Professional Documents
Culture Documents
Name : K.SENTHIL
Nationality : Indian
Marital Status : Married
Date of Birth : 21/04/1980
Languages Known : English, Tamil, Hindi, Malayalam
Qualification : BE Mechanical Engineering
Mail Id : senthil_tlnd@yahoo.com
Cell No : 91-9790645911,
: Madurai(Dt), tamilnadu
Passport no : U8840645
ADDITIONAL QUALIFICATION :
SHUTDOWN EXPERIENCE :
Summary :
JOB RESBONSIBLITY
Working in Now ,HCU Unit (hydrogen cracking unit)
• In Stripper column, Fractinatry Column,Etc. Inspection of Static
equipment such as vessel, column,& Reactors
Inspect the smooth metal loss around tangential feed inlet portions
• Inspection of Static equipment such as vessel, column,& Reactors
• Check the demister pad and frames for fouling integrity, cladding
lining. Suspect the severe corrosion of nozzle , dish head,
• Inspect the smooth metal loss around tangential feed inlet portions.
• Suspect the hot spot top & bottom head, nozzle. Fouling,
deterioration of collector, shell internal welds. Verify the integrity of
thermo welds inspect the vortex breaker, tray support weld. Including
attachments welds. Inspect the ladders, lifting lug/ trunions.
• Check the skirt& skirt attachments welds. Fireproofing demage in
any abnormality.
Check the any signs of leakage check the evidence of corrosion, cracks,
movement, detachment, any abnormal condition, Etc.
• Third ) Inspection of Tube bundle, baffle plate, tie rods, support plate,
impingement plate for bend, corrosion and mechanical damages.
• Internal inspection of shell, Nozzle for any corrosion, pitting and
Mechanical damage.
• Inspecting the Hydro test on shell side, tube side, ring test at the
hydro test pressure and giving recommendations for any
abnormalities.
• Inspection of the condition of Insulation.
•
,03.10.2018 to 13.12.2018
Duration29.07.2017 to 20.08.2017
.
Project shutdown Reliance Petrochemicals limited Gujarat Hazira
Company: M/s Induspect Limited
JOB RESBONSIBLITY
Project ; RAZ AL KAIR POWER PLANT SAUDI(SWCC).
ERECTION and fabrication piping, spools and weld visual inspection,
preparation of ndt works. such as DPI, MPI PMI.Test.,as per applicable
customer specification. fit up& dimension check of piping spools, Carried
out welding Inspection, fit up joint of piping as per approved codes
&drawing.
EMPOLYMENT DETAILS
DURATION; 28.02.2009 TO 5.3.2012
M/S ZAMIL STEEL INDUSTRIES(Process Equipment division) Dammam
Saudi Arabia. Worked as SR QC INSPECTOR OF Past 3 Years,(FEB 28th
2009 to MAR 3,2012) Company have a stamp ASME U,U2.ISO 9001-
2008,ASME B31.3, National Board etc.,British Standard. Worked at
SATORP , YANPET, Kurshaniya gas plant fabrication of vessel. Karan gas
facility , Manifa gas project in manufactured pressure vessel , heat
exchanger.etc.
JOP RESPONSIBILITY :
. To collate all relevant QC documentation for the job and ensure and
NDT reports.
Isometric & spooling) and documents (Weld Plan, ITPs & WPS)
assembly work the compliance of ITP and MRB prior to Pressure test
inspection activity
EXPERIENCE :
Dimension check (Pressure Vessel, Pressure Piping) Air leak test,
Raw Material inspection PMI, PT,MT,VT Inspection test, Welding
monitoring and make A NDT reports, Hydro test etc., Checking and follow
the ECR,NCR Report make the Dimension report .material inspection on
New material carbon material, loy alloy, stainless steel,
EXPERIENCE :
Job Responsibilities:
Reformer tube inspection
• Inspection of reformers tubes, Pigtails &Headers full circumference,
visual inspection, bow check measurements, creep measurement
ultrasonic inspection of tube ,Bore carburization measurements, hardness
testInspection planning& execution screening evaluation of flaws.
• More detailed evaluation of flaws which do not meet screening
guidelines. Brittle fracture assessments, Guidance in selecting NDE
techniques and developing an inspection plan.
• Inspection of Static equipment such as vessel, column,& Reactors
• Check the demister pad and frames for fouling integrity, cladding
lining. Suspect the severe corrosion of nozzle , dish head,
• Inspect the smooth metal loss around tangential feed inlet portions.
• Suspect the hot spot top & bottom head, nozzle. Fouling ,
deterioration of collector, shell internal welds. Verify the integrity of thermo
welds inspect the vortex breaker, tray support weld.Ingluding attachments
welds.inpect the ladders, lifting lug/ trunions .
• Witness of hydro test of vessel& piping spools.
JOP RESPONSIBILITIES:
JOB RESPONSIBILITIES :