.02% 100.0% 0.16% 0.02%
DN068CPIPPBF730 Partial Backfill for sewer pipeline 40/24 4,211 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CPIPTES830 Test for sewer pipeline 40/24 1,755 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CPIPFBF930 Final Backfill for sewer pipeline 40/24 2,106 0.03% 0.00% 100.0% 0.03% 0.00%
Manhole Works (5M.H.) 95,374 100.0%
DN068CMHLEXC440 Excavation works for manhole 40/24 8,398 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CMHLBLI540 Blinding for manhole 40/24 1,527 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLTAP640 Tanking membrane and protection for manhole 40/24 763 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS740 Base slab for manhole 40/24 15,269 0.23% 0.03% 100.0% 0.23% 0.03%
DN068CMHLGRP1140 GRP liner for manhole 40/24 17,559 0.27% 0.03% 100.0% 0.27% 0.03%
DN068CMHLWCP840 Wall concrete and pipe for manhole 40/24 19,086 0.29% 0.04% 100.0% 0.29% 0.04%
DN068CMHLCOV940 Cover slab for manhole 40/24 2,290 0.04% 0.00% 100.0% 0.04% 0.00%
DN068CMHLDIC1720 DI cover for manhole 40/24 1,527 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLDIC1730 Ladder for manhole 40/24 1,527 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLEMB1240 External tanking membrane and protection for manhole 40/24 2,290 0.04% 0.00% 100.0% 0.04% 0.00%
DN068CMHLBAC1260 Backfilling for manhole 40/24 6,108 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLDIC1740 Reinstatement works 40/24 19,030 0.29% 0.04% 100.0% 0.29% 0.04%
House Connection Works (1D, 6ABC) 129,616 100.0%
DN068CHCODEM420 Demolition for existing underground structure 40/24 29,645 0.45% 0.06% 100.0% 0.45% 0.06%
DN068CHCOEXC520 Excavation for pipeline and inspection chamber 40/24 10,045 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CHCOPIP620 Pipe laying for house connection 40/24 12,915 0.20% 0.02% 100.0% 0.20% 0.02%
DN068CHCOBAS720 Base for inspection chamber 40/24 7,269 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CHCOWAL820 Wall for inspection chamber 40/24 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOFIN1220 Finishing for inspection chamber 40/24 5,452 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CHCOCOV920 Cover for inspection chamber 40/24 5,452 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CHCOBAC1020 Backfilling for house connection 40/24 5,740 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CHCOREN1120 Reinstatement work for house connection 40/24 34,927 0.54% 0.07% 100.0% 0.54% 0.07%
Foul 34/1/27/40/22 (264LM, 11MH) 549,629 100.0%
PipeLine Works (255LM) 105,683 100.0%
DN068CPIPEXC440 Excavation for sewer pipeline 40/22 31,705 0.49% 0.06% 100.0% 0.49% 0.06%
DN068CPIPBED540 Geotextile and Bedding for sewer pipeline 40/22 17,966 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CPIPLAY640 Pipe Laying for sewer pipeline 40/22 31,705 0.49% 0.06% 100.0% 0.49% 0.06%
DN068CPIPPBF740 Partial Backfill for sewer pipeline 40/22 12,682 0.19% 0.02% 100.0% 0.19% 0.02%
DN068CPIPTES840 Test for sewer pipeline 40/22 5,284 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CPIPFBF940 Final Backfill for sewer pipeline 40/22 6,341 0.10% 0.01% 100.0% 0.10% 0.01%
Manhole Works (11M.H.) 225,001 100.0%
DN068CMHLEXC450 Excavation works for manhole 40/22 18,446 0.28% 0.04% 100.0% 0.28% 0.04%
DN068CMHLBLI550 Blinding for manhole 40/22 3,354 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLTAP650 Tanking membrane and protection for manhole 40/22 1,677 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLBAS750 Base slab for manhole 40/22 33,539 0.51% 0.06% 100.0% 0.51% 0.06%
DN068CMHLGRP1150 GRP liner for manhole 40/22 38,570 0.59% 0.07% 100.0% 0.59% 0.07%
DN068CMHLWCP850 Wall concrete and pipe for manhole 40/22 41,923 0.64% 0.08% 100.0% 0.64% 0.08%
DN068CMHLCOV950 Cover slab for manhole 40/22 5,031 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CMHLDIC1750 DI cover for manhole 40/22 3,354 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLDIC1760 Ladder for manhole 40/22 3,354 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLEMB1250 External tanking membrane and protection for manhole 40/22 5,031 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CMHLBAC1270 Backfilling for manhole 40/22 13,416 0.21% 0.03% 100.0% 0.21% 0.03%
DN068CMHLDIC1770 Reinstatement works 40/22 57,307 0.88% 0.11% 100.0% 0.88% 0.11%
House Connection Works (12D, 8ABC) 218,945 100.0%
DN068CHCODEM430 Demolition for existing underground structure 40/22 39,527 0.61% 0.08% 100.0% 0.61% 0.08%
DN068CHCOEXC530 Excavation for pipeline and inspection chamber 40/22 28,630 0.44% 0.05% 100.0% 0.44% 0.05%
DN068CHCOPIP630 Pipe laying for house connection 40/22 36,811 0.56% 0.07% 100.0% 0.56% 0.07%
DN068CHCOBAS730 Base for inspection chamber 40/22 9,692 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CHCOWAL830 Wall for inspection chamber 40/22 24,230 0.37% 0.05% 100.0% 0.37% 0.05%
DN068CHCOFIN1230 Finishing for inspection chamber 40/22 7,269 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CHCOCOV930 Cover for inspection chamber 40/22 7,269 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CHCOBAC1030 Backfilling for house connection 40/22 16,360 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CHCOREN1130 Reinstatement work for house connection 40/22 49,158 0.75% 0.09% 100.0% 0.75% 0.09%
Foul 34/1/27/40/14 (339LM, 13MH) 638,959 100.0%
PipeLine Works (339LM) 135,687 100.0%
DN068CPIPEXC450 Excavation for sewer pipeline 40/14 40,706 0.62% 0.08% 100.0% 0.62% 0.08%
DN068CPIPBED550 Geotextile and Bedding for sewer pipeline 40/14 23,067 0.35% 0.04% 100.0% 0.35% 0.04%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CPIPLAY650 Pipe Laying for sewer pipeline 40/14 40,706 0.62% 0.08% 100.0% 0.62% 0.08%
DN068CPIPPBF750 Partial Backfill for sewer pipeline 40/14 16,283 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CPIPTES850 Test for sewer pipeline 40/14 6,784 0.10% 0.01% 100.0% 0.10% 0.01%
DN068CPIPFBF950 Final Backfill for sewer pipeline 40/14 8,141 0.12% 0.02% 100.0% 0.12% 0.02%
Manhole Works (13M.H.) 271,846 100.0%
DN068CMHLEXC460 Excavation works for manhole 40/14 21,810 0.33% 0.04% 100.0% 0.33% 0.04%
DN068CMHLBLI560 Blinding for manhole 40/14 3,965 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CMHLTAP660 Tanking membrane and protection for manhole 40/14 1,983 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLBAS760 Base slab for manhole 40/14 39,654 0.61% 0.08% 100.0% 0.61% 0.08%
DN068CMHLGRP1160 GRP liner for manhole 40/14 45,602 0.70% 0.09% 100.0% 0.70% 0.09%
DN068CMHLWCP860 Wall concrete and pipe for manhole 40/14 49,567 0.76% 0.10% 100.0% 0.76% 0.10%
DN068CMHLCOV960 Cover slab for manhole 40/14 5,948 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLDIC1780 DI cover for manhole 40/14 3,965 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CMHLDIC1790 Ladder for manhole 40/14 3,965 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CMHLEMB1260 External tanking membrane and protection for manhole 40/14 5,948 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLBAC1280 Backfilling for manhole 40/14 15,862 0.24% 0.03% 100.0% 0.24% 0.03%
DN068CMHLDIC1800 Reinstatement works 40/14 73,577 1.13% 0.14% 100.0% 1.13% 0.14%
House Connection Works (10D, 9ABC) 231,426 100.0%
DN068CHCODEM440 Demolition for existing underground structure 40/14 44,468 0.68% 0.09% 100.0% 0.68% 0.09%
DN068CHCOEXC540 Excavation for pipeline and inspection chamber 40/14 27,296 0.42% 0.05% 100.0% 0.42% 0.05%
DN068CHCOPIP640 Pipe laying for house connection 40/14 35,095 0.54% 0.07% 100.0% 0.54% 0.07%
DN068CHCOBAS740 Base for inspection chamber 40/14 10,903 0.17% 0.02% 100.0% 0.17% 0.02%
DN068CHCOWAL840 Wall for inspection chamber 40/14 27,259 0.42% 0.05% 100.0% 0.42% 0.05%
DN068CHCOFIN1240 Finishing for inspection chamber 40/14 8,178 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CHCOCOV940 Cover for inspection chamber 40/14 8,178 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CHCOBAC1040 Backfilling for house connection 40/14 15,598 0.24% 0.03% 100.0% 0.24% 0.03%
DN068CHCOREN1140 Reinstatement work for house connection 40/14 54,453 0.83% 0.10% 100.0% 0.83% 0.10%
Foul 34/1/27/40/9 (411LM, 15MH) 834,899 100.0%
PipeLine Works (411LM) 164,486 100.0%
DN068CPIPEXC460 Excavation for sewer pipeline 40/9 49,346 0.76% 0.09% 100.0% 0.76% 0.09%
DN068CPIPBED560 Geotextile and Bedding for sewer pipeline 40/9 27,963 0.43% 0.05% 100.0% 0.43% 0.05%
DN068CPIPLAY660 Pipe Laying for sewer pipeline 40/9 49,346 0.76% 0.09% 100.0% 0.76% 0.09%
DN068CPIPPBF760 Partial Backfill for sewer pipeline 40/9 19,738 0.30% 0.04% 100.0% 0.30% 0.04%
DN068CPIPTES860 Test for sewer pipeline 40/9 8,224 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CPIPFBF960 Final Backfill for sewer pipeline 40/9 9,869 0.15% 0.02% 100.0% 0.15% 0.02%
Manhole Works (15M.H.) 318,036 100.0%
DN068CMHLEXC470 Excavation works for manhole 40/9 25,173 0.39% 0.05% 100.0% 0.39% 0.05%
DN068CMHLBLI570 Blinding for manhole 40/9 4,577 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLTAP670 Tanking membrane and protection for manhole 40/9 2,288 0.04% 0.00% 100.0% 0.04% 0.00%
DN068CMHLBAS770 Base slab for manhole 40/9 45,769 0.70% 0.09% 100.0% 0.70% 0.09%
DN068CMHLGRP1170 GRP liner for manhole 40/9 52,634 0.81% 0.10% 100.0% 0.81% 0.10%
DN068CMHLWCP870 Wall concrete and pipe for manhole 40/9 57,211 0.88% 0.11% 100.0% 0.88% 0.11%
DN068CMHLCOV970 Cover slab for manhole 40/9 6,865 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLDIC1810 DI cover for manhole 40/9 4,577 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLDIC1820 Ladder for manhole 40/9 4,577 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLEMB1270 External tanking membrane and protection for manhole 40/9 6,865 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLBAC1290 Backfilling for manhole 40/9 18,308 0.28% 0.04% 100.0% 0.28% 0.04%
DN068CMHLDIC1830 Reinstatement works 40/9 89,193 1.37% 0.17% 100.0% 1.37% 0.17%
House Connection Works (9D, 15ABC) 352,377 100.0%
DN068CHCODEM450 Demolition for existing underground structure 40/9 74,113 1.14% 0.14% 100.0% 1.14% 0.14%
DN068CHCOEXC550 Excavation for pipeline and inspection chamber 40/9 34,478 0.53% 0.07% 100.0% 0.53% 0.07%
DN068CHCOPIP650 Pipe laying for house connection 40/9 44,329 0.68% 0.09% 100.0% 0.68% 0.09%
DN068CHCOBAS750 Base for inspection chamber 40/9 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOWAL850 Wall for inspection chamber 40/9 45,431 0.70% 0.09% 100.0% 0.70% 0.09%
DN068CHCOFIN1250 Finishing for inspection chamber 40/9 13,629 0.21% 0.03% 100.0% 0.21% 0.03%
DN068CHCOCOV950 Cover for inspection chamber 40/9 13,629 0.21% 0.03% 100.0% 0.21% 0.03%
DN068CHCOBAC1050 Backfilling for house connection 40/9 19,702 0.30% 0.04% 100.0% 0.30% 0.04%
DN068CHCOREN1150 Reinstatement work for house connection 40/9 88,894 1.36% 0.17% 100.0% 1.36% 0.17%
Foul 34/1/27/40/5 (1060LM, 47MH) 2,576,320 100.0%
PipeLine Works (1060LM) 424,073 100.0%
DN068CPIPEXC470 Excavation for sewer pipeline 40/5 127,222 1.95% 0.24% 100.0% 1.95% 0.24%
DN068CPIPBED570 Geotextile and Bedding for sewer pipeline 40/5 72,093 1.10% 0.14% 100.0% 1.10% 0.14%
DN068CPIPLAY670 Pipe Laying for sewer pipeline 40/5 127,222 1.95% 0.24% 100.0% 1.95% 0.24%
DN068CPIPPBF770 Partial Backfill for sewer pipeline 40/5 50,889 0.78% 0.10% 100.0% 0.78% 0.10%
DN068CPIPTES870 Test for sewer pipeline 40/5 21,204 0.32% 0.04% 100.0% 0.32% 0.04%
DN068CPIPFBF970 Final Backfill for sewer pipeline 40/5 25,444 0.39% 0.05% 100.0% 0.39% 0.05%
Manhole Works (47M.H.) 946,498 100.0%
DN068CMHLEXC480 Excavation works for manhole 40/5 78,820 1.21% 0.15% 100.0% 1.21% 0.15%
DN068CMHLBLI580 Blinding for manhole 40/5 14,331 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLTAP680 Tanking membrane and protection for manhole 40/5 7,165 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLBAS780 Base slab for manhole 40/5 143,309 2.20% 0.28% 100.0% 2.20% 0.28%
DN068CMHLGRP1180 GRP liner for manhole 40/5 164,805 2.52% 0.32% 100.0% 2.52% 0.32%
DN068CMHLWCP880 Wall concrete and pipe for manhole 40/5 179,136 2.74% 0.34% 100.0% 2.74% 0.34%
DN068CMHLCOV980 Cover slab for manhole 40/5 21,496 0.33% 0.04% 100.0% 0.33% 0.04%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMHLDIC1840 DI cover for manhole 40/5 14,331 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLEMB1280 External tanking membrane and protection for manhole 40/5 21,496 0.33% 0.04% 100.0% 0.33% 0.04%
DN068CMHLDIC1850 Ladder for manhole 40/5 14,331 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLBAC1300 Backfilling for manhole 40/5 57,324 0.88% 0.11% 100.0% 0.88% 0.11%
DN068CMHLDIC1860 Reinstatement works 40/5 229,954 3.52% 0.44% 100.0% 3.52% 0.44%
House Connection Works (18D, 54ABC) 1,205,749 100.0%
DN068CHCODEM460 Demolition for existing underground structure 40/5 266,806 4.09% 0.51% 100.0% 4.09% 0.51%
DN068CHCOEXC560 Excavation for pipeline and inspection chamber 40/5 103,361 1.58% 0.20% 100.0% 1.58% 0.20%
DN068CHCOPIP660 Pipe laying for house connection 40/5 132,892 2.04% 0.26% 100.0% 2.04% 0.26%
DN068CHCOBAS760 Base for inspection chamber 40/5 65,420 1.00% 0.13% 100.0% 1.00% 0.13%
DN068CHCOWAL860 Wall for inspection chamber 40/5 163,551 2.51% 0.31% 100.0% 2.51% 0.31%
DN068CHCOFIN1260 Finishing for inspection chamber 40/5 49,065 0.75% 0.09% 100.0% 0.75% 0.09%
DN068CHCOCOV960 Cover for inspection chamber 40/5 49,065 0.75% 0.09% 100.0% 0.75% 0.09%
DN068CHCOBAC1060 Backfilling for house connection 40/5 59,063 0.90% 0.11% 100.0% 0.90% 0.11%
DN068CHCOREN1160 Reinstatement work for house connection 40/5 316,525 4.85% 0.61% 100.0% 4.85% 0.61%
Line 34/1/27/30/1 (603LM, 18MH) 774,319 100.00% 100.00% 1.49%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS300 Obtaining RO from authorities 30/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA200 Traffic Diversion 30/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET100 Setting out 30/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (603 LM) 220,564 100.0%
DN068CPIPEXC100 Excavation for sewer pipeline 30/1 66,169 8.55% 0.13% 100.0% 8.55% 0.13%
DN068CPIPBED200 Geotextile and Bedding for sewer pipeline 30/1 37,496 4.84% 0.07% 100.0% 4.84% 0.07%
DN068CPIPLAY300 Pipe Laying for sewer pipeline 30/1 66,169 8.55% 0.13% 100.0% 8.55% 0.13%
DN068CPIPPBF400 Partial Backfill for sewer pipeline 30/1 26,468 3.42% 0.05% 100.0% 3.42% 0.05%
DN068CPIPTES500 Test for sewer pipeline 30/1 11,028 1.42% 0.02% 100.0% 1.42% 0.02%
DN068CPIPFBF600 Final Backfill for sewer pipeline 30/1 13,234 1.71% 0.03% 100.0% 1.71% 0.03%
Manhole Works (18 M.H.) 352,781 100.0%
DN068CMHLEXC100 Excavation works for manhole 30/1 24,714 3.19% 0.05% 100.0% 3.19% 0.05%
DN068CMHLBLI200 Blinding for manhole 30/1 4,494 0.58% 0.01% 100.0% 0.58% 0.01%
DN068CMHLTAP300 Tanking membrane and protection for manhole 30/1 2,247 0.29% 0.00% 100.0% 0.29% 0.00%
DN068CMHLBAS400 Base slab for manhole 30/1 44,935 5.80% 0.09% 100.0% 5.80% 0.09%
DN068CMHLGRP800 GRP liner for manhole 30/1 51,675 6.67% 0.10% 100.0% 6.67% 0.10%
DN068CMHLWCP500 Wall concrete and pipe for manhole 30/1 56,169 7.25% 0.11% 100.0% 7.25% 0.11%
DN068CMHLCOV600 Cover slab for manhole 30/1 6,740 0.87% 0.01% 100.0% 0.87% 0.01%
DN068CMHLDIC700 DI cover for manhole 30/1 4,494 0.58% 0.01% 100.0% 0.58% 0.01%
DN068CMHLDIC710 Ladder for manhole 30/1 4,494 0.58% 0.01% 100.0% 0.58% 0.01%
DN068CMHLEMB900 External tanking membrane and protection for manhole 30/1 6,740 0.87% 0.01% 100.0% 0.87% 0.01%
DN068CMHLBAC920 Backfilling for manhole 30/1 17,974 2.32% 0.03% 100.0% 2.32% 0.03%
DN068CMHLDIC720 Reinstatement works 30/1 128,106 16.54% 0.25% 100.0% 16.54% 0.25%
House Connection Works (12D, 7ABC) 200,973 100.0%
DN068CHCODEM100 Demolition for existing underground structure 30/1 34,586 4.47% 0.07% 100.0% 4.47% 0.07%
DN068CHCOEXC200 Excavation for pipeline and inspection chamber 30/1 28,213 3.64% 0.05% 100.0% 3.64% 0.05%
DN068CHCOPIP300 Pipe laying for house connection 30/1 36,274 4.68% 0.07% 100.0% 4.68% 0.07%
DN068CHCOBAS400 Base for inspection chamber 30/1 8,480 1.10% 0.02% 100.0% 1.10% 0.02%
DN068CHCOWAL500 Wall for inspection chamber 30/1 21,201 2.74% 0.04% 100.0% 2.74% 0.04%
DN068CHCOFIN900 Finishing for inspection chamber 30/1 6,360 0.82% 0.01% 100.0% 0.82% 0.01%
DN068CHCOCOV600 Cover for inspection chamber 30/1 6,360 0.82% 0.01% 100.0% 0.82% 0.01%
DN068CHCOBAC700 Backfilling for house connection 30/1 16,122 2.08% 0.03% 100.0% 2.08% 0.03%
DN068CHCOREN800 Reinstatement work for house connection 30/1 43,377 5.60% 0.08% 100.0% 5.60% 0.08%
Line 34/1/27/24 (1324LM, 32MH) 1,226,714 100.00% 100.00% 2.35%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA290 Traffic Diversion 24 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET110 Setting out 24 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (1324 LM) 422,007 100.0%
DN068CPIPEXC110 Excavation for sewer pipeline 24 126,602 10.32% 0.24% 100.0% 10.32% 0.24%
DN068CPIPBED210 Geotextile and Bedding for sewer pipeline 24 71,741 5.85% 0.14% 100.0% 5.85% 0.14%
DN068CPIPLAY310 Pipe Laying for sewer pipeline 24 126,602 10.32% 0.24% 100.0% 10.32% 0.24%
DN068CPIPPBF410 Partial Backfill for sewer pipeline 24 50,641 4.13% 0.10% 100.0% 4.13% 0.10%
DN068CPIPTES510 Test for sewer pipeline 24 21,100 1.72% 0.04% 100.0% 1.72% 0.04%
DN068CPIPFBF610 Final Backfill for sewer pipeline 24 25,320 2.06% 0.05% 100.0% 2.06% 0.05%
Manhole Works (32 M.H.) 635,300 100.0%
DN068CMHLEXC120 Excavation works for manhole 24 37,815 3.08% 0.07% 100.0% 3.08% 0.07%
DN068CMHLBLI220 Blinding for manhole 24 6,876 0.56% 0.01% 100.0% 0.56% 0.01%
DN068CMHLTAP320 Tanking membrane and protection for manhole 24 3,438 0.28% 0.01% 100.0% 0.28% 0.01%
DN068CMHLBAS420 Base slab for manhole 24 68,755 5.60% 0.13% 100.0% 5.60% 0.13%
DN068CMHLGRP820 GRP liner for manhole 24 79,068 6.45% 0.15% 100.0% 6.45% 0.15%
DN068CMHLWCP520 Wall concrete and pipe for manhole 24 85,943 7.01% 0.16% 100.0% 7.01% 0.16%
DN068CMHLCOV620 Cover slab for manhole 24 10,313 0.84% 0.02% 100.0% 0.84% 0.02%
DN068CMHLDIC760 DI cover for manhole 24 6,876 0.56% 0.01% 100.0% 0.56% 0.01%
DN068CMHLEMB920 External tanking membrane and protection for manhole 24 10,313 0.84% 0.02% 100.0% 0.84% 0.02%
DN068CMHLDIC770 Ladder for manhole 24 6,876 0.56% 0.01% 100.0% 0.56% 0.01%
DN068CMHLBAC940 Backfilling for manhole 24 27,502 2.24% 0.05% 100.0% 2.24% 0.05%
DN068CMHLDIC780 Reinstatement works 24 291,527 23.76% 0.56% 100.0% 23.76% 0.56%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
House Connection Works (39D) 169,408 100.0%
DN068CHCOEXC220 Excavation for pipeline and inspection chamber 24 55,980 4.56% 0.11% 100.0% 4.56% 0.11%
DN068CHCOPIP320 Pipe laying for house connection 24 71,975 5.87% 0.14% 100.0% 5.87% 0.14%
DN068CHCOBAC720 Backfilling for Pipe for house connection 24 31,989 2.61% 0.06% 100.0% 2.61% 0.06%
DN068CHCOREN820 Marker Post for house connection 24 9,464 0.77% 0.02% 100.0% 0.77% 0.02%
Line 34/1/27/27 (7003LM, 227MH) 17,359,260 100.00% 100.00% 33.32%
Trunk Sewer 34/1/27/27/24 To 34/1/27/27/41 (518 LM, 17 MH) 2,649,075 100.0%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS440 Obtaining RO from authorities 27 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA340 Traffic Diversion 27 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET240 Setting out 27 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (518 LM) 186,920 100.0%
DN068CPIPEXC240 Excavation for sewer pipeline 27 56,076 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPBED340 Geotextile and Bedding for sewer pipeline 27 31,777 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY440 Pipe Laying for sewer pipeline 27 56,076 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF540 Partial Backfill for sewer pipeline 27 22,431 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES640 Test for sewer pipeline 27 9,346 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF740 Final Backfill for sewer pipeline 27 11,215 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (17 M.H.) 386,470 100.0%
DN068CMHLEXC250 Excavation works for manhole 27 29,869 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLBLI350 Blinding for manhole 27 5,431 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP450 Tanking membrane and protection for manhole 27 2,715 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS550 Base slab for manhole 27 54,307 0.31% 0.10% 100.0% 0.31% 0.10%
DN068CMHLGRP950 GRP liner for manhole 27 62,453 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMHLWCP650 Wall concrete and pipe for manhole 27 67,883 0.39% 0.13% 100.0% 0.39% 0.13%
DN068CMHLCOV750 Cover slab for manhole 27 8,146 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1150 DI cover for manhole 27 5,431 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1160 Ladder for manhole 27 5,431 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1050 External tanking membrane and protection for manhole 27 8,146 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC1070 Backfilling for manhole 27 21,723 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLDIC1170 Reinstatement works 27 114,937 0.66% 0.22% 100.0% 0.66% 0.22%
House Connection Works (10D, 10ABC) 252,258 100.0%
DN068CHCODEM480 Demolition for existing underground structure 27 49,409 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CHCOEXC580 Excavation for pipeline and inspection chamber 27 28,715 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOPIP680 Pipe laying for house connection 27 36,919 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CHCOBAS780 Base for inspection chamber 27 12,115 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOWAL880 Wall for inspection chamber 27 30,287 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOFIN1280 Finishing for inspection chamber 27 9,086 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOCOV980 Cover for inspection chamber 27 9,086 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOBAC1080 Backfilling for house connection 27 16,408 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOREN1180 Reinstatement work for house connection 27 60,234 0.35% 0.12% 100.0% 0.35% 0.12%
Foul 34/1/27/27/27 (134 LM, 2 MH) 152,170 100.0%
PipeLine Works (134 LM) 48,424 100.0%
DN068CPIPEXC280 Excavation for sewer pipeline 27/27 14,527 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPBED380 Geotextile and Bedding for sewer pipeline 27/27 8,232 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPLAY480 Pipe Laying for sewer pipeline 27/27 14,527 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPPBF580 Partial Backfill for sewer pipeline 27/27 5,811 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPTES680 Test for sewer pipeline 27/27 2,421 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CPIPFBF780 Final Backfill for sewer pipeline 27/27 2,905 0.02% 0.01% 100.0% 0.02% 0.01%
Manhole Works (2 M.H.) 61,998 100.0%
DN068CMHLEXC290 Excavation works for manhole 27/27 3,544 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBLI390 Blinding for manhole 27/27 644 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLTAP490 Tanking membrane and protection for manhole 27/27 322 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLBAS590 Base slab for manhole 27/27 6,444 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLGRP990 GRP liner for manhole 27/27 7,411 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLWCP690 Wall concrete and pipe for manhole 27/27 8,056 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLCOV790 Cover slab for manhole 27/27 967 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1270 DI cover for manhole 27/27 644 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLDIC1280 Ladder for manhole 27/27 644 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLEMB1090 External tanking membrane and protection for manhole 27/27 967 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAC1110 Backfilling for manhole 27/27 2,578 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1290 Reinstatement works 27/27 29,776 0.17% 0.06% 100.0% 0.17% 0.06%
House Connection Works (2ABC) 41,749 100.0%
DN068CHCODEM280 Demolition for existing underground structure 27/27 9,882 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CHCOEXC380 Excavation for pipeline and inspection chamber 27/27 2,867 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOPIP480 Pipe laying for house connection 27/27 3,686 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOBAS580 Base for inspection chamber 27/27 2,423 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOWAL680 Wall for inspection chamber 27/27 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOFIN1080 Finishing for inspection chamber 27/27 1,817 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOCOV780 Cover for inspection chamber 27/27 1,817 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOBAC880 Backfilling for house connection 27/27 1,638 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOREN980 Reinstatement work 27/27 11,561 0.07% 0.02% 100.0% 0.07% 0.02%
Foul 34/1/27/27/29 (146 LM, 6 MH) 306,922 100.0%
PipeLine Works (146 LM) 52,808 100.0%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CPIPEXC270 Excavation for sewer pipeline 27/29 15,842 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPBED370 Geotextile and Bedding for sewer pipeline 27/29 8,977 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPLAY470 Pipe Laying for sewer pipeline 27/29 15,842 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPPBF570 Partial Backfill for sewer pipeline 27/29 6,337 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CPIPTES670 Test for sewer pipeline 27/29 2,640 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF770 Final Backfill for sewer pipeline 27/29 3,169 0.02% 0.01% 100.0% 0.02% 0.01%
Manhole Works (6 M.H.) 128,051 100.0%
DN068CMHLEXC280 Excavation works for manhole 27/29 10,514 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBLI380 Blinding for manhole 27/29 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP480 Tanking membrane and protection for manhole 27/29 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS580 Base slab for manhole 27/29 19,116 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CMHLGRP980 GRP liner for manhole 27/29 21,983 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLWCP680 Wall concrete and pipe for manhole 27/29 23,895 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CMHLCOV780 Cover slab for manhole 27/29 2,867 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1240 DI cover for manhole 27/29 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1250 Ladder for manhole 27/29 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1080 External tanking membrane and protection for manhole 27/29 2,867 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1100 Backfilling for manhole 27/29 7,646 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1260 Reinstatement works 27/29 32,472 0.19% 0.06% 100.0% 0.19% 0.06%
House Connection Works (5D, 5B) 126,063 100.0%
DN068CHCODEM270 Demolition for existing underground structure 27/29 24,704 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOEXC370 Excavation for pipeline and inspection chamber 27/29 14,334 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CHCOPIP470 Pipe laying for house connection 27/29 18,430 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOBAS570 Base for inspection chamber 27/29 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL670 Wall for inspection chamber 27/29 15,144 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOFIN1070 Finishing for inspection chamber 27/29 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOCOV770 Cover for inspection chamber 27/29 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOBAC870 Backfilling for house connection 27/29 8,191 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOREN970 Reinstatement work for house connection 27/29 30,117 0.17% 0.06% 100.0% 0.17% 0.06%
Foul 34/1/27/27/30 (515 LM, 18 MH) 1,026,339 100.0%
PipeLine Works (515 LM) 185,725 100.0%
DN068CPIPEXC260 Excavation for sewer pipeline 27/30 55,717 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPBED360 Geotextile and Bedding for sewer pipeline 27/30 31,573 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY460 Pipe Laying for sewer pipeline 27/30 55,717 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF560 Partial Backfill for sewer pipeline 27/30 22,287 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES660 Test for sewer pipeline 27/30 9,286 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF760 Final Backfill for sewer pipeline 27/30 11,144 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (18 M.H.) 401,302 100.0%
DN068CMHLEXC270 Excavation works for manhole 27/30 31,581 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMHLBLI370 Blinding for manhole 27/30 5,742 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP470 Tanking membrane and protection for manhole 27/30 2,871 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS570 Base slab for manhole 27/30 57,420 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CMHLGRP970 GRP liner for manhole 27/30 66,033 0.38% 0.13% 100.0% 0.38% 0.13%
DN068CMHLWCP670 Wall concrete and pipe for manhole 27/30 71,775 0.41% 0.14% 100.0% 0.41% 0.14%
DN068CMHLCOV770 Cover slab for manhole 27/30 8,613 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1210 DI cover for manhole 27/30 5,742 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1220 Ladder for manhole 27/30 5,742 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1070 External tanking membrane and protection for manhole 27/30 8,613 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC1090 Backfilling for manhole 27/30 22,968 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLDIC1230 Reinstatement works 27/30 114,202 0.66% 0.22% 100.0% 0.66% 0.22%
House Connection Works (5D, 20ABC) 439,312 100.0%
DN068CHCODEM260 Demolition for existing underground structure 27/30 98,817 0.57% 0.19% 100.0% 0.57% 0.19%
DN068CHCOEXC360 Excavation for pipeline and inspection chamber 27/30 35,882 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CHCOPIP460 Pipe laying for house connection 27/30 46,134 0.27% 0.09% 100.0% 0.27% 0.09%
DN068CHCOBAS560 Base for inspection chamber 27/30 24,230 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOWAL660 Wall for inspection chamber 27/30 60,575 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CHCOFIN1060 Finishing for inspection chamber 27/30 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOCOV760 Cover for inspection chamber 27/30 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOBAC860 Backfilling for house connection 27/30 20,504 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CHCOREN960 Reinstatement work for house connection 27/30 116,827 0.67% 0.22% 100.0% 0.67% 0.22%
Foul 34/1/27/27/34 (179 LM, 7 MH) 337,995 100.0%
PipeLine Works (179 LM) 64,565 100.0%
DN068CPIPEXC250 Excavation for sewer pipeline 27/34 19,370 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CPIPBED350 Geotextile and Bedding for sewer pipeline 27/34 10,976 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPLAY450 Pipe Laying for sewer pipeline 27/34 19,370 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CPIPPBF550 Partial Backfill for sewer pipeline 27/34 7,748 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CPIPTES650 Test for sewer pipeline 27/34 3,228 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF750 Final Backfill for sewer pipeline 27/34 3,874 0.02% 0.01% 100.0% 0.02% 0.01%
Manhole Works (7 M.H.) 151,572 100.0%
DN068CMHLEXC260 Excavation works for manhole 27/34 12,306 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLBLI360 Blinding for manhole 27/34 2,237 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP460 Tanking membrane and protection for manhole 27/34 1,119 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS560 Base slab for manhole 27/34 22,374 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLGRP960 GRP liner for manhole27/34 25,730 0.15% 0.05% 100.0% 0.15% 0.05%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMHLWCP660 Wall concrete and pipe for manhole 27/34 27,968 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CMHLCOV760 Cover slab for manhole 27/34 3,356 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1180 DI cover for manhole 27/34 2,237 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1190 Ladder for manhole 27/34 2,237 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1060 External tanking membrane and protection for manhole 27/34 3,356 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1080 Backfilling for manhole 27/34 8,950 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1200 Reinstatement works 27/34 39,701 0.23% 0.08% 100.0% 0.23% 0.08%
House Connection Works (4D, 5ABC) 121,857 100.0%
DN068CHCODEM250 Demolition for existing underground structure 27/34 24,704 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOEXC350 Excavation for pipeline and inspection chamber 27/34 12,947 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOPIP450 Pipe laying for house connection 27/34 16,646 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOBAS550 Base for inspection chamber 27/34 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL650 Wall for inspection chamber 27/34 15,144 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOFIN1050 Finishing for inspection chamber 27/34 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOCOV750 Cover for inspection chamber 27/34 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOBAC850 Backfilling for house connection 27/34 7,398 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CHCOREN950 Reinstatement work for house connection 27/34 29,874 0.17% 0.06% 100.0% 0.17% 0.06%
Trunk Sewer Microtunnelling 34/1/27/27 To 34/1/27/27/24 (1480 LM, 26 MH, 1 14,710,184 100.0%
Pipeline Works (34/1/27/27/2 To 34/1/27/27 102LM) 563,606 100.0%
DN068CMITEXC100 Excavation for jacking shaft 48,609 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CMITCJS110 Concrete for jacking shaft 24,304 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CMITEXR120 Excavation for recieving shaft 48,609 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CMITFIR200 1st Tunneling & Driving the Pipes + Equipment 300,309 1.73% 0.58% 100.0% 1.73% 0.58%
DN068CMITSEC300 2nd Tunneling & Driving the Pipes and dismantle 141,775 0.82% 0.27% 100.0% 0.82% 0.27%
Pipeline Works (34/1/27/27/4 To 34/1/27/27/2 127LM) 504,429 100.0%
DN068CMITEXC130 Excavation for jacking shaft 60,532 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CMITCJS140 Concrete for jacking shaft 30,266 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITEXR150 Excavation for recieving shaft 60,532 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CMITFIR210 1st Tunneling & Driving the Pipes 176,550 1.02% 0.34% 100.0% 1.02% 0.34%
DN068CMITSEC310 2nd Tunneling & Driving the Pipes and dismantle 176,550 1.02% 0.34% 100.0% 1.02% 0.34%
Pipeline Works (34/1/27/27/6 To 34/1/27/27/4 107LM) 425,061 100.0%
DN068CMITEXC160 Excavation for jacking shaft 51,007 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITCJS170 Concrete for jacking shaft 25,504 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMITEXR180 Excavation for recieving shaft 51,007 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITFIR220 1st Tunneling & Driving the Pipes 148,771 0.86% 0.29% 100.0% 0.86% 0.29%
DN068CMITSEC320 2nd Tunneling & Driving the Pipes and dismantle 148,771 0.86% 0.29% 100.0% 0.86% 0.29%
Pipeline Works (34/1/27/27/7 To 34/1/27/27/6 130LM) 516,187 100.0%
DN068CMITEXC190 Excavation for jacking shaft 61,942 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMITCJS230 Concrete for jacking shaft 30,971 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMITEXR240 Excavation for recieving shaft 61,942 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMITFIR250 1st Tunneling & Driving the Pipes 180,666 1.04% 0.35% 100.0% 1.04% 0.35%
DN068CMITSEC330 2nd Tunneling & Driving the Pipes and dismantle 180,666 1.04% 0.35% 100.0% 1.04% 0.35%
Pipeline Works (34/1/27/27/9A To 34/1/27/27/7 124LM) 492,671 100.0%
DN068CMITEXC260 Excavation for jacking shaft 59,121 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CMITCJS270 Concrete for jacking shaft 29,560 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITEXR280 Excavation for recieving shaft 59,121 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CMITFIR290 1st Tunneling & Driving the Pipes 172,435 0.99% 0.33% 100.0% 0.99% 0.33%
DN068CMITSEC340 2nd Tunneling & Driving the Pipes and dismantle 172,435 0.99% 0.33% 100.0% 0.99% 0.33%
Pipeline Works (34/1/27/27/10 To 34/1/27/27/9A 104LM) 413,302 100.0%
DN068CMITEXC350 Excavation for jacking shaft 49,596 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITCJS360 Concrete for jacking shaft 24,798 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CMITEXR370 Excavation for recieving shaft 49,596 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITFIR380 1st Tunneling & Driving the Pipes 144,656 0.83% 0.28% 100.0% 0.83% 0.28%
DN068CMITSEC390 2nd Tunneling & Driving the Pipes and dismantle 144,656 0.83% 0.28% 100.0% 0.83% 0.28%
Pipeline Works (34/1/27/27/12 To 34/1/27/27/10 154LM) 612,017 100.0%
DN068CMITEXC400 Excavation for jacking shaft 73,442 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITCJS410 Concrete for jacking shaft 36,721 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMITEXR420 Excavation for recieving shaft 73,442 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITFIR430 1st Tunneling & Driving the Pipes 214,206 1.23% 0.41% 100.0% 1.23% 0.41%
DN068CMITSEC440 2nd Tunneling & Driving the Pipes and dismantle 214,206 1.23% 0.41% 100.0% 1.23% 0.41%
Pipeline Works (34/1/27/27/14 To 34/1/27/27/12 152LM) 603,786 100.0%
DN068CMITEXC450 Excavation for jacking shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITCJS460 Concrete for jacking shaft 36,227 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMITEXR470 Excavation for recieving shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITFIR480 1st Tunneling & Driving the Pipes 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
DN068CMITSEC490 2nd Tunneling & Driving the Pipes and dismantle 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
Pipeline Works (34/1/27/27/16 To 34/1/27/27/14 152LM) 603,786 100.0%
DN068CMITEXC500 Excavation for jacking shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITCJS510 Concrete for jacking shaft 36,227 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMITEXR520 Excavation for recieving shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITFIR530 1st Tunneling & Driving the Pipes 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
DN068CMITSEC540 2nd Tunneling & Driving the Pipes and dismantle 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
Pipeline Works (34/1/27/27/18 To 34/1/27/27/16 83LM) 329,819 100.0%
DN068CMITEXC550 Excavation for jacking shaft 39,578 0.23% 0.08% 100.0% 0.23% 0.08%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMITCJS560 Concrete for jacking shaft 19,789 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CMITEXR570 Excavation for recieving shaft 39,578 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CMITFIR580 1st Tunneling & Driving the Pipes 115,437 0.66% 0.22% 100.0% 0.66% 0.22%
DN068CMITSEC590 2nd Tunneling & Driving the Pipes and dismantle 115,437 0.66% 0.22% 100.0% 0.66% 0.22%
Pipeline Works (34/1/27/27/20 To 34/1/27/27/18 90LM) 357,451 100.0%
DN068CMITEXC600 Excavation for jacking shaft 42,894 0.25% 0.08% 100.0% 0.25% 0.08%
DN068CMITCJS610 Concrete for jacking shaft 21,447 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CMITEXR620 Excavation for recieving shaft 42,894 0.25% 0.08% 100.0% 0.25% 0.08%
DN068CMITFIR630 1st Tunneling & Driving the Pipes 125,108 0.72% 0.24% 100.0% 0.72% 0.24%
DN068CMITSEC640 2nd Tunneling & Driving the Pipes and dismantle 125,108 0.72% 0.24% 100.0% 0.72% 0.24%
Pipeline Works (34/1/27/27/22 To 34/1/27/27/20 94LM) 373,324 100.0%
DN068CMITEXC650 Excavation for jacking shaft 44,799 0.26% 0.09% 100.0% 0.26% 0.09%
DN068CMITCJS660 Concrete for jacking shaft 22,400 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMITEXR670 Excavation for recieving shaft 44,799 0.26% 0.09% 100.0% 0.26% 0.09%
DN068CMITFIR680 1st Tunneling & Driving the Pipes 130,664 0.75% 0.25% 100.0% 0.75% 0.25%
DN068CMITSEC690 2nd Tunneling & Driving the Pipes and dismantle 130,664 0.75% 0.25% 100.0% 0.75% 0.25%
Pipeline Works (34/1/27/27/24 To 34/1/27/27/22 61LM) 242,220 100.0%
DN068CMITEXC700 Excavation for jacking shaft 29,066 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITCJS710 Concrete for jacking shaft 14,533 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMITEXR720 Excavation for recieving shaft 29,066 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITFIR730 1st Tunneling & Driving the Pipes 84,777 0.49% 0.16% 100.0% 0.49% 0.16%
DN068CMITSEC740 2nd Tunneling & Driving the Pipes and dismantle 84,777 0.49% 0.16% 100.0% 0.49% 0.16%
Manhole Works (26 M.H.) 545,812 100.0%
DN068CMHLBLI210 Blinding for manhole for Microtunnel 33,163 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CMHLTAP310 Tanking membrane and protection for manhole for Microtunne 8,291 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAS410 Base slab for manhole for Microtunnel 82,908 0.48% 0.16% 100.0% 0.48% 0.16%
DN068CMHLGRP810 GRP liner for manhole for Microtunnel 124,362 0.72% 0.24% 100.0% 0.72% 0.24%
DN068CMHLWCP510 Wall concrete and pipe for manhole for Microtunnel 82,908 0.48% 0.16% 100.0% 0.48% 0.16%
DN068CMHLCOV610 Cover slab for manhole for Microtunnel 12,436 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLDIC730 DI cover for manhole for Microtunnel 8,291 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLEMB910 External tanking membrane and protection for manhole for Mi 20,727 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CMHLDIC740 Ladder for manhole for Microtunnel 8,291 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC930 Backfilling for manhole for Microtunnel 33,163 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CMHLDIC750 Reinstatement works for Microtunnel and house connection (1 131,272 0.76% 0.25% 100.0% 0.76% 0.25%
Foul 34/1/27/27/1 (107 LM, 3 MH) 130,773 100.0%
PipeLine Works (107 LM) 38,460 100.0%
DN068CPIPEXC390 Excavation for sewer pipeline 27/1 11,538 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CPIPBED490 Geotextile and Bedding for sewer pipeline 27/1 6,538 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CPIPLAY590 Pipe Laying for sewer pipeline 27/1 11,538 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CPIPPBF690 Partial Backfill for sewer pipeline 27/1 4,615 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPTES790 Test for sewer pipeline 27/1 1,923 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CPIPFBF890 Final Backfill for sewer pipeline 27/1 2,308 0.01% 0.00% 100.0% 0.01% 0.00%
Manhole Works (3 M.H.) 71,439 100.0%
DN068CMHLEXC400 Excavation works for manhole 27/1 5,257 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLBLI500 Blinding for manhole 27/1 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP600 Tanking membrane and protection for manhole 27/1 478 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLBAS700 Base slab for manhole 27/1 9,558 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLGRP1100 GRP liner for manhole 27/1 10,992 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLWCP800 Wall concrete and pipe for manhole 27/1 11,947 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLCOV900 Cover slab for manhole 27/1 1,434 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1600 DI cover for manhole 27/1 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1610 Ladder for manhole 27/1 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1200 External tanking membrane and protection for manhole 27/1 1,434 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAC1220 Backfilling for manhole 27/1 3,823 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1620 Reinstatement works 27/1 23,649 0.14% 0.05% 100.0% 0.14% 0.05%
House Connection Works (1ABC) 20,874 100.0%
DN068CHCODEM390 Demolition for existing underground structure 27/1 4,941 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOEXC490 Excavation for pipeline and inspection chamber 27/1 1,433 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOPIP590 Pipe laying for house connection 27/1 1,843 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOBAS690 Base for inspection chamber 27/1 1,212 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOWAL790 Wall for inspection chamber 27/1 3,029 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOFIN1190 Finishing for inspection chamber 27/1 909 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOCOV890 Cover for inspection chamber 27/1 909 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOBAC990 Backfilling for house connection 27/1 819 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CHCOREN1090 Reinstatement work for house connection 27/1 5,781 0.03% 0.01% 100.0% 0.03% 0.01%
Foul 34/1/27/27/5 (236 LM, 4 MH) 227,161 100.0%
PipeLine Works (263 LM) 85,091 100.0%
DN068CPIPEXC380 Excavation for sewer pipeline 27/5 25,527 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPBED480 Geotextile and Bedding for sewer pipeline 27/5 14,465 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPLAY580 Pipe Laying for sewer pipeline 27/5 25,527 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPPBF680 Partial Backfill for sewer pipeline 27/5 10,211 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPTES780 Test for sewer pipeline 27/5 4,255 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF880 Final Backfill for sewer pipeline 27/5 5,105 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (4 M.H.) 116,042 100.0%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMHLEXC390 Excavation works for manhole 27/5 7,009 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLBLI490 Blinding for manhole 27/5 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP590 Tanking membrane and protection for manhole 27/5 637 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLBAS690 Base slab for manhole 27/5 12,744 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLGRP1090 GRP liner for manhole 27/5 14,656 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMHLWCP790 Wall concrete and pipe for manhole 27/5 15,930 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CMHLCOV890 Cover slab for manhole 27/5 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1570 DI cover for manhole 27/5 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1580 Ladder for manhole 27/5 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1190 External tanking membrane and protection for manhole 27/5 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAC1210 Backfilling for manhole 27/5 5,098 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1590 Reinstatement works 27/5 52,322 0.30% 0.10% 100.0% 0.30% 0.10%
House Connection Works (6D) 26,029 100.0%
DN068CHCOEXC480 Excavation for pipeline for house connection 27/5 8,601 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOPIP580 Pipe laying for house connection 27/5 11,058 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CHCOBAC980 Backfilling for Pipe for house connection 27/5 4,915 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOREN1080 Marker post for house connection 27/5 1,456 0.01% 0.00% 100.0% 0.01% 0.00%
Foul 34/1/27/27/8 (465 LM, 17 MH) 899,259 100.0%
PipeLine Works (465 LM) 167,591 100.0%
DN068CPIPEXC370 Excavation for sewer pipeline 27/8 50,277 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CPIPBED470 Geotextile and Bedding for sewer pipeline 27/8 28,490 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CPIPLAY570 Pipe Laying for sewer pipeline 27/8 50,277 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CPIPPBF670 Partial Backfill for sewer pipeline 27/8 20,111 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CPIPTES770 Test for sewer pipeline 27/8 8,380 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF870 Final Backfill for sewer pipeline 27/8 10,055 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (17 M.H.) 374,222 100.0%
DN068CMHLEXC380 Excavation works for manhole 27/8 29,829 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLBLI480 Blinding for manhole 27/8 5,423 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP580 Tanking membrane and protection for manhole 27/8 2,712 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS680 Base slab for manhole 27/8 54,234 0.31% 0.10% 100.0% 0.31% 0.10%
DN068CMHLGRP1080 GRP liner for manhole 27/8 62,369 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMHLWCP780 Wall concrete and pipe for manhole 27/8 67,793 0.39% 0.13% 100.0% 0.39% 0.13%
DN068CMHLCOV880 Cover slab for manhole 27/8 8,135 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1540 DI cover for manhole 27/8 5,423 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1550 Ladder for manhole 27/8 5,423 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1180 External tanking membrane and protection for manhole 27/8 8,135 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC1200 Backfilling for manhole 27/8 21,694 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CMHLDIC1560 Reinstatement works 27/8 103,051 0.59% 0.20% 100.0% 0.59% 0.20%
House Connection Works (15D, 14ABC) 357,447 100.0%
DN068CHCODEM370 Demolition for existing underground structure 27/8 69,172 0.40% 0.13% 100.0% 0.40% 0.13%
DN068CHCOEXC470 Excavation for pipeline and inspection chamber 27/8 41,615 0.24% 0.08% 100.0% 0.24% 0.08%
DN068CHCOPIP570 Pipe laying for house connection 27/8 53,506 0.31% 0.10% 100.0% 0.31% 0.10%
DN068CHCOBAS670 Base for inspection chamber 27/8 16,961 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOWAL770 Wall for inspection chamber 27/8 42,402 0.24% 0.08% 100.0% 0.24% 0.08%
DN068CHCOFIN1170 Finishing for inspection chamber 27/8 12,721 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOCOV870 Cover for inspection chamber 27/8 12,721 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOBAC970 Backfilling for house connection 27/8 23,780 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOREN1070 Reinstatement work for house connection 27/8 84,570 0.49% 0.16% 100.0% 0.49% 0.16%
Foul 34/1/27/27/10 (521 LM, 23 MH) 1,228,680 100.0%
PipeLine Works (521 LM) 187,917 100.0%
DN068CPIPEXC360 Excavation for sewer pipeline 27/10 56,375 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPBED460 Geotextile and Bedding for sewer pipeline 27/10 31,946 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY560 Pipe Laying for sewer pipeline 27/10 56,375 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF660 Partial Backfill for sewer pipeline 27/10 22,550 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES760 Test for sewer pipeline 27/10 9,396 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF860 Final Backfill for sewer pipeline 27/10 11,275 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (23 M.H.) 482,300 100.0%
DN068CMHLEXC370 Excavation works for manhole 27/10 40,343 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CMHLBLI470 Blinding for manhole 27/10 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP570 Tanking membrane and protection for manhole 27/10 3,668 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS670 Base slab for manhole 27/10 73,350 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMHLGRP1070 GRP liner for manhole 27/10 84,353 0.49% 0.16% 100.0% 0.49% 0.16%
DN068CMHLWCP770 Wall concrete and pipe for manhole 27/10 91,688 0.53% 0.18% 100.0% 0.53% 0.18%
DN068CMHLCOV870 Cover slab for manhole 27/10 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1510 DI cover for manhole 27/10 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1520 Ladder for manhole 27/10 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1170 External tanking membrane and protection for manhole 27/10 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1190 Backfilling for manhole 27/10 29,340 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLDIC1530 Reinstatement works 27/10 115,550 0.67% 0.22% 100.0% 0.67% 0.22%
House Connection Works (18D, 23ABC) 558,464 100.0%
DN068CHCODEM360 Demolition for existing underground structure 27/10 113,640 0.65% 0.22% 100.0% 0.65% 0.22%
DN068CHCOEXC460 Excavation for pipeline and inspection chamber 27/10 58,863 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CHCOPIP560 Pipe laying for house connection 27/10 75,681 0.44% 0.15% 100.0% 0.44% 0.15%
DN068CHCOBAS660 Base for inspection chamber 27/10 27,864 0.16% 0.05% 100.0% 0.16% 0.05%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CHCOWAL760 Wall for inspection chamber 27/10 69,661 0.40% 0.13% 100.0% 0.40% 0.13%
DN068CHCOFIN1160 Finishing for inspection chamber 27/10 20,898 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CHCOCOV860 Cover for inspection chamber 27/10 20,898 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CHCOBAC960 Backfilling for house connection 27/10 33,636 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CHCOREN1060 Reinstatement work for house connection 27/10 137,324 0.79% 0.26% 100.0% 0.79% 0.26%
Foul 34/1/27/27/11 (241 LM, 7 MH) 457,173 100.0%
PipeLine Works (241 LM) 86,884 100.0%
DN068CPIPEXC350 Excavation for sewer pipeline 27/11 26,065 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPBED450 Geotextile and Bedding for sewer pipeline 27/11 14,770 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPLAY550 Pipe Laying for sewer pipeline 27/11 26,065 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPPBF650 Partial Backfill for sewer pipeline 27/11 10,426 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPTES750 Test for sewer pipeline 27/11 4,344 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPFBF850 Final Backfill for sewer pipeline 27/11 5,213 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (7 M.H.) 164,935 100.0%
DN068CMHLEXC360 Excavation works for manhole 27/11 12,266 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLBLI460 Blinding for manhole 27/11 2,230 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP560 Tanking membrane and protection for manhole 27/11 1,115 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS660 Base slab for manhole 27/11 22,302 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLGRP1060 GRP liner for manhole 27/11 25,647 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLWCP760 Wall concrete and pipe for manhole 27/11 27,877 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CMHLCOV860 Cover slab for manhole 27/11 3,345 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1480 DI cover for manhole 27/11 2,230 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1490 Ladder for manhole 27/11 2,230 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1160 External tanking membrane and protection for manhole 27/11 3,345 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1180 Backfilling for manhole 27/11 8,921 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1500 Reinstatement works 27/11 53,425 0.31% 0.10% 100.0% 0.31% 0.10%
House Connection Works (4D, 9ABC) 205,355 100.0%
DN068CHCODEM350 Demolition for existing underground structure 27/11 44,468 0.26% 0.09% 100.0% 0.26% 0.09%
DN068CHCOEXC450 Excavation for pipeline and inspection chamber 27/11 18,681 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOPIP550 Pipe laying for house connection 27/11 24,018 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOBAS650 Base for inspection chamber 27/11 10,903 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CHCOWAL750 Wall for inspection chamber 27/11 27,259 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CHCOFIN1150 Finishing for inspection chamber 27/11 8,178 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOCOV850 Cover for inspection chamber 27/11 8,178 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOBAC950 Backfilling for house connection 27/11 10,675 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CHCOREN1050 Reinstatement work for house connection 27/11 52,997 0.31% 0.10% 100.0% 0.31% 0.10%
Foul 34/1/27/27/12 (522 LM, 23 HM) 1,319,865 100.0%
PipeLine Works (522 LM) 188,315 100.0%
DN068CPIPEXC340 Excavation for sewer pipeline 27/12 56,495 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPBED440 Geotextile and Bedding for sewer pipeline 27/12 32,014 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY540 Pipe Laying for sewer pipeline 27/12 56,495 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPPBF640 Partial Backfill for sewer pipeline 27/12 22,598 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES740 Test for sewer pipeline 27/12 9,416 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF840 Final Backfill for sewer pipeline 27/12 11,299 0.07% 0.02% 100.0% 0.07% 0.02%
Manhole Works (23 M.H.) 482,545 100.0%
DN068CMHLEXC350 Excavation works for manhole 27/12 40,343 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CMHLBLI450 Blinding for manhole 27/12 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP550 Tanking membrane and protection for manhole 27/12 3,668 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS650 Base slab for manhole 27/12 73,350 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMHLGRP1050 GRP liner for manhole 27/12 84,353 0.49% 0.16% 100.0% 0.49% 0.16%
DN068CMHLWCP750 Wall concrete and pipe for manhole 27/12 91,688 0.53% 0.18% 100.0% 0.53% 0.18%
DN068CMHLCOV850 Cover slab for manhole 27/12 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1450 DI cover for manhole 27/12 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1460 Ladder for manhole 27/12 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1150 External tanking membrane and protection for manhole 27/12 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1170 Backfilling for manhole 27/12 29,340 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLDIC1470 Reinstatement works 27/12 115,795 0.67% 0.22% 100.0% 0.67% 0.22%
House Connection Works (10D, 29ABC) 649,005 100.0%
DN068CHCODEM340 Demolition for existing underground structure 27/12 143,285 0.83% 0.28% 100.0% 0.83% 0.28%
DN068CHCOEXC440 Excavation for pipeline and inspection chamber 27/12 55,996 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CHCOPIP540 Pipe laying for house connection 27/12 71,995 0.41% 0.14% 100.0% 0.41% 0.14%
DN068CHCOBAS640 Base for inspection chamber 27/12 35,133 0.20% 0.07% 100.0% 0.20% 0.07%
DN068CHCOWAL740 Wall for inspection chamber 27/12 87,833 0.51% 0.17% 100.0% 0.51% 0.17%
DN068CHCOFIN1140 Finishing for inspection chamber 27/12 26,350 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CHCOCOV840 Cover for inspection chamber 27/12 26,350 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CHCOBAC940 Backfilling for house connection 27/12 31,998 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CHCOREN1040 Reinstatement work for house connection 27/12 170,067 0.98% 0.33% 100.0% 0.98% 0.33%
Foul 34/1/27/27/14 (509 LM, 22 MH) 1,350,481 100.0%
PipeLine Works (509 LM) 183,732 100.0%
DN068CPIPEXC330 Excavation for sewer pipeline 27/14 55,120 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPBED430 Geotextile and Bedding for sewer pipeline 27/14 31,234 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY530 Pipe Laying for sewer pipeline 27/14 55,120 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF630 Partial Backfill for sewer pipeline 27/14 22,048 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES730 Test for sewer pipeline 27/14 9,187 0.05% 0.02% 100.0% 0.05% 0.02%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CPIPFBF830 Final Backfill for sewer pipeline 27/14 11,024 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (22 M.H.) 463,797 100.0%
DN068CMHLEXC340 Excavation works for manhole 27/14 38,590 0.22% 0.07% 100.0% 0.22% 0.07%
DN068CMHLBLI440 Blinding for manhole 27/14 7,016 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP540 Tanking membrane and protection for manhole 27/14 3,508 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS640 Base slab for manhole 27/14 70,164 0.40% 0.13% 100.0% 0.40% 0.13%
DN068CMHLGRP1040 GRP liner for manhole 27/14 80,689 0.46% 0.15% 100.0% 0.46% 0.15%
DN068CMHLWCP740 Wall concrete and pipe for manhole 27/14 87,705 0.51% 0.17% 100.0% 0.51% 0.17%
DN068CMHLCOV840 Cover slab for manhole 27/14 10,525 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1420 DI cover for manhole 27/14 7,016 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1430 Ladder for manhole 27/14 7,016 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1140 External tanking membrane and protection for manhole 27/14 10,525 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1160 Backfilling for manhole 27/14 28,066 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CMHLDIC1440 Reinstatement works 27/14 112,977 0.65% 0.22% 100.0% 0.65% 0.22%
House Connection Works (8D, 32ABC) 702,952 100.0%
DN068CHCODEM330 Demolition for existing underground structure 27/14 158,107 0.91% 0.30% 100.0% 0.91% 0.30%
DN068CHCOEXC430 Excavation for pipeline and inspection chamber 27/14 57,429 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CHCOPIP530 Pipe laying for house connection 27/14 73,838 0.43% 0.14% 100.0% 0.43% 0.14%
DN068CHCOBAS630 Base for inspection chamber 27/14 38,768 0.22% 0.07% 100.0% 0.22% 0.07%
DN068CHCOWAL730 Wall for inspection chamber 27/14 96,919 0.56% 0.19% 100.0% 0.56% 0.19%
DN068CHCOFIN1130 Finishing for inspection chamber 27/14 29,076 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOCOV830 Cover for inspection chamber 27/14 29,076 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOBAC930 Backfilling for house connection 27/14 32,817 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CHCOREN1030 Reinstatement work 27/14 186,923 1.08% 0.36% 100.0% 1.08% 0.36%
Foul 34/1/27/27/16 (532 LM, 21 MH) 1,097,252 100.0%
PipeLine Works (532 LM) 191,902 100.0%
DN068CPIPEXC320 Excavation for sewer pipeline 27/16 57,571 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPBED420 Geotextile and Bedding for sewer pipeline 27/16 32,623 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CPIPLAY520 Pipe Laying for sewer pipeline 27/16 57,571 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPPBF620 Partial Backfill for sewer pipeline 27/16 23,028 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES720 Test for sewer pipeline 27/16 9,595 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPFBF820 Final Backfill for sewer pipeline 27/16 11,514 0.07% 0.02% 100.0% 0.07% 0.02%
Manhole Works (21 M.H.) 452,891 100.0%
DN068CMHLEXC330 Excavation works for manhole 27/16 36,838 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMHLBLI430 Blinding for manhole 27/16 6,698 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP530 Tanking membrane and protection for manhole 27/16 3,349 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS630 Base slab for manhole 27/16 66,978 0.39% 0.13% 100.0% 0.39% 0.13%
DN068CMHLGRP1030 GRP liner for manhole 27/16 77,025 0.44% 0.15% 100.0% 0.44% 0.15%
DN068CMHLWCP730 Wall concrete and pipe for manhole 27/16 83,723 0.48% 0.16% 100.0% 0.48% 0.16%
DN068CMHLCOV830 Cover slab for manhole 27/16 10,047 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1390 DI cover for manhole 27/16 6,698 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1400 Ladder for manhole 27/16 6,698 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1130 External tanking membrane and protection for manhole 27/16 10,047 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1150 Backfilling for manhole 27/16 26,791 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLDIC1410 Reinstatement works 27/16 118,000 0.68% 0.23% 100.0% 0.68% 0.23%
House Connection Works (8D, 20ABC) 452,459 100.0%
DN068CHCODEM320 Demolition for existing underground structure 27/16 98,817 0.57% 0.19% 100.0% 0.57% 0.19%
DN068CHCOEXC420 Excavation for pipeline and inspection chamber 27/16 40,228 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CHCOPIP520 Pipe laying for house connection 27/16 51,722 0.30% 0.10% 100.0% 0.30% 0.10%
DN068CHCOBAS620 Base for inspection chamber 27/16 24,230 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOWAL720 Wall for inspection chamber 27/16 60,575 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CHCOFIN1120 Finishing for inspection chamber 27/16 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOCOV820 Cover for inspection chamber 27/16 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOBAC920 Backfilling for house connection 27/16 22,988 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CHCOREN1020 Reinstatement work for house connection 27/16 117,555 0.68% 0.23% 100.0% 0.68% 0.23%
Foul 34/1/27/27/17 (439 LM, 15 MH) 652,528 100.0%
PipeLine Works (439 LM) 158,424 100.0%
DN068CPIPEXC310 Excavation for sewer pipeline 27/17 47,527 0.27% 0.09% 100.0% 0.27% 0.09%
DN068CPIPBED410 Geotextile and Bedding for sewer pipeline 27/17 26,932 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CPIPLAY510 Pipe Laying for sewer pipeline 27/17 47,527 0.27% 0.09% 100.0% 0.27% 0.09%
DN068CPIPPBF610 Partial Backfill for sewer pipeline 27/17 19,011 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CPIPTES710 Test for sewer pipeline 27/17 7,921 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF810 Final Backfill for sewer pipeline 27/17 9,505 0.05% 0.02% 100.0% 0.05% 0.02%
Manhole Works (15 M.H.) 336,725 100.0%
DN068CMHLEXC320 Excavation works for manhole 27/17 26,324 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLBLI420 Blinding for manhole 27/17 4,786 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP520 Tanking membrane and protection for manhole 27/17 2,393 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS620 Base slab for manhole 27/17 47,862 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CMHLGRP1020 GRP liner for manhole 27/17 55,042 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CMHLWCP720 Wall concrete and pipe for manhole 27/17 59,828 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CMHLCOV820 Cover slab for manhole 27/17 7,179 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1360 DI cover for manhole 27/17 4,786 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1370 Ladder for manhole 27/17 4,786 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1120 External tanking membrane and protection for manhole 27/17 7,179 0.04% 0.01% 100.0% 0.04% 0.01%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
DN068CMHLBAC1140 Backfilling for manhole 27/17 19,145 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CMHLDIC1380 Reinstatement works 27/17 97,415 0.56% 0.19% 100.0% 0.56% 0.19%
House Connection Works (17D, 4ABC) 157,379 100.0%
DN068CHCODEM310 Demolition for existing underground structure 27/17 19,763 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOEXC410 Excavation for pipeline and inspection chamber 27/17 30,148 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOPIP510 Pipe laying for house connection 27/17 38,762 0.22% 0.07% 100.0% 0.22% 0.07%
DN068CHCOBAS610 Base for inspection chamber 27/17 4,846 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL710 Wall for inspection chamber 27/17 12,115 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOFIN1110 Finishing for inspection chamber 27/17 3,635 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOCOV810 Cover for inspection chamber 27/17 3,635 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOBAC910 Backfilling for house connection 27/17 17,227 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOREN1010 Reinstatement work 27/17 27,248 0.16% 0.05% 100.0% 0.16% 0.05%
Foul 34/1/27/27/19 (243 LM, 8 MH) 395,098 100.0%
PipeLine Works (243 LM) 87,681 100.0%
DN068CPIPEXC300 Excavation for sewer pipeline 27/19 26,304 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPBED400 Geotextile and Bedding for sewer pipeline 14,906 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPLAY500 Pipe Laying for sewer pipeline 27/19 26,304 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPPBF600 Partial Backfill for sewer pipeline 27/19 10,522 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPTES700 Test for sewer pipeline 27/19 4,384 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPFBF800 Final Backfill for sewer pipeline 27/19 5,261 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (8 M.H.) 181,354 100.0%
DN068CMHLEXC310 Excavation works for manhole 27/19 14,018 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMHLBLI410 Blinding for manhole 27/19 2,549 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP510 Tanking membrane and protection for manhole 27/19 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS610 Base slab for manhole 27/19 25,488 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLGRP1010 GRP liner for manhole 27/19 29,311 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLWCP710 Wall concrete and pipe for manhole 27/19 31,860 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMHLCOV810 Cover slab for manhole 27/19 3,823 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1330 DI cover for manhole 27/19 2,549 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1340 Ladder for manhole 27/19 2,549 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1110 External tanking membrane and protection for manhole 27/19 3,823 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1130 Backfilling for manhole 27/19 10,195 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1350 Reinstatement works 27/19 53,915 0.31% 0.10% 100.0% 0.31% 0.10%
House Connection Works (5D, 5ABC) 126,063 100.0%
DN068CHCODEM300 Demolition for existing underground structure 27/19 24,704 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOEXC400 Excavation for pipeline and inspection chamber 27/19 14,334 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CHCOPIP500 Pipe laying for house connection 27/19 18,430 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOBAS600 Base for inspection chamber 27/19 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL700 Wall for inspection chamber 27/19 15,144 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOFIN1100 Finishing for inspection chamber 27/19 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOCOV800 Cover for inspection chamber 27/19 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOBAC900 Backfilling for house connection 27/19 8,191 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOREN1000 Reinstatement work 27/19 30,117 0.17% 0.06% 100.0% 0.17% 0.06%
Foul 34/1/27/27/23 (216 LM, 8 MH) 368,442 100.0%
PipeLine Works (216 LM) 77,917 100.0%
DN068CPIPEXC290 Excavation for sewer pipeline 27/23 23,375 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPBED390 Geotextile and Bedding for sewer pipeline 27/23 13,246 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPLAY490 Pipe Laying for sewer pipeline 27/23 23,375 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPPBF590 Partial Backfill for sewer pipeline 27/23 9,350 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPTES690 Test for sewer pipeline 27/23 3,896 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF790 Final Backfill for sewer pipeline 27/23 4,675 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (8 M.H.) 175,712 100.0%
DN068CMHLEXC300 Excavation works for manhole 27/23 14,058 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMHLBLI400 Blinding for manhole 27/23 2,556 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP500 Tanking membrane and protection for manhole 27/23 1,278 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS600 Base slab for manhole 27/23 25,560 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLGRP1000 GRP liner for manhole 27/23 29,394 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLWCP700 Wall concrete and pipe for manhole 27/23 31,950 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMHLCOV800 Cover slab for manhole 27/23 3,834 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1300 DI cover for manhole 27/23 2,556 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1310 Ladder for manhole 27/23 2,556 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1100 External tanking membrane and protection for manhole 27/23 3,834 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1120 Backfilling for manhole 27/23 10,224 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1320 Reinstatement works 27/23 47,911 0.28% 0.09% 100.0% 0.28% 0.09%
House Connection Works (12D, 3ABC) 114,813 100.0%
DN068CHCODEM290 Demolition for existing underground structure 27/23 14,823 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOEXC390 Excavation for pipeline and inspection chamber 27/23 21,548 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CHCOPIP490 Pipe laying for house connection 27/23 27,704 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CHCOBAS590 Base for inspection chamber 27/23 3,635 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOWAL690 Wall for inspection chamber 27/23 9,086 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOFIN1090 Finishing for inspection chamber 27/23 2,726 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOCOV790 Cover for inspection chamber 27/23 2,726 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOBAC890 Backfilling for house connection 27/23 12,313 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOREN990 Reinstatement work for house connection 27/23 20,254 0.12% 0.04% 100.0% 0.12% 0.04%
Weight Weight Progress Progress
Activity ID Activity Name Budgeted Total Cost PCT %
Area Overall Area Overall
Handing Over 0 0.0%
DN068HALPASB10 As Built Drawingss 0 100.0%
DN068HALPHAV20Demobilisation 0 100.0%
Actual Percentage Of Completion Data Date: 01st January 2015

Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
CONSTRUCTION OF AL GARAFFA AREA SEWERAGE - PHASE 2 6-9-2012 52,101,812 100.00% 99.00%
General 7,652,093 100.00% 14.03%
DN068GALPTPI700 Third Party Insurance 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068GALPSIO200 Supply and Installation of Site Offices 395,298 5.17% 0.76% 100.0% 5.17% 0.76%
DN068GALPALO100 Site Mobilisation 901,296 11.78% 1.73% 100.0% 11.78% 1.73%
DN068GALPTPI720 Contract Administration 5,331,554 69.67% 10.23% 94.6% 65.92% 9.68%
DN068GALPTPI730 Site offices maintain 842,670 11.01% 1.62% 94.6% 10.42% 1.53%
DN068GALPTPI710 Site Survey 181,274 2.37% 0.35% 93.6% 2.22% 0.33%
Construction 44,449,719 84.97%
Line 34/1/27/56/1 (320Lm, 4MH) 312,287 100.00% 100.00% 0.60%
Traffic Management and Setting Out 0
DN068CGENROS380 Obtaining RO from authorities 56/1, 51/1, 46, 46/11, 45/19 and 60 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA280 Traffic Diversion 56/1, 51/1 and 46 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET180 Setting out 56/1, 51/1 and 46 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (320 LM) 147,513 100.0%
DN068CPIPEXC220 Excavation for sewer pipeline 56/1 44,254 14.17% 0.08% 100.0% 14.17% 0.08%
DN068CPIPBED320 Geotextile and Bedding for sewer pipeline 56/1 25,077 8.03% 0.05% 100.0% 8.03% 0.05%
DN068CPIPLAY420 Pipe Laying for sewer pipeline 56/1 44,254 14.17% 0.08% 100.0% 14.17% 0.08%
DN068CPIPPBF520 Partial Backfill for sewer pipeline 56/1 17,702 5.67% 0.03% 100.0% 5.67% 0.03%
DN068CPIPTES620 Test for sewer pipeline 56/1 7,376 2.36% 0.01% 100.0% 2.36% 0.01%
DN068CPIPFBF720 Final Backfill for sewer pipeline 56/1 8,851 2.83% 0.02% 100.0% 2.83% 0.02%
Manhole Works (4 M.H.) 130,165 100.0%
DN068CMHLEXC230 Excavation works for manhole 56/1 6,309 2.02% 0.01% 100.0% 2.02% 0.01%
DN068CMHLBLI330 Blinding for manhole 56/1 1,147 0.37% 0.00% 100.0% 0.37% 0.00%
DN068CMHLTAP430 Tanking membrane and protection for manhole 56/1 574 0.18% 0.00% 100.0% 0.18% 0.00%
DN068CMHLBAS530 Base slab for manhole 56/1 11,472 3.67% 0.02% 100.0% 3.67% 0.02%
DN068CMHLGRP930 GRP liner for manhole 56/1 13,192 4.22% 0.03% 100.0% 4.22% 0.03%
DN068CMHLWCP630 Wall concrete and pipe for manhole 56/1 14,340 4.59% 0.03% 100.0% 4.59% 0.03%
DN068CMHLCOV730 Cover slab for manhole 56/1 1,721 0.55% 0.00% 100.0% 0.55% 0.00%
DN068CMHLDIC190 DI cover for manhole 56/1 1,147 0.37% 0.00% 100.0% 0.37% 0.00%
DN068CMHLDIC100 Ladder for manhole 56/1 1,147 0.37% 0.00% 100.0% 0.37% 0.00%
DN068CMHLEMB130 External tanking membrane and protection for manhole 56/1 1,721 0.55% 0.00% 100.0% 0.55% 0.00%
DN068CMHLBAC150 Backfilling for manhole 56/1 4,589 1.47% 0.01% 100.0% 1.47% 0.01%
DN068CMHLDIC110 Reinstatement works 56/1 72,807 23.31% 0.14% 100.0% 23.31% 0.14%
House Connection Works (8D) 34,609 100.0%
DN068CHCOEXC330 Excavation for pipeline for house connection 56/1 11,434 3.66% 0.02% 100.0% 3.66% 0.02%
DN068CHCOPIP430 Pipe laying for house connection 56/1 14,700 4.71% 0.03% 100.0% 4.71% 0.03%
DN068CHCOBAC830 Backfilling for Pipe for house connection 56/1 6,534 2.09% 0.01% 100.0% 2.09% 0.01%
DN068CHCOREN930 Marker post for house connection 56/1 1,941 0.62% 0.00% 100.0% 0.62% 0.00%
Line 34/1/27/51/1 (828LM, 17MH) 940,955 100.00% 100.00% 1.81%
PipeLine Works (828 LM) 348,389 100.0%
DN068CPIPEXC190 Excavation for sewer pipeline 51/1 104,517 11.11% 0.20% 100.0% 11.1% 0.2%
DN068CPIPBED290 Geotextile and Bedding for sewer pipeline 51/1 59,226 6.29% 0.11% 100.0% 6.3% 0.1%
DN068CPIPLAY390 Pipe Laying for sewer pipeline 51/1 104,517 11.11% 0.20% 100.0% 11.1% 0.2%
DN068CPIPPBF490 Partial Backfill for sewer pipeline 51/1 41,807 4.44% 0.08% 100.0% 4.4% 0.1%
DN068CPIPTES590 Test for sewer pipeline 51/1 17,420 1.85% 0.03% 100.0% 1.9% 0.0%
DN068CPIPFBF690 Final Backfill for sewer pipeline 51/1 20,903 2.22% 0.04% 100.0% 2.2% 0.0%
Manhole Works (17 M.H.) 440,242 100.0%
DN068CMHLEXC200 Excavation works for manhole 51/1 27,961 2.97% 0.05% 100.0% 3.0% 0.1%
DN068CMHLBLI300 Blinding for manhole 51/1 5,084 0.54% 0.01% 100.0% 0.5% 0.0%
DN068CMHLTAP400 Tanking membrane and protection for manhole 51/1 2,542 0.27% 0.00% 100.0% 0.3% 0.0%
DN068CMHLBAS500 Base slab for manhole 51/1 50,839 5.40% 0.10% 100.0% 5.4% 0.1%
DN068CMHLGRP900 GRP liner for manhole 51/1 58,465 6.21% 0.11% 100.0% 6.2% 0.1%
DN068CMHLWCP600 Wall concrete and pipe for manhole 51/1 63,549 6.75% 0.12% 100.0% 6.8% 0.1%
DN068CMHLCOV700 Cover slab for manhole 51/1 7,626 0.81% 0.01% 100.0% 0.8% 0.0%
DN068CMHLDIC1000 DI cover for manhole 51/1 5,084 0.54% 0.01% 100.0% 0.5% 0.0%
DN068CMHLDIC1010 Ladder for manhole 51/1 5,084 0.54% 0.01% 100.0% 0.5% 0.0%
DN068CMHLEMB100 External tanking membrane and protection for manhole 51/1 7,626 0.81% 0.01% 100.0% 0.8% 0.0%
DN068CMHLBAC120 Backfilling for manhole 51/1 20,336 2.16% 0.04% 100.0% 2.2% 0.0%
DN068CMHLDIC1020 Reinstatement works 51/1 186,048 19.77% 0.36% 100.0% 19.8% 0.4%
House Connection Works (11D,5ABC) 152,324 100.0%
DN068CHCODEM200 Demolition for existing underground structure 51/1 24,704 2.63% 0.05% 100.0% 2.6% 0.0%
DN068CHCOEXC300 Excavation for pipeline and inspection chamber 51/1 23,016 2.45% 0.04% 100.0% 2.4% 0.0%
DN068CHCOPIP400 Pipe laying for house connection 51/1 29,592 3.14% 0.06% 100.0% 3.1% 0.1%
DN068CHCOBAS500 Base for inspection chamber 51/1 6,057 0.64% 0.01% 100.0% 0.6% 0.0%
DN068CHCOWAL600 Wall for inspection chamber 51/1 15,144 1.61% 0.03% 100.0% 1.6% 0.0%
DN068CHCOFIN1000 Finishing for inspection chamber 51/1 4,543 0.48% 0.01% 100.0% 0.5% 0.0%
DN068CHCOCOV700 Cover for inspection chamber 51/1 4,543 0.48% 0.01% 100.0% 0.5% 0.0%
DN068CHCOBAC800 Backfilling for house connection 51/1 13,152 1.40% 0.03% 100.0% 1.4% 0.0%
DN068CHCOREN900 Reinstatement work for house connection 51/1 31,573 3.36% 0.06% 100.0% 3.4% 0.1%
Line 34/1/27/46/11(493LM, 9MH) 406,563 100.00% 100.00% 0.78%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA300 Traffic Diversion 46/11 0 0.00% 0.00% 100.0% 0.0% 0.0%
DN068CGENSET200 Setting out 46/11 0 0.00% 0.00% 100.0% 0.0% 0.0%
PipeLine Works (493 LM) 145,902 100.0%
DN068CPIPEXC200 Excavation for sewer pipeline 46/11 43,771 10.77% 0.08% 100.0% 10.8% 0.1%
DN068CPIPBED300 Geotextile and Bedding for sewer pipeline 46/11 24,803 6.10% 0.05% 100.0% 6.1% 0.0%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CPIPLAY400 Pipe Laying for sewer pipeline 46/11 43,771 10.77% 0.08% 100.0% 10.8% 0.1%
DN068CPIPPBF500 Partial Backfill for sewer pipeline 46/11 17,508 4.31% 0.03% 100.0% 4.3% 0.0%
DN068CPIPTES600 Test for sewer pipeline 46/11 7,295 1.79% 0.01% 100.0% 1.8% 0.0%
DN068CPIPFBF700 Final Backfill for sewer pipeline 46/11 8,754 2.15% 0.02% 100.0% 2.2% 0.0%
Manhole Works (9 M.H.) 195,505 100.0%
DN068CMHLEXC210 Excavation works for manhole 46/11 9,227 2.27% 0.02% 100.0% 2.3% 0.0%
DN068CMHLBLI310 Blinding for manhole 46/11 1,678 0.41% 0.00% 100.0% 0.4% 0.0%
DN068CMHLTAP410 Tanking membrane and protection for manhole 46/11 839 0.21% 0.00% 100.0% 0.2% 0.0%
DN068CMHLBAS510 Base slab for manhole 46/11 16,777 4.13% 0.03% 100.0% 4.1% 0.0%
DN068CMHLGRP910 GRP liner for manhole 46/11 19,293 4.75% 0.04% 100.0% 4.7% 0.0%
DN068CMHLWCP610 Wall concrete and pipe for manhole 46/11 20,971 5.16% 0.04% 100.0% 5.2% 0.0%
DN068CMHLCOV710 Cover slab for manhole 46/11 2,517 0.62% 0.00% 100.0% 0.6% 0.0%
DN068CMHLDIC1030 DI cover for manhole 46/11 1,678 0.41% 0.00% 100.0% 0.4% 0.0%
DN068CMHLDIC1040 Ladder for manhole 46/11 1,678 0.41% 0.00% 100.0% 0.4% 0.0%
DN068CMHLEMB1010 External tanking membrane and protection for manhole 46/11 2,517 0.62% 0.00% 100.0% 0.6% 0.0%
DN068CMHLBAC1030 Backfilling for manhole 46/11 6,711 1.65% 0.01% 100.0% 1.7% 0.0%
DN068CMHLDIC1050 Reinstatement works 46/11 111,622 27.46% 0.21% 100.0% 27.5% 0.2%
House Connection Works (15D) 65,157 100.0%
DN068CHCOEXC310 Excavation for pipeline for house connection 46/11 21,531 5.30% 0.04% 100.0% 5.3% 0.0%
DN068CHCOPIP410 Pipe laying for house connection 46/11 27,683 6.81% 0.05% 100.0% 6.8% 0.1%
DN068CHCOBAC810 Backfilling for Pipe for house connection 46/11 12,303 3.03% 0.02% 100.0% 3.0% 0.0%
DN068CHCOREN910 Marker Post for house connection 46/11 3,640 0.90% 0.01% 100.0% 0.9% 0.0%
Line 34/1/27/45/19/1 (431LM, 8MH) 390,220 100.00% 100.00% 0.75%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA310 Traffic Diversion 45/19/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET210 Setting out 45/19/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (431 LM) 139,802 100.0%
DN068CPIPEXC210 Excavation for sewer pipeline 45/19/1 41,941 10.75% 0.08% 100.0% 10.75% 0.08%
DN068CPIPBED310 Geotextile and Bedding for sewer pipeline45/19/1 23,766 6.09% 0.05% 100.0% 6.09% 0.05%
DN068CPIPLAY410 Pipe Laying for sewer pipeline 45/19/1 41,941 10.75% 0.08% 100.0% 10.75% 0.08%
DN068CPIPPBF510 Partial Backfill for sewer pipeline 45/19/1 16,776 4.30% 0.03% 100.0% 4.30% 0.03%
DN068CPIPTES610 Test for sewer pipeline 45/19/1 6,990 1.79% 0.01% 100.0% 1.79% 0.01%
DN068CPIPFBF710 Final Backfill for sewer pipeline 45/19/1 8,388 2.15% 0.02% 100.0% 2.15% 0.02%
Manhole Works (8 M.H.) 188,363 100.0%
DN068CMHLEXC220 Excavation works for manhole 45/19/1 10,015 2.57% 0.02% 100.0% 2.57% 0.02%
DN068CMHLBLI320 Blinding for manhole 45/19/1 1,821 0.47% 0.00% 100.0% 0.47% 0.00%
DN068CMHLTAP420 Tanking membrane and protection for manhole 45/19/1 910 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CMHLBAS520 Base slab for manhole 45/19/1 18,209 4.67% 0.03% 100.0% 4.67% 0.03%
DN068CMHLGRP920 GRP liner for manhole 45/19/1 20,940 5.37% 0.04% 100.0% 5.37% 0.04%
DN068CMHLWCP620 Wall concrete and pipe for manhole 45/19/1 22,761 5.83% 0.04% 100.0% 5.83% 0.04%
DN068CMHLCOV720 Cover slab for manhole 45/19/1 2,731 0.70% 0.01% 100.0% 0.70% 0.01%
DN068CMHLDIC1060 DI cover for manhole 45/19/1 1,821 0.47% 0.00% 100.0% 0.47% 0.00%
DN068CMHLDIC1070 Ladder for manhole 45/19/1 1,821 0.47% 0.00% 100.0% 0.47% 0.00%
DN068CMHLEMB1020 External tanking membrane and protection for manhole 45/19/1 2,731 0.70% 0.01% 100.0% 0.70% 0.01%
DN068CMHLBAC1040 Backfilling for manhole 45/19/1 7,284 1.87% 0.01% 100.0% 1.87% 0.01%
DN068CMHLDIC1080 Reinstatement works 45/19/1 97,319 24.94% 0.19% 100.0% 24.94% 0.19%
House Connection Works (10D, 1ABC) 62,055 100.0%
DN068CHCODEM220 Demolition for existing underground structure 45/19/1 4,941 1.27% 0.01% 100.0% 1.27% 0.01%
DN068CHCOEXC320 Excavation for pipeline and inspection chamber 45/19/1 14,997 3.84% 0.03% 100.0% 3.84% 0.03%
DN068CHCOPIP420 Pipe laying for house connection 45/19/1 19,282 4.94% 0.04% 100.0% 4.94% 0.04%
DN068CHCOBAS520 Base for inspection chamber 45/19/1 1,212 0.31% 0.00% 100.0% 0.31% 0.00%
DN068CHCOWAL620 Wall for inspection chamber 45/19/1 3,029 0.78% 0.01% 100.0% 0.78% 0.01%
DN068CHCOFIN1020 Finishing for inspection chamber 45/19/1 909 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CHCOCOV720 Cover for inspection chamber 45/19/1 909 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CHCOBAC820 Backfilling for house connection 45/19/1 8,570 2.20% 0.02% 100.0% 2.20% 0.02%
DN068CHCOREN920 Reinstatement work for house connection 45/19/1 8,207 2.10% 0.02% 100.0% 2.10% 0.02%
Line 34/1/27/60/1 (779LM, 12MH) 750,241 100.00% 100.00% 1.44%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA330 Traffic Diversion 60/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET230 Setting out 60/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (779 LM) 320,547 100.0%
DN068CPIPEXC230 Excavation for sewer pipeline 60/1 96,164 12.82% 0.18% 100.0% 12.82% 0.18%
DN068CPIPBED330 Geotextile and Bedding for sewer pipeline 60/1 54,493 7.26% 0.10% 100.0% 7.26% 0.10%
DN068CPIPLAY430 Pipe Laying for sewer pipeline 60/1 96,164 12.82% 0.18% 100.0% 12.82% 0.18%
DN068CPIPPBF530 Partial Backfill for sewer pipeline 60/1 38,466 5.13% 0.07% 100.0% 5.13% 0.07%
DN068CPIPTES630 Test for sewer pipeline 60/1 16,027 2.14% 0.03% 100.0% 2.14% 0.03%
DN068CPIPFBF730 Final Backfill for sewer pipeline 60/1 19,233 2.56% 0.04% 100.0% 2.56% 0.04%
Manhole Works (12 M.H.) 355,992 100.0%
DN068CMHLEXC240 Excavation works for manhole 60/1 19,773 2.64% 0.04% 100.0% 2.64% 0.04%
DN068CMHLBLI340 Blinding for manhole 60/1 3,595 0.48% 0.01% 100.0% 0.48% 0.01%
DN068CMHLTAP440 Tanking membrane and protection for manhole 60/1 1,798 0.24% 0.00% 100.0% 0.24% 0.00%
DN068CMHLBAS540 Base slab for manhole 60/1 35,951 4.79% 0.07% 100.0% 4.79% 0.07%
DN068CMHLGRP940 GRP liner for manhole 60/1 41,343 5.51% 0.08% 100.0% 5.51% 0.08%
DN068CMHLWCP640 Wall concrete and pipe for manhole 60/1 44,939 5.99% 0.09% 100.0% 5.99% 0.09%
DN068CMHLCOV740 Cover slab for manhole 60/1 5,393 0.72% 0.01% 100.0% 0.72% 0.01%
DN068CMHLDIC1120 DI cover for manhole 60/1 3,595 0.48% 0.01% 100.0% 0.48% 0.01%
DN068CMHLDIC1130 Ladder for manhole 60/1 3,595 0.48% 0.01% 100.0% 0.48% 0.01%
DN068CMHLEMB1040 External tanking membrane and protection for manhole 60/1 5,393 0.72% 0.01% 100.0% 0.72% 0.01%
DN068CMHLBAC1060 Backfilling for manhole 60/1 14,380 1.92% 0.03% 100.0% 1.92% 0.03%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CMHLDIC1140 Reinstatement works 60/1 176,238 23.49% 0.34% 100.0% 23.49% 0.34%
House Connection Works (17D) 73,703 100.0%
DN068CHCOEXC340 Excavation for pipeline for house connection 60/1 24,352 3.25% 0.05% 100.0% 3.25% 0.05%
DN068CHCOPIP440 Pipe laying for house connection 60/1 31,310 4.17% 0.06% 100.0% 4.17% 0.06%
DN068CHCOBAC840 Backfilling for Pipe for house connection 60/1 13,916 1.85% 0.03% 100.0% 1.85% 0.03%
DN068CHCOREN940 Marker Post for house connection 60/1 4,125 0.55% 0.01% 100.0% 0.55% 0.01%
Line 34/1/27/45/15/2 (2417LM, 91MH) 4,592,315 100.00% 99.37% 8.76%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS340 Obtaining RO from authorities for 45 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA240 Traffic Diversion 45/15/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET140 Setting out 45/15/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (2417 LM) 830,892 100.0%
DN068CPIPEXC140 Excavation for sewer pipeline 45/15/2 249,268 5.43% 0.48% 100.0% 5.43% 0.48%
DN068CPIPBED240 Geotextile and Bedding for sewer pipeline 45/15/2 141,252 3.08% 0.27% 100.0% 3.08% 0.27%
DN068CPIPLAY340 Pipe Laying for sewer pipeline 45/15/2 249,268 5.43% 0.48% 100.0% 5.43% 0.48%
DN068CPIPPBF440 Partial Backfill for sewer pipeline 45/15/2 99,707 2.17% 0.19% 100.0% 2.17% 0.19%
DN068CPIPTES540 Test for sewer pipeline 45/15/2 41,545 0.90% 0.08% 100.0% 0.90% 0.08%
DN068CPIPFBF640 Final Backfill for sewer pipeline 45/15/2 49,854 1.09% 0.10% 100.0% 1.09% 0.10%
Manhole Works (91 M.H.) 1,756,950 100.0%
DN068CMHLEXC150 Excavation works for manhole 45/15/2 134,626 2.93% 0.26% 100.0% 2.93% 0.26%
DN068CMHLBLI250 Blinding for manhole 45/15/2 24,478 0.53% 0.05% 100.0% 0.53% 0.05%
DN068CMHLTAP350 Tanking membrane and protection for manhole 45/15/2 12,239 0.27% 0.02% 100.0% 0.27% 0.02%
DN068CMHLBAS450 Base slab for manhole 45/15/2 244,775 5.33% 0.47% 100.0% 5.33% 0.47%
DN068CMHLGRP850 GRP liner for manhole 45/15/2 281,491 6.13% 0.54% 100.0% 6.13% 0.54%
DN068CMHLWCP550 Wall concrete and pipe for manhole 45/15/2 305,968 6.66% 0.59% 100.0% 6.66% 0.59%
DN068CMHLCOV650 Cover slab for manhole 45/15/2 36,716 0.80% 0.07% 100.0% 0.80% 0.07%
DN068CMHLDIC850 DI cover for manhole 45/15/2 24,478 0.53% 0.05% 100.0% 0.53% 0.05%
DN068CMHLEMB950 External tanking membrane and protection for manhole 45/15/2 36,716 0.80% 0.07% 100.0% 0.80% 0.07%
DN068CMHLDIC860 Ladder for manhole 45/15/2 24,478 0.53% 0.05% 100.0% 0.53% 0.05%
DN068CMHLBAC970 Backfilling for manhole 45/15/2 97,910 2.13% 0.19% 100.0% 2.13% 0.19%
DN068CMHLDIC870 Reinstatement works 45/15/2 533,076 11.61% 1.02% 100.0% 11.61% 1.02%
House Connection Works (48D,86ABC) 2,004,473 98.6%
DN068CHCODEM150 Demolition for existing underground structure 45/15/2 424,913 9.25% 0.82% 98.0% 9.07% 0.80%
DN068CHCOEXC250 Excavation for pipeline and inspection chamber 45/15/2 192,441 4.19% 0.37% 100.0% 4.19% 0.37%
DN068CHCOPIP350 Pipe laying for house connection 45/15/2 247,425 5.39% 0.47% 100.0% 5.39% 0.47%
DN068CHCOBAS450 Base for inspection chamber 45/15/2 104,188 2.27% 0.20% 98.0% 2.22% 0.20%
DN068CHCOWAL550 Wall for inspection chamber 45/15/2 260,470 5.67% 0.50% 98.0% 5.56% 0.49%
DN068CHCOFIN950 Finishing for inspection chamber 45/15/2 78,141 1.70% 0.15% 98.0% 1.67% 0.15%
DN068CHCOCOV650 Cover for inspection chamber 45/15/2 78,141 1.70% 0.15% 98.0% 1.67% 0.15%
DN068CHCOBAC750 Backfilling for house connection 45/15/2 109,967 2.39% 0.21% 100.0% 2.39% 0.21%
DN068CHCOREN850 Reinstatement work for house connection 45/15/2 508,787 11.08% 0.98% 98.0% 10.86% 0.96%
Line 34/1/27/45/18/1 (479LM, 21MH) 853,192 100.00% 100.00% 1.64%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA230 Traffic Diversion 45/18/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET130 Setting out 45/18/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (479 LM) 144,658 100.0%
DN068CPIPEXC130 Excavation for sewer pipeline 45/18/1 43,398 5.09% 0.08% 100.0% 5.09% 0.08%
DN068CPIPBED230 Geotextile and Bedding for sewer pipeline 45/18/1 24,592 2.88% 0.05% 100.0% 2.88% 0.05%
DN068CPIPLAY330 Pipe Laying for sewer pipeline 45/18/1 43,398 5.09% 0.08% 100.0% 5.09% 0.08%
DN068CPIPPBF430 Partial Backfill for sewer pipeline 45/18/1 17,359 2.03% 0.03% 100.0% 2.03% 0.03%
DN068CPIPTES530 Test for sewer pipeline 45/18/1 7,233 0.85% 0.01% 100.0% 0.85% 0.01%
DN068CPIPFBF630 Final Backfill for sewer pipeline 45/18/1 8,680 1.02% 0.02% 100.0% 1.02% 0.02%
Manhole Works (21 M.H.) 300,607 100.0%
DN068CMHLEXC140 Excavation works for manhole 45/18/1 21,482 2.52% 0.04% 100.0% 2.52% 0.04%
DN068CMHLBLI240 Blinding for manhole 45/18/1 3,906 0.46% 0.01% 100.0% 0.46% 0.01%
DN068CMHLTAP340 Tanking membrane and protection for manhole 45/18/1 1,953 0.23% 0.00% 100.0% 0.23% 0.00%
DN068CMHLBAS440 Base slab for manhole 45/18/1 39,059 4.58% 0.07% 100.0% 4.58% 0.07%
DN068CMHLGRP840 GRP liner for manhole 45/18/1 44,917 5.26% 0.09% 100.0% 5.26% 0.09%
DN068CMHLWCP540 Wall concrete and pipe for manhole 45/18/1 48,823 5.72% 0.09% 100.0% 5.72% 0.09%
DN068CMHLCOV640 Cover slab for manhole 45/18/1 5,859 0.69% 0.01% 100.0% 0.69% 0.01%
DN068CMHLDIC820 DI cover for manhole 45/18/1 3,906 0.46% 0.01% 100.0% 0.46% 0.01%
DN068CMHLDIC830 Ladder for manhole 45/18/1 3,906 0.46% 0.01% 100.0% 0.46% 0.01%
DN068CMHLEMB940 External tanking membrane and protection for manhole 45/18/1 5,859 0.69% 0.01% 100.0% 0.69% 0.01%
DN068CMHLBAC960 Backfilling for manhole 45/18/1 15,623 1.83% 0.03% 100.0% 1.83% 0.03%
DN068CMHLDIC840 Reinstatement works 45/18/1 105,314 12.34% 0.20% 100.0% 12.34% 0.20%
House Connection Works (17D, 16ABC) 407,926 100.0%
DN068CHCODEM140 Demolition for existing underground structure 45/18/1 79,054 9.27% 0.15% 100.0% 9.27% 0.15%
DN068CHCOEXC240 Excavation for pipeline and inspection chamber 45/18/1 47,368 5.55% 0.09% 100.0% 5.55% 0.09%
DN068CHCOPIP340 Pipe laying for house connection 45/18/1 60,902 7.14% 0.12% 100.0% 7.14% 0.12%
DN068CHCOBAS440 Base for inspection chamber 45/18/1 19,384 2.27% 0.04% 100.0% 2.27% 0.04%
DN068CHCOWAL540 Wall for inspection chamber 45/18/1 48,460 5.68% 0.09% 100.0% 5.68% 0.09%
DN068CHCOFIN940 Finishing for inspection chamber 45/18/1 14,538 1.70% 0.03% 100.0% 1.70% 0.03%
DN068CHCOCOV640 Cover for inspection chamber 45/18/1 14,538 1.70% 0.03% 100.0% 1.70% 0.03%
DN068CHCOBAC740 Backfilling for house connection 45/18/1 27,067 3.17% 0.05% 100.0% 3.17% 0.05%
DN068CHCOREN840 Reinstatement work for house connection 45/18/1 96,616 11.32% 0.19% 100.0% 11.32% 0.19%
Line 34/1/27/45/20/1 (1672 LM, 50MH) 2,820,436 100.00% #N/A 99.60% 5.39%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA220 Traffic Diversion 45/20/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET120 Setting out 45/20/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
PipeLine Works (1672 LM) 764,925 100.0%
DN068CPIPEXC120 Excavation for sewer pipeline 45/20/1 229,477 8.14% 0.44% 100.0% 8.14% 0.44%
DN068CPIPBED220 Geotextile and Bedding for sewer pipeline 45/20/1 130,037 4.61% 0.25% 100.0% 4.61% 0.25%
DN068CPIPLAY320 Pipe Laying for sewer pipeline 45/20/1 229,477 8.14% 0.44% 100.0% 8.14% 0.44%
DN068CPIPPBF420 Partial Backfill for sewer pipeline 45/20/1 91,791 3.25% 0.18% 100.0% 3.25% 0.18%
DN068CPIPTES520 Test for sewer pipeline 45/20/1 38,246 1.36% 0.07% 100.0% 1.36% 0.07%
DN068CPIPFBF620 Final Backfill for sewer pipeline 45/20/1 45,896 1.63% 0.09% 100.0% 1.63% 0.09%
Manhole Works (50 M.H.) 1,253,247 100.0%
DN068CMHLEXC130 Excavation works for manhole 45/20/1 97,039 3.44% 0.19% 100.0% 3.44% 0.19%
DN068CMHLBLI230 Blinding for manhole 45/20/1 17,644 0.63% 0.03% 100.0% 0.63% 0.03%
DN068CMHLTAP330 Tanking membrane and protection for manhole 45/20/1 8,822 0.31% 0.02% 100.0% 0.31% 0.02%
DN068CMHLBAS430 Base slab for manhole 45/20/1 176,435 6.26% 0.34% 100.0% 6.26% 0.34%
DN068CMHLGRP830 GRP liner for manhole 45/20/1 202,900 7.19% 0.39% 100.0% 7.19% 0.39%
DN068CMHLWCP530 Wall concrete and pipe for manhole 45/20/1 220,543 7.82% 0.42% 100.0% 7.82% 0.42%
DN068CMHLCOV630 Cover slab for manhole 45/20/1 26,465 0.94% 0.05% 100.0% 0.94% 0.05%
DN068CMHLDIC790 DI cover for manhole 45/20/1 17,644 0.63% 0.03% 100.0% 0.63% 0.03%
DN068CMHLEMB930 External tanking membrane and protection for manhole 45/20/1 26,465 0.94% 0.05% 100.0% 0.94% 0.05%
DN068CMHLDIC800 Ladder for manhole 45/20/1 17,644 0.63% 0.03% 100.0% 0.63% 0.03%
DN068CMHLBAC950 Backfilling for manhole 45/20/1 70,574 2.50% 0.14% 100.0% 2.50% 0.14%
DN068CMHLDIC810 Reinstatement works 45/20/1 371,073 13.16% 0.71% 100.0% 13.16% 0.71%
House Connection Works (26D, 33ABC) 802,265 98.6%
DN068CHCODEM130 Demolition for existing underground structure 45/20/1 163,048 5.78% 0.31% 98.0% 5.67% 0.31%
DN068CHCOEXC230 Excavation for pipeline and inspection chamber 45/20/1 84,787 3.01% 0.16% 100.0% 3.01% 0.16%
DN068CHCOPIP330 Pipe laying for house connection 45/20/1 109,012 3.87% 0.21% 100.0% 3.87% 0.21%
DN068CHCOBAS430 Base for inspection chamber 45/20/1 39,979 1.42% 0.08% 98.0% 1.39% 0.08%
DN068CHCOWAL530 Wall for inspection chamber 45/20/1 99,948 3.54% 0.19% 98.0% 3.47% 0.19%
DN068CHCOFIN930 Finishing for inspection chamber 45/20/1 29,984 1.06% 0.06% 98.0% 1.04% 0.06%
DN068CHCOCOV630 Cover for inspection chamber 45/20/1 29,984 1.06% 0.06% 98.0% 1.04% 0.06%
DN068CHCOBAC730 Backfilling for house connection 45/20/1 48,450 1.72% 0.09% 100.0% 1.72% 0.09%
DN068CHCOREN830 Reinstatement work for house connection 45/20/1 197,072 6.99% 0.38% 98.0% 6.85% 0.37%
Line 34/1/27/33/2 (4102LM, 120MH) 6,765,910 100.00% #N/A 100.00% 12.99%
Trunk Sewer 34/1/27/33/2 To 34/27/33/18 (1087 LM, 20 MH) 6,765,910 100.0%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS350 Obtaining RO from authorities 33/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA250 Traffic Diversion 33/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET150 Setting out 33/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (1087 LM) 468,560 100.0%
DN068CPIPEXC150 Excavation for sewer pipeline 33/2 140,568 2.08% 0.27% 100.0% 2.08% 0.27%
DN068CPIPBED250 Geotextile and Bedding for sewer pipeline 33/2 79,655 1.18% 0.15% 100.0% 1.18% 0.15%
DN068CPIPLAY350 Pipe Laying for sewer pipeline 33/2 140,568 2.08% 0.27% 100.0% 2.08% 0.27%
DN068CPIPPBF450 Partial Backfill for sewer pipeline 33/2 56,227 0.83% 0.11% 100.0% 0.83% 0.11%
DN068CPIPTES550 Test for sewer pipeline 33/2 23,428 0.35% 0.04% 100.0% 0.35% 0.04%
DN068CPIPFBF650 Final Backfill for sewer pipeline 33/2 28,114 0.42% 0.05% 100.0% 0.42% 0.05%
Manhole Works (20 M.H.) 550,350 100.0%
DN068CMHLEXC160 Excavation works for manhole 33/2 33,909 0.50% 0.07% 100.0% 0.50% 0.07%
DN068CMHLBLI260 Blinding for manhole 33/2 6,165 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLTAP360 Tanking membrane and protection for manhole 33/2 3,083 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLBAS460 Base slab for manhole 33/2 61,652 0.91% 0.12% 100.0% 0.91% 0.12%
DN068CMHLGRP860 GRP liner for manhole 33/2 70,900 1.05% 0.14% 100.0% 1.05% 0.14%
DN068CMHLWCP560 Wall concrete and pipe for manhole 33/2 77,065 1.14% 0.15% 100.0% 1.14% 0.15%
DN068CMHLCOV660 Cover slab for manhole 33/2 9,248 0.14% 0.02% 100.0% 0.14% 0.02%
DN068CMHLDIC880 DI cover for manhole 33/2 6,165 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLDIC890 Ladder for manhole 33/2 6,165 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLEMB960 External tanking membrane and protection for manhole 33/2 9,248 0.14% 0.02% 100.0% 0.14% 0.02%
DN068CMHLBAC980 Backfilling for manhole 33/2 24,661 0.36% 0.05% 100.0% 0.36% 0.05%
DN068CMHLDIC900 Reinstatement works 33/2 242,088 3.58% 0.46% 100.0% 3.58% 0.46%
House Connection Works (16D, 4ABC) 153,089 100.0%
DN068CHCODEM180 Demolition for existing underground structure 33/2 19,763 0.29% 0.04% 100.0% 0.29% 0.04%
DN068CHCOEXC280 Excavation for pipeline and inspection chamber 33/2 28,732 0.42% 0.06% 100.0% 0.42% 0.06%
DN068CHCOPIP380 Pipe laying for house connection 33/2 36,940 0.55% 0.07% 100.0% 0.55% 0.07%
DN068CHCOBAS480 Base for inspection chamber 33/2 4,846 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CHCOWAL580 Wall for inspection chamber 33/2 12,115 0.18% 0.02% 100.0% 0.18% 0.02%
DN068CHCOFIN980 Finishing for inspection chamber 33/2 3,635 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CHCOCOV680 Cover for inspection chamber 33/2 3,635 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CHCOBAC780 Backfilling for house connection 33/2 16,418 0.24% 0.03% 100.0% 0.24% 0.03%
DN068CHCOREN880 Reinstatement work for house connection 33/2 27,005 0.40% 0.05% 100.0% 0.40% 0.05%
Foul 34/1/27/33/12 (2304 LM, 84 MH) 4,756,500 100.0%
PipeLine Works (2304 LM) 993,723 100.0%
DN068CPIPEXC400 Excavation for sewer pipeline 33/12 298,117 4.41% 0.57% 100.0% 4.41% 0.57%
DN068CPIPBED500 Geotextile and Bedding for sewer pipeline 33/12 168,933 2.50% 0.32% 100.0% 2.50% 0.32%
DN068CPIPLAY600 Pipe Laying for sewer pipeline 33/12 298,117 4.41% 0.57% 100.0% 4.41% 0.57%
DN068CPIPPBF700 Partial Backfill for sewer pipeline 33/12 119,247 1.76% 0.23% 100.0% 1.76% 0.23%
DN068CPIPTES800 Test for sewer pipeline 33/12 49,686 0.73% 0.10% 100.0% 0.73% 0.10%
DN068CPIPFBF900 Final Backfill for sewer pipeline 33/12 59,623 0.88% 0.11% 100.0% 0.88% 0.11%
Manhole Works (84 M.H.) 1,807,861 100.0%
DN068CMHLEXC410 Excavation works for manhole 33/12 142,388 2.10% 0.27% 100.0% 2.10% 0.27%
DN068CMHLBLI510 Blinding for manhole 33/12 25,889 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CMHLTAP610 Tanking membrane and protection for manhole 33/12 12,944 0.19% 0.02% 100.0% 0.19% 0.02%
DN068CMHLBAS710 Base slab for manhole 33/12 258,888 3.83% 0.50% 100.0% 3.83% 0.50%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CMHLGRP1110 GRP liner for manhole 33/12 297,721 4.40% 0.57% 100.0% 4.40% 0.57%
DN068CMHLWCP810 Wall concrete and pipe for manhole 33/12 323,610 4.78% 0.62% 100.0% 4.78% 0.62%
DN068CMHLCOV910 Cover slab for manhole 33/12 38,833 0.57% 0.07% 100.0% 0.57% 0.07%
DN068CMHLDIC1630 DI cover for manhole 33/12 25,889 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CMHLEMB1210 External tanking membrane and protection for manhole 33/12 38,833 0.57% 0.07% 100.0% 0.57% 0.07%
DN068CMHLDIC1640 Ladder for manhole 33/12 25,889 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CMHLBAC1230 Backfilling for manhole 33/12 103,555 1.53% 0.20% 100.0% 1.53% 0.20%
DN068CMHLDIC1650 Reinstatement works 33/12 513,421 7.59% 0.99% 100.0% 7.59% 0.99%
House Connection Works (27D, 88ABC) 1,954,916 100.0%
DN068CHCODEM160 Demolition for existing underground structure 33/12 434,795 6.43% 0.83% 100.0% 6.43% 0.83%
DN068CHCOEXC260 Excavation for pipeline and inspection chamber 33/12 165,135 2.44% 0.32% 100.0% 2.44% 0.32%
DN068CHCOPIP360 Pipe laying for house connection 33/12 212,316 3.14% 0.41% 100.0% 3.14% 0.41%
DN068CHCOBAS460 Base for inspection chamber 33/12 106,611 1.58% 0.20% 100.0% 1.58% 0.20%
DN068CHCOWAL560 Wall for inspection chamber 33/12 266,528 3.94% 0.51% 100.0% 3.94% 0.51%
DN068CHCOFIN960 Finishing for inspection chamber 33/12 79,958 1.18% 0.15% 100.0% 1.18% 0.15%
DN068CHCOCOV660 Cover for inspection chamber 33/12 79,958 1.18% 0.15% 100.0% 1.18% 0.15%
DN068CHCOBAC760 Backfilling for house connection 33/12 94,363 1.39% 0.18% 100.0% 1.39% 0.18%
DN068CHCOREN860 Reinstatement work for house connection 33/12 515,252 7.62% 0.99% 100.0% 7.62% 0.99%
Foul 34/1/27/33/5 (482 LM, 10 MH) 547,505 100.0%
PipeLine Works (482 LM) 207,836 100.0%
DN068CPIPEXC410 Excavation for sewer pipeline 33/5 62,351 0.92% 0.12% 100.0% 0.92% 0.12%
DN068CPIPBED510 Geotextile and Bedding for sewer pipeline 33/5 35,332 0.52% 0.07% 100.0% 0.52% 0.07%
DN068CPIPLAY610 Pipe Laying for sewer pipeline 33/5 62,351 0.92% 0.12% 100.0% 0.92% 0.12%
DN068CPIPPBF710 Partial Backfill for sewer pipeline 33/5 24,940 0.37% 0.05% 100.0% 0.37% 0.05%
DN068CPIPTES810 Test for sewer pipeline 33/5 10,392 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CPIPFBF910 Final Backfill for sewer pipeline 33/5 12,470 0.18% 0.02% 100.0% 0.18% 0.02%
Manhole Works (10 M.H.) 261,420 100.0%
DN068CMHLEXC420 Excavation works for manhole 33/5 16,944 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CMHLBLI520 Blinding for manhole 33/5 3,081 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLTAP620 Tanking membrane and protection for manhole 33/5 1,540 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLBAS720 Base slab for manhole 33/5 30,808 0.46% 0.06% 100.0% 0.46% 0.06%
DN068CMHLGRP1120 GRP liner for manhole 33/5 35,429 0.52% 0.07% 100.0% 0.52% 0.07%
DN068CMHLWCP820 Wall concrete and pipe for manhole 33/5 38,510 0.57% 0.07% 100.0% 0.57% 0.07%
DN068CMHLCOV920 Cover slab for manhole 33/5 4,621 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLDIC1660 DI cover for manhole 33/5 3,081 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLDIC1670 Ladder for manhole 33/5 3,081 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLEMB1220 External tanking membrane and protection for manhole 33/5 4,621 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLBAC1240 Backfilling for manhole 33/5 12,323 0.18% 0.02% 100.0% 0.18% 0.02%
DN068CMHLDIC1680 Reinstatement works 33/5 107,382 1.59% 0.21% 100.0% 1.59% 0.21%
House Connection Works (18D) 78,249 100.0%
DN068CHCOEXC500 Excavation for pipeline for house connection 33/5 25,858 0.38% 0.05% 100.0% 0.38% 0.05%
DN068CHCOPIP600 Pipe laying for house connection 33/5 33,246 0.49% 0.06% 100.0% 0.49% 0.06%
DN068CHCOBAC1000 Backfilling for pipe for house connection 33/5 14,776 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CHCOREN1100 Marker Post for house connection 33/5 4,368 0.06% 0.01% 100.0% 0.06% 0.01%
Foul 34/1/27/33/3A (229 LM, 6 MH) 289,906 100.0%
PipeLine Works (229 LM) 98,700 100.0%
DN068CPIPEXC420 Excavation for sewer pipeline 33/3A 29,610 0.44% 0.06% 100.0% 0.44% 0.06%
DN068CPIPBED520 Geotextile and Bedding for sewer pipeline 33/3A 16,779 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CPIPLAY620 Pipe Laying for sewer pipeline 33/3A 29,610 0.44% 0.06% 100.0% 0.44% 0.06%
DN068CPIPPBF720 Partial Backfill for sewer pipeline 33/3A 11,844 0.18% 0.02% 100.0% 0.18% 0.02%
DN068CPIPTES820 Test for sewer pipeline 33/3A 4,935 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CPIPFBF920 Final Backfill for sewer pipeline 33/3A 5,922 0.09% 0.01% 100.0% 0.09% 0.01%
Manhole Works (6 M.H.) 143,455 100.0%
DN068CMHLEXC430 Excavation works for manhole 33/3A 10,171 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CMHLBLI530 Blinding for manhole 33/3A 1,849 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLTAP630 Tanking membrane and protection for manhole 33/3A 925 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS730 Base slab for manhole 33/3A 18,492 0.27% 0.04% 100.0% 0.27% 0.04%
DN068CMHLGRP1130 GRP liner for manhole 33/3A 21,266 0.31% 0.04% 100.0% 0.31% 0.04%
DN068CMHLWCP830 Wall concrete and pipe for manhole 33/3A 23,115 0.34% 0.04% 100.0% 0.34% 0.04%
DN068CMHLCOV930 Cover slab for manhole 33/3A 2,774 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1690 DI cover for manhole 33/3A 1,849 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLDIC1700 Ladder for manhole 33/3A 1,849 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLEMB1230 External tanking membrane and protection for manhole 33/3A 2,774 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLBAC1250 Backfilling for manhole 33/3A 7,397 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLDIC1710 Reinstatement works 33/3A 50,995 0.75% 0.10% 100.0% 0.75% 0.10%
House Connection Works (11D) 47,751 100.0%
DN068CHCOEXC510 Excavation for pipeline for house connection 33/3A 15,779 0.23% 0.03% 100.0% 0.23% 0.03%
DN068CHCOPIP610 Pipe laying for house connection 33/3A 20,287 0.30% 0.04% 100.0% 0.30% 0.04%
DN068CHCOBAC1010 Backfilling for Pipe for house connection 33/3A 9,016 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CHCOREN1110 Marker post for house connection 33/3A 2,669 0.04% 0.01% 100.0% 0.04% 0.01%
Line 34/1/27/38/1 (750LM, 18MH) 729,448 100.00% #N/A 99.92% 1.40%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS360 Obtaining RO from authorities 38/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA260 Traffic Diversion 38/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET160 Setting out 38/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (750 LM) 248,235 100.0%
DN068CPIPEXC160 Excavation for sewer pipeline 38/1 74,471 10.21% 0.14% 100.0% 10.21% 0.14%
DN068CPIPBED260 Geotextile and Bedding for sewer pipeline 38/1 42,200 5.79% 0.08% 100.0% 5.79% 0.08%
DN068CPIPLAY360 Pipe Laying for sewer pipeline 38/1 74,471 10.21% 0.14% 100.0% 10.21% 0.14%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CPIPPBF460 Partial Backfill for sewer pipeline 38/1 29,788 4.08% 0.06% 100.0% 4.08% 0.06%
DN068CPIPTES560 Test for sewer pipeline 38/1 12,412 1.70% 0.02% 100.0% 1.70% 0.02%
DN068CPIPFBF660 Final Backfill for sewer pipeline 38/1 14,894 2.04% 0.03% 100.0% 2.04% 0.03%
Manhole Works (18 M.H.) 376,962 100.0%
DN068CMHLEXC170 Excavation works for manhole 38/1 22,956 3.15% 0.04% 100.0% 3.15% 0.04%
DN068CMHLBLI270 Blinding for manhole 38/1 4,174 0.57% 0.01% 100.0% 0.57% 0.01%
DN068CMHLTAP370 Tanking membrane and protection for manhole 38/1 2,087 0.29% 0.00% 100.0% 0.29% 0.00%
DN068CMHLBAS470 Base slab for manhole 38/1 41,737 5.72% 0.08% 100.0% 5.72% 0.08%
DN068CMHLGRP870 GRP liner for manhole 38/1 47,998 6.58% 0.09% 100.0% 6.58% 0.09%
DN068CMHLWCP570 Wall concrete and pipe for manhole 38/1 52,172 7.15% 0.10% 100.0% 7.15% 0.10%
DN068CMHLCOV670 Cover slab for manhole 38/1 6,261 0.86% 0.01% 100.0% 0.86% 0.01%
DN068CMHLDIC910 DI cover for manhole 38/1 4,174 0.57% 0.01% 100.0% 0.57% 0.01%
DN068CMHLDIC920 Ladder for manhole 38/1 4,174 0.57% 0.01% 100.0% 0.57% 0.01%
DN068CMHLEMB970 External tanking membrane and protection for manhole 38/1 6,261 0.86% 0.01% 100.0% 0.86% 0.01%
DN068CMHLBAC990 Backfilling for manhole 38/1 16,695 2.29% 0.03% 100.0% 2.29% 0.03%
DN068CMHLDIC930 Reinstatement works 38/1 168,276 23.07% 0.32% 100.0% 23.07% 0.32%
House Connection Works (24D) 104,251 99.4%
DN068CHCOEXC270 Excavation for pipeline for house connection 38/1 34,449 4.72% 0.07% 100.0% 4.72% 0.07%
DN068CHCOPIP370 Pipe laying for house connection 38/1 44,292 6.07% 0.09% 100.0% 6.07% 0.09%
DN068CHCOBAC770 Backfilling for Pipe for house connection 38/1 19,685 2.70% 0.04% 100.0% 2.70% 0.04%
DN068CHCOREN870 Marker post for house connection 38/1 5,824 0.80% 0.01% 90.0% 0.72% 0.01%
Line 34/1/27/40/2 (3348LM, 123MH) 6,527,860 100.00% #N/A 100.00% 12.53%
Trunk sewer 34/1/27/40/2 To 34/1/27/40/32 6,527,860 100.0%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS370 Obtaining RO from authorities 40/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA270 Traffic Diversion 40/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET170 Setting out 40/2 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (1186 LM) 474,437 100.0%
DN068CPIPEXC170 Excavation for sewer pipeline 40/2 142,331 2.18% 0.27% 100.0% 2.18% 0.27%
DN068CPIPBED270 Geotextile and Bedding for sewer pipeline 40/2 80,654 1.24% 0.15% 100.0% 1.24% 0.15%
DN068CPIPLAY370 Pipe Laying for sewer pipeline 40/2 142,331 2.18% 0.27% 100.0% 2.18% 0.27%
DN068CPIPPBF470 Partial Backfill for sewer pipeline 40/2 56,932 0.87% 0.11% 100.0% 0.87% 0.11%
DN068CPIPTES570 Test for sewer pipeline 40/2 23,722 0.36% 0.05% 100.0% 0.36% 0.05%
DN068CPIPFBF670 Final Backfill for sewer pipeline 40/2 28,466 0.44% 0.05% 100.0% 0.44% 0.05%
Manhole Works (32 M.H.) 745,339 100.0%
DN068CMHLEXC180 Excavation works for manhole 40/2 53,688 0.82% 0.10% 100.0% 0.82% 0.10%
DN068CMHLBLI280 Blinding for manhole 40/2 9,762 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CMHLTAP380 Tanking membrane and protection for manhole 40/2 4,881 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLBAS480 Base slab for manhole 40/2 97,615 1.50% 0.19% 100.0% 1.50% 0.19%
DN068CMHLGRP880 GRP liner for manhole 40/2 112,257 1.72% 0.22% 100.0% 1.72% 0.22%
DN068CMHLWCP580 Wall concrete and pipe for manhole 40/2 122,019 1.87% 0.23% 100.0% 1.87% 0.23%
DN068CMHLCOV680 Cover slab for manhole 40/2 14,642 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLDIC940 DI cover for manhole 40/2 9,762 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CMHLEMB980 External tanking membrane and protection for manhole 40/2 14,642 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLDIC950 Ladder for manhole 40/2 9,762 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CMHLBAC1000 Backfilling for manhole 40/2 39,046 0.60% 0.07% 100.0% 0.60% 0.07%
DN068CMHLDIC960 Reinstatement works 40/2 257,264 3.94% 0.49% 100.0% 3.94% 0.49%
House Connection Works (7D, 20ABC) 448,195 100.0%
DN068CHCODEM470 Demolition for existing underground structure 40/2 98,817 1.51% 0.19% 100.0% 1.51% 0.19%
DN068CHCOEXC570 Excavation for pipeline and inspection chamber 40/2 38,821 0.59% 0.07% 100.0% 0.59% 0.07%
DN068CHCOPIP670 Pipe laying for house connection 40/2 49,913 0.76% 0.10% 100.0% 0.76% 0.10%
DN068CHCOBAS770 Base for inspection chamber 40/2 24,230 0.37% 0.05% 100.0% 0.37% 0.05%
DN068CHCOWAL870 Wall for inspection chamber 40/2 60,575 0.93% 0.12% 100.0% 0.93% 0.12%
DN068CHCOFIN1270 Finishing for inspection chamber 40/2 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOCOV970 Cover for inspection chamber 40/2 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOBAC1070 Backfilling for house connection 40/2 22,183 0.34% 0.04% 100.0% 0.34% 0.04%
DN068CHCOREN1170 Reinstatement work for house connection 40/2 117,312 1.80% 0.23% 100.0% 1.80% 0.23%
Foul 34/1/27/40/24 (88LM, 5MH) 260,084 100.0%
PipeLine Works (88LM) 35,094 100.0%
DN068CPIPEXC430 Excavation for sewer pipeline 40/24 10,528 0.16% 0.02% 100.0% 0.16% 0.02%
DN068CPIPBED530 Geotextile and Bedding for sewer pipeline 40/24 5,966 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CPIPLAY630 Pipe Laying for sewer pipeline 40/24 10,528 0.16% 0.02% 100.0% 0.16% 0.02%
DN068CPIPPBF730 Partial Backfill for sewer pipeline 40/24 4,211 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CPIPTES830 Test for sewer pipeline 40/24 1,755 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CPIPFBF930 Final Backfill for sewer pipeline 40/24 2,106 0.03% 0.00% 100.0% 0.03% 0.00%
Manhole Works (5M.H.) 95,374 100.0%
DN068CMHLEXC440 Excavation works for manhole 40/24 8,398 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CMHLBLI540 Blinding for manhole 40/24 1,527 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLTAP640 Tanking membrane and protection for manhole 40/24 763 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS740 Base slab for manhole 40/24 15,269 0.23% 0.03% 100.0% 0.23% 0.03%
DN068CMHLGRP1140 GRP liner for manhole 40/24 17,559 0.27% 0.03% 100.0% 0.27% 0.03%
DN068CMHLWCP840 Wall concrete and pipe for manhole 40/24 19,086 0.29% 0.04% 100.0% 0.29% 0.04%
DN068CMHLCOV940 Cover slab for manhole 40/24 2,290 0.04% 0.00% 100.0% 0.04% 0.00%
DN068CMHLDIC1720 DI cover for manhole 40/24 1,527 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLDIC1730 Ladder for manhole 40/24 1,527 0.02% 0.00% 100.0% 0.02% 0.00%
DN068CMHLEMB1240 External tanking membrane and protection for manhole 40/24 2,290 0.04% 0.00% 100.0% 0.04% 0.00%
DN068CMHLBAC1260 Backfilling for manhole 40/24 6,108 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLDIC1740 Reinstatement works 40/24 19,030 0.29% 0.04% 100.0% 0.29% 0.04%
House Connection Works (1D, 6ABC) 129,616 100.0%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CHCODEM420 Demolition for existing underground structure 40/24 29,645 0.45% 0.06% 100.0% 0.45% 0.06%
DN068CHCOEXC520 Excavation for pipeline and inspection chamber 40/24 10,045 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CHCOPIP620 Pipe laying for house connection 40/24 12,915 0.20% 0.02% 100.0% 0.20% 0.02%
DN068CHCOBAS720 Base for inspection chamber 40/24 7,269 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CHCOWAL820 Wall for inspection chamber 40/24 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOFIN1220 Finishing for inspection chamber 40/24 5,452 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CHCOCOV920 Cover for inspection chamber 40/24 5,452 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CHCOBAC1020 Backfilling for house connection 40/24 5,740 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CHCOREN1120 Reinstatement work for house connection 40/24 34,927 0.54% 0.07% 100.0% 0.54% 0.07%
Foul 34/1/27/40/22 (264LM, 11MH) 549,629 100.0%
PipeLine Works (255LM) 105,683 100.0%
DN068CPIPEXC440 Excavation for sewer pipeline 40/22 31,705 0.49% 0.06% 100.0% 0.49% 0.06%
DN068CPIPBED540 Geotextile and Bedding for sewer pipeline 40/22 17,966 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CPIPLAY640 Pipe Laying for sewer pipeline 40/22 31,705 0.49% 0.06% 100.0% 0.49% 0.06%
DN068CPIPPBF740 Partial Backfill for sewer pipeline 40/22 12,682 0.19% 0.02% 100.0% 0.19% 0.02%
DN068CPIPTES840 Test for sewer pipeline 40/22 5,284 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CPIPFBF940 Final Backfill for sewer pipeline 40/22 6,341 0.10% 0.01% 100.0% 0.10% 0.01%
Manhole Works (11M.H.) 225,001 100.0%
DN068CMHLEXC450 Excavation works for manhole 40/22 18,446 0.28% 0.04% 100.0% 0.28% 0.04%
DN068CMHLBLI550 Blinding for manhole 40/22 3,354 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLTAP650 Tanking membrane and protection for manhole 40/22 1,677 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLBAS750 Base slab for manhole 40/22 33,539 0.51% 0.06% 100.0% 0.51% 0.06%
DN068CMHLGRP1150 GRP liner for manhole 40/22 38,570 0.59% 0.07% 100.0% 0.59% 0.07%
DN068CMHLWCP850 Wall concrete and pipe for manhole 40/22 41,923 0.64% 0.08% 100.0% 0.64% 0.08%
DN068CMHLCOV950 Cover slab for manhole 40/22 5,031 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CMHLDIC1750 DI cover for manhole 40/22 3,354 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLDIC1760 Ladder for manhole 40/22 3,354 0.05% 0.01% 100.0% 0.05% 0.01%
DN068CMHLEMB1250 External tanking membrane and protection for manhole 40/22 5,031 0.08% 0.01% 100.0% 0.08% 0.01%
DN068CMHLBAC1270 Backfilling for manhole 40/22 13,416 0.21% 0.03% 100.0% 0.21% 0.03%
DN068CMHLDIC1770 Reinstatement works 40/22 57,307 0.88% 0.11% 100.0% 0.88% 0.11%
House Connection Works (12D, 8ABC) 218,945 100.0%
DN068CHCODEM430 Demolition for existing underground structure 40/22 39,527 0.61% 0.08% 100.0% 0.61% 0.08%
DN068CHCOEXC530 Excavation for pipeline and inspection chamber 40/22 28,630 0.44% 0.05% 100.0% 0.44% 0.05%
DN068CHCOPIP630 Pipe laying for house connection 40/22 36,811 0.56% 0.07% 100.0% 0.56% 0.07%
DN068CHCOBAS730 Base for inspection chamber 40/22 9,692 0.15% 0.02% 100.0% 0.15% 0.02%
DN068CHCOWAL830 Wall for inspection chamber 40/22 24,230 0.37% 0.05% 100.0% 0.37% 0.05%
DN068CHCOFIN1230 Finishing for inspection chamber 40/22 7,269 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CHCOCOV930 Cover for inspection chamber 40/22 7,269 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CHCOBAC1030 Backfilling for house connection 40/22 16,360 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CHCOREN1130 Reinstatement work for house connection 40/22 49,158 0.75% 0.09% 100.0% 0.75% 0.09%
Foul 34/1/27/40/14 (339LM, 13MH) 638,959 100.0%
PipeLine Works (339LM) 135,687 100.0%
DN068CPIPEXC450 Excavation for sewer pipeline 40/14 40,706 0.62% 0.08% 100.0% 0.62% 0.08%
DN068CPIPBED550 Geotextile and Bedding for sewer pipeline 40/14 23,067 0.35% 0.04% 100.0% 0.35% 0.04%
DN068CPIPLAY650 Pipe Laying for sewer pipeline 40/14 40,706 0.62% 0.08% 100.0% 0.62% 0.08%
DN068CPIPPBF750 Partial Backfill for sewer pipeline 40/14 16,283 0.25% 0.03% 100.0% 0.25% 0.03%
DN068CPIPTES850 Test for sewer pipeline 40/14 6,784 0.10% 0.01% 100.0% 0.10% 0.01%
DN068CPIPFBF950 Final Backfill for sewer pipeline 40/14 8,141 0.12% 0.02% 100.0% 0.12% 0.02%
Manhole Works (13M.H.) 271,846 100.0%
DN068CMHLEXC460 Excavation works for manhole 40/14 21,810 0.33% 0.04% 100.0% 0.33% 0.04%
DN068CMHLBLI560 Blinding for manhole 40/14 3,965 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CMHLTAP660 Tanking membrane and protection for manhole 40/14 1,983 0.03% 0.00% 100.0% 0.03% 0.00%
DN068CMHLBAS760 Base slab for manhole 40/14 39,654 0.61% 0.08% 100.0% 0.61% 0.08%
DN068CMHLGRP1160 GRP liner for manhole 40/14 45,602 0.70% 0.09% 100.0% 0.70% 0.09%
DN068CMHLWCP860 Wall concrete and pipe for manhole 40/14 49,567 0.76% 0.10% 100.0% 0.76% 0.10%
DN068CMHLCOV960 Cover slab for manhole 40/14 5,948 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLDIC1780 DI cover for manhole 40/14 3,965 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CMHLDIC1790 Ladder for manhole 40/14 3,965 0.06% 0.01% 100.0% 0.06% 0.01%
DN068CMHLEMB1260 External tanking membrane and protection for manhole 40/14 5,948 0.09% 0.01% 100.0% 0.09% 0.01%
DN068CMHLBAC1280 Backfilling for manhole 40/14 15,862 0.24% 0.03% 100.0% 0.24% 0.03%
DN068CMHLDIC1800 Reinstatement works 40/14 73,577 1.13% 0.14% 100.0% 1.13% 0.14%
House Connection Works (10D, 9ABC) 231,426 100.0%
DN068CHCODEM440 Demolition for existing underground structure 40/14 44,468 0.68% 0.09% 100.0% 0.68% 0.09%
DN068CHCOEXC540 Excavation for pipeline and inspection chamber 40/14 27,296 0.42% 0.05% 100.0% 0.42% 0.05%
DN068CHCOPIP640 Pipe laying for house connection 40/14 35,095 0.54% 0.07% 100.0% 0.54% 0.07%
DN068CHCOBAS740 Base for inspection chamber 40/14 10,903 0.17% 0.02% 100.0% 0.17% 0.02%
DN068CHCOWAL840 Wall for inspection chamber 40/14 27,259 0.42% 0.05% 100.0% 0.42% 0.05%
DN068CHCOFIN1240 Finishing for inspection chamber 40/14 8,178 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CHCOCOV940 Cover for inspection chamber 40/14 8,178 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CHCOBAC1040 Backfilling for house connection 40/14 15,598 0.24% 0.03% 100.0% 0.24% 0.03%
DN068CHCOREN1140 Reinstatement work for house connection 40/14 54,453 0.83% 0.10% 100.0% 0.83% 0.10%
Foul 34/1/27/40/9 (411LM, 15MH) 834,899 100.0%
PipeLine Works (411LM) 164,486 100.0%
DN068CPIPEXC460 Excavation for sewer pipeline 40/9 49,346 0.76% 0.09% 100.0% 0.76% 0.09%
DN068CPIPBED560 Geotextile and Bedding for sewer pipeline 40/9 27,963 0.43% 0.05% 100.0% 0.43% 0.05%
DN068CPIPLAY660 Pipe Laying for sewer pipeline 40/9 49,346 0.76% 0.09% 100.0% 0.76% 0.09%
DN068CPIPPBF760 Partial Backfill for sewer pipeline 40/9 19,738 0.30% 0.04% 100.0% 0.30% 0.04%
DN068CPIPTES860 Test for sewer pipeline 40/9 8,224 0.13% 0.02% 100.0% 0.13% 0.02%
DN068CPIPFBF960 Final Backfill for sewer pipeline 40/9 9,869 0.15% 0.02% 100.0% 0.15% 0.02%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
Manhole Works (15M.H.) 318,036 100.0%
DN068CMHLEXC470 Excavation works for manhole 40/9 25,173 0.39% 0.05% 100.0% 0.39% 0.05%
DN068CMHLBLI570 Blinding for manhole 40/9 4,577 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLTAP670 Tanking membrane and protection for manhole 40/9 2,288 0.04% 0.00% 100.0% 0.04% 0.00%
DN068CMHLBAS770 Base slab for manhole 40/9 45,769 0.70% 0.09% 100.0% 0.70% 0.09%
DN068CMHLGRP1170 GRP liner for manhole 40/9 52,634 0.81% 0.10% 100.0% 0.81% 0.10%
DN068CMHLWCP870 Wall concrete and pipe for manhole 40/9 57,211 0.88% 0.11% 100.0% 0.88% 0.11%
DN068CMHLCOV970 Cover slab for manhole 40/9 6,865 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLDIC1810 DI cover for manhole 40/9 4,577 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLDIC1820 Ladder for manhole 40/9 4,577 0.07% 0.01% 100.0% 0.07% 0.01%
DN068CMHLEMB1270 External tanking membrane and protection for manhole 40/9 6,865 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLBAC1290 Backfilling for manhole 40/9 18,308 0.28% 0.04% 100.0% 0.28% 0.04%
DN068CMHLDIC1830 Reinstatement works 40/9 89,193 1.37% 0.17% 100.0% 1.37% 0.17%
House Connection Works (9D, 15ABC) 352,377 100.0%
DN068CHCODEM450 Demolition for existing underground structure 40/9 74,113 1.14% 0.14% 100.0% 1.14% 0.14%
DN068CHCOEXC550 Excavation for pipeline and inspection chamber 40/9 34,478 0.53% 0.07% 100.0% 0.53% 0.07%
DN068CHCOPIP650 Pipe laying for house connection 40/9 44,329 0.68% 0.09% 100.0% 0.68% 0.09%
DN068CHCOBAS750 Base for inspection chamber 40/9 18,172 0.28% 0.03% 100.0% 0.28% 0.03%
DN068CHCOWAL850 Wall for inspection chamber 40/9 45,431 0.70% 0.09% 100.0% 0.70% 0.09%
DN068CHCOFIN1250 Finishing for inspection chamber 40/9 13,629 0.21% 0.03% 100.0% 0.21% 0.03%
DN068CHCOCOV950 Cover for inspection chamber 40/9 13,629 0.21% 0.03% 100.0% 0.21% 0.03%
DN068CHCOBAC1050 Backfilling for house connection 40/9 19,702 0.30% 0.04% 100.0% 0.30% 0.04%
DN068CHCOREN1150 Reinstatement work for house connection 40/9 88,894 1.36% 0.17% 100.0% 1.36% 0.17%
Foul 34/1/27/40/5 (1060LM, 47MH) 2,576,320 100.0%
PipeLine Works (1060LM) 424,073 100.0%
DN068CPIPEXC470 Excavation for sewer pipeline 40/5 127,222 1.95% 0.24% 100.0% 1.95% 0.24%
DN068CPIPBED570 Geotextile and Bedding for sewer pipeline 40/5 72,093 1.10% 0.14% 100.0% 1.10% 0.14%
DN068CPIPLAY670 Pipe Laying for sewer pipeline 40/5 127,222 1.95% 0.24% 100.0% 1.95% 0.24%
DN068CPIPPBF770 Partial Backfill for sewer pipeline 40/5 50,889 0.78% 0.10% 100.0% 0.78% 0.10%
DN068CPIPTES870 Test for sewer pipeline 40/5 21,204 0.32% 0.04% 100.0% 0.32% 0.04%
DN068CPIPFBF970 Final Backfill for sewer pipeline 40/5 25,444 0.39% 0.05% 100.0% 0.39% 0.05%
Manhole Works (47M.H.) 946,498 100.0%
DN068CMHLEXC480 Excavation works for manhole 40/5 78,820 1.21% 0.15% 100.0% 1.21% 0.15%
DN068CMHLBLI580 Blinding for manhole 40/5 14,331 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLTAP680 Tanking membrane and protection for manhole 40/5 7,165 0.11% 0.01% 100.0% 0.11% 0.01%
DN068CMHLBAS780 Base slab for manhole 40/5 143,309 2.20% 0.28% 100.0% 2.20% 0.28%
DN068CMHLGRP1180 GRP liner for manhole 40/5 164,805 2.52% 0.32% 100.0% 2.52% 0.32%
DN068CMHLWCP880 Wall concrete and pipe for manhole 40/5 179,136 2.74% 0.34% 100.0% 2.74% 0.34%
DN068CMHLCOV980 Cover slab for manhole 40/5 21,496 0.33% 0.04% 100.0% 0.33% 0.04%
DN068CMHLDIC1840 DI cover for manhole 40/5 14,331 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLEMB1280 External tanking membrane and protection for manhole 40/5 21,496 0.33% 0.04% 100.0% 0.33% 0.04%
DN068CMHLDIC1850 Ladder for manhole 40/5 14,331 0.22% 0.03% 100.0% 0.22% 0.03%
DN068CMHLBAC1300 Backfilling for manhole 40/5 57,324 0.88% 0.11% 100.0% 0.88% 0.11%
DN068CMHLDIC1860 Reinstatement works 40/5 229,954 3.52% 0.44% 100.0% 3.52% 0.44%
House Connection Works (18D, 54ABC) 1,205,749 100.0%
DN068CHCODEM460 Demolition for existing underground structure 40/5 266,806 4.09% 0.51% 100.0% 4.09% 0.51%
DN068CHCOEXC560 Excavation for pipeline and inspection chamber 40/5 103,361 1.58% 0.20% 100.0% 1.58% 0.20%
DN068CHCOPIP660 Pipe laying for house connection 40/5 132,892 2.04% 0.26% 100.0% 2.04% 0.26%
DN068CHCOBAS760 Base for inspection chamber 40/5 65,420 1.00% 0.13% 100.0% 1.00% 0.13%
DN068CHCOWAL860 Wall for inspection chamber 40/5 163,551 2.51% 0.31% 100.0% 2.51% 0.31%
DN068CHCOFIN1260 Finishing for inspection chamber 40/5 49,065 0.75% 0.09% 100.0% 0.75% 0.09%
DN068CHCOCOV960 Cover for inspection chamber 40/5 49,065 0.75% 0.09% 100.0% 0.75% 0.09%
DN068CHCOBAC1060 Backfilling for house connection 40/5 59,063 0.90% 0.11% 100.0% 0.90% 0.11%
DN068CHCOREN1160 Reinstatement work for house connection 40/5 316,525 4.85% 0.61% 100.0% 4.85% 0.61%
Line 34/1/27/30/1 (603LM, 18MH) 774,319 100.00% #N/A 97.05% 1.44%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS300 Obtaining RO from authorities 30/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA200 Traffic Diversion 30/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET100 Setting out 30/1 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (603 LM) 220,564 100.0%
DN068CPIPEXC100 Excavation for sewer pipeline 30/1 66,169 8.55% 0.13% 100.0% 8.55% 0.13%
DN068CPIPBED200 Geotextile and Bedding for sewer pipeline 30/1 37,496 4.84% 0.07% 100.0% 4.84% 0.07%
DN068CPIPLAY300 Pipe Laying for sewer pipeline 30/1 66,169 8.55% 0.13% 100.0% 8.55% 0.13%
DN068CPIPPBF400 Partial Backfill for sewer pipeline 30/1 26,468 3.42% 0.05% 100.0% 3.42% 0.05%
DN068CPIPTES500 Test for sewer pipeline 30/1 11,028 1.42% 0.02% 100.0% 1.42% 0.02%
DN068CPIPFBF600 Final Backfill for sewer pipeline 30/1 13,234 1.71% 0.03% 100.0% 1.71% 0.03%
Manhole Works (18 M.H.) 352,781 100.0%
DN068CMHLEXC100 Excavation works for manhole 30/1 24,714 3.19% 0.05% 100.0% 3.19% 0.05%
DN068CMHLBLI200 Blinding for manhole 30/1 4,494 0.58% 0.01% 100.0% 0.58% 0.01%
DN068CMHLTAP300 Tanking membrane and protection for manhole 30/1 2,247 0.29% 0.00% 100.0% 0.29% 0.00%
DN068CMHLBAS400 Base slab for manhole 30/1 44,935 5.80% 0.09% 100.0% 5.80% 0.09%
DN068CMHLGRP800 GRP liner for manhole 30/1 51,675 6.67% 0.10% 100.0% 6.67% 0.10%
DN068CMHLWCP500 Wall concrete and pipe for manhole 30/1 56,169 7.25% 0.11% 100.0% 7.25% 0.11%
DN068CMHLCOV600 Cover slab for manhole 30/1 6,740 0.87% 0.01% 100.0% 0.87% 0.01%
DN068CMHLDIC700 DI cover for manhole 30/1 4,494 0.58% 0.01% 100.0% 0.58% 0.01%
DN068CMHLDIC710 Ladder for manhole 30/1 4,494 0.58% 0.01% 100.0% 0.58% 0.01%
DN068CMHLEMB900 External tanking membrane and protection for manhole 30/1 6,740 0.87% 0.01% 100.0% 0.87% 0.01%
DN068CMHLBAC920 Backfilling for manhole 30/1 17,974 2.32% 0.03% 100.0% 2.32% 0.03%
DN068CMHLDIC720 Reinstatement works 30/1 128,106 16.54% 0.25% 90.0% 14.89% 0.22%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
House Connection Works (12D, 7ABC) 200,973 95.0%
DN068CHCODEM100 Demolition for existing underground structure 30/1 34,586 4.47% 0.07% 95.0% 4.24% 0.06%
DN068CHCOEXC200 Excavation for pipeline and inspection chamber 30/1 28,213 3.64% 0.05% 95.0% 3.46% 0.05%
DN068CHCOPIP300 Pipe laying for house connection 30/1 36,274 4.68% 0.07% 95.0% 4.45% 0.07%
DN068CHCOBAS400 Base for inspection chamber 30/1 8,480 1.10% 0.02% 95.0% 1.04% 0.02%
DN068CHCOWAL500 Wall for inspection chamber 30/1 21,201 2.74% 0.04% 95.0% 2.60% 0.04%
DN068CHCOFIN900 Finishing for inspection chamber 30/1 6,360 0.82% 0.01% 95.0% 0.78% 0.01%
DN068CHCOCOV600 Cover for inspection chamber 30/1 6,360 0.82% 0.01% 95.0% 0.78% 0.01%
DN068CHCOBAC700 Backfilling for house connection 30/1 16,122 2.08% 0.03% 95.0% 1.98% 0.03%
DN068CHCOREN800 Reinstatement work for house connection 30/1 43,377 5.60% 0.08% 95.0% 5.32% 0.08%
Line 34/1/27/24 (1324LM, 32MH) 1,226,714 100.00% #N/A 99.05% 2.33%
Traffic Management and Setting Out 0 0.0%
DN068CGENTRA290 Traffic Diversion 24 0 0.00% 0.00% 90.0% 0.00% 0.00%
DN068CGENSET110 Setting out 24 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (1324 LM) 422,007 100.0%
DN068CPIPEXC110 Excavation for sewer pipeline 24 126,602 10.32% 0.24% 100.0% 10.32% 0.24%
DN068CPIPBED210 Geotextile and Bedding for sewer pipeline 24 71,741 5.85% 0.14% 100.0% 5.85% 0.14%
DN068CPIPLAY310 Pipe Laying for sewer pipeline 24 126,602 10.32% 0.24% 100.0% 10.32% 0.24%
DN068CPIPPBF410 Partial Backfill for sewer pipeline 24 50,641 4.13% 0.10% 100.0% 4.13% 0.10%
DN068CPIPTES510 Test for sewer pipeline 24 21,100 1.72% 0.04% 100.0% 1.72% 0.04%
DN068CPIPFBF610 Final Backfill for sewer pipeline 24 25,320 2.06% 0.05% 100.0% 2.06% 0.05%
Manhole Works (32 M.H.) 635,300 98.2%
DN068CMHLEXC120 Excavation works for manhole 24 37,815 3.08% 0.07% 100.0% 3.08% 0.07%
DN068CMHLBLI220 Blinding for manhole 24 6,876 0.56% 0.01% 100.0% 0.56% 0.01%
DN068CMHLTAP320 Tanking membrane and protection for manhole 24 3,438 0.28% 0.01% 100.0% 0.28% 0.01%
DN068CMHLBAS420 Base slab for manhole 24 68,755 5.60% 0.13% 100.0% 5.60% 0.13%
DN068CMHLGRP820 GRP liner for manhole 24 79,068 6.45% 0.15% 100.0% 6.45% 0.15%
DN068CMHLWCP520 Wall concrete and pipe for manhole 24 85,943 7.01% 0.16% 100.0% 7.01% 0.16%
DN068CMHLCOV620 Cover slab for manhole 24 10,313 0.84% 0.02% 100.0% 0.84% 0.02%
DN068CMHLDIC760 DI cover for manhole 24 6,876 0.56% 0.01% 100.0% 0.56% 0.01%
DN068CMHLEMB920 External tanking membrane and protection for manhole 24 10,313 0.84% 0.02% 100.0% 0.84% 0.02%
DN068CMHLDIC770 Ladder for manhole 24 6,876 0.56% 0.01% 100.0% 0.56% 0.01%
DN068CMHLBAC940 Backfilling for manhole 24 27,502 2.24% 0.05% 100.0% 2.24% 0.05%
DN068CMHLDIC780 Reinstatement works 24 291,527 23.76% 0.56% 96.0% 22.81% 0.54%
House Connection Works (39D) 169,408 100.0%
DN068CHCOEXC220 Excavation for pipeline and inspection chamber 24 55,980 4.56% 0.11% 100.0% 4.56% 0.11%
DN068CHCOPIP320 Pipe laying for house connection 24 71,975 5.87% 0.14% 100.0% 5.87% 0.14%
DN068CHCOBAC720 Backfilling for Pipe for house connection 24 31,989 2.61% 0.06% 100.0% 2.61% 0.06%
DN068CHCOREN820 Marker Post for house connection 24 9,464 0.77% 0.02% 100.0% 0.77% 0.02%
Line 34/1/27/27 (7003LM, 227MH) 17,359,260 100.00% #N/A 99.41% 33.12%
Trunk Sewer 34/1/27/27/24 To 34/1/27/27/41 (518 LM, 17 MH) 2,649,075 99.8%
Traffic Management and Setting Out 0 0.0%
DN068CGENROS440 Obtaining RO from authorities 27 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENTRA340 Traffic Diversion 27 0 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CGENSET240 Setting out 27 0 0.00% 0.00% 100.0% 0.00% 0.00%
PipeLine Works (518 LM) 186,920 100.0%
DN068CPIPEXC240 Excavation for sewer pipeline 27 56,076 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPBED340 Geotextile and Bedding for sewer pipeline 27 31,777 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY440 Pipe Laying for sewer pipeline 27 56,076 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF540 Partial Backfill for sewer pipeline 27 22,431 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES640 Test for sewer pipeline 27 9,346 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF740 Final Backfill for sewer pipeline 27 11,215 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (17 M.H.) 386,470 100.0%
DN068CMHLEXC250 Excavation works for manhole 27 29,869 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLBLI350 Blinding for manhole 27 5,431 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP450 Tanking membrane and protection for manhole 27 2,715 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS550 Base slab for manhole 27 54,307 0.31% 0.10% 100.0% 0.31% 0.10%
DN068CMHLGRP950 GRP liner for manhole 27 62,453 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMHLWCP650 Wall concrete and pipe for manhole 27 67,883 0.39% 0.13% 100.0% 0.39% 0.13%
DN068CMHLCOV750 Cover slab for manhole 27 8,146 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1150 DI cover for manhole 27 5,431 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1160 Ladder for manhole 27 5,431 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1050 External tanking membrane and protection for manhole 27 8,146 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC1070 Backfilling for manhole 27 21,723 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLDIC1170 Reinstatement works 27 114,937 0.66% 0.22% 100.0% 0.66% 0.22%
House Connection Works (10D, 10ABC) 252,258 100.0%
DN068CHCODEM480 Demolition for existing underground structure 27 49,409 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CHCOEXC580 Excavation for pipeline and inspection chamber 27 28,715 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOPIP680 Pipe laying for house connection 27 36,919 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CHCOBAS780 Base for inspection chamber 27 12,115 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOWAL880 Wall for inspection chamber 27 30,287 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOFIN1280 Finishing for inspection chamber 27 9,086 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOCOV980 Cover for inspection chamber 27 9,086 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOBAC1080 Backfilling for house connection 27 16,408 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOREN1180 Reinstatement work for house connection 27 60,234 0.35% 0.12% 100.0% 0.35% 0.12%
Foul 34/1/27/27/27 (134 LM, 2 MH) 152,170 100.0%
PipeLine Works (134 LM) 48,424 100.0%
DN068CPIPEXC280 Excavation for sewer pipeline 27/27 14,527 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPBED380 Geotextile and Bedding for sewer pipeline 27/27 8,232 0.05% 0.02% 100.0% 0.05% 0.02%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CPIPLAY480 Pipe Laying for sewer pipeline 27/27 14,527 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPPBF580 Partial Backfill for sewer pipeline 27/27 5,811 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPTES680 Test for sewer pipeline 27/27 2,421 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CPIPFBF780 Final Backfill for sewer pipeline 27/27 2,905 0.02% 0.01% 100.0% 0.02% 0.01%
Manhole Works (2 M.H.) 61,998 100.0%
DN068CMHLEXC290 Excavation works for manhole 27/27 3,544 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBLI390 Blinding for manhole 27/27 644 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLTAP490 Tanking membrane and protection for manhole 27/27 322 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLBAS590 Base slab for manhole 27/27 6,444 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLGRP990 GRP liner for manhole 27/27 7,411 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLWCP690 Wall concrete and pipe for manhole 27/27 8,056 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLCOV790 Cover slab for manhole 27/27 967 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1270 DI cover for manhole 27/27 644 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLDIC1280 Ladder for manhole 27/27 644 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLEMB1090 External tanking membrane and protection for manhole 27/27 967 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAC1110 Backfilling for manhole 27/27 2,578 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1290 Reinstatement works 27/27 29,776 0.17% 0.06% 100.0% 0.17% 0.06%
House Connection Works (2ABC) 41,749 100.0%
DN068CHCODEM280 Demolition for existing underground structure 27/27 9,882 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CHCOEXC380 Excavation for pipeline and inspection chamber 27/27 2,867 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOPIP480 Pipe laying for house connection 27/27 3,686 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOBAS580 Base for inspection chamber 27/27 2,423 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOWAL680 Wall for inspection chamber 27/27 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOFIN1080 Finishing for inspection chamber 27/27 1,817 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOCOV780 Cover for inspection chamber 27/27 1,817 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOBAC880 Backfilling for house connection 27/27 1,638 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOREN980 Reinstatement work 27/27 11,561 0.07% 0.02% 100.0% 0.07% 0.02%
Foul 34/1/27/27/29 (146 LM, 6 MH) 306,922 100.0%
PipeLine Works (146 LM) 52,808 100.0%
DN068CPIPEXC270 Excavation for sewer pipeline 27/29 15,842 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPBED370 Geotextile and Bedding for sewer pipeline 27/29 8,977 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPLAY470 Pipe Laying for sewer pipeline 27/29 15,842 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPPBF570 Partial Backfill for sewer pipeline 27/29 6,337 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CPIPTES670 Test for sewer pipeline 27/29 2,640 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF770 Final Backfill for sewer pipeline 27/29 3,169 0.02% 0.01% 100.0% 0.02% 0.01%
Manhole Works (6 M.H.) 128,051 100.0%
DN068CMHLEXC280 Excavation works for manhole 27/29 10,514 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBLI380 Blinding for manhole 27/29 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP480 Tanking membrane and protection for manhole 27/29 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS580 Base slab for manhole 27/29 19,116 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CMHLGRP980 GRP liner for manhole 27/29 21,983 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLWCP680 Wall concrete and pipe for manhole 27/29 23,895 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CMHLCOV780 Cover slab for manhole 27/29 2,867 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1240 DI cover for manhole 27/29 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1250 Ladder for manhole 27/29 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1080 External tanking membrane and protection for manhole 27/29 2,867 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1100 Backfilling for manhole 27/29 7,646 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1260 Reinstatement works 27/29 32,472 0.19% 0.06% 100.0% 0.19% 0.06%
House Connection Works (5D, 5B) 126,063 100.0%
DN068CHCODEM270 Demolition for existing underground structure 27/29 24,704 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOEXC370 Excavation for pipeline and inspection chamber 27/29 14,334 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CHCOPIP470 Pipe laying for house connection 27/29 18,430 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOBAS570 Base for inspection chamber 27/29 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL670 Wall for inspection chamber 27/29 15,144 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOFIN1070 Finishing for inspection chamber 27/29 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOCOV770 Cover for inspection chamber 27/29 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOBAC870 Backfilling for house connection 27/29 8,191 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOREN970 Reinstatement work for house connection 27/29 30,117 0.17% 0.06% 100.0% 0.17% 0.06%
Foul 34/1/27/27/30 (515 LM, 18 MH) 1,026,339 99.5%
PipeLine Works (515 LM) 185,725 100.0%
DN068CPIPEXC260 Excavation for sewer pipeline 27/30 55,717 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPBED360 Geotextile and Bedding for sewer pipeline 27/30 31,573 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY460 Pipe Laying for sewer pipeline 27/30 55,717 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF560 Partial Backfill for sewer pipeline 27/30 22,287 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES660 Test for sewer pipeline 27/30 9,286 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF760 Final Backfill for sewer pipeline 27/30 11,144 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (18 M.H.) 401,302 100.0%
DN068CMHLEXC270 Excavation works for manhole 27/30 31,581 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMHLBLI370 Blinding for manhole 27/30 5,742 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP470 Tanking membrane and protection for manhole 27/30 2,871 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS570 Base slab for manhole 27/30 57,420 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CMHLGRP970 GRP liner for manhole 27/30 66,033 0.38% 0.13% 100.0% 0.38% 0.13%
DN068CMHLWCP670 Wall concrete and pipe for manhole 27/30 71,775 0.41% 0.14% 100.0% 0.41% 0.14%
DN068CMHLCOV770 Cover slab for manhole 27/30 8,613 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1210 DI cover for manhole 27/30 5,742 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1220 Ladder for manhole 27/30 5,742 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1070 External tanking membrane and protection for manhole 27/30 8,613 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC1090 Backfilling for manhole 27/30 22,968 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLDIC1230 Reinstatement works 27/30 114,202 0.66% 0.22% 100.0% 0.66% 0.22%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
House Connection Works (5D, 20ABC) 439,312 98.8%
DN068CHCODEM260 Demolition for existing underground structure 27/30 98,817 0.57% 0.19% 100.0% 0.57% 0.19%
DN068CHCOEXC360 Excavation for pipeline and inspection chamber 27/30 35,882 0.21% 0.07% 95.0% 0.20% 0.07%
DN068CHCOPIP460 Pipe laying for house connection 27/30 46,134 0.27% 0.09% 95.0% 0.25% 0.08%
DN068CHCOBAS560 Base for inspection chamber 27/30 24,230 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOWAL660 Wall for inspection chamber 27/30 60,575 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CHCOFIN1060 Finishing for inspection chamber 27/30 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOCOV760 Cover for inspection chamber 27/30 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOBAC860 Backfilling for house connection 27/30 20,504 0.12% 0.04% 95.0% 0.11% 0.04%
DN068CHCOREN960 Reinstatement work for house connection 27/30 116,827 0.67% 0.22% 100.0% 0.67% 0.22%
Foul 34/1/27/27/34 (179 LM, 7 MH) 337,995 100.0%
PipeLine Works (179 LM) 64,565 100.0%
DN068CPIPEXC250 Excavation for sewer pipeline 27/34 19,370 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CPIPBED350 Geotextile and Bedding for sewer pipeline 27/34 10,976 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPLAY450 Pipe Laying for sewer pipeline 27/34 19,370 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CPIPPBF550 Partial Backfill for sewer pipeline 27/34 7,748 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CPIPTES650 Test for sewer pipeline 27/34 3,228 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF750 Final Backfill for sewer pipeline 27/34 3,874 0.02% 0.01% 100.0% 0.02% 0.01%
Manhole Works (7 M.H.) 151,572 100.0%
DN068CMHLEXC260 Excavation works for manhole 27/34 12,306 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLBLI360 Blinding for manhole 27/34 2,237 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP460 Tanking membrane and protection for manhole 27/34 1,119 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS560 Base slab for manhole 27/34 22,374 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLGRP960 GRP liner for manhole27/34 25,730 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLWCP660 Wall concrete and pipe for manhole 27/34 27,968 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CMHLCOV760 Cover slab for manhole 27/34 3,356 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1180 DI cover for manhole 27/34 2,237 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1190 Ladder for manhole 27/34 2,237 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1060 External tanking membrane and protection for manhole 27/34 3,356 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1080 Backfilling for manhole 27/34 8,950 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1200 Reinstatement works 27/34 39,701 0.23% 0.08% 100.0% 0.23% 0.08%
House Connection Works (4D, 5ABC) 121,857 100.0%
DN068CHCODEM250 Demolition for existing underground structure 27/34 24,704 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOEXC350 Excavation for pipeline and inspection chamber 27/34 12,947 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOPIP450 Pipe laying for house connection 27/34 16,646 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOBAS550 Base for inspection chamber 27/34 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL650 Wall for inspection chamber 27/34 15,144 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOFIN1050 Finishing for inspection chamber 27/34 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOCOV750 Cover for inspection chamber 27/34 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOBAC850 Backfilling for house connection 27/34 7,398 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CHCOREN950 Reinstatement work for house connection 27/34 29,874 0.17% 0.06% 100.0% 0.17% 0.06%
Trunk Sewer Microtunnelling 34/1/27/27 To 34/1/27/27/24 (1480 LM, 26 MH, 12D, 1 14,710,184 99.3%
Pipeline Works (34/1/27/27/2 To 34/1/27/27 102LM) 563,606 100.0%
DN068CMITEXC100 Excavation for jacking shaft 48,609 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CMITCJS110 Concrete for jacking shaft 24,304 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CMITEXR120 Excavation for recieving shaft 48,609 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CMITFIR200 1st Tunneling & Driving the Pipes + Equipment 300,309 1.73% 0.58% 100.0% 1.73% 0.58%
DN068CMITSEC300 2nd Tunneling & Driving the Pipes and dismantle 141,775 0.82% 0.27% 100.0% 0.82% 0.27%
Pipeline Works (34/1/27/27/4 To 34/1/27/27/2 127LM) 504,429 100.0%
DN068CMITEXC130 Excavation for jacking shaft 60,532 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CMITCJS140 Concrete for jacking shaft 30,266 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITEXR150 Excavation for recieving shaft 60,532 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CMITFIR210 1st Tunneling & Driving the Pipes 176,550 1.02% 0.34% 100.0% 1.02% 0.34%
DN068CMITSEC310 2nd Tunneling & Driving the Pipes and dismantle 176,550 1.02% 0.34% 100.0% 1.02% 0.34%
Pipeline Works (34/1/27/27/6 To 34/1/27/27/4 107LM) 425,061 100.0%
DN068CMITEXC160 Excavation for jacking shaft 51,007 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITCJS170 Concrete for jacking shaft 25,504 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMITEXR180 Excavation for recieving shaft 51,007 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITFIR220 1st Tunneling & Driving the Pipes 148,771 0.86% 0.29% 100.0% 0.86% 0.29%
DN068CMITSEC320 2nd Tunneling & Driving the Pipes and dismantle 148,771 0.86% 0.29% 100.0% 0.86% 0.29%
Pipeline Works (34/1/27/27/7 To 34/1/27/27/6 130LM) 516,187 100.0%
DN068CMITEXC190 Excavation for jacking shaft 61,942 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMITCJS230 Concrete for jacking shaft 30,971 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMITEXR240 Excavation for recieving shaft 61,942 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMITFIR250 1st Tunneling & Driving the Pipes 180,666 1.04% 0.35% 100.0% 1.04% 0.35%
DN068CMITSEC330 2nd Tunneling & Driving the Pipes and dismantle 180,666 1.04% 0.35% 100.0% 1.04% 0.35%
Pipeline Works (34/1/27/27/9A To 34/1/27/27/7 124LM) 492,671 100.0%
DN068CMITEXC260 Excavation for jacking shaft 59,121 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CMITCJS270 Concrete for jacking shaft 29,560 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITEXR280 Excavation for recieving shaft 59,121 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CMITFIR290 1st Tunneling & Driving the Pipes 172,435 0.99% 0.33% 100.0% 0.99% 0.33%
DN068CMITSEC340 2nd Tunneling & Driving the Pipes and dismantle 172,435 0.99% 0.33% 100.0% 0.99% 0.33%
Pipeline Works (34/1/27/27/10 To 34/1/27/27/9A 104LM) 413,302 100.0%
DN068CMITEXC350 Excavation for jacking shaft 49,596 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITCJS360 Concrete for jacking shaft 24,798 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CMITEXR370 Excavation for recieving shaft 49,596 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CMITFIR380 1st Tunneling & Driving the Pipes 144,656 0.83% 0.28% 100.0% 0.83% 0.28%
DN068CMITSEC390 2nd Tunneling & Driving the Pipes and dismantle 144,656 0.83% 0.28% 100.0% 0.83% 0.28%
Pipeline Works (34/1/27/27/12 To 34/1/27/27/10 154LM) 612,017 100.0%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CMITEXC400 Excavation for jacking shaft 73,442 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITCJS410 Concrete for jacking shaft 36,721 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMITEXR420 Excavation for recieving shaft 73,442 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITFIR430 1st Tunneling & Driving the Pipes 214,206 1.23% 0.41% 100.0% 1.23% 0.41%
DN068CMITSEC440 2nd Tunneling & Driving the Pipes and dismantle 214,206 1.23% 0.41% 100.0% 1.23% 0.41%
Pipeline Works (34/1/27/27/14 To 34/1/27/27/12 152LM) 603,786 100.0%
DN068CMITEXC450 Excavation for jacking shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITCJS460 Concrete for jacking shaft 36,227 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMITEXR470 Excavation for recieving shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITFIR480 1st Tunneling & Driving the Pipes 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
DN068CMITSEC490 2nd Tunneling & Driving the Pipes and dismantle 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
Pipeline Works (34/1/27/27/16 To 34/1/27/27/14 152LM) 603,786 100.0%
DN068CMITEXC500 Excavation for jacking shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITCJS510 Concrete for jacking shaft 36,227 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMITEXR520 Excavation for recieving shaft 72,454 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMITFIR530 1st Tunneling & Driving the Pipes 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
DN068CMITSEC540 2nd Tunneling & Driving the Pipes and dismantle 211,325 1.22% 0.41% 100.0% 1.22% 0.41%
Pipeline Works (34/1/27/27/18 To 34/1/27/27/16 83LM) 329,819 100.0%
DN068CMITEXC550 Excavation for jacking shaft 39,578 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CMITCJS560 Concrete for jacking shaft 19,789 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CMITEXR570 Excavation for recieving shaft 39,578 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CMITFIR580 1st Tunneling & Driving the Pipes 115,437 0.66% 0.22% 100.0% 0.66% 0.22%
DN068CMITSEC590 2nd Tunneling & Driving the Pipes and dismantle 115,437 0.66% 0.22% 100.0% 0.66% 0.22%
Pipeline Works (34/1/27/27/20 To 34/1/27/27/18 90LM) 357,451 100.0%
DN068CMITEXC600 Excavation for jacking shaft 42,894 0.25% 0.08% 100.0% 0.25% 0.08%
DN068CMITCJS610 Concrete for jacking shaft 21,447 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CMITEXR620 Excavation for recieving shaft 42,894 0.25% 0.08% 100.0% 0.25% 0.08%
DN068CMITFIR630 1st Tunneling & Driving the Pipes 125,108 0.72% 0.24% 100.0% 0.72% 0.24%
DN068CMITSEC640 2nd Tunneling & Driving the Pipes and dismantle 125,108 0.72% 0.24% 100.0% 0.72% 0.24%
Pipeline Works (34/1/27/27/22 To 34/1/27/27/20 94LM) 373,324 100.0%
DN068CMITEXC650 Excavation for jacking shaft 44,799 0.26% 0.09% 100.0% 0.26% 0.09%
DN068CMITCJS660 Concrete for jacking shaft 22,400 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMITEXR670 Excavation for recieving shaft 44,799 0.26% 0.09% 100.0% 0.26% 0.09%
DN068CMITFIR680 1st Tunneling & Driving the Pipes 130,664 0.75% 0.25% 100.0% 0.75% 0.25%
DN068CMITSEC690 2nd Tunneling & Driving the Pipes and dismantle 130,664 0.75% 0.25% 100.0% 0.75% 0.25%
Pipeline Works (34/1/27/27/24 To 34/1/27/27/22 61LM) 242,220 100.0%
DN068CMITEXC700 Excavation for jacking shaft 29,066 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITCJS710 Concrete for jacking shaft 14,533 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMITEXR720 Excavation for recieving shaft 29,066 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMITFIR730 1st Tunneling & Driving the Pipes 84,777 0.49% 0.16% 100.0% 0.49% 0.16%
DN068CMITSEC740 2nd Tunneling & Driving the Pipes and dismantle 84,777 0.49% 0.16% 100.0% 0.49% 0.16%
Manhole Works (26 M.H.) 545,812 100.0%
DN068CMHLBLI210 Blinding for manhole for Microtunnel 33,163 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CMHLTAP310 Tanking membrane and protection for manhole for Microtunnel 8,291 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAS410 Base slab for manhole for Microtunnel 82,908 0.48% 0.16% 100.0% 0.48% 0.16%
DN068CMHLGRP810 GRP liner for manhole for Microtunnel 124,362 0.72% 0.24% 100.0% 0.72% 0.24%
DN068CMHLWCP510 Wall concrete and pipe for manhole for Microtunnel 82,908 0.48% 0.16% 100.0% 0.48% 0.16%
DN068CMHLCOV610 Cover slab for manhole for Microtunnel 12,436 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLDIC730 DI cover for manhole for Microtunnel 8,291 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLEMB910 External tanking membrane and protection for manhole for Microtu 20,727 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CMHLDIC740 Ladder for manhole for Microtunnel 8,291 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC930 Backfilling for manhole for Microtunnel 33,163 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CMHLDIC750 Reinstatement works for Microtunnel and house connection (12D, 131,272 0.76% 0.25% 100.0% 0.76% 0.25%
Foul 34/1/27/27/1 (107 LM, 3 MH) 130,773 100.0%
PipeLine Works (107 LM) 38,460 100.0%
DN068CPIPEXC390 Excavation for sewer pipeline 27/1 11,538 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CPIPBED490 Geotextile and Bedding for sewer pipeline 27/1 6,538 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CPIPLAY590 Pipe Laying for sewer pipeline 27/1 11,538 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CPIPPBF690 Partial Backfill for sewer pipeline 27/1 4,615 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPTES790 Test for sewer pipeline 27/1 1,923 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CPIPFBF890 Final Backfill for sewer pipeline 27/1 2,308 0.01% 0.00% 100.0% 0.01% 0.00%
Manhole Works (3 M.H.) 71,439 100.0%
DN068CMHLEXC400 Excavation works for manhole 27/1 5,257 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLBLI500 Blinding for manhole 27/1 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP600 Tanking membrane and protection for manhole 27/1 478 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLBAS700 Base slab for manhole 27/1 9,558 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLGRP1100 GRP liner for manhole 27/1 10,992 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLWCP800 Wall concrete and pipe for manhole 27/1 11,947 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLCOV900 Cover slab for manhole 27/1 1,434 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1600 DI cover for manhole 27/1 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1610 Ladder for manhole 27/1 956 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1200 External tanking membrane and protection for manhole 27/1 1,434 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAC1220 Backfilling for manhole 27/1 3,823 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1620 Reinstatement works 27/1 23,649 0.14% 0.05% 100.0% 0.14% 0.05%
House Connection Works (1ABC) 20,874 100.0%
DN068CHCODEM390 Demolition for existing underground structure 27/1 4,941 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOEXC490 Excavation for pipeline and inspection chamber 27/1 1,433 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOPIP590 Pipe laying for house connection 27/1 1,843 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOBAS690 Base for inspection chamber 27/1 1,212 0.01% 0.00% 100.0% 0.01% 0.00%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CHCOWAL790 Wall for inspection chamber 27/1 3,029 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOFIN1190 Finishing for inspection chamber 27/1 909 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOCOV890 Cover for inspection chamber 27/1 909 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CHCOBAC990 Backfilling for house connection 27/1 819 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CHCOREN1090 Reinstatement work for house connection 27/1 5,781 0.03% 0.01% 100.0% 0.03% 0.01%
Foul 34/1/27/27/5 (236 LM, 4 MH) 227,161 90.8%
PipeLine Works (263 LM) 85,091 100.0%
DN068CPIPEXC380 Excavation for sewer pipeline 27/5 25,527 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPBED480 Geotextile and Bedding for sewer pipeline 27/5 14,465 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPLAY580 Pipe Laying for sewer pipeline 27/5 25,527 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPPBF680 Partial Backfill for sewer pipeline 27/5 10,211 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPTES780 Test for sewer pipeline 27/5 4,255 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF880 Final Backfill for sewer pipeline 27/5 5,105 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (4 M.H.) 116,042 82.0%
DN068CMHLEXC390 Excavation works for manhole 27/5 7,009 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLBLI490 Blinding for manhole 27/5 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP590 Tanking membrane and protection for manhole 27/5 637 0.00% 0.00% 100.0% 0.00% 0.00%
DN068CMHLBAS690 Base slab for manhole 27/5 12,744 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLGRP1090 GRP liner for manhole 27/5 14,656 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMHLWCP790 Wall concrete and pipe for manhole 27/5 15,930 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CMHLCOV890 Cover slab for manhole 27/5 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1570 DI cover for manhole 27/5 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1580 Ladder for manhole 27/5 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1190 External tanking membrane and protection for manhole 27/5 1,912 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAC1210 Backfilling for manhole 27/5 5,098 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1590 Reinstatement works 27/5 52,322 0.30% 0.10% 60.0% 0.18% 0.06%
House Connection Works (6D) 26,029 100.0%
DN068CHCOEXC480 Excavation for pipeline for house connection 27/5 8,601 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOPIP580 Pipe laying for house connection 27/5 11,058 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CHCOBAC980 Backfilling for Pipe for house connection 27/5 4,915 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOREN1080 Marker post for house connection 27/5 1,456 0.01% 0.00% 100.0% 0.01% 0.00%
Foul 34/1/27/27/8 (465 LM, 17 MH) 899,259 93.1%
PipeLine Works (465 LM) 167,591 100.0%
DN068CPIPEXC370 Excavation for sewer pipeline 27/8 50,277 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CPIPBED470 Geotextile and Bedding for sewer pipeline 27/8 28,490 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CPIPLAY570 Pipe Laying for sewer pipeline 27/8 50,277 0.29% 0.10% 100.0% 0.29% 0.10%
DN068CPIPPBF670 Partial Backfill for sewer pipeline 27/8 20,111 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CPIPTES770 Test for sewer pipeline 27/8 8,380 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF870 Final Backfill for sewer pipeline 27/8 10,055 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (17 M.H.) 374,222 83.5%
DN068CMHLEXC380 Excavation works for manhole 27/8 29,829 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLBLI480 Blinding for manhole 27/8 5,423 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP580 Tanking membrane and protection for manhole 27/8 2,712 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS680 Base slab for manhole 27/8 54,234 0.31% 0.10% 100.0% 0.31% 0.10%
DN068CMHLGRP1080 GRP liner for manhole 27/8 62,369 0.36% 0.12% 100.0% 0.36% 0.12%
DN068CMHLWCP780 Wall concrete and pipe for manhole 27/8 67,793 0.39% 0.13% 100.0% 0.39% 0.13%
DN068CMHLCOV880 Cover slab for manhole 27/8 8,135 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1540 DI cover for manhole 27/8 5,423 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1550 Ladder for manhole 27/8 5,423 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1180 External tanking membrane and protection for manhole 27/8 8,135 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLBAC1200 Backfilling for manhole 27/8 21,694 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CMHLDIC1560 Reinstatement works 27/8 103,051 0.59% 0.20% 40.0% 0.24% 0.08%
House Connection Works (15D, 14ABC) 357,447 100.0%
DN068CHCODEM370 Demolition for existing underground structure 27/8 69,172 0.40% 0.13% 100.0% 0.40% 0.13%
DN068CHCOEXC470 Excavation for pipeline and inspection chamber 27/8 41,615 0.24% 0.08% 100.0% 0.24% 0.08%
DN068CHCOPIP570 Pipe laying for house connection 27/8 53,506 0.31% 0.10% 100.0% 0.31% 0.10%
DN068CHCOBAS670 Base for inspection chamber 27/8 16,961 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOWAL770 Wall for inspection chamber 27/8 42,402 0.24% 0.08% 100.0% 0.24% 0.08%
DN068CHCOFIN1170 Finishing for inspection chamber 27/8 12,721 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOCOV870 Cover for inspection chamber 27/8 12,721 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOBAC970 Backfilling for house connection 27/8 23,780 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOREN1070 Reinstatement work for house connection 27/8 84,570 0.49% 0.16% 100.0% 0.49% 0.16%
Foul 34/1/27/27/10 (521 LM, 23 MH) 1,228,680 100.0%
PipeLine Works (521 LM) 187,917 100.0%
DN068CPIPEXC360 Excavation for sewer pipeline 27/10 56,375 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPBED460 Geotextile and Bedding for sewer pipeline 27/10 31,946 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY560 Pipe Laying for sewer pipeline 27/10 56,375 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF660 Partial Backfill for sewer pipeline 27/10 22,550 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES760 Test for sewer pipeline 27/10 9,396 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF860 Final Backfill for sewer pipeline 27/10 11,275 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (23 M.H.) 482,300 100.0%
DN068CMHLEXC370 Excavation works for manhole 27/10 40,343 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CMHLBLI470 Blinding for manhole 27/10 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP570 Tanking membrane and protection for manhole 27/10 3,668 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS670 Base slab for manhole 27/10 73,350 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMHLGRP1070 GRP liner for manhole 27/10 84,353 0.49% 0.16% 100.0% 0.49% 0.16%
DN068CMHLWCP770 Wall concrete and pipe for manhole 27/10 91,688 0.53% 0.18% 100.0% 0.53% 0.18%
DN068CMHLCOV870 Cover slab for manhole 27/10 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1510 DI cover for manhole 27/10 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CMHLDIC1520 Ladder for manhole 27/10 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1170 External tanking membrane and protection for manhole 27/10 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1190 Backfilling for manhole 27/10 29,340 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLDIC1530 Reinstatement works 27/10 115,550 0.67% 0.22% 100.0% 0.67% 0.22%
House Connection Works (18D, 23ABC) 558,464 100.0%
DN068CHCODEM360 Demolition for existing underground structure 27/10 113,640 0.65% 0.22% 100.0% 0.65% 0.22%
DN068CHCOEXC460 Excavation for pipeline and inspection chamber 27/10 58,863 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CHCOPIP560 Pipe laying for house connection 27/10 75,681 0.44% 0.15% 100.0% 0.44% 0.15%
DN068CHCOBAS660 Base for inspection chamber 27/10 27,864 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CHCOWAL760 Wall for inspection chamber 27/10 69,661 0.40% 0.13% 100.0% 0.40% 0.13%
DN068CHCOFIN1160 Finishing for inspection chamber 27/10 20,898 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CHCOCOV860 Cover for inspection chamber 27/10 20,898 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CHCOBAC960 Backfilling for house connection 27/10 33,636 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CHCOREN1060 Reinstatement work for house connection 27/10 137,324 0.79% 0.26% 100.0% 0.79% 0.26%
Foul 34/1/27/27/11 (241 LM, 7 MH) 457,173 96.7%
PipeLine Works (241 LM) 86,884 100.0%
DN068CPIPEXC350 Excavation for sewer pipeline 27/11 26,065 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPBED450 Geotextile and Bedding for sewer pipeline 27/11 14,770 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPLAY550 Pipe Laying for sewer pipeline 27/11 26,065 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPPBF650 Partial Backfill for sewer pipeline 27/11 10,426 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPTES750 Test for sewer pipeline 27/11 4,344 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPFBF850 Final Backfill for sewer pipeline 27/11 5,213 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (7 M.H.) 164,935 100.0%
DN068CMHLEXC360 Excavation works for manhole 27/11 12,266 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CMHLBLI460 Blinding for manhole 27/11 2,230 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP560 Tanking membrane and protection for manhole 27/11 1,115 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS660 Base slab for manhole 27/11 22,302 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CMHLGRP1060 GRP liner for manhole 27/11 25,647 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLWCP760 Wall concrete and pipe for manhole 27/11 27,877 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CMHLCOV860 Cover slab for manhole 27/11 3,345 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1480 DI cover for manhole 27/11 2,230 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1490 Ladder for manhole 27/11 2,230 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1160 External tanking membrane and protection for manhole 27/11 3,345 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1180 Backfilling for manhole 27/11 8,921 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CMHLDIC1500 Reinstatement works 27/11 53,425 0.31% 0.10% 100.0% 0.31% 0.10%
House Connection Works (4D, 9ABC) 205,355 92.6%
DN068CHCODEM350 Demolition for existing underground structure 27/11 44,468 0.26% 0.09% 90.0% 0.23% 0.08%
DN068CHCOEXC450 Excavation for pipeline and inspection chamber 27/11 18,681 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOPIP550 Pipe laying for house connection 27/11 24,018 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOBAS650 Base for inspection chamber 27/11 10,903 0.06% 0.02% 90.0% 0.06% 0.02%
DN068CHCOWAL750 Wall for inspection chamber 27/11 27,259 0.16% 0.05% 90.0% 0.14% 0.05%
DN068CHCOFIN1150 Finishing for inspection chamber 27/11 8,178 0.05% 0.02% 90.0% 0.04% 0.01%
DN068CHCOCOV850 Cover for inspection chamber 27/11 8,178 0.05% 0.02% 90.0% 0.04% 0.01%
DN068CHCOBAC950 Backfilling for house connection 27/11 10,675 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CHCOREN1050 Reinstatement work for house connection 27/11 52,997 0.31% 0.10% 90.0% 0.27% 0.09%
Foul 34/1/27/27/12 (522 LM, 23 HM) 1,319,865 100.0%
PipeLine Works (522 LM) 188,315 100.0%
DN068CPIPEXC340 Excavation for sewer pipeline 27/12 56,495 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPBED440 Geotextile and Bedding for sewer pipeline 27/12 32,014 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY540 Pipe Laying for sewer pipeline 27/12 56,495 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPPBF640 Partial Backfill for sewer pipeline 27/12 22,598 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES740 Test for sewer pipeline 27/12 9,416 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF840 Final Backfill for sewer pipeline 27/12 11,299 0.07% 0.02% 100.0% 0.07% 0.02%
Manhole Works (23 M.H.) 482,545 100.0%
DN068CMHLEXC350 Excavation works for manhole 27/12 40,343 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CMHLBLI450 Blinding for manhole 27/12 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP550 Tanking membrane and protection for manhole 27/12 3,668 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS650 Base slab for manhole 27/12 73,350 0.42% 0.14% 100.0% 0.42% 0.14%
DN068CMHLGRP1050 GRP liner for manhole 27/12 84,353 0.49% 0.16% 100.0% 0.49% 0.16%
DN068CMHLWCP750 Wall concrete and pipe for manhole 27/12 91,688 0.53% 0.18% 100.0% 0.53% 0.18%
DN068CMHLCOV850 Cover slab for manhole 27/12 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1450 DI cover for manhole 27/12 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1460 Ladder for manhole 27/12 7,335 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1150 External tanking membrane and protection for manhole 27/12 11,003 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1170 Backfilling for manhole 27/12 29,340 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLDIC1470 Reinstatement works 27/12 115,795 0.67% 0.22% 100.0% 0.67% 0.22%
House Connection Works (10D, 29ABC) 649,005 100.0%
DN068CHCODEM340 Demolition for existing underground structure 27/12 143,285 0.83% 0.28% 100.0% 0.83% 0.28%
DN068CHCOEXC440 Excavation for pipeline and inspection chamber 27/12 55,996 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CHCOPIP540 Pipe laying for house connection 27/12 71,995 0.41% 0.14% 100.0% 0.41% 0.14%
DN068CHCOBAS640 Base for inspection chamber 27/12 35,133 0.20% 0.07% 100.0% 0.20% 0.07%
DN068CHCOWAL740 Wall for inspection chamber 27/12 87,833 0.51% 0.17% 100.0% 0.51% 0.17%
DN068CHCOFIN1140 Finishing for inspection chamber 27/12 26,350 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CHCOCOV840 Cover for inspection chamber 27/12 26,350 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CHCOBAC940 Backfilling for house connection 27/12 31,998 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CHCOREN1040 Reinstatement work for house connection 27/12 170,067 0.98% 0.33% 100.0% 0.98% 0.33%
Foul 34/1/27/27/14 (509 LM, 22 MH) 1,350,481 100.0%
PipeLine Works (509 LM) 183,732 100.0%
DN068CPIPEXC330 Excavation for sewer pipeline 27/14 55,120 0.32% 0.11% 100.0% 0.32% 0.11%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CPIPBED430 Geotextile and Bedding for sewer pipeline 27/14 31,234 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CPIPLAY530 Pipe Laying for sewer pipeline 27/14 55,120 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CPIPPBF630 Partial Backfill for sewer pipeline 27/14 22,048 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES730 Test for sewer pipeline 27/14 9,187 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF830 Final Backfill for sewer pipeline 27/14 11,024 0.06% 0.02% 100.0% 0.06% 0.02%
Manhole Works (22 M.H.) 463,797 100.0%
DN068CMHLEXC340 Excavation works for manhole 27/14 38,590 0.22% 0.07% 100.0% 0.22% 0.07%
DN068CMHLBLI440 Blinding for manhole 27/14 7,016 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP540 Tanking membrane and protection for manhole 27/14 3,508 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS640 Base slab for manhole 27/14 70,164 0.40% 0.13% 100.0% 0.40% 0.13%
DN068CMHLGRP1040 GRP liner for manhole 27/14 80,689 0.46% 0.15% 100.0% 0.46% 0.15%
DN068CMHLWCP740 Wall concrete and pipe for manhole 27/14 87,705 0.51% 0.17% 100.0% 0.51% 0.17%
DN068CMHLCOV840 Cover slab for manhole 27/14 10,525 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1420 DI cover for manhole 27/14 7,016 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1430 Ladder for manhole 27/14 7,016 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1140 External tanking membrane and protection for manhole 27/14 10,525 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1160 Backfilling for manhole 27/14 28,066 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CMHLDIC1440 Reinstatement works 27/14 112,977 0.65% 0.22% 100.0% 0.65% 0.22%
House Connection Works (8D, 32ABC) 702,952 100.0%
DN068CHCODEM330 Demolition for existing underground structure 27/14 158,107 0.91% 0.30% 100.0% 0.91% 0.30%
DN068CHCOEXC430 Excavation for pipeline and inspection chamber 27/14 57,429 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CHCOPIP530 Pipe laying for house connection 27/14 73,838 0.43% 0.14% 100.0% 0.43% 0.14%
DN068CHCOBAS630 Base for inspection chamber 27/14 38,768 0.22% 0.07% 100.0% 0.22% 0.07%
DN068CHCOWAL730 Wall for inspection chamber 27/14 96,919 0.56% 0.19% 100.0% 0.56% 0.19%
DN068CHCOFIN1130 Finishing for inspection chamber 27/14 29,076 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOCOV830 Cover for inspection chamber 27/14 29,076 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOBAC930 Backfilling for house connection 27/14 32,817 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CHCOREN1030 Reinstatement work 27/14 186,923 1.08% 0.36% 100.0% 1.08% 0.36%
Foul 34/1/27/27/16 (532 LM, 21 MH) 1,097,252 100.0%
PipeLine Works (532 LM) 191,902 100.0%
DN068CPIPEXC320 Excavation for sewer pipeline 27/16 57,571 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPBED420 Geotextile and Bedding for sewer pipeline 27/16 32,623 0.19% 0.06% 100.0% 0.19% 0.06%
DN068CPIPLAY520 Pipe Laying for sewer pipeline 27/16 57,571 0.33% 0.11% 100.0% 0.33% 0.11%
DN068CPIPPBF620 Partial Backfill for sewer pipeline 27/16 23,028 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPTES720 Test for sewer pipeline 27/16 9,595 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPFBF820 Final Backfill for sewer pipeline 27/16 11,514 0.07% 0.02% 100.0% 0.07% 0.02%
Manhole Works (21 M.H.) 452,891 100.0%
DN068CMHLEXC330 Excavation works for manhole 27/16 36,838 0.21% 0.07% 100.0% 0.21% 0.07%
DN068CMHLBLI430 Blinding for manhole 27/16 6,698 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLTAP530 Tanking membrane and protection for manhole 27/16 3,349 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAS630 Base slab for manhole 27/16 66,978 0.39% 0.13% 100.0% 0.39% 0.13%
DN068CMHLGRP1030 GRP liner for manhole 27/16 77,025 0.44% 0.15% 100.0% 0.44% 0.15%
DN068CMHLWCP730 Wall concrete and pipe for manhole 27/16 83,723 0.48% 0.16% 100.0% 0.48% 0.16%
DN068CMHLCOV830 Cover slab for manhole 27/16 10,047 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1390 DI cover for manhole 27/16 6,698 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1400 Ladder for manhole 27/16 6,698 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLEMB1130 External tanking membrane and protection for manhole 27/16 10,047 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLBAC1150 Backfilling for manhole 27/16 26,791 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLDIC1410 Reinstatement works 27/16 118,000 0.68% 0.23% 100.0% 0.68% 0.23%
House Connection Works (8D, 20ABC) 452,459 100.0%
DN068CHCODEM320 Demolition for existing underground structure 27/16 98,817 0.57% 0.19% 100.0% 0.57% 0.19%
DN068CHCOEXC420 Excavation for pipeline and inspection chamber 27/16 40,228 0.23% 0.08% 100.0% 0.23% 0.08%
DN068CHCOPIP520 Pipe laying for house connection 27/16 51,722 0.30% 0.10% 100.0% 0.30% 0.10%
DN068CHCOBAS620 Base for inspection chamber 27/16 24,230 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOWAL720 Wall for inspection chamber 27/16 60,575 0.35% 0.12% 100.0% 0.35% 0.12%
DN068CHCOFIN1120 Finishing for inspection chamber 27/16 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOCOV820 Cover for inspection chamber 27/16 18,172 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOBAC920 Backfilling for house connection 27/16 22,988 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CHCOREN1020 Reinstatement work for house connection 27/16 117,555 0.68% 0.23% 100.0% 0.68% 0.23%
Foul 34/1/27/27/17 (439 LM, 15 MH) 652,528 100.0%
PipeLine Works (439 LM) 158,424 100.0%
DN068CPIPEXC310 Excavation for sewer pipeline 27/17 47,527 0.27% 0.09% 100.0% 0.27% 0.09%
DN068CPIPBED410 Geotextile and Bedding for sewer pipeline 27/17 26,932 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CPIPLAY510 Pipe Laying for sewer pipeline 27/17 47,527 0.27% 0.09% 100.0% 0.27% 0.09%
DN068CPIPPBF610 Partial Backfill for sewer pipeline 27/17 19,011 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CPIPTES710 Test for sewer pipeline 27/17 7,921 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPFBF810 Final Backfill for sewer pipeline 27/17 9,505 0.05% 0.02% 100.0% 0.05% 0.02%
Manhole Works (15 M.H.) 336,725 100.0%
DN068CMHLEXC320 Excavation works for manhole 27/17 26,324 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLBLI420 Blinding for manhole 27/17 4,786 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLTAP520 Tanking membrane and protection for manhole 27/17 2,393 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS620 Base slab for manhole 27/17 47,862 0.28% 0.09% 100.0% 0.28% 0.09%
DN068CMHLGRP1020 GRP liner for manhole 27/17 55,042 0.32% 0.11% 100.0% 0.32% 0.11%
DN068CMHLWCP720 Wall concrete and pipe for manhole 27/17 59,828 0.34% 0.11% 100.0% 0.34% 0.11%
DN068CMHLCOV820 Cover slab for manhole 27/17 7,179 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLDIC1360 DI cover for manhole 27/17 4,786 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLDIC1370 Ladder for manhole 27/17 4,786 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CMHLEMB1120 External tanking membrane and protection for manhole 27/17 7,179 0.04% 0.01% 100.0% 0.04% 0.01%
DN068CMHLBAC1140 Backfilling for manhole 27/17 19,145 0.11% 0.04% 100.0% 0.11% 0.04%
Activity ID Activity Name Budgeted Total Cost Weight Weight PCT % Progress Progress
Area Overall Area Overall
DN068CMHLDIC1380 Reinstatement works 27/17 97,415 0.56% 0.19% 100.0% 0.56% 0.19%
House Connection Works (17D, 4ABC) 157,379 100.0%
DN068CHCODEM310 Demolition for existing underground structure 27/17 19,763 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOEXC410 Excavation for pipeline and inspection chamber 27/17 30,148 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CHCOPIP510 Pipe laying for house connection 27/17 38,762 0.22% 0.07% 100.0% 0.22% 0.07%
DN068CHCOBAS610 Base for inspection chamber 27/17 4,846 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL710 Wall for inspection chamber 27/17 12,115 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOFIN1110 Finishing for inspection chamber 27/17 3,635 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOCOV810 Cover for inspection chamber 27/17 3,635 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOBAC910 Backfilling for house connection 27/17 17,227 0.10% 0.03% 100.0% 0.10% 0.03%
DN068CHCOREN1010 Reinstatement work 27/17 27,248 0.16% 0.05% 100.0% 0.16% 0.05%
Foul 34/1/27/27/19 (243 LM, 8 MH) 395,098 100.0%
PipeLine Works (243 LM) 87,681 100.0%
DN068CPIPEXC300 Excavation for sewer pipeline 27/19 26,304 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPBED400 Geotextile and Bedding for sewer pipeline 14,906 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CPIPLAY500 Pipe Laying for sewer pipeline 27/19 26,304 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CPIPPBF600 Partial Backfill for sewer pipeline 27/19 10,522 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CPIPTES700 Test for sewer pipeline 27/19 4,384 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CPIPFBF800 Final Backfill for sewer pipeline 27/19 5,261 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (8 M.H.) 181,354 100.0%
DN068CMHLEXC310 Excavation works for manhole 27/19 14,018 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMHLBLI410 Blinding for manhole 27/19 2,549 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP510 Tanking membrane and protection for manhole 27/19 1,274 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS610 Base slab for manhole 27/19 25,488 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLGRP1010 GRP liner for manhole 27/19 29,311 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLWCP710 Wall concrete and pipe for manhole 27/19 31,860 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMHLCOV810 Cover slab for manhole 27/19 3,823 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1330 DI cover for manhole 27/19 2,549 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1340 Ladder for manhole 27/19 2,549 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1110 External tanking membrane and protection for manhole 27/19 3,823 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1130 Backfilling for manhole 27/19 10,195 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1350 Reinstatement works 27/19 53,915 0.31% 0.10% 100.0% 0.31% 0.10%
House Connection Works (5D, 5ABC) 126,063 100.0%
DN068CHCODEM300 Demolition for existing underground structure 27/19 24,704 0.14% 0.05% 100.0% 0.14% 0.05%
DN068CHCOEXC400 Excavation for pipeline and inspection chamber 27/19 14,334 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CHCOPIP500 Pipe laying for house connection 27/19 18,430 0.11% 0.04% 100.0% 0.11% 0.04%
DN068CHCOBAS600 Base for inspection chamber 27/19 6,057 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOWAL700 Wall for inspection chamber 27/19 15,144 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOFIN1100 Finishing for inspection chamber 27/19 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOCOV800 Cover for inspection chamber 27/19 4,543 0.03% 0.01% 100.0% 0.03% 0.01%
DN068CHCOBAC900 Backfilling for house connection 27/19 8,191 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOREN1000 Reinstatement work 27/19 30,117 0.17% 0.06% 100.0% 0.17% 0.06%
Foul 34/1/27/27/23 (216 LM, 8 MH) 368,442 100.0%
PipeLine Works (216 LM) 77,917 100.0%
DN068CPIPEXC290 Excavation for sewer pipeline 27/23 23,375 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPBED390 Geotextile and Bedding for sewer pipeline 27/23 13,246 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CPIPLAY490 Pipe Laying for sewer pipeline 27/23 23,375 0.13% 0.04% 100.0% 0.13% 0.04%
DN068CPIPPBF590 Partial Backfill for sewer pipeline 27/23 9,350 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CPIPTES690 Test for sewer pipeline 27/23 3,896 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CPIPFBF790 Final Backfill for sewer pipeline 27/23 4,675 0.03% 0.01% 100.0% 0.03% 0.01%
Manhole Works (8 M.H.) 175,712 100.0%
DN068CMHLEXC300 Excavation works for manhole 27/23 14,058 0.08% 0.03% 100.0% 0.08% 0.03%
DN068CMHLBLI400 Blinding for manhole 27/23 2,556 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLTAP500 Tanking membrane and protection for manhole 27/23 1,278 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLBAS600 Base slab for manhole 27/23 25,560 0.15% 0.05% 100.0% 0.15% 0.05%
DN068CMHLGRP1000 GRP liner for manhole 27/23 29,394 0.17% 0.06% 100.0% 0.17% 0.06%
DN068CMHLWCP700 Wall concrete and pipe for manhole 27/23 31,950 0.18% 0.06% 100.0% 0.18% 0.06%
DN068CMHLCOV800 Cover slab for manhole 27/23 3,834 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLDIC1300 DI cover for manhole 27/23 2,556 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLDIC1310 Ladder for manhole 27/23 2,556 0.01% 0.00% 100.0% 0.01% 0.00%
DN068CMHLEMB1100 External tanking membrane and protection for manhole 27/23 3,834 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CMHLBAC1120 Backfilling for manhole 27/23 10,224 0.06% 0.02% 100.0% 0.06% 0.02%
DN068CMHLDIC1320 Reinstatement works 27/23 47,911 0.28% 0.09% 100.0% 0.28% 0.09%
House Connection Works (12D, 3ABC) 114,813 100.0%
DN068CHCODEM290 Demolition for existing underground structure 27/23 14,823 0.09% 0.03% 100.0% 0.09% 0.03%
DN068CHCOEXC390 Excavation for pipeline and inspection chamber 27/23 21,548 0.12% 0.04% 100.0% 0.12% 0.04%
DN068CHCOPIP490 Pipe laying for house connection 27/23 27,704 0.16% 0.05% 100.0% 0.16% 0.05%
DN068CHCOBAS590 Base for inspection chamber 27/23 3,635 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOWAL690 Wall for inspection chamber 27/23 9,086 0.05% 0.02% 100.0% 0.05% 0.02%
DN068CHCOFIN1090 Finishing for inspection chamber 27/23 2,726 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOCOV790 Cover for inspection chamber 27/23 2,726 0.02% 0.01% 100.0% 0.02% 0.01%
DN068CHCOBAC890 Backfilling for house connection 27/23 12,313 0.07% 0.02% 100.0% 0.07% 0.02%
DN068CHCOREN990 Reinstatement work for house connection 27/23 20,254 0.12% 0.04% 100.0% 0.12% 0.04%
Handing Over 0 0.0%
DN068HALPASB10 As Built Drawingss 0 0.0%
DN068HALPHAV20Demobilisation 0 0.0%
CP 745/2
Data Date

1-Jan-15

Start Date Duration Finish Date

1-May-12 825 3-Aug-14 Project Elapsed Duration 976 PCT 118.30%

Remaining Duration -151

Weekly Report CP 745/2 Contract Data


Activity ID Activity Name Original Dur
CONSTRUCTION OF AL GARAFFA AREA SEWERAGE - PHASE 2 15.07.2014 1071
General 1020
Milestones 1020
DN068GALPCED100 Project Start Date 0
DN068GALPDUR300 Project Duration 825
DN068GALPPRC200 Project Completion Date 0
General Work 825
DN068GALPTPI700 Third Party Insurance 825
DN068GALPSIO200 Supply and Installation of Site Offices 60
DN068GALPALO100 Site Mobilisation 60
DN068GALPTPI720 Contract Administration 825
DN068GALPTPI730 Site offices maintain 825
DN068GALPTPI710 Site Survey 584
Engineering 1008
General Items 85
General Items Submission 25
DN068GALPHSS400 HSE Management Plan - Submission 10
DN068GALPQMS300 Project Quality Plan - Submission 10
DN068GALPCSS100 Construction Schedule-Submission 20
DN068GALPTMS600 Traffic Management Plan-Submission 10
General Items Approval 40
DN068GALPCSA100 Construction Schedule-Approval 20
DN068GALPHSA400 HSE Management Plan - Approval 14
DN068GALPQMA300 Project Quality Plan - Approval 14
DN068GALPTMA600 Traffic Management Plan-Approval 14
Subcontractor Prequalification Submission 49
DN068GALPHSS470 Micro Tunneling Subcontractor - Submission 10
DN068GALPHSS460 Surveying Work Subcontractor - Submission 4
DN068GALPHSS450 Laboratory Subcontractor - Submission 20
DN068GALPHSS480 Asphalt Subcontractor - Submission 20
Subcontractor Prequalification Approval 72
DN068GALPHSA470 Micro Tunneling Subcontractor - Approval 14
DN068GALPHSA450 Laboratory Subcontractor - Approval 14
DN068GALPHSA460 Surveying Work Subcontractor - Approval 12
DN068GALPHSA480 Asphalt Subcontractor - Approval 14
Shop Drawing Submittal/ Approval 727
DN068EALPSDS100 Shop Drawings- Submission 453
DN068EALPSDA200 Shop Drawings- Approval 449
Material and Method statements 1002
Mathod Statemenets Submission 65
DN068GALPSSM100 Sewer Open-Cut Method Statement - Submission 12
DN068GALPSCC600 House Connection Chamber Construction Method Statement - Submiss 20
DN068GALPSHC400 House Connection Method Statement - Submission 12
DN068GALPSMC500 Manhole Construction Method Statement - Submission 12
DN068GALPSMT300 MicroTunneling Method Statement - Submission 20
DN068GALPSRM200 Reinstatement Method Statement - Submission 14
Method Statements Approval 77
DN068GALPASM100 Sewer
House Open-Cut
Connection Method Statement
Chamber - Approval
Construction Method Statement - 14
DN068GALPACC500 Approval 14
DN068GALPAHC300 House Connection Method Statement - Approval 14
DN068GALPAMC400 Manhole Construction Method Statement - Approval 14
DN068GALPAMT200 MicroTunneling Method Statement - Approval 14
DN068GALPARM600 Reinstatement Method Statement - Approval 14
Material Submission 982
DN068GALPMSG200 Material Submittal for Geotextile Membrane 5
DN068GALPMSV900 Material Submittal for VC Pipes 5
DN068GALPMSM700 Material Submittal for Manhole Liners 10
DN068GALPMSW300 Material Submittal for Water Proofing Material 10
DN068GALPMSC130 Material Submittal for DI Covers 10
DN068GALPMSJ600 Material Submittal for Jacking Pipes for Micro Tunneling 10
DN068GALPMSP120 Material Submittal for Paving Blocks for Reinstatement Works 10
Material Approvals 996
DN068GALPMAG200 Material Approval for Geotextile Membrane 14
DN068GALPMAV900 Material Approval for VC Pipes & Bends 14
DN068GALPMAW300 Material Approval for Water Proofing Material 14
DN068GALPMAM700 Material Approval for Manhole Liners 14
DN068GALPMAC130 Material Approval for DI Covers 14
DN068GALPMAJ600 Material Approval for Jacking Pipes for Micro Tunneling 14
DN068GALPMAP120 Material Approval for Paving Blocks for Reinstatement Works 14
Procurement/Delivery 1039
DN068PALPPVC900 Procurement of VC Pipes 120
DN068PALPPGM300 Procurement of Geotextile Membrane 90
DN068PALPPML700 Procurement of Manhole Liners 60
DN068PALPPWP400 Procurement of Water Proofing Material 120
DN068PALPPJP500 Procurement of Jacking Pipes for Micro Tunneling 60
DN068PALPPDC130 Procurement of DI Cover 60
DN068PALPPPB120 Procurement of Paving Blocks for Reinstatement Works 60
Construction 1020
Line V 34/1/27/56/1 (320Lm, 4MH) 126
Traffic Management and Setting Out 63
DN068CGENROS380 Obtaining RO from authorities 56/1, 51/1, 46, 46/11, 45/19 and 60 23
DN068CGENSET180 Setting out 56/1, 51/1 and 46 20
DN068CGENTRA280 Traffic Diversion 56/1, 51/1 and 46 20
PipeLine Works (320 LM) 32
DN068CPIPEXC220 Excavation for sewer pipeline 56/1 8
DN068CPIPBED320 Geotextile and Bedding for sewer pipeline 56/1 8
DN068CPIPTES620 Test for sewer pipeline 56/1 8
DN068CPIPLAY420 Pipe Laying for sewer pipeline 56/1 8
DN068CPIPPBF520 Partial Backfill for sewer pipeline 56/1 8
DN068CPIPFBF720 Final Backfill for sewer pipeline 56/1 7
Manhole Works (4 M.H.) 58
DN068CMHLEXC230 Excavation works for manhole 56/1 4
DN068CMHLBLI330 Blinding for manhole 56/1 4
DN068CMHLTAP430 Tanking membrane and protection for manhole 56/1 4
DN068CMHLBAS530 Base slab for manhole 56/1 4
DN068CMHLGRP930 GRP liner for manhole 56/1 4
DN068CMHLWCP630 Wall concrete and pipe for manhole 56/1 4
DN068CMHLDIC100 Ladder for manhole 56/1 4
DN068CMHLDIC110 Reinstatement works 56/1 10
DN068CMHLEMB130 External tanking membrane and protection for manhole 56/1 4
DN068CMHLCOV730 Cover slab for manhole 56/1 4
DN068CMHLBAC150 Backfilling for manhole 56/1 4
DN068CMHLDIC190 DI cover for manhole 56/1 4
House Connection Works (8D) 43
DN068CHCOEXC330 Excavation for pipeline for house connection 56/1 5
DN068CHCOPIP430 Pipe laying for house connection 56/1 5
DN068CHCOBAC830 Backfilling for Pipe for house connection 56/1 5
DN068CHCOREN930 Marker post for house connection 56/1 6
Line AE 34/1/27/51/1 (828LM, 17MH) 83
PipeLine Works (828 LM) 58
DN068CPIPEXC190 Excavation for sewer pipeline 51/1 20
DN068CPIPBED290 Geotextile and Bedding for sewer pipeline 51/1 20
DN068CPIPLAY390 Pipe Laying for sewer pipeline 51/1 20
DN068CPIPPBF490 Partial Backfill for sewer pipeline 51/1 20
DN068CPIPTES590 Test for sewer pipeline 51/1 20
DN068CPIPFBF690 Final Backfill for sewer pipeline 51/1 18
Manhole Works (17 M.H.) 81
DN068CMHLEXC200 Excavation works for manhole 51/1 14
DN068CMHLBLI300 Blinding for manhole 51/1 14
DN068CMHLTAP400 Tanking membrane and protection for manhole 51/1 14
DN068CMHLBAS500 Base slab for manhole 51/1 14
DN068CMHLGRP900 GRP liner for manhole 51/1 14
DN068CMHLWCP600 Wall concrete and pipe for manhole 51/1 14
DN068CMHLDIC1010 Ladder for manhole 51/1 14
DN068CMHLEMB100 External tanking membrane and protection for manhole 51/1 14
DN068CMHLBAC120 Backfilling for manhole 51/1 14
DN068CMHLCOV700 Cover slab for manhole 51/1 14
DN068CMHLDIC1000 DI cover for manhole 51/1 14
DN068CMHLDIC1020 Reinstatement works 51/1 20
House Connection Works (11D,5ABC) 34
DN068CHCOEXC300 Excavation for pipeline and inspection chamber 51/1 10
DN068CHCOPIP400 Pipe laying for house connection 51/1 10
DN068CHCOBAC800 Backfilling for house connection 51/1 5
DN068CHCODEM200 Demolition for existing underground structure 51/1 5
DN068CHCOBAS500 Base for inspection chamber 51/1 5
DN068CHCOWAL600 Wall for inspection chamber 51/1 5
DN068CHCOFIN1000 Finishing for inspection chamber 51/1 5
DN068CHCOCOV700 Cover for inspection chamber 51/1 5
DN068CHCOREN900 Reinstatement work for house connection 51/1 10
Line AD1 34/1/27/46/11(493LM, 9MH) 140
Traffic Management and Setting Out 71
DN068CGENSET200 Setting out 46/11 23
DN068CGENTRA300 Traffic Diversion 46/11 23
PipeLine Works (493 LM) 24
DN068CPIPEXC200 Excavation for sewer pipeline 46/11 12
DN068CPIPBED300 Geotextile and Bedding for sewer pipeline 46/11 12
DN068CPIPLAY400 Pipe Laying for sewer pipeline 46/11 12
DN068CPIPTES600 Test for sewer pipeline 46/11 12
DN068CPIPPBF500 Partial Backfill for sewer pipeline 46/11 12
DN068CPIPFBF700 Final Backfill for sewer pipeline 46/11 11
Manhole Works (9 M.H.) 41
DN068CMHLEXC210 Excavation works for manhole 46/11 8
DN068CMHLBLI310 Blinding for manhole 46/11 8
DN068CMHLTAP410 Tanking membrane and protection for manhole 46/11 8
DN068CMHLBAS510 Base slab for manhole 46/11 8
DN068CMHLGRP910 GRP liner for manhole 46/11 8
DN068CMHLWCP610 Wall concrete and pipe for manhole 46/11 8
DN068CMHLDIC1040 Ladder for manhole 46/11 8
DN068CMHLDIC1050 Reinstatement works 46/11 12
DN068CMHLEMB1010 External tanking membrane and protection for manhole 46/11 8
DN068CMHLCOV710 Cover slab for manhole 46/11 8
DN068CMHLBAC1030 Backfilling for manhole 46/11 9
DN068CMHLDIC1030 DI cover for manhole 46/11 8
House Connection Works (15D) 53
DN068CHCOEXC310 Excavation for pipeline for house connection 46/11 10
DN068CHCOBAC810 Backfilling for Pipe for house connection 46/11 10
DN068CHCOPIP410 Pipe laying for house connection 46/11 10
DN068CHCOREN910 Marker Post for house connection 46/11 12
Line AC 34/1/27/45/19/1 (431LM, 8MH) 96
Traffic Management and Setting Out 38
DN068CGENSET210 Setting out 45/19/1 20
DN068CGENTRA310 Traffic Diversion 45/19/1 20
PipeLine Works (431 LM) 17
DN068CPIPEXC210 Excavation for sewer pipeline 45/19/1 10
DN068CPIPBED310 Geotextile and Bedding for sewer pipeline45/19/1 10
DN068CPIPLAY410 Pipe Laying for sewer pipeline 45/19/1 10
DN068CPIPPBF510 Partial Backfill for sewer pipeline 45/19/1 10
DN068CPIPTES610 Test for sewer pipeline 45/19/1 10
DN068CPIPFBF710 Final Backfill for sewer pipeline 45/19/1 9
Manhole Works (8 M.H.) 39
DN068CMHLEXC220 Excavation works for manhole 45/19/1 7
DN068CMHLBLI320 Blinding for manhole 45/19/1 7
DN068CMHLTAP420 Tanking membrane and protection for manhole 45/19/1 7
DN068CMHLBAS520 Base slab for manhole 45/19/1 7
DN068CMHLGRP920 GRP liner for manhole 45/19/1 7
DN068CMHLWCP620 Wall concrete and pipe for manhole 45/19/1 7
DN068CMHLDIC1070 Ladder for manhole 45/19/1 7
DN068CMHLEMB1020 External tanking membrane and protection for manhole 45/19/1 7
DN068CMHLBAC1040 Backfilling for manhole 45/19/1 6
DN068CMHLDIC1080 Reinstatement works 45/19/1 10
DN068CMHLCOV720 Cover slab for manhole 45/19/1 7
DN068CMHLDIC1060 DI cover for manhole 45/19/1 7
House Connection Works (10D, 1ABC) 41
DN068CHCOEXC320 Excavation for pipeline and inspection chamber 45/19/1 8
DN068CHCOPIP420 Pipe laying for house connection 45/19/1 8
DN068CHCOBAC820 Backfilling for house connection 45/19/1 8
DN068CHCODEM220 Demolition for existing underground structure 45/19/1 8
DN068CHCOBAS520 Base for inspection chamber 45/19/1 8
DN068CHCOWAL620 Wall for inspection chamber 45/19/1 8
DN068CHCOFIN1020 Finishing for inspection chamber 45/19/1 8
DN068CHCOCOV720 Cover for inspection chamber 45/19/1 8
DN068CHCOREN920 Reinstatement work for house connection 45/19/1 10
Line U 34/1/27/60/1 (779LM, 12MH) 113
Traffic Management and Setting Out 29
DN068CGENSET230 Setting out 60/1 20
DN068CGENTRA330 Traffic Diversion 60/1 20
PipeLine Works (779 LM) 35
DN068CPIPEXC230 Excavation for sewer pipeline 60/1 18
DN068CPIPBED330 Geotextile and Bedding for sewer pipeline 60/1 18
DN068CPIPLAY430 Pipe Laying for sewer pipeline 60/1 18
DN068CPIPTES630 Test for sewer pipeline 60/1 18
DN068CPIPPBF530 Partial Backfill for sewer pipeline 60/1 18
DN068CPIPFBF730 Final Backfill for sewer pipeline 60/1 17
Manhole Works (12 M.H.) 52
DN068CMHLEXC240 Excavation works for manhole 60/1 11
DN068CMHLBLI340 Blinding for manhole 60/1 11
DN068CMHLTAP440 Tanking membrane and protection for manhole 60/1 11
DN068CMHLBAS540 Base slab for manhole 60/1 11
DN068CMHLGRP940 GRP liner for manhole 60/1 11
DN068CMHLWCP640 Wall concrete and pipe for manhole 60/1 11
DN068CMHLEMB1040 External tanking membrane and protection for manhole 60/1 11
DN068CMHLBAC1060 Backfilling for manhole 60/1 13
DN068CMHLDIC1140 Reinstatement works 60/1 15
DN068CMHLDIC1130 Ladder for manhole 60/1 11
DN068CMHLCOV740 Cover slab for manhole 60/1 11
DN068CMHLDIC1120 DI cover for manhole 60/1 11
House Connection Works (17D) 58
DN068CHCOEXC340 Excavation for pipeline for house connection 60/1 12
DN068CHCOPIP440 Pipe laying for house connection 60/1 11
DN068CHCOBAC840 Backfilling for Pipe for house connection 60/1 11
DN068CHCOREN940 Marker Post for house connection 60/1 15
Line AB3 34/1/27/45/15/2 (2417LM, 91MH) 247
Traffic Management and Setting Out 92
DN068CGENROS340 Obtaining RO from authorities for 45 25
DN068CGENSET140 Setting out 45/15/2 23
DN068CGENTRA240 Traffic Diversion 45/15/2 23
PipeLine Works (2417 LM) 48
DN068CPIPEXC140 Excavation for sewer pipeline 45/15/2 23
DN068CPIPBED240 Geotextile and Bedding for sewer pipeline 45/15/2 23
DN068CPIPLAY340 Pipe Laying for sewer pipeline 45/15/2 23
DN068CPIPPBF440 Partial Backfill for sewer pipeline 45/15/2 23
DN068CPIPTES540 Test for sewer pipeline 45/15/2 23
DN068CPIPFBF640 Final Backfill for sewer pipeline 45/15/2 23
Manhole Works (91 M.H.) 83
DN068CMHLEXC150 Excavation works for manhole 45/15/2 23
DN068CMHLBLI250 Blinding for manhole 45/15/2 23
DN068CMHLTAP350 Tanking membrane and protection for manhole 45/15/2 23
DN068CMHLBAS450 Base slab for manhole 45/15/2 23
DN068CMHLGRP850 GRP liner for manhole 45/15/2 23
DN068CMHLWCP550 Wall concrete and pipe for manhole 45/15/2 23
DN068CMHLEMB950 External tanking membrane and protection for manhole 45/15/2 23
DN068CMHLBAC970 Backfilling for manhole 45/15/2 23
DN068CMHLDIC860 Ladder for manhole 45/15/2 20
DN068CMHLCOV650 Cover slab for manhole 45/15/2 23
DN068CMHLDIC850 DI cover for manhole 45/15/2 23
DN068CMHLDIC870 Reinstatement works 45/15/2 23
House Connection Works (48D,86ABC) 97
DN068CHCOEXC250 Excavation for pipeline and inspection chamber 45/15/2 23
DN068CHCOPIP350 Pipe laying for house connection 45/15/2 23
DN068CHCOBAC750 Backfilling for house connection 45/15/2 23
DN068CHCODEM150 Demolition for existing underground structure 45/15/2 23
DN068CHCOBAS450 Base for inspection chamber 45/15/2 23
DN068CHCOWAL550 Wall for inspection chamber 45/15/2 23
DN068CHCOCOV650 Cover for inspection chamber 45/15/2 23
DN068CHCOFIN950 Finishing for inspection chamber 45/15/2 23
DN068CHCOREN850 Reinstatement work for house connection 45/15/2 23
Line AB2 34/1/27/45/18/1 (479LM, 21MH) 162
Traffic Management and Setting Out 48
DN068CGENSET130 Setting out 45/18/1 23
DN068CGENTRA230 Traffic Diversion 45/18/1 23
PipeLine Works (479 LM) 28
DN068CPIPEXC130 Excavation for sewer pipeline 45/18/1 12
DN068CPIPBED230 Geotextile and Bedding for sewer pipeline 45/18/1 12
DN068CPIPLAY330 Pipe Laying for sewer pipeline 45/18/1 12
DN068CPIPTES530 Test for sewer pipeline 45/18/1 12
DN068CPIPPBF430 Partial Backfill for sewer pipeline 45/18/1 12
DN068CPIPFBF630 Final Backfill for sewer pipeline 45/18/1 12
Manhole Works (21 M.H.) 67
DN068CMHLEXC140 Excavation works for manhole 45/18/1 17
DN068CMHLBLI240 Blinding for manhole 45/18/1 17
DN068CMHLTAP340 Tanking membrane and protection for manhole 45/18/1 17
DN068CMHLBAS440 Base slab for manhole 45/18/1 17
DN068CMHLGRP840 GRP liner for manhole 45/18/1 17
DN068CMHLWCP540 Wall concrete and pipe for manhole 45/18/1 17
DN068CMHLEMB940 External tanking membrane and protection for manhole 45/18/1 17
DN068CMHLBAC960 Backfilling for manhole 45/18/1 15
DN068CMHLCOV640 Cover slab for manhole 45/18/1 17
DN068CMHLDIC830 Ladder for manhole 45/18/1 17
DN068CMHLDIC840 Reinstatement works 45/18/1 20
DN068CMHLDIC820 DI cover for manhole 45/18/1 17
House Connection Works (17D, 16ABC) 67
DN068CHCOEXC240 Excavation for pipeline and inspection chamber 45/18/1 13
DN068CHCOPIP340 Pipe laying for house connection 45/18/1 13
DN068CHCODEM140 Demolition for existing underground structure 45/18/1 13
DN068CHCOBAS440 Base for inspection chamber 45/18/1 13
DN068CHCOWAL540 Wall for inspection chamber 45/18/1 13
DN068CHCOFIN940 Finishing for inspection chamber 45/18/1 13
DN068CHCOCOV640 Cover for inspection chamber 45/18/1 13
DN068CHCOBAC740 Backfilling for house connection 45/18/1 13
DN068CHCOREN840 Reinstatement work for house connection 45/18/1 15
Line AB1 34/1/27/45/20/1 (1672 LM, 50MH) 148
Traffic Management and Setting Out 29
DN068CGENTRA220 Traffic Diversion 45/20/1 20
DN068CGENSET120 Setting out 45/20/1 20
PipeLine Works (1672 LM) 47
DN068CPIPEXC120 Excavation for sewer pipeline 45/20/1 23
DN068CPIPBED220 Geotextile and Bedding for sewer pipeline 45/20/1 23
DN068CPIPLAY320 Pipe Laying for sewer pipeline 45/20/1 23
DN068CPIPTES520 Test for sewer pipeline 45/20/1 23
DN068CPIPPBF420 Partial Backfill for sewer pipeline 45/20/1 23
DN068CPIPFBF620 Final Backfill for sewer pipeline 45/20/1 23
Manhole Works (50 M.H.) 85
DN068CMHLEXC130 Excavation works for manhole 45/20/1 23
DN068CMHLBLI230 Blinding for manhole 45/20/1 23
DN068CMHLTAP330 Tanking membrane and protection for manhole 45/20/1 23
DN068CMHLBAS430 Base slab for manhole 45/20/1 23
DN068CMHLGRP830 GRP liner for manhole 45/20/1 23
DN068CMHLWCP530 Wall concrete and pipe for manhole 45/20/1 23
DN068CMHLEMB930 External tanking membrane and protection for manhole 45/20/1 23
DN068CMHLBAC950 Backfilling for manhole 45/20/1 23
DN068CMHLDIC810 Reinstatement works 45/20/1 23
DN068CMHLCOV630 Cover slab for manhole 45/20/1 23
DN068CMHLDIC790 DI cover for manhole 45/20/1 23
DN068CMHLDIC800 Ladder for manhole 45/20/1 22
House Connection Works (26D, 33ABC) 64
DN068CHCOEXC230 Excavation for pipeline and inspection chamber 45/20/1 20
DN068CHCOPIP330 Pipe laying for house connection 45/20/1 20
DN068CHCOBAC730 Backfilling for house connection 45/20/1 20
DN068CHCODEM130 Demolition for existing underground structure 45/20/1 20
DN068CHCOBAS430 Base for inspection chamber 45/20/1 20
DN068CHCOWAL530 Wall for inspection chamber 45/20/1 20
DN068CHCOFIN930 Finishing for inspection chamber 45/20/1 20
DN068CHCOCOV630 Cover for inspection chamber 45/20/1 20
DN068CHCOREN830 Reinstatement work for house connection 45/20/1 20
Line AK 34/1/27/33/2 (4102LM, 120MH) 825
Trunk Sewer 34/1/27/33/2 To 34/27/33/18 (1087 LM, 20 MH) 825
Traffic Management and Setting Out 98
DN068CGENROS350 Obtaining RO from authorities 33/2 20
DN068CGENSET150 Setting out 33/2 50
DN068CGENTRA250 Traffic Diversion 33/2 35
PipeLine Works (1087 LM) 51
DN068CPIPEXC150 Excavation for sewer pipeline 33/2 23
DN068CPIPBED250 Geotextile and Bedding for sewer pipeline 33/2 23
DN068CPIPLAY350 Pipe Laying for sewer pipeline 33/2 23
DN068CPIPPBF450 Partial Backfill for sewer pipeline 33/2 23
DN068CPIPTES550 Test for sewer pipeline 33/2 23
DN068CPIPFBF650 Final Backfill for sewer pipeline 33/2 23
Manhole Works (20 M.H.) 93
DN068CMHLEXC160 Excavation works for manhole 33/2 17
DN068CMHLBLI260 Blinding for manhole 33/2 17
DN068CMHLTAP360 Tanking membrane and protection for manhole 33/2 17
DN068CMHLBAS460 Base slab for manhole 33/2 17
DN068CMHLGRP860 GRP liner for manhole 33/2 17
DN068CMHLWCP560 Wall concrete and pipe for manhole 33/2 17
DN068CMHLEMB960 External tanking membrane and protection for manhole 33/2 17
DN068CMHLBAC980 Backfilling for manhole 33/2 17
DN068CMHLDIC900 Reinstatement works 33/2 25
DN068CMHLCOV660 Cover slab for manhole 33/2 17
DN068CMHLDIC880 DI cover for manhole 33/2 17
DN068CMHLDIC890 Ladder for manhole 33/2 17
House Connection Works (16D, 4ABC) 35
DN068CHCOEXC280 Excavation for pipeline and inspection chamber 33/2 8
DN068CHCOPIP380 Pipe laying for house connection 33/2 8
DN068CHCOBAC780 Backfilling for house connection 33/2 8
DN068CHCODEM180 Demolition for existing underground structure 33/2 8
DN068CHCOBAS480 Base for inspection chamber 33/2 8
DN068CHCOWAL580 Wall for inspection chamber 33/2 8
DN068CHCOCOV680 Cover for inspection chamber 33/2 8
DN068CHCOFIN980 Finishing for inspection chamber 33/2 8
DN068CHCOREN880 Reinstatement work for house connection 33/2 8
Foul 34/1/27/33/12 (2304 LM, 84 MH) 148
PipeLine Works (2304 LM) 46
DN068CPIPEXC400 Excavation for sewer pipeline 33/12 23
DN068CPIPBED500 Geotextile and Bedding for sewer pipeline 33/12 23
DN068CPIPLAY600 Pipe Laying for sewer pipeline 33/12 23
DN068CPIPPBF700 Partial Backfill for sewer pipeline 33/12 23
DN068CPIPTES800 Test for sewer pipeline 33/12 23
DN068CPIPFBF900 Final Backfill for sewer pipeline 33/12 23
Manhole Works (84 M.H.) 83
DN068CMHLEXC410 Excavation works for manhole 33/12 23
DN068CMHLBLI510 Blinding for manhole 33/12 23
DN068CMHLTAP610 Tanking membrane and protection for manhole 33/12 23
DN068CMHLBAS710 Base slab for manhole 33/12 23
DN068CMHLGRP1110 GRP liner for manhole 33/12 23
DN068CMHLWCP810 Wall concrete and pipe for manhole 33/12 23
DN068CMHLEMB1210 External tanking membrane and protection for manhole 33/12 23
DN068CMHLCOV910 Cover slab for manhole 33/12 23
DN068CMHLBAC1230 Backfilling for manhole 33/12 23
DN068CMHLDIC1630 DI cover for manhole 33/12 23
DN068CMHLDIC1640 Ladder for manhole 33/12 23
DN068CMHLDIC1650 Reinstatement works 33/12 23
House Connection Works (27D, 88ABC) 100
DN068CHCOEXC260 Excavation for pipeline and inspection chamber 33/12 23
DN068CHCOPIP360 Pipe laying for house connection 33/12 23
DN068CHCOBAC760 Backfilling for house connection 33/12 23
DN068CHCODEM160 Demolition for existing underground structure 33/12 23
DN068CHCOBAS460 Base for inspection chamber 33/12 23
DN068CHCOWAL560 Wall for inspection chamber 33/12 23
DN068CHCOCOV660 Cover for inspection chamber 33/12 23
DN068CHCOFIN960 Finishing for inspection chamber 33/12 23
DN068CHCOREN860 Reinstatement work for house connection 33/12 23
Foul 34/1/27/33/5 (482 LM, 10 MH) 671
PipeLine Works (482 LM) 24
DN068CPIPEXC410 Excavation for sewer pipeline 33/5 12
DN068CPIPBED510 Geotextile and Bedding for sewer pipeline 33/5 12
DN068CPIPLAY610 Pipe Laying for sewer pipeline 33/5 12
DN068CPIPPBF710 Partial Backfill for sewer pipeline 33/5 12
DN068CPIPTES810 Test for sewer pipeline 33/5 12
DN068CPIPFBF910 Final Backfill for sewer pipeline 33/5 11
Manhole Works (10 M.H.) 41
DN068CMHLEXC420 Excavation works for manhole 33/5 8
DN068CMHLBLI520 Blinding for manhole 33/5 8
DN068CMHLTAP620 Tanking membrane and protection for manhole 33/5 8
DN068CMHLBAS720 Base slab for manhole 33/5 8
DN068CMHLGRP1120 GRP liner for manhole 33/5 8
DN068CMHLWCP820 Wall concrete and pipe for manhole 33/5 8
DN068CMHLCOV920 Cover slab for manhole 33/5 8
DN068CMHLEMB1220 External tanking membrane and protection for manhole 33/5 8
DN068CMHLBAC1240 Backfilling for manhole 33/5 9
DN068CMHLDIC1680 Reinstatement works 33/5 12
DN068CMHLDIC1670 Ladder for manhole 33/5 8
DN068CMHLDIC1660 DI cover for manhole 33/5 8
House Connection Works (18D) 654
DN068CHCOEXC500 Excavation for pipeline for house connection 33/5 7
DN068CHCOPIP600 Pipe laying for house connection 33/5 7
DN068CHCOBAC1000 Backfilling for pipe for house connection 33/5 7
DN068CHCOREN1100 Marker Post for house connection 33/5 10
Foul 34/1/27/33/3A (229 LM, 6 MH) 651
PipeLine Works (229 LM) 15
DN068CPIPEXC420 Excavation for sewer pipeline 33/3A 6
DN068CPIPBED520 Geotextile and Bedding for sewer pipeline 33/3A 6
DN068CPIPLAY620 Pipe Laying for sewer pipeline 33/3A 6
DN068CPIPPBF720 Partial Backfill for sewer pipeline 33/3A 6
DN068CPIPTES820 Test for sewer pipeline 33/3A 6
DN068CPIPFBF920 Final Backfill for sewer pipeline 33/3A 6
Manhole Works (6 M.H.) 34
DN068CMHLEXC430 Excavation works for manhole 33/3A 5
DN068CMHLBLI530 Blinding for manhole 33/3A 5
DN068CMHLTAP630 Tanking membrane and protection for manhole 33/3A 5
DN068CMHLBAS730 Base slab for manhole 33/3A 5
DN068CMHLGRP1130 GRP liner for manhole 33/3A 5
DN068CMHLWCP830 Wall concrete and pipe for manhole 33/3A 5
DN068CMHLDIC1710 Reinstatement works 33/3A 10
DN068CMHLCOV930 Cover slab for manhole 33/3A 5
DN068CMHLDIC1700 Ladder for manhole 33/3A 4
DN068CMHLEMB1230 External tanking membrane and protection for manhole 33/3A 5
DN068CMHLBAC1250 Backfilling for manhole 33/3A 5
DN068CMHLDIC1690 DI cover for manhole 33/3A 5
House Connection Works (11D) 639
DN068CHCOEXC510 Excavation for pipeline for house connection 33/3A 5
DN068CHCOPIP610 Pipe laying for house connection 33/3A 5
DN068CHCOBAC1010 Backfilling for Pipe for house connection 33/3A 5
DN068CHCOREN1110 Marker post for house connection 33/3A 5
Line AJ 34/1/27/38/1 (750LM, 18MH) 774
Traffic Management and Setting Out 84
DN068CGENROS360 Obtaining RO from authorities 38/1 25
DN068CGENSET160 Setting out 38/1 20
DN068CGENTRA260 Traffic Diversion 38/1 20
PipeLine Works (750 LM) 32
DN068CPIPEXC160 Excavation for sewer pipeline 38/1 18
DN068CPIPBED260 Geotextile and Bedding for sewer pipeline 38/1 18
DN068CPIPLAY360 Pipe Laying for sewer pipeline 38/1 18
DN068CPIPPBF460 Partial Backfill for sewer pipeline 38/1 18
DN068CPIPTES560 Test for sewer pipeline 38/1 18
DN068CPIPFBF660 Final Backfill for sewer pipeline 38/1 18
Manhole Works (18 M.H.) 63
DN068CMHLEXC170 Excavation works for manhole 38/1 15
DN068CMHLBLI270 Blinding for manhole 38/1 15
DN068CMHLTAP370 Tanking membrane and protection for manhole 38/1 15
DN068CMHLBAS470 Base slab for manhole 38/1 15
DN068CMHLGRP870 GRP liner for manhole 38/1 15
DN068CMHLWCP570 Wall concrete and pipe for manhole 38/1 15
DN068CMHLEMB970 External tanking membrane and protection for manhole 38/1 15
DN068CMHLBAC990 Backfilling for manhole 38/1 15
DN068CMHLDIC930 Reinstatement works 38/1 20
DN068CMHLDIC920 Ladder for manhole 38/1 13
DN068CMHLCOV670 Cover slab for manhole 38/1 15
DN068CMHLDIC910 DI cover for manhole 38/1 15
House Connection Works (24D) 632
DN068CHCOEXC270 Excavation for pipeline for house connection 38/1 10
DN068CHCOPIP370 Pipe laying for house connection 38/1 10
DN068CHCOBAC770 Backfilling for Pipe for house connection 38/1 10
DN068CHCOREN870 Marker post for house connection 38/1 10
Line AI 34/1/27/40/2 (3348LM, 123MH) 713
Trunk sewer 34/1/27/40/2 To 34/1/27/40/32 713
Traffic Management and Setting Out 86
DN068CGENROS370 Obtaining RO from authorities 40/2 20
DN068CGENSET170 Setting out 40/2 35
DN068CGENTRA270 Traffic Diversion 40/2 35
PipeLine Works (1186 LM) 52
DN068CPIPEXC170 Excavation for sewer pipeline 40/2 23
DN068CPIPBED270 Geotextile and Bedding for sewer pipeline 40/2 23
DN068CPIPLAY370 Pipe Laying for sewer pipeline 40/2 23
DN068CPIPPBF470 Partial Backfill for sewer pipeline 40/2 23
DN068CPIPTES570 Test for sewer pipeline 40/2 23
DN068CPIPFBF670 Final Backfill for sewer pipeline 40/2 22
Manhole Works (32 M.H.) 566
DN068CMHLEXC180 Excavation works for manhole 40/2 23
DN068CMHLBLI280 Blinding for manhole 40/2 23
DN068CMHLTAP380 Tanking membrane and protection for manhole 40/2 23
DN068CMHLBAS480 Base slab for manhole 40/2 23
DN068CMHLGRP880 GRP liner for manhole 40/2 23
DN068CMHLWCP580 Wall concrete and pipe for manhole 40/2 24
DN068CMHLEMB980 External tanking membrane and protection for manhole 40/2 25
DN068CMHLBAC1000 Backfilling for manhole 40/2 25
DN068CMHLCOV680 Cover slab for manhole 40/2 25
DN068CMHLDIC940 DI cover for manhole 40/2 23
DN068CMHLDIC950 Ladder for manhole 40/2 20
DN068CMHLDIC960 Reinstatement works 40/2 23
House Connection Works (7D, 20ABC) 516
DN068CHCOEXC570 Excavation for pipeline and inspection chamber 40/2 10
DN068CHCOPIP670 Pipe laying for house connection 40/2 10
DN068CHCOBAC1070 Backfilling for house connection 40/2 11
DN068CHCODEM470 Demolition for existing underground structure 40/2 10
DN068CHCOBAS770 Base for inspection chamber 40/2 10
DN068CHCOWAL870 Wall for inspection chamber 40/2 10
DN068CHCOFIN1270 Finishing for inspection chamber 40/2 10
DN068CHCOCOV970 Cover for inspection chamber 40/2 10
DN068CHCOREN1170 Reinstatement work for house connection 40/2 12
Foul 34/1/27/40/24 (88LM, 5MH) 577
PipeLine Works (88LM) 9
DN068CPIPEXC430 Excavation for sewer pipeline 40/24 3
DN068CPIPBED530 Geotextile and Bedding for sewer pipeline 40/24 3
DN068CPIPLAY630 Pipe Laying for sewer pipeline 40/24 3
DN068CPIPPBF730 Partial Backfill for sewer pipeline 40/24 3
DN068CPIPTES830 Test for sewer pipeline 40/24 3
DN068CPIPFBF930 Final Backfill for sewer pipeline 40/24 3
Manhole Works (5M.H.) 577
DN068CMHLEXC440 Excavation works for manhole 40/24 4
DN068CMHLBLI540 Blinding for manhole 40/24 4
DN068CMHLTAP640 Tanking membrane and protection for manhole 40/24 4
DN068CMHLBAS740 Base slab for manhole 40/24 4
DN068CMHLWCP840 Wall concrete and pipe for manhole 40/24 4
DN068CMHLGRP1140 GRP liner for manhole 40/24 4
DN068CMHLCOV940 Cover slab for manhole 40/24 4
DN068CMHLEMB1240 External tanking membrane and protection for manhole 40/24 5
DN068CMHLDIC1720 DI cover for manhole 40/24 4
DN068CMHLBAC1260 Backfilling for manhole 40/24 6
DN068CMHLDIC1730 Ladder for manhole 40/24 3
DN068CMHLDIC1740 Reinstatement works 40/24 8
House Connection Works (1D, 6ABC) 491
DN068CHCOEXC520 Excavation for pipeline and inspection chamber 40/24 5
DN068CHCOPIP620 Pipe laying for house connection 40/24 5
DN068CHCOBAC1020 Backfilling for house connection 40/24 5
DN068CHCODEM420 Demolition for existing underground structure 40/24 5
DN068CHCOBAS720 Base for inspection chamber 40/24 5
DN068CHCOWAL820 Wall for inspection chamber 40/24 5
DN068CHCOFIN1220 Finishing for inspection chamber 40/24 5
DN068CHCOCOV920 Cover for inspection chamber 40/24 5
DN068CHCOREN1120 Reinstatement work for house connection 40/24 5
Foul 34/1/27/40/22 (264LM, 11MH) 579
PipeLine Works (255LM) 13
DN068CPIPEXC440 Excavation for sewer pipeline 40/22 6
DN068CPIPBED540 Geotextile and Bedding for sewer pipeline 40/22 6
DN068CPIPLAY640 Pipe Laying for sewer pipeline 40/22 6
DN068CPIPPBF740 Partial Backfill for sewer pipeline 40/22 6
DN068CPIPTES840 Test for sewer pipeline 40/22 6
DN068CPIPFBF940 Final Backfill for sewer pipeline 40/22 6
Manhole Works (11M.H.) 578
DN068CMHLEXC450 Excavation works for manhole 40/22 9
DN068CMHLBLI550 Blinding for manhole 40/22 9
DN068CMHLTAP650 Tanking membrane and protection for manhole 40/22 10
DN068CMHLBAS750 Base slab for manhole 40/22 10
DN068CMHLGRP1150 GRP liner for manhole 40/22 9
DN068CMHLWCP850 Wall concrete and pipe for manhole 40/22 11
DN068CMHLCOV950 Cover slab for manhole 40/22 11
DN068CMHLDIC1750 DI cover for manhole 40/22 9
DN068CMHLEMB1250 External tanking membrane and protection for manhole 40/22 10
DN068CMHLDIC1760 Ladder for manhole 40/22 9
DN068CMHLBAC1270 Backfilling for manhole 40/22 9
DN068CMHLDIC1770 Reinstatement works 40/22 12
House Connection Works (12D, 8ABC) 484
DN068CHCOEXC530 Excavation for pipeline and inspection chamber 40/22 8
DN068CHCOPIP630 Pipe laying for house connection 40/22 8
DN068CHCOBAC1030 Backfilling for house connection 40/22 8
DN068CHCODEM430 Demolition for existing underground structure 40/22 8
DN068CHCOBAS730 Base for inspection chamber 40/22 8
DN068CHCOWAL830 Wall for inspection chamber 40/22 8
DN068CHCOFIN1230 Finishing for inspection chamber 40/22 8
DN068CHCOCOV930 Cover for inspection chamber 40/22 8
DN068CHCOREN1130 Reinstatement work for house connection 40/22 10
Foul 34/1/27/40/14 (339LM, 13MH) 518
PipeLine Works (339LM) 15
DN068CPIPEXC450 Excavation for sewer pipeline 40/14 8
DN068CPIPBED550 Geotextile and Bedding for sewer pipeline 40/14 10
DN068CPIPLAY650 Pipe Laying for sewer pipeline 40/14 8
DN068CPIPPBF750 Partial Backfill for sewer pipeline 40/14 8
DN068CPIPTES850 Test for sewer pipeline 40/14 8
DN068CPIPFBF950 Final Backfill for sewer pipeline 40/14 8
Manhole Works (13M.H.) 515
DN068CMHLEXC460 Excavation works for manhole 40/14 14
DN068CMHLBLI560 Blinding for manhole 40/14 14
DN068CMHLTAP660 Tanking membrane and protection for manhole 40/14 13
DN068CMHLBAS760 Base slab for manhole 40/14 12
DN068CMHLGRP1160 GRP liner for manhole 40/14 12
DN068CMHLWCP860 Wall concrete and pipe for manhole 40/14 12
DN068CMHLCOV960 Cover slab for manhole 40/14 12
DN068CMHLEMB1260 External tanking membrane and protection for manhole 40/14 12
DN068CMHLDIC1780 DI cover for manhole 40/14 12
DN068CMHLBAC1280 Backfilling for manhole 40/14 12
DN068CMHLDIC1790 Ladder for manhole 40/14 10
DN068CMHLDIC1800 Reinstatement works 40/14 15
House Connection Works (10D, 9ABC) 462
DN068CHCOEXC540 Excavation for pipeline and inspection chamber 40/14 7
DN068CHCOPIP640 Pipe laying for house connection 40/14 7
DN068CHCOBAC1040 Backfilling for house connection 40/14 7
DN068CHCODEM440 Demolition for existing underground structure 40/14 7
DN068CHCOBAS740 Base for inspection chamber 40/14 7
DN068CHCOWAL840 Wall for inspection chamber 40/14 7
DN068CHCOFIN1240 Finishing for inspection chamber 40/14 7
DN068CHCOCOV940 Cover for inspection chamber 40/14 7
DN068CHCOREN1140 Reinstatement work for house connection 40/14 10
Foul 34/1/27/40/9 (411LM, 15MH) 519
PipeLine Works (411LM) 25
DN068CPIPEXC460 Excavation for sewer pipeline 40/9 10
DN068CPIPBED560 Geotextile and Bedding for sewer pipeline 40/9 10
DN068CPIPLAY660 Pipe Laying for sewer pipeline 40/9 10
DN068CPIPTES860 Test for sewer pipeline 40/9 10
DN068CPIPPBF760 Partial Backfill for sewer pipeline 40/9 10
DN068CPIPFBF960 Final Backfill for sewer pipeline 40/9 10
Manhole Works (15M.H.) 512
DN068CMHLEXC470 Excavation works for manhole 40/9 14
DN068CMHLBLI570 Blinding for manhole 40/9 14
DN068CMHLTAP670 Tanking membrane and protection for manhole 40/9 14
DN068CMHLBAS770 Base slab for manhole 40/9 14
DN068CMHLGRP1170 GRP liner for manhole 40/9 14
DN068CMHLWCP870 Wall concrete and pipe for manhole 40/9 14
DN068CMHLCOV970 Cover slab for manhole 40/9 14
DN068CMHLEMB1270 External tanking membrane and protection for manhole 40/9 14
DN068CMHLDIC1810 DI cover for manhole 40/9 14
DN068CMHLBAC1290 Backfilling for manhole 40/9 14
DN068CMHLDIC1820 Ladder for manhole 40/9 12
DN068CMHLDIC1830 Reinstatement works 40/9 18
House Connection Works (9D, 15ABC) 402
DN068CHCOEXC550 Excavation for pipeline and inspection chamber 40/9 9
DN068CHCOPIP650 Pipe laying for house connection 40/9 9
DN068CHCOBAC1050 Backfilling for house connection 40/9 9
DN068CHCODEM450 Demolition for existing underground structure 40/9 9
DN068CHCOBAS750 Base for inspection chamber 40/9 9
DN068CHCOWAL850 Wall for inspection chamber 40/9 9
DN068CHCOFIN1250 Finishing for inspection chamber 40/9 9
DN068CHCOCOV950 Cover for inspection chamber 40/9 9
DN068CHCOREN1150 Reinstatement work for house connection 40/9 10
Foul 34/1/27/40/5 (1060LM, 47MH) 530
PipeLine Works (1060LM) 76
DN068CPIPEXC470 Excavation for sewer pipeline 40/5 23
DN068CPIPBED570 Geotextile and Bedding for sewer pipeline 40/5 23
DN068CPIPLAY670 Pipe Laying for sewer pipeline 40/5 23
DN068CPIPPBF770 Partial Backfill for sewer pipeline 40/5 23
DN068CPIPTES870 Test for sewer pipeline 40/5 23
DN068CPIPFBF970 Final Backfill for sewer pipeline 40/5 23
Manhole Works (47M.H.) 511
DN068CMHLEXC480 Excavation works for manhole 40/5 23
DN068CMHLBLI580 Blinding for manhole 40/5 23
DN068CMHLTAP680 Tanking membrane and protection for manhole 40/5 23
DN068CMHLBAS780 Base slab for manhole 40/5 23
DN068CMHLGRP1180 GRP liner for manhole 40/5 23
DN068CMHLWCP880 Wall concrete and pipe for manhole 40/5 23
DN068CMHLEMB1280 External tanking membrane and protection for manhole 40/5 23
DN068CMHLCOV980 Cover slab for manhole 40/5 23
DN068CMHLDIC1840 DI cover for manhole 40/5 23
DN068CMHLBAC1300 Backfilling for manhole 40/5 23
DN068CMHLDIC1850 Ladder for manhole 40/5 20
DN068CMHLDIC1860 Reinstatement works 40/5 23
House Connection Works (18D, 54ABC) 437
DN068CHCOEXC560 Excavation for pipeline and inspection chamber 40/5 23
DN068CHCOPIP660 Pipe laying for house connection 40/5 23
DN068CHCOBAC1060 Backfilling for house connection 40/5 23
DN068CHCODEM460 Demolition for existing underground structure 40/5 23
DN068CHCOBAS760 Base for inspection chamber 40/5 23
DN068CHCOWAL860 Wall for inspection chamber 40/5 23
DN068CHCOFIN1260 Finishing for inspection chamber 40/5 23
DN068CHCOCOV960 Cover for inspection chamber 40/5 23
DN068CHCOREN1160 Reinstatement work for house connection 40/5 23
Line AL 34/1/27/30/1 (603LM, 18MH) 619
Traffic Management and Setting Out 77
DN068CGENROS300 Obtaining RO from authorities 30/1 25
DN068CGENSET100 Setting out 30/1 10
DN068CGENTRA200 Traffic Diversion 30/1 10
PipeLine Works (603 LM) 42
DN068CPIPEXC100 Excavation for sewer pipeline 30/1 15
DN068CPIPBED200 Geotextile and Bedding for sewer pipeline 30/1 14
DN068CPIPLAY300 Pipe Laying for sewer pipeline 30/1 14
DN068CPIPPBF400 Partial Backfill for sewer pipeline 30/1 14
DN068CPIPTES500 Test for sewer pipeline 30/1 14
DN068CPIPFBF600 Final Backfill for sewer pipeline 30/1 14
Manhole Works (18 M.H.) 468
DN068CMHLEXC100 Excavation works for manhole 30/1 16
DN068CMHLBLI200 Blinding for manhole 30/1 16
DN068CMHLTAP300 Tanking membrane and protection for manhole 30/1 16
DN068CMHLBAS400 Base slab for manhole 30/1 16
DN068CMHLGRP800 GRP liner for manhole 30/1 16
DN068CMHLWCP500 Wall concrete and pipe for manhole 30/1 16
DN068CMHLCOV600 Cover slab for manhole 30/1 16
DN068CMHLEMB900 External tanking membrane and protection for manhole 30/1 16
DN068CMHLDIC700 DI cover for manhole 30/1 16
DN068CMHLDIC710 Ladder for manhole 30/1 16
DN068CMHLBAC920 Backfilling for manhole 30/1 16
DN068CMHLDIC720 Reinstatement works 30/1 20
House Connection Works (12D, 7ABC) 66
DN068CHCOEXC200 Excavation for pipeline and inspection chamber 30/1 7
DN068CHCOPIP300 Pipe laying for house connection 30/1 7
DN068CHCOBAC700 Backfilling for house connection 30/1 7
DN068CHCODEM100 Demolition for existing underground structure 30/1 7
DN068CHCOBAS400 Base for inspection chamber 30/1 7
DN068CHCOWAL500 Wall for inspection chamber 30/1 7
DN068CHCOFIN900 Finishing for inspection chamber 30/1 7
DN068CHCOCOV600 Cover for inspection chamber 30/1 7
DN068CHCOREN800 Reinstatement work for house connection 30/1 10
Line AN1 34/1/27/24 (1324LM, 32MH) 596
Traffic Management and Setting Out 451
DN068CGENSET110 Setting out 24 20
DN068CGENTRA290 Traffic Diversion 24 20
PipeLine Works (1324 LM) 48
DN068CPIPEXC110 Excavation for sewer pipeline 24 23
DN068CPIPBED210 Geotextile and Bedding for sewer pipeline 24 23
DN068CPIPLAY310 Pipe Laying for sewer pipeline 24 23
DN068CPIPPBF410 Partial Backfill for sewer pipeline 24 23
DN068CPIPTES510 Test for sewer pipeline 24 23
DN068CPIPFBF610 Final Backfill for sewer pipeline 24 23
Manhole Works (32 M.H.) 520
DN068CMHLEXC120 Excavation works for manhole 24 21
DN068CMHLBLI220 Blinding for manhole 24 21
DN068CMHLTAP320 Tanking membrane and protection for manhole 24 21
DN068CMHLBAS420 Base slab for manhole 24 21
DN068CMHLGRP820 GRP liner for manhole 24 21
DN068CMHLWCP520 Wall concrete and pipe for manhole 24 21
DN068CMHLCOV620 Cover slab for manhole 24 21
DN068CMHLEMB920 External tanking membrane and protection for manhole 24 21
DN068CMHLDIC760 DI cover for manhole 24 21
DN068CMHLBAC940 Backfilling for manhole 24 21
DN068CMHLDIC770 Ladder for manhole 24 18
DN068CMHLDIC780 Reinstatement works 24 23
House Connection Works (39D) 76
DN068CHCOEXC220 Excavation for pipeline and inspection chamber 24 15
DN068CHCOPIP320 Pipe laying for house connection 24 15
DN068CHCOBAC720 Backfilling for Pipe for house connection 24 15
DN068CHCOREN820 Marker Post for house connection 24 20
Line AM 34/1/27/27 (7003LM, 227MH) 896
Trunk Sewer 34/1/27/27/24 To 34/1/27/27/41 (518 LM, 17 MH) 659
Traffic Management and Setting Out 141
DN068CGENROS440 Obtaining RO from authorities 27 20
DN068CGENSET240 Setting out 27 60
DN068CGENTRA340 Traffic Diversion 27 40
PipeLine Works (518 LM) 29
DN068CPIPEXC240 Excavation for sewer pipeline 27 12
DN068CPIPBED340 Geotextile and Bedding for sewer pipeline 27 12
DN068CPIPLAY440 Pipe Laying for sewer pipeline 27 12
DN068CPIPPBF540 Partial Backfill for sewer pipeline 27 12
DN068CPIPTES640 Test for sewer pipeline 27 12
DN068CPIPFBF740 Final Backfill for sewer pipeline 27 12
Manhole Works (17 M.H.) 426
DN068CMHLEXC250 Excavation works for manhole 27 14
DN068CMHLBLI350 Blinding for manhole 27 14
DN068CMHLTAP450 Tanking membrane and protection for manhole 27 14
DN068CMHLBAS550 Base slab for manhole 27 14
DN068CMHLGRP950 GRP liner for manhole 27 14
DN068CMHLWCP650 Wall concrete and pipe for manhole 27 14
DN068CMHLDIC1160 Ladder for manhole 27 10
DN068CMHLEMB1050 External tanking membrane and protection for manhole 27 14
DN068CMHLCOV750 Cover slab for manhole 27 14
DN068CMHLDIC1150 DI cover for manhole 27 14
DN068CMHLBAC1070 Backfilling for manhole 27 14
DN068CMHLDIC1170 Reinstatement works 27 18
House Connection Works (10D, 10ABC) 30
DN068CHCOEXC580 Excavation for pipeline and inspection chamber 27 10
DN068CHCOPIP680 Pipe laying for house connection 27 10
DN068CHCOBAC1080 Backfilling for house connection 27 10
DN068CHCODEM480 Demolition for existing underground structure 27 10
DN068CHCOBAS780 Base for inspection chamber 27 10
DN068CHCOWAL880 Wall for inspection chamber 27 10
DN068CHCOFIN1280 Finishing for inspection chamber 27 10
DN068CHCOCOV980 Cover for inspection chamber 27 10
DN068CHCOREN1180 Reinstatement work for house connection 27 12
Foul 34/1/27/27/27 (134 LM, 2 MH) 406
PipeLine Works (134 LM) 14
DN068CPIPEXC280 Excavation for sewer pipeline 27/27 5
DN068CPIPBED380 Geotextile and Bedding for sewer pipeline 27/27 4
DN068CPIPLAY480 Pipe Laying for sewer pipeline 27/27 4
DN068CPIPTES680 Test for sewer pipeline 27/27 4
DN068CPIPPBF580 Partial Backfill for sewer pipeline 27/27 4
DN068CPIPFBF780 Final Backfill for sewer pipeline 27/27 4
Manhole Works (2 M.H.) 404
DN068CMHLEXC290 Excavation works for manhole 27/27 2
DN068CMHLBLI390 Blinding for manhole 27/27 2
DN068CMHLTAP490 Tanking membrane and protection for manhole 27/27 2
DN068CMHLBAS590 Base slab for manhole 27/27 2
DN068CMHLGRP990 GRP liner for manhole 27/27 2
DN068CMHLWCP690 Wall concrete and pipe for manhole 27/27 2
DN068CMHLEMB1090 External tanking membrane and protection for manhole 27/27 2
DN068CMHLDIC1280 Ladder for manhole 27/27 1
DN068CMHLCOV790 Cover slab for manhole 27/27 2
DN068CMHLDIC1270 DI cover for manhole 27/27 2
DN068CMHLBAC1110 Backfilling for manhole 27/27 2
DN068CMHLDIC1290 Reinstatement works 27/27 5
House Connection Works (2ABC) 119
DN068CHCOEXC380 Excavation for pipeline and inspection chamber 27/27 2
DN068CHCOPIP480 Pipe laying for house connection 27/27 2
DN068CHCOBAC880 Backfilling for house connection 27/27 2
DN068CHCODEM280 Demolition for existing underground structure 27/27 2
DN068CHCOBAS580 Base for inspection chamber 27/27 2
DN068CHCOWAL680 Wall for inspection chamber 27/27 2
DN068CHCOCOV780 Cover for inspection chamber 27/27 2
DN068CHCOFIN1080 Finishing for inspection chamber 27/27 2
DN068CHCOREN980 Reinstatement work 27/27 4
Foul 34/1/27/27/29 (146 LM, 6 MH) 406
PipeLine Works (146 LM) 10
DN068CPIPEXC270 Excavation for sewer pipeline 27/29 5
DN068CPIPBED370 Geotextile and Bedding for sewer pipeline 27/29 4
DN068CPIPLAY470 Pipe Laying for sewer pipeline 27/29 4
DN068CPIPPBF570 Partial Backfill for sewer pipeline 27/29 4
DN068CPIPTES670 Test for sewer pipeline 27/29 4
DN068CPIPFBF770 Final Backfill for sewer pipeline 27/29 4
Manhole Works (6 M.H.) 392
DN068CMHLEXC280 Excavation works for manhole 27/29 5
DN068CMHLBLI380 Blinding for manhole 27/29 5
DN068CMHLTAP480 Tanking membrane and protection for manhole 27/29 5
DN068CMHLBAS580 Base slab for manhole 27/29 5
DN068CMHLGRP980 GRP liner for manhole 27/29 5
DN068CMHLWCP680 Wall concrete and pipe for manhole 27/29 5
DN068CMHLCOV780 Cover slab for manhole 27/29 5
DN068CMHLDIC1240 DI cover for manhole 27/29 5
DN068CMHLEMB1080 External tanking membrane and protection for manhole 27/29 5
DN068CMHLDIC1250 Ladder for manhole 27/29 5
DN068CMHLBAC1100 Backfilling for manhole 27/29 5
DN068CMHLDIC1260 Reinstatement works 27/29 8
House Connection Works (5D, 5B) 103
DN068CHCOEXC370 Excavation for pipeline and inspection chamber 27/29 4
DN068CHCOPIP470 Pipe laying for house connection 27/29 4
DN068CHCOBAC870 Backfilling for house connection 27/29 4
DN068CHCODEM270 Demolition for existing underground structure 27/29 4
DN068CHCOBAS570 Base for inspection chamber 27/29 4
DN068CHCOWAL670 Wall for inspection chamber 27/29 4
DN068CHCOCOV770 Cover for inspection chamber 27/29 4
DN068CHCOFIN1070 Finishing for inspection chamber 27/29 4
DN068CHCOREN970 Reinstatement work for house connection 27/29 10
Foul 34/1/27/27/30 (515 LM, 18 MH) 408
PipeLine Works (515 LM) 25
DN068CPIPEXC260 Excavation for sewer pipeline 27/30 12
DN068CPIPBED360 Geotextile and Bedding for sewer pipeline 27/30 12
DN068CPIPLAY460 Pipe Laying for sewer pipeline 27/30 12
DN068CPIPPBF560 Partial Backfill for sewer pipeline 27/30 12
DN068CPIPTES660 Test for sewer pipeline 27/30 12
DN068CPIPFBF760 Final Backfill for sewer pipeline 27/30 12
Manhole Works (18 M.H.) 406
DN068CMHLEXC270 Excavation works for manhole 27/30 15
DN068CMHLBLI370 Blinding for manhole 27/30 15
DN068CMHLTAP470 Tanking membrane and protection for manhole 27/30 15
DN068CMHLBAS570 Base slab for manhole 27/30 15
DN068CMHLGRP970 GRP liner for manhole 27/30 15
DN068CMHLWCP670 Wall concrete and pipe for manhole 27/30 15
DN068CMHLCOV770 Cover slab for manhole 27/30 15
DN068CMHLEMB1070 External tanking membrane and protection for manhole 27/30 15
DN068CMHLDIC1210 DI cover for manhole 27/30 15
DN068CMHLBAC1090 Backfilling for manhole 27/30 15
DN068CMHLDIC1220 Ladder for manhole 27/30 12
DN068CMHLDIC1230 Reinstatement works 27/30 18
House Connection Works (5D, 20ABC) 87
DN068CHCOEXC360 Excavation for pipeline and inspection chamber 27/30 10
DN068CHCOPIP460 Pipe laying for house connection 27/30 10
DN068CHCOBAC860 Backfilling for house connection 27/30 10
DN068CHCODEM260 Demolition for existing underground structure 27/30 10
DN068CHCOBAS560 Base for inspection chamber 27/30 10
DN068CHCOWAL660 Wall for inspection chamber 27/30 10
DN068CHCOFIN1060 Finishing for inspection chamber 27/30 10
DN068CHCOCOV760 Cover for inspection chamber 27/30 10
DN068CHCOREN960 Reinstatement work for house connection 27/30 12
Foul 34/1/27/27/34 (179 LM, 7 MH) 459
PipeLine Works (179 LM) 11
DN068CPIPEXC250 Excavation for sewer pipeline 27/34 5
DN068CPIPBED350 Geotextile and Bedding for sewer pipeline 27/34 5
DN068CPIPLAY450 Pipe Laying for sewer pipeline 27/34 5
DN068CPIPTES650 Test for sewer pipeline 27/34 5
DN068CPIPPBF550 Partial Backfill for sewer pipeline 27/34 5
DN068CPIPFBF750 Final Backfill for sewer pipeline 27/34 5
Manhole Works (7 M.H.) 457
DN068CMHLEXC260 Excavation works for manhole 27/34 6
DN068CMHLBLI360 Blinding for manhole 27/34 6
DN068CMHLTAP460 Tanking membrane and protection for manhole 27/34 6
DN068CMHLBAS560 Base slab for manhole 27/34 6
DN068CMHLGRP960 GRP liner for manhole27/34 6
DN068CMHLWCP660 Wall concrete and pipe for manhole 27/34 6
DN068CMHLCOV760 Cover slab for manhole 27/34 6
DN068CMHLDIC1180 DI cover for manhole 27/34 6
DN068CMHLDIC1190 Ladder for manhole 27/34 4
DN068CMHLEMB1060 External tanking membrane and protection for manhole 27/34 6
DN068CMHLBAC1080 Backfilling for manhole 27/34 6
DN068CMHLDIC1200 Reinstatement works 27/34 10
House Connection Works (4D, 5ABC) 19
DN068CHCOEXC350 Excavation for pipeline and inspection chamber 27/34 4
DN068CHCOPIP450 Pipe laying for house connection 27/34 4
DN068CHCOBAC850 Backfilling for house connection 27/34 4
DN068CHCOBAS550 Base for inspection chamber 27/34 4
DN068CHCODEM250 Demolition for existing underground structure 27/34 4
DN068CHCOWAL650 Wall for inspection chamber 27/34 4
DN068CHCOFIN1050 Finishing for inspection chamber 27/34 4
DN068CHCOCOV750 Cover for inspection chamber 27/34 4
DN068CHCOREN950 Reinstatement work for house connection 27/34 4
Trunk Sewer Microtunnelling 34/1/27/27 To 34/1/27/27/24 (1480 LM, 26 MH, 12D, 1ABC) 858
Pipeline Works (34/1/27/27/2 To 34/1/27/27 102LM) 41
DN068CMITEXC100 Excavation for jacking shaft 5
DN068CMITCJS110 Concrete for jacking shaft 10
DN068CMITEXR120 Excavation for recieving shaft 10
DN068CMITSEC300 2nd Tunneling & Driving the Pipes and dismantle 4
DN068CMITFIR200 1st Tunneling & Driving the Pipes + Equipment 5
Pipeline Works (34/1/27/27/4 To 34/1/27/27/2 127LM) 50
DN068CMITEXR150 Excavation for recieving shaft 10
DN068CMITFIR210 1st Tunneling & Driving the Pipes 5
DN068CMITEXC130 Excavation for jacking shaft 5
DN068CMITCJS140 Concrete for jacking shaft 10
DN068CMITSEC310 2nd Tunneling & Driving the Pipes and dismantle 6
Pipeline Works (34/1/27/27/6 To 34/1/27/27/4 107LM) 56
DN068CMITEXC160 Excavation for jacking shaft 5
DN068CMITEXR180 Excavation for recieving shaft 10
DN068CMITCJS170 Concrete for jacking shaft 10
DN068CMITFIR220 1st Tunneling & Driving the Pipes 4
DN068CMITSEC320 2nd Tunneling & Driving the Pipes and dismantle 6
Pipeline Works (34/1/27/27/7 To 34/1/27/27/6 130LM) 65
DN068CMITEXC190 Excavation for jacking shaft 5
DN068CMITEXR240 Excavation for recieving shaft 10
DN068CMITCJS230 Concrete for jacking shaft 10
DN068CMITFIR250 1st Tunneling & Driving the Pipes 4
DN068CMITSEC330 2nd Tunneling & Driving the Pipes and dismantle 8
Pipeline Works (34/1/27/27/9A To 34/1/27/27/7 124LM) 70
DN068CMITEXC260 Excavation for jacking shaft 5
DN068CMITEXR280 Excavation for recieving shaft 10
DN068CMITCJS270 Concrete for jacking shaft 10
DN068CMITFIR290 1st Tunneling & Driving the Pipes 7
DN068CMITSEC340 2nd Tunneling & Driving the Pipes and dismantle 5
Pipeline Works (34/1/27/27/10 To 34/1/27/27/9A 104LM) 77
DN068CMITEXC350 Excavation for jacking shaft 5
DN068CMITEXR370 Excavation for recieving shaft 10
DN068CMITFIR380 1st Tunneling & Driving the Pipes 4
DN068CMITCJS360 Concrete for jacking shaft 10
DN068CMITSEC390 2nd Tunneling & Driving the Pipes and dismantle 6
Pipeline Works (34/1/27/27/12 To 34/1/27/27/10 154LM) 88
DN068CMITEXC400 Excavation for jacking shaft 5
DN068CMITEXR420 Excavation for recieving shaft 10
DN068CMITCJS410 Concrete for jacking shaft 10
DN068CMITFIR430 1st Tunneling & Driving the Pipes 7
DN068CMITSEC440 2nd Tunneling & Driving the Pipes and dismantle 8
Pipeline Works (34/1/27/27/14 To 34/1/27/27/12 152LM) 95
DN068CMITEXR470 Excavation for recieving shaft 10
DN068CMITEXC450 Excavation for jacking shaft 5
DN068CMITFIR480 1st Tunneling & Driving the Pipes 4
DN068CMITCJS460 Concrete for jacking shaft 10
DN068CMITSEC490 2nd Tunneling & Driving the Pipes and dismantle 8
Pipeline Works (34/1/27/27/16 To 34/1/27/27/14 152LM) 107
DN068CMITEXC500 Excavation for jacking shaft 5
DN068CMITEXR520 Excavation for recieving shaft 10
DN068CMITFIR530 1st Tunneling & Driving the Pipes 7
DN068CMITCJS510 Concrete for jacking shaft 10
DN068CMITSEC540 2nd Tunneling & Driving the Pipes and dismantle 8
Pipeline Works (34/1/27/27/18 To 34/1/27/27/16 83LM) 112
DN068CMITEXC550 Excavation for jacking shaft 5
DN068CMITEXR570 Excavation for recieving shaft 10
DN068CMITCJS560 Concrete for jacking shaft 10
DN068CMITFIR580 1st Tunneling & Driving the Pipes 4
DN068CMITSEC590 2nd Tunneling & Driving the Pipes and dismantle 5
Pipeline Works (34/1/27/27/20 To 34/1/27/27/18 90LM) 126
DN068CMITEXC600 Excavation for jacking shaft 5
DN068CMITEXR620 Excavation for recieving shaft 10
DN068CMITFIR630 1st Tunneling & Driving the Pipes 4
DN068CMITCJS610 Concrete for jacking shaft 10
DN068CMITSEC640 2nd Tunneling & Driving the Pipes and dismantle 5
Pipeline Works (34/1/27/27/22 To 34/1/27/27/20 94LM) 145
DN068CMITEXC650 Excavation for jacking shaft 5
DN068CMITEXR670 Excavation for recieving shaft 10
DN068CMITCJS660 Concrete for jacking shaft 10
DN068CMITSEC690 2nd Tunneling & Driving the Pipes and dismantle 5
DN068CMITFIR680 1st Tunneling & Driving the Pipes 4
Pipeline Works (34/1/27/27/24 To 34/1/27/27/22 61LM) 160
DN068CMITEXC700 Excavation for jacking shaft 5
DN068CMITEXR720 Excavation for recieving shaft 10
DN068CMITCJS710 Concrete for jacking shaft 10
DN068CMITFIR730 1st Tunneling & Driving the Pipes 3
DN068CMITSEC740 2nd Tunneling & Driving the Pipes and dismantle 5
Manhole Works (26 M.H.) 145
DN068CMHLBLI210 Blinding for manhole for Microtunnel 21
DN068CMHLTAP310 Tanking membrane and protection for manhole for Microtunnel 21
DN068CMHLBAS410 Base slab for manhole for Microtunnel 21
DN068CMHLGRP810 GRP liner for manhole for Microtunnel 21
DN068CMHLWCP510 Wall concrete and pipe for manhole for Microtunnel 21
DN068CMHLEMB910 External tanking membrane and protection for manhole for Microtunn 21
DN068CMHLBAC930 Backfilling for manhole for Microtunnel 21
DN068CMHLCOV610 Cover slab for manhole for Microtunnel 21
DN068CMHLDIC730 DI cover for manhole for Microtunnel 21
DN068CMHLDIC740 Ladder for manhole for Microtunnel 18
DN068CMHLDIC750 Reinstatement works for Microtunnel and house connection (12D, 1AB 20
Foul 34/1/27/27/1 (107 LM, 3 MH) 390
PipeLine Works (107 LM) 11
DN068CPIPEXC390 Excavation for sewer pipeline 27/1 3
DN068CPIPBED490 Geotextile and Bedding for sewer pipeline 27/1 4
DN068CPIPLAY590 Pipe Laying for sewer pipeline 27/1 4
DN068CPIPPBF690 Partial Backfill for sewer pipeline 27/1 4
DN068CPIPTES790 Test for sewer pipeline 27/1 4
DN068CPIPFBF890 Final Backfill for sewer pipeline 27/1 4
Manhole Works (3 M.H.) 372
DN068CMHLEXC400 Excavation works for manhole 27/1 3
DN068CMHLBLI500 Blinding for manhole 27/1 3
DN068CMHLTAP600 Tanking membrane and protection for manhole 27/1 3
DN068CMHLBAS700 Base slab for manhole 27/1 3
DN068CMHLWCP800 Wall concrete and pipe for manhole 27/1 3
DN068CMHLGRP1100 GRP liner for manhole 27/1 3
DN068CMHLCOV900 Cover slab for manhole 27/1 3
DN068CMHLEMB1200 External tanking membrane and protection for manhole 27/1 3
DN068CMHLDIC1600 DI cover for manhole 27/1 3
DN068CMHLBAC1220 Backfilling for manhole 27/1 3
DN068CMHLDIC1610 Ladder for manhole 27/1 3
DN068CMHLDIC1620 Reinstatement works 27/1 7
House Connection Works (1ABC) 70
DN068CHCOEXC490 Excavation for pipeline and inspection chamber 27/1 2
DN068CHCOPIP590 Pipe laying for house connection 27/1 2
DN068CHCOBAC990 Backfilling for house connection 27/1 2
DN068CHCOBAS690 Base for inspection chamber 27/1 2
DN068CHCOWAL790 Wall for inspection chamber 27/1 2
DN068CHCODEM390 Demolition for existing underground structure 27/1 2
DN068CHCOFIN1190 Finishing for inspection chamber 27/1 2
DN068CHCOCOV890 Cover for inspection chamber 27/1 2
DN068CHCOREN1090 Reinstatement work for house connection 27/1 4
Foul 34/1/27/27/5 (236 LM, 4 MH) 412
PipeLine Works (263 LM) 14
DN068CPIPEXC380 Excavation for sewer pipeline 27/5 7
DN068CPIPBED480 Geotextile and Bedding for sewer pipeline 27/5 7
DN068CPIPLAY580 Pipe Laying for sewer pipeline 27/5 7
DN068CPIPPBF680 Partial Backfill for sewer pipeline 27/5 7
DN068CPIPTES780 Test for sewer pipeline 27/5 7
DN068CPIPFBF880 Final Backfill for sewer pipeline 27/5 7
Manhole Works (4 M.H.) 410
DN068CMHLEXC390 Excavation works for manhole 27/5 4
DN068CMHLBLI490 Blinding for manhole 27/5 4
DN068CMHLTAP590 Tanking membrane and protection for manhole 27/5 4
DN068CMHLBAS690 Base slab for manhole 27/5 4
DN068CMHLGRP1090 GRP liner for manhole 27/5 4
DN068CMHLWCP790 Wall concrete and pipe for manhole 27/5 4
DN068CMHLCOV890 Cover slab for manhole 27/5 4
DN068CMHLDIC1580 Ladder for manhole 27/5 2
DN068CMHLDIC1570 DI cover for manhole 27/5 4
DN068CMHLEMB1190 External tanking membrane and protection for manhole 27/5 4
DN068CMHLBAC1210 Backfilling for manhole 27/5 4
DN068CMHLDIC1590 Reinstatement works 27/5 6
House Connection Works (6D) 51
DN068CHCOEXC480 Excavation for pipeline for house connection 27/5 3
DN068CHCOPIP580 Pipe laying for house connection 27/5 3
DN068CHCOBAC980 Backfilling for Pipe for house connection 27/5 3
DN068CHCOREN1080 Marker post for house connection 27/5 4
Foul 34/1/27/27/8 (465 LM, 17 MH) 390
PipeLine Works (465 LM) 26
DN068CPIPEXC370 Excavation for sewer pipeline 27/8 11
DN068CPIPBED470 Geotextile and Bedding for sewer pipeline 27/8 11
DN068CPIPLAY570 Pipe Laying for sewer pipeline 27/8 11
DN068CPIPPBF670 Partial Backfill for sewer pipeline 27/8 11
DN068CPIPTES770 Test for sewer pipeline 27/8 11
DN068CPIPFBF870 Final Backfill for sewer pipeline 27/8 11
Manhole Works (17 M.H.) 340
DN068CMHLEXC380 Excavation works for manhole 27/8 14
DN068CMHLBLI480 Blinding for manhole 27/8 14
DN068CMHLTAP580 Tanking membrane and protection for manhole 27/8 14
DN068CMHLBAS680 Base slab for manhole 27/8 14
DN068CMHLGRP1080 GRP liner for manhole 27/8 14
DN068CMHLWCP780 Wall concrete and pipe for manhole 27/8 14
DN068CMHLCOV880 Cover slab for manhole 27/8 14
DN068CMHLEMB1180 External tanking membrane and protection for manhole 27/8 14
DN068CMHLDIC1540 DI cover for manhole 27/8 14
DN068CMHLBAC1200 Backfilling for manhole 27/8 14
DN068CMHLDIC1550 Ladder for manhole 27/8 12
DN068CMHLDIC1560 Reinstatement works 27/8 18
Upsizing from 200mm to 400mm - 34/1/27/27/8-8/1 173
PipeLine Works (40.42 LM) 16
DN068CPIPEXC480 Excavation for sewer pipeline 27/8-8/1 5
DN068CPIPBED580 Geotextile and Bedding for sewer pipeline 27/8-8/1 1
DN068CPIPLAY680 Pipe Laying for sewer pipeline 27/8-8/1 1
DN068CPIPPBF780 Partial Backfill for sewer pipeline 27/8-8/1 1
DN068CPIPTES880 Test for sewer pipeline 27/8-8/1 1
DN068CPIPFBF980 Final Backfill for sewer pipeline 27/8-8/1 2
Manhole Works (1 M.H.) 173
DN068CMHLEXC490 Excavation works for manhole 27/8/1 and Demolition of back drop 3
DN068CMHLBLI590 Blinding for manhole 27/8/1 1
DN068CMHLTAP690 Tanking membrane and protection for manhole 27/8/1 1
DN068CMHLBAS790 Base slab for manhole 27/8/1 2
DN068CMHLGRP1190 GRP liner for manhole 27/8/1 2
DN068CMHLWCP890 Wall concrete and pipe for manhole 27/8/1 2
DN068CMHLCOV990 Cover slab for manhole27/8/1 0
DN068CMHLEMB1290 External tanking membrane and protection for manhole 27/8/1 1
DN068CMHLDIC1870 DI cover for manhole 27/8/1 2
DN068CMHLBAC1310 Backfilling for manhole 27/8/1 1
DN068CMHLDIC1880 Ladder for manhole 27/8/1 1
DN068CMHLDIC1890 Reinstatement works 27/8/1 2
House Connection Works (15D, 14ABC) 134
DN068CHCOEXC470 Excavation for pipeline and inspection chamber 27/8 10
DN068CHCOPIP570 Pipe laying for house connection 27/8 10
DN068CHCOBAC970 Backfilling for house connection 27/8 10
DN068CHCODEM370 Demolition for existing underground structure 27/8 10
DN068CHCOBAS670 Base for inspection chamber 27/8 10
DN068CHCOWAL770 Wall for inspection chamber 27/8 10
DN068CHCOFIN1170 Finishing for inspection chamber 27/8 10
DN068CHCOCOV870 Cover for inspection chamber 27/8 10
DN068CHCOREN1070 Reinstatement work for house connection 27/8 12
Foul 34/1/27/27/10 (521 LM, 23 MH) 384
PipeLine Works (521 LM) 27
DN068CPIPEXC360 Excavation for sewer pipeline 27/10 12
DN068CPIPBED460 Geotextile and Bedding for sewer pipeline 27/10 12
DN068CPIPLAY560 Pipe Laying for sewer pipeline 27/10 12
DN068CPIPPBF660 Partial Backfill for sewer pipeline 27/10 12
DN068CPIPTES760 Test for sewer pipeline 27/10 12
DN068CPIPFBF860 Final Backfill for sewer pipeline 27/10 12
Manhole Works (23 M.H.) 379
DN068CMHLEXC370 Excavation works for manhole 27/10 20
DN068CMHLBLI470 Blinding for manhole 27/10 20
DN068CMHLTAP570 Tanking membrane and protection for manhole 27/10 20
DN068CMHLBAS670 Base slab for manhole 27/10 20
DN068CMHLGRP1070 GRP liner for manhole 27/10 20
DN068CMHLWCP770 Wall concrete and pipe for manhole 27/10 20
DN068CMHLEMB1170 External tanking membrane and protection for manhole 27/10 20
DN068CMHLCOV870 Cover slab for manhole 27/10 20
DN068CMHLDIC1510 DI cover for manhole 27/10 20
DN068CMHLBAC1190 Backfilling for manhole 27/10 20
DN068CMHLDIC1520 Ladder for manhole 27/10 18
DN068CMHLDIC1530 Reinstatement works 27/10 22
Upsizing from 200mm to 400mm - 34/1/27/27/10-10/1 136
PipeLine Works (44 LM) 26
DN068CPIPEXC490 Excavation for sewer pipeline 27/10-10/1 5
DN068CPIPBED590 Geotextile and Bedding for sewer pipeline 27/10-10/1 1
DN068CPIPLAY690 Pipe Laying for sewer pipeline 27/10-10/1 1
DN068CPIPPBF790 Partial Backfill for sewer pipeline 27/10-10/1 1
DN068CPIPTES890 Test for sewer pipeline 27/10-10/1 1
DN068CPIPFBF990 Final Backfill for sewer pipeline 27/10-10/1 2
Manhole Works (1 M.H.) 129
DN068CMHLEXC500 Excavation works for manhole 27/10/1 and Demolition of back drop 3
DN068CMHLBLI600 Blinding for manhole 27/10/1 1
DN068CMHLTAP700 Tanking membrane and protection for manhole 27/10/1 1
DN068CMHLBAS800 Base slab for manhole 27/10/1 2
DN068CMHLGRP1200 GRP liner for manhole 27/10/1 2
DN068CMHLWCP900 Wall concrete and pipe for manhole 27/10/1 2
DN068CMHLEMB1300 External tanking membrane and protection for manhole 27/10/1 2
DN068CMHLBAC1320 Backfilling for manhole 27/10/1 3
DN068CMHLCOV1000 Cover slab for manhole 27/10/1 2
DN068CMHLDIC1900 DI cover for manhole 27/10/1 2
DN068CMHLDIC1910 Ladder for manhole 27/10/1 1
DN068CMHLDIC1920 Reinstatement works 27/10/1 2
House Connection Works (18D, 23ABC) 145
DN068CHCOEXC460 Excavation for pipeline and inspection chamber 27/10 15
DN068CHCOPIP560 Pipe laying for house connection 27/10 15
DN068CHCOBAC960 Backfilling for house connection 27/10 15
DN068CHCODEM360 Demolition for existing underground structure 27/10 15
DN068CHCOBAS660 Base for inspection chamber 27/10 15
DN068CHCOWAL760 Wall for inspection chamber 27/10 15
DN068CHCOFIN1160 Finishing for inspection chamber 27/10 15
DN068CHCOCOV860 Cover for inspection chamber 27/10 15
DN068CHCOREN1060 Reinstatement work for house connection 27/10 18
Foul 34/1/27/27/11 (241 LM, 7 MH) 314
PipeLine Works (241 LM) 13
DN068CPIPEXC350 Excavation for sewer pipeline 27/11 6
DN068CPIPBED450 Geotextile and Bedding for sewer pipeline 27/11 6
DN068CPIPLAY550 Pipe Laying for sewer pipeline 27/11 6
DN068CPIPTES750 Test for sewer pipeline 27/11 6
DN068CPIPPBF650 Partial Backfill for sewer pipeline 27/11 6
DN068CPIPFBF850 Final Backfill for sewer pipeline 27/11 6
Manhole Works (7 M.H.) 33
DN068CMHLEXC360 Excavation works for manhole 27/11 6
DN068CMHLBLI460 Blinding for manhole 27/11 6
DN068CMHLTAP560 Tanking membrane and protection for manhole 27/11 6
DN068CMHLBAS660 Base slab for manhole 27/11 6
DN068CMHLGRP1060 GRP liner for manhole 27/11 6
DN068CMHLWCP760 Wall concrete and pipe for manhole 27/11 6
DN068CMHLEMB1160 External tanking membrane and protection for manhole 27/11 6
DN068CMHLBAC1180 Backfilling for manhole 27/11 6
DN068CMHLCOV860 Cover slab for manhole 27/11 6
DN068CMHLDIC1500 Reinstatement works 27/11 9
DN068CMHLDIC1480 DI cover for manhole 27/11 6
DN068CMHLDIC1490 Ladder for manhole 27/11 6
House Connection Works (4D, 9ABC) 291
DN068CHCOEXC450 Excavation for pipeline and inspection chamber 27/11 5
DN068CHCOPIP550 Pipe laying for house connection 27/11 5
DN068CHCOBAC950 Backfilling for house connection 27/11 5
DN068CHCODEM350 Demolition for existing underground structure 27/11 5
DN068CHCOBAS650 Base for inspection chamber 27/11 5
DN068CHCOWAL750 Wall for inspection chamber 27/11 5
DN068CHCOCOV850 Cover for inspection chamber 27/11 5
DN068CHCOREN1050 Reinstatement work for house connection 27/11 8
DN068CHCOFIN1150 Finishing for inspection chamber 27/11 5
Foul 34/1/27/27/12 (522 LM, 23 HM) 366
PipeLine Works (522 LM) 26
DN068CPIPEXC340 Excavation for sewer pipeline 27/12 12
DN068CPIPBED440 Geotextile and Bedding for sewer pipeline 27/12 12
DN068CPIPLAY540 Pipe Laying for sewer pipeline 27/12 12
DN068CPIPTES740 Test for sewer pipeline 27/12 12
DN068CPIPPBF640 Partial Backfill for sewer pipeline 27/12 12
DN068CPIPFBF840 Final Backfill for sewer pipeline 27/12 12
Manhole Works (23 M.H.) 364
DN068CMHLEXC350 Excavation works for manhole 27/12 19
DN068CMHLBLI450 Blinding for manhole 27/12 19
DN068CMHLTAP550 Tanking membrane and protection for manhole 27/12 19
DN068CMHLBAS650 Base slab for manhole 27/12 19
DN068CMHLGRP1050 GRP liner for manhole 27/12 19
DN068CMHLWCP750 Wall concrete and pipe for manhole 27/12 19
DN068CMHLCOV850 Cover slab for manhole 27/12 19
DN068CMHLEMB1150 External tanking membrane and protection for manhole 27/12 19
DN068CMHLDIC1450 DI cover for manhole 27/12 19
DN068CMHLBAC1170 Backfilling for manhole 27/12 19
DN068CMHLDIC1460 Ladder for manhole 27/12 17
DN068CMHLDIC1470 Reinstatement works 27/12 22
Upsizing from 200mm to 400mm - 34/1/27/27/12-12/1 125
PipeLine Works (45.65 LM) 36
DN068CPIPEXC500 Excavation for sewer pipeline 27/12-12/1 5
DN068CPIPBED600 Geotextile and Bedding for sewer pipeline 27/12-12/1 1
DN068CPIPLAY700 Pipe Laying for sewer pipeline 27/12-12/1 1
DN068CPIPTES900 Test for sewer pipeline 27/12-12/1 1
DN068CPIPPBF800 Partial Backfill for sewer pipeline 27/12-12/1 1
DN068CPIPFBF1000 Final Backfill for sewer pipeline 27/12-12/1 3
Manhole Works (1 M.H.) 125
DN068CMHLEXC510 Excavation works for manhole 27/12/1 and Demolition of back drop 3
DN068CMHLBLI610 Blinding for manhole 27/12/1 1
DN068CMHLTAP710 Tanking membrane and protection for manhole 27/12/1 1
DN068CMHLBAS810 Base slab for manhole 27/12/1 2
DN068CMHLGRP1210 GRP liner for manhole 27/12/1 2
DN068CMHLWCP910 Wall concrete and pipe for manhole 27/12/1 2
DN068CMHLCOV1010 Cover slab for manhole 27/12/1 2
DN068CMHLEMB1310 External tanking membrane and protection for manhole 27/12/1 2
DN068CMHLDIC1930 DI cover for manhole 27/12/1 2
DN068CMHLBAC1330 Backfilling for manhole 27/12/1 3
DN068CMHLDIC1940 Ladder for manhole 27/12/1 1
DN068CMHLDIC1950 Reinstatement works 27/12/1 2
House Connection Works (10D, 29ABC) 97
DN068CHCOEXC440 Excavation for pipeline and inspection chamber 27/12/1 15
DN068CHCOPIP540 Pipe laying for house connection 27/12/1 15
DN068CHCOBAC940 Backfilling for house connection 2712/1 15
DN068CHCODEM340 Demolition for existing underground structure 27/12/1 15
DN068CHCOBAS640 Base for inspection chamber 27/12/1 15
DN068CHCOWAL740 Wall for inspection chamber 27/12/1 15
DN068CHCOFIN1140 Finishing for inspection chamber 2712/1 15
DN068CHCOCOV840 Cover for inspection chamber 2712/1 15
DN068CHCOREN1040 Reinstatement work for house connection 2712/1 11
Foul 34/1/27/27/14 (509 LM, 22 MH) 305
PipeLine Works (509 LM) 26
DN068CPIPEXC330 Excavation for sewer pipeline 27/14 12
DN068CPIPBED430 Geotextile and Bedding for sewer pipeline 27/14 12
DN068CPIPLAY530 Pipe Laying for sewer pipeline 27/14 12
DN068CPIPPBF630 Partial Backfill for sewer pipeline 27/14 12
DN068CPIPTES730 Test for sewer pipeline 27/14 12
DN068CPIPFBF830 Final Backfill for sewer pipeline 27/14 12
Manhole Works (22 M.H.) 278
DN068CMHLEXC340 Excavation works for manhole 27/14 18
DN068CMHLBLI440 Blinding for manhole 27/14 18
DN068CMHLTAP540 Tanking membrane and protection for manhole 27/14 18
DN068CMHLBAS640 Base slab for manhole 27/14 18
DN068CMHLGRP1040 GRP liner for manhole 27/14 18
DN068CMHLWCP740 Wall concrete and pipe for manhole 27/14 18
DN068CMHLCOV840 Cover slab for manhole 27/14 18
DN068CMHLDIC1420 DI cover for manhole 27/14 18
DN068CMHLEMB1140 External tanking membrane and protection for manhole 27/14 18
DN068CMHLBAC1160 Backfilling for manhole 27/14 18
DN068CMHLDIC1430 Ladder for manhole 27/14 16
DN068CMHLDIC1440 Reinstatement works 27/14 20
Upsizing from 200mm to 400mm - 34/1/27/27/14-14/1 71
PipeLine Works (66.95LM) 32
DN068CPIPEXC510 Excavation for sewer pipeline 27/14-14/1 6
DN068CPIPBED610 Geotextile and Bedding for sewer pipeline 27/14-14/1 1
DN068CPIPLAY710 Pipe Laying for sewer pipeline 27/14-14/1 2
DN068CPIPPBF810 Partial Backfill for sewer pipeline 27/14-14/1 2
DN068CPIPTES910 Test for sewer pipeline 27/14-14/1 2
DN068CPIPFBF1010 Final Backfill for sewer pipeline 27/14-14/1 5
Manhole Works (1 M.H.) 31
DN068CMHLEXC520 Excavation works for manhole 27/14/1 and Demolition of back drop 3
DN068CMHLBLI620 Blinding for manhole 27/14/1 1
DN068CMHLTAP720 Tanking membrane and protection for manhole 27/14/1 1
DN068CMHLBAS820 Base slab for manhole 27/14/1 2
DN068CMHLGRP1220 GRP liner for manhole 27/14/1 2
DN068CMHLWCP920 Wall concrete and pipe for manhole 27/14/1 2
DN068CMHLCOV1020 Cover slab for manhole 27/14/1 2
DN068CMHLEMB1320 External tanking membrane and protection for manhole 27/14/1 2
DN068CMHLDIC1960 DI cover for manhole 27/14/1 2
DN068CMHLBAC1340 Backfilling for manhole 27/14/1 3
DN068CMHLDIC1970 Ladder for manhole 27/14/1 1
DN068CMHLDIC1980 Reinstatement works 27/14/1 2
House Connection Works (8D, 32ABC) 84
DN068CHCOEXC430 Excavation for pipeline and inspection chamber 27/14 15
DN068CHCOPIP530 Pipe laying for house connection 27/14 15
DN068CHCOBAC930 Backfilling for house connection 27/14 17
DN068CHCODEM330 Demolition for existing underground structure 27/14 15
DN068CHCOBAS630 Base for inspection chamber 27/14 15
DN068CHCOWAL730 Wall for inspection chamber 27/14 15
DN068CHCOFIN1130 Finishing for inspection chamber 27/14 15
DN068CHCOCOV830 Cover for inspection chamber 27/14 16
DN068CHCOREN1030 Reinstatement work 27/14 18
Foul 34/1/27/27/16 (532 LM, 21 MH) 274
PipeLine Works (532 LM) 28
DN068CPIPEXC320 Excavation for sewer pipeline 27/16 13
DN068CPIPBED420 Geotextile and Bedding for sewer pipeline 27/16 13
DN068CPIPLAY520 Pipe Laying for sewer pipeline 27/16 13
DN068CPIPPBF620 Partial Backfill for sewer pipeline 27/16 13
DN068CPIPTES720 Test for sewer pipeline 27/16 13
DN068CPIPFBF820 Final Backfill for sewer pipeline 27/16 13
Manhole Works (21 M.H.) 240
DN068CMHLEXC330 Excavation works for manhole 27/16 17
DN068CMHLBLI430 Blinding for manhole 27/16 17
DN068CMHLTAP530 Tanking membrane and protection for manhole 27/16 17
DN068CMHLBAS630 Base slab for manhole 27/16 17
DN068CMHLGRP1030 GRP liner for manhole 27/16 17
DN068CMHLWCP730 Wall concrete and pipe for manhole 27/16 17
DN068CMHLCOV830 Cover slab for manhole 27/16 17
DN068CMHLDIC1390 DI cover for manhole 27/16 17
DN068CMHLEMB1130 External tanking membrane and protection for manhole 27/16 17
DN068CMHLBAC1150 Backfilling for manhole 27/16 17
DN068CMHLDIC1400 Ladder for manhole 27/16 15
DN068CMHLDIC1410 Reinstatement works 27/16 17
Upsizing from 200mm to 400mm - 34/1/27/27/16-16/1 102
PipeLine Works (53.13LM) 16
DN068CPIPEXC520 Excavation for sewer pipeline 27/16-16/1 5
DN068CPIPBED620 Geotextile and Bedding for sewer pipeline 27/16-16/1 1
DN068CPIPLAY720 Pipe Laying for sewer pipeline 27/16-16/1 2
DN068CPIPPBF820 Partial Backfill for sewer pipeline 27/16-16/1 1
DN068CPIPTES920 Test for sewer pipeline 27/16-16/1 1
DN068CPIPFBF1020 Final Backfill for sewer pipeline 27/16-16/1 3
Manhole Works (1 M.H.) 102
DN068CMHLEXC530 Excavation works for manhole 27/16/1 and Demolition of back drop 3
DN068CMHLBLI630 Blinding for manhole 27/16/1 1
DN068CMHLTAP730 Tanking membrane and protection for manhole 27/16/1 1
DN068CMHLBAS830 Base slab for manhole 27/16/1 2
DN068CMHLGRP1230 GRP liner for manhole 27/16/1 2
DN068CMHLWCP930 Wall concrete and pipe for manhole 27/16/1 2
DN068CMHLCOV1030 Cover slab for manhole 27/16/1 2
DN068CMHLEMB1330 External tanking membrane and protection for manhole 27/16/1 2
DN068CMHLDIC1990 DI cover for manhole 27/16/1 2
DN068CMHLBAC1350 Backfilling for manhole 27/16/1 3
DN068CMHLDIC2000 Ladder for manhole 27/16/1 1
DN068CMHLDIC2010 Reinstatement works 27/16/1 2
House Connection Works (8D, 20ABC) 57
DN068CHCOEXC420 Excavation for pipeline and inspection chamber 27/16 10
DN068CHCOPIP520 Pipe laying for house connection 27/16 10
DN068CHCOBAC920 Backfilling for house connection 27/16 12
DN068CHCODEM320 Demolition for existing underground structure 27/16 10
DN068CHCOBAS620 Base for inspection chamber 27/16 10
DN068CHCOWAL720 Wall for inspection chamber 27/16 10
DN068CHCOCOV820 Cover for inspection chamber 27/16 12
DN068CHCOREN1020 Reinstatement work for house connection 27/16 10
DN068CHCOFIN1120 Finishing for inspection chamber 27/16 10
Foul 34/1/27/27/17 (439 LM, 15 MH) 266
PipeLine Works (439 LM) 25
DN068CPIPEXC310 Excavation for sewer pipeline 27/17 11
DN068CPIPBED410 Geotextile and Bedding for sewer pipeline 27/17 11
DN068CPIPLAY510 Pipe Laying for sewer pipeline 27/17 11
DN068CPIPPBF610 Partial Backfill for sewer pipeline 27/17 11
DN068CPIPTES710 Test for sewer pipeline 27/17 11
DN068CPIPFBF810 Final Backfill for sewer pipeline 27/17 11
Manhole Works (15 M.H.) 51
DN068CMHLEXC320 Excavation works for manhole 27/17 12
DN068CMHLBLI420 Blinding for manhole 27/17 12
DN068CMHLTAP520 Tanking membrane and protection for manhole 27/17 12
DN068CMHLBAS620 Base slab for manhole 27/17 12
DN068CMHLGRP1020 GRP liner for manhole 27/17 12
DN068CMHLWCP720 Wall concrete and pipe for manhole 27/17 12
DN068CMHLBAC1140 Backfilling for manhole 27/17 12
DN068CMHLCOV820 Cover slab for manhole 27/17 12
DN068CMHLDIC1360 DI cover for manhole 27/17 12
DN068CMHLEMB1120 External tanking membrane and protection for manhole 27/17 12
DN068CMHLDIC1370 Ladder for manhole 27/17 10
DN068CMHLDIC1380 Reinstatement works 27/17 12
House Connection Works (17D, 4ABC) 238
DN068CHCOEXC410 Excavation for pipeline and inspection chamber 27/17 7
DN068CHCOPIP510 Pipe laying for house connection 27/17 7
DN068CHCODEM310 Demolition for existing underground structure 27/17 7
DN068CHCOBAS610 Base for inspection chamber 27/17 7
DN068CHCOWAL710 Wall for inspection chamber 27/17 7
DN068CHCOFIN1110 Finishing for inspection chamber 27/17 7
DN068CHCOCOV810 Cover for inspection chamber 27/17 7
DN068CHCOBAC910 Backfilling for house connection 27/17 7
DN068CHCOREN1010 Reinstatement work 27/17 7
Foul 34/1/27/27/19 (243 LM, 8 MH) 247
PipeLine Works (243 LM) 13
DN068CPIPEXC300 Excavation for sewer pipeline 27/19 6
DN068CPIPBED400 Geotextile and Bedding for sewer pipeline 6
DN068CPIPLAY500 Pipe Laying for sewer pipeline 27/19 6
DN068CPIPTES700 Test for sewer pipeline 27/19 6
DN068CPIPPBF600 Partial Backfill for sewer pipeline 27/19 6
DN068CPIPFBF800 Final Backfill for sewer pipeline 27/19 6
Manhole Works (8 M.H.) 201
DN068CMHLEXC310 Excavation works for manhole 27/19 7
DN068CMHLBLI410 Blinding for manhole 27/19 7
DN068CMHLTAP510 Tanking membrane and protection for manhole 27/19 7
DN068CMHLBAS610 Base slab for manhole 27/19 7
DN068CMHLGRP1010 GRP liner for manhole 27/19 7
DN068CMHLWCP710 Wall concrete and pipe for manhole 27/19 7
DN068CMHLCOV810 Cover slab for manhole 27/19 7
DN068CMHLEMB1110 External tanking membrane and protection for manhole 27/19 7
DN068CMHLDIC1330 DI cover for manhole 27/19 7
DN068CMHLBAC1130 Backfilling for manhole 27/19 7
DN068CMHLDIC1340 Ladder for manhole 27/19 5
DN068CMHLDIC1350 Reinstatement works 27/19 7
Upsizing from 200mm to 400mm - 34/1/27/27/19-19/1 63
PipeLine Works (50.6 LM) 17
DN068CPIPEXC530 Excavation for sewer pipeline 27/19-19/1 5
DN068CPIPBED630 Geotextile and Bedding for sewer pipeline 1
DN068CPIPLAY730 Pipe Laying for sewer pipeline 27/19-19/1 1
DN068CPIPPBF830 Partial Backfill for sewer pipeline 27/19-19/1 1
DN068CPIPTES930 Test for sewer pipeline 27/19-19/1 1
DN068CPIPFBF1030 Final Backfill for sewer pipeline 27/19-19/1 3
Manhole Works (2 M.H.) 63
DN068CMHLEXC540 Excavation works for manhole 27/19/1 and Demolition of back drop 4
DN068CMHLBLI640 Blinding for manhole 27/19/1 2
DN068CMHLTAP740 Tanking membrane and protection for manhole 27/19/1 2
DN068CMHLBAS840 Base slab for manhole 27/19/1 4
DN068CMHLGRP1240 GRP liner for manhole 27/19/1 2
DN068CMHLWCP940 Wall concrete and pipe for manhole 27/19/1 4
DN068CMHLCOV1040 Cover slab for manhole 27/19/1 2
DN068CMHLDIC2030 Ladder for manhole 27/19/1 2
DN068CMHLDIC2020 DI cover for manhole 27/19/1 2
DN068CMHLEMB1340 External tanking membrane and protection for manhole 27/19/1 2
DN068CMHLBAC1360 Backfilling for manhole 27/19/1 4
DN068CMHLDIC2040 Reinstatement works 27/19/1 2
House Connection Works (5D, 5ABC) 143
DN068CHCOEXC400 Excavation for pipeline and inspection chamber 27/19 4
DN068CHCOPIP500 Pipe laying for house connection 27/19 4
DN068CHCOBAC900 Backfilling for house connection 27/19 5
DN068CHCODEM300 Demolition for existing underground structure 27/19 4
DN068CHCOBAS600 Base for inspection chamber 27/19 5
DN068CHCOWAL700 Wall for inspection chamber 27/19 5
DN068CHCOFIN1100 Finishing for inspection chamber 27/19 4
DN068CHCOCOV800 Cover for inspection chamber 27/19 5
DN068CHCOREN1000 Reinstatement work 27/19 6
Foul 34/1/27/27/23 (216 LM, 8 MH) 226
PipeLine Works (216 LM) 12
DN068CPIPEXC290 Excavation for sewer pipeline 27/23 5
DN068CPIPBED390 Geotextile and Bedding for sewer pipeline 27/23 5
DN068CPIPLAY490 Pipe Laying for sewer pipeline 27/23 5
DN068CPIPPBF590 Partial Backfill for sewer pipeline 27/23 5
DN068CPIPTES690 Test for sewer pipeline 27/23 5
DN068CPIPFBF790 Final Backfill for sewer pipeline 27/23 5
Manhole Works (8 M.H.) 31
DN068CMHLEXC300 Excavation works for manhole 27/23 7
DN068CMHLBLI400 Blinding for manhole 27/23 7
DN068CMHLTAP500 Tanking membrane and protection for manhole 27/23 7
DN068CMHLBAS600 Base slab for manhole 27/23 7
DN068CMHLGRP1000 GRP liner for manhole 27/23 7
DN068CMHLWCP700 Wall concrete and pipe for manhole 27/23 7
DN068CMHLCOV800 Cover slab for manhole 27/23 7
DN068CMHLDIC1300 DI cover for manhole 27/23 7
DN068CMHLEMB1100 External tanking membrane and protection for manhole 27/23 7
DN068CMHLBAC1120 Backfilling for manhole 27/23 7
DN068CMHLDIC1310 Ladder for manhole 27/23 5
DN068CMHLDIC1320 Reinstatement works 27/23 7
House Connection Works (12D, 3ABC) 205
DN068CHCOEXC390 Excavation for pipeline and inspection chamber 27/23 5
DN068CHCOPIP490 Pipe laying for house connection 27/23 5
DN068CHCOBAC890 Backfilling for house connection 27/23 5
DN068CHCODEM290 Demolition for existing underground structure 27/23 5
DN068CHCOBAS590 Base for inspection chamber 27/23 5
DN068CHCOWAL690 Wall for inspection chamber 27/23 5
DN068CHCOFIN1090 Finishing for inspection chamber 27/23 5
DN068CHCOCOV790 Cover for inspection chamber 27/23 5
DN068CHCOREN990 Reinstatement work for house connection 27/23 6
Handing Over 9
DN068HALPASB100 As Built Drawingss 7
DN068HALPHAV200 Demobilisation 7
Activity % Schedule %Performan Start Finish Total Float BL1 Start
100.00% 99.00% 26-Mar-12 A 14-Feb-15 -183.00 1-May-12
100.00% 95.50% 01-May-12 A 14-Feb-15 -195.00 1-May-12
0% 0% 01-May-12 A 14-Feb-15 -195.00 1-May-12
100% 100% 100% 01-May-12 A 1-May-12
94.6% 100% 95% 01-May-12 A 14-Feb-15 -195.00 1-May-12
0% 100% 0% 14-Feb-15* -161.00
100% 96% 01-May-12 A 14-Feb-15 -195.00 1-May-12
95% 100% 95% 01-May-12 A 14-Feb-15 -195.00 1-May-12
100% 100% 100% 01-May-12 A 02-Mar-13 A 1-May-12
100% 100% 100% 01-May-12 A 02-Mar-13 A 1-May-12
95% 100% 95% 01-May-12 A 14-Feb-15 -195.00 1-May-12
95% 100% 95% 01-May-12 A 14-Feb-15 -195.00 1-May-12
94% 100% 94% 06-Jun-12 A 14-Feb-15 -161.00 7-Jun-12
0% 0% 26-Mar-12 A 14-Feb-15 -195.00 1-May-12
0% 0% 26-Mar-12 A 29-Aug-14 A 1-May-12
0% 0% 26-Mar-12 A 25-Aug-14 A 1-May-12
100% 100% 100% 26-Mar-12 A 01-May-12 A 14-May-12
100% 100% 100% 26-Mar-12 A 01-Apr-12 A 1-May-12
100% 100% 100% 16-Apr-12 A 07-May-12 A 1-May-12
100% 100% 100% 21-May-12 A 25-Aug-14 A 1-May-12
0% 0% 01-May-12 A 29-Aug-14 A 13-May-12
100% 100% 100% 01-May-12 A 09-May-12 A 24-May-12
100% 100% 100% 16-Jun-12 A 17-Dec-12 A 26-May-12
100% 100% 100% 16-Jun-12 A 27-Dec-12 A 13-May-12
100% 100% 100% 26-Sep-12 A 29-Aug-14 A 13-May-12
0% 0% 28-Apr-12 A 17-May-12 A 9-May-12
100% 100% 100% 28-Apr-12 A 28-Apr-12 A 20-May-12
100% 100% 100% 05-May-12 A 17-May-12 A 9-May-12
100% 100% 100% 17-May-12 A 17-May-12 A 24-May-12
100% 100% 100% 17-May-12 A 17-May-12 A 24-May-12
0% 0% 28-Apr-12 A 20-May-12 A 14-May-12
100% 100% 100% 28-Apr-12 A 10-May-12 A 31-May-12
100% 100% 100% 17-May-12 A 20-May-12 A 26-Jun-12
100% 100% 100% 17-May-12 A 20-May-12 A 14-May-12
100% 100% 100% 17-May-12 A 20-May-12 A 26-Jun-12
0% 0% 05-Aug-12 A 14-Feb-15 -195.00 5-Aug-12
100% 100% 100% 05-Aug-12 A 06-Jun-13 A 5-Aug-12
93% 100% 93% 02-Sep-12 A 14-Feb-15 -128.00 3-Sep-12
0% 0% 01-May-12 A 2-Feb-15 -200.00 7-May-12
0% 0% 24-May-12 A 08-Jul-12 A 13-May-12
100% 100% 100% 24-May-12 A 26-May-12 A 13-May-12
100% 100% 100% 24-May-12 A 26-May-12 A 7-Jun-12
100% 100% 100% 24-May-12 A 26-May-12 A 13-May-12
100% 100% 100% 29-May-12 A 18-Jun-12 A 19-May-12
100% 100% 100% 05-Jul-12 A 05-Jul-12 A 7-Jun-12
100% 100% 100% 07-Jul-12 A 08-Jul-12 A 24-May-12
0% 0% 26-May-12 A 09-Mar-14 A 27-May-12
100% 100% 100% 26-May-12 A 07-Jul-12 A 27-May-12
100% 100% 100% 26-May-12 A 08-Jul-12 A 16-Jul-12
100% 100% 100% 26-May-12 A 18-Jul-12 A 27-May-12
100% 100% 100% 18-Jun-12 A 09-Mar-14 A 2-Jun-12
100% 100% 100% 08-Jul-12 A 02-Aug-12 A 16-Jul-12
100% 100% 100% 08-Jul-12 A 18-Jul-12 A 14-Jun-12
0% 0% 01-May-12 A 12-Jan-15 -180.00 7-May-12
100% 100% 100% 01-May-12 A 01-May-12 A 7-May-12
100% 100% 100% 01-May-12 A 01-May-12 A 9-May-12
100% 100% 100% 07-May-12 A 10-Jun-12 A 7-May-12
100% 100% 100% 07-May-12 A 08-May-12 A 7-May-12
100% 100% 100% 05-Jun-12 A 05-Jun-12 A 13-May-12
100% 100% 100% 07-Jun-12 A 11-Jun-12 A 7-Jun-12
0% 100% 0% 1-Jan-15 12-Jan-15 -160.00 13-May-12
0% 0% 01-May-12 A 2-Feb-15 -200.00 13-May-12
100% 100% 100% 01-May-12 A 03-May-12 A 13-May-12
100% 100% 100% 01-May-12 A 01-May-12 A 15-May-12
100% 100% 100% 08-May-12 A 07-Jun-12 A 19-May-12
100% 100% 100% 05-Jun-12 A 13-Jun-12 A 19-May-12
100% 100% 100% 05-Jun-12 A 13-Jun-12 A 24-May-12
100% 100% 100% 11-Jun-12 A 08-Sep-12 A 26-Jun-12
0% 100% 0% 13-Jan-15 2-Feb-15 -132.00 24-May-12
0% 0% 02-May-12 A 27-Dec-14 A 2-Jun-12
100% 100% 100% 02-May-12 A 12-Dec-14 A 4-Jun-12
100% 100% 100% 01-Sep-12 A 12-Dec-14 A 2-Jun-12
100% 100% 100% 09-Sep-12 A 27-Oct-14 A 7-Jun-12
100% 100% 100% 10-Sep-12 A 28-Oct-14 A 7-Jun-12
100% 100% 100% 15-Nov-12 A 27-Feb-14 A 17-Jul-12
100% 100% 100% 01-Dec-12 A 27-Dec-14 A 13-Jun-12
100% 100% 100% 10-Jun-14 A 06-Dec-14 A 13-Jun-12
100% 100% 03-May-12 A 14-Feb-15 -183.00 1-May-12
100.00% 100% 03-May-12 A 03-May-14 A 1-May-12
0% 0% 03-May-12 A 22-Apr-13 A 1-May-12
100% 100% 100% 03-May-12 A 14-Jul-12 A 1-May-12
100% 100% 100% 26-May-12 A 08-Sep-12 A 28-May-12
100% 100% 100% 09-Jun-12 A 22-Apr-13 A 28-May-12
100% 100% 12-Sep-12 A 02-Jan-13 A 2-Jul-12
100% 100% 100% 12-Sep-12 A 04-Oct-12 A 2-Jul-12
100% 100% 100% 20-Sep-12 A 04-Oct-12 A 7-Jul-12
100% 100% 100% 22-Sep-12 A 01-Jan-13 A 16-Jul-12
100% 100% 100% 22-Sep-12 A 01-Jan-13 A 8-Jul-12
100% 100% 100% 23-Sep-12 A 02-Jan-13 A 12-Jul-12
100% 100% 100% 29-Sep-12 A 02-Jan-13 A 19-Jul-12
100% 100% 19-Sep-12 A 08-Mar-14 A 4-Jul-12
100% 100% 100% 19-Sep-12 A 29-Sep-12 A 4-Jul-12
100% 100% 100% 20-Sep-12 A 30-Sep-12 A 7-Jul-12
100% 100% 100% 22-Sep-12 A 01-Oct-12 A 8-Jul-12
100% 100% 100% 23-Sep-12 A 01-Oct-12 A 10-Jul-12
100% 100% 100% 01-Oct-12 A 25-Oct-12 A 12-Jul-12
100% 100% 100% 02-Oct-12 A 25-Oct-12 A 14-Jul-12
100% 100% 100% 06-Oct-12 A 25-Oct-12 A 22-Jul-12
100% 100% 100% 06-Oct-12 A 19-Feb-13 A 8-Aug-12
100% 100% 100% 30-Oct-12 A 18-Feb-14 A 28-Jul-12
100% 100% 100% 29-Dec-12 A 02-Jan-13 A 18-Jul-12
100% 100% 100% 29-Dec-12 A 22-Feb-14 A 31-Jul-12
100% 100% 100% 05-Jan-13 A 08-Mar-14 A 19-Jul-12
100% 100% 04-Oct-12 A 03-May-14 A 22-Jul-12
100% 100% 100% 04-Oct-12 A 20-Oct-12 A 22-Jul-12
100% 100% 100% 15-Oct-12 A 02-Mar-14 A 31-Jul-12
100% 100% 100% 18-Oct-12 A 03-Mar-14 A 11-Aug-12
100% 100% 100% 01-May-14 A 03-May-14 A 23-Aug-12
100% 100% 12-Nov-12 A 17-Jun-14 A 18-Jul-12
100% 100% 12-Nov-12 A 21-Feb-13 A 18-Jul-12
100% 100% 100% 12-Nov-12 A 30-Jan-13 A 18-Jul-12
100% 100% 100% 02-Dec-12 A 09-Feb-13 A 24-Jul-12
100% 100% 100% 03-Dec-12 A 10-Feb-13 A 30-Jul-12
100% 100% 100% 03-Dec-12 A 11-Feb-13 A 5-Aug-12
100% 100% 100% 04-Dec-12 A 11-Feb-13 A 11-Aug-12
100% 100% 100% 04-Dec-12 A 21-Feb-13 A 16-Aug-12
100% 100% 01-Dec-12 A 07-Apr-13 A 19-Jul-12
100% 100% 100% 01-Dec-12 A 06-Feb-13 A 19-Jul-12
100% 100% 100% 02-Dec-12 A 09-Feb-13 A 24-Jul-12
100% 100% 100% 03-Dec-12 A 10-Feb-13 A 28-Jul-12
100% 100% 100% 04-Dec-12 A 11-Feb-13 A 31-Jul-12
100% 100% 100% 08-Dec-12 A 11-Feb-13 A 5-Aug-12
100% 100% 100% 10-Dec-12 A 13-Feb-13 A 8-Aug-12
100% 100% 100% 13-Dec-12 A 11-Feb-13 A 23-Aug-12
100% 100% 100% 02-Jan-13 A 21-Feb-13 A 26-Aug-12
100% 100% 100% 12-Jan-13 A 28-Feb-13 A 29-Aug-12
100% 100% 100% 09-Feb-13 A 02-Mar-13 A 12-Aug-12
100% 100% 100% 11-Feb-13 A 02-Mar-13 A 16-Aug-12
100% 100% 100% 19-Mar-13 A 07-Apr-13 A 16-Sep-12
100% 100% 06-Jan-13 A 17-Jun-14 A 5-Sep-12
100% 100% 100% 06-Jan-13 A 02-Jun-14 A 8-Sep-12
100% 100% 100% 16-Feb-13 A 02-Jun-14 A 10-Sep-12
100% 100% 100% 17-Feb-13 A 02-Jun-14 A 22-Sep-12
100% 100% 100% 01-Feb-14 A 04-Jun-14 A 5-Sep-12
100% 100% 100% 02-Feb-14 A 08-Jun-14 A 12-Sep-12
100% 100% 100% 03-Feb-14 A 09-Jun-14 A 15-Sep-12
100% 100% 100% 04-Feb-14 A 10-Jun-14 A 17-Sep-12
100% 100% 100% 05-Feb-14 A 14-Jun-14 A 19-Sep-12
100% 100% 100% 05-Feb-14 A 17-Jun-14 A 27-Sep-12
100% 100% 29-May-12 A 04-Jul-14 A 2-Jul-12
0% 0% 29-May-12 A 28-Jul-12 A 2-Jul-12
100% 100% 100% 29-May-12 A 06-Jun-12 A 31-Jul-12
100% 100% 100% 23-Jul-12 A 28-Jul-12 A 2-Jul-12
100% 100% 06-Sep-12 A 13-Feb-13 A 11-Sep-12
100% 100% 100% 06-Sep-12 A 15-Oct-12 A 11-Sep-12
100% 100% 100% 16-Sep-12 A 13-Jan-13 A 13-Sep-12
100% 100% 100% 16-Sep-12 A 13-Jan-13 A 16-Sep-12
100% 100% 100% 17-Sep-12 A 13-Jan-13 A 20-Sep-12
100% 100% 100% 17-Sep-12 A 11-Feb-13 A 18-Sep-12
100% 100% 100% 25-Sep-12 A 13-Feb-13 A 23-Sep-12
100% 100% 12-Sep-12 A 11-Apr-13 A 12-Sep-12
100% 100% 100% 12-Sep-12 A 25-Oct-12 A 12-Sep-12
100% 100% 100% 15-Sep-12 A 25-Oct-12 A 13-Sep-12
100% 100% 100% 16-Sep-12 A 03-Nov-12 A 15-Sep-12
100% 100% 100% 17-Sep-12 A 06-Nov-12 A 16-Sep-12
100% 100% 100% 11-Nov-12 A 24-Dec-12 A 17-Sep-12
100% 100% 100% 12-Nov-12 A 24-Dec-12 A 18-Sep-12
100% 100% 100% 10-Dec-12 A 25-Dec-12 A 23-Sep-12
100% 100% 100% 27-Dec-12 A 31-Dec-12 A 9-Oct-12
100% 100% 100% 05-Jan-13 A 09-Mar-13 A 26-Sep-12
100% 100% 100% 14-Jan-13 A 30-Mar-13 A 20-Sep-12
100% 100% 100% 15-Jan-13 A 14-Mar-13 A 29-Sep-12
100% 100% 100% 19-Jan-13 A 11-Apr-13 A 22-Sep-12
100% 100% 15-Oct-12 A 04-Jul-14 A 27-Sep-12
100% 100% 100% 15-Oct-12 A 21-Dec-13 A 27-Sep-12
100% 100% 100% 17-Oct-12 A 28-Dec-13 A 21-Oct-12
100% 100% 100% 18-Oct-12 A 30-Dec-13 A 9-Oct-12
100% 100% 100% 10-May-14 A 04-Jul-14 A 5-Nov-12
100% 100% 27-May-12 A 27-Feb-14 A 16-Aug-12
0% 0% 27-May-12 A 25-Jul-12 A 16-Aug-12
100% 100% 100% 27-May-12 A 04-Jun-12 A 29-Aug-12
100% 100% 100% 21-Jul-12 A 25-Jul-12 A 16-Aug-12
100% 100% 30-Jul-12 A 09-Jan-13 A 25-Sep-12
100% 100% 100% 30-Jul-12 A 22-Aug-12 A 25-Sep-12
100% 100% 100% 26-Aug-12 A 04-Sep-12 A 26-Sep-12
100% 100% 100% 27-Aug-12 A 06-Jan-13 A 29-Sep-12
100% 100% 100% 02-Sep-12 A 07-Jan-13 A 30-Sep-12
100% 100% 100% 03-Sep-12 A 07-Jan-13 A 1-Oct-12
100% 100% 100% 10-Sep-12 A 09-Jan-13 A 2-Oct-12
100% 100% 22-Aug-12 A 12-Mar-13 A 26-Sep-12
100% 100% 100% 22-Aug-12 A 29-Aug-12 A 26-Sep-12
100% 100% 100% 26-Aug-12 A 03-Sep-12 A 27-Sep-12
100% 100% 100% 27-Aug-12 A 11-Sep-12 A 29-Sep-12
100% 100% 100% 30-Aug-12 A 12-Sep-12 A 30-Sep-12
100% 100% 100% 26-Sep-12 A 11-Nov-12 A 1-Oct-12
100% 100% 100% 27-Sep-12 A 12-Nov-12 A 2-Oct-12
100% 100% 100% 03-Oct-12 A 04-Dec-12 A 7-Oct-12
100% 100% 100% 15-Oct-12 A 12-Jan-13 A 10-Oct-12
100% 100% 100% 17-Nov-12 A 19-Feb-13 A 13-Oct-12
100% 100% 100% 01-Dec-12 A 21-Feb-13 A 20-Oct-12
100% 100% 100% 06-Jan-13 A 12-Mar-13 A 4-Oct-12
100% 100% 100% 10-Jan-13 A 12-Mar-13 A 6-Oct-12
100% 100% 29-Sep-12 A 27-Feb-14 A 10-Oct-12
100% 100% 100% 29-Sep-12 A 04-Jan-14 A 13-Oct-12
100% 100% 100% 03-Oct-12 A 05-Jan-14 A 15-Oct-12
100% 100% 100% 07-Oct-12 A 06-Jan-14 A 30-Oct-12
100% 100% 100% 22-Feb-14 A 25-Feb-14 A 10-Oct-12
100% 100% 100% 23-Feb-14 A 26-Feb-14 A 17-Oct-12
100% 100% 100% 24-Feb-14 A 27-Feb-14 A 20-Oct-12
100% 100% 100% 25-Feb-14 A 27-Feb-14 A 22-Oct-12
100% 100% 100% 26-Feb-14 A 27-Feb-14 A 24-Oct-12
100% 100% 100% 27-Feb-14 A 27-Feb-14 A 8-Nov-12
100% 100% 02-Jun-12 A 04-May-14 A 5-Sep-12
0% 0% 02-Jun-12 A 28-Jul-12 A 5-Sep-12
100% 100% 100% 02-Jun-12 A 06-Jun-12 A 11-Sep-12
100% 100% 100% 26-Jul-12 A 28-Jul-12 A 5-Sep-12
100% 100% 29-Jul-12 A 13-Nov-12 A 7-Oct-12
100% 100% 100% 29-Jul-12 A 21-Oct-12 A 7-Oct-12
100% 100% 100% 02-Sep-12 A 25-Oct-12 A 9-Oct-12
100% 100% 100% 08-Sep-12 A 25-Oct-12 A 11-Oct-12
100% 100% 100% 09-Sep-12 A 03-Nov-12 A 16-Oct-12
100% 100% 100% 13-Sep-12 A 01-Nov-12 A 14-Oct-12
100% 100% 100% 16-Sep-12 A 13-Nov-12 A 18-Oct-12
100% 100% 22-Aug-12 A 29-Dec-12 A 8-Oct-12
100% 100% 100% 22-Aug-12 A 17-Sep-12 A 8-Oct-12
100% 100% 100% 03-Sep-12 A 11-Nov-12 A 9-Oct-12
100% 100% 100% 09-Sep-12 A 12-Nov-12 A 10-Oct-12
100% 100% 100% 10-Sep-12 A 13-Nov-12 A 11-Oct-12
100% 100% 100% 29-Sep-12 A 09-Dec-12 A 13-Oct-12
100% 100% 100% 30-Sep-12 A 10-Dec-12 A 14-Oct-12
100% 100% 100% 16-Oct-12 A 29-Dec-12 A 22-Oct-12
100% 100% 100% 19-Nov-12 A 29-Dec-12 A 24-Oct-12
100% 100% 100% 24-Nov-12 A 29-Dec-12 A 12-Nov-12
100% 100% 100% 01-Dec-12 A 29-Dec-12 A 18-Oct-12
100% 100% 100% 03-Dec-12 A 27-Dec-12 A 16-Oct-12
100% 100% 100% 13-Dec-12 A 29-Dec-12 A 17-Oct-12
100% 100% 22-Sep-12 A 04-May-14 A 30-Oct-12
100% 100% 100% 22-Sep-12 A 14-Nov-13 A 30-Oct-12
100% 100% 100% 29-Sep-12 A 19-Nov-13 A 13-Nov-12
100% 100% 100% 06-Oct-12 A 23-Nov-13 A 26-Nov-12
100% 100% 100% 01-May-14 A 04-May-14 A 9-Dec-12
100% 99% 03-May-12 A 1-Jan-15 -202.00 22-Jul-12
0% 0% 03-May-12 A 10-Sep-13 A 22-Jul-12
100% 100% 100% 03-May-12 A 14-Jul-12 A 22-Jul-12
100% 100% 100% 16-Jun-12 A 20-Jun-12 A 25-Sep-12
100% 100% 100% 02-Feb-13 A 10-Sep-13 A 8-Sep-12
100% 100% 27-Jan-13 A 12-Sep-13 A 31-Oct-12
100% 100% 100% 27-Jan-13 A 15-Aug-13 A 31-Oct-12
100% 100% 100% 14-Mar-13 A 09-Sep-13 A 4-Nov-12
100% 100% 100% 16-Mar-13 A 09-Sep-13 A 8-Nov-12
100% 100% 100% 18-Mar-13 A 10-Sep-13 A 13-Nov-12
100% 100% 100% 19-Mar-13 A 10-Sep-13 A 18-Nov-12
100% 100% 100% 19-Mar-13 A 12-Sep-13 A 21-Nov-12
100% 100% 26-Feb-13 A 18-Jul-14 A 1-Nov-12
100% 100% 100% 26-Feb-13 A 07-Sep-13 A 1-Nov-12
100% 100% 100% 02-Mar-13 A 07-Sep-13 A 5-Nov-12
100% 100% 100% 03-Mar-13 A 08-Sep-13 A 8-Nov-12
100% 100% 100% 12-Mar-13 A 10-Sep-13 A 12-Nov-12
100% 100% 100% 16-Mar-13 A 19-Sep-13 A 15-Nov-12
100% 100% 100% 17-Mar-13 A 21-Sep-13 A 19-Nov-12
100% 100% 100% 30-Mar-13 A 22-Sep-13 A 27-Nov-12
100% 100% 100% 01-Apr-13 A 23-Sep-13 A 29-Nov-12
100% 100% 100% 20-Apr-13 A 19-Sep-13 A 28-Nov-12
100% 100% 100% 21-Apr-13 A 22-Sep-13 A 22-Nov-12
100% 100% 100% 25-Apr-13 A 23-Sep-13 A 26-Nov-12
100% 100% 100% 09-Jun-13 A 18-Jul-14 A 27-Dec-12
100% 99% 01-May-13 A 1-Jan-15 -170.00 19-Dec-12
100% 100% 100% 01-May-13 A 23-Dec-14 A 24-Dec-12
100% 100% 100% 04-May-13 A 23-Dec-14 A 31-Dec-12
100% 100% 100% 04-May-13 A 23-Dec-14 A 30-Jan-13
98% 100% 98% 01-Feb-14 A 1-Jan-15 -132.00 19-Dec-12
98% 100% 98% 02-Feb-14 A 1-Jan-15 -132.00 7-Jan-13
98% 100% 98% 03-Feb-14 A 1-Jan-15 -132.00 14-Jan-13
98% 100% 98% 05-Feb-14 A 1-Jan-15 -132.00 26-Jan-13
98% 100% 98% 05-Feb-14 A 1-Jan-15 -132.00 19-Jan-13
98% 100% 98% 06-Feb-14 A 1-Jan-15 -132.00 27-Feb-13
100% 100% 09-Jun-12 A 20-Mar-14 A 4-Oct-12
0% 0% 09-Jun-12 A 21-Oct-12 A 4-Oct-12
100% 100% 100% 09-Jun-12 A 20-Jun-12 A 22-Oct-12
100% 100% 100% 15-Oct-12 A 21-Oct-12 A 4-Oct-12
100% 100% 20-Oct-12 A 23-Jul-13 A 27-Nov-12
100% 100% 100% 20-Oct-12 A 13-Jul-13 A 27-Nov-12
100% 100% 100% 04-Nov-12 A 14-Jul-13 A 29-Nov-12
100% 100% 100% 06-Nov-12 A 15-Jul-13 A 2-Dec-12
100% 100% 100% 08-Nov-12 A 15-Jul-13 A 6-Dec-12
100% 100% 100% 08-Nov-12 A 16-Jul-13 A 4-Dec-12
100% 100% 100% 13-Nov-12 A 23-Jul-13 A 10-Dec-12
100% 100% 01-Nov-12 A 05-Jan-14 A 28-Nov-12
100% 100% 100% 01-Nov-12 A 06-Jun-13 A 28-Nov-12
100% 100% 100% 04-Nov-12 A 10-Jun-13 A 1-Dec-12
100% 100% 100% 05-Nov-12 A 13-Jun-13 A 3-Dec-12
100% 100% 100% 11-Nov-12 A 15-Jun-13 A 5-Dec-12
100% 100% 100% 26-Nov-12 A 20-Jun-13 A 8-Dec-12
100% 100% 100% 27-Nov-12 A 20-Jun-13 A 10-Dec-12
100% 100% 100% 29-Dec-12 A 06-Aug-13 A 19-Dec-12
100% 100% 100% 12-Jan-13 A 06-Aug-13 A 24-Dec-12
100% 100% 100% 11-Feb-13 A 07-Aug-13 A 12-Dec-12
100% 100% 100% 14-Feb-13 A 05-Aug-13 A 17-Dec-12
100% 100% 100% 24-Feb-13 A 05-Jan-14 A 10-Jan-13
100% 100% 100% 02-Mar-13 A 19-Aug-13 A 15-Dec-12
100% 100% 15-Jan-13 A 20-Mar-14 A 7-Jan-13
100% 100% 100% 15-Jan-13 A 01-Feb-14 A 20-Jan-13
100% 100% 100% 19-Jan-13 A 02-Feb-14 A 23-Jan-13
100% 100% 100% 21-Jan-13 A 16-Mar-14 A 7-Jan-13
100% 100% 100% 13-Jan-14 A 17-Mar-14 A 27-Jan-13
100% 100% 100% 16-Jan-14 A 18-Mar-14 A 30-Jan-13
100% 100% 100% 18-Jan-14 A 19-Mar-14 A 3-Feb-13
100% 100% 100% 20-Jan-14 A 20-Mar-14 A 6-Feb-13
100% 100% 100% 23-Jan-14 A 06-Feb-14 A 10-Feb-13
100% 100% 100% 26-Jan-14 A 20-Mar-14 A 26-Feb-13
100% 100% 09-Jun-12 A 1-Jan-15 -168.00 10-Nov-12
0% 0% 09-Jun-12 A 02-Oct-13 A 10-Nov-12
100% 100% 100% 09-Jun-12 A 02-Oct-13 A 10-Nov-12
100% 100% 100% 09-Jun-12 A 20-Jun-12 A 15-Nov-12
100% 100% 29-Nov-12 A 06-Nov-13 A 11-Dec-12
100% 100% 100% 29-Nov-12 A 09-Oct-13 A 11-Dec-12
100% 100% 100% 02-Dec-12 A 03-Nov-13 A 15-Dec-12
100% 100% 100% 03-Dec-12 A 04-Nov-13 A 19-Dec-12
100% 100% 100% 04-Dec-12 A 04-Nov-13 A 26-Dec-12
100% 100% 100% 04-Dec-12 A 05-Nov-13 A 23-Dec-12
100% 100% 100% 08-Dec-12 A 06-Nov-13 A 31-Dec-12
100% 100% 01-Dec-12 A 15-Jul-14 A 19-Dec-12
100% 100% 100% 01-Dec-12 A 06-Jun-13 A 19-Dec-12
100% 100% 100% 03-Dec-12 A 22-Aug-13 A 23-Dec-12
100% 100% 100% 04-Dec-12 A 26-Aug-13 A 26-Dec-12
100% 100% 100% 06-Dec-12 A 02-Sep-13 A 30-Dec-12
100% 100% 100% 09-Feb-13 A 07-Sep-13 A 2-Jan-13
100% 100% 100% 11-Feb-13 A 10-Sep-13 A 6-Jan-13
100% 100% 100% 17-Feb-13 A 05-Oct-13 A 15-Jan-13
100% 100% 100% 18-Feb-13 A 06-Oct-13 A 19-Jan-13
100% 100% 100% 27-Feb-13 A 15-Jul-14 A 16-Feb-13
100% 100% 100% 17-Mar-13 A 07-Oct-13 A 10-Jan-13
100% 100% 100% 18-Mar-13 A 08-Oct-13 A 15-Jan-13
100% 100% 100% 13-Apr-13 A 09-Oct-13 A 17-Jan-13
100% 99% 06-May-13 A 1-Jan-15 -168.00 2-Feb-13
100% 100% 100% 06-May-13 A 03-May-14 A 4-Feb-13
100% 100% 100% 08-May-13 A 04-May-14 A 6-Feb-13
100% 100% 100% 11-May-13 A 06-May-14 A 19-Feb-13
98% 100% 98% 01-Feb-14 A 1-Jan-15 -132.00 2-Feb-13
98% 100% 98% 03-Feb-14 A 1-Jan-15 -131.00 9-Feb-13
98% 100% 98% 04-Feb-14 A 1-Jan-15 -131.00 11-Feb-13
98% 100% 98% 04-Feb-14 A 1-Jan-15 -131.00 14-Feb-13
98% 100% 98% 05-Feb-14 A 1-Jan-15 -131.00 17-Feb-13
98% 100% 98% 06-Feb-14 A 1-Jan-15 -131.00 14-Mar-13
100% 100% 03-May-12 A 28-Dec-14 A 1-Oct-12
100% 100% 03-May-12 A 28-Dec-14 A 1-Oct-12
0% 0% 03-May-12 A 31-Dec-13 A 1-Oct-12
100% 100% 100% 03-May-12 A 14-Jul-12 A 1-Oct-12
100% 100% 100% 19-Jun-12 A 29-Dec-13 A 8-Nov-12
100% 100% 100% 24-Jan-13 A 31-Dec-13 A 24-Oct-12
100% 100% 27-Jan-13 A 29-Dec-13 A 8-Jan-13
100% 100% 100% 27-Jan-13 A 14-Mar-13 A 8-Jan-13
100% 100% 100% 19-Feb-13 A 26-Dec-13 A 13-Jan-13
100% 100% 100% 19-Feb-13 A 28-Dec-13 A 17-Jan-13
100% 100% 100% 23-Feb-13 A 29-Dec-13 A 22-Jan-13
100% 100% 100% 24-Feb-13 A 29-Dec-13 A 27-Jan-13
100% 100% 100% 28-Feb-13 A 29-Dec-13 A 31-Jan-13
100% 100% 13-Feb-13 A 15-Jul-14 A 15-Jan-13
100% 100% 100% 13-Feb-13 A 06-Nov-13 A 15-Jan-13
100% 100% 100% 10-Mar-13 A 09-Nov-13 A 20-Jan-13
100% 100% 100% 11-Mar-13 A 09-Nov-13 A 23-Jan-13
100% 100% 100% 12-Mar-13 A 18-Nov-13 A 27-Jan-13
100% 100% 100% 12-Mar-13 A 21-Dec-13 A 30-Jan-13
100% 100% 100% 13-Mar-13 A 22-Dec-13 A 3-Feb-13
100% 100% 100% 16-Mar-13 A 23-Dec-13 A 13-Feb-13
100% 100% 100% 04-Apr-13 A 24-Dec-13 A 16-Feb-13
100% 100% 100% 07-Apr-13 A 15-Jul-14 A 20-Mar-13
100% 100% 100% 26-Oct-13 A 25-Dec-13 A 5-Feb-13
100% 100% 100% 27-Oct-13 A 28-Dec-13 A 7-Feb-13
100% 100% 100% 02-Nov-13 A 28-Dec-13 A 10-Feb-13
100% 100% 04-Apr-13 A 17-Nov-14 A 28-Feb-13
100% 100% 100% 04-Apr-13 A 16-Nov-14 A 3-Mar-13
100% 100% 100% 06-Apr-13 A 16-Nov-14 A 5-Mar-13
100% 100% 100% 21-Apr-13 A 16-Nov-14 A 17-Mar-13
100% 100% 100% 01-Jun-14 A 16-Nov-14 A 28-Feb-13
100% 100% 100% 02-Jun-14 A 16-Nov-14 A 7-Mar-13
100% 100% 100% 02-Jun-14 A 16-Nov-14 A 10-Mar-13
100% 100% 100% 03-Jun-14 A 16-Nov-14 A 14-Mar-13
100% 100% 100% 03-Jun-14 A 16-Nov-14 A 12-Mar-13
100% 100% 100% 04-Jun-14 A 17-Nov-14 A 26-Mar-13
100% 100% 28-Mar-13 A 17-Nov-14 A 4-Feb-13
100% 100% 28-Mar-13 A 12-Mar-14 A 4-Feb-13
100% 100% 100% 28-Mar-13 A 18-Jan-14 A 4-Feb-13
100% 100% 100% 27-Jul-13 A 08-Mar-14 A 7-Feb-13
100% 100% 100% 28-Jul-13 A 09-Mar-14 A 11-Feb-13
100% 100% 100% 29-Jul-13 A 10-Mar-14 A 16-Feb-13
100% 100% 100% 12-Aug-13 A 11-Mar-14 A 20-Feb-13
100% 100% 100% 15-Aug-13 A 12-Mar-14 A 24-Feb-13
100% 100% 21-Jul-13 A 29-Sep-14 A 6-Feb-13
100% 100% 100% 21-Jul-13 A 15-Dec-13 A 6-Feb-13
100% 100% 100% 23-Jul-13 A 16-Dec-13 A 10-Feb-13
100% 100% 100% 24-Jul-13 A 17-Dec-13 A 14-Feb-13
100% 100% 100% 29-Jul-13 A 17-Dec-13 A 18-Feb-13
100% 100% 100% 12-Aug-13 A 19-Dec-13 A 21-Feb-13
100% 100% 100% 13-Aug-13 A 02-Jan-14 A 25-Feb-13
100% 100% 100% 14-Aug-13 A 06-Jan-14 A 5-Mar-13
100% 100% 100% 24-Aug-13 A 07-Jan-14 A 27-Feb-13
100% 100% 100% 25-Aug-13 A 09-Jan-14 A 7-Mar-13
100% 100% 100% 26-Aug-13 A 09-Jan-14 A 3-Mar-13
100% 100% 100% 26-Aug-13 A 13-Jan-14 A 5-Mar-13
100% 100% 100% 07-Jul-14 A 29-Sep-14 A 3-Apr-13
100% 100% 10-Dec-13 A 17-Nov-14 A 24-Mar-13
100% 100% 100% 10-Dec-13 A 16-Nov-14 A 25-Mar-13
100% 100% 100% 15-Dec-13 A 17-Nov-14 A 31-Mar-13
100% 100% 100% 21-Dec-13 A 17-Nov-14 A 29-Apr-13
100% 100% 100% 11-May-14 A 17-Nov-14 A 24-Mar-13
100% 100% 100% 13-May-14 A 17-Nov-14 A 6-Apr-13
100% 100% 100% 14-May-14 A 17-Nov-14 A 11-Apr-13
100% 100% 100% 18-May-14 A 17-Nov-14 A 23-Apr-13
100% 100% 100% 18-May-14 A 17-Nov-14 A 17-Apr-13
100% 100% 100% 20-May-14 A 17-Nov-14 A 26-May-13
100% 100% 17-Nov-12 A 13-Dec-14 A 4-Mar-13
100% 100% 17-Nov-12 A 18-Feb-13 A 4-Mar-13
100% 100% 100% 17-Nov-12 A 16-Feb-13 A 4-Mar-13
100% 100% 100% 08-Dec-12 A 17-Feb-13 A 6-Mar-13
100% 100% 100% 09-Dec-12 A 18-Feb-13 A 9-Mar-13
100% 100% 100% 17-Dec-12 A 18-Feb-13 A 11-Mar-13
100% 100% 100% 05-Jan-13 A 18-Feb-13 A 13-Mar-13
100% 100% 100% 06-Jan-13 A 18-Feb-13 A 16-Mar-13
100% 100% 05-Dec-12 A 25-Mar-13 A 6-Mar-13
100% 100% 100% 05-Dec-12 A 28-Jan-13 A 6-Mar-13
100% 100% 100% 15-Dec-12 A 28-Jan-13 A 7-Mar-13
100% 100% 100% 16-Dec-12 A 28-Jan-13 A 9-Mar-13
100% 100% 100% 19-Dec-12 A 29-Jan-13 A 10-Mar-13
100% 100% 100% 02-Feb-13 A 16-Feb-13 A 11-Mar-13
100% 100% 100% 04-Feb-13 A 17-Feb-13 A 12-Mar-13
100% 100% 100% 09-Feb-13 A 17-Mar-13 A 14-Mar-13
100% 100% 100% 13-Feb-13 A 18-Feb-13 A 20-Mar-13
100% 100% 100% 16-Feb-13 A 20-Feb-13 A 23-Mar-13
100% 100% 100% 16-Feb-13 A 21-Feb-13 A 2-Apr-13
100% 100% 100% 23-Feb-13 A 28-Feb-13 A 17-Mar-13
100% 100% 100% 04-Mar-13 A 25-Mar-13 A 16-Mar-13
100% 100% 02-Mar-13 A 13-Dec-14 A 21-Mar-13
100% 100% 100% 02-Mar-13 A 15-Mar-14 A 21-Mar-13
100% 100% 100% 03-Mar-13 A 17-Mar-14 A 30-Mar-13
100% 100% 100% 05-Mar-13 A 18-Mar-14 A 7-Apr-13
100% 100% 100% 10-Dec-14 A 13-Dec-14 A 15-Apr-13
100% 100% 11-Nov-12 A 28-Dec-14 A 18-Mar-13
100% 100% 11-Nov-12 A 19-Mar-13 A 18-Mar-13
100% 100% 100% 11-Nov-12 A 15-Nov-12 A 18-Mar-13
100% 100% 100% 01-Dec-12 A 03-Mar-13 A 19-Mar-13
100% 100% 100% 03-Dec-12 A 03-Mar-13 A 20-Mar-13
100% 100% 100% 03-Dec-12 A 04-Mar-13 A 23-Mar-13
100% 100% 100% 06-Dec-12 A 04-Mar-13 A 24-Mar-13
100% 100% 100% 08-Dec-12 A 19-Mar-13 A 26-Mar-13
100% 100% 01-Dec-12 A 07-Jul-14 A 18-Mar-13
100% 100% 100% 01-Dec-12 A 02-Dec-12 A 18-Mar-13
100% 100% 100% 02-Dec-12 A 03-Dec-12 A 19-Mar-13
100% 100% 100% 03-Dec-12 A 03-Dec-12 A 20-Mar-13
100% 100% 100% 03-Dec-12 A 05-Dec-12 A 21-Mar-13
100% 100% 100% 04-Feb-13 A 11-Feb-13 A 23-Mar-13
100% 100% 100% 05-Feb-13 A 13-Feb-13 A 24-Mar-13
100% 100% 100% 11-Feb-13 A 07-Jul-14 A 9-Apr-13
100% 100% 100% 16-Feb-13 A 18-Feb-13 A 26-Mar-13
100% 100% 100% 23-Feb-13 A 26-Feb-13 A 28-Mar-13
100% 100% 100% 05-Mar-13 A 12-Mar-13 A 1-Apr-13
100% 100% 100% 16-Mar-13 A 18-Mar-13 A 3-Apr-13
100% 100% 100% 23-Feb-14 A 26-Feb-14 A 27-Mar-13
100% 100% 28-Feb-13 A 28-Dec-14 A 30-Mar-13
100% 100% 100% 28-Feb-13 A 07-Mar-13 A 30-Mar-13
100% 100% 100% 06-Mar-13 A 14-Mar-13 A 4-Apr-13
100% 100% 100% 09-Mar-13 A 20-Mar-13 A 10-Apr-13
100% 100% 100% 22-Dec-14 A 28-Dec-14 A 16-Apr-13
100% 100% 03-May-12 A 3-Jan-15 -200.00 2-Dec-12
0% 0% 03-May-12 A 23-Jun-13 A 2-Dec-12
100% 100% 100% 03-May-12 A 14-Jul-12 A 2-Dec-12
100% 100% 100% 18-Jun-12 A 23-Jun-13 A 30-Jan-13
100% 100% 100% 24-Sep-12 A 30-Oct-12 A 19-Jan-13
100% 100% 27-Sep-12 A 04-Jun-14 A 25-Mar-13
100% 100% 100% 27-Sep-12 A 02-Jun-14 A 25-Mar-13
100% 100% 100% 08-Oct-12 A 03-Jun-14 A 27-Mar-13
100% 100% 100% 09-Oct-12 A 03-Jun-14 A 30-Mar-13
100% 100% 100% 14-Oct-12 A 03-Jun-14 A 1-Apr-13
100% 100% 100% 15-Oct-12 A 03-Jun-14 A 3-Apr-13
100% 100% 100% 15-Oct-12 A 04-Jun-14 A 6-Apr-13
100% 100% 07-Oct-12 A 04-Jun-14 A 25-Mar-13
100% 100% 100% 07-Oct-12 A 13-Apr-14 A 25-Mar-13
100% 100% 100% 09-Oct-12 A 01-Jun-14 A 27-Mar-13
100% 100% 100% 10-Oct-12 A 02-Jun-14 A 30-Mar-13
100% 100% 100% 14-Oct-12 A 03-Jun-14 A 1-Apr-13
100% 100% 100% 25-Oct-12 A 03-Jun-14 A 3-Apr-13
100% 100% 100% 30-Oct-12 A 04-Jun-14 A 6-Apr-13
100% 100% 100% 18-Nov-12 A 01-Jun-14 A 14-Apr-13
100% 100% 100% 22-Nov-12 A 01-Jun-14 A 16-Apr-13
100% 100% 100% 03-Jan-13 A 02-Jun-14 A 4-May-13
100% 100% 100% 05-Jan-13 A 03-Jun-14 A 13-Apr-13
100% 100% 100% 06-Apr-13 A 03-Jun-14 A 8-Apr-13
100% 100% 100% 25-Apr-13 A 04-Jun-14 A 10-Apr-13
100% 99% 03-Nov-12 A 3-Jan-15 -170.00 23-Apr-13
100% 100% 100% 03-Nov-12 A 13-Mar-13 A 23-Apr-13
100% 100% 100% 05-Nov-12 A 19-Mar-13 A 5-May-13
100% 100% 100% 17-Nov-12 A 08-Apr-13 A 16-May-13
90% 100% 90% 01-Dec-14 A 3-Jan-15 -132.00 28-May-13
100% 100% 03-May-12 A 23-Dec-14 A 1-Jan-13
100% 100% 03-May-12 A 23-Dec-14 A 1-Jan-13
0% 0% 03-May-12 A 19-May-14 A 1-Jan-13
100% 100% 100% 03-May-12 A 14-Jul-12 A 1-Jan-13
100% 100% 100% 20-Jun-12 A 28-Dec-13 A 16-Feb-13
100% 100% 100% 01-Sep-13 A 19-May-14 A 3-Feb-13
100% 100% 02-May-13 A 20-Jun-14 A 15-Apr-13
100% 100% 100% 02-May-13 A 01-Feb-14 A 15-Apr-13
100% 100% 100% 11-Sep-13 A 16-Jun-14 A 21-Apr-13
100% 100% 100% 14-Sep-13 A 17-Jun-14 A 27-Apr-13
100% 100% 100% 14-Sep-13 A 18-Jun-14 A 2-May-13
100% 100% 100% 15-Sep-13 A 18-Jun-14 A 8-May-13
100% 100% 100% 21-Sep-13 A 20-Jun-14 A 12-May-13
100% 100% 15-Sep-13 A 18-Dec-14 A 15-Apr-13
100% 100% 100% 15-Sep-13 A 16-Jun-14 A 15-Apr-13
100% 100% 100% 06-Oct-13 A 17-Jun-14 A 18-Apr-13
100% 100% 100% 08-Oct-13 A 18-Jun-14 A 22-Apr-13
100% 100% 100% 13-Oct-13 A 19-Jun-14 A 25-Apr-13
100% 100% 100% 14-Oct-13 A 21-Jun-14 A 29-Apr-13
100% 100% 100% 19-Oct-13 A 22-Jun-14 A 2-May-13
100% 100% 100% 03-Nov-13 A 23-Jun-14 A 11-May-13
100% 100% 100% 04-Nov-13 A 24-Jun-14 A 13-May-13
100% 100% 100% 06-Nov-13 A 25-Jun-14 A 5-May-13
100% 100% 100% 07-Nov-13 A 26-Jun-14 A 8-May-13
100% 100% 100% 07-Nov-13 A 20-Jun-14 A 12-May-13
100% 100% 100% 25-Aug-14 A 18-Dec-14 A 10-Jun-13
100% 100% 02-Feb-14 A 10-Dec-14 A 2-May-13
100% 100% 100% 02-Feb-14 A 17-Nov-14 A 5-May-13
100% 100% 100% 06-Feb-14 A 17-Nov-14 A 7-May-13
100% 100% 100% 08-Feb-14 A 17-Nov-14 A 19-May-13
100% 100% 100% 03-Aug-14 A 17-Nov-14 A 2-May-13
100% 100% 100% 06-Aug-14 A 17-Nov-14 A 9-May-13
100% 100% 100% 09-Aug-14 A 17-Nov-14 A 12-May-13
100% 100% 100% 12-Aug-14 A 17-Nov-14 A 14-May-13
100% 100% 100% 14-Aug-14 A 17-Nov-14 A 16-May-13
100% 100% 100% 18-Aug-14 A 10-Dec-14 A 1-Jul-13
100% 100% 08-Feb-14 A 23-Dec-14 A 12-May-13
100% 100% 08-Feb-14 A 27-Mar-14 A 12-May-13
100% 100% 100% 08-Feb-14 A 17-Feb-14 A 12-May-13
100% 100% 100% 08-Mar-14 A 23-Mar-14 A 13-May-13
100% 100% 100% 09-Mar-14 A 24-Mar-14 A 14-May-13
100% 100% 100% 10-Mar-14 A 25-Mar-14 A 15-May-13
100% 100% 100% 12-Mar-14 A 26-Mar-14 A 16-May-13
100% 100% 100% 15-Mar-14 A 27-Mar-14 A 18-May-13
100% 100% 08-Mar-14 A 23-Dec-14 A 12-May-13
100% 100% 100% 08-Mar-14 A 09-Mar-14 A 12-May-13
100% 100% 100% 09-Mar-14 A 10-Mar-14 A 13-May-13
100% 100% 100% 10-Mar-14 A 10-Apr-14 A 14-May-13
100% 100% 100% 11-Mar-14 A 12-Apr-14 A 15-May-13
100% 100% 100% 12-Mar-14 A 13-Mar-14 A 18-May-13
100% 100% 100% 12-Mar-14 A 12-Mar-14 A 16-May-13
100% 100% 100% 15-Mar-14 A 24-Mar-14 A 19-May-13
100% 100% 100% 17-Mar-14 A 22-Mar-14 A 26-May-13
100% 100% 100% 19-Mar-14 A 23-Mar-14 A 20-May-13
100% 100% 100% 19-Mar-14 A 23-Mar-14 A 27-May-13
100% 100% 100% 20-Mar-14 A 23-Mar-14 A 21-May-13
100% 100% 100% 30-Nov-14 A 23-Dec-14 A 1-Jun-13
100% 100% 23-Jun-14 A 18-Nov-14 A 22-May-13
100% 100% 100% 23-Jun-14 A 16-Nov-14 A 22-May-13
100% 100% 100% 24-Jun-14 A 17-Nov-14 A 28-May-13
100% 100% 100% 25-Jun-14 A 18-Nov-14 A 9-Jul-13
100% 100% 100% 16-Aug-14 A 16-Nov-14 A 22-May-13
100% 100% 100% 17-Aug-14 A 17-Nov-14 A 3-Jun-13
100% 100% 100% 18-Aug-14 A 17-Nov-14 A 10-Jun-13
100% 100% 100% 19-Aug-14 A 17-Nov-14 A 19-Jun-13
100% 100% 100% 20-Aug-14 A 18-Nov-14 A 30-Jun-13
100% 100% 100% 20-Aug-14 A 18-Nov-14 A 18-Jul-13
100% 100% 16-Dec-13 A 16-Dec-14 A 15-May-13
100% 100% 16-Dec-13 A 26-Mar-14 A 15-May-13
100% 100% 100% 16-Dec-13 A 31-Dec-13 A 15-May-13
100% 100% 100% 01-Mar-14 A 22-Mar-14 A 16-May-13
100% 100% 100% 02-Mar-14 A 23-Mar-14 A 18-May-13
100% 100% 100% 03-Mar-14 A 24-Mar-14 A 19-May-13
100% 100% 100% 04-Mar-14 A 25-Mar-14 A 20-May-13
100% 100% 100% 06-Mar-14 A 26-Mar-14 A 21-May-13
100% 100% 16-Feb-14 A 16-Dec-14 A 16-May-13
100% 100% 100% 16-Feb-14 A 06-Mar-14 A 16-May-13
100% 100% 100% 22-Feb-14 A 22-Mar-14 A 18-May-13
100% 100% 100% 22-Feb-14 A 23-Mar-14 A 19-May-13
100% 100% 100% 23-Feb-14 A 23-Mar-14 A 20-May-13
100% 100% 100% 02-Mar-14 A 24-Mar-14 A 21-May-13
100% 100% 100% 03-Mar-14 A 24-Mar-14 A 22-May-13
100% 100% 100% 08-Mar-14 A 25-Mar-14 A 23-May-13
100% 100% 100% 10-Mar-14 A 25-Mar-14 A 25-May-13
100% 100% 100% 12-Mar-14 A 25-Mar-14 A 30-May-13
100% 100% 100% 12-Mar-14 A 26-Mar-14 A 26-May-13
100% 100% 100% 13-Mar-14 A 31-Mar-14 A 1-Jun-13
100% 100% 100% 30-Nov-14 A 16-Dec-14 A 13-Jun-13
100% 100% 21-Jun-14 A 10-Nov-14 A 2-Jun-13
100% 100% 100% 21-Jun-14 A 10-Nov-14 A 4-Jun-13
100% 100% 100% 22-Jun-14 A 10-Nov-14 A 6-Jun-13
100% 100% 100% 23-Jun-14 A 10-Nov-14 A 25-Jun-13
100% 100% 100% 01-Sep-14 A 10-Nov-14 A 2-Jun-13
100% 100% 100% 02-Sep-14 A 10-Nov-14 A 10-Jun-13
100% 100% 100% 03-Sep-14 A 10-Nov-14 A 13-Jun-13
100% 100% 100% 04-Sep-14 A 10-Nov-14 A 18-Jun-13
100% 100% 100% 06-Sep-14 A 10-Nov-14 A 22-Jun-13
100% 100% 100% 07-Sep-14 A 10-Nov-14 A 11-Jul-13
100% 100% 29-Sep-13 A 12-Nov-14 A 22-May-13
100% 100% 29-Sep-13 A 28-Dec-13 A 22-May-13
100% 100% 100% 29-Sep-13 A 17-Nov-13 A 22-May-13
100% 100% 100% 12-Oct-13 A 25-Dec-13 A 23-May-13
100% 100% 100% 12-Oct-13 A 25-Dec-13 A 25-May-13
100% 100% 100% 19-Oct-13 A 28-Dec-13 A 26-May-13
100% 100% 100% 20-Oct-13 A 28-Dec-13 A 27-May-13
100% 100% 100% 10-Dec-13 A 28-Dec-13 A 28-May-13
100% 100% 27-Nov-13 A 12-Nov-14 A 25-May-13
100% 100% 100% 27-Nov-13 A 23-Dec-13 A 25-May-13
100% 100% 100% 28-Nov-13 A 23-Dec-13 A 27-May-13
100% 100% 100% 28-Nov-13 A 24-Dec-13 A 29-May-13
100% 100% 100% 30-Nov-13 A 25-Dec-13 A 1-Jun-13
100% 100% 100% 02-Dec-13 A 25-Dec-13 A 3-Jun-13
100% 100% 100% 03-Dec-13 A 26-Dec-13 A 5-Jun-13
100% 100% 100% 23-Dec-13 A 25-Feb-14 A 8-Jun-13
100% 100% 100% 24-Dec-13 A 27-Feb-14 A 18-Jun-13
100% 100% 100% 28-Dec-13 A 01-Mar-14 A 12-Jun-13
100% 100% 100% 29-Dec-13 A 02-Mar-14 A 22-Jun-13
100% 100% 100% 29-Jan-14 A 03-Mar-14 A 16-Jun-13
100% 100% 100% 02-Aug-14 A 12-Nov-14 A 15-Jul-13
100% 100% 05-Apr-14 A 09-Nov-14 A 27-Jun-13
100% 100% 100% 05-Apr-14 A 08-Nov-14 A 27-Jun-13
100% 100% 100% 07-Apr-14 A 08-Nov-14 A 3-Jul-13
100% 100% 100% 09-Apr-14 A 08-Nov-14 A 1-Aug-13
100% 100% 100% 01-Sep-14 A 08-Nov-14 A 27-Jun-13
100% 100% 100% 02-Sep-14 A 09-Nov-14 A 9-Jul-13
100% 100% 100% 03-Sep-14 A 09-Nov-14 A 15-Jul-13
100% 100% 100% 04-Sep-14 A 09-Nov-14 A 21-Jul-13
100% 100% 100% 06-Sep-14 A 09-Nov-14 A 27-Jul-13
100% 100% 100% 07-Sep-14 A 09-Nov-14 A 18-Aug-13
100% 100% 24-Oct-13 A 12-Nov-14 A 1-Jun-13
100% 100% 24-Oct-13 A 12-Jan-14 A 1-Jun-13
100% 100% 100% 24-Oct-13 A 11-Nov-13 A 1-Jun-13
100% 100% 100% 14-Dec-13 A 08-Jan-14 A 2-Jun-13
100% 100% 100% 15-Dec-13 A 08-Jan-14 A 3-Jun-13
100% 100% 100% 19-Dec-13 A 08-Jan-14 A 5-Jun-13
100% 100% 100% 19-Dec-13 A 11-Jan-14 A 4-Jun-13
100% 100% 100% 19-Dec-13 A 12-Jan-14 A 6-Jun-13
100% 100% 26-Nov-13 A 11-Nov-14 A 8-Jun-13
100% 100% 100% 26-Nov-13 A 10-Dec-13 A 8-Jun-13
100% 100% 100% 14-Dec-13 A 17-Dec-13 A 12-Jun-13
100% 100% 100% 15-Dec-13 A 19-Dec-13 A 16-Jun-13
100% 100% 100% 17-Dec-13 A 21-Dec-13 A 19-Jun-13
100% 100% 100% 19-Dec-13 A 28-Dec-13 A 24-Jun-13
100% 100% 100% 23-Dec-13 A 29-Dec-13 A 27-Jun-13
100% 100% 100% 24-Dec-13 A 12-Jan-14 A 1-Jul-13
100% 100% 100% 24-Dec-13 A 18-Jan-14 A 11-Jul-13
100% 100% 100% 25-Dec-13 A 19-Jan-14 A 6-Jul-13
100% 100% 100% 25-Dec-13 A 20-Jan-14 A 15-Jul-13
100% 100% 100% 25-Dec-13 A 05-Jan-14 A 9-Jul-13
100% 100% 100% 12-Oct-14 A 11-Nov-14 A 13-Aug-13
100% 100% 28-Apr-14 A 12-Nov-14 A 24-Jul-13
100% 100% 100% 28-Apr-14 A 08-Nov-14 A 29-Jul-13
100% 100% 100% 29-Apr-14 A 08-Nov-14 A 1-Aug-13
100% 100% 100% 29-Apr-14 A 08-Nov-14 A 24-Aug-13
100% 100% 100% 21-Jul-14 A 08-Nov-14 A 24-Jul-13
100% 100% 100% 22-Jul-14 A 08-Nov-14 A 5-Aug-13
100% 100% 100% 23-Jul-14 A 09-Nov-14 A 12-Aug-13
100% 100% 100% 24-Jul-14 A 10-Nov-14 A 15-Aug-13
100% 100% 100% 26-Jul-14 A 10-Nov-14 A 19-Aug-13
100% 100% 100% 27-Jul-14 A 12-Nov-14 A 5-Sep-13
100% 100% 03-Nov-13 A 11-Dec-14 A 17-Jun-13
100% 100% 03-Nov-13 A 18-Feb-14 A 17-Jun-13
100% 100% 100% 03-Nov-13 A 20-Nov-13 A 17-Jun-13
100% 100% 100% 21-Dec-13 A 15-Feb-14 A 23-Jun-13
100% 100% 100% 22-Dec-13 A 16-Feb-14 A 29-Jun-13
100% 100% 100% 23-Dec-13 A 17-Feb-14 A 4-Jul-13
100% 100% 100% 25-Dec-13 A 17-Feb-14 A 10-Jul-13
100% 100% 100% 31-Dec-13 A 18-Feb-14 A 16-Jul-13
100% 100% 14-Dec-13 A 09-Nov-14 A 6-Jul-13
100% 100% 100% 14-Dec-13 A 05-Feb-14 A 6-Jul-13
100% 100% 100% 21-Dec-13 A 06-Feb-14 A 11-Jul-13
100% 100% 100% 26-Dec-13 A 08-Feb-14 A 17-Jul-13
100% 100% 100% 28-Dec-13 A 09-Feb-14 A 23-Jul-13
100% 100% 100% 29-Dec-13 A 10-Feb-14 A 29-Jul-13
100% 100% 100% 30-Dec-13 A 11-Mar-14 A 4-Aug-13
100% 100% 100% 12-Jan-14 A 22-Feb-14 A 19-Aug-13
100% 100% 100% 14-Jan-14 A 23-Feb-14 A 7-Aug-13
100% 100% 100% 18-Jan-14 A 24-Feb-14 A 15-Aug-13
100% 100% 100% 18-Jan-14 A 26-Feb-14 A 24-Aug-13
100% 100% 100% 16-Feb-14 A 27-Feb-14 A 21-Aug-13
100% 100% 100% 27-Aug-14 A 09-Nov-14 A 22-Sep-13
100% 100% 27-Apr-14 A 11-Dec-14 A 13-Aug-13
100% 100% 100% 27-Apr-14 A 08-Nov-14 A 18-Aug-13
100% 100% 100% 28-Apr-14 A 08-Nov-14 A 21-Aug-13
100% 100% 100% 28-Apr-14 A 08-Nov-14 A 5-Sep-13
100% 100% 100% 09-Aug-14 A 08-Nov-14 A 13-Aug-13
100% 100% 100% 11-Aug-14 A 08-Nov-14 A 25-Aug-13
100% 100% 100% 13-Aug-14 A 08-Nov-14 A 29-Aug-13
100% 100% 100% 20-Aug-14 A 08-Nov-14 A 1-Sep-13
100% 100% 100% 23-Aug-14 A 08-Nov-14 A 3-Sep-13
100% 100% 100% 26-Aug-14 A 11-Dec-14 A 2-Oct-13
100% 97% 03-May-12 A 4-Feb-15 -193.00 25-Mar-13
0% 0% 03-May-12 A 06-May-14 A 25-Mar-13
100% 100% 100% 03-May-12 A 14-Jul-12 A 25-Mar-13
100% 100% 100% 23-Jun-12 A 24-Jun-12 A 28-May-13
100% 100% 100% 27-Mar-14 A 06-May-14 A 5-May-13
100% 100% 30-Mar-14 A 30-Apr-14 A 31-Jul-13
100% 100% 100% 30-Mar-14 A 28-Apr-14 A 31-Jul-13
100% 100% 100% 05-Apr-14 A 28-Apr-14 A 4-Aug-13
100% 100% 100% 06-Apr-14 A 29-Apr-14 A 8-Aug-13
100% 100% 100% 08-Apr-14 A 29-Apr-14 A 14-Aug-13
100% 100% 100% 09-Apr-14 A 29-Apr-14 A 18-Aug-13
100% 100% 100% 09-Apr-14 A 30-Apr-14 A 22-Aug-13
100% 96% 07-Apr-14 A 4-Feb-15 -193.00 22-Aug-13
100% 100% 100% 07-Apr-14 A 26-Apr-14 A 22-Aug-13
100% 100% 100% 08-Apr-14 A 27-Apr-14 A 26-Aug-13
100% 100% 100% 09-Apr-14 A 28-Apr-14 A 29-Aug-13
100% 100% 100% 14-Apr-14 A 28-Apr-14 A 2-Sep-13
100% 100% 100% 14-Apr-14 A 28-Apr-14 A 4-Sep-13
100% 100% 100% 16-Apr-14 A 04-May-14 A 7-Sep-13
100% 100% 100% 28-Apr-14 A 19-May-14 A 9-Sep-13
100% 100% 100% 28-Apr-14 A 20-May-14 A 15-Sep-13
100% 100% 100% 29-Apr-14 A 21-May-14 A 11-Sep-13
100% 100% 100% 05-May-14 A 26-May-14 A 14-Sep-13
100% 100% 100% 06-May-14 A 26-May-14 A 17-Sep-13
90% 100% 90% 10-Jun-14 A 4-Feb-15 -161.00 22-Oct-13
100% 95% 22-Jul-14 A 1-Jan-15 -168.00 25-Sep-13
95% 100% 95% 22-Jul-14 A 1-Jan-15 -132.00 25-Sep-13
95% 100% 95% 23-Jul-14 A 1-Jan-15 -132.00 28-Sep-13
95% 100% 95% 24-Jul-14 A 1-Jan-15 -132.00 9-Oct-13
95% 100% 95% 01-Sep-14 A 1-Jan-15 -132.00 25-Sep-13
95% 100% 95% 02-Sep-14 A 1-Jan-15 -132.00 30-Sep-13
95% 100% 95% 03-Sep-14 A 1-Jan-15 -132.00 2-Oct-13
95% 100% 95% 04-Sep-14 A 1-Jan-15 -132.00 5-Oct-13
95% 100% 95% 06-Sep-14 A 1-Jan-15 -132.00 7-Oct-13
95% 100% 95% 07-Sep-14 A 1-Jan-15 -132.00 21-Oct-13
100% 99% 21-Oct-13 A 5-Feb-15 -203.00 4-Jun-13
0% 0% 21-Oct-13 A 3-Jan-15 -192.00 4-Jun-13
100% 100% 100% 21-Oct-13 A 22-Jul-14 A 23-Jun-13
90% 100% 90% 09-Jun-14 A 3-Jan-15 -144.00 4-Jun-13
100% 100% 10-Apr-14 A 28-Aug-14 A 1-Sep-13
100% 100% 100% 10-Apr-14 A 26-Aug-14 A 1-Sep-13
100% 100% 100% 26-Apr-14 A 27-Aug-14 A 4-Sep-13
100% 100% 100% 27-Apr-14 A 27-Aug-14 A 8-Sep-13
100% 100% 100% 28-Apr-14 A 27-Aug-14 A 11-Sep-13
100% 100% 100% 29-Apr-14 A 27-Aug-14 A 15-Sep-13
100% 100% 100% 30-Apr-14 A 28-Aug-14 A 18-Sep-13
100% 98% 26-Apr-14 A 5-Feb-15 -203.00 7-Sep-13
100% 100% 100% 26-Apr-14 A 23-Aug-14 A 7-Sep-13
100% 100% 100% 28-Apr-14 A 24-Aug-14 A 10-Sep-13
100% 100% 100% 01-May-14 A 25-Aug-14 A 14-Sep-13
100% 100% 100% 03-May-14 A 26-Aug-14 A 17-Sep-13
100% 100% 100% 04-May-14 A 26-Aug-14 A 21-Sep-13
100% 100% 100% 06-May-14 A 27-Aug-14 A 24-Sep-13
100% 100% 100% 11-May-14 A 28-Aug-14 A 26-Sep-13
100% 100% 100% 12-May-14 A 28-Aug-14 A 2-Oct-13
100% 100% 100% 13-May-14 A 28-Aug-14 A 30-Sep-13
100% 100% 100% 13-May-14 A 28-Aug-14 A 5-Oct-13
100% 100% 100% 14-May-14 A 28-Aug-14 A 3-Oct-13
96% 100% 96% 02-Nov-14 A 5-Feb-15 -161.00 14-Nov-13
100% 100% 13-Sep-14 A 24-Dec-14 A 3-Oct-13
100% 100% 100% 13-Sep-14 A 23-Dec-14 A 3-Oct-13
100% 100% 100% 16-Sep-14 A 24-Dec-14 A 24-Oct-13
100% 100% 100% 18-Sep-14 A 24-Dec-14 A 11-Nov-13
100% 100% 100% 20-Sep-14 A 24-Dec-14 A 28-Nov-13
100% 99% 03-May-12 A 17-Jan-15 -174.00 29-Aug-12
100% 100% 03-May-12 A 5-Jan-15 -196.00 23-Apr-13
0% 0% 03-May-12 A 15-Jul-14 A 23-Apr-13
100% 100% 100% 03-May-12 A 14-Jul-12 A 23-Apr-13
100% 100% 100% 01-Sep-12 A 15-Jul-14 A 28-May-13
100% 100% 100% 03-Nov-12 A 15-Jul-14 A 16-May-13
100% 100% 04-Apr-13 A 26-Mar-14 A 28-Sep-13
100% 100% 100% 04-Apr-13 A 09-Feb-14 A 28-Sep-13
100% 100% 100% 21-Dec-13 A 23-Mar-14 A 30-Sep-13
100% 100% 100% 22-Dec-13 A 24-Mar-14 A 2-Oct-13
100% 100% 100% 23-Dec-13 A 24-Mar-14 A 5-Oct-13
100% 100% 100% 25-Dec-13 A 25-Mar-14 A 7-Oct-13
100% 100% 100% 29-Dec-13 A 26-Mar-14 A 9-Oct-13
100% 100% 02-Dec-13 A 10-Dec-14 A 30-Sep-13
100% 100% 100% 02-Dec-13 A 07-Apr-14 A 30-Sep-13
100% 100% 100% 21-Dec-13 A 08-Apr-14 A 2-Oct-13
100% 100% 100% 22-Dec-13 A 09-Apr-14 A 5-Oct-13
100% 100% 100% 22-Dec-13 A 10-Apr-14 A 7-Oct-13
100% 100% 100% 23-Dec-13 A 10-Apr-14 A 9-Oct-13
100% 100% 100% 24-Dec-13 A 10-Apr-14 A 12-Oct-13
100% 100% 100% 04-Jan-14 A 12-Apr-14 A 22-Oct-13
100% 100% 100% 06-Jan-14 A 13-Apr-14 A 23-Oct-13
100% 100% 100% 12-Jan-14 A 14-Apr-14 A 14-Oct-13
100% 100% 100% 13-Jan-14 A 15-Apr-14 A 20-Oct-13
100% 100% 100% 18-Jan-14 A 15-Apr-14 A 26-Oct-13
100% 100% 100% 04-Nov-14 A 10-Dec-14 A 11-Nov-13
100% 100% 03-Sep-14 A 25-Dec-14 A 12-Oct-13
100% 100% 100% 03-Sep-14 A 13-Oct-14 A 12-Oct-13
100% 100% 100% 13-Sep-14 A 13-Oct-14 A 14-Oct-13
100% 100% 100% 16-Sep-14 A 16-Oct-14 A 29-Oct-13
100% 100% 100% 04-Oct-14 A 24-Dec-14 A 12-Oct-13
100% 100% 100% 04-Oct-14 A 24-Dec-14 A 20-Oct-13
100% 100% 100% 06-Oct-14 A 24-Dec-14 A 22-Oct-13
100% 100% 100% 08-Oct-14 A 24-Dec-14 A 24-Oct-13
100% 100% 100% 10-Oct-14 A 24-Dec-14 A 27-Oct-13
100% 100% 100% 11-Oct-14 A 25-Dec-14 A 10-Nov-13
100% 100% 11-May-13 A 30-Dec-14 A 12-Oct-13
100% 100% 11-May-13 A 10-Feb-14 A 12-Oct-13
100% 100% 100% 11-May-13 A 13-Nov-13 A 12-Oct-13
100% 100% 100% 16-Jan-14 A 27-Jan-14 A 13-Oct-13
100% 100% 100% 18-Jan-14 A 02-Feb-14 A 14-Oct-13
100% 100% 100% 19-Jan-14 A 03-Feb-14 A 20-Oct-13
100% 100% 100% 19-Jan-14 A 04-Feb-14 A 19-Oct-13
100% 100% 100% 21-Jan-14 A 10-Feb-14 A 21-Oct-13
100% 100% 29-Dec-13 A 18-Nov-14 A 14-Oct-13
100% 100% 100% 29-Dec-13 A 09-Jan-14 A 14-Oct-13
100% 100% 100% 06-Jan-14 A 08-Jan-14 A 19-Oct-13
100% 100% 100% 07-Jan-14 A 11-Jan-14 A 20-Oct-13
100% 100% 100% 09-Jan-14 A 11-Jan-14 A 21-Oct-13
100% 100% 100% 11-Jan-14 A 03-Feb-14 A 22-Oct-13
100% 100% 100% 18-Jan-14 A 05-Feb-14 A 23-Oct-13
100% 100% 100% 28-Jan-14 A 24-Mar-14 A 31-Oct-13
100% 100% 100% 06-Feb-14 A 26-Mar-14 A 27-Oct-13
100% 100% 100% 09-Feb-14 A 27-Mar-14 A 24-Oct-13
100% 100% 100% 10-Feb-14 A 27-Mar-14 A 26-Oct-13
100% 100% 100% 12-Feb-14 A 25-Mar-14 A 2-Nov-13
100% 100% 100% 16-Nov-14 A 18-Nov-14 A 4-Nov-13
100% 100% 05-Aug-14 A 30-Dec-14 A 23-Oct-13
100% 100% 100% 05-Aug-14 A 23-Dec-14 A 26-Oct-13
100% 100% 100% 06-Aug-14 A 23-Dec-14 A 28-Oct-13
100% 100% 100% 16-Aug-14 A 28-Dec-14 A 9-Nov-13
100% 100% 100% 18-Oct-14 A 23-Dec-14 A 23-Oct-13
100% 100% 100% 19-Oct-14 A 24-Dec-14 A 30-Oct-13
100% 100% 100% 19-Oct-14 A 25-Dec-14 A 2-Nov-13
100% 100% 100% 20-Oct-14 A 28-Dec-14 A 6-Nov-13
100% 100% 100% 20-Oct-14 A 27-Dec-14 A 4-Nov-13
100% 100% 100% 21-Oct-14 A 30-Dec-14 A 11-Nov-13
100% 100% 04-Jun-13 A 05-Jan-15 A 21-Oct-13
100% 100% 04-Jun-13 A 26-Feb-14 A 21-Oct-13
100% 100% 100% 04-Jun-13 A 18-Nov-13 A 21-Oct-13
100% 100% 100% 11-Jan-14 A 22-Feb-14 A 22-Oct-13
100% 100% 100% 12-Jan-14 A 23-Feb-14 A 23-Oct-13
100% 100% 100% 13-Jan-14 A 24-Feb-14 A 24-Oct-13
100% 100% 100% 14-Jan-14 A 25-Feb-14 A 26-Oct-13
100% 100% 100% 15-Jan-14 A 26-Feb-14 A 27-Oct-13
100% 100% 30-Dec-13 A 26-Nov-14 A 21-Oct-13
100% 100% 100% 30-Dec-13 A 10-Feb-14 A 21-Oct-13
100% 100% 100% 07-Jan-14 A 10-Feb-14 A 22-Oct-13
100% 100% 100% 08-Jan-14 A 12-Feb-14 A 23-Oct-13
100% 100% 100% 09-Jan-14 A 13-Feb-14 A 24-Oct-13
100% 100% 100% 09-Jan-14 A 15-Feb-14 A 26-Oct-13
100% 100% 100% 11-Jan-14 A 15-Feb-14 A 27-Oct-13
100% 100% 100% 08-Feb-14 A 22-Feb-14 A 28-Oct-13
100% 100% 100% 09-Feb-14 A 23-Feb-14 A 29-Oct-13
100% 100% 100% 09-Feb-14 A 24-Feb-14 A 4-Nov-13
100% 100% 100% 16-Feb-14 A 24-Feb-14 A 30-Oct-13
100% 100% 100% 17-Feb-14 A 27-Feb-14 A 5-Nov-13
100% 100% 100% 01-Nov-14 A 26-Nov-14 A 11-Nov-13
100% 100% 09-Aug-14 A 05-Jan-15 A 2-Nov-13
100% 100% 100% 09-Aug-14 A 22-Dec-14 A 2-Nov-13
100% 100% 100% 10-Aug-14 A 22-Dec-14 A 4-Nov-13
100% 100% 100% 12-Aug-14 A 22-Dec-14 A 16-Nov-13
100% 100% 100% 18-Oct-14 A 24-Dec-14 A 2-Nov-13
100% 100% 100% 19-Oct-14 A 24-Dec-14 A 6-Nov-13
100% 100% 100% 19-Oct-14 A 24-Dec-14 A 9-Nov-13
100% 100% 100% 20-Oct-14 A 24-Dec-14 A 13-Nov-13
100% 100% 100% 20-Oct-14 A 24-Dec-14 A 11-Nov-13
100% 100% 100% 21-Oct-14 A 05-Jan-15 A 20-Nov-13
100% 100% 05-May-13 A 1-Jan-15 -168.00 26-Oct-13
100% 100% 05-May-13 A 19-Mar-14 A 26-Oct-13
100% 100% 100% 05-May-13 A 12-Mar-14 A 26-Oct-13
100% 100% 100% 02-Feb-14 A 16-Mar-14 A 28-Oct-13
100% 100% 100% 03-Feb-14 A 17-Mar-14 A 30-Oct-13
100% 100% 100% 04-Feb-14 A 18-Mar-14 A 2-Nov-13
100% 100% 100% 05-Feb-14 A 18-Mar-14 A 4-Nov-13
100% 100% 100% 06-Feb-14 A 19-Mar-14 A 6-Nov-13
100% 100% 30-Dec-13 A 27-Dec-14 A 28-Oct-13
100% 100% 100% 30-Dec-13 A 01-Mar-14 A 28-Oct-13
100% 100% 100% 31-Dec-13 A 02-Mar-14 A 30-Oct-13
100% 100% 100% 06-Jan-14 A 03-Mar-14 A 2-Nov-13
100% 100% 100% 09-Jan-14 A 05-Mar-14 A 4-Nov-13
100% 100% 100% 12-Jan-14 A 09-Mar-14 A 6-Nov-13
100% 100% 100% 14-Jan-14 A 12-Mar-14 A 9-Nov-13
100% 100% 100% 15-Feb-14 A 15-Mar-14 A 11-Nov-13
100% 100% 100% 16-Feb-14 A 16-Mar-14 A 17-Nov-13
100% 100% 100% 17-Feb-14 A 17-Mar-14 A 13-Nov-13
100% 100% 100% 18-Feb-14 A 18-Mar-14 A 19-Nov-13
100% 100% 100% 19-Feb-14 A 15-Mar-14 A 16-Nov-13
100% 100% 100% 02-Nov-14 A 27-Dec-14 A 7-Dec-13
100% 99% 18-Aug-14 A 1-Jan-15 -168.00 9-Nov-13
95% 100% 95% 18-Aug-14 A 1-Jan-15 -131.00 11-Nov-13
95% 100% 95% 19-Aug-14 A 1-Jan-15 -131.00 13-Nov-13
95% 100% 95% 20-Aug-14 A 1-Jan-15 -131.00 25-Nov-13
100% 100% 100% 12-Oct-14 A 25-Dec-14 A 9-Nov-13
100% 100% 100% 14-Oct-14 A 25-Dec-14 A 16-Nov-13
100% 100% 100% 16-Oct-14 A 25-Dec-14 A 18-Nov-13
100% 100% 100% 19-Oct-14 A 25-Dec-14 A 20-Nov-13
100% 100% 100% 20-Oct-14 A 25-Dec-14 A 23-Nov-13
100% 100% 100% 21-Oct-14 A 24-Dec-14 A 7-Dec-13
100% 100% 02-May-13 A 24-Dec-14 A 9-Nov-13
100% 100% 02-May-13 A 25-Feb-14 A 9-Nov-13
100% 100% 100% 02-May-13 A 08-May-13 A 9-Nov-13
100% 100% 100% 28-Dec-13 A 22-Feb-14 A 10-Nov-13
100% 100% 100% 29-Dec-13 A 23-Feb-14 A 11-Nov-13
100% 100% 100% 30-Dec-13 A 24-Feb-14 A 13-Nov-13
100% 100% 100% 30-Dec-13 A 24-Feb-14 A 12-Nov-13
100% 100% 100% 01-Jan-14 A 25-Feb-14 A 14-Nov-13
100% 100% 08-Dec-13 A 09-Dec-14 A 11-Nov-13
100% 100% 100% 08-Dec-13 A 14-Dec-13 A 11-Nov-13
100% 100% 100% 11-Dec-13 A 16-Dec-13 A 12-Nov-13
100% 100% 100% 14-Dec-13 A 17-Dec-13 A 13-Nov-13
100% 100% 100% 16-Dec-13 A 19-Dec-13 A 14-Nov-13
100% 100% 100% 29-Dec-13 A 30-Jan-14 A 16-Nov-13
100% 100% 100% 30-Dec-13 A 01-Feb-14 A 17-Nov-13
100% 100% 100% 18-Jan-14 A 02-Feb-14 A 18-Nov-13
100% 100% 100% 19-Jan-14 A 02-Feb-14 A 19-Nov-13
100% 100% 100% 20-Jan-14 A 03-Feb-14 A 20-Nov-13
100% 100% 100% 21-Jan-14 A 04-Feb-14 A 25-Nov-13
100% 100% 100% 22-Jan-14 A 06-Feb-14 A 26-Nov-13
100% 100% 100% 09-Nov-14 A 09-Dec-14 A 29-Dec-13
100% 100% 28-Sep-14 A 24-Dec-14 A 24-Nov-13
100% 100% 100% 28-Sep-14 A 22-Dec-14 A 24-Nov-13
100% 100% 100% 30-Sep-14 A 22-Dec-14 A 26-Nov-13
100% 100% 100% 01-Oct-14 A 22-Dec-14 A 8-Dec-13
100% 100% 100% 01-Oct-14 A 23-Dec-14 A 28-Nov-13
100% 100% 100% 02-Oct-14 A 23-Dec-14 A 24-Nov-13
100% 100% 100% 07-Oct-14 A 23-Dec-14 A 1-Dec-13
100% 100% 100% 07-Oct-14 A 23-Dec-14 A 3-Dec-13
100% 100% 100% 08-Oct-14 A 23-Dec-14 A 5-Dec-13
100% 100% 100% 11-Oct-14 A 24-Dec-14 A 12-Dec-13
100% 99% 03-Sep-12 A 17-Jan-15 -174.00 29-Aug-12
100% 100% 06-Nov-12 A 29-Jul-13 A 29-Aug-12
100% 100% 100% 06-Nov-12 A 22-Nov-12 A 29-Aug-12
100% 100% 100% 01-Dec-12 A 03-Dec-12 A 5-Sep-12
100% 100% 100% 04-Jun-13 A 16-Jun-13 A 5-Sep-12
100% 100% 100% 26-Jun-13 A 02-Jul-13 A 4-Oct-12
100% 100% 100% 17-Jul-13 A 29-Jul-13 A 17-Sep-12
100% 100% 12-Nov-12 A 01-Jan-13 A 17-Sep-12
100% 100% 100% 12-Nov-12 A 04-Dec-12 A 23-Sep-12
100% 100% 100% 03-Dec-12 A 10-Dec-12 A 9-Oct-12
100% 100% 100% 15-Dec-12 A 20-Dec-12 A 17-Sep-12
100% 100% 100% 25-Dec-12 A 27-Dec-12 A 23-Sep-12
100% 100% 100% 29-Dec-12 A 01-Jan-13 A 30-Oct-12
100% 100% 01-Jan-13 A 1-Jan-15 -168.00 4-Oct-12
100% 100% 100% 01-Jan-13 A 10-Jan-13 A 4-Oct-12
100% 100% 100% 05-Jan-13 A 24-Jan-13 A 10-Oct-12
100% 100% 100% 10-Jan-13 A 1-Jan-15 -131.00 10-Oct-12
100% 100% 100% 15-Jan-13 A 20-Jan-13 A 6-Nov-12
100% 100% 100% 22-Jan-13 A 27-Jan-13 A 22-Nov-12
100% 100% 13-Jan-13 A 10-Feb-13 A 22-Oct-12
100% 100% 100% 13-Jan-13 A 23-Jan-13 A 22-Oct-12
100% 100% 100% 17-Jan-13 A 02-Feb-13 A 31-Oct-12
100% 100% 100% 27-Jan-13 A 28-Jan-13 A 31-Oct-12
100% 100% 100% 29-Jan-13 A 02-Feb-13 A 29-Nov-12
100% 100% 100% 05-Feb-13 A 10-Feb-13 A 16-Dec-12
100% 100% 13-Jan-13 A 17-Feb-13 A 12-Nov-12
100% 100% 100% 13-Jan-13 A 24-Jan-13 A 12-Nov-12
100% 100% 100% 15-Jan-13 A 11-Feb-13 A 18-Nov-12
100% 100% 100% 02-Feb-13 A 02-Feb-13 A 18-Nov-12
100% 100% 100% 03-Feb-13 A 13-Feb-13 A 26-Dec-12
100% 100% 100% 14-Feb-13 A 17-Feb-13 A 15-Jan-13
100% 100% 14-Jan-13 A 28-Feb-13 A 29-Nov-12
100% 100% 100% 14-Jan-13 A 24-Jan-13 A 29-Nov-12
100% 100% 100% 15-Jan-13 A 27-Jan-13 A 5-Dec-12
100% 100% 100% 18-Feb-13 A 20-Feb-13 A 21-Jan-13
100% 100% 100% 23-Feb-13 A 24-Feb-13 A 5-Dec-12
100% 100% 100% 25-Feb-13 A 28-Feb-13 A 6-Feb-13
100% 100% 20-Jan-13 A 06-Mar-13 A 17-Dec-12
100% 100% 100% 20-Jan-13 A 29-Jan-13 A 17-Dec-12
100% 100% 100% 22-Jan-13 A 28-Jan-13 A 24-Dec-12
100% 100% 100% 02-Mar-13 A 03-Mar-13 A 24-Dec-12
100% 100% 100% 03-Mar-13 A 04-Mar-13 A 14-Feb-13
100% 100% 100% 04-Mar-13 A 06-Mar-13 A 6-Mar-13
100% 100% 22-Jan-13 A 23-Jun-13 A 5-Jan-13
100% 100% 100% 22-Jan-13 A 27-Jan-13 A 10-Jan-13
100% 100% 100% 23-Jan-13 A 27-Jan-13 A 5-Jan-13
100% 100% 100% 30-Mar-13 A 21-Apr-13 A 16-Mar-13
100% 100% 100% 22-Apr-13 A 23-Jun-13 A 10-Jan-13
100% 100% 100% 27-Apr-13 A 09-May-13 A 1-Apr-13
100% 100% 02-Feb-13 A 05-Jun-13 A 22-Jan-13
100% 100% 100% 02-Feb-13 A 03-Feb-13 A 22-Jan-13
100% 100% 100% 03-Feb-13 A 04-Feb-13 A 28-Jan-13
100% 100% 100% 16-May-13 A 23-May-13 A 10-Apr-13
100% 100% 100% 23-May-13 A 25-May-13 A 28-Jan-13
100% 100% 100% 26-May-13 A 05-Jun-13 A 30-Apr-13
100% 100% 26-Jan-13 A 04-May-13 A 9-Feb-13
100% 100% 100% 26-Jan-13 A 27-Feb-13 A 9-Feb-13
100% 100% 100% 27-Jan-13 A 18-Apr-13 A 16-Feb-13
100% 100% 100% 18-Apr-13 A 18-Apr-13 A 16-Feb-13
100% 100% 100% 20-Apr-13 A 23-Apr-13 A 9-May-13
100% 100% 100% 23-Apr-13 A 04-May-13 A 26-May-13
100% 100% 26-Jan-13 A 01-Dec-13 A 27-Feb-13
100% 100% 100% 26-Jan-13 A 01-Dec-13 A 27-Feb-13
100% 100% 100% 27-Jan-13 A 01-Dec-13 A 5-Mar-13
100% 100% 100% 27-Apr-13 A 30-Apr-13 A 1-Jun-13
100% 100% 100% 23-May-13 A 05-Jun-13 A 5-Mar-13
100% 100% 100% 08-Jun-13 A 13-Jun-13 A 23-Jun-13
100% 100% 04-Feb-13 A 09-Jun-13 A 17-Mar-13
100% 100% 100% 04-Feb-13 A 23-Feb-13 A 17-Mar-13
100% 100% 100% 03-Mar-13 A 06-Mar-13 A 23-Mar-13
100% 100% 100% 13-Mar-13 A 14-Mar-13 A 23-Mar-13
100% 100% 100% 24-Mar-13 A 01-Apr-13 A 30-Jul-13
100% 100% 100% 03-Jun-13 A 09-Jun-13 A 3-Jul-13
100% 100% 02-Mar-13 A 07-May-13 A 3-Apr-13
100% 100% 100% 02-Mar-13 A 06-Mar-13 A 3-Apr-13
100% 100% 100% 02-Mar-13 A 06-Mar-13 A 9-Apr-13
100% 100% 100% 09-Mar-13 A 10-Mar-13 A 9-Apr-13
100% 100% 100% 11-Mar-13 A 30-Apr-13 A 8-Aug-13
100% 100% 100% 02-May-13 A 07-May-13 A 3-Sep-13
100% 100% 24-Nov-12 A 11-Mar-14 A 9-Sep-13
100% 100% 100% 24-Nov-12 A 22-Sep-13 A 9-Sep-13
100% 100% 100% 09-Feb-13 A 23-Sep-13 A 10-Sep-13
100% 100% 100% 14-Feb-13 A 26-Sep-13 A 12-Sep-13
100% 100% 100% 14-Feb-13 A 05-Oct-13 A 15-Sep-13
100% 100% 100% 16-Feb-13 A 07-Oct-13 A 18-Sep-13
100% 100% 100% 23-Feb-13 A 19-Dec-13 A 26-Sep-13
100% 100% 100% 03-Mar-13 A 19-Dec-13 A 3-Oct-13
100% 100% 100% 09-Apr-13 A 21-Dec-13 A 22-Sep-13
100% 100% 100% 13-Apr-13 A 22-Dec-13 A 25-Sep-13
100% 100% 100% 28-Apr-13 A 21-Dec-13 A 29-Sep-13
100% 100% 100% 07-Jul-13 A 11-Mar-14 A 9-Jan-14
100% 100% 25-May-14 A 25-Nov-14 A 14-Nov-13
100% 100% 25-May-14 A 01-Jun-14 A 14-Nov-13
100% 100% 100% 25-May-14 A 26-May-14 A 14-Nov-13
100% 100% 100% 27-May-14 A 28-May-14 A 16-Nov-13
100% 100% 100% 28-May-14 A 29-May-14 A 17-Nov-13
100% 100% 100% 29-May-14 A 29-May-14 A 18-Nov-13
100% 100% 100% 31-May-14 A 31-May-14 A 19-Nov-13
100% 100% 100% 31-May-14 A 01-Jun-14 A 20-Nov-13
100% 100% 01-Jun-14 A 19-Nov-14 A 17-Nov-13
100% 100% 100% 01-Jun-14 A 02-Jun-14 A 17-Nov-13
100% 100% 100% 02-Jun-14 A 02-Jun-14 A 18-Nov-13
100% 100% 100% 03-Jun-14 A 03-Jun-14 A 19-Nov-13
100% 100% 100% 03-Jun-14 A 03-Jun-14 A 20-Nov-13
100% 100% 100% 04-Jun-14 A 04-Jun-14 A 23-Nov-13
100% 100% 100% 04-Jun-14 A 04-Jun-14 A 21-Nov-13
100% 100% 100% 07-Jul-14 A 13-Jul-14 A 24-Nov-13
100% 100% 100% 07-Jul-14 A 13-Jul-14 A 1-Dec-13
100% 100% 100% 09-Jul-14 A 15-Jul-14 A 25-Nov-13
100% 100% 100% 09-Jul-14 A 15-Jul-14 A 2-Dec-13
100% 100% 100% 12-Jul-14 A 17-Jul-14 A 26-Nov-13
100% 100% 100% 16-Nov-14 A 19-Nov-14 A 5-Dec-13
100% 100% 30-Aug-14 A 25-Nov-14 A 26-Nov-13
100% 100% 100% 30-Aug-14 A 08-Nov-14 A 28-Nov-13
100% 100% 100% 02-Sep-14 A 08-Nov-14 A 1-Dec-13
100% 100% 100% 07-Sep-14 A 17-Nov-14 A 12-Dec-13
100% 100% 100% 08-Nov-14 A 10-Nov-14 A 3-Dec-13
100% 100% 100% 10-Nov-14 A 12-Nov-14 A 5-Dec-13
100% 100% 100% 11-Nov-14 A 11-Nov-14 A 26-Nov-13
100% 100% 100% 12-Nov-14 A 15-Nov-14 A 8-Dec-13
100% 100% 100% 15-Nov-14 A 17-Nov-14 A 10-Dec-13
100% 100% 100% 20-Nov-14 A 25-Nov-14 A 17-Dec-13
100% 91% 12-Oct-13 A 6-Jan-15 -171.00 18-Nov-13
100% 100% 12-Oct-13 A 10-Nov-13 A 18-Nov-13
100% 100% 100% 12-Oct-13 A 28-Oct-13 A 18-Nov-13
100% 100% 100% 02-Nov-13 A 04-Nov-13 A 19-Nov-13
100% 100% 100% 02-Nov-13 A 04-Nov-13 A 20-Nov-13
100% 100% 100% 03-Nov-13 A 04-Nov-13 A 21-Nov-13
100% 100% 100% 05-Nov-13 A 06-Nov-13 A 23-Nov-13
100% 100% 100% 05-Nov-13 A 10-Nov-13 A 24-Nov-13
100% 82% 02-Nov-13 A 4-Jan-15 -192.00 20-Nov-13
100% 100% 100% 02-Nov-13 A 03-Nov-13 A 20-Nov-13
100% 100% 100% 03-Nov-13 A 04-Nov-13 A 21-Nov-13
100% 100% 100% 04-Nov-13 A 09-Nov-13 A 23-Nov-13
100% 100% 100% 04-Nov-13 A 11-Nov-13 A 24-Nov-13
100% 100% 100% 05-Nov-13 A 13-Nov-13 A 25-Nov-13
100% 100% 100% 06-Nov-13 A 13-Nov-13 A 26-Nov-13
100% 100% 100% 07-Nov-13 A 22-Dec-13 A 27-Nov-13
100% 100% 100% 07-Nov-13 A 19-Dec-13 A 30-Nov-13
100% 100% 100% 09-Nov-13 A 23-Dec-13 A 28-Nov-13
100% 100% 100% 10-Nov-13 A 22-Dec-13 A 4-Dec-13
100% 100% 100% 11-Nov-13 A 28-Dec-13 A 5-Dec-13
60% 100% 60% 28-Dec-14 A 4-Jan-15 -144.00 14-Dec-13
100% 100% 28-Jun-14 A 06-Jan-15 A 1-Dec-13
100% 100% 100% 28-Jun-14 A 22-Dec-14 A 1-Dec-13
100% 100% 100% 01-Jul-14 A 22-Dec-14 A 4-Dec-13
100% 100% 100% 05-Jul-14 A 23-Dec-14 A 8-Dec-13
100% 100% 100% 13-Jul-14 A 06-Jan-15 A 23-Dec-13
100% 93% 02-Mar-14 A 17-Jan-15 -184.00 26-Nov-13
100% 100% 06-Mar-14 A 16-Jul-14 A 26-Nov-13
100% 100% 100% 06-Mar-14 A 12-Jul-14 A 26-Nov-13
100% 100% 100% 08-Mar-14 A 13-Jul-14 A 28-Nov-13
100% 100% 100% 09-Mar-14 A 14-Jul-14 A 1-Dec-13
100% 100% 100% 10-Mar-14 A 15-Jul-14 A 3-Dec-13
100% 100% 100% 11-Mar-14 A 15-Jul-14 A 5-Dec-13
100% 100% 100% 12-Mar-14 A 16-Jul-14 A 8-Dec-13
100% 83% 02-Mar-14 A 17-Jan-15 -184.00 28-Nov-13
100% 100% 100% 02-Mar-14 A 05-Apr-14 A 28-Nov-13
100% 100% 100% 04-Mar-14 A 06-Apr-14 A 1-Dec-13
100% 100% 100% 05-Mar-14 A 07-Apr-14 A 3-Dec-13
100% 100% 100% 08-Mar-14 A 21-Apr-14 A 5-Dec-13
100% 100% 100% 09-Mar-14 A 22-Apr-14 A 8-Dec-13
100% 100% 100% 12-Mar-14 A 23-Apr-14 A 10-Dec-13
100% 100% 100% 23-Mar-14 A 11-May-14 A 12-Dec-13
100% 100% 100% 23-Mar-14 A 12-May-14 A 19-Dec-13
100% 100% 100% 24-Mar-14 A 13-May-14 A 15-Dec-13
100% 100% 100% 27-Mar-14 A 14-May-14 A 22-Dec-13
100% 100% 100% 27-Mar-14 A 15-May-14 A 17-Dec-13
40% 100% 40% 09-Aug-14 A 17-Jan-15 -144.00 7-Jan-14
0% 0% 01-Jul-14 A 20-Dec-14 A 1-Apr-14
0% 0% 07-Jul-14 A 24-Jul-14 A 1-Apr-14
100% 100% 100% 07-Jul-14 A 17-Jul-14 A 1-Apr-14
100% 100% 100% 08-Jul-14 A 19-Jul-14 A 6-Apr-14
100% 100% 100% 09-Jul-14 A 20-Jul-14 A 8-Apr-14
100% 100% 100% 10-Jul-14 A 21-Jul-14 A 10-Apr-14
100% 100% 100% 12-Jul-14 A 22-Jul-14 A 13-Apr-14
100% 100% 100% 13-Jul-14 A 24-Jul-14 A 15-Apr-14
0% 0% 01-Jul-14 A 20-Dec-14 A 3-Apr-14
100% 100% 100% 01-Jul-14 A 07-Jul-14 A 3-Apr-14
100% 100% 100% 07-Jul-14 A 09-Jul-14 A 7-Apr-14
100% 100% 100% 09-Jul-14 A 10-Jul-14 A 8-Apr-14
100% 100% 100% 10-Jul-14 A 15-Jul-14 A 9-Apr-14
100% 100% 100% 15-Jul-14 A 19-Jul-14 A 12-Apr-14
100% 100% 100% 19-Jul-14 A 20-Jul-14 A 14-Apr-14
100% 100% 100% 20-Jul-14 A 21-Jul-14 A 16-Apr-14
100% 100% 100% 22-Jul-14 A 23-Jul-14 A 16-Apr-14
100% 100% 100% 24-Jul-14 A 25-Jul-14 A 19-Apr-14
100% 100% 100% 24-Jul-14 A 26-Jul-14 A 19-Apr-14
100% 100% 100% 26-Jul-14 A 26-Jul-14 A 19-Apr-14
100% 100% 100% 17-Dec-14 A 20-Dec-14 A 22-Apr-14
100% 100% 07-Jul-14 A 20-Oct-14 A 14-Apr-14
100% 100% 100% 07-Jul-14 A 29-Sep-14 A 14-Apr-14
100% 100% 100% 12-Jul-14 A 29-Sep-14 A 16-Apr-14
100% 100% 100% 21-Jul-14 A 29-Sep-14 A 28-Apr-14
100% 100% 100% 01-Sep-14 A 01-Oct-14 A 14-Apr-14
100% 100% 100% 02-Sep-14 A 01-Oct-14 A 19-Apr-14
100% 100% 100% 03-Sep-14 A 01-Oct-14 A 21-Apr-14
100% 100% 100% 06-Sep-14 A 01-Oct-14 A 23-Apr-14
100% 100% 100% 08-Sep-14 A 01-Oct-14 A 26-Apr-14
100% 100% 100% 10-Sep-14 A 20-Oct-14 A 10-May-14
100% 100% 22-Mar-14 A 11-Nov-14 A 9-Dec-13
100% 100% 22-Mar-14 A 16-Jul-14 A 9-Dec-13
100% 100% 100% 22-Mar-14 A 12-Jul-14 A 9-Dec-13
100% 100% 100% 29-Mar-14 A 13-Jul-14 A 11-Dec-13
100% 100% 100% 29-Mar-14 A 14-Jul-14 A 14-Dec-13
100% 100% 100% 30-Mar-14 A 15-Jul-14 A 16-Dec-13
100% 100% 100% 01-Apr-14 A 16-Jul-14 A 19-Dec-13
100% 100% 100% 01-Apr-14 A 16-Jul-14 A 22-Dec-13
100% 100% 29-Mar-14 A 09-Nov-14 A 14-Dec-13
100% 100% 100% 29-Mar-14 A 26-Apr-14 A 14-Dec-13
100% 100% 100% 30-Mar-14 A 27-Apr-14 A 16-Dec-13
100% 100% 100% 31-Mar-14 A 27-Apr-14 A 19-Dec-13
100% 100% 100% 01-Apr-14 A 28-Apr-14 A 22-Dec-13
100% 100% 100% 03-Apr-14 A 28-Apr-14 A 24-Dec-13
100% 100% 100% 05-Apr-14 A 29-Apr-14 A 26-Dec-13
100% 100% 100% 07-Apr-14 A 25-May-14 A 4-Jan-14
100% 100% 100% 26-Apr-14 A 26-May-14 A 29-Dec-13
100% 100% 100% 27-Apr-14 A 27-May-14 A 31-Dec-13
100% 100% 100% 28-Apr-14 A 27-May-14 A 6-Jan-14
100% 100% 100% 28-Apr-14 A 25-May-14 A 2-Jan-14
100% 100% 100% 28-Oct-14 A 09-Nov-14 A 29-Jan-14
0% 0% 28-Jun-14 A 11-Nov-14 A 7-Apr-14
0% 0% 28-Jun-14 A 24-Jul-14 A 7-Apr-14
100% 100% 100% 28-Jun-14 A 07-Jul-14 A 7-Apr-14
100% 100% 100% 05-Jul-14 A 07-Jul-14 A 12-Apr-14
100% 100% 100% 09-Jul-14 A 10-Jul-14 A 14-Apr-14
100% 100% 100% 13-Jul-14 A 15-Jul-14 A 16-Apr-14
100% 100% 100% 16-Jul-14 A 19-Jul-14 A 19-Apr-14
100% 100% 100% 21-Jul-14 A 24-Jul-14 A 21-Apr-14
0% 0% 05-Jul-14 A 11-Nov-14 A 12-Apr-14
100% 100% 100% 05-Jul-14 A 10-Jul-14 A 12-Apr-14
100% 100% 100% 09-Jul-14 A 10-Jul-14 A 14-Apr-14
100% 100% 100% 10-Jul-14 A 13-Jul-14 A 15-Apr-14
100% 100% 100% 13-Jul-14 A 16-Jul-14 A 16-Apr-14
100% 100% 100% 16-Jul-14 A 21-Jul-14 A 19-Apr-14
100% 100% 100% 21-Jul-14 A 24-Jul-14 A 21-Apr-14
100% 100% 100% 22-Jul-14 A 31-Jul-14 A 23-Apr-14
100% 100% 100% 24-Jul-14 A 31-Jul-14 A 26-Apr-14
100% 100% 100% 24-Jul-14 A 31-Jul-14 A 23-Apr-14
100% 100% 100% 26-Jul-14 A 31-Jul-14 A 26-Apr-14
100% 100% 100% 27-Jul-14 A 31-Jul-14 A 28-Apr-14
100% 100% 100% 09-Nov-14 A 11-Nov-14 A 29-Apr-14
100% 100% 17-Jul-14 A 15-Oct-14 A 27-Apr-14
100% 100% 100% 17-Jul-14 A 13-Oct-14 A 29-Apr-14
100% 100% 100% 21-Jul-14 A 13-Oct-14 A 1-May-14
100% 100% 100% 23-Jul-14 A 13-Oct-14 A 13-May-14
100% 100% 100% 06-Sep-14 A 13-Oct-14 A 27-Apr-14
100% 100% 100% 07-Sep-14 A 13-Oct-14 A 4-May-14
100% 100% 100% 08-Sep-14 A 13-Oct-14 A 6-May-14
100% 100% 100% 09-Sep-14 A 13-Oct-14 A 8-May-14
100% 100% 100% 10-Sep-14 A 13-Oct-14 A 11-May-14
100% 100% 100% 11-Sep-14 A 15-Oct-14 A 31-May-14
100% 97% 03-Sep-12 A 1-Jan-15 -168.00 24-Dec-13
100% 100% 03-Sep-12 A 07-May-14 A 24-Dec-13
100% 100% 100% 03-Sep-12 A 04-May-14 A 24-Dec-13
100% 100% 100% 22-Sep-12 A 05-May-14 A 25-Dec-13
100% 100% 100% 23-Sep-12 A 06-May-14 A 26-Dec-13
100% 100% 100% 24-Sep-12 A 06-May-14 A 29-Dec-13
100% 100% 100% 24-Sep-12 A 07-May-14 A 28-Dec-13
100% 100% 100% 29-Sep-12 A 07-May-14 A 30-Dec-13
100% 100% 15-Sep-12 A 10-Nov-14 A 1-Jan-14
100% 100% 100% 15-Sep-12 A 16-Dec-12 A 1-Jan-14
100% 100% 100% 17-Sep-12 A 16-Dec-12 A 2-Jan-14
100% 100% 100% 19-Sep-12 A 17-Dec-12 A 4-Jan-14
100% 100% 100% 20-Sep-12 A 17-Dec-12 A 5-Jan-14
100% 100% 100% 29-Sep-12 A 23-Dec-12 A 6-Jan-14
100% 100% 100% 30-Sep-12 A 09-Jan-13 A 7-Jan-14
100% 100% 100% 22-Dec-12 A 28-Mar-13 A 15-Jan-14
100% 100% 100% 05-Jan-13 A 31-Mar-13 A 16-Jan-14
100% 100% 100% 07-Jan-13 A 28-Mar-13 A 8-Jan-14
100% 100% 100% 24-Feb-13 A 10-Nov-14 A 23-Jan-14
100% 100% 100% 02-Mar-13 A 07-Mar-13 A 9-Jan-14
100% 100% 100% 02-Mar-14 A 05-Mar-14 A 11-Jan-14
100% 93% 10-Nov-12 A 1-Jan-15 -168.00 14-Jan-14
100% 100% 100% 10-Nov-12 A 14-Oct-14 A 16-Jan-14
100% 100% 100% 12-Dec-12 A 14-Oct-14 A 19-Jan-14
100% 100% 100% 15-Dec-12 A 23-Oct-14 A 30-Jan-14
90% 100% 90% 12-Oct-14 A 1-Jan-15 -132.00 14-Jan-14
90% 100% 90% 13-Oct-14 A 1-Jan-15 -132.00 21-Jan-14
90% 100% 90% 14-Oct-14 A 1-Jan-15 -132.00 23-Jan-14
90% 100% 90% 16-Oct-14 A 1-Jan-15 -132.00 28-Jan-14
90% 100% 90% 16-Oct-14 A 1-Jan-15 -132.00 5-Feb-14
90% 100% 90% 16-Oct-14 A 1-Jan-15 -132.00 26-Jan-14
100% 100% 21-Dec-13 A 11-Nov-14 A 31-Dec-13
100% 100% 15-Feb-14 A 27-Jul-14 A 31-Dec-13
100% 100% 100% 15-Feb-14 A 26-Jul-14 A 31-Dec-13
100% 100% 100% 17-Feb-14 A 26-Jul-14 A 2-Jan-14
100% 100% 100% 17-Feb-14 A 26-Jul-14 A 5-Jan-14
100% 100% 100% 18-Feb-14 A 27-Jul-14 A 9-Jan-14
100% 100% 100% 18-Feb-14 A 27-Jul-14 A 7-Jan-14
100% 100% 100% 19-Feb-14 A 27-Jul-14 A 12-Jan-14
100% 100% 21-Dec-13 A 09-Nov-14 A 2-Jan-14
100% 100% 100% 21-Dec-13 A 27-May-14 A 2-Jan-14
100% 100% 100% 08-Feb-14 A 08-Jun-14 A 5-Jan-14
100% 100% 100% 13-Feb-14 A 09-Jun-14 A 7-Jan-14
100% 100% 100% 15-Feb-14 A 10-Jun-14 A 9-Jan-14
100% 100% 100% 17-Feb-14 A 11-Jun-14 A 12-Jan-14
100% 100% 100% 18-Feb-14 A 11-Jun-14 A 14-Jan-14
100% 100% 100% 01-Mar-14 A 28-Jun-14 A 16-Jan-14
100% 100% 100% 03-Mar-14 A 29-Jun-14 A 22-Jan-14
100% 100% 100% 04-Mar-14 A 30-Jun-14 A 19-Jan-14
100% 100% 100% 06-Mar-14 A 30-Jun-14 A 25-Jan-14
100% 100% 100% 06-Mar-14 A 30-Jun-14 A 21-Jan-14
100% 100% 100% 11-Oct-14 A 09-Nov-14 A 25-Feb-14
0% 0% 09-Jul-14 A 11-Nov-14 A 17-Apr-14
0% 0% 15-Jul-14 A 27-Jul-14 A 17-Apr-14
100% 100% 100% 15-Jul-14 A 24-Jul-14 A 17-Apr-14
100% 100% 100% 22-Jul-14 A 24-Jul-14 A 22-Apr-14
100% 100% 100% 23-Jul-14 A 24-Jul-14 A 24-Apr-14
100% 100% 100% 24-Jul-14 A 26-Jul-14 A 29-Apr-14
100% 100% 100% 24-Jul-14 A 26-Jul-14 A 27-Apr-14
100% 100% 100% 24-Jul-14 A 27-Jul-14 A 1-May-14
0% 0% 09-Jul-14 A 11-Nov-14 A 20-Apr-14
100% 100% 100% 09-Jul-14 A 15-Jul-14 A 20-Apr-14
100% 100% 100% 15-Jul-14 A 16-Jul-14 A 23-Apr-14
100% 100% 100% 16-Jul-14 A 19-Jul-14 A 24-Apr-14
100% 100% 100% 19-Jul-14 A 22-Jul-14 A 26-Apr-14
100% 100% 100% 22-Jul-14 A 30-Jul-14 A 28-Apr-14
100% 100% 100% 24-Jul-14 A 26-Jul-14 A 30-Apr-14
100% 100% 100% 26-Jul-14 A 02-Aug-14 A 3-May-14
100% 100% 100% 26-Jul-14 A 02-Aug-14 A 3-May-14
100% 100% 100% 02-Aug-14 A 05-Aug-14 A 5-May-14
100% 100% 100% 02-Aug-14 A 06-Aug-14 A 5-May-14
100% 100% 100% 02-Aug-14 A 03-Aug-14 A 5-May-14
100% 100% 100% 09-Nov-14 A 11-Nov-14 A 8-May-14
100% 100% 17-Aug-14 A 16-Oct-14 A 3-May-14
100% 100% 100% 17-Aug-14 A 13-Oct-14 A 5-May-14
100% 100% 100% 18-Aug-14 A 13-Oct-14 A 7-May-14
100% 100% 100% 19-Aug-14 A 13-Oct-14 A 19-May-14
100% 100% 100% 15-Sep-14 A 13-Oct-14 A 3-May-14
100% 100% 100% 16-Sep-14 A 13-Oct-14 A 10-May-14
100% 100% 100% 17-Sep-14 A 13-Oct-14 A 12-May-14
100% 100% 100% 18-Sep-14 A 13-Oct-14 A 14-May-14
100% 100% 100% 20-Sep-14 A 13-Oct-14 A 17-May-14
100% 100% 100% 22-Sep-14 A 16-Oct-14 A 25-Jun-14
100% 100% 12-May-13 A 06-Nov-14 A 14-Jan-14
100% 100% 12-May-13 A 14-Jun-14 A 14-Jan-14
100% 100% 100% 12-May-13 A 14-Jun-14 A 14-Jan-14
100% 100% 100% 01-Feb-14 A 14-Jun-14 A 16-Jan-14
100% 100% 100% 02-Feb-14 A 14-Jun-14 A 19-Jan-14
100% 100% 100% 03-Feb-14 A 14-Jun-14 A 21-Jan-14
100% 100% 100% 04-Feb-14 A 14-Jun-14 A 23-Jan-14
100% 100% 100% 05-Feb-14 A 14-Jun-14 A 26-Jan-14
100% 100% 26-Jan-14 A 09-Oct-14 A 16-Jan-14
100% 100% 100% 26-Jan-14 A 09-Apr-14 A 16-Jan-14
100% 100% 100% 28-Jan-14 A 19-Apr-14 A 19-Jan-14
100% 100% 100% 29-Jan-14 A 20-Apr-14 A 21-Jan-14
100% 100% 100% 30-Jan-14 A 21-Apr-14 A 23-Jan-14
100% 100% 100% 01-Feb-14 A 22-Apr-14 A 26-Jan-14
100% 100% 100% 03-Feb-14 A 22-Apr-14 A 28-Jan-14
100% 100% 100% 04-Feb-14 A 08-Jun-14 A 30-Jan-14
100% 100% 100% 06-Feb-14 A 09-Jun-14 A 2-Feb-14
100% 100% 100% 06-Feb-14 A 10-Jun-14 A 5-Feb-14
100% 100% 100% 12-Feb-14 A 12-Jun-14 A 8-Feb-14
100% 100% 100% 12-Feb-14 A 11-Jun-14 A 4-Feb-14
100% 100% 100% 22-Sep-14 A 09-Oct-14 A 2-Mar-14
0% 0% 15-Jun-14 A 05-Oct-14 A 23-Apr-14
0% 0% 24-Jul-14 A 24-Aug-14 A 23-Apr-14
100% 100% 100% 24-Jul-14 A 19-Aug-14 A 23-Apr-14
100% 100% 100% 25-Jul-14 A 20-Aug-14 A 29-Apr-14
100% 100% 100% 26-Jul-14 A 21-Aug-14 A 1-May-14
100% 100% 100% 26-Jul-14 A 21-Aug-14 A 4-May-14
100% 100% 100% 27-Jul-14 A 23-Aug-14 A 6-May-14
100% 100% 100% 27-Jul-14 A 24-Aug-14 A 8-May-14
0% 0% 15-Jun-14 A 05-Oct-14 A 26-Apr-14
100% 100% 100% 15-Jun-14 A 19-Jun-14 A 26-Apr-14
100% 100% 100% 19-Jun-14 A 21-Jun-14 A 29-Apr-14
100% 100% 100% 21-Jun-14 A 22-Jun-14 A 30-Apr-14
100% 100% 100% 22-Jun-14 A 25-Jun-14 A 1-May-14
100% 100% 100% 25-Jun-14 A 29-Jun-14 A 4-May-14
100% 100% 100% 29-Jun-14 A 02-Jul-14 A 6-May-14
100% 100% 100% 02-Jul-14 A 06-Jul-14 A 8-May-14
100% 100% 100% 02-Jul-14 A 06-Jul-14 A 8-May-14
100% 100% 100% 06-Jul-14 A 10-Jul-14 A 11-May-14
100% 100% 100% 06-Jul-14 A 12-Jul-14 A 11-May-14
100% 100% 100% 06-Jul-14 A 08-Jul-14 A 11-May-14
100% 100% 100% 12-Jul-14 A 05-Oct-14 A 14-May-14
100% 100% 13-Aug-14 A 06-Nov-14 A 8-May-14
100% 100% 100% 13-Aug-14 A 06-Nov-14 A 11-May-14
100% 100% 100% 14-Aug-14 A 06-Nov-14 A 13-May-14
100% 100% 100% 14-Aug-14 A 06-Nov-14 A 25-May-14
100% 100% 100% 12-Oct-14 A 06-Nov-14 A 8-May-14
100% 100% 100% 13-Oct-14 A 06-Nov-14 A 15-May-14
100% 100% 100% 13-Oct-14 A 06-Nov-14 A 18-May-14
100% 100% 100% 14-Oct-14 A 06-Nov-14 A 20-May-14
100% 100% 100% 15-Oct-14 A 06-Nov-14 A 22-May-14
100% 100% 100% 16-Oct-14 A 06-Nov-14 A 14-Jun-14
100% 100% 20-Apr-13 A 15-Oct-14 A 28-Jan-14
100% 100% 20-Apr-13 A 14-Aug-14 A 28-Jan-14
100% 100% 100% 20-Apr-13 A 11-Aug-14 A 28-Jan-14
100% 100% 100% 11-Jan-14 A 12-Aug-14 A 30-Jan-14
100% 100% 100% 12-Jan-14 A 12-Aug-14 A 2-Feb-14
100% 100% 100% 13-Jan-14 A 13-Aug-14 A 4-Feb-14
100% 100% 100% 15-Jan-14 A 14-Aug-14 A 6-Feb-14
100% 100% 100% 15-Jan-14 A 14-Aug-14 A 9-Feb-14
100% 100% 07-Dec-13 A 07-Oct-14 A 30-Jan-14
100% 100% 100% 07-Dec-13 A 04-Mar-14 A 30-Jan-14
100% 100% 100% 23-Dec-13 A 09-Mar-14 A 2-Feb-14
100% 100% 100% 24-Dec-13 A 10-Mar-14 A 4-Feb-14
100% 100% 100% 25-Dec-13 A 11-Mar-14 A 6-Feb-14
100% 100% 100% 04-Jan-14 A 12-Mar-14 A 9-Feb-14
100% 100% 100% 06-Jan-14 A 20-Apr-14 A 12-Feb-14
100% 100% 100% 08-Jan-14 A 21-Apr-14 A 15-Feb-14
100% 100% 100% 09-Jan-14 A 22-Apr-14 A 17-Feb-14
100% 100% 100% 11-Jan-14 A 23-Apr-14 A 20-Feb-14
100% 100% 100% 11-Jan-14 A 23-Apr-14 A 23-Feb-14
100% 100% 100% 13-Jan-14 A 19-May-14 A 19-Feb-14
100% 100% 100% 01-Sep-14 A 07-Oct-14 A 15-Mar-14
0% 0% 26-Jun-14 A 06-Oct-14 A 4-May-14
0% 0% 26-Jul-14 A 18-Aug-14 A 4-May-14
100% 100% 100% 26-Jul-14 A 06-Aug-14 A 4-May-14
100% 100% 100% 09-Aug-14 A 09-Aug-14 A 8-May-14
100% 100% 100% 11-Aug-14 A 14-Aug-14 A 11-May-14
100% 100% 100% 13-Aug-14 A 14-Aug-14 A 13-May-14
100% 100% 100% 14-Aug-14 A 14-Aug-14 A 15-May-14
100% 100% 100% 14-Aug-14 A 18-Aug-14 A 18-May-14
0% 0% 26-Jun-14 A 06-Oct-14 A 8-May-14
100% 100% 100% 26-Jun-14 A 02-Jul-14 A 8-May-14
100% 100% 100% 02-Jul-14 A 05-Jul-14 A 12-May-14
100% 100% 100% 05-Jul-14 A 06-Jul-14 A 13-May-14
100% 100% 100% 06-Jul-14 A 10-Jul-14 A 14-May-14
100% 100% 100% 10-Jul-14 A 14-Jul-14 A 17-May-14
100% 100% 100% 14-Jul-14 A 17-Jul-14 A 19-May-14
100% 100% 100% 17-Jul-14 A 22-Jul-14 A 21-May-14
100% 100% 100% 17-Jul-14 A 22-Jul-14 A 21-May-14
100% 100% 100% 22-Jul-14 A 26-Jul-14 A 24-May-14
100% 100% 100% 22-Jul-14 A 30-Jul-14 A 24-May-14
100% 100% 100% 22-Jul-14 A 23-Jul-14 A 24-May-14
100% 100% 100% 04-Oct-14 A 06-Oct-14 A 27-May-14
100% 100% 03-Aug-14 A 15-Oct-14 A 21-May-14
100% 100% 100% 03-Aug-14 A 13-Oct-14 A 25-May-14
100% 100% 100% 04-Aug-14 A 13-Oct-14 A 27-May-14
100% 100% 100% 06-Aug-14 A 14-Oct-14 A 10-Jun-14
100% 100% 100% 04-Oct-14 A 15-Oct-14 A 21-May-14
100% 100% 100% 07-Oct-14 A 15-Oct-14 A 29-May-14
100% 100% 100% 09-Oct-14 A 15-Oct-14 A 1-Jun-14
100% 100% 100% 10-Oct-14 A 15-Oct-14 A 7-Jun-14
100% 100% 100% 10-Oct-14 A 15-Oct-14 A 24-Jun-14
100% 100% 100% 10-Oct-14 A 15-Oct-14 A 4-Jun-14
100% 100% 20-Mar-13 A 16-Oct-14 A 13-Feb-14
100% 100% 20-Mar-13 A 15-May-14 A 13-Feb-14
100% 100% 100% 20-Mar-13 A 11-May-14 A 13-Feb-14
100% 100% 100% 04-Apr-13 A 12-May-14 A 16-Feb-14
100% 100% 100% 06-Apr-13 A 13-May-14 A 18-Feb-14
100% 100% 100% 06-Apr-13 A 13-May-14 A 20-Feb-14
100% 100% 100% 07-Apr-13 A 14-May-14 A 23-Feb-14
100% 100% 100% 07-Apr-13 A 15-May-14 A 25-Feb-14
100% 100% 06-Apr-13 A 15-Jul-14 A 13-Feb-14
100% 100% 100% 06-Apr-13 A 03-Jun-13 A 13-Feb-14
100% 100% 100% 07-Apr-13 A 08-Jun-13 A 16-Feb-14
100% 100% 100% 08-Apr-13 A 09-Jun-13 A 18-Feb-14
100% 100% 100% 08-Apr-13 A 09-Jun-13 A 20-Feb-14
100% 100% 100% 27-Apr-13 A 12-May-14 A 23-Feb-14
100% 100% 100% 30-Apr-13 A 14-May-14 A 25-Feb-14
100% 100% 100% 04-May-13 A 08-Jun-14 A 8-Mar-14
100% 100% 100% 11-May-13 A 09-Jun-14 A 27-Feb-14
100% 100% 100% 13-May-13 A 10-Jun-14 A 2-Mar-14
100% 100% 100% 27-May-13 A 11-Jun-14 A 5-Mar-14
100% 100% 100% 03-Jun-13 A 12-Jun-14 A 4-Mar-14
100% 100% 100% 10-Jun-13 A 15-Jul-14 A 22-Mar-14
100% 100.00% 01-Jul-13 A 16-Oct-14 A 13-Mar-14
100% 100% 100% 01-Jul-13 A 13-Oct-14 A 16-Mar-14
100% 100% 100% 06-Jul-13 A 13-Oct-14 A 18-Mar-14
100% 100% 100% 13-Jul-13 A 13-Oct-14 A 13-Mar-14
100% 100% 100% 11-Oct-14 A 13-Oct-14 A 20-Mar-14
100% 100% 100% 12-Oct-14 A 14-Oct-14 A 23-Mar-14
100% 100% 100% 13-Oct-14 A 15-Oct-14 A 25-Mar-14
100% 100% 100% 14-Oct-14 A 16-Oct-14 A 27-Mar-14
100% 100% 100% 14-Oct-14 A 16-Oct-14 A 30-Mar-14
100% 100% 100% 15-Oct-14 A 16-Oct-14 A 7-Apr-14
100% 100.00% 08-Apr-13 A 23-Dec-14 A 26-Feb-14
100% 100.00% 08-Apr-13 A 27-Aug-14 A 26-Feb-14
100% 100% 100% 08-Apr-13 A 20-Aug-14 A 26-Feb-14
100% 100% 100% 25-Dec-13 A 26-Aug-14 A 27-Feb-14
100% 100% 100% 26-Dec-13 A 26-Aug-14 A 1-Mar-14
100% 100% 100% 28-Dec-13 A 26-Aug-14 A 3-Mar-14
100% 100% 100% 28-Dec-13 A 26-Aug-14 A 2-Mar-14
100% 100% 100% 29-Dec-13 A 27-Aug-14 A 4-Mar-14
100% 100.00% 12-Dec-13 A 25-Sep-14 A 26-Feb-14
100% 100% 100% 12-Dec-13 A 20-Aug-14 A 26-Feb-14
100% 100% 100% 14-Dec-13 A 21-Aug-14 A 27-Feb-14
100% 100% 100% 15-Dec-13 A 23-Aug-14 A 1-Mar-14
100% 100% 100% 15-Dec-13 A 24-Aug-14 A 2-Mar-14
100% 100% 100% 17-Dec-13 A 25-Aug-14 A 3-Mar-14
100% 100% 100% 19-Dec-13 A 26-Aug-14 A 4-Mar-14
100% 100% 100% 22-Dec-13 A 27-Aug-14 A 6-Mar-14
100% 100% 100% 22-Dec-13 A 28-Aug-14 A 12-Mar-14
100% 100% 100% 23-Dec-13 A 28-Aug-14 A 8-Mar-14
100% 100% 100% 28-Dec-13 A 28-Aug-14 A 15-Mar-14
100% 100% 100% 28-Dec-13 A 26-Aug-14 A 9-Mar-14
100% 100% 100% 07-Sep-14 A 25-Sep-14 A 23-Mar-14
0% 0% 06-Aug-14 A 23-Dec-14 A 10-May-14
0% 0% 06-Aug-14 A 28-Aug-14 A 10-May-14
100% 100% 100% 06-Aug-14 A 14-Aug-14 A 10-May-14
100% 100% 100% 12-Aug-14 A 14-Aug-14 A 14-May-14
100% 100% 100% 14-Aug-14 A 16-Aug-14 A 15-May-14
100% 100% 100% 16-Aug-14 A 17-Aug-14 A 17-May-14
100% 100% 100% 17-Aug-14 A 18-Aug-14 A 18-May-14
100% 100% 100% 18-Aug-14 A 28-Aug-14 A 19-May-14
0% 0% 06-Aug-14 A 23-Dec-14 A 10-May-14
100% 100% 100% 06-Aug-14 A 12-Aug-14 A 10-May-14
100% 100% 100% 12-Aug-14 A 16-Aug-14 A 14-May-14
100% 100% 100% 14-Aug-14 A 18-Aug-14 A 17-May-14
100% 100% 100% 16-Aug-14 A 19-Aug-14 A 19-May-14
100% 100% 100% 17-Aug-14 A 20-Aug-14 A 24-May-14
100% 100% 100% 18-Aug-14 A 21-Aug-14 A 26-May-14
100% 100% 100% 19-Aug-14 A 23-Dec-14 A 31-May-14
100% 100% 100% 19-Aug-14 A 01-Sep-14 A 31-May-14
100% 100% 100% 20-Aug-14 A 02-Sep-14 A 31-May-14
100% 100% 100% 20-Aug-14 A 28-Aug-14 A 31-May-14
100% 100% 100% 21-Aug-14 A 03-Sep-14 A 2-Jun-14
100% 100% 100% 13-Sep-14 A 15-Sep-14 A 8-Jun-14
100% 100.00% 20-Jan-14 A 16-Oct-14 A 7-Jun-14
100.00% 100% 100.00% 20-Jan-14 A 14-Oct-14 A 10-Jun-14
100.00% 100% 100.00% 25-Jan-14 A 14-Oct-14 A 12-Jun-14
100% 100% 100% 02-Feb-14 A 14-Oct-14 A 28-Jun-14
100% 100% 100% 12-Oct-14 A 13-Oct-14 A 7-Jun-14
100% 100% 100% 13-Oct-14 A 14-Oct-14 A 16-Jun-14
100% 100% 100% 15-Oct-14 A 16-Oct-14 A 18-Jun-14
100% 100% 100% 15-Oct-14 A 16-Oct-14 A 22-Jun-14
100% 100% 100% 16-Oct-14 A 16-Oct-14 A 24-Jun-14
100% 100% 100% 16-Oct-14 A 16-Oct-14 A 5-Jul-14
100% 100.00% 03-Apr-13 A 22-Dec-14 A 5-Mar-14
100% 100% 03-Apr-13 A 06-Jun-13 A 5-Mar-14
100% 100% 100% 03-Apr-13 A 14-Apr-13 A 5-Mar-14
100% 100% 100% 06-Apr-13 A 12-May-13 A 6-Mar-14
100% 100% 100% 07-Apr-13 A 13-May-13 A 8-Mar-14
100% 100% 100% 10-Apr-13 A 13-May-13 A 9-Mar-14
100% 100% 100% 27-Apr-13 A 04-Jun-13 A 10-Mar-14
100% 100% 100% 30-Apr-13 A 06-Jun-13 A 11-Mar-14
100% 100.00% 18-Apr-13 A 11-Nov-14 A 8-Mar-14
100% 100% 100% 18-Apr-13 A 11-May-13 A 8-Mar-14
100% 100% 100% 20-Apr-13 A 13-May-13 A 9-Mar-14
100% 100% 100% 21-Apr-13 A 18-May-13 A 10-Mar-14
100% 100% 100% 22-Apr-13 A 13-May-13 A 11-Mar-14
100% 100% 100% 27-Apr-13 A 14-May-13 A 12-Mar-14
100% 100% 100% 28-Apr-13 A 15-May-13 A 13-Mar-14
100% 100% 100% 04-May-13 A 08-Jun-13 A 16-Mar-14
100% 100% 100% 05-May-13 A 09-Jun-13 A 17-Mar-14
100% 100% 100% 05-May-13 A 10-Jun-13 A 22-Mar-14
100% 100% 100% 07-May-13 A 10-Jun-13 A 23-Mar-14
100% 100% 100% 08-May-13 A 12-Jun-13 A 18-Mar-14
100% 100% 100% 13-Jun-13 A 11-Nov-14 A 31-Mar-14
100% 100.00% 16-Jun-13 A 22-Dec-14 A 25-Mar-14
100% 100% 100% 16-Jun-13 A 22-Dec-14 A 26-Mar-14
100% 100% 100% 19-Jun-13 A 22-Dec-14 A 27-Mar-14
100% 100% 100% 29-Jun-13 A 22-Dec-14 A 2-Apr-14
100% 100% 100% 04-Oct-14 A 22-Dec-14 A 25-Mar-14
100% 100% 100% 05-Oct-14 A 22-Dec-14 A 29-Mar-14
100% 100% 100% 06-Oct-14 A 22-Dec-14 A 30-Mar-14
100% 100% 100% 07-Oct-14 A 22-Dec-14 A 31-Mar-14
100% 100% 100% 08-Oct-14 A 22-Dec-14 A 1-Apr-14
100% 100% 100% 09-Oct-14 A 22-Dec-14 A 8-Apr-14
0% 0% 5-Feb-15 14-Feb-15 -195.00 17-Jul-14
0% 100% 0% 5-Feb-15 14-Feb-15 -161.00 17-Jul-14
0% 100% 0% 5-Feb-15 14-Feb-15 -161.00 17-Jul-14
BL1 Finish Budgeted NonlaboCalendar Budgeted Total CoSchedule PerformPercent Co
3-Aug-14 QAR0.00 QAR52,101,812.10 $1
3-Aug-14 QAR0.00 QAR7,652,092.75 1
3-Aug-14 QAR0.00 QAR0.00 $0
QAR0.00 CP 745/2 QAR0.00 $0 Duration
3-Aug-14 QAR0.00 7 Days Working QAR0.00 $0 Duration
3-Aug-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
3-Aug-14 QAR0.00 QAR7,652,092.75 $1
3-Aug-14 QAR0.00 7 Days Working QAR0.00 $0 Duration
4-Aug-12 QAR0.00 CP 745/2 QAR395,298.25 $1 Duration
4-Aug-12 QAR0.00 CP 745/2 QAR901,296.25 $1 Duration
3-Aug-14 QAR0.00 7 Days Working QAR5,331,554.25 $1 Duration
3-Aug-14 QAR0.00 7 Days Working QAR842,670.00 $1 Duration
3-Aug-14 QAR0.00 CP 745/2 QAR181,274.00 $1 Duration
2-Aug-14 QAR0.00 QAR0.00 $0
23-Jul-12 QAR0.00 QAR0.00 $0
26-May-12 QAR0.00 QAR0.00 $0
26-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
12-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
12-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
21-Jun-12 QAR0.00 QAR0.00 $0
21-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
14-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
2-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
2-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
26-Jun-12 QAR0.00 QAR0.00 $0
30-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
13-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Jun-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Jun-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Jul-12 QAR0.00 QAR0.00 $0
26-Jun-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Jul-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
27-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Jul-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
2-Aug-14 QAR0.00 QAR0.00 $0
17-Mar-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
2-Aug-14 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
11-Aug-12 QAR0.00 QAR0.00 $0
16-Jul-12 QAR0.00 QAR0.00 $0
26-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
16-Jul-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
31-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
16-Jul-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-Jun-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-Aug-12 QAR0.00 QAR0.00 $0
16-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
11-Aug-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
16-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
21-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
11-Aug-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
5-Jul-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
26-Jun-12 QAR0.00 QAR0.00 $0
12-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Jun-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
16-Jul-12 QAR0.00 QAR0.00 $0
2-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
4-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
7-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
7-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
13-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
16-Jul-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
13-Jun-12 QAR0.00 CP 745/2 C QAR0.00 $0 Duration
4-Dec-12 QAR0.00 QAR0.00 $0
2-Dec-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Oct-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
22-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
4-Dec-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
15-Oct-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
25-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
25-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
3-Aug-14 QAR0.00 QAR44,449,719.35 $1
2-Sep-12 QAR0.00 QAR312,287.25 $1
2-Jul-12 QAR0.00 QAR0.00 $0
27-May-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
2-Jul-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
2-Jul-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
2-Aug-12 QAR0.00 QAR147,513.25 $1
17-Jul-12 QAR0.00 CP 745/2 QAR44,253.75 $1 Duration
22-Jul-12 QAR0.00 CP 745/2 QAR25,076.75 $1 Duration
31-Jul-12 QAR0.00 CP 745/2 QAR7,376.00 $1 Duration
23-Jul-12 QAR0.00 CP 745/2 QAR44,253.75 $1 Duration
28-Jul-12 QAR0.00 CP 745/2 QAR17,702.00 $1 Duration
2-Aug-12 QAR0.00 CP 745/2 QAR8,851.00 $1 Duration
30-Aug-12 QAR0.00 QAR130,165.00 $1
11-Jul-12 QAR0.00 CP 745/2 QAR6,308.75 $1 Duration
14-Jul-12 QAR0.00 CP 745/2 QAR1,146.75 $1 Duration
16-Jul-12 QAR0.00 CP 745/2 QAR574.00 $1 Duration
17-Jul-12 QAR0.00 CP 745/2 QAR11,471.75 $1 Duration
19-Jul-12 QAR0.00 CP 745/2 QAR13,191.75 $1 Duration
22-Jul-12 QAR0.00 CP 745/2 QAR14,340.00 $1 Duration
29-Jul-12 QAR0.00 CP 745/2 QAR1,147.00 $1 Duration
30-Aug-12 QAR0.00 CP 745/2 QAR72,807.00 $1 Duration
4-Aug-12 QAR0.00 CP 745/2 QAR1,721.00 $1 Duration
25-Jul-12 QAR0.00 CP 745/2 QAR1,721.00 $1 Duration
8-Aug-12 QAR0.00 CP 745/2 QAR4,589.00 $1 Duration
28-Jul-12 QAR0.00 CP 745/2 QAR1,147.00 $1 Duration
2-Sep-12 QAR0.00 QAR34,609.00 $1
31-Jul-12 QAR0.00 CP 745/2 QAR11,434.00 $1 Duration
9-Aug-12 QAR0.00 CP 745/2 QAR14,700.00 $1 Duration
23-Aug-12 QAR0.00 CP 745/2 QAR6,534.00 $1 Duration
2-Sep-12 QAR0.00 CP 745/2 QAR1,941.00 $1 Duration
8-Oct-12 QAR0.00 QAR940,954.75 $1
13-Sep-12 QAR0.00 QAR348,389.25 $1
29-Aug-12 QAR0.00 CP 745/2 QAR104,516.75 $1 Duration
2-Sep-12 QAR0.00 CP 745/2 QAR59,225.75 $1 Duration
5-Sep-12 QAR0.00 CP 745/2 QAR104,516.75 $1 Duration
9-Sep-12 QAR0.00 CP 745/2 QAR41,807.00 $1 Duration
12-Sep-12 QAR0.00 CP 745/2 QAR17,420.00 $1 Duration
13-Sep-12 QAR0.00 CP 745/2 QAR20,903.00 $1 Duration
8-Oct-12 QAR0.00 QAR440,241.50 $1
15-Aug-12 QAR0.00 CP 745/2 QAR27,960.75 $1 Duration
23-Aug-12 QAR0.00 CP 745/2 QAR5,083.75 $1 Duration
27-Aug-12 QAR0.00 CP 745/2 QAR2,541.75 $1 Duration
30-Aug-12 QAR0.00 CP 745/2 QAR50,838.75 $1 Duration
2-Sep-12 QAR0.00 CP 745/2 QAR58,464.75 $1 Duration
4-Sep-12 QAR0.00 CP 745/2 QAR63,548.75 $1 Duration
11-Sep-12 QAR0.00 CP 745/2 QAR5,084.00 $1 Duration
12-Sep-12 QAR0.00 CP 745/2 QAR7,626.00 $1 Duration
15-Sep-12 QAR0.00 CP 745/2 QAR20,336.00 $1 Duration
6-Sep-12 QAR0.00 CP 745/2 QAR7,625.25 $1 Duration
9-Sep-12 QAR0.00 CP 745/2 QAR5,083.75 $1 Duration
8-Oct-12 QAR0.00 CP 745/2 QAR186,048.00 $1 Duration
8-Oct-12 QAR0.00 QAR152,324.00 $1
18-Sep-12 QAR0.00 CP 745/2 QAR23,016.00 $1 Duration
20-Sep-12 QAR0.00 CP 745/2 QAR29,592.00 $1 Duration
26-Sep-12 QAR0.00 CP 745/2 QAR13,152.00 $1 Duration
10-Sep-12 QAR0.00 CP 745/2 QAR24,704.00 $1 Duration
17-Sep-12 QAR0.00 CP 745/2 QAR6,057.00 $1 Duration
19-Sep-12 QAR0.00 CP 745/2 QAR15,144.00 $1 Duration
22-Sep-12 QAR0.00 CP 745/2 QAR4,543.00 $1 Duration
24-Sep-12 QAR0.00 CP 745/2 QAR4,543.00 $1 Duration
8-Oct-12 QAR0.00 CP 745/2 QAR31,573.00 $1 Duration
18-Nov-12 QAR0.00 QAR406,563.35 $1
10-Sep-12 QAR0.00 QAR0.00 $0
10-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
15-Aug-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
4-Oct-12 QAR0.00 QAR145,901.70 $1
24-Sep-12 QAR0.00 CP 745/2 QAR43,770.90 $1 Duration
26-Sep-12 QAR0.00 CP 745/2 QAR24,802.80 $1 Duration
29-Sep-12 QAR0.00 CP 745/2 QAR43,771.00 $1 Duration
3-Oct-12 QAR0.00 CP 745/2 QAR7,295.00 $1 Duration
1-Oct-12 QAR0.00 CP 745/2 QAR17,508.00 $1 Duration
4-Oct-12 QAR0.00 CP 745/2 QAR8,754.00 $1 Duration
22-Oct-12 QAR0.00 QAR195,504.65 $1
20-Sep-12 QAR0.00 CP 745/2 QAR9,226.75 $1 Duration
22-Sep-12 QAR0.00 CP 745/2 QAR1,677.50 $1 Duration
23-Sep-12 QAR0.00 CP 745/2 QAR838.75 $1 Duration
24-Sep-12 QAR0.00 CP 745/2 QAR16,776.50 $1 Duration
25-Sep-12 QAR0.00 CP 745/2 QAR19,292.90 $1 Duration
26-Sep-12 QAR0.00 CP 745/2 QAR20,970.75 $1 Duration
1-Oct-12 QAR0.00 CP 745/2 QAR1,677.75 $1 Duration
22-Oct-12 QAR0.00 CP 745/2 QAR111,621.75 $1 Duration
4-Oct-12 QAR0.00 CP 745/2 QAR2,516.75 $1 Duration
29-Sep-12 QAR0.00 CP 745/2 QAR2,516.75 $1 Duration
8-Oct-12 QAR0.00 CP 745/2 QAR6,710.75 $1 Duration
30-Sep-12 QAR0.00 CP 745/2 QAR1,677.75 $1 Duration
18-Nov-12 QAR0.00 QAR65,157.00 $1
8-Oct-12 QAR0.00 CP 745/2 QAR21,531.00 $1 Duration
4-Nov-12 QAR0.00 CP 745/2 QAR12,303.00 $1 Duration
20-Oct-12 QAR0.00 CP 745/2 QAR27,683.00 $1 Duration
18-Nov-12 QAR0.00 CP 745/2 QAR3,640.00 $1 Duration
19-Nov-12 QAR0.00 QAR390,220.25 $1
22-Sep-12 QAR0.00 QAR0.00 $0
22-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
16-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-Oct-12 QAR0.00 QAR139,802.00 $1
6-Oct-12 QAR0.00 CP 745/2 QAR41,941.00 $1 Duration
7-Oct-12 QAR0.00 CP 745/2 QAR23,766.00 $1 Duration
9-Oct-12 QAR0.00 CP 745/2 QAR41,941.00 $1 Duration
10-Oct-12 QAR0.00 CP 745/2 QAR16,776.00 $1 Duration
11-Oct-12 QAR0.00 CP 745/2 QAR6,990.00 $1 Duration
11-Oct-12 QAR0.00 CP 745/2 QAR8,388.00 $1 Duration
3-Nov-12 QAR0.00 QAR188,363.00 $1
3-Oct-12 QAR0.00 CP 745/2 QAR10,015.00 $1 Duration
4-Oct-12 QAR0.00 CP 745/2 QAR1,821.00 $1 Duration
6-Oct-12 QAR0.00 CP 745/2 QAR910.00 $1 Duration
7-Oct-12 QAR0.00 CP 745/2 QAR18,209.00 $1 Duration
8-Oct-12 QAR0.00 CP 745/2 QAR20,940.00 $1 Duration
9-Oct-12 QAR0.00 CP 745/2 QAR22,761.00 $1 Duration
14-Oct-12 QAR0.00 CP 745/2 QAR1,821.00 $1 Duration
17-Oct-12 QAR0.00 CP 745/2 QAR2,731.00 $1 Duration
18-Oct-12 QAR0.00 CP 745/2 QAR7,284.00 $1 Duration
3-Nov-12 QAR0.00 CP 745/2 QAR97,319.00 $1 Duration
11-Oct-12 QAR0.00 CP 745/2 QAR2,731.00 $1 Duration
13-Oct-12 QAR0.00 CP 745/2 QAR1,821.00 $1 Duration
19-Nov-12 QAR0.00 QAR62,055.25 $1
21-Oct-12 QAR0.00 CP 745/2 QAR14,996.75 $1 Duration
23-Oct-12 QAR0.00 CP 745/2 QAR19,281.75 $1 Duration
7-Nov-12 QAR0.00 CP 745/2 QAR8,570.00 $1 Duration
18-Oct-12 QAR0.00 CP 745/2 QAR4,940.75 $1 Duration
25-Oct-12 QAR0.00 CP 745/2 QAR1,212.00 $1 Duration
31-Oct-12 QAR0.00 CP 745/2 QAR3,029.00 $1 Duration
3-Nov-12 QAR0.00 CP 745/2 QAR909.00 $1 Duration
5-Nov-12 QAR0.00 CP 745/2 QAR909.00 $1 Duration
19-Nov-12 QAR0.00 CP 745/2 QAR8,207.00 $1 Duration
26-Dec-12 QAR0.00 QAR750,241.00 $1
3-Oct-12 QAR0.00 QAR0.00 $0
3-Oct-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
27-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
10-Nov-12 QAR0.00 QAR320,546.25 $1
30-Oct-12 QAR0.00 CP 745/2 QAR96,163.75 $1 Duration
1-Nov-12 QAR0.00 CP 745/2 QAR54,492.75 $1 Duration
4-Nov-12 QAR0.00 CP 745/2 QAR96,164.00 $1 Duration
8-Nov-12 QAR0.00 CP 745/2 QAR16,027.00 $1 Duration
6-Nov-12 QAR0.00 CP 745/2 QAR38,465.75 $1 Duration
10-Nov-12 QAR0.00 CP 745/2 QAR19,233.00 $1 Duration
28-Nov-12 QAR0.00 QAR355,992.25 $1
20-Oct-12 QAR0.00 CP 745/2 QAR19,772.75 $1 Duration
21-Oct-12 QAR0.00 CP 745/2 QAR3,594.75 $1 Duration
22-Oct-12 QAR0.00 CP 745/2 QAR1,797.75 $1 Duration
23-Oct-12 QAR0.00 CP 745/2 QAR35,951.00 $1 Duration
24-Oct-12 QAR0.00 CP 745/2 QAR41,343.00 $1 Duration
25-Oct-12 QAR0.00 CP 745/2 QAR44,939.00 $1 Duration
6-Nov-12 QAR0.00 CP 745/2 QAR5,393.00 $1 Duration
11-Nov-12 QAR0.00 CP 745/2 QAR14,380.00 $1 Duration
28-Nov-12 QAR0.00 CP 745/2 QAR176,238.00 $1 Duration
3-Nov-12 QAR0.00 CP 745/2 QAR3,595.00 $1 Duration
31-Oct-12 QAR0.00 CP 745/2 QAR5,393.00 $1 Duration
1-Nov-12 QAR0.00 CP 745/2 QAR3,595.00 $1 Duration
26-Dec-12 QAR0.00 QAR73,702.50 $1
12-Nov-12 QAR0.00 CP 745/2 QAR24,351.50 $1 Duration
25-Nov-12 QAR0.00 CP 745/2 QAR31,310.00 $1 Duration
8-Dec-12 QAR0.00 CP 745/2 QAR13,916.00 $1 Duration
26-Dec-12 QAR0.00 CP 745/2 QAR4,125.00 $1 Duration
25-Mar-13 QAR0.00 QAR4,592,315.00 $1
21-Oct-12 QAR0.00 QAR0.00 $0
6-Sep-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
21-Oct-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
3-Oct-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-Dec-12 QAR0.00 QAR830,892.00 $1
26-Nov-12 QAR0.00 CP 745/2 QAR249,267.00 $1 Duration
29-Nov-12 QAR0.00 CP 745/2 QAR141,251.00 $1 Duration
4-Dec-12 QAR0.00 CP 745/2 QAR249,268.00 $1 Duration
9-Dec-12 QAR0.00 CP 745/2 QAR99,707.00 $1 Duration
13-Dec-12 QAR0.00 CP 745/2 QAR41,545.00 $1 Duration
17-Dec-12 QAR0.00 CP 745/2 QAR49,854.00 $1 Duration
22-Jan-13 QAR0.00 QAR1,756,950.00 $1
27-Nov-12 QAR0.00 CP 745/2 QAR134,626.00 $1 Duration
1-Dec-12 QAR0.00 CP 745/2 QAR24,478.00 $1 Duration
4-Dec-12 QAR0.00 CP 745/2 QAR12,238.00 $1 Duration
8-Dec-12 QAR0.00 CP 745/2 QAR244,775.00 $1 Duration
11-Dec-12 QAR0.00 CP 745/2 QAR281,491.00 $1 Duration
15-Dec-12 QAR0.00 CP 745/2 QAR305,968.00 $1 Duration
24-Dec-12 QAR0.00 CP 745/2 QAR36,716.00 $1 Duration
26-Dec-12 QAR0.00 CP 745/2 QAR97,910.00 $1 Duration
22-Dec-12 QAR0.00 CP 745/2 QAR24,478.00 $1 Duration
19-Dec-12 QAR0.00 CP 745/2 QAR36,716.00 $1 Duration
23-Dec-12 QAR0.00 CP 745/2 QAR24,478.00 $1 Duration
22-Jan-13 QAR0.00 CP 745/2 QAR533,076.00 $1 Duration
25-Mar-13 QAR0.00 QAR2,004,473.00 $1
19-Jan-13 QAR0.00 CP 745/2 QAR192,441.00 $1 Duration
26-Jan-13 QAR0.00 CP 745/2 QAR247,425.00 $1 Duration
26-Feb-13 QAR0.00 CP 745/2 QAR109,967.00 $1 Duration
14-Jan-13 QAR0.00 CP 745/2 QAR424,913.00 $1 Duration
2-Feb-13 QAR0.00 CP 745/2 QAR104,188.00 $1 Duration
9-Feb-13 QAR0.00 CP 745/2 QAR260,470.00 $1 Duration
21-Feb-13 QAR0.00 CP 745/2 QAR78,141.00 $1 Duration
14-Feb-13 QAR0.00 CP 745/2 QAR78,141.00 $1 Duration
25-Mar-13 QAR0.00 CP 745/2 QAR508,787.00 $1 Duration
14-Mar-13 QAR0.00 QAR853,191.80 $1
20-Nov-12 QAR0.00 QAR0.00 $0
20-Nov-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
3-Nov-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
24-Dec-12 QAR0.00 QAR144,658.40 $1
10-Dec-12 QAR0.00 CP 745/2 QAR43,397.40 $1 Duration
12-Dec-12 QAR0.00 CP 745/2 QAR24,592.00 $1 Duration
15-Dec-12 QAR0.00 CP 745/2 QAR43,398.00 $1 Duration
20-Dec-12 QAR0.00 CP 745/2 QAR7,232.00 $1 Duration
17-Dec-12 QAR0.00 CP 745/2 QAR17,359.00 $1 Duration
24-Dec-12 QAR0.00 CP 745/2 QAR8,680.00 $1 Duration
2-Feb-13 QAR0.00 QAR300,607.00 $1
17-Dec-12 QAR0.00 CP 745/2 QAR21,482.00 $1 Duration
20-Dec-12 QAR0.00 CP 745/2 QAR3,906.00 $1 Duration
23-Dec-12 QAR0.00 CP 745/2 QAR1,953.00 $1 Duration
25-Dec-12 QAR0.00 CP 745/2 QAR39,059.00 $1 Duration
27-Dec-12 QAR0.00 CP 745/2 QAR44,917.00 $1 Duration
30-Dec-12 QAR0.00 CP 745/2 QAR48,823.00 $1 Duration
7-Jan-13 QAR0.00 CP 745/2 QAR5,859.00 $1 Duration
9-Jan-13 QAR0.00 CP 745/2 QAR15,623.00 $1 Duration
1-Jan-13 QAR0.00 CP 745/2 QAR5,859.00 $1 Duration
6-Jan-13 QAR0.00 CP 745/2 QAR3,906.00 $1 Duration
2-Feb-13 QAR0.00 CP 745/2 QAR105,314.00 $1 Duration
3-Jan-13 QAR0.00 CP 745/2 QAR3,906.00 $1 Duration
14-Mar-13 QAR0.00 QAR407,926.40 $1
3-Feb-13 QAR0.00 CP 745/2 QAR47,367.90 $1 Duration
6-Feb-13 QAR0.00 CP 745/2 QAR60,902.00 $1 Duration
21-Jan-13 QAR0.00 CP 745/2 QAR79,053.50 $1 Duration
10-Feb-13 QAR0.00 CP 745/2 QAR19,384.00 $1 Duration
14-Feb-13 QAR0.00 CP 745/2 QAR48,460.00 $1 Duration
18-Feb-13 QAR0.00 CP 745/2 QAR14,538.00 $1 Duration
21-Feb-13 QAR0.00 CP 745/2 QAR14,538.00 $1 Duration
25-Feb-13 QAR0.00 CP 745/2 QAR27,067.00 $1 Duration
14-Mar-13 QAR0.00 CP 745/2 QAR96,616.00 $1 Duration
6-Apr-13 QAR0.00 QAR2,820,436.00 $1
8-Dec-12 QAR0.00 QAR0.00 $0
2-Dec-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
8-Dec-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Jan-13 QAR0.00 QAR764,924.50 $1
7-Jan-13 QAR0.00 CP 745/2 QAR229,477.25 $1 Duration
10-Jan-13 QAR0.00 CP 745/2 QAR130,037.25 $1 Duration
14-Jan-13 QAR0.00 CP 745/2 QAR229,477.00 $1 Duration
21-Jan-13 QAR0.00 CP 745/2 QAR38,246.00 $1 Duration
17-Jan-13 QAR0.00 CP 745/2 QAR91,791.00 $1 Duration
26-Jan-13 QAR0.00 CP 745/2 QAR45,896.00 $1 Duration
13-Mar-13 QAR0.00 QAR1,253,247.00 $1
14-Jan-13 QAR0.00 CP 745/2 QAR97,039.00 $1 Duration
17-Jan-13 QAR0.00 CP 745/2 QAR17,644.00 $1 Duration
21-Jan-13 QAR0.00 CP 745/2 QAR8,822.00 $1 Duration
24-Jan-13 QAR0.00 CP 745/2 QAR176,435.00 $1 Duration
28-Jan-13 QAR0.00 CP 745/2 QAR202,900.00 $1 Duration
31-Jan-13 QAR0.00 CP 745/2 QAR220,543.00 $1 Duration
10-Feb-13 QAR0.00 CP 745/2 QAR26,465.00 $1 Duration
14-Feb-13 QAR0.00 CP 745/2 QAR70,574.00 $1 Duration
13-Mar-13 QAR0.00 CP 745/2 QAR371,073.00 $1 Duration
5-Feb-13 QAR0.00 CP 745/2 QAR26,464.00 $1 Duration
10-Feb-13 QAR0.00 CP 745/2 QAR17,644.00 $1 Duration
11-Feb-13 QAR0.00 CP 745/2 QAR17,644.00 $1 Duration
6-Apr-13 QAR0.00 QAR802,264.50 $1
27-Feb-13 QAR0.00 CP 745/2 QAR84,787.50 $1 Duration
2-Mar-13 QAR0.00 CP 745/2 QAR109,012.00 $1 Duration
13-Mar-13 QAR0.00 CP 745/2 QAR48,450.00 $1 Duration
25-Feb-13 QAR0.00 CP 745/2 QAR163,048.00 $1 Duration
4-Mar-13 QAR0.00 CP 745/2 QAR39,979.00 $1 Duration
6-Mar-13 QAR0.00 CP 745/2 QAR99,948.00 $1 Duration
9-Mar-13 QAR0.00 CP 745/2 QAR29,984.00 $1 Duration
11-Mar-13 QAR0.00 CP 745/2 QAR29,984.00 $1 Duration
6-Apr-13 QAR0.00 CP 745/2 QAR197,072.00 $1 Duration
1-Jul-13 QAR0.00 QAR6,765,909.50 $1
1-Jul-13 QAR0.00 QAR6,765,909.50 $1
6-Jan-13 QAR0.00 QAR0.00 $0
23-Oct-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
6-Jan-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
6-Dec-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
27-Feb-13 QAR0.00 QAR468,560.00 $1
3-Feb-13 QAR0.00 CP 745/2 QAR140,568.00 $1 Duration
7-Feb-13 QAR0.00 CP 745/2 QAR79,655.00 $1 Duration
13-Feb-13 QAR0.00 CP 745/2 QAR140,568.00 $1 Duration
18-Feb-13 QAR0.00 CP 745/2 QAR56,227.00 $1 Duration
23-Feb-13 QAR0.00 CP 745/2 QAR23,428.00 $1 Duration
27-Feb-13 QAR0.00 CP 745/2 QAR28,114.00 $1 Duration
17-Apr-13 QAR0.00 QAR550,349.50 $1
3-Feb-13 QAR0.00 CP 745/2 QAR33,909.00 $1 Duration
7-Feb-13 QAR0.00 CP 745/2 QAR6,165.50 $1 Duration
11-Feb-13 QAR0.00 CP 745/2 QAR3,083.00 $1 Duration
16-Feb-13 QAR0.00 CP 745/2 QAR61,652.00 $1 Duration
19-Feb-13 QAR0.00 CP 745/2 QAR70,900.00 $1 Duration
23-Feb-13 QAR0.00 CP 745/2 QAR77,065.00 $1 Duration
4-Mar-13 QAR0.00 CP 745/2 QAR9,248.00 $1 Duration
6-Mar-13 QAR0.00 CP 745/2 QAR24,661.00 $1 Duration
17-Apr-13 QAR0.00 CP 745/2 QAR242,088.00 $1 Duration
25-Feb-13 QAR0.00 CP 745/2 QAR9,248.00 $1 Duration
27-Feb-13 QAR0.00 CP 745/2 QAR6,165.00 $1 Duration
2-Mar-13 QAR0.00 CP 745/2 QAR6,165.00 $1 Duration
3-Apr-13 QAR0.00 QAR153,089.00 $1
11-Mar-13 QAR0.00 CP 745/2 QAR28,732.00 $1 Duration
13-Mar-13 QAR0.00 CP 745/2 QAR36,940.00 $1 Duration
25-Mar-13 QAR0.00 CP 745/2 QAR16,418.00 $1 Duration
9-Mar-13 QAR0.00 CP 745/2 QAR19,763.00 $1 Duration
16-Mar-13 QAR0.00 CP 745/2 QAR4,846.00 $1 Duration
18-Mar-13 QAR0.00 CP 745/2 QAR12,115.00 $1 Duration
23-Mar-13 QAR0.00 CP 745/2 QAR3,635.00 $1 Duration
20-Mar-13 QAR0.00 CP 745/2 QAR3,635.00 $1 Duration
3-Apr-13 QAR0.00 CP 745/2 QAR27,005.00 $1 Duration
1-Jul-13 QAR0.00 QAR4,756,500.25 $1
21-Mar-13 QAR0.00 QAR993,723.00 $1
3-Mar-13 QAR0.00 CP 745/2 QAR298,117.00 $1 Duration
6-Mar-13 QAR0.00 CP 745/2 QAR168,933.00 $1 Duration
10-Mar-13 QAR0.00 CP 745/2 QAR298,117.00 $1 Duration
13-Mar-13 QAR0.00 CP 745/2 QAR119,247.00 $1 Duration
18-Mar-13 QAR0.00 CP 745/2 QAR49,686.00 $1 Duration
21-Mar-13 QAR0.00 CP 745/2 QAR59,623.00 $1 Duration
29-Apr-13 QAR0.00 QAR1,807,861.00 $1
5-Mar-13 QAR0.00 CP 745/2 QAR142,388.00 $1 Duration
9-Mar-13 QAR0.00 CP 745/2 QAR25,890.00 $1 Duration
12-Mar-13 QAR0.00 CP 745/2 QAR12,944.00 $1 Duration
16-Mar-13 QAR0.00 CP 745/2 QAR258,888.00 $1 Duration
19-Mar-13 QAR0.00 CP 745/2 QAR297,721.00 $1 Duration
23-Mar-13 QAR0.00 CP 745/2 QAR323,610.00 $1 Duration
31-Mar-13 QAR0.00 CP 745/2 QAR38,833.00 $1 Duration
25-Mar-13 QAR0.00 CP 745/2 QAR38,833.00 $1 Duration
2-Apr-13 QAR0.00 CP 745/2 QAR103,555.00 $1 Duration
28-Mar-13 QAR0.00 CP 745/2 QAR25,889.00 $1 Duration
31-Mar-13 QAR0.00 CP 745/2 QAR25,889.00 $1 Duration
29-Apr-13 QAR0.00 CP 745/2 QAR513,421.00 $1 Duration
1-Jul-13 QAR0.00 QAR1,954,916.25 $1
20-Apr-13 QAR0.00 CP 745/2 QAR165,135.00 $1 Duration
25-Apr-13 QAR0.00 CP 745/2 QAR212,316.00 $1 Duration
25-May-13 QAR0.00 CP 745/2 QAR94,363.00 $1 Duration
18-Apr-13 QAR0.00 CP 745/2 QAR434,795.25 $1 Duration
1-May-13 QAR0.00 CP 745/2 QAR106,611.00 $1 Duration
7-May-13 QAR0.00 CP 745/2 QAR266,528.00 $1 Duration
19-May-13 QAR0.00 CP 745/2 QAR79,958.00 $1 Duration
13-May-13 QAR0.00 CP 745/2 QAR79,958.00 $1 Duration
1-Jul-13 QAR0.00 CP 745/2 QAR515,252.00 $1 Duration
25-Apr-13 QAR0.00 QAR547,504.75 $1
27-Mar-13 QAR0.00 QAR207,836.25 $1
17-Mar-13 QAR0.00 CP 745/2 QAR62,351.25 $1 Duration
19-Mar-13 QAR0.00 CP 745/2 QAR35,332.00 $1 Duration
21-Mar-13 QAR0.00 CP 745/2 QAR62,351.00 $1 Duration
24-Mar-13 QAR0.00 CP 745/2 QAR24,940.00 $1 Duration
26-Mar-13 QAR0.00 CP 745/2 QAR10,392.00 $1 Duration
27-Mar-13 QAR0.00 CP 745/2 QAR12,470.00 $1 Duration
15-Apr-13 QAR0.00 QAR261,420.00 $1
14-Mar-13 QAR0.00 CP 745/2 QAR16,944.00 $1 Duration
16-Mar-13 QAR0.00 CP 745/2 QAR3,080.00 $1 Duration
17-Mar-13 QAR0.00 CP 745/2 QAR1,540.00 $1 Duration
18-Mar-13 QAR0.00 CP 745/2 QAR30,808.00 $1 Duration
19-Mar-13 QAR0.00 CP 745/2 QAR35,429.00 $1 Duration
20-Mar-13 QAR0.00 CP 745/2 QAR38,510.00 $1 Duration
23-Mar-13 QAR0.00 CP 745/2 QAR4,621.00 $1 Duration
28-Mar-13 QAR0.00 CP 745/2 QAR4,621.00 $1 Duration
1-Apr-13 QAR0.00 CP 745/2 QAR12,323.00 $1 Duration
15-Apr-13 QAR0.00 CP 745/2 QAR107,382.00 $1 Duration
25-Mar-13 QAR0.00 CP 745/2 QAR3,081.00 $1 Duration
24-Mar-13 QAR0.00 CP 745/2 QAR3,081.00 $1 Duration
25-Apr-13 QAR0.00 QAR78,248.50 $1
28-Mar-13 QAR0.00 CP 745/2 QAR25,858.50 $1 Duration
6-Apr-13 QAR0.00 CP 745/2 QAR33,246.00 $1 Duration
14-Apr-13 QAR0.00 CP 745/2 QAR14,776.00 $1 Duration
25-Apr-13 QAR0.00 CP 745/2 QAR4,368.00 $1 Duration
21-Apr-13 QAR0.00 QAR289,906.00 $1
1-Apr-13 QAR0.00 QAR98,700.00 $1
24-Mar-13 QAR0.00 CP 745/2 QAR29,610.00 $1 Duration
25-Mar-13 QAR0.00 CP 745/2 QAR16,779.00 $1 Duration
26-Mar-13 QAR0.00 CP 745/2 QAR29,610.00 $1 Duration
28-Mar-13 QAR0.00 CP 745/2 QAR11,844.00 $1 Duration
30-Mar-13 QAR0.00 CP 745/2 QAR4,935.00 $1 Duration
1-Apr-13 QAR0.00 CP 745/2 QAR5,922.00 $1 Duration
20-Apr-13 QAR0.00 QAR143,455.00 $1
23-Mar-13 QAR0.00 CP 745/2 QAR10,171.00 $1 Duration
24-Mar-13 QAR0.00 CP 745/2 QAR1,848.00 $1 Duration
25-Mar-13 QAR0.00 CP 745/2 QAR925.00 $1 Duration
26-Mar-13 QAR0.00 CP 745/2 QAR18,492.00 $1 Duration
27-Mar-13 QAR0.00 CP 745/2 QAR21,266.00 $1 Duration
28-Mar-13 QAR0.00 CP 745/2 QAR23,115.00 $1 Duration
20-Apr-13 QAR0.00 CP 745/2 QAR50,995.00 $1 Duration
31-Mar-13 QAR0.00 CP 745/2 QAR2,774.00 $1 Duration
1-Apr-13 QAR0.00 CP 745/2 QAR1,849.00 $1 Duration
6-Apr-13 QAR0.00 CP 745/2 QAR2,774.00 $1 Duration
8-Apr-13 QAR0.00 CP 745/2 QAR7,397.00 $1 Duration
1-Apr-13 QAR0.00 CP 745/2 QAR1,849.00 $1 Duration
21-Apr-13 QAR0.00 QAR47,751.00 $1
3-Apr-13 QAR0.00 CP 745/2 QAR15,779.00 $1 Duration
9-Apr-13 QAR0.00 CP 745/2 QAR20,287.00 $1 Duration
15-Apr-13 QAR0.00 CP 745/2 QAR9,016.00 $1 Duration
21-Apr-13 QAR0.00 CP 745/2 QAR2,669.00 $1 Duration
10-Jun-13 QAR0.00 QAR729,448.00 $1
23-Feb-13 QAR0.00 QAR0.00 $0
31-Dec-12 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Feb-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
10-Feb-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
25-Apr-13 QAR0.00 QAR248,235.00 $1
14-Apr-13 QAR0.00 CP 745/2 QAR74,471.00 $1 Duration
16-Apr-13 QAR0.00 CP 745/2 QAR42,200.00 $1 Duration
18-Apr-13 QAR0.00 CP 745/2 QAR74,471.00 $1 Duration
21-Apr-13 QAR0.00 CP 745/2 QAR29,788.00 $1 Duration
23-Apr-13 QAR0.00 CP 745/2 QAR12,411.00 $1 Duration
25-Apr-13 QAR0.00 CP 745/2 QAR14,894.00 $1 Duration
26-May-13 QAR0.00 QAR376,962.00 $1
10-Apr-13 QAR0.00 CP 745/2 QAR22,956.00 $1 Duration
13-Apr-13 QAR0.00 CP 745/2 QAR4,174.00 $1 Duration
15-Apr-13 QAR0.00 CP 745/2 QAR2,087.00 $1 Duration
17-Apr-13 QAR0.00 CP 745/2 QAR41,736.00 $1 Duration
20-Apr-13 QAR0.00 CP 745/2 QAR47,997.00 $1 Duration
22-Apr-13 QAR0.00 CP 745/2 QAR52,171.00 $1 Duration
30-Apr-13 QAR0.00 CP 745/2 QAR6,261.00 $1 Duration
2-May-13 QAR0.00 CP 745/2 QAR16,695.00 $1 Duration
26-May-13 QAR0.00 CP 745/2 QAR168,276.00 $1 Duration
27-Apr-13 QAR0.00 CP 745/2 QAR4,174.00 $1 Duration
24-Apr-13 QAR0.00 CP 745/2 QAR6,261.00 $1 Duration
27-Apr-13 QAR0.00 CP 745/2 QAR4,174.00 $1 Duration
10-Jun-13 QAR0.00 QAR104,251.00 $1
4-May-13 QAR0.00 CP 745/2 QAR34,449.00 $1 Duration
15-May-13 QAR0.00 CP 745/2 QAR44,293.00 $1 Duration
27-May-13 QAR0.00 CP 745/2 QAR19,685.00 $1 Duration
10-Jun-13 QAR0.00 CP 745/2 QAR5,824.00 $1 Duration
2-Nov-13 QAR0.00 QAR6,527,860.25 $1
2-Nov-13 QAR0.00 QAR6,527,860.25 $1
27-Mar-13 QAR0.00 QAR0.00 $0
23-Jan-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
27-Mar-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
16-Mar-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
5-Jun-13 QAR0.00 QAR474,436.75 $1
11-May-13 QAR0.00 CP 745/2 QAR142,331.00 $1 Duration
16-May-13 QAR0.00 CP 745/2 QAR80,653.75 $1 Duration
22-May-13 QAR0.00 CP 745/2 QAR142,331.00 $1 Duration
28-May-13 QAR0.00 CP 745/2 QAR56,933.00 $1 Duration
3-Jun-13 QAR0.00 CP 745/2 QAR23,722.00 $1 Duration
5-Jun-13 QAR0.00 CP 745/2 QAR28,466.00 $1 Duration
24-Jul-13 QAR0.00 QAR745,338.75 $1
11-May-13 QAR0.00 CP 745/2 QAR53,688.00 $1 Duration
14-May-13 QAR0.00 CP 745/2 QAR9,762.00 $1 Duration
18-May-13 QAR0.00 CP 745/2 QAR4,880.00 $1 Duration
21-May-13 QAR0.00 CP 745/2 QAR97,614.75 $1 Duration
25-May-13 QAR0.00 CP 745/2 QAR112,257.00 $1 Duration
28-May-13 QAR0.00 CP 745/2 QAR122,019.00 $1 Duration
5-Jun-13 QAR0.00 CP 745/2 QAR14,642.00 $1 Duration
10-Jun-13 QAR0.00 CP 745/2 QAR39,046.00 $1 Duration
30-May-13 QAR0.00 CP 745/2 QAR14,642.00 $1 Duration
3-Jun-13 QAR0.00 CP 745/2 QAR9,762.00 $1 Duration
3-Jun-13 QAR0.00 CP 745/2 QAR9,762.00 $1 Duration
24-Jul-13 QAR0.00 CP 745/2 QAR257,264.00 $1 Duration
24-Jul-13 QAR0.00 QAR448,194.75 $1
15-May-13 QAR0.00 CP 745/2 QAR38,821.00 $1 Duration
18-May-13 QAR0.00 CP 745/2 QAR49,913.00 $1 Duration
29-May-13 QAR0.00 CP 745/2 QAR22,183.00 $1 Duration
13-May-13 QAR0.00 CP 745/2 QAR98,817.00 $1 Duration
20-May-13 QAR0.00 CP 745/2 QAR24,230.00 $1 Duration
22-May-13 QAR0.00 CP 745/2 QAR60,574.75 $1 Duration
25-May-13 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
27-May-13 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
24-Jul-13 QAR0.00 CP 745/2 QAR117,312.00 $1 Duration
28-Jul-13 QAR0.00 QAR260,083.75 $1
20-May-13 QAR0.00 QAR35,094.00 $1
14-May-13 QAR0.00 CP 745/2 QAR10,528.00 $1 Duration
15-May-13 QAR0.00 CP 745/2 QAR5,966.00 $1 Duration
16-May-13 QAR0.00 CP 745/2 QAR10,528.00 $1 Duration
18-May-13 QAR0.00 CP 745/2 QAR4,211.00 $1 Duration
19-May-13 QAR0.00 CP 745/2 QAR1,755.00 $1 Duration
20-May-13 QAR0.00 CP 745/2 QAR2,106.00 $1 Duration
11-Jun-13 QAR0.00 QAR95,374.00 $1
15-May-13 QAR0.00 CP 745/2 QAR8,398.00 $1 Duration
16-May-13 QAR0.00 CP 745/2 QAR1,527.00 $1 Duration
18-May-13 QAR0.00 CP 745/2 QAR763.00 $1 Duration
19-May-13 QAR0.00 CP 745/2 QAR15,269.00 $1 Duration
21-May-13 QAR0.00 CP 745/2 QAR19,086.00 $1 Duration
20-May-13 QAR0.00 CP 745/2 QAR17,559.00 $1 Duration
22-May-13 QAR0.00 CP 745/2 QAR2,290.00 $1 Duration
29-May-13 QAR0.00 CP 745/2 QAR2,290.00 $1 Duration
23-May-13 QAR0.00 CP 745/2 QAR1,527.00 $1 Duration
30-May-13 QAR0.00 CP 745/2 QAR6,108.00 $1 Duration
23-May-13 QAR0.00 CP 745/2 QAR1,527.00 $1 Duration
11-Jun-13 QAR0.00 CP 745/2 QAR19,030.00 $1 Duration
28-Jul-13 QAR0.00 QAR129,615.75 $1
27-May-13 QAR0.00 CP 745/2 QAR10,045.00 $1 Duration
2-Jun-13 QAR0.00 CP 745/2 QAR12,913.75 $1 Duration
18-Jul-13 QAR0.00 CP 745/2 QAR5,740.00 $1 Duration
27-May-13 QAR0.00 CP 745/2 QAR29,645.00 $1 Duration
10-Jun-13 QAR0.00 CP 745/2 QAR7,269.00 $1 Duration
19-Jun-13 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
29-Jun-13 QAR0.00 CP 745/2 QAR5,452.00 $1 Duration
9-Jul-13 QAR0.00 CP 745/2 QAR5,452.00 $1 Duration
28-Jul-13 QAR0.00 CP 745/2 QAR34,927.00 $1 Duration
30-Jul-13 QAR0.00 QAR549,629.00 $1
27-May-13 QAR0.00 QAR105,683.00 $1
21-May-13 QAR0.00 CP 745/2 QAR31,705.00 $1 Duration
22-May-13 QAR0.00 CP 745/2 QAR17,966.00 $1 Duration
23-May-13 QAR0.00 CP 745/2 QAR31,705.00 $1 Duration
25-May-13 QAR0.00 CP 745/2 QAR12,682.00 $1 Duration
26-May-13 QAR0.00 CP 745/2 QAR5,284.00 $1 Duration
27-May-13 QAR0.00 CP 745/2 QAR6,341.00 $1 Duration
7-Jul-13 QAR0.00 QAR225,001.00 $1
26-May-13 QAR0.00 CP 745/2 QAR18,446.00 $1 Duration
27-May-13 QAR0.00 CP 745/2 QAR3,354.00 $1 Duration
28-May-13 QAR0.00 CP 745/2 QAR1,676.00 $1 Duration
29-May-13 QAR0.00 CP 745/2 QAR33,539.00 $1 Duration
30-May-13 QAR0.00 CP 745/2 QAR38,570.00 $1 Duration
1-Jun-13 QAR0.00 CP 745/2 QAR41,923.00 $1 Duration
2-Jun-13 QAR0.00 CP 745/2 QAR5,031.00 $1 Duration
3-Jun-13 QAR0.00 CP 745/2 QAR3,354.00 $1 Duration
11-Jun-13 QAR0.00 CP 745/2 QAR5,031.00 $1 Duration
4-Jun-13 QAR0.00 CP 745/2 QAR3,354.00 $1 Duration
13-Jun-13 QAR0.00 CP 745/2 QAR13,416.00 $1 Duration
7-Jul-13 QAR0.00 CP 745/2 QAR57,307.00 $1 Duration
30-Jul-13 QAR0.00 QAR218,945.00 $1
17-Jun-13 QAR0.00 CP 745/2 QAR28,630.00 $1 Duration
22-Jun-13 QAR0.00 CP 745/2 QAR36,810.50 $1 Duration
10-Jul-13 QAR0.00 CP 745/2 QAR16,360.00 $1 Duration
13-Jun-13 QAR0.00 CP 745/2 QAR39,527.00 $1 Duration
25-Jun-13 QAR0.00 CP 745/2 QAR9,691.50 $1 Duration
29-Jun-13 QAR0.00 CP 745/2 QAR24,230.00 $1 Duration
3-Jul-13 QAR0.00 CP 745/2 QAR7,269.00 $1 Duration
7-Jul-13 QAR0.00 CP 745/2 QAR7,269.00 $1 Duration
30-Jul-13 QAR0.00 CP 745/2 QAR49,158.00 $1 Duration
3-Sep-13 QAR0.00 QAR638,958.75 $1
5-Jun-13 QAR0.00 QAR135,686.75 $1
1-Jun-13 QAR0.00 CP 745/2 QAR40,705.75 $1 Duration
1-Jun-13 QAR0.00 CP 745/2 QAR23,067.00 $1 Duration
2-Jun-13 QAR0.00 CP 745/2 QAR40,706.00 $1 Duration
3-Jun-13 QAR0.00 CP 745/2 QAR16,283.00 $1 Duration
4-Jun-13 QAR0.00 CP 745/2 QAR6,784.00 $1 Duration
5-Jun-13 QAR0.00 CP 745/2 QAR8,141.00 $1 Duration
15-Aug-13 QAR0.00 QAR271,846.00 $1
8-Jun-13 QAR0.00 CP 745/2 QAR21,810.00 $1 Duration
11-Jun-13 QAR0.00 CP 745/2 QAR3,965.00 $1 Duration
16-Jun-13 QAR0.00 CP 745/2 QAR1,983.00 $1 Duration
19-Jun-13 QAR0.00 CP 745/2 QAR39,654.00 $1 Duration
23-Jun-13 QAR0.00 CP 745/2 QAR45,602.00 $1 Duration
27-Jun-13 QAR0.00 CP 745/2 QAR49,567.00 $1 Duration
1-Jul-13 QAR0.00 CP 745/2 QAR5,948.00 $1 Duration
10-Jul-13 QAR0.00 CP 745/2 QAR5,948.00 $1 Duration
4-Jul-13 QAR0.00 CP 745/2 QAR3,965.00 $1 Duration
15-Jul-13 QAR0.00 CP 745/2 QAR15,862.00 $1 Duration
4-Jul-13 QAR0.00 CP 745/2 QAR3,965.00 $1 Duration
15-Aug-13 QAR0.00 CP 745/2 QAR73,577.00 $1 Duration
3-Sep-13 QAR0.00 QAR231,426.00 $1
10-Jul-13 QAR0.00 CP 745/2 QAR27,296.00 $1 Duration
16-Jul-13 QAR0.00 CP 745/2 QAR35,094.00 $1 Duration
17-Aug-13 QAR0.00 CP 745/2 QAR15,598.00 $1 Duration
10-Jul-13 QAR0.00 CP 745/2 QAR44,468.00 $1 Duration
22-Jul-13 QAR0.00 CP 745/2 QAR10,903.00 $1 Duration
28-Jul-13 QAR0.00 CP 745/2 QAR27,259.00 $1 Duration
3-Aug-13 QAR0.00 CP 745/2 QAR8,177.00 $1 Duration
8-Aug-13 QAR0.00 CP 745/2 QAR8,178.00 $1 Duration
3-Sep-13 QAR0.00 CP 745/2 QAR54,453.00 $1 Duration
17-Sep-13 QAR0.00 QAR834,898.75 $1
26-Jun-13 QAR0.00 QAR164,486.00 $1
17-Jun-13 QAR0.00 CP 745/2 QAR49,346.00 $1 Duration
18-Jun-13 QAR0.00 CP 745/2 QAR27,963.00 $1 Duration
20-Jun-13 QAR0.00 CP 745/2 QAR49,346.00 $1 Duration
24-Jun-13 QAR0.00 CP 745/2 QAR8,224.00 $1 Duration
23-Jun-13 QAR0.00 CP 745/2 QAR19,738.00 $1 Duration
26-Jun-13 QAR0.00 CP 745/2 QAR9,869.00 $1 Duration
10-Sep-13 QAR0.00 QAR318,035.75 $1
4-Jul-13 QAR0.00 CP 745/2 QAR25,173.00 $1 Duration
9-Jul-13 QAR0.00 CP 745/2 QAR4,577.00 $1 Duration
13-Jul-13 QAR0.00 CP 745/2 QAR2,288.00 $1 Duration
16-Jul-13 QAR0.00 CP 745/2 QAR45,769.00 $1 Duration
21-Jul-13 QAR0.00 CP 745/2 QAR52,633.75 $1 Duration
24-Jul-13 QAR0.00 CP 745/2 QAR57,210.00 $1 Duration
28-Jul-13 QAR0.00 CP 745/2 QAR6,865.00 $1 Duration
7-Aug-13 QAR0.00 CP 745/2 QAR6,865.00 $1 Duration
1-Aug-13 QAR0.00 CP 745/2 QAR4,577.00 $1 Duration
13-Aug-13 QAR0.00 CP 745/2 QAR18,308.00 $1 Duration
1-Aug-13 QAR0.00 CP 745/2 QAR4,577.00 $1 Duration
10-Sep-13 QAR0.00 CP 745/2 QAR89,193.00 $1 Duration
17-Sep-13 QAR0.00 QAR352,377.00 $1
17-Aug-13 QAR0.00 CP 745/2 QAR34,478.00 $1 Duration
21-Aug-13 QAR0.00 CP 745/2 QAR44,329.00 $1 Duration
5-Sep-13 QAR0.00 CP 745/2 QAR19,702.00 $1 Duration
13-Aug-13 QAR0.00 CP 745/2 QAR74,113.00 $1 Duration
25-Aug-13 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
28-Aug-13 QAR0.00 CP 745/2 QAR45,431.00 $1 Duration
1-Sep-13 QAR0.00 CP 745/2 QAR13,629.00 $1 Duration
3-Sep-13 QAR0.00 CP 745/2 QAR13,629.00 $1 Duration
17-Sep-13 QAR0.00 CP 745/2 QAR88,894.00 $1 Duration
2-Nov-13 QAR0.00 QAR2,576,319.75 $1
1-Sep-13 QAR0.00 QAR424,073.00 $1
31-Jul-13 QAR0.00 CP 745/2 QAR127,222.00 $1 Duration
6-Aug-13 QAR0.00 CP 745/2 QAR72,093.00 $1 Duration
14-Aug-13 QAR0.00 CP 745/2 QAR127,221.00 $1 Duration
20-Aug-13 QAR0.00 CP 745/2 QAR50,889.00 $1 Duration
26-Aug-13 QAR0.00 CP 745/2 QAR21,204.00 $1 Duration
1-Sep-13 QAR0.00 CP 745/2 QAR25,444.00 $1 Duration
22-Oct-13 QAR0.00 QAR946,497.75 $1
21-Aug-13 QAR0.00 CP 745/2 QAR78,820.00 $1 Duration
27-Aug-13 QAR0.00 CP 745/2 QAR14,331.00 $1 Duration
1-Sep-13 QAR0.00 CP 745/2 QAR7,165.00 $1 Duration
4-Sep-13 QAR0.00 CP 745/2 QAR143,309.00 $1 Duration
8-Sep-13 QAR0.00 CP 745/2 QAR164,804.75 $1 Duration
11-Sep-13 QAR0.00 CP 745/2 QAR179,136.00 $1 Duration
19-Sep-13 QAR0.00 CP 745/2 QAR21,496.00 $1 Duration
14-Sep-13 QAR0.00 CP 745/2 QAR21,496.00 $1 Duration
17-Sep-13 QAR0.00 CP 745/2 QAR14,331.00 $1 Duration
22-Sep-13 QAR0.00 CP 745/2 QAR57,324.00 $1 Duration
17-Sep-13 QAR0.00 CP 745/2 QAR14,331.00 $1 Duration
22-Oct-13 QAR0.00 CP 745/2 QAR229,954.00 $1 Duration
2-Nov-13 QAR0.00 QAR1,205,749.00 $1
18-Sep-13 QAR0.00 CP 745/2 QAR103,361.00 $1 Duration
21-Sep-13 QAR0.00 CP 745/2 QAR132,892.00 $1 Duration
2-Oct-13 QAR0.00 CP 745/2 QAR59,063.00 $1 Duration
16-Sep-13 QAR0.00 CP 745/2 QAR266,806.00 $1 Duration
23-Sep-13 QAR0.00 CP 745/2 QAR65,420.00 $1 Duration
25-Sep-13 QAR0.00 CP 745/2 QAR163,551.00 $1 Duration
28-Sep-13 QAR0.00 CP 745/2 QAR49,066.00 $1 Duration
30-Sep-13 QAR0.00 CP 745/2 QAR49,065.00 $1 Duration
2-Nov-13 QAR0.00 CP 745/2 QAR316,525.00 $1 Duration
14-Nov-13 QAR0.00 QAR774,318.55 $1
10-Jun-13 QAR0.00 QAR0.00 $0
22-Apr-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
10-Jun-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
15-May-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-Sep-13 QAR0.00 QAR220,564.10 $1
1-Sep-13 QAR0.00 CP 745/2 QAR66,169.25 $1 Duration
2-Sep-13 QAR0.00 CP 745/2 QAR37,495.75 $1 Duration
4-Sep-13 QAR0.00 CP 745/2 QAR66,169.00 $1 Duration
7-Sep-13 QAR0.00 CP 745/2 QAR26,468.10 $1 Duration
9-Sep-13 QAR0.00 CP 745/2 QAR11,028.00 $1 Duration
11-Sep-13 QAR0.00 CP 745/2 QAR13,234.00 $1 Duration
14-Nov-13 QAR0.00 QAR352,781.10 $1
14-Sep-13 QAR0.00 CP 745/2 QAR24,712.60 $1 Duration
16-Sep-13 QAR0.00 CP 745/2 QAR4,494.00 $1 Duration
18-Sep-13 QAR0.00 CP 745/2 QAR2,247.00 $1 Duration
21-Sep-13 QAR0.00 CP 745/2 QAR44,935.00 $1 Duration
23-Sep-13 QAR0.00 CP 745/2 QAR51,675.00 $1 Duration
25-Sep-13 QAR0.00 CP 745/2 QAR56,169.00 $1 Duration
28-Sep-13 QAR0.00 CP 745/2 QAR6,740.50 $1 Duration
3-Oct-13 QAR0.00 CP 745/2 QAR6,740.00 $1 Duration
30-Sep-13 QAR0.00 CP 745/2 QAR4,494.00 $1 Duration
2-Oct-13 QAR0.00 CP 745/2 QAR4,494.00 $1 Duration
6-Oct-13 QAR0.00 CP 745/2 QAR17,974.00 $1 Duration
14-Nov-13 QAR0.00 CP 745/2 QAR128,106.00 $1 Duration
2-Nov-13 QAR0.00 QAR200,973.35 $1
3-Oct-13 QAR0.00 CP 745/2 QAR28,213.25 $1 Duration
6-Oct-13 QAR0.00 CP 745/2 QAR36,274.00 $1 Duration
21-Oct-13 QAR0.00 CP 745/2 QAR16,122.00 $1 Duration
3-Oct-13 QAR0.00 CP 745/2 QAR34,586.00 $1 Duration
8-Oct-13 QAR0.00 CP 745/2 QAR8,480.00 $1 Duration
10-Oct-13 QAR0.00 CP 745/2 QAR21,201.10 $1 Duration
13-Oct-13 QAR0.00 CP 745/2 QAR6,360.00 $1 Duration
19-Oct-13 QAR0.00 CP 745/2 QAR6,360.00 $1 Duration
2-Nov-13 QAR0.00 CP 745/2 QAR43,377.00 $1 Duration
23-Dec-13 QAR0.00 QAR1,226,714.00 $1
31-Jul-13 QAR0.00 QAR0.00 $0
31-Jul-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-Jul-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
19-Oct-13 QAR0.00 QAR422,007.00 $1
28-Sep-13 QAR0.00 CP 745/2 QAR126,602.00 $1 Duration
1-Oct-13 QAR0.00 CP 745/2 QAR71,741.00 $1 Duration
5-Oct-13 QAR0.00 CP 745/2 QAR126,602.00 $1 Duration
8-Oct-13 QAR0.00 CP 745/2 QAR50,642.00 $1 Duration
12-Oct-13 QAR0.00 CP 745/2 QAR21,100.00 $1 Duration
19-Oct-13 QAR0.00 CP 745/2 QAR25,320.00 $1 Duration
11-Dec-13 QAR0.00 QAR635,299.50 $1
1-Oct-13 QAR0.00 CP 745/2 QAR37,815.00 $1 Duration
5-Oct-13 QAR0.00 CP 745/2 QAR6,875.00 $1 Duration
8-Oct-13 QAR0.00 CP 745/2 QAR3,438.00 $1 Duration
12-Oct-13 QAR0.00 CP 745/2 QAR68,755.00 $1 Duration
19-Oct-13 QAR0.00 CP 745/2 QAR79,066.50 $1 Duration
22-Oct-13 QAR0.00 CP 745/2 QAR85,943.00 $1 Duration
24-Oct-13 QAR0.00 CP 745/2 QAR10,313.00 $1 Duration
30-Oct-13 QAR0.00 CP 745/2 QAR10,313.00 $1 Duration
28-Oct-13 QAR0.00 CP 745/2 QAR6,876.00 $1 Duration
2-Nov-13 QAR0.00 CP 745/2 QAR27,502.00 $1 Duration
28-Oct-13 QAR0.00 CP 745/2 QAR6,876.00 $1 Duration
11-Dec-13 QAR0.00 CP 745/2 QAR291,527.00 $1 Duration
23-Dec-13 QAR0.00 QAR169,407.50 $1
24-Oct-13 QAR0.00 CP 745/2 QAR55,980.00 $1 Duration
11-Nov-13 QAR0.00 CP 745/2 QAR71,974.50 $1 Duration
28-Nov-13 QAR0.00 CP 745/2 QAR31,989.00 $1 Duration
23-Dec-13 QAR0.00 CP 745/2 QAR9,464.00 $1 Duration
17-Jul-14 QAR0.00 QAR17,359,259.65 $1
9-Jan-14 QAR0.00 QAR2,649,074.50 $1
10-Sep-13 QAR0.00 QAR0.00 $0
15-May-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
10-Sep-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
18-Jul-13 QAR0.00 CP 745/2 QAR0.00 $0 Duration
27-Oct-13 QAR0.00 QAR186,920.00 $1
12-Oct-13 QAR0.00 CP 745/2 QAR56,076.25 $1 Duration
14-Oct-13 QAR0.00 CP 745/2 QAR31,776.75 $1 Duration
20-Oct-13 QAR0.00 CP 745/2 QAR56,076.00 $1 Duration
22-Oct-13 QAR0.00 CP 745/2 QAR22,430.00 $1 Duration
24-Oct-13 QAR0.00 CP 745/2 QAR9,346.00 $1 Duration
27-Oct-13 QAR0.00 CP 745/2 QAR11,215.00 $1 Duration
2-Dec-13 QAR0.00 QAR386,470.00 $1
20-Oct-13 QAR0.00 CP 745/2 QAR29,869.25 $1 Duration
22-Oct-13 QAR0.00 CP 745/2 QAR5,430.75 $1 Duration
24-Oct-13 QAR0.00 CP 745/2 QAR2,715.00 $1 Duration
27-Oct-13 QAR0.00 CP 745/2 QAR54,306.00 $1 Duration
29-Oct-13 QAR0.00 CP 745/2 QAR62,453.00 $1 Duration
31-Oct-13 QAR0.00 CP 745/2 QAR67,883.00 $1 Duration
3-Nov-13 QAR0.00 CP 745/2 QAR5,431.00 $1 Duration
9-Nov-13 QAR0.00 CP 745/2 QAR8,146.00 $1 Duration
3-Nov-13 QAR0.00 CP 745/2 QAR8,145.00 $1 Duration
5-Nov-13 QAR0.00 CP 745/2 QAR5,431.00 $1 Duration
11-Nov-13 QAR0.00 CP 745/2 QAR21,723.00 $1 Duration
2-Dec-13 QAR0.00 CP 745/2 QAR114,937.00 $1 Duration
24-Nov-13 QAR0.00 QAR252,258.25 $1
27-Oct-13 QAR0.00 CP 745/2 QAR28,715.00 $1 Duration
29-Oct-13 QAR0.00 CP 745/2 QAR36,918.25 $1 Duration
10-Nov-13 QAR0.00 CP 745/2 QAR16,408.00 $1 Duration
27-Oct-13 QAR0.00 CP 745/2 QAR49,409.00 $1 Duration
31-Oct-13 QAR0.00 CP 745/2 QAR12,115.00 $1 Duration
3-Nov-13 QAR0.00 CP 745/2 QAR30,287.00 $1 Duration
5-Nov-13 QAR0.00 CP 745/2 QAR9,086.00 $1 Duration
7-Nov-13 QAR0.00 CP 745/2 QAR9,086.00 $1 Duration
24-Nov-13 QAR0.00 CP 745/2 QAR60,234.00 $1 Duration
16-Nov-13 QAR0.00 QAR152,171.00 $1
26-Oct-13 QAR0.00 QAR48,424.00 $1
21-Oct-13 QAR0.00 CP 745/2 QAR14,527.00 $1 Duration
21-Oct-13 QAR0.00 CP 745/2 QAR8,233.00 $1 Duration
22-Oct-13 QAR0.00 CP 745/2 QAR14,527.00 $1 Duration
24-Oct-13 QAR0.00 CP 745/2 QAR2,421.00 $1 Duration
23-Oct-13 QAR0.00 CP 745/2 QAR5,811.00 $1 Duration
26-Oct-13 QAR0.00 CP 745/2 QAR2,905.00 $1 Duration
10-Nov-13 QAR0.00 QAR61,998.00 $1
20-Oct-13 QAR0.00 CP 745/2 QAR3,544.00 $1 Duration
21-Oct-13 QAR0.00 CP 745/2 QAR644.00 $1 Duration
22-Oct-13 QAR0.00 CP 745/2 QAR322.00 $1 Duration
23-Oct-13 QAR0.00 CP 745/2 QAR6,445.00 $1 Duration
24-Oct-13 QAR0.00 CP 745/2 QAR7,411.00 $1 Duration
26-Oct-13 QAR0.00 CP 745/2 QAR8,056.00 $1 Duration
3-Nov-13 QAR0.00 CP 745/2 QAR967.00 $1 Duration
28-Oct-13 QAR0.00 CP 745/2 QAR644.00 $1 Duration
27-Oct-13 QAR0.00 CP 745/2 QAR967.00 $1 Duration
28-Oct-13 QAR0.00 CP 745/2 QAR644.00 $1 Duration
4-Nov-13 QAR0.00 CP 745/2 QAR2,578.00 $1 Duration
10-Nov-13 QAR0.00 CP 745/2 QAR29,776.00 $1 Duration
16-Nov-13 QAR0.00 QAR41,749.00 $1
28-Oct-13 QAR0.00 CP 745/2 QAR2,867.00 $1 Duration
30-Oct-13 QAR0.00 CP 745/2 QAR3,686.00 $1 Duration
11-Nov-13 QAR0.00 CP 745/2 QAR1,638.00 $1 Duration
26-Oct-13 QAR0.00 CP 745/2 QAR9,882.00 $1 Duration
2-Nov-13 QAR0.00 CP 745/2 QAR2,424.00 $1 Duration
4-Nov-13 QAR0.00 CP 745/2 QAR6,057.00 $1 Duration
9-Nov-13 QAR0.00 CP 745/2 QAR1,817.00 $1 Duration
6-Nov-13 QAR0.00 CP 745/2 QAR1,817.00 $1 Duration
16-Nov-13 QAR0.00 CP 745/2 QAR11,561.00 $1 Duration
2-Dec-13 QAR0.00 QAR306,922.25 $1
31-Oct-13 QAR0.00 QAR52,808.25 $1
27-Oct-13 QAR0.00 CP 745/2 QAR15,842.00 $1 Duration
27-Oct-13 QAR0.00 CP 745/2 QAR8,977.25 $1 Duration
28-Oct-13 QAR0.00 CP 745/2 QAR15,842.00 $1 Duration
29-Oct-13 QAR0.00 CP 745/2 QAR6,338.00 $1 Duration
30-Oct-13 QAR0.00 CP 745/2 QAR2,640.00 $1 Duration
31-Oct-13 QAR0.00 CP 745/2 QAR3,169.00 $1 Duration
20-Nov-13 QAR0.00 QAR128,051.00 $1
27-Oct-13 QAR0.00 CP 745/2 QAR10,514.00 $1 Duration
28-Oct-13 QAR0.00 CP 745/2 QAR1,912.00 $1 Duration
29-Oct-13 QAR0.00 CP 745/2 QAR955.00 $1 Duration
30-Oct-13 QAR0.00 CP 745/2 QAR19,116.00 $1 Duration
31-Oct-13 QAR0.00 CP 745/2 QAR21,983.00 $1 Duration
2-Nov-13 QAR0.00 CP 745/2 QAR23,895.00 $1 Duration
3-Nov-13 QAR0.00 CP 745/2 QAR2,867.00 $1 Duration
4-Nov-13 QAR0.00 CP 745/2 QAR1,912.00 $1 Duration
10-Nov-13 QAR0.00 CP 745/2 QAR2,867.00 $1 Duration
5-Nov-13 QAR0.00 CP 745/2 QAR1,912.00 $1 Duration
11-Nov-13 QAR0.00 CP 745/2 QAR7,646.00 $1 Duration
20-Nov-13 QAR0.00 CP 745/2 QAR32,472.00 $1 Duration
2-Dec-13 QAR0.00 QAR126,063.00 $1
6-Nov-13 QAR0.00 CP 745/2 QAR14,334.00 $1 Duration
9-Nov-13 QAR0.00 CP 745/2 QAR18,430.00 $1 Duration
20-Nov-13 QAR0.00 CP 745/2 QAR8,191.00 $1 Duration
6-Nov-13 QAR0.00 CP 745/2 QAR24,704.00 $1 Duration
11-Nov-13 QAR0.00 CP 745/2 QAR6,057.00 $1 Duration
13-Nov-13 QAR0.00 CP 745/2 QAR15,144.00 $1 Duration
18-Nov-13 QAR0.00 CP 745/2 QAR4,543.00 $1 Duration
16-Nov-13 QAR0.00 CP 745/2 QAR4,543.00 $1 Duration
2-Dec-13 QAR0.00 CP 745/2 QAR30,117.00 $1 Duration
29-Dec-13 QAR0.00 QAR1,026,339.00 $1
20-Nov-13 QAR0.00 QAR185,725.00 $1
9-Nov-13 QAR0.00 CP 745/2 QAR55,717.00 $1 Duration
11-Nov-13 QAR0.00 CP 745/2 QAR31,573.00 $1 Duration
13-Nov-13 QAR0.00 CP 745/2 QAR55,718.00 $1 Duration
16-Nov-13 QAR0.00 CP 745/2 QAR22,287.00 $1 Duration
18-Nov-13 QAR0.00 CP 745/2 QAR9,286.00 $1 Duration
20-Nov-13 QAR0.00 CP 745/2 QAR11,144.00 $1 Duration
29-Dec-13 QAR0.00 QAR401,302.00 $1
14-Nov-13 QAR0.00 CP 745/2 QAR31,581.00 $1 Duration
17-Nov-13 QAR0.00 CP 745/2 QAR5,742.00 $1 Duration
19-Nov-13 QAR0.00 CP 745/2 QAR2,871.00 $1 Duration
21-Nov-13 QAR0.00 CP 745/2 QAR57,420.00 $1 Duration
24-Nov-13 QAR0.00 CP 745/2 QAR66,033.00 $1 Duration
26-Nov-13 QAR0.00 CP 745/2 QAR71,775.00 $1 Duration
28-Nov-13 QAR0.00 CP 745/2 QAR8,613.00 $1 Duration
4-Dec-13 QAR0.00 CP 745/2 QAR8,613.00 $1 Duration
1-Dec-13 QAR0.00 CP 745/2 QAR5,742.00 $1 Duration
7-Dec-13 QAR0.00 CP 745/2 QAR22,968.00 $1 Duration
30-Nov-13 QAR0.00 CP 745/2 QAR5,742.00 $1 Duration
29-Dec-13 QAR0.00 CP 745/2 QAR114,202.00 $1 Duration
22-Dec-13 QAR0.00 QAR439,312.00 $1
23-Nov-13 QAR0.00 CP 745/2 QAR35,882.00 $1 Duration
25-Nov-13 QAR0.00 CP 745/2 QAR46,133.00 $1 Duration
7-Dec-13 QAR0.00 CP 745/2 QAR20,504.00 $1 Duration
20-Nov-13 QAR0.00 CP 745/2 QAR98,817.00 $1 Duration
27-Nov-13 QAR0.00 CP 745/2 QAR24,230.00 $1 Duration
30-Nov-13 QAR0.00 CP 745/2 QAR60,575.00 $1 Duration
2-Dec-13 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
4-Dec-13 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
22-Dec-13 QAR0.00 CP 745/2 QAR116,827.00 $1 Duration
9-Jan-14 QAR0.00 QAR337,994.00 $1
20-Nov-13 QAR0.00 QAR64,565.00 $1
14-Nov-13 QAR0.00 CP 745/2 QAR19,370.00 $1 Duration
16-Nov-13 QAR0.00 CP 745/2 QAR10,976.00 $1 Duration
17-Nov-13 QAR0.00 CP 745/2 QAR19,370.00 $1 Duration
19-Nov-13 QAR0.00 CP 745/2 QAR3,228.00 $1 Duration
18-Nov-13 QAR0.00 CP 745/2 QAR7,747.00 $1 Duration
20-Nov-13 QAR0.00 CP 745/2 QAR3,874.00 $1 Duration
9-Jan-14 QAR0.00 QAR151,572.00 $1
18-Nov-13 QAR0.00 CP 745/2 QAR12,306.00 $1 Duration
19-Nov-13 QAR0.00 CP 745/2 QAR2,238.00 $1 Duration
20-Nov-13 QAR0.00 CP 745/2 QAR1,119.00 $1 Duration
21-Nov-13 QAR0.00 CP 745/2 QAR22,374.00 $1 Duration
23-Nov-13 QAR0.00 CP 745/2 QAR25,730.00 $1 Duration
24-Nov-13 QAR0.00 CP 745/2 QAR27,968.00 $1 Duration
25-Nov-13 QAR0.00 CP 745/2 QAR3,356.00 $1 Duration
26-Nov-13 QAR0.00 CP 745/2 QAR2,237.00 $1 Duration
25-Nov-13 QAR0.00 CP 745/2 QAR2,237.00 $1 Duration
2-Dec-13 QAR0.00 CP 745/2 QAR3,356.00 $1 Duration
3-Dec-13 QAR0.00 CP 745/2 QAR8,950.00 $1 Duration
9-Jan-14 QAR0.00 CP 745/2 QAR39,701.00 $1 Duration
17-Dec-13 QAR0.00 QAR121,857.00 $1
28-Nov-13 QAR0.00 CP 745/2 QAR12,947.00 $1 Duration
1-Dec-13 QAR0.00 CP 745/2 QAR16,646.00 $1 Duration
12-Dec-13 QAR0.00 CP 745/2 QAR7,398.00 $1 Duration
3-Dec-13 QAR0.00 CP 745/2 QAR6,058.00 $1 Duration
28-Nov-13 QAR0.00 CP 745/2 QAR24,704.00 $1 Duration
5-Dec-13 QAR0.00 CP 745/2 QAR15,144.00 $1 Duration
8-Dec-13 QAR0.00 CP 745/2 QAR4,543.00 $1 Duration
10-Dec-13 QAR0.00 CP 745/2 QAR4,543.00 $1 Duration
17-Dec-13 QAR0.00 CP 745/2 QAR29,874.00 $1 Duration
17-Jul-14 QAR0.00 QAR14,710,185.15 $1
8-Oct-12 QAR0.00 QAR563,607.50 $1
4-Sep-12 QAR0.00 CP 745/2 QAR48,609.00 $1 Duration
16-Sep-12 QAR0.00 CP 745/2 QAR24,304.75 $1 Duration
16-Sep-12 QAR0.00 CP 745/2 QAR48,609.50 $1 Duration
8-Oct-12 QAR0.00 CP 745/2 QAR141,775.00 $1 Duration
22-Sep-12 QAR0.00 CP 745/2 QAR300,309.25 $1 Duration
5-Nov-12 QAR0.00 QAR504,428.75 $1
3-Oct-12 QAR0.00 CP 745/2 QAR60,532.00 $1 Duration
14-Oct-12 QAR0.00 CP 745/2 QAR176,550.00 $1 Duration
22-Sep-12 QAR0.00 CP 745/2 QAR60,532.00 $1 Duration
3-Oct-12 QAR0.00 CP 745/2 QAR30,264.75 $1 Duration
5-Nov-12 QAR0.00 CP 745/2 QAR176,550.00 $1 Duration
28-Nov-12 QAR0.00 QAR425,061.00 $1
9-Oct-12 QAR0.00 CP 745/2 QAR51,007.00 $1 Duration
21-Oct-12 QAR0.00 CP 745/2 QAR51,007.00 $1 Duration
21-Oct-12 QAR0.00 CP 745/2 QAR25,505.00 $1 Duration
10-Nov-12 QAR0.00 CP 745/2 QAR148,771.00 $1 Duration
28-Nov-12 QAR0.00 CP 745/2 QAR148,771.00 $1 Duration
25-Dec-12 QAR0.00 QAR516,187.00 $1
30-Oct-12 QAR0.00 CP 745/2 QAR61,942.00 $1 Duration
11-Nov-12 QAR0.00 CP 745/2 QAR61,942.00 $1 Duration
11-Nov-12 QAR0.00 CP 745/2 QAR30,971.00 $1 Duration
3-Dec-12 QAR0.00 CP 745/2 QAR180,666.00 $1 Duration
25-Dec-12 QAR0.00 CP 745/2 QAR180,666.00 $1 Duration
20-Jan-13 QAR0.00 QAR492,671.25 $1
17-Nov-12 QAR0.00 CP 745/2 QAR59,121.00 $1 Duration
28-Nov-12 QAR0.00 CP 745/2 QAR59,121.00 $1 Duration
28-Nov-12 QAR0.00 CP 745/2 QAR29,559.25 $1 Duration
2-Jan-13 QAR0.00 CP 745/2 QAR172,435.00 $1 Duration
20-Jan-13 QAR0.00 CP 745/2 QAR172,435.00 $1 Duration
13-Feb-13 QAR0.00 QAR413,302.00 $1
4-Dec-12 QAR0.00 CP 745/2 QAR49,596.00 $1 Duration
16-Dec-12 QAR0.00 CP 745/2 QAR49,596.00 $1 Duration
24-Jan-13 QAR0.00 CP 745/2 QAR144,656.00 $1 Duration
16-Dec-12 QAR0.00 CP 745/2 QAR24,798.00 $1 Duration
13-Feb-13 QAR0.00 CP 745/2 QAR144,656.00 $1 Duration
14-Mar-13 QAR0.00 QAR612,017.00 $1
23-Dec-12 QAR0.00 CP 745/2 QAR73,442.00 $1 Duration
3-Jan-13 QAR0.00 CP 745/2 QAR73,442.00 $1 Duration
3-Jan-13 QAR0.00 CP 745/2 QAR36,721.00 $1 Duration
21-Feb-13 QAR0.00 CP 745/2 QAR214,206.00 $1 Duration
14-Mar-13 QAR0.00 CP 745/2 QAR214,206.00 $1 Duration
10-Apr-13 QAR0.00 QAR603,786.00 $1
21-Jan-13 QAR0.00 CP 745/2 QAR72,454.00 $1 Duration
9-Jan-13 QAR0.00 CP 745/2 QAR72,454.00 $1 Duration
20-Mar-13 QAR0.00 CP 745/2 QAR211,325.00 $1 Duration
21-Jan-13 QAR0.00 CP 745/2 QAR36,228.00 $1 Duration
10-Apr-13 QAR0.00 CP 745/2 QAR211,325.00 $1 Duration
9-May-13 QAR0.00 QAR603,786.00 $1
27-Jan-13 QAR0.00 CP 745/2 QAR72,455.00 $1 Duration
7-Feb-13 QAR0.00 CP 745/2 QAR72,454.00 $1 Duration
18-Apr-13 QAR0.00 CP 745/2 QAR211,325.00 $1 Duration
7-Feb-13 QAR0.00 CP 745/2 QAR36,227.00 $1 Duration
9-May-13 QAR0.00 CP 745/2 QAR211,325.00 $1 Duration
1-Jun-13 QAR0.00 QAR329,819.00 $1
14-Feb-13 QAR0.00 CP 745/2 QAR39,578.00 $1 Duration
26-Feb-13 QAR0.00 CP 745/2 QAR39,578.00 $1 Duration
26-Feb-13 QAR0.00 CP 745/2 QAR19,789.00 $1 Duration
14-May-13 QAR0.00 CP 745/2 QAR115,437.00 $1 Duration
1-Jun-13 QAR0.00 CP 745/2 QAR115,437.00 $1 Duration
2-Jul-13 QAR0.00 QAR357,451.00 $1
4-Mar-13 QAR0.00 CP 745/2 QAR42,894.00 $1 Duration
16-Mar-13 QAR0.00 CP 745/2 QAR42,894.00 $1 Duration
4-Jun-13 QAR0.00 CP 745/2 QAR125,108.00 $1 Duration
16-Mar-13 QAR0.00 CP 745/2 QAR21,447.00 $1 Duration
2-Jul-13 QAR0.00 CP 745/2 QAR125,108.00 $1 Duration
8-Aug-13 QAR0.00 QAR373,324.00 $1
21-Mar-13 QAR0.00 CP 745/2 QAR44,799.00 $1 Duration
2-Apr-13 QAR0.00 CP 745/2 QAR44,797.00 $1 Duration
2-Apr-13 QAR0.00 CP 745/2 QAR22,400.00 $1 Duration
8-Aug-13 QAR0.00 CP 745/2 QAR130,664.00 $1 Duration
10-Jul-13 QAR0.00 CP 745/2 QAR130,664.00 $1 Duration
9-Sep-13 QAR0.00 QAR242,220.00 $1
8-Apr-13 QAR0.00 CP 745/2 QAR29,067.00 $1 Duration
20-Apr-13 QAR0.00 CP 745/2 QAR29,066.00 $1 Duration
20-Apr-13 QAR0.00 CP 745/2 QAR14,533.00 $1 Duration
17-Aug-13 QAR0.00 CP 745/2 QAR84,777.00 $1 Duration
9-Sep-13 QAR0.00 CP 745/2 QAR84,777.00 $1 Duration
2-Feb-14 QAR0.00 QAR545,812.15 $1
3-Oct-13 QAR0.00 CP 745/2 QAR33,162.90 $1 Duration
5-Oct-13 QAR0.00 CP 745/2 QAR8,291.25 $1 Duration
7-Oct-13 QAR0.00 CP 745/2 QAR82,908.00 $1 Duration
9-Oct-13 QAR0.00 CP 745/2 QAR124,362.00 $1 Duration
13-Oct-13 QAR0.00 CP 745/2 QAR82,908.00 $1 Duration
24-Oct-13 QAR0.00 CP 745/2 QAR20,727.00 $1 Duration
31-Oct-13 QAR0.00 CP 745/2 QAR33,163.00 $1 Duration
20-Oct-13 QAR0.00 CP 745/2 QAR12,436.00 $1 Duration
23-Oct-13 QAR0.00 CP 745/2 QAR8,291.00 $1 Duration
23-Oct-13 QAR0.00 CP 745/2 QAR8,291.00 $1 Duration
2-Feb-14 QAR0.00 CP 745/2 QAR131,272.00 $1 Duration
23-Dec-13 QAR0.00 QAR130,773.25 $1
25-Nov-13 QAR0.00 QAR38,460.25 $1
18-Nov-13 QAR0.00 CP 745/2 QAR11,538.00 $1 Duration
20-Nov-13 QAR0.00 CP 745/2 QAR6,538.00 $1 Duration
21-Nov-13 QAR0.00 CP 745/2 QAR11,538.25 $1 Duration
23-Nov-13 QAR0.00 CP 745/2 QAR4,615.00 $1 Duration
24-Nov-13 QAR0.00 CP 745/2 QAR1,923.00 $1 Duration
25-Nov-13 QAR0.00 CP 745/2 QAR2,308.00 $1 Duration
14-Dec-13 QAR0.00 QAR71,439.00 $1
20-Nov-13 QAR0.00 CP 745/2 QAR5,257.00 $1 Duration
21-Nov-13 QAR0.00 CP 745/2 QAR956.00 $1 Duration
23-Nov-13 QAR0.00 CP 745/2 QAR478.00 $1 Duration
24-Nov-13 QAR0.00 CP 745/2 QAR9,557.00 $1 Duration
26-Nov-13 QAR0.00 CP 745/2 QAR11,947.00 $1 Duration
25-Nov-13 QAR0.00 CP 745/2 QAR10,992.00 $1 Duration
27-Nov-13 QAR0.00 CP 745/2 QAR1,434.00 $1 Duration
4-Dec-13 QAR0.00 CP 745/2 QAR1,434.00 $1 Duration
28-Nov-13 QAR0.00 CP 745/2 QAR956.00 $1 Duration
5-Dec-13 QAR0.00 CP 745/2 QAR3,823.00 $1 Duration
30-Nov-13 QAR0.00 CP 745/2 QAR956.00 $1 Duration
14-Dec-13 QAR0.00 CP 745/2 QAR23,649.00 $1 Duration
23-Dec-13 QAR0.00 QAR20,874.00 $1
1-Dec-13 QAR0.00 CP 745/2 QAR1,433.00 $1 Duration
3-Dec-13 QAR0.00 CP 745/2 QAR1,842.00 $1 Duration
15-Dec-13 QAR0.00 CP 745/2 QAR819.00 $1 Duration
5-Dec-13 QAR0.00 CP 745/2 QAR1,211.00 $1 Duration
8-Dec-13 QAR0.00 CP 745/2 QAR3,029.00 $1 Duration
28-Nov-13 QAR0.00 CP 745/2 QAR4,941.00 $1 Duration
10-Dec-13 QAR0.00 CP 745/2 QAR909.00 $1 Duration
12-Dec-13 QAR0.00 CP 745/2 QAR909.00 $1 Duration
23-Dec-13 QAR0.00 CP 745/2 QAR5,781.00 $1 Duration
28-Dec-13 QAR0.00 QAR227,161.25 $1
2-Dec-13 QAR0.00 QAR85,090.75 $1
26-Nov-13 QAR0.00 CP 745/2 QAR25,528.00 $1 Duration
27-Nov-13 QAR0.00 CP 745/2 QAR14,465.00 $1 Duration
28-Nov-13 QAR0.00 CP 745/2 QAR25,527.00 $1 Duration
30-Nov-13 QAR0.00 CP 745/2 QAR10,211.00 $1 Duration
1-Dec-13 QAR0.00 CP 745/2 QAR4,255.00 $1 Duration
2-Dec-13 QAR0.00 CP 745/2 QAR5,104.75 $1 Duration
22-Dec-13 QAR0.00 QAR116,041.75 $1
25-Nov-13 QAR0.00 CP 745/2 QAR7,009.00 $1 Duration
26-Nov-13 QAR0.00 CP 745/2 QAR1,274.00 $1 Duration
27-Nov-13 QAR0.00 CP 745/2 QAR637.00 $1 Duration
28-Nov-13 QAR0.00 CP 745/2 QAR12,744.00 $1 Duration
30-Nov-13 QAR0.00 CP 745/2 QAR14,655.75 $1 Duration
1-Dec-13 QAR0.00 CP 745/2 QAR15,930.00 $1 Duration
2-Dec-13 QAR0.00 CP 745/2 QAR1,912.00 $1 Duration
2-Dec-13 QAR0.00 CP 745/2 QAR1,274.00 $1 Duration
3-Dec-13 QAR0.00 CP 745/2 QAR1,274.00 $1 Duration
9-Dec-13 QAR0.00 CP 745/2 QAR1,912.00 $1 Duration
10-Dec-13 QAR0.00 CP 745/2 QAR5,098.00 $1 Duration
22-Dec-13 QAR0.00 CP 745/2 QAR52,322.00 $1 Duration
28-Dec-13 QAR0.00 QAR26,028.75 $1
4-Dec-13 QAR0.00 CP 745/2 QAR8,600.00 $1 Duration
8-Dec-13 QAR0.00 CP 745/2 QAR11,058.00 $1 Duration
11-Dec-13 QAR0.00 CP 745/2 QAR4,914.75 $1 Duration
28-Dec-13 QAR0.00 CP 745/2 QAR1,456.00 $1 Duration
24-May-14 QAR0.00 QAR899,259.00 $1
22-Dec-13 QAR0.00 QAR167,590.00 $1
9-Dec-13 QAR0.00 CP 745/2 QAR50,277.00 $1 Duration
11-Dec-13 QAR0.00 CP 745/2 QAR28,490.00 $1 Duration
14-Dec-13 QAR0.00 CP 745/2 QAR50,277.00 $1 Duration
16-Dec-13 QAR0.00 CP 745/2 QAR20,111.00 $1 Duration
19-Dec-13 QAR0.00 CP 745/2 QAR8,380.00 $1 Duration
22-Dec-13 QAR0.00 CP 745/2 QAR10,055.00 $1 Duration
28-Jan-14 QAR0.00 QAR374,221.00 $1
15-Dec-13 QAR0.00 CP 745/2 QAR29,829.00 $1 Duration
17-Dec-13 QAR0.00 CP 745/2 QAR5,423.00 $1 Duration
21-Dec-13 QAR0.00 CP 745/2 QAR2,712.00 $1 Duration
23-Dec-13 QAR0.00 CP 745/2 QAR54,234.00 $1 Duration
25-Dec-13 QAR0.00 CP 745/2 QAR62,369.00 $1 Duration
28-Dec-13 QAR0.00 CP 745/2 QAR67,793.00 $1 Duration
30-Dec-13 QAR0.00 CP 745/2 QAR8,135.00 $1 Duration
5-Jan-14 QAR0.00 CP 745/2 QAR8,135.00 $1 Duration
1-Jan-14 QAR0.00 CP 745/2 QAR5,423.00 $1 Duration
7-Jan-14 QAR0.00 CP 745/2 QAR21,694.00 $1 Duration
1-Jan-14 QAR0.00 CP 745/2 QAR5,423.00 $1 Duration
28-Jan-14 QAR0.00 CP 745/2 QAR103,051.00 $0 Duration
24-Apr-14 QAR0.00 QAR0.00 $0
17-Apr-14 QAR0.00 QAR0.00 $0
7-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
7-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
9-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
12-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
24-Apr-14 QAR0.00 QAR0.00 $0
7-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
8-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
9-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
12-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
16-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
19-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
19-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
21-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
22-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
20-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
24-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
24-May-14 QAR0.00 QAR357,448.00 $1
26-Apr-14 QAR0.00 CP 745/2 QAR41,615.00 $1 Duration
28-Apr-14 QAR0.00 CP 745/2 QAR53,506.00 $1 Duration
10-May-14 QAR0.00 CP 745/2 QAR23,780.00 $1 Duration
26-Apr-14 QAR0.00 CP 745/2 QAR69,172.00 $1 Duration
30-Apr-14 QAR0.00 CP 745/2 QAR16,961.00 $1 Duration
3-May-14 QAR0.00 CP 745/2 QAR42,402.00 $1 Duration
5-May-14 QAR0.00 CP 745/2 QAR12,721.00 $1 Duration
7-May-14 QAR0.00 CP 745/2 QAR12,721.00 $1 Duration
24-May-14 QAR0.00 CP 745/2 QAR84,570.00 $1 Duration
25-Jun-14 QAR0.00 QAR1,228,680.00 $1
5-Jan-14 QAR0.00 QAR187,916.75 $1
24-Dec-13 QAR0.00 CP 745/2 QAR56,375.00 $1 Duration
26-Dec-13 QAR0.00 CP 745/2 QAR31,945.75 $1 Duration
29-Dec-13 QAR0.00 CP 745/2 QAR56,375.00 $1 Duration
31-Dec-13 QAR0.00 CP 745/2 QAR22,550.00 $1 Duration
2-Jan-14 QAR0.00 CP 745/2 QAR9,396.00 $1 Duration
5-Jan-14 QAR0.00 CP 745/2 QAR11,275.00 $1 Duration
25-Feb-14 QAR0.00 QAR482,299.50 $1
7-Jan-14 QAR0.00 CP 745/2 QAR40,342.00 $1 Duration
9-Jan-14 QAR0.00 CP 745/2 QAR7,333.75 $1 Duration
12-Jan-14 QAR0.00 CP 745/2 QAR3,668.00 $1 Duration
14-Jan-14 QAR0.00 CP 745/2 QAR73,349.75 $1 Duration
16-Jan-14 QAR0.00 CP 745/2 QAR84,352.00 $1 Duration
19-Jan-14 QAR0.00 CP 745/2 QAR91,688.00 $1 Duration
27-Jan-14 QAR0.00 CP 745/2 QAR11,003.00 $1 Duration
21-Jan-14 QAR0.00 CP 745/2 QAR11,003.00 $1 Duration
23-Jan-14 QAR0.00 CP 745/2 QAR7,335.00 $1 Duration
29-Jan-14 QAR0.00 CP 745/2 QAR29,340.00 $1 Duration
23-Jan-14 QAR0.00 CP 745/2 QAR7,335.00 $1 Duration
25-Feb-14 QAR0.00 CP 745/2 QAR115,550.00 $1 Duration
1-May-14 QAR0.00 QAR0.00 $0
23-Apr-14 QAR0.00 QAR0.00 $0
13-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
13-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
15-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
20-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
1-May-14 QAR0.00 QAR0.00 $0
15-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
15-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
16-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
19-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
21-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
29-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
28-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
29-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
1-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
25-Jun-14 QAR0.00 QAR558,463.75 $1
17-May-14 QAR0.00 CP 745/2 QAR58,861.75 $1 Duration
19-May-14 QAR0.00 CP 745/2 QAR75,681.00 $1 Duration
31-May-14 QAR0.00 CP 745/2 QAR33,636.00 $1 Duration
14-May-14 QAR0.00 CP 745/2 QAR113,640.00 $1 Duration
21-May-14 QAR0.00 CP 745/2 QAR27,864.00 $1 Duration
24-May-14 QAR0.00 CP 745/2 QAR69,661.00 $1 Duration
26-May-14 QAR0.00 CP 745/2 QAR20,898.00 $1 Duration
28-May-14 QAR0.00 CP 745/2 QAR20,898.00 $1 Duration
25-Jun-14 QAR0.00 CP 745/2 QAR137,324.00 $1 Duration
16-Feb-14 QAR0.00 QAR457,173.00 $1
6-Jan-14 QAR0.00 QAR86,883.00 $1
31-Dec-13 QAR0.00 CP 745/2 QAR26,065.00 $1 Duration
1-Jan-14 QAR0.00 CP 745/2 QAR14,770.00 $1 Duration
2-Jan-14 QAR0.00 CP 745/2 QAR26,065.00 $1 Duration
5-Jan-14 QAR0.00 CP 745/2 QAR4,344.00 $1 Duration
4-Jan-14 QAR0.00 CP 745/2 QAR10,426.00 $1 Duration
6-Jan-14 QAR0.00 CP 745/2 QAR5,213.00 $1 Duration
3-Feb-14 QAR0.00 QAR164,933.00 $1
8-Jan-14 QAR0.00 CP 745/2 QAR12,266.00 $1 Duration
9-Jan-14 QAR0.00 CP 745/2 QAR2,230.00 $1 Duration
11-Jan-14 QAR0.00 CP 745/2 QAR1,115.00 $1 Duration
12-Jan-14 QAR0.00 CP 745/2 QAR22,302.00 $1 Duration
13-Jan-14 QAR0.00 CP 745/2 QAR25,647.00 $1 Duration
14-Jan-14 QAR0.00 CP 745/2 QAR27,877.00 $1 Duration
22-Jan-14 QAR0.00 CP 745/2 QAR3,345.00 $1 Duration
23-Jan-14 QAR0.00 CP 745/2 QAR8,921.00 $1 Duration
15-Jan-14 QAR0.00 CP 745/2 QAR3,345.00 $1 Duration
3-Feb-14 QAR0.00 CP 745/2 QAR53,425.00 $1 Duration
16-Jan-14 QAR0.00 CP 745/2 QAR2,230.00 $1 Duration
18-Jan-14 QAR0.00 CP 745/2 QAR2,230.00 $1 Duration
16-Feb-14 QAR0.00 QAR205,357.00 $1
22-Jan-14 QAR0.00 CP 745/2 QAR18,681.00 $1 Duration
25-Jan-14 QAR0.00 CP 745/2 QAR24,018.00 $1 Duration
5-Feb-14 QAR0.00 CP 745/2 QAR10,675.00 $1 Duration
20-Jan-14 QAR0.00 CP 745/2 QAR44,468.00 $1 Duration
27-Jan-14 QAR0.00 CP 745/2 QAR10,903.00 $1 Duration
29-Jan-14 QAR0.00 CP 745/2 QAR27,259.00 $1 Duration
3-Feb-14 QAR0.00 CP 745/2 QAR8,178.00 $1 Duration
16-Feb-14 QAR0.00 CP 745/2 QAR52,997.00 $1 Duration
1-Feb-14 QAR0.00 CP 745/2 QAR8,178.00 $1 Duration
17-Jul-14 QAR0.00 QAR1,319,865.00 $1
26-Jan-14 QAR0.00 QAR188,315.00 $1
14-Jan-14 QAR0.00 CP 745/2 QAR56,494.00 $1 Duration
16-Jan-14 QAR0.00 CP 745/2 QAR32,013.00 $1 Duration
19-Jan-14 QAR0.00 CP 745/2 QAR56,495.00 $1 Duration
23-Jan-14 QAR0.00 CP 745/2 QAR9,416.00 $1 Duration
21-Jan-14 QAR0.00 CP 745/2 QAR22,598.00 $1 Duration
26-Jan-14 QAR0.00 CP 745/2 QAR11,299.00 $1 Duration
23-Mar-14 QAR0.00 QAR482,545.00 $1
25-Jan-14 QAR0.00 CP 745/2 QAR40,343.00 $1 Duration
27-Jan-14 QAR0.00 CP 745/2 QAR7,335.00 $1 Duration
29-Jan-14 QAR0.00 CP 745/2 QAR3,667.00 $1 Duration
1-Feb-14 QAR0.00 CP 745/2 QAR73,350.00 $1 Duration
3-Feb-14 QAR0.00 CP 745/2 QAR84,352.00 $1 Duration
5-Feb-14 QAR0.00 CP 745/2 QAR91,688.00 $1 Duration
8-Feb-14 QAR0.00 CP 745/2 QAR11,002.00 $1 Duration
15-Feb-14 QAR0.00 CP 745/2 QAR11,003.00 $1 Duration
10-Feb-14 QAR0.00 CP 745/2 QAR7,335.00 $1 Duration
17-Feb-14 QAR0.00 CP 745/2 QAR29,340.00 $1 Duration
10-Feb-14 QAR0.00 CP 745/2 QAR7,335.00 $1 Duration
23-Mar-14 QAR0.00 CP 745/2 QAR115,795.00 $1 Duration
11-May-14 QAR0.00 QAR0.00 $0
5-May-14 QAR0.00 QAR0.00 $0
23-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
23-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
30-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
28-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
5-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-May-14 QAR0.00 QAR0.00 $0
23-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
24-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
28-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
30-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
3-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
5-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
5-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
7-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
8-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
6-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-Jul-14 QAR0.00 QAR649,005.00 $1
22-May-14 QAR0.00 CP 745/2 QAR55,995.00 $1 Duration
25-May-14 QAR0.00 CP 745/2 QAR71,995.00 $1 Duration
7-Jun-14 QAR0.00 CP 745/2 QAR31,998.00 $1 Duration
20-May-14 QAR0.00 CP 745/2 QAR143,285.00 $1 Duration
27-May-14 QAR0.00 CP 745/2 QAR35,132.00 $1 Duration
29-May-14 QAR0.00 CP 745/2 QAR87,833.00 $1 Duration
1-Jun-14 QAR0.00 CP 745/2 QAR26,350.00 $1 Duration
3-Jun-14 QAR0.00 CP 745/2 QAR26,350.00 $1 Duration
17-Jul-14 QAR0.00 CP 745/2 QAR170,067.00 $1 Duration
14-Jul-14 QAR0.00 QAR1,350,481.00 $1
9-Feb-14 QAR0.00 QAR183,732.00 $1
28-Jan-14 QAR0.00 CP 745/2 QAR55,120.00 $1 Duration
30-Jan-14 QAR0.00 CP 745/2 QAR31,233.00 $1 Duration
2-Feb-14 QAR0.00 CP 745/2 QAR55,120.00 $1 Duration
4-Feb-14 QAR0.00 CP 745/2 QAR22,048.00 $1 Duration
6-Feb-14 QAR0.00 CP 745/2 QAR9,187.00 $1 Duration
9-Feb-14 QAR0.00 CP 745/2 QAR11,024.00 $1 Duration
25-Mar-14 QAR0.00 QAR463,797.00 $1
6-Feb-14 QAR0.00 CP 745/2 QAR38,590.00 $1 Duration
9-Feb-14 QAR0.00 CP 745/2 QAR7,016.00 $1 Duration
12-Feb-14 QAR0.00 CP 745/2 QAR3,508.00 $1 Duration
15-Feb-14 QAR0.00 CP 745/2 QAR70,164.00 $1 Duration
17-Feb-14 QAR0.00 CP 745/2 QAR80,689.00 $1 Duration
19-Feb-14 QAR0.00 CP 745/2 QAR87,705.00 $1 Duration
22-Feb-14 QAR0.00 CP 745/2 QAR10,525.00 $1 Duration
24-Feb-14 QAR0.00 CP 745/2 QAR7,016.00 $1 Duration
27-Feb-14 QAR0.00 CP 745/2 QAR10,525.00 $1 Duration
2-Mar-14 QAR0.00 CP 745/2 QAR28,066.00 $1 Duration
24-Feb-14 QAR0.00 CP 745/2 QAR7,016.00 $1 Duration
25-Mar-14 QAR0.00 CP 745/2 QAR112,977.00 $1 Duration
17-May-14 QAR0.00 QAR0.00 $0
14-May-14 QAR0.00 QAR0.00 $0
30-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
30-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
4-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
6-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
8-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-May-14 QAR0.00 QAR0.00 $0
29-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
30-Apr-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
1-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
4-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
6-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
8-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
11-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
13-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
12-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-Jul-14 QAR0.00 QAR702,952.00 $1
28-May-14 QAR0.00 CP 745/2 QAR57,429.00 $1 Duration
31-May-14 QAR0.00 CP 745/2 QAR73,837.00 $1 Duration
14-Jun-14 QAR0.00 CP 745/2 QAR32,817.00 $1 Duration
26-May-14 QAR0.00 CP 745/2 QAR158,107.00 $1 Duration
2-Jun-14 QAR0.00 CP 745/2 QAR38,768.00 $1 Duration
5-Jun-14 QAR0.00 CP 745/2 QAR96,919.00 $1 Duration
8-Jun-14 QAR0.00 CP 745/2 QAR29,076.00 $1 Duration
11-Jun-14 QAR0.00 CP 745/2 QAR29,076.00 $1 Duration
14-Jul-14 QAR0.00 CP 745/2 QAR186,923.00 $1 Duration
13-Jul-14 QAR0.00 QAR1,097,252.00 $1
25-Feb-14 QAR0.00 QAR191,902.00 $1
13-Feb-14 QAR0.00 CP 745/2 QAR57,571.00 $1 Duration
16-Feb-14 QAR0.00 CP 745/2 QAR32,623.00 $1 Duration
18-Feb-14 QAR0.00 CP 745/2 QAR57,571.00 $1 Duration
20-Feb-14 QAR0.00 CP 745/2 QAR23,028.00 $1 Duration
23-Feb-14 QAR0.00 CP 745/2 QAR9,595.00 $1 Duration
25-Feb-14 QAR0.00 CP 745/2 QAR11,514.00 $1 Duration
3-Apr-14 QAR0.00 QAR452,891.00 $1
20-Feb-14 QAR0.00 CP 745/2 QAR36,838.00 $1 Duration
23-Feb-14 QAR0.00 CP 745/2 QAR6,698.00 $1 Duration
25-Feb-14 QAR0.00 CP 745/2 QAR3,349.00 $1 Duration
27-Feb-14 QAR0.00 CP 745/2 QAR66,977.00 $1 Duration
2-Mar-14 QAR0.00 CP 745/2 QAR77,025.00 $1 Duration
4-Mar-14 QAR0.00 CP 745/2 QAR83,723.00 $1 Duration
6-Mar-14 QAR0.00 CP 745/2 QAR10,047.00 $1 Duration
9-Mar-14 QAR0.00 CP 745/2 QAR6,698.00 $1 Duration
12-Mar-14 QAR0.00 CP 745/2 QAR10,047.00 $1 Duration
15-Mar-14 QAR0.00 CP 745/2 QAR26,791.00 $1 Duration
9-Mar-14 QAR0.00 CP 745/2 QAR6,698.00 $1 Duration
3-Apr-14 QAR0.00 CP 745/2 QAR118,000.00 $1 Duration
29-May-14 QAR0.00 QAR0.00 $0
21-May-14 QAR0.00 QAR0.00 $0
10-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
10-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
13-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
21-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
29-May-14 QAR0.00 QAR0.00 $0
12-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
13-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
14-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
17-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
19-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
21-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
24-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
24-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
26-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
27-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
25-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
29-May-14 QAR0.00 CP 745/2 QAR0.00 $0 Duration
13-Jul-14 QAR0.00 QAR452,459.00 $1
7-Jun-14 QAR0.00 CP 745/2 QAR40,228.00 $1 Duration
9-Jun-14 QAR0.00 CP 745/2 QAR51,722.00 $1 Duration
24-Jun-14 QAR0.00 CP 745/2 QAR22,988.00 $1 Duration
2-Jun-14 QAR0.00 CP 745/2 QAR98,817.00 $1 Duration
12-Jun-14 QAR0.00 CP 745/2 QAR24,230.00 $1 Duration
15-Jun-14 QAR0.00 CP 745/2 QAR60,575.00 $1 Duration
21-Jun-14 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
13-Jul-14 QAR0.00 CP 745/2 QAR117,555.00 $1 Duration
18-Jun-14 QAR0.00 CP 745/2 QAR18,172.00 $1 Duration
15-Apr-14 QAR0.00 QAR652,528.00 $1
10-Mar-14 QAR0.00 QAR158,424.00 $1
26-Feb-14 QAR0.00 CP 745/2 QAR47,527.00 $1 Duration
1-Mar-14 QAR0.00 CP 745/2 QAR26,933.00 $1 Duration
3-Mar-14 QAR0.00 CP 745/2 QAR47,527.00 $1 Duration
5-Mar-14 QAR0.00 CP 745/2 QAR19,011.00 $1 Duration
8-Mar-14 QAR0.00 CP 745/2 QAR7,921.00 $1 Duration
10-Mar-14 QAR0.00 CP 745/2 QAR9,505.00 $1 Duration
5-Apr-14 QAR0.00 QAR336,725.00 $1
27-Feb-14 QAR0.00 CP 745/2 QAR26,324.00 $1 Duration
2-Mar-14 QAR0.00 CP 745/2 QAR4,786.00 $1 Duration
4-Mar-14 QAR0.00 CP 745/2 QAR2,393.00 $1 Duration
6-Mar-14 QAR0.00 CP 745/2 QAR47,862.00 $1 Duration
9-Mar-14 QAR0.00 CP 745/2 QAR55,042.00 $1 Duration
11-Mar-14 QAR0.00 CP 745/2 QAR59,828.00 $1 Duration
22-Mar-14 QAR0.00 CP 745/2 QAR19,145.00 $1 Duration
13-Mar-14 QAR0.00 CP 745/2 QAR7,179.00 $1 Duration
16-Mar-14 QAR0.00 CP 745/2 QAR4,786.00 1 Duration
19-Mar-14 QAR0.00 CP 745/2 QAR7,179.00 1 Duration
16-Mar-14 QAR0.00 CP 745/2 QAR4,786.00 1 Duration
5-Apr-14 QAR0.00 CP 745/2 QAR97,415.00 1 Duration
15-Apr-14 QAR0.00 QAR157,379.00 1
24-Mar-14 QAR0.00 CP 745/2 QAR30,148.00 1 Duration
26-Mar-14 QAR0.00 CP 745/2 QAR38,762.00 1 Duration
22-Mar-14 QAR0.00 CP 745/2 QAR19,763.00 1 Duration
29-Mar-14 QAR0.00 CP 745/2 QAR4,846.00 1 Duration
31-Mar-14 QAR0.00 CP 745/2 QAR12,115.00 1 Duration
2-Apr-14 QAR0.00 CP 745/2 QAR3,635.00 1 Duration
5-Apr-14 QAR0.00 CP 745/2 QAR3,635.00 1 Duration
7-Apr-14 QAR0.00 CP 745/2 QAR17,227.00 1 Duration
15-Apr-14 QAR0.00 CP 745/2 QAR27,248.00 1 Duration
16-Jul-14 QAR0.00 QAR395,098.00 1
11-Mar-14 QAR0.00 QAR87,681.00 1
5-Mar-14 QAR0.00 CP 745/2 QAR26,304.00 1 Duration
6-Mar-14 QAR0.00 CP 745/2 QAR14,906.00 1 Duration
8-Mar-14 QAR0.00 CP 745/2 QAR26,304.00 1 Duration
10-Mar-14 QAR0.00 CP 745/2 QAR4,384.00 1 Duration
9-Mar-14 QAR0.00 CP 745/2 QAR10,522.00 1 Duration
11-Mar-14 QAR0.00 CP 745/2 QAR5,261.00 1 Duration
31-Mar-14 QAR0.00 QAR181,354.00 1
6-Mar-14 QAR0.00 CP 745/2 QAR14,018.00 1 Duration
8-Mar-14 QAR0.00 CP 745/2 QAR2,549.00 1 Duration
9-Mar-14 QAR0.00 CP 745/2 QAR1,274.00 1 Duration
10-Mar-14 QAR0.00 CP 745/2 QAR25,488.00 1 Duration
11-Mar-14 QAR0.00 CP 745/2 QAR29,311.00 1 Duration
12-Mar-14 QAR0.00 CP 745/2 QAR31,860.00 1 Duration
15-Mar-14 QAR0.00 CP 745/2 QAR3,823.00 1 Duration
20-Mar-14 QAR0.00 CP 745/2 QAR3,823.00 1 Duration
16-Mar-14 QAR0.00 CP 745/2 QAR2,549.00 1 Duration
23-Mar-14 QAR0.00 CP 745/2 QAR10,195.00 1 Duration
15-Mar-14 QAR0.00 CP 745/2 QAR2,549.00 1 Duration
31-Mar-14 QAR0.00 CP 745/2 QAR53,915.00 1 Duration
11-Jun-14 QAR0.00 QAR0.00 0
22-May-14 QAR0.00 QAR0.00 0
15-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
15-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
17-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
18-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
19-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
22-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
11-Jun-14 QAR0.00 QAR0.00 0
14-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
17-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
19-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
24-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
26-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
31-May-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
2-Jun-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
2-Jun-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
2-Jun-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
2-Jun-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
8-Jun-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
11-Jun-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
16-Jul-14 QAR0.00 QAR126,063.00 1
15-Jun-14 QAR0.00 CP 745/2 QAR14,334.00 1 Duration
18-Jun-14 QAR0.00 CP 745/2 QAR18,430.00 1 Duration
5-Jul-14 QAR0.00 CP 745/2 QAR8,191.00 1 Duration
12-Jun-14 QAR0.00 CP 745/2 QAR24,704.00 1 Duration
21-Jun-14 QAR0.00 CP 745/2 QAR6,057.00 1 Duration
24-Jun-14 QAR0.00 CP 745/2 QAR15,144.00 1 Duration
26-Jun-14 QAR0.00 CP 745/2 QAR4,543.00 1 Duration
1-Jul-14 QAR0.00 CP 745/2 QAR4,543.00 1 Duration
16-Jul-14 QAR0.00 CP 745/2 QAR30,117.00 1 Duration
15-Apr-14 QAR0.00 QAR368,442.00 1
17-Mar-14 QAR0.00 QAR77,917.00 1
11-Mar-14 QAR0.00 CP 745/2 QAR23,375.00 1 Duration
12-Mar-14 QAR0.00 CP 745/2 QAR13,246.00 1 Duration
13-Mar-14 QAR0.00 CP 745/2 QAR23,375.00 1 Duration
15-Mar-14 QAR0.00 CP 745/2 QAR9,350.00 1 Duration
16-Mar-14 QAR0.00 CP 745/2 QAR3,896.00 1 Duration
17-Mar-14 QAR0.00 CP 745/2 QAR4,675.00 1 Duration
8-Apr-14 QAR0.00 QAR175,712.00 1
16-Mar-14 QAR0.00 CP 745/2 QAR14,058.00 1 Duration
17-Mar-14 QAR0.00 CP 745/2 QAR2,557.00 1 Duration
18-Mar-14 QAR0.00 CP 745/2 QAR1,278.00 1 Duration
19-Mar-14 QAR0.00 CP 745/2 QAR25,560.00 1 Duration
20-Mar-14 QAR0.00 CP 745/2 QAR29,394.00 1 Duration
22-Mar-14 QAR0.00 CP 745/2 QAR31,950.00 1 Duration
24-Mar-14 QAR0.00 CP 745/2 QAR3,834.00 1 Duration
25-Mar-14 QAR0.00 CP 745/2 QAR2,556.00 1 Duration
30-Mar-14 QAR0.00 CP 745/2 QAR3,834.00 1 Duration
31-Mar-14 QAR0.00 CP 745/2 QAR10,224.00 1 Duration
24-Mar-14 QAR0.00 CP 745/2 QAR2,556.00 1 Duration
8-Apr-14 QAR0.00 CP 745/2 QAR47,911.00 1 Duration
15-Apr-14 QAR0.00 QAR114,813.00 1
1-Apr-14 QAR0.00 CP 745/2 QAR21,548.00 1 Duration
2-Apr-14 QAR0.00 CP 745/2 QAR27,703.00 1 Duration
8-Apr-14 QAR0.00 CP 745/2 QAR12,313.00 1 Duration
31-Mar-14 QAR0.00 CP 745/2 QAR14,823.00 1 Duration
3-Apr-14 QAR0.00 CP 745/2 QAR3,635.00 1 Duration
5-Apr-14 QAR0.00 CP 745/2 QAR9,086.00 1 Duration
6-Apr-14 QAR0.00 CP 745/2 QAR2,725.00 1 Duration
7-Apr-14 QAR0.00 CP 745/2 QAR2,726.00 1 Duration
15-Apr-14 QAR0.00 CP 745/2 QAR20,254.00 1 Duration
3-Aug-14 QAR0.00 QAR0.00 0
3-Aug-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
3-Aug-14 QAR0.00 CP 745/2 QAR0.00 0 Duration
Variance - BL1Actual TotaEarned ValPlanned Value Cost
($195) QAR0.00 QAR51,579QAR52,101,812.10
($195) QAR0.00 QAR7,307,QAR7,652,092.75
($195) QAR0.00 QAR0.00 QAR0.00
$0 QAR0.00 QAR0.00 QAR0.00
($195) QAR0.00 QAR0.00 QAR0.00
($161) QAR0.00 QAR0.00 QAR0.00
($195) QAR0.00 QAR7,307,QAR7,652,092.75
($195) QAR0.00 QAR0.00 QAR0.00
($164) QAR0.00 QAR395,29QAR395,298.25
($164) QAR0.00 QAR901,29QAR901,296.25
($195) QAR0.00 QAR5,044,QAR5,331,554.25
($195) QAR0.00 QAR797,28QAR842,670.00
($161) QAR0.00 QAR169,65QAR181,274.00
($196) QAR0.00 QAR0.00 QAR0.00
($766) QAR0.00 QAR0.00 QAR0.00
($821) QAR0.00 QAR0.00 QAR0.00
$20 QAR0.00 QAR0.00 QAR0.00
$35 QAR0.00 QAR0.00 QAR0.00
$14 QAR0.00 QAR0.00 QAR0.00
($619) QAR0.00 QAR0.00 QAR0.00
($799) QAR0.00 QAR0.00 QAR0.00
$30 QAR0.00 QAR0.00 QAR0.00
($118) QAR0.00 QAR0.00 QAR0.00
($133) QAR0.00 QAR0.00 QAR0.00
($519) QAR0.00 QAR0.00 QAR0.00
$40 QAR0.00 QAR0.00 QAR0.00
$28 QAR0.00 QAR0.00 QAR0.00
($4) QAR0.00 QAR0.00 QAR0.00
$25 QAR0.00 QAR0.00 QAR0.00
$25 QAR0.00 QAR0.00 QAR0.00
$65 QAR0.00 QAR0.00 QAR0.00
$31 QAR0.00 QAR0.00 QAR0.00
$37 QAR0.00 QAR0.00 QAR0.00
$6 QAR0.00 QAR0.00 QAR0.00
$37 QAR0.00 QAR0.00 QAR0.00
($196) QAR0.00 QAR0.00 QAR0.00
$207 QAR0.00 QAR0.00 QAR0.00
($128) QAR0.00 QAR0.00 QAR0.00
($905) QAR0.00 QAR0.00 QAR0.00
$8 QAR0.00 QAR0.00 QAR0.00
$0 QAR0.00 QAR0.00 QAR0.00
$28 QAR0.00 QAR0.00 QAR0.00
$0 QAR0.00 QAR0.00 QAR0.00
($8) QAR0.00 QAR0.00 QAR0.00
$5 QAR0.00 QAR0.00 QAR0.00
($12) QAR0.00 QAR0.00 QAR0.00
($575) QAR0.00 QAR0.00 QAR0.00
($15) QAR0.00 QAR0.00 QAR0.00
$19 QAR0.00 QAR0.00 QAR0.00
($23) QAR0.00 QAR0.00 QAR0.00
($402) QAR0.00 QAR0.00 QAR0.00
$4 QAR0.00 QAR0.00 QAR0.00
($10) QAR0.00 QAR0.00 QAR0.00
($931) QAR0.00 QAR0.00 QAR0.00
$9 QAR0.00 QAR0.00 QAR0.00
$11 QAR0.00 QAR0.00 QAR0.00
($17) QAR0.00 QAR0.00 QAR0.00
$8 QAR0.00 QAR0.00 QAR0.00
($9) QAR0.00 QAR0.00 QAR0.00
$8 QAR0.00 QAR0.00 QAR0.00
($728) QAR0.00 QAR0.00 QAR0.00
($931) QAR0.00 QAR0.00 QAR0.00
$20 QAR0.00 QAR0.00 QAR0.00
$23 QAR0.00 QAR0.00 QAR0.00
$0 QAR0.00 QAR0.00 QAR0.00
($4) QAR0.00 QAR0.00 QAR0.00
$0 QAR0.00 QAR0.00 QAR0.00
($29) QAR0.00 QAR0.00 QAR0.00
($617) QAR0.00 QAR0.00 QAR0.00
($753) QAR0.00 QAR0.00 QAR0.00
($573) QAR0.00 QAR0.00 QAR0.00
($605) QAR0.00 QAR0.00 QAR0.00
($592) QAR0.00 QAR0.00 QAR0.00
($533) QAR0.00 QAR0.00 QAR0.00
($388) QAR0.00 QAR0.00 QAR0.00
($640) QAR0.00 QAR0.00 QAR0.00
($623) QAR0.00 QAR0.00 QAR0.00
($195) QAR0.00 QAR44,271QAR44,449,719.35
($608) QAR0.00 QAR312,28QAR312,287.25
($295) QAR0.00 QAR0.00 QAR0.00
($26) QAR0.00 QAR0.00 QAR0.00
($36) QAR0.00 QAR0.00 QAR0.00
($225) QAR0.00 QAR0.00 QAR0.00
($154) QAR0.00 QAR147,51QAR147,513.25
($51) QAR0.00 QAR44,253QAR44,253.75
($49) QAR0.00 QAR25,076QAR25,076.75
($116) QAR0.00 QAR7,376.QAR7,376.00
($120) QAR0.00 QAR44,253QAR44,253.75
($119) QAR0.00 QAR17,702QAR17,702.00
($116) QAR0.00 QAR8,851.QAR8,851.00
($555) QAR0.00 QAR130,16QAR130,165.00
($49) QAR0.00 QAR6,308.QAR6,308.75
($49) QAR0.00 QAR1,146.QAR1,146.75
($49) QAR0.00 QAR574.00QAR574.00
($48) QAR0.00 QAR11,471QAR11,471.75
($68) QAR0.00 QAR13,191QAR13,191.75
($67) QAR0.00 QAR14,340QAR14,340.00
($63) QAR0.00 QAR1,147.QAR1,147.00
($143) QAR0.00 QAR72,807QAR72,807.00
($431) QAR0.00 QAR1,721.QAR1,721.00
($120) QAR0.00 QAR1,721.QAR1,721.00
($432) QAR0.00 QAR4,589.QAR4,589.00
($450) QAR0.00 QAR1,147.QAR1,147.00
($608) QAR0.00 QAR34,609QAR34,609.00
($57) QAR0.00 QAR11,434QAR11,434.00
($438) QAR0.00 QAR14,700QAR14,700.00
($434) QAR0.00 QAR6,534.QAR6,534.00
($480) QAR0.00 QAR1,941.QAR1,941.00
($616) QAR0.00 QAR940,95QAR940,954.75
($161) QAR0.00 QAR348,38QAR348,389.25
($128) QAR0.00 QAR104,51QAR104,516.75
($133) QAR0.00 QAR59,225QAR59,225.75
($131) QAR0.00 QAR104,51QAR104,516.75
($129) QAR0.00 QAR41,807QAR41,807.00
($126) QAR0.00 QAR17,420QAR17,420.00
($133) QAR0.00 QAR20,903QAR20,903.00
($181) QAR0.00 QAR440,24QAR440,241.50
($139) QAR0.00 QAR27,960QAR27,960.75
($139) QAR0.00 QAR5,083.QAR5,083.75
($138) QAR0.00 QAR2,541.QAR2,541.75
($137) QAR0.00 QAR50,838QAR50,838.75
($135) QAR0.00 QAR58,464QAR58,464.75
($134) QAR0.00 QAR63,548QAR63,548.75
($127) QAR0.00 QAR5,084.QAR5,084.00
($134) QAR0.00 QAR7,626.QAR7,626.00
($138) QAR0.00 QAR20,336QAR20,336.00
($146) QAR0.00 QAR7,625.QAR7,625.25
($144) QAR0.00 QAR5,083.QAR5,083.75
($150) QAR0.00 QAR186,04QAR186,048.00
($616) QAR0.00 QAR152,32QAR152,324.00
($491) QAR0.00 QAR23,016QAR23,016.00
($489) QAR0.00 QAR29,592QAR29,592.00
($484) QAR0.00 QAR13,152QAR13,152.00
($500) QAR0.00 QAR24,704QAR24,704.00
($496) QAR0.00 QAR6,057.QAR6,057.00
($495) QAR0.00 QAR15,144QAR15,144.00
($494) QAR0.00 QAR4,543.QAR4,543.00
($494) QAR0.00 QAR4,543.QAR4,543.00
($484) QAR0.00 QAR31,573QAR31,573.00
($592) QAR0.00 QAR406,56QAR406,563.35
$44 QAR0.00 QAR0.00 QAR0.00
$51 QAR0.00 QAR0.00 QAR0.00
$10 QAR0.00 QAR0.00 QAR0.00
($131) QAR0.00 QAR145,90QAR145,901.70
($18) QAR0.00 QAR43,770QAR43,770.90
($89) QAR0.00 QAR24,802QAR24,802.80
($87) QAR0.00 QAR43,771QAR43,771.00
($83) QAR0.00 QAR7,295.QAR7,295.00
($110) QAR0.00 QAR17,508QAR17,508.00
($107) QAR0.00 QAR8,754.QAR8,754.00
($171) QAR0.00 QAR195,50QAR195,504.65
($30) QAR0.00 QAR9,226.QAR9,226.75
($29) QAR0.00 QAR1,677.QAR1,677.50
($32) QAR0.00 QAR838.75QAR838.75
($34) QAR0.00 QAR16,776QAR16,776.50
($73) QAR0.00 QAR19,292QAR19,292.90
($72) QAR0.00 QAR20,970QAR20,970.75
($69) QAR0.00 QAR1,677.QAR1,677.75
($56) QAR0.00 QAR111,62QAR111,621.75
($128) QAR0.00 QAR2,516.QAR2,516.75
($151) QAR0.00 QAR2,516.QAR2,516.75
($130) QAR0.00 QAR6,710.QAR6,710.75
($161) QAR0.00 QAR1,677.QAR1,677.75
($592) QAR0.00 QAR65,157QAR65,157.00
($336) QAR0.00 QAR21,531QAR21,531.00
($322) QAR0.00 QAR12,303QAR12,303.00
($334) QAR0.00 QAR27,683QAR27,683.00
($463) QAR0.00 QAR3,640.QAR3,640.00
($465) QAR0.00 QAR390,22QAR390,220.25
$59 QAR0.00 QAR0.00 QAR0.00
$62 QAR0.00 QAR0.00 QAR0.00
$31 QAR0.00 QAR0.00 QAR0.00
($90) QAR0.00 QAR139,80QAR139,802.00
$35 QAR0.00 QAR41,941QAR41,941.00
$28 QAR0.00 QAR23,766QAR23,766.00
($72) QAR0.00 QAR41,941QAR41,941.00
($72) QAR0.00 QAR16,776QAR16,776.00
($71) QAR0.00 QAR6,990.QAR6,990.00
($73) QAR0.00 QAR8,388.QAR8,388.00
($129) QAR0.00 QAR188,36QAR188,363.00
$30 QAR0.00 QAR10,015QAR10,015.00
$27 QAR0.00 QAR1,821.QAR1,821.00
$21 QAR0.00 QAR910.00QAR910.00
$21 QAR0.00 QAR18,209QAR18,209.00
($26) QAR0.00 QAR20,940QAR20,940.00
($26) QAR0.00 QAR22,761QAR22,761.00
($41) QAR0.00 QAR1,821.QAR1,821.00
($70) QAR0.00 QAR2,731.QAR2,731.00
($101) QAR0.00 QAR7,284.QAR7,284.00
($93) QAR0.00 QAR97,319QAR97,319.00
($125) QAR0.00 QAR2,731.QAR2,731.00
($124) QAR0.00 QAR1,821.QAR1,821.00
($465) QAR0.00 QAR62,055QAR62,055.25
($337) QAR0.00 QAR14,996QAR14,996.75
($336) QAR0.00 QAR19,281QAR19,281.75
($327) QAR0.00 QAR8,570.QAR8,570.00
($383) QAR0.00 QAR4,940.QAR4,940.75
($378) QAR0.00 QAR1,212.QAR1,212.00
($377) QAR0.00 QAR3,029.QAR3,029.00
($375) QAR0.00 QAR909.00QAR909.00
($373) QAR0.00 QAR909.00QAR909.00
($361) QAR0.00 QAR8,207.QAR8,207.00
($494) QAR0.00 QAR750,24QAR750,241.00
$67 QAR0.00 QAR0.00 QAR0.00
$71 QAR0.00 QAR0.00 QAR0.00
$40 QAR0.00 QAR0.00 QAR0.00
($3) QAR0.00 QAR320,54QAR320,546.25
$5 QAR0.00 QAR96,163QAR96,163.75
$3 QAR0.00 QAR54,492QAR54,492.75
$5 QAR0.00 QAR96,164QAR96,164.00
$5 QAR0.00 QAR16,027QAR16,027.00
$4 QAR0.00 QAR38,465QAR38,465.75
($3) QAR0.00 QAR19,233QAR19,233.00
($31) QAR0.00 QAR355,99QAR355,992.25
$28 QAR0.00 QAR19,772QAR19,772.75
($15) QAR0.00 QAR3,594.QAR3,594.75
($15) QAR0.00 QAR1,797.QAR1,797.75
($15) QAR0.00 QAR35,951QAR35,951.00
($36) QAR0.00 QAR41,343QAR41,343.00
($36) QAR0.00 QAR44,939QAR44,939.00
($44) QAR0.00 QAR5,393.QAR5,393.00
($40) QAR0.00 QAR14,380QAR14,380.00
($25) QAR0.00 QAR176,23QAR176,238.00
($47) QAR0.00 QAR3,595.QAR3,595.00
($48) QAR0.00 QAR5,393.QAR5,393.00
($48) QAR0.00 QAR3,595.QAR3,595.00
($494) QAR0.00 QAR73,702QAR73,702.50
($279) QAR0.00 QAR24,351QAR24,351.50
($272) QAR0.00 QAR31,310QAR31,310.00
($264) QAR0.00 QAR13,916QAR13,916.00
($386) QAR0.00 QAR4,125.QAR4,125.00
($646) QAR0.00 QAR4,563,QAR4,592,315.00
($324) QAR0.00 QAR0.00 QAR0.00
$29 QAR0.00 QAR0.00 QAR0.00
$79 QAR0.00 QAR0.00 QAR0.00
($257) QAR0.00 QAR0.00 QAR0.00
($269) QAR0.00 QAR830,89QAR830,892.00
($197) QAR0.00 QAR249,26QAR249,267.00
($210) QAR0.00 QAR141,25QAR141,251.00
($206) QAR0.00 QAR249,26QAR249,268.00
($203) QAR0.00 QAR99,707QAR99,707.00
($199) QAR0.00 QAR41,545QAR41,545.00
($198) QAR0.00 QAR49,854QAR49,854.00
($541) QAR0.00 QAR1,756,QAR1,756,950.00
($210) QAR0.00 QAR134,62QAR134,626.00
($207) QAR0.00 QAR24,478QAR24,478.00
($205) QAR0.00 QAR12,238QAR12,238.00
($204) QAR0.00 QAR244,77QAR244,775.00
($209) QAR0.00 QAR281,49QAR281,491.00
($207) QAR0.00 QAR305,96QAR305,968.00
($201) QAR0.00 QAR36,716QAR36,716.00
($200) QAR0.00 QAR97,910QAR97,910.00
($201) QAR0.00 QAR24,478QAR24,478.00
($205) QAR0.00 QAR36,716QAR36,716.00
($203) QAR0.00 QAR24,478QAR24,478.00
($415) QAR0.00 QAR533,07QAR533,076.00
($646) QAR0.00 QAR1,975,QAR2,004,473.00
($541) QAR0.00 QAR192,44QAR192,441.00
($535) QAR0.00 QAR247,42QAR247,425.00
($509) QAR0.00 QAR109,96QAR109,967.00
($553) QAR0.00 QAR416,41QAR424,913.00
($537) QAR0.00 QAR102,10QAR104,188.00
($531) QAR0.00 QAR255,26QAR260,470.00
($521) QAR0.00 QAR76,578QAR78,141.00
($527) QAR0.00 QAR76,578QAR78,141.00
($494) QAR0.00 QAR498,61QAR508,787.00
($371) QAR0.00 QAR853,19QAR853,191.80
$30 QAR0.00 QAR0.00 QAR0.00
$102 QAR0.00 QAR0.00 QAR0.00
$8 QAR0.00 QAR0.00 QAR0.00
($211) QAR0.00 QAR144,65QAR144,658.40
($169) QAR0.00 QAR43,397QAR43,397.40
($168) QAR0.00 QAR24,592QAR24,592.00
($166) QAR0.00 QAR43,398QAR43,398.00
($162) QAR0.00 QAR7,232.QAR7,232.00
($165) QAR0.00 QAR17,359QAR17,359.00
($164) QAR0.00 QAR8,680.QAR8,680.00
($337) QAR0.00 QAR300,60QAR300,607.00
($145) QAR0.00 QAR21,482QAR21,482.00
($144) QAR0.00 QAR3,906.QAR3,906.00
($144) QAR0.00 QAR1,953.QAR1,953.00
($143) QAR0.00 QAR39,059QAR39,059.00
($144) QAR0.00 QAR44,917QAR44,917.00
($142) QAR0.00 QAR48,823QAR48,823.00
($159) QAR0.00 QAR5,859.QAR5,859.00
($157) QAR0.00 QAR15,623QAR15,623.00
($164) QAR0.00 QAR5,859.QAR5,859.00
($159) QAR0.00 QAR3,906.QAR3,906.00
($253) QAR0.00 QAR105,31QAR105,314.00
($167) QAR0.00 QAR3,906.QAR3,906.00
($371) QAR0.00 QAR407,92QAR407,926.40
($275) QAR0.00 QAR47,367QAR47,367.90
($273) QAR0.00 QAR60,902QAR60,902.00
($322) QAR0.00 QAR79,053QAR79,053.50
($306) QAR0.00 QAR19,384QAR19,384.00
($304) QAR0.00 QAR48,460QAR48,460.00
($302) QAR0.00 QAR14,538QAR14,538.00
($300) QAR0.00 QAR14,538QAR14,538.00
($261) QAR0.00 QAR27,067QAR27,067.00
($282) QAR0.00 QAR96,616QAR96,616.00
($634) QAR0.00 QAR2,809,QAR2,820,436.00
($298) QAR0.00 QAR0.00 QAR0.00
($228) QAR0.00 QAR0.00 QAR0.00
$117 QAR0.00 QAR0.00 QAR0.00
($284) QAR0.00 QAR764,92QAR764,924.50
($204) QAR0.00 QAR229,47QAR229,477.25
($219) QAR0.00 QAR130,03QAR130,037.25
($217) QAR0.00 QAR229,47QAR229,477.00
($211) QAR0.00 QAR38,246QAR38,246.00
($215) QAR0.00 QAR91,791QAR91,791.00
($209) QAR0.00 QAR45,896QAR45,896.00
($488) QAR0.00 QAR1,253,QAR1,253,247.00
($122) QAR0.00 QAR97,039QAR97,039.00
($157) QAR0.00 QAR17,644QAR17,644.00
($156) QAR0.00 QAR8,822.QAR8,822.00
($157) QAR0.00 QAR176,43QAR176,435.00
($158) QAR0.00 QAR202,90QAR202,900.00
($158) QAR0.00 QAR220,54QAR220,543.00
($171) QAR0.00 QAR26,465QAR26,465.00
($169) QAR0.00 QAR70,574QAR70,574.00
($372) QAR0.00 QAR371,07QAR371,073.00
($177) QAR0.00 QAR26,464QAR26,464.00
($174) QAR0.00 QAR17,644QAR17,644.00
($174) QAR0.00 QAR17,644QAR17,644.00
($634) QAR0.00 QAR791,06QAR802,264.50
($332) QAR0.00 QAR84,787QAR84,787.50
($331) QAR0.00 QAR109,01QAR109,012.00
($323) QAR0.00 QAR48,450QAR48,450.00
($518) QAR0.00 QAR159,78QAR163,048.00
($512) QAR0.00 QAR39,179QAR39,979.00
($510) QAR0.00 QAR97,949QAR99,948.00
($508) QAR0.00 QAR29,384QAR29,984.00
($506) QAR0.00 QAR29,384QAR29,984.00
($484) QAR0.00 QAR193,13QAR197,072.00
($545) QAR0.00 QAR6,765,QAR6,765,909.50
($545) QAR0.00 QAR6,765,QAR6,765,909.50
($358) QAR0.00 QAR0.00 QAR0.00
$69 QAR0.00 QAR0.00 QAR0.00
($270) QAR0.00 QAR0.00 QAR0.00
($296) QAR0.00 QAR0.00 QAR0.00
($305) QAR0.00 QAR468,56QAR468,560.00
($33) QAR0.00 QAR140,56QAR140,568.00
($240) QAR0.00 QAR79,655QAR79,655.00
($237) QAR0.00 QAR140,56QAR140,568.00
($234) QAR0.00 QAR56,227QAR56,227.00
($230) QAR0.00 QAR23,428QAR23,428.00
($226) QAR0.00 QAR28,114QAR28,114.00
($454) QAR0.00 QAR550,34QAR550,349.50
($202) QAR0.00 QAR33,909QAR33,909.00
($200) QAR0.00 QAR6,165.QAR6,165.50
($197) QAR0.00 QAR3,083.QAR3,083.00
($202) QAR0.00 QAR61,652QAR61,652.00
($226) QAR0.00 QAR70,900QAR70,900.00
($224) QAR0.00 QAR77,065QAR77,065.00
($217) QAR0.00 QAR9,248.QAR9,248.00
($216) QAR0.00 QAR24,661QAR24,661.00
($342) QAR0.00 QAR242,08QAR242,088.00
($225) QAR0.00 QAR9,248.QAR9,248.00
($225) QAR0.00 QAR6,165.QAR6,165.00
($223) QAR0.00 QAR6,165.QAR6,165.00
($593) QAR0.00 QAR153,08QAR153,089.00
($468) QAR0.00 QAR28,732QAR28,732.00
($466) QAR0.00 QAR36,940QAR36,940.00
($456) QAR0.00 QAR16,418QAR16,418.00
($470) QAR0.00 QAR19,763QAR19,763.00
($464) QAR0.00 QAR4,846.QAR4,846.00
($462) QAR0.00 QAR12,115QAR12,115.00
($458) QAR0.00 QAR3,635.QAR3,635.00
($460) QAR0.00 QAR3,635.QAR3,635.00
($449) QAR0.00 QAR27,005QAR27,005.00
($504) QAR0.00 QAR4,756,QAR4,756,500.25
($356) QAR0.00 QAR993,72QAR993,723.00
($240) QAR0.00 QAR298,11QAR298,117.00
($278) QAR0.00 QAR168,93QAR168,933.00
($276) QAR0.00 QAR298,11QAR298,117.00
($274) QAR0.00 QAR119,24QAR119,247.00
($271) QAR0.00 QAR49,686QAR49,686.00
($269) QAR0.00 QAR59,623QAR59,623.00
($517) QAR0.00 QAR1,807,QAR1,807,861.00
($210) QAR0.00 QAR142,38QAR142,388.00
($208) QAR0.00 QAR25,890QAR25,890.00
($206) QAR0.00 QAR12,944QAR12,944.00
($203) QAR0.00 QAR258,88QAR258,888.00
($201) QAR0.00 QAR297,72QAR297,721.00
($210) QAR0.00 QAR323,61QAR323,610.00
($206) QAR0.00 QAR38,833QAR38,833.00
($212) QAR0.00 QAR38,833QAR38,833.00
($207) QAR0.00 QAR103,55QAR103,555.00
($211) QAR0.00 QAR25,889QAR25,889.00
($212) QAR0.00 QAR25,889QAR25,889.00
($384) QAR0.00 QAR513,42QAR513,421.00
($504) QAR0.00 QAR1,954,QAR1,954,916.25
($434) QAR0.00 QAR165,13QAR165,135.00
($429) QAR0.00 QAR212,31QAR212,316.00
($404) QAR0.00 QAR94,363QAR94,363.00
($435) QAR0.00 QAR434,79QAR434,795.25
($424) QAR0.00 QAR106,61QAR106,611.00
($419) QAR0.00 QAR266,52QAR266,528.00
($409) QAR0.00 QAR79,958QAR79,958.00
($414) QAR0.00 QAR79,958QAR79,958.00
($381) QAR0.00 QAR515,25QAR515,252.00
($596) QAR0.00 QAR547,50QAR547,504.75
$37 QAR0.00 QAR207,83QAR207,836.25
$25 QAR0.00 QAR62,351QAR62,351.25
$26 QAR0.00 QAR35,332QAR35,332.00
$27 QAR0.00 QAR62,351QAR62,351.00
$29 QAR0.00 QAR24,940QAR24,940.00
$31 QAR0.00 QAR10,392QAR10,392.00
$32 QAR0.00 QAR12,470QAR12,470.00
$21 QAR0.00 QAR261,42QAR261,420.00
$38 QAR0.00 QAR16,944QAR16,944.00
$39 QAR0.00 QAR3,080.QAR3,080.00
$40 QAR0.00 QAR1,540.QAR1,540.00
$40 QAR0.00 QAR30,808QAR30,808.00
$27 QAR0.00 QAR35,429QAR35,429.00
$27 QAR0.00 QAR38,510QAR38,510.00
$5 QAR0.00 QAR4,621.QAR4,621.00
$33 QAR0.00 QAR4,621.QAR4,621.00
$34 QAR0.00 QAR12,323QAR12,323.00
$45 QAR0.00 QAR107,38QAR107,382.00
$21 QAR0.00 QAR3,081.QAR3,081.00
($1) QAR0.00 QAR3,081.QAR3,081.00
($596) QAR0.00 QAR78,248QAR78,248.50
($265) QAR0.00 QAR25,858QAR25,858.50
($260) QAR0.00 QAR33,246QAR33,246.00
($254) QAR0.00 QAR14,776QAR14,776.00
($451) QAR0.00 QAR4,368.QAR4,368.00
($616) QAR0.00 QAR289,90QAR289,906.00
$13 QAR0.00 QAR98,700QAR98,700.00
$108 QAR0.00 QAR29,610QAR29,610.00
$19 QAR0.00 QAR16,779QAR16,779.00
$20 QAR0.00 QAR29,610QAR29,610.00
$21 QAR0.00 QAR11,844QAR11,844.00
$22 QAR0.00 QAR4,935.QAR4,935.00
$11 QAR0.00 QAR5,922.QAR5,922.00
($442) QAR0.00 QAR143,45QAR143,455.00
$93 QAR0.00 QAR10,171QAR10,171.00
$93 QAR0.00 QAR1,848.QAR1,848.00
$94 QAR0.00 QAR925.00QAR925.00
$93 QAR0.00 QAR18,492QAR18,492.00
$37 QAR0.00 QAR21,266QAR21,266.00
$37 QAR0.00 QAR23,115QAR23,115.00
($335) QAR0.00 QAR50,995QAR50,995.00
$35 QAR0.00 QAR2,774.QAR2,774.00
$30 QAR0.00 QAR1,849.QAR1,849.00
$21 QAR0.00 QAR2,774.QAR2,774.00
$18 QAR0.00 QAR7,397.QAR7,397.00
($248) QAR0.00 QAR1,849.QAR1,849.00
($616) QAR0.00 QAR47,751QAR47,751.00
$23 QAR0.00 QAR15,779QAR15,779.00
$22 QAR0.00 QAR20,287QAR20,287.00
$22 QAR0.00 QAR9,016.QAR9,016.00
($468) QAR0.00 QAR2,669.QAR2,669.00
($572) QAR0.00 QAR728,86QAR729,448.00
($120) QAR0.00 QAR0.00 QAR0.00
$124 QAR0.00 QAR0.00 QAR0.00
($97) QAR0.00 QAR0.00 QAR0.00
$87 QAR0.00 QAR0.00 QAR0.00
($405) QAR0.00 QAR248,23QAR248,235.00
($319) QAR0.00 QAR74,471QAR74,471.00
($317) QAR0.00 QAR42,200QAR42,200.00
($315) QAR0.00 QAR74,471QAR74,471.00
($313) QAR0.00 QAR29,788QAR29,788.00
($311) QAR0.00 QAR12,411QAR12,411.00
($310) QAR0.00 QAR14,894QAR14,894.00
($374) QAR0.00 QAR376,96QAR376,962.00
($279) QAR0.00 QAR22,956QAR22,956.00
($319) QAR0.00 QAR4,174.QAR4,174.00
($318) QAR0.00 QAR2,087.QAR2,087.00
($316) QAR0.00 QAR41,736QAR41,736.00
($314) QAR0.00 QAR47,997QAR47,997.00
($313) QAR0.00 QAR52,171QAR52,171.00
($304) QAR0.00 QAR6,261.QAR6,261.00
($302) QAR0.00 QAR16,695QAR16,695.00
($283) QAR0.00 QAR168,27QAR168,276.00
($309) QAR0.00 QAR4,174.QAR4,174.00
($311) QAR0.00 QAR6,261.QAR6,261.00
($309) QAR0.00 QAR4,174.QAR4,174.00
($572) QAR0.00 QAR103,66QAR104,251.00
$44 QAR0.00 QAR34,449QAR34,449.00
$49 QAR0.00 QAR44,293QAR44,293.00
$42 QAR0.00 QAR19,685QAR19,685.00
($431) QAR0.00 QAR5,241.QAR5,824.00
($416) QAR0.00 QAR6,527,QAR6,527,860.25
($416) QAR0.00 QAR6,527,QAR6,527,860.25
($417) QAR0.00 QAR0.00 QAR0.00
$144 QAR0.00 QAR0.00 QAR0.00
($201) QAR0.00 QAR0.00 QAR0.00
($331) QAR0.00 QAR0.00 QAR0.00
($379) QAR0.00 QAR474,43QAR474,436.75
($193) QAR0.00 QAR142,33QAR142,331.00
($300) QAR0.00 QAR80,653QAR80,653.75
($295) QAR0.00 QAR142,33QAR142,331.00
($291) QAR0.00 QAR56,933QAR56,933.00
($286) QAR0.00 QAR23,722QAR23,722.00
($286) QAR0.00 QAR28,466QAR28,466.00
($511) QAR0.00 QAR745,33QAR745,338.75
($305) QAR0.00 QAR53,688QAR53,688.00
($302) QAR0.00 QAR9,762.QAR9,762.00
($300) QAR0.00 QAR4,880.QAR4,880.00
($298) QAR0.00 QAR97,614QAR97,614.75
($296) QAR0.00 QAR112,25QAR112,257.00
($294) QAR0.00 QAR122,01QAR122,019.00
($287) QAR0.00 QAR14,642QAR14,642.00
($286) QAR0.00 QAR39,046QAR39,046.00
($294) QAR0.00 QAR14,642QAR14,642.00
($292) QAR0.00 QAR9,762.QAR9,762.00
($288) QAR0.00 QAR9,762.QAR9,762.00
($396) QAR0.00 QAR257,26QAR257,264.00
($504) QAR0.00 QAR448,19QAR448,194.75
($412) QAR0.00 QAR38,821QAR38,821.00
($410) QAR0.00 QAR49,913QAR49,913.00
($400) QAR0.00 QAR22,183QAR22,183.00
($414) QAR0.00 QAR98,817QAR98,817.00
($408) QAR0.00 QAR24,230QAR24,230.00
($406) QAR0.00 QAR60,574QAR60,574.75
($404) QAR0.00 QAR18,172QAR18,172.00
($402) QAR0.00 QAR18,172QAR18,172.00
($389) QAR0.00 QAR117,31QAR117,312.00
($513) QAR0.00 QAR260,08QAR260,083.75
($311) QAR0.00 QAR35,094QAR35,094.00
($203) QAR0.00 QAR10,528QAR10,528.00
($231) QAR0.00 QAR5,966.QAR5,966.00
($231) QAR0.00 QAR10,528QAR10,528.00
($231) QAR0.00 QAR4,211.QAR4,211.00
($231) QAR0.00 QAR1,755.QAR1,755.00
($231) QAR0.00 QAR2,106.QAR2,106.00
($560) QAR0.00 QAR95,374QAR95,374.00
($219) QAR0.00 QAR8,398.QAR8,398.00
($219) QAR0.00 QAR1,527.QAR1,527.00
($245) QAR0.00 QAR763.00QAR763.00
($245) QAR0.00 QAR15,269QAR15,269.00
($218) QAR0.00 QAR19,086QAR19,086.00
($218) QAR0.00 QAR17,559QAR17,559.00
($226) QAR0.00 QAR2,290.QAR2,290.00
($218) QAR0.00 QAR2,290.QAR2,290.00
($223) QAR0.00 QAR1,527.QAR1,527.00
($217) QAR0.00 QAR6,108.QAR6,108.00
($223) QAR0.00 QAR1,527.QAR1,527.00
($421) QAR0.00 QAR19,030QAR19,030.00
($478) QAR0.00 QAR129,61QAR129,615.75
($402) QAR0.00 QAR10,045QAR10,045.00
($397) QAR0.00 QAR12,913QAR12,913.75
($373) QAR0.00 QAR5,740.QAR5,740.00
($402) QAR0.00 QAR29,645QAR29,645.00
($392) QAR0.00 QAR7,269.QAR7,269.00
($388) QAR0.00 QAR18,172QAR18,172.00
($383) QAR0.00 QAR5,452.QAR5,452.00
($378) QAR0.00 QAR5,452.QAR5,452.00
($369) QAR0.00 QAR34,927QAR34,927.00
($504) QAR0.00 QAR549,62QAR549,629.00
($303) QAR0.00 QAR105,68QAR105,683.00
($157) QAR0.00 QAR31,705QAR31,705.00
($224) QAR0.00 QAR17,966QAR17,966.00
($224) QAR0.00 QAR31,705QAR31,705.00
($224) QAR0.00 QAR12,682QAR12,682.00
($224) QAR0.00 QAR5,284.QAR5,284.00
($224) QAR0.00 QAR6,341.QAR6,341.00
($527) QAR0.00 QAR225,00QAR225,001.00
($208) QAR0.00 QAR18,446QAR18,446.00
($220) QAR0.00 QAR3,354.QAR3,354.00
($220) QAR0.00 QAR1,676.QAR1,676.00
($219) QAR0.00 QAR33,539QAR33,539.00
($219) QAR0.00 QAR38,570QAR38,570.00
($218) QAR0.00 QAR41,923QAR41,923.00
($218) QAR0.00 QAR5,031.QAR5,031.00
($217) QAR0.00 QAR3,354.QAR3,354.00
($212) QAR0.00 QAR5,031.QAR5,031.00
($217) QAR0.00 QAR3,354.QAR3,354.00
($216) QAR0.00 QAR13,416QAR13,416.00
($403) QAR0.00 QAR57,307QAR57,307.00
($467) QAR0.00 QAR218,94QAR218,945.00
($382) QAR0.00 QAR28,630QAR28,630.00
($380) QAR0.00 QAR36,810QAR36,810.50
($370) QAR0.00 QAR16,360QAR16,360.00
($384) QAR0.00 QAR39,527QAR39,527.00
($378) QAR0.00 QAR9,691.QAR9,691.50
($376) QAR0.00 QAR24,230QAR24,230.00
($374) QAR0.00 QAR7,269.QAR7,269.00
($372) QAR0.00 QAR7,269.QAR7,269.00
($360) QAR0.00 QAR49,158QAR49,158.00
($435) QAR0.00 QAR638,95QAR638,958.75
($206) QAR0.00 QAR135,68QAR135,686.75
($112) QAR0.00 QAR40,705QAR40,705.75
($143) QAR0.00 QAR23,067QAR23,067.00
($142) QAR0.00 QAR40,706QAR40,706.00
($143) QAR0.00 QAR16,283QAR16,283.00
($142) QAR0.00 QAR6,784.QAR6,784.00
($141) QAR0.00 QAR8,141.QAR8,141.00
($454) QAR0.00 QAR271,84QAR271,846.00
($136) QAR0.00 QAR21,810QAR21,810.00
($134) QAR0.00 QAR3,965.QAR3,965.00
($133) QAR0.00 QAR1,983.QAR1,983.00
($132) QAR0.00 QAR39,654QAR39,654.00
($130) QAR0.00 QAR45,602QAR45,602.00
($129) QAR0.00 QAR49,567QAR49,567.00
($178) QAR0.00 QAR5,948.QAR5,948.00
($175) QAR0.00 QAR5,948.QAR5,948.00
($179) QAR0.00 QAR3,965.QAR3,965.00
($175) QAR0.00 QAR15,862QAR15,862.00
($181) QAR0.00 QAR3,965.QAR3,965.00
($356) QAR0.00 QAR73,577QAR73,577.00
($431) QAR0.00 QAR231,42QAR231,426.00
($368) QAR0.00 QAR27,296QAR27,296.00
($365) QAR0.00 QAR35,094QAR35,094.00
($350) QAR0.00 QAR15,598QAR15,598.00
($368) QAR0.00 QAR44,468QAR44,468.00
($363) QAR0.00 QAR10,903QAR10,903.00
($360) QAR0.00 QAR27,259QAR27,259.00
($357) QAR0.00 QAR8,177.QAR8,177.00
($354) QAR0.00 QAR8,178.QAR8,178.00
($341) QAR0.00 QAR54,453QAR54,453.00
($420) QAR0.00 QAR834,89QAR834,898.75
($200) QAR0.00 QAR164,48QAR164,486.00
($97) QAR0.00 QAR49,346QAR49,346.00
($145) QAR0.00 QAR27,963QAR27,963.00
($144) QAR0.00 QAR49,346QAR49,346.00
($142) QAR0.00 QAR8,224.QAR8,224.00
($145) QAR0.00 QAR19,738QAR19,738.00
($144) QAR0.00 QAR9,869.QAR9,869.00
($427) QAR0.00 QAR318,03QAR318,035.75
($112) QAR0.00 QAR25,173QAR25,173.00
($116) QAR0.00 QAR4,577.QAR4,577.00
($115) QAR0.00 QAR2,288.QAR2,288.00
($114) QAR0.00 QAR45,769QAR45,769.00
($118) QAR0.00 QAR52,633QAR52,633.75
($117) QAR0.00 QAR57,210QAR57,210.00
($127) QAR0.00 QAR6,865.QAR6,865.00
($127) QAR0.00 QAR6,865.QAR6,865.00
($131) QAR0.00 QAR4,577.QAR4,577.00
($127) QAR0.00 QAR18,308QAR18,308.00
($119) QAR0.00 QAR4,577.QAR4,577.00
($337) QAR0.00 QAR89,193QAR89,193.00
($420) QAR0.00 QAR352,37QAR352,377.00
($350) QAR0.00 QAR34,478QAR34,478.00
($348) QAR0.00 QAR44,329QAR44,329.00
($338) QAR0.00 QAR19,702QAR19,702.00
($352) QAR0.00 QAR74,113QAR74,113.00
($346) QAR0.00 QAR18,172QAR18,172.00
($345) QAR0.00 QAR45,431QAR45,431.00
($344) QAR0.00 QAR13,629QAR13,629.00
($342) QAR0.00 QAR13,629QAR13,629.00
($332) QAR0.00 QAR88,894QAR88,894.00
($404) QAR0.00 QAR2,576,QAR2,576,319.75
($171) QAR0.00 QAR424,07QAR424,073.00
($82) QAR0.00 QAR127,22QAR127,222.00
($151) QAR0.00 QAR72,093QAR72,093.00
($149) QAR0.00 QAR127,22QAR127,221.00
($147) QAR0.00 QAR50,889QAR50,889.00
($144) QAR0.00 QAR21,204QAR21,204.00
($142) QAR0.00 QAR25,444QAR25,444.00
($382) QAR0.00 QAR946,49QAR946,497.75
($137) QAR0.00 QAR78,820QAR78,820.00
($135) QAR0.00 QAR14,331QAR14,331.00
($133) QAR0.00 QAR7,165.QAR7,165.00
($131) QAR0.00 QAR143,30QAR143,309.00
($129) QAR0.00 QAR164,80QAR164,804.75
($150) QAR0.00 QAR179,13QAR179,136.00
($128) QAR0.00 QAR21,496QAR21,496.00
($134) QAR0.00 QAR21,496QAR21,496.00
($132) QAR0.00 QAR14,331QAR14,331.00
($130) QAR0.00 QAR57,324QAR57,324.00
($135) QAR0.00 QAR14,331QAR14,331.00
($302) QAR0.00 QAR229,95QAR229,954.00
($404) QAR0.00 QAR1,205,QAR1,205,749.00
($327) QAR0.00 QAR103,36QAR103,361.00
($325) QAR0.00 QAR132,89QAR132,892.00
($315) QAR0.00 QAR59,063QAR59,063.00
($329) QAR0.00 QAR266,80QAR266,806.00
($323) QAR0.00 QAR65,420QAR65,420.00
($321) QAR0.00 QAR163,55QAR163,551.00
($319) QAR0.00 QAR49,066QAR49,066.00
($317) QAR0.00 QAR49,065QAR49,065.00
($321) QAR0.00 QAR316,52QAR316,525.00
($447) QAR0.00 QAR751,45QAR774,318.55
($329) QAR0.00 QAR0.00 QAR0.00
$219 QAR0.00 QAR0.00 QAR0.00
$269 QAR0.00 QAR0.00 QAR0.00
($268) QAR0.00 QAR0.00 QAR0.00
($232) QAR0.00 QAR220,56QAR220,564.10
($200) QAR0.00 QAR66,169QAR66,169.25
($200) QAR0.00 QAR37,495QAR37,495.75
($199) QAR0.00 QAR66,169QAR66,169.00
($197) QAR0.00 QAR26,468QAR26,468.10
($195) QAR0.00 QAR11,028QAR11,028.00
($194) QAR0.00 QAR13,234QAR13,234.00
($447) QAR0.00 QAR339,97QAR352,781.10
($188) QAR0.00 QAR24,712QAR24,712.60
($187) QAR0.00 QAR4,494.QAR4,494.00
($186) QAR0.00 QAR2,247.QAR2,247.00
($184) QAR0.00 QAR44,935QAR44,935.00
($182) QAR0.00 QAR51,675QAR51,675.00
($184) QAR0.00 QAR56,169QAR56,169.00
($195) QAR0.00 QAR6,740.QAR6,740.50
($191) QAR0.00 QAR6,740.QAR6,740.00
($195) QAR0.00 QAR4,494.QAR4,494.00
($197) QAR0.00 QAR4,494.QAR4,494.00
($194) QAR0.00 QAR17,974QAR17,974.00
($356) QAR0.00 QAR115,29QAR128,106.00
($425) QAR0.00 QAR190,92QAR200,973.35
($361) QAR0.00 QAR26,802QAR28,213.25
($359) QAR0.00 QAR34,460QAR36,274.00
($349) QAR0.00 QAR15,315QAR16,122.00
($361) QAR0.00 QAR32,856QAR34,586.00
($357) QAR0.00 QAR8,056.QAR8,480.00
($355) QAR0.00 QAR20,141QAR21,201.10
($353) QAR0.00 QAR6,042.QAR6,360.00
($351) QAR0.00 QAR6,042.QAR6,360.00
($339) QAR0.00 QAR41,208QAR43,377.00
($409) QAR0.00 QAR1,215,QAR1,226,714.00
($521) QAR0.00 QAR0.00 QAR0.00
($275) QAR0.00 QAR0.00 QAR0.00
($415) QAR0.00 QAR0.00 QAR0.00
($313) QAR0.00 QAR422,00QAR422,007.00
($258) QAR0.00 QAR126,60QAR126,602.00
($255) QAR0.00 QAR71,741QAR71,741.00
($252) QAR0.00 QAR126,60QAR126,602.00
($249) QAR0.00 QAR50,642QAR50,642.00
($246) QAR0.00 QAR21,100QAR21,100.00
($244) QAR0.00 QAR25,320QAR25,320.00
($420) QAR0.00 QAR623,63QAR635,299.50
($252) QAR0.00 QAR37,815QAR37,815.00
($250) QAR0.00 QAR6,875.QAR6,875.00
($248) QAR0.00 QAR3,438.QAR3,438.00
($246) QAR0.00 QAR68,755QAR68,755.00
($243) QAR0.00 QAR79,066QAR79,066.50
($240) QAR0.00 QAR85,943QAR85,943.00
($239) QAR0.00 QAR10,313QAR10,313.00
($234) QAR0.00 QAR10,313QAR10,313.00
($236) QAR0.00 QAR6,876.QAR6,876.00
($232) QAR0.00 QAR27,502QAR27,502.00
($236) QAR0.00 QAR6,876.QAR6,876.00
($334) QAR0.00 QAR279,86QAR291,527.00
($366) QAR0.00 QAR169,40QAR169,407.50
($338) QAR0.00 QAR55,980QAR55,980.00
($324) QAR0.00 QAR71,974QAR71,974.50
($309) QAR0.00 QAR31,989QAR31,989.00
($288) QAR0.00 QAR9,464.QAR9,464.00
($184) QAR0.00 QAR17,256QAR17,359,259.65
($362) QAR0.00 QAR2,643,QAR2,649,074.50
($307) QAR0.00 QAR0.00 QAR0.00
$239 QAR0.00 QAR0.00 QAR0.00
($248) QAR0.00 QAR0.00 QAR0.00
($278) QAR0.00 QAR0.00 QAR0.00
($151) QAR0.00 QAR186,92QAR186,920.00
($100) QAR0.00 QAR56,076QAR56,076.25
($133) QAR0.00 QAR31,776QAR31,776.75
($132) QAR0.00 QAR56,076QAR56,076.00
($130) QAR0.00 QAR22,430QAR22,430.00
($129) QAR0.00 QAR9,346.QAR9,346.00
($128) QAR0.00 QAR11,215QAR11,215.00
($373) QAR0.00 QAR386,47QAR386,470.00
($144) QAR0.00 QAR29,869QAR29,869.25
($143) QAR0.00 QAR5,430.QAR5,430.75
($142) QAR0.00 QAR2,715.QAR2,715.00
($141) QAR0.00 QAR54,306QAR54,306.00
($139) QAR0.00 QAR62,453QAR62,453.00
($137) QAR0.00 QAR67,883QAR67,883.00
($136) QAR0.00 QAR5,431.QAR5,431.00
($132) QAR0.00 QAR8,146.QAR8,146.00
($138) QAR0.00 QAR8,145.QAR8,145.00
($137) QAR0.00 QAR5,431.QAR5,431.00
($132) QAR0.00 QAR21,723QAR21,723.00
($295) QAR0.00 QAR114,93QAR114,937.00
($396) QAR0.00 QAR252,25QAR252,258.25
($276) QAR0.00 QAR28,715QAR28,715.00
($274) QAR0.00 QAR36,918QAR36,918.25
($267) QAR0.00 QAR16,408QAR16,408.00
($337) QAR0.00 QAR49,409QAR49,409.00
($333) QAR0.00 QAR12,115QAR12,115.00
($331) QAR0.00 QAR30,287QAR30,287.00
($329) QAR0.00 QAR9,086.QAR9,086.00
($327) QAR0.00 QAR9,086.QAR9,086.00
($313) QAR0.00 QAR60,234QAR60,234.00
($409) QAR0.00 QAR152,17QAR152,171.00
($108) QAR0.00 QAR48,424QAR48,424.00
($21) QAR0.00 QAR14,527QAR14,527.00
($84) QAR0.00 QAR8,233.QAR8,233.00
($88) QAR0.00 QAR14,527QAR14,527.00
($87) QAR0.00 QAR2,421.QAR2,421.00
($89) QAR0.00 QAR5,811.QAR5,811.00
($92) QAR0.00 QAR2,905.QAR2,905.00
($373) QAR0.00 QAR61,998QAR61,998.00
($70) QAR0.00 QAR3,544.QAR3,544.00
($68) QAR0.00 QAR644.00QAR644.00
($69) QAR0.00 QAR322.00QAR322.00
($67) QAR0.00 QAR6,445.QAR6,445.00
($87) QAR0.00 QAR7,411.QAR7,411.00
($88) QAR0.00 QAR8,056.QAR8,056.00
($120) QAR0.00 QAR967.00QAR967.00
($127) QAR0.00 QAR644.00QAR644.00
($129) QAR0.00 QAR967.00QAR967.00
($128) QAR0.00 QAR644.00QAR644.00
($120) QAR0.00 QAR2,578.QAR2,578.00
($294) QAR0.00 QAR29,776QAR29,776.00
($409) QAR0.00 QAR41,749QAR41,749.00
($335) QAR0.00 QAR2,867.QAR2,867.00
($333) QAR0.00 QAR3,686.QAR3,686.00
($327) QAR0.00 QAR1,638.QAR1,638.00
($337) QAR0.00 QAR9,882.QAR9,882.00
($332) QAR0.00 QAR2,424.QAR2,424.00
($331) QAR0.00 QAR6,057.QAR6,057.00
($329) QAR0.00 QAR1,817.QAR1,817.00
($330) QAR0.00 QAR1,817.QAR1,817.00
($325) QAR0.00 QAR11,561QAR11,561.00
($399) QAR0.00 QAR306,92QAR306,922.25
($119) QAR0.00 QAR52,808QAR52,808.25
($20) QAR0.00 QAR15,842QAR15,842.00
($100) QAR0.00 QAR8,977.QAR8,977.25
($100) QAR0.00 QAR15,842QAR15,842.00
($100) QAR0.00 QAR6,338.QAR6,338.00
($100) QAR0.00 QAR2,640.QAR2,640.00
($100) QAR0.00 QAR3,169.QAR3,169.00
($371) QAR0.00 QAR128,05QAR128,051.00
($91) QAR0.00 QAR10,514QAR10,514.00
($90) QAR0.00 QAR1,912.QAR1,912.00
($90) QAR0.00 QAR955.00QAR955.00
($90) QAR0.00 QAR19,116QAR19,116.00
($90) QAR0.00 QAR21,983QAR21,983.00
($89) QAR0.00 QAR23,895QAR23,895.00
($94) QAR0.00 QAR2,867.QAR2,867.00
($94) QAR0.00 QAR1,912.QAR1,912.00
($90) QAR0.00 QAR2,867.QAR2,867.00
($94) QAR0.00 QAR1,912.QAR1,912.00
($92) QAR0.00 QAR7,646.QAR7,646.00
($293) QAR0.00 QAR32,472QAR32,472.00
($399) QAR0.00 QAR126,06QAR126,063.00
($326) QAR0.00 QAR14,334QAR14,334.00
($324) QAR0.00 QAR18,430QAR18,430.00
($314) QAR0.00 QAR8,191.QAR8,191.00
($328) QAR0.00 QAR24,704QAR24,704.00
($324) QAR0.00 QAR6,057.QAR6,057.00
($322) QAR0.00 QAR15,144QAR15,144.00
($318) QAR0.00 QAR4,543.QAR4,543.00
($320) QAR0.00 QAR4,543.QAR4,543.00
($316) QAR0.00 QAR30,117QAR30,117.00
($368) QAR0.00 QAR1,021,QAR1,026,339.00
($120) QAR0.00 QAR185,72QAR185,725.00
($105) QAR0.00 QAR55,717QAR55,717.00
($106) QAR0.00 QAR31,573QAR31,573.00
($105) QAR0.00 QAR55,718QAR55,718.00
($104) QAR0.00 QAR22,287QAR22,287.00
($102) QAR0.00 QAR9,286.QAR9,286.00
($101) QAR0.00 QAR11,144QAR11,144.00
($363) QAR0.00 QAR401,30QAR401,302.00
($90) QAR0.00 QAR31,581QAR31,581.00
($89) QAR0.00 QAR5,742.QAR5,742.00
($88) QAR0.00 QAR2,871.QAR2,871.00
($88) QAR0.00 QAR57,420QAR57,420.00
($89) QAR0.00 QAR66,033QAR66,033.00
($90) QAR0.00 QAR71,775QAR71,775.00
($90) QAR0.00 QAR8,613.QAR8,613.00
($86) QAR0.00 QAR8,613.QAR8,613.00
($90) QAR0.00 QAR5,742.QAR5,742.00
($86) QAR0.00 QAR22,968QAR22,968.00
($89) QAR0.00 QAR5,742.QAR5,742.00
($285) QAR0.00 QAR114,20QAR114,202.00
($375) QAR0.00 QAR434,18QAR439,312.00
($321) QAR0.00 QAR34,087QAR35,882.00
($319) QAR0.00 QAR43,826QAR46,133.00
($309) QAR0.00 QAR19,478QAR20,504.00
($317) QAR0.00 QAR98,817QAR98,817.00
($311) QAR0.00 QAR24,230QAR24,230.00
($309) QAR0.00 QAR60,575QAR60,575.00
($307) QAR0.00 QAR18,172QAR18,172.00
($305) QAR0.00 QAR18,172QAR18,172.00
($289) QAR0.00 QAR116,82QAR116,827.00
($349) QAR0.00 QAR337,99QAR337,994.00
($98) QAR0.00 QAR64,565QAR64,565.00
$128 QAR0.00 QAR19,370QAR19,370.00
($83) QAR0.00 QAR10,976QAR10,976.00
($83) QAR0.00 QAR19,370QAR19,370.00
($82) QAR0.00 QAR3,228.QAR3,228.00
($83) QAR0.00 QAR7,747.QAR7,747.00
($82) QAR0.00 QAR3,874.QAR3,874.00
($334) QAR0.00 QAR151,57QAR151,572.00
($22) QAR0.00 QAR12,306QAR12,306.00
($24) QAR0.00 QAR2,238.QAR2,238.00
($24) QAR0.00 QAR1,119.QAR1,119.00
($24) QAR0.00 QAR22,374QAR22,374.00
($59) QAR0.00 QAR25,730QAR25,730.00
($59) QAR0.00 QAR27,968QAR27,968.00
($59) QAR0.00 QAR3,356.QAR3,356.00
($58) QAR0.00 QAR2,237.QAR2,237.00
($60) QAR0.00 QAR2,237.QAR2,237.00
($55) QAR0.00 QAR3,356.QAR3,356.00
($56) QAR0.00 QAR8,950.QAR8,950.00
($261) QAR0.00 QAR39,701QAR39,701.00
($372) QAR0.00 QAR121,85QAR121,857.00
($307) QAR0.00 QAR12,947QAR12,947.00
($305) QAR0.00 QAR16,646QAR16,646.00
($295) QAR0.00 QAR7,398.QAR7,398.00
($303) QAR0.00 QAR6,058.QAR6,058.00
($307) QAR0.00 QAR24,704QAR24,704.00
($301) QAR0.00 QAR15,144QAR15,144.00
($299) QAR0.00 QAR4,543.QAR4,543.00
($297) QAR0.00 QAR4,543.QAR4,543.00
($292) QAR0.00 QAR29,874QAR29,874.00
($184) QAR0.00 QAR14,612QAR14,710,185.15
($294) QAR0.00 QAR563,60QAR563,607.50
($65) QAR0.00 QAR48,609QAR48,609.00
($64) QAR0.00 QAR24,304QAR24,304.75
($225) QAR0.00 QAR48,609QAR48,609.50
($215) QAR0.00 QAR141,77QAR141,775.00
($243) QAR0.00 QAR300,30QAR300,309.25
($57) QAR0.00 QAR504,42QAR504,428.75
($50) QAR0.00 QAR60,532QAR60,532.00
($46) QAR0.00 QAR176,55QAR176,550.00
($73) QAR0.00 QAR60,532QAR60,532.00
($69) QAR0.00 QAR30,264QAR30,264.75
($48) QAR0.00 QAR176,55QAR176,550.00
($763) QAR0.00 QAR425,06QAR425,061.00
($76) QAR0.00 QAR51,007QAR51,007.00
($78) QAR0.00 QAR51,007QAR51,007.00
($622) QAR0.00 QAR25,505QAR25,505.00
($60) QAR0.00 QAR148,77QAR148,771.00
($50) QAR0.00 QAR148,77QAR148,771.00
($47) QAR0.00 QAR516,18QAR516,187.00
($72) QAR0.00 QAR61,942QAR61,942.00
($70) QAR0.00 QAR61,942QAR61,942.00
($66) QAR0.00 QAR30,971QAR30,971.00
($50) QAR0.00 QAR180,66QAR180,666.00
($40) QAR0.00 QAR180,66QAR180,666.00
($28) QAR0.00 QAR492,67QAR492,671.25
($58) QAR0.00 QAR59,121QAR59,121.00
($63) QAR0.00 QAR59,121QAR59,121.00
($55) QAR0.00 QAR29,559QAR29,559.25
($35) QAR0.00 QAR172,43QAR172,435.00
($23) QAR0.00 QAR172,43QAR172,435.00
($15) QAR0.00 QAR413,30QAR413,302.00
($43) QAR0.00 QAR49,596QAR49,596.00
($35) QAR0.00 QAR49,596QAR49,596.00
($22) QAR0.00 QAR144,65QAR144,656.00
($58) QAR0.00 QAR24,798QAR24,798.00
($13) QAR0.00 QAR144,65QAR144,656.00
$8 QAR0.00 QAR612,01QAR612,017.00
($32) QAR0.00 QAR73,442QAR73,442.00
($21) QAR0.00 QAR73,442QAR73,442.00
($49) QAR0.00 QAR36,721QAR36,721.00
($9) QAR0.00 QAR214,20QAR214,206.00
$7 QAR0.00 QAR214,20QAR214,206.00
($75) QAR0.00 QAR603,78QAR603,786.00
($5) QAR0.00 QAR72,454QAR72,454.00
($15) QAR0.00 QAR72,454QAR72,454.00
($28) QAR0.00 QAR211,32QAR211,325.00
($124) QAR0.00 QAR36,228QAR36,228.00
($26) QAR0.00 QAR211,32QAR211,325.00
($28) QAR0.00 QAR603,78QAR603,786.00
($6) QAR0.00 QAR72,455QAR72,455.00
$3 QAR0.00 QAR72,454QAR72,454.00
($30) QAR0.00 QAR211,32QAR211,325.00
($90) QAR0.00 QAR36,227QAR36,227.00
($24) QAR0.00 QAR211,32QAR211,325.00
$27 QAR0.00 QAR329,81QAR329,819.00
($11) QAR0.00 QAR39,578QAR39,578.00
($44) QAR0.00 QAR39,578QAR39,578.00
($44) QAR0.00 QAR19,789QAR19,789.00
$18 QAR0.00 QAR115,43QAR115,437.00
$23 QAR0.00 QAR115,43QAR115,437.00
($152) QAR0.00 QAR357,45QAR357,451.00
($199) QAR0.00 QAR42,894QAR42,894.00
($189) QAR0.00 QAR42,894QAR42,894.00
$31 QAR0.00 QAR125,10QAR125,108.00
($70) QAR0.00 QAR21,447QAR21,447.00
$10 QAR0.00 QAR125,10QAR125,108.00
$60 QAR0.00 QAR373,32QAR373,324.00
$23 QAR0.00 QAR44,799QAR44,799.00
$23 QAR0.00 QAR44,797QAR44,797.00
$16 QAR0.00 QAR22,400QAR22,400.00
$89 QAR0.00 QAR130,66QAR130,664.00
$16 QAR0.00 QAR130,66QAR130,664.00
$126 QAR0.00 QAR242,22QAR242,220.00
$29 QAR0.00 QAR29,067QAR29,067.00
$38 QAR0.00 QAR29,066QAR29,066.00
$35 QAR0.00 QAR14,533QAR14,533.00
$67 QAR0.00 QAR84,777QAR84,777.00
$77 QAR0.00 QAR84,777QAR84,777.00
($38) QAR0.00 QAR545,81QAR545,812.15
$10 QAR0.00 QAR33,162QAR33,162.90
$10 QAR0.00 QAR8,291.QAR8,291.25
$9 QAR0.00 QAR82,908QAR82,908.00
$4 QAR0.00 QAR124,36QAR124,362.00
$5 QAR0.00 QAR82,908QAR82,908.00
($47) QAR0.00 QAR20,727QAR20,727.00
($41) QAR0.00 QAR33,163QAR33,163.00
($52) QAR0.00 QAR12,436QAR12,436.00
($50) QAR0.00 QAR8,291.QAR8,291.00
($49) QAR0.00 QAR8,291.QAR8,291.00
($32) QAR0.00 QAR131,27QAR131,272.00
($337) QAR0.00 QAR130,77QAR130,773.25
($189) QAR0.00 QAR38,460QAR38,460.25
($161) QAR0.00 QAR11,538QAR11,538.00
($161) QAR0.00 QAR6,538.QAR6,538.00
($161) QAR0.00 QAR11,538QAR11,538.25
($160) QAR0.00 QAR4,615.QAR4,615.00
($160) QAR0.00 QAR1,923.QAR1,923.00
($160) QAR0.00 QAR2,308.QAR2,308.00
($340) QAR0.00 QAR71,439QAR71,439.00
($164) QAR0.00 QAR5,257.QAR5,257.00
($163) QAR0.00 QAR956.00QAR956.00
($163) QAR0.00 QAR478.00QAR478.00
($162) QAR0.00 QAR9,557.QAR9,557.00
($161) QAR0.00 QAR11,947QAR11,947.00
($162) QAR0.00 QAR10,992QAR10,992.00
($183) QAR0.00 QAR1,434.QAR1,434.00
($177) QAR0.00 QAR1,434.QAR1,434.00
($183) QAR0.00 QAR956.00QAR956.00
($177) QAR0.00 QAR3,823.QAR3,823.00
($183) QAR0.00 QAR956.00QAR956.00
($266) QAR0.00 QAR23,649QAR23,649.00
($337) QAR0.00 QAR20,874QAR20,874.00
($268) QAR0.00 QAR1,433.QAR1,433.00
($266) QAR0.00 QAR1,842.QAR1,842.00
($264) QAR0.00 QAR819.00QAR819.00
($266) QAR0.00 QAR1,211.QAR1,211.00
($266) QAR0.00 QAR3,029.QAR3,029.00
($272) QAR0.00 QAR4,941.QAR4,941.00
($266) QAR0.00 QAR909.00QAR909.00
($266) QAR0.00 QAR909.00QAR909.00
($265) QAR0.00 QAR5,781.QAR5,781.00
($374) QAR0.00 QAR206,23QAR227,161.25
$21 QAR0.00 QAR85,090QAR85,090.75
$24 QAR0.00 QAR25,528QAR25,528.00
$19 QAR0.00 QAR14,465QAR14,465.00
$20 QAR0.00 QAR25,527QAR25,527.00
$21 QAR0.00 QAR10,211QAR10,211.00
$20 QAR0.00 QAR4,255.QAR4,255.00
$18 QAR0.00 QAR5,104.QAR5,104.75
($378) QAR0.00 QAR95,112QAR116,041.75
$18 QAR0.00 QAR7,009.QAR7,009.00
$18 QAR0.00 QAR1,274.QAR1,274.00
$15 QAR0.00 QAR637.00QAR637.00
$14 QAR0.00 QAR12,744QAR12,744.00
$13 QAR0.00 QAR14,655QAR14,655.75
$14 QAR0.00 QAR15,930QAR15,930.00
($17) QAR0.00 QAR1,912.QAR1,912.00
($15) QAR0.00 QAR1,274.QAR1,274.00
($17) QAR0.00 QAR1,274.QAR1,274.00
($11) QAR0.00 QAR1,912.QAR1,912.00
($15) QAR0.00 QAR5,098.QAR5,098.00
($299) QAR0.00 QAR31,393QAR52,322.00
($374) QAR0.00 QAR26,028QAR26,028.75
($302) QAR0.00 QAR8,600.QAR8,600.00
($299) QAR0.00 QAR11,058QAR11,058.00
($297) QAR0.00 QAR4,914.QAR4,914.75
($296) QAR0.00 QAR1,456.QAR1,456.00
($238) QAR0.00 QAR837,42QAR899,259.00
($206) QAR0.00 QAR167,59QAR167,590.00
($173) QAR0.00 QAR50,277QAR50,277.00
($172) QAR0.00 QAR28,490QAR28,490.00
($170) QAR0.00 QAR50,277QAR50,277.00
($169) QAR0.00 QAR20,111QAR20,111.00
($167) QAR0.00 QAR8,380.QAR8,380.00
($165) QAR0.00 QAR10,055QAR10,055.00
($354) QAR0.00 QAR312,39QAR374,221.00
($94) QAR0.00 QAR29,829QAR29,829.00
($93) QAR0.00 QAR5,423.QAR5,423.00
($92) QAR0.00 QAR2,712.QAR2,712.00
($102) QAR0.00 QAR54,234QAR54,234.00
($101) QAR0.00 QAR62,369QAR62,369.00
($100) QAR0.00 QAR67,793QAR67,793.00
($113) QAR0.00 QAR8,135.QAR8,135.00
($109) QAR0.00 QAR8,135.QAR8,135.00
($113) QAR0.00 QAR5,423.QAR5,423.00
($109) QAR0.00 QAR21,694QAR21,694.00
($115) QAR0.00 QAR5,423.QAR5,423.00
($278) QAR0.00 QAR41,220QAR103,051.00
($241) QAR0.00 QAR0.00 QAR0.00
($98) QAR0.00 QAR0.00 QAR0.00
($75) QAR0.00 QAR0.00 QAR0.00
($76) QAR0.00 QAR0.00 QAR0.00
($74) QAR0.00 QAR0.00 QAR0.00
($73) QAR0.00 QAR0.00 QAR0.00
($72) QAR0.00 QAR0.00 QAR0.00
($70) QAR0.00 QAR0.00 QAR0.00
($241) QAR0.00 QAR0.00 QAR0.00
($70) QAR0.00 QAR0.00 QAR0.00
($70) QAR0.00 QAR0.00 QAR0.00
($70) QAR0.00 QAR0.00 QAR0.00
($70) QAR0.00 QAR0.00 QAR0.00
($70) QAR0.00 QAR0.00 QAR0.00
($68) QAR0.00 QAR0.00 QAR0.00
($67) QAR0.00 QAR0.00 QAR0.00
($69) QAR0.00 QAR0.00 QAR0.00
($67) QAR0.00 QAR0.00 QAR0.00
($67) QAR0.00 QAR0.00 QAR0.00
($68) QAR0.00 QAR0.00 QAR0.00
($181) QAR0.00 QAR0.00 QAR0.00
($149) QAR0.00 QAR357,44QAR357,448.00
($110) QAR0.00 QAR41,615QAR41,615.00
($108) QAR0.00 QAR53,506QAR53,506.00
($98) QAR0.00 QAR23,780QAR23,780.00
($113) QAR0.00 QAR69,172QAR69,172.00
($109) QAR0.00 QAR16,961QAR16,961.00
($107) QAR0.00 QAR42,402QAR42,402.00
($105) QAR0.00 QAR12,721QAR12,721.00
($103) QAR0.00 QAR12,721QAR12,721.00
($104) QAR0.00 QAR84,570QAR84,570.00
($139) QAR0.00 QAR1,228,QAR1,228,680.00
($193) QAR0.00 QAR187,91QAR187,916.75
($161) QAR0.00 QAR56,375QAR56,375.00
($160) QAR0.00 QAR31,945QAR31,945.75
($158) QAR0.00 QAR56,375QAR56,375.00
($157) QAR0.00 QAR22,550QAR22,550.00
($155) QAR0.00 QAR9,396.QAR9,396.00
($153) QAR0.00 QAR11,275QAR11,275.00
($257) QAR0.00 QAR482,29QAR482,299.50
($92) QAR0.00 QAR40,342QAR40,342.00
($92) QAR0.00 QAR7,333.QAR7,333.75
($90) QAR0.00 QAR3,668.QAR3,668.00
($89) QAR0.00 QAR73,349QAR73,349.75
($87) QAR0.00 QAR84,352QAR84,352.00
($86) QAR0.00 QAR91,688QAR91,688.00
($101) QAR0.00 QAR11,003QAR11,003.00
($107) QAR0.00 QAR11,003QAR11,003.00
($106) QAR0.00 QAR7,335.QAR7,335.00
($100) QAR0.00 QAR29,340QAR29,340.00
($104) QAR0.00 QAR7,335.QAR7,335.00
($196) QAR0.00 QAR115,55QAR115,550.00
($194) QAR0.00 QAR0.00 QAR0.00
($92) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($194) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($62) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($63) QAR0.00 QAR0.00 QAR0.00
($62) QAR0.00 QAR0.00 QAR0.00
($143) QAR0.00 QAR0.00 QAR0.00
($111) QAR0.00 QAR558,46QAR558,463.75
($105) QAR0.00 QAR58,861QAR58,861.75
($103) QAR0.00 QAR75,681QAR75,681.00
($93) QAR0.00 QAR33,636QAR33,636.00
($107) QAR0.00 QAR113,64QAR113,640.00
($101) QAR0.00 QAR27,864QAR27,864.00
($99) QAR0.00 QAR69,661QAR69,661.00
($97) QAR0.00 QAR20,898QAR20,898.00
($95) QAR0.00 QAR20,898QAR20,898.00
($76) QAR0.00 QAR137,32QAR137,324.00
($320) QAR0.00 QAR441,97QAR457,173.00
($122) QAR0.00 QAR86,883QAR86,883.00
($106) QAR0.00 QAR26,065QAR26,065.00
($106) QAR0.00 QAR14,770QAR14,770.00
($106) QAR0.00 QAR26,065QAR26,065.00
($104) QAR0.00 QAR4,344.QAR4,344.00
($106) QAR0.00 QAR10,426QAR10,426.00
($104) QAR0.00 QAR5,213.QAR5,213.00
($280) QAR0.00 QAR164,93QAR164,933.00
$295 QAR0.00 QAR12,266QAR12,266.00
$296 QAR0.00 QAR2,230.QAR2,230.00
$296 QAR0.00 QAR1,115.QAR1,115.00
$297 QAR0.00 QAR22,302QAR22,302.00
$294 QAR0.00 QAR25,647QAR25,647.00
$280 QAR0.00 QAR27,877QAR27,877.00
$221 QAR0.00 QAR3,345.QAR3,345.00
$220 QAR0.00 QAR8,921.QAR8,921.00
$215 QAR0.00 QAR3,345.QAR3,345.00
($216) QAR0.00 QAR53,425QAR53,425.00
$235 QAR0.00 QAR2,230.QAR2,230.00
($40) QAR0.00 QAR2,230.QAR2,230.00
($320) QAR0.00 QAR190,15QAR205,357.00
($203) QAR0.00 QAR18,681QAR18,681.00
($201) QAR0.00 QAR24,018QAR24,018.00
($199) QAR0.00 QAR10,675QAR10,675.00
($272) QAR0.00 QAR40,021QAR44,468.00
($266) QAR0.00 QAR9,812.QAR10,903.00
($264) QAR0.00 QAR24,533QAR27,259.00
($260) QAR0.00 QAR7,360.QAR8,178.00
($250) QAR0.00 QAR47,697QAR52,997.00
($262) QAR0.00 QAR7,360.QAR8,178.00
($117) QAR0.00 QAR1,319,QAR1,319,865.00
($182) QAR0.00 QAR188,31QAR188,315.00
($150) QAR0.00 QAR56,494QAR56,494.00
($148) QAR0.00 QAR32,013QAR32,013.00
($146) QAR0.00 QAR56,495QAR56,495.00
($142) QAR0.00 QAR9,416.QAR9,416.00
($144) QAR0.00 QAR22,598QAR22,598.00
($140) QAR0.00 QAR11,299QAR11,299.00
($231) QAR0.00 QAR482,54QAR482,545.00
($105) QAR0.00 QAR40,343QAR40,343.00
($111) QAR0.00 QAR7,335.QAR7,335.00
($110) QAR0.00 QAR3,667.QAR3,667.00
($109) QAR0.00 QAR73,350QAR73,350.00
($108) QAR0.00 QAR84,352QAR84,352.00
($106) QAR0.00 QAR91,688QAR91,688.00
($115) QAR0.00 QAR11,002QAR11,002.00
($110) QAR0.00 QAR11,003QAR11,003.00
($114) QAR0.00 QAR7,335.QAR7,335.00
($109) QAR0.00 QAR29,340QAR29,340.00
($114) QAR0.00 QAR7,335.QAR7,335.00
($174) QAR0.00 QAR115,79QAR115,795.00
($184) QAR0.00 QAR0.00 QAR0.00
($83) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($63) QAR0.00 QAR0.00 QAR0.00
($59) QAR0.00 QAR0.00 QAR0.00
($61) QAR0.00 QAR0.00 QAR0.00
($56) QAR0.00 QAR0.00 QAR0.00
($184) QAR0.00 QAR0.00 QAR0.00
($60) QAR0.00 QAR0.00 QAR0.00
($60) QAR0.00 QAR0.00 QAR0.00
($60) QAR0.00 QAR0.00 QAR0.00
($60) QAR0.00 QAR0.00 QAR0.00
($60) QAR0.00 QAR0.00 QAR0.00
($57) QAR0.00 QAR0.00 QAR0.00
($58) QAR0.00 QAR0.00 QAR0.00
($58) QAR0.00 QAR0.00 QAR0.00
($58) QAR0.00 QAR0.00 QAR0.00
($58) QAR0.00 QAR0.00 QAR0.00
($58) QAR0.00 QAR0.00 QAR0.00
($135) QAR0.00 QAR0.00 QAR0.00
($91) QAR0.00 QAR649,00QAR649,005.00
($100) QAR0.00 QAR55,995QAR55,995.00
($98) QAR0.00 QAR71,995QAR71,995.00
($88) QAR0.00 QAR31,998QAR31,998.00
($102) QAR0.00 QAR143,28QAR143,285.00
($96) QAR0.00 QAR35,132QAR35,132.00
($94) QAR0.00 QAR87,833QAR87,833.00
($92) QAR0.00 QAR26,350QAR26,350.00
($90) QAR0.00 QAR26,350QAR26,350.00
($66) QAR0.00 QAR170,06QAR170,067.00
($114) QAR0.00 QAR1,350,QAR1,350,481.00
($125) QAR0.00 QAR183,73QAR183,732.00
($114) QAR0.00 QAR55,120QAR55,120.00
($112) QAR0.00 QAR31,233QAR31,233.00
($110) QAR0.00 QAR55,120QAR55,120.00
($108) QAR0.00 QAR22,048QAR22,048.00
($106) QAR0.00 QAR9,187.QAR9,187.00
($104) QAR0.00 QAR11,024QAR11,024.00
($198) QAR0.00 QAR463,79QAR463,797.00
($53) QAR0.00 QAR38,590QAR38,590.00
($59) QAR0.00 QAR7,016.QAR7,016.00
($58) QAR0.00 QAR3,508.QAR3,508.00
($57) QAR0.00 QAR70,164QAR70,164.00
($56) QAR0.00 QAR80,689QAR80,689.00
($54) QAR0.00 QAR87,705QAR87,705.00
($90) QAR0.00 QAR10,525QAR10,525.00
($89) QAR0.00 QAR7,016.QAR7,016.00
($87) QAR0.00 QAR10,525QAR10,525.00
($87) QAR0.00 QAR28,066QAR28,066.00
($91) QAR0.00 QAR7,016.QAR7,016.00
($146) QAR0.00 QAR112,97QAR112,977.00
($141) QAR0.00 QAR0.00 QAR0.00
($102) QAR0.00 QAR0.00 QAR0.00
($73) QAR0.00 QAR0.00 QAR0.00
($74) QAR0.00 QAR0.00 QAR0.00
($72) QAR0.00 QAR0.00 QAR0.00
($70) QAR0.00 QAR0.00 QAR0.00
($69) QAR0.00 QAR0.00 QAR0.00
($65) QAR0.00 QAR0.00 QAR0.00
($141) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($41) QAR0.00 QAR0.00 QAR0.00
($98) QAR0.00 QAR0.00 QAR0.00
($114) QAR0.00 QAR702,95QAR702,952.00
($115) QAR0.00 QAR57,429QAR57,429.00
($113) QAR0.00 QAR73,837QAR73,837.00
($103) QAR0.00 QAR32,817QAR32,817.00
($117) QAR0.00 QAR158,10QAR158,107.00
($111) QAR0.00 QAR38,768QAR38,768.00
($109) QAR0.00 QAR96,919QAR96,919.00
($107) QAR0.00 QAR29,076QAR29,076.00
($105) QAR0.00 QAR29,076QAR29,076.00
($85) QAR0.00 QAR186,92QAR186,923.00
($94) QAR0.00 QAR1,097,QAR1,097,252.00
($170) QAR0.00 QAR191,90QAR191,902.00
($133) QAR0.00 QAR57,571QAR57,571.00
($132) QAR0.00 QAR32,623QAR32,623.00
($130) QAR0.00 QAR57,571QAR57,571.00
($129) QAR0.00 QAR23,028QAR23,028.00
($127) QAR0.00 QAR9,595.QAR9,595.00
($126) QAR0.00 QAR11,514QAR11,514.00
($187) QAR0.00 QAR452,89QAR452,891.00
($11) QAR0.00 QAR36,838QAR36,838.00
($13) QAR0.00 QAR6,698.QAR6,698.00
($12) QAR0.00 QAR3,349.QAR3,349.00
($11) QAR0.00 QAR66,977QAR66,977.00
($10) QAR0.00 QAR77,025QAR77,025.00
($41) QAR0.00 QAR83,723QAR83,723.00
($40) QAR0.00 QAR10,047QAR10,047.00
($39) QAR0.00 QAR6,698.QAR6,698.00
($37) QAR0.00 QAR10,047QAR10,047.00
($35) QAR0.00 QAR26,791QAR26,791.00
($62) QAR0.00 QAR6,698.QAR6,698.00
($137) QAR0.00 QAR118,00QAR118,000.00
($130) QAR0.00 QAR0.00 QAR0.00
($89) QAR0.00 QAR0.00 QAR0.00
($57) QAR0.00 QAR0.00 QAR0.00
($59) QAR0.00 QAR0.00 QAR0.00
($59) QAR0.00 QAR0.00 QAR0.00
($58) QAR0.00 QAR0.00 QAR0.00
($56) QAR0.00 QAR0.00 QAR0.00
($55) QAR0.00 QAR0.00 QAR0.00
($130) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($38) QAR0.00 QAR0.00 QAR0.00
($88) QAR0.00 QAR0.00 QAR0.00
($94) QAR0.00 QAR452,45QAR452,459.00
($87) QAR0.00 QAR40,228QAR40,228.00
($85) QAR0.00 QAR51,722QAR51,722.00
($76) QAR0.00 QAR22,988QAR22,988.00
($92) QAR0.00 QAR98,817QAR98,817.00
($85) QAR0.00 QAR24,230QAR24,230.00
($83) QAR0.00 QAR60,575QAR60,575.00
($79) QAR0.00 QAR18,172QAR18,172.00
($67) QAR0.00 QAR117,55QAR117,555.00
($81) QAR0.00 QAR18,172QAR18,172.00
($184) QAR0.00 QAR652,52QAR652,528.00
($67) QAR0.00 QAR158,42QAR158,424.00
($64) QAR0.00 QAR47,527QAR47,527.00
($63) QAR0.00 QAR26,933QAR26,933.00
($62) QAR0.00 QAR47,527QAR47,527.00
($60) QAR0.00 QAR19,011QAR19,011.00
($59) QAR0.00 QAR7,921.QAR7,921.00
($58) QAR0.00 QAR9,505.QAR9,505.00
($101) QAR0.00 QAR336,72QAR336,725.00
$194 QAR0.00 QAR26,324QAR26,324.00
$193 QAR0.00 QAR4,786.QAR4,786.00
$195 QAR0.00 QAR2,393.QAR2,393.00
$197 QAR0.00 QAR47,862QAR47,862.00
($56) QAR0.00 QAR55,042QAR55,042.00
($56) QAR0.00 QAR59,828QAR59,828.00
($66) QAR0.00 QAR19,145QAR19,145.00
($74) QAR0.00 QAR7,179.QAR7,179.00
-73 QAR0.00 QAR4,786.QAR4,786.00
-71 QAR0.00 QAR7,179.QAR7,179.00
-75 QAR0.00 QAR4,786.QAR4,786.00
-76 QAR0.00 QAR97,415QAR97,415.00
-184 QAR0.00 QAR157,37QAR157,379.00
-150 QAR0.00 QAR30,148QAR30,148.00
-148 QAR0.00 QAR38,762QAR38,762.00
-152 QAR0.00 QAR19,763QAR19,763.00
-146 QAR0.00 QAR4,846.QAR4,846.00
-145 QAR0.00 QAR12,115QAR12,115.00
-144 QAR0.00 QAR3,635.QAR3,635.00
-143 QAR0.00 QAR3,635.QAR3,635.00
-141 QAR0.00 QAR17,227QAR17,227.00
-134 QAR0.00 QAR27,248QAR27,248.00
-159 QAR0.00 QAR395,09QAR395,098.00
-169 QAR0.00 QAR87,681QAR87,681.00
-123 QAR0.00 QAR26,304QAR26,304.00
-126 QAR0.00 QAR14,906QAR14,906.00
-125 QAR0.00 QAR26,304QAR26,304.00
-123 QAR0.00 QAR4,384.QAR4,384.00
-124 QAR0.00 QAR10,522QAR10,522.00
-123 QAR0.00 QAR5,261.QAR5,261.00
-178 QAR0.00 QAR181,35QAR181,354.00
-121 QAR0.00 QAR14,018QAR14,018.00
-121 QAR0.00 QAR2,549.QAR2,549.00
-121 QAR0.00 QAR1,274.QAR1,274.00
-121 QAR0.00 QAR25,488QAR25,488.00
-121 QAR0.00 QAR29,311QAR29,311.00
-121 QAR0.00 QAR31,860QAR31,860.00
-119 QAR0.00 QAR3,823.QAR3,823.00
-115 QAR0.00 QAR3,823.QAR3,823.00
-119 QAR0.00 QAR2,549.QAR2,549.00
-113 QAR0.00 QAR10,195QAR10,195.00
-119 QAR0.00 QAR2,549.QAR2,549.00
-129 QAR0.00 QAR53,915QAR53,915.00
-195 QAR0.00 QAR0.00 QAR0.00
-98 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-61 QAR0.00 QAR0.00 QAR0.00
-195 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-57 QAR0.00 QAR0.00 QAR0.00
-53 QAR0.00 QAR0.00 QAR0.00
-52 QAR0.00 QAR0.00 QAR0.00
-49 QAR0.00 QAR0.00 QAR0.00
-150 QAR0.00 QAR0.00 QAR0.00
-54 QAR0.00 QAR0.00 QAR0.00
-55 QAR0.00 QAR0.00 QAR0.00
-52 QAR0.00 QAR0.00 QAR0.00
-52 QAR0.00 QAR0.00 QAR0.00
-60 QAR0.00 QAR0.00 QAR0.00
-91 QAR0.00 QAR126,06QAR126,063.00
-83 QAR0.00 QAR14,334QAR14,334.00
-81 QAR0.00 QAR18,430QAR18,430.00
-70 QAR0.00 QAR8,191.QAR8,191.00
-83 QAR0.00 QAR24,704QAR24,704.00
-78 QAR0.00 QAR6,057.QAR6,057.00
-78 QAR0.00 QAR15,144QAR15,144.00
-76 QAR0.00 QAR4,543.QAR4,543.00
-74 QAR0.00 QAR4,543.QAR4,543.00
-66 QAR0.00 QAR30,117QAR30,117.00
-252 QAR0.00 QAR368,44QAR368,442.00
283 QAR0.00 QAR77,917QAR77,917.00
247 QAR0.00 QAR23,375QAR23,375.00
224 QAR0.00 QAR13,246QAR13,246.00
224 QAR0.00 QAR23,375QAR23,375.00
225 QAR0.00 QAR9,350.QAR9,350.00
207 QAR0.00 QAR3,896.QAR3,896.00
207 QAR0.00 QAR4,675.QAR4,675.00
-217 QAR0.00 QAR175,71QAR175,712.00
228 QAR0.00 QAR14,058QAR14,058.00
227 QAR0.00 QAR2,557.QAR2,557.00
224 QAR0.00 QAR1,278.QAR1,278.00
229 QAR0.00 QAR25,560QAR25,560.00
229 QAR0.00 QAR29,394QAR29,394.00
229 QAR0.00 QAR31,950QAR31,950.00
212 QAR0.00 QAR3,834.QAR3,834.00
213 QAR0.00 QAR2,556.QAR2,556.00
216 QAR0.00 QAR3,834.QAR3,834.00
217 QAR0.00 QAR10,224QAR10,224.00
210 QAR0.00 QAR2,556.QAR2,556.00
-162 QAR0.00 QAR47,911QAR47,911.00
-252 QAR0.00 QAR114,81QAR114,813.00
-203 QAR0.00 QAR21,548QAR21,548.00
-202 QAR0.00 QAR27,703QAR27,703.00
-197 QAR0.00 QAR12,313QAR12,313.00
-204 QAR0.00 QAR14,823QAR14,823.00
-201 QAR0.00 QAR3,635.QAR3,635.00
-200 QAR0.00 QAR9,086.QAR9,086.00
-199 QAR0.00 QAR2,725.QAR2,725.00
-198 QAR0.00 QAR2,726.QAR2,726.00
-191 QAR0.00 QAR20,254QAR20,254.00
-195 QAR0.00 QAR0.00 QAR0.00
-161 QAR0.00 QAR0.00 QAR0.00
-161 QAR0.00 QAR0.00 QAR0.00

You might also like